QUEEN'S BENCH DIVISION
COMMERCIAL COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
AIC LIMITED |
Claimant |
|
- and - |
||
ITS TESTING SERVICES (UK) LIMITED |
Defendant |
____________________
Mr D Mildon QC and Miss Jessica Mance (instructed by Hill Taylor Dickinson) for the Defendants
Hearing dates:
____________________
Crown Copyright ©
INDEX
paragraphs | |
1. INTRODUCTION | (1) to (14). |
2. A CHRONOLOGICAL ACCOUNT OF THE HISTORY OF THE DISPUTES AND PREVIOUS LITIGATION | (15) to (72). |
3. AIC's CASE AND ITS' CASE | (73) to (94). |
4. WITNESSES | (95) to (163). |
5. LIST OF MAIN ISSUES IN DISPUTE | (164) to (165). |
6. MISTAKE AND DEPARTURE FROM INSTRUCTIONS CONTRASTED | (166) to (174). |
7. ANALYSIS AND DISCUSSION OF AND CONCLUSIONS AS TO THE AGREED ISSUES | (175) to (351). |
8. CONCLUSION | (352). |
Mr. Justice Cresswell :
1. INTRODUCTION
It is also convenient to refer by way of introduction to gasoline cargoes and Vapour Pressure. The quality of a gasoline cargo to be loaded on to a vessel can be determined as follows: -
i) Analyse each individual shore tank prior to loading to confirm they meet specification.
ii) Prepare a shore tank composite for analysis. However, the Vapour Pressure would be based on a calculation from the individual results (weighted average).
iii) Sample and test a ship's composite. For Vapour Pressure individual tanks would be tested and a weighted average calculated.
Vapour Pressure is measured on crude oils and volatile petroleum products. It is an important property for gasoline, because the Vapour Pressure affects the operation of fuel pumps and engines. It will be difficult to pump a gasoline with a high Vapour Pressure without vapour locks resulting at high altitudes or at high temperatures. Conversely there needs to be sufficient vapour generated at low temperatures to facilitate engine start-up and warm-up.
In addition, Vapour Pressure can be used as an indirect measure of the evaporation rate of the gasoline.
Vapour Pressure can also be used as a means of assessing the amount of VOCs a gasoline will release. A high Vapour Pressure can indicate high concentrations of VOCs in the gasoline. VOCs can impact adversely on the environment: they are a constituent of smog and have other health implications. In the case of gasoline they are also an indirect measure of flammability.
In some countries, e.g. the USA, there are seasonal limitations on the quantity of VOCs which can be released from materials such as gasoline.
2. A CHRONOLOGICAL ACCOUNT OF THE HISTORY OF THE DISPUTE AND PREVIOUS LITIGATION
Banque Paribas (for account of AIC) opened a letter of credit in favour of Mobil.
ITS acknowledged nomination of Kriti Palm and confirmed attendance.
ITS enquired whether loading should be halted to enable tests of first foot ship's tank samples.
The Kriti Palm arrived at Coryton and tendered NOR to load. No product was ready for loading and could be loaded until ITS certified that it complied with the CPS.
Mobil informed ITS that AIC should pay 100% for listed requests, otherwise 50/50.
A message from Mr Damian Twyford (of ITS) to Mr Giovanni Sampino (of AIC) confirmed that AIC no longer required additional tests of first foot ship's tank samples.
ITS forwarded a Certificate of Quality ("CofQ") for shore tank 75x1 (1st parcel) regular gasoline to AIC. The CofQ stated that Reid Vapour Pressure tested by ASTM D323 = 8.91/8.98 psi; and that "FUEL MEETS SPECIFICATION".
The Kriti Palm commenced loading.
ITS forwarded CofQ for tank 75x1 (2nd parcel) regular gasoline and for tank 100x1 regular gasoline to AIC. The CofQ for tank 75x1 (2nd parcel) stated that Reid Vapour Pressure tested by ASTM D323 = 7.67/7.60 psi, and that "FUEL MEETS SPECIFICATION". The CofQ for tank 100x1 stated that Reid Vapour Pressure tested by ASTM D323 = 7.83/7.81psi, and that "FUEL MEETS SPECIFICATION".
ITS reported provisional results for shore tank 61x4 to Mobil (but not AIC). The fuel did not meet specification due to results for MON and Olefins. Mobil requested ITS to prepare a weighted lab blend of samples i.e. a "shore composite blend". ITS performed certain physical analyses of the blend and calculated RVP by reference to the weighted average of the RVPs of the individual shore tanks.
ITS forwarded to AIC, cc. Mobil:
CofQ for the shore tank 61x4 regular gasoline, which bore words: "fuel does not meet specification". According to ITS' provisional report the fuel did not meet specification for MON and Olefins only. The CofQ stated that Reid Vapour Pressure tested by ASTM D323 = 8.85/9.01. It is agreed that the average of these two figures is ½(8.85+9.01) = 8.93 i.e. within specification.
CofQ for the shore tanks composite blend regular gasoline, which reported Reid Vapour Pressure of 8.22psi and states "FUEL MEETS SPECIFICATION". I will refer to the shore tanks composite blend certificate as "the certificate". I will refer to all 5 certificates in respect of the regular gasoline as "the certificates".
AIC faxed ITS' CofQ for the shore composite blend to First National Oil Brokers Inc., Connecticut ("FN"). FN communicated certain figures by telephone to Galaxy Energy (USA) ("Galaxy") before Galaxy agreed to the sub-sale.
In a fax timed 16:34 (local time Connecticut), FN confirmed the sub-sale of the cargo by AIC to Galaxy. The Quality clause in the AIC/Galaxy sub-sale provided: "Quality: (A) M 2 meeting statutory baseline [i.e. CPS] with the following guarantees RVP 9.0psi determination of quality: As ascertained at load port and confirmed by Caleb Brett". The sub-sale did not contain an express choice of law clause.
ITS forwarded the CofQ for tank 100x1 premium gasoline to AIC.
The Kriti Palm completed loading and sailed for New York.
ITS sent a telex to AIC attaching time log, cargo summary, and quality analysis (which did not include the phrase "Fuel meets [or does not meet] specification".) The quality results for the regular gasoline were stated on the basis of the shore composite blend CofQ.
In a message to Galaxy, AIC nominated the Kriti Palm and relayed loading information and details of the quality analysis as provided by ITS.
"The loading operations were protracted due to the vessel having to wait for available cargo. Analysis was performed on shore tanks soon as the tanks were available. The final tank for the regular parcel was found to be outside the required specifications, however after re-testing with a volumetric composite of all four tanks, the results were found to be acceptable."
Analysis was performed by test ASTM D5191 on disport samples of cargo from the vessel's tanks, and on load port samples which had been transported on board. ITS USA (the discharge port inspectors appointed for the purposes of the AIC/Galaxy contract) obtained the following results for the regular cargo: (1) analysis of samples from the ship's tanks RVP = 9.11 to 9.56 psi; (2) analysis of load port shore tank composite RVP = 9.04 psi; and (3) analysis of load port ship's composite RVP = 9.30 psi. Galaxy subsequently instructed SGS to take further samples from the ship's tanks and test them for Vapour Pressure using ASTM D5191. SGS obtained RVP results for the regular cargo of 9.30 to 9.69 psi.
The Kriti Palm commenced discharge of premium gasoline.
AIC informed ITS about problems at the discharge port.
Galaxy ceased discharge of cargoes.
Mr Rackham (of ITS) sent an internal ITS e-mail message to Mr Chalmers (of ITS), cc Dave Johnston and Nigel Lucas, discussing problems at the discharge port. The message said: -
"Problem: ITS as Disport Inspectors declare high RVP and Octanes.
Mobil declined to issue individual shore tank results as cargo sold FOB and final document was bench blend as representative of cargo loaded. This passed to AIC.
RVP was tested by ITS Lab Tech at Coryton to ASTM D323 as an oversight and error not picked up at reporting stage by Inspection office.
Very early days yet but AIC state that vessel is held on demurrage and also if RVP method is found to be erroneously used they will hold us for total quality failure of cargo."
ITS informed AIC that Mobil had instructed ITS not to release information regarding Kriti Palm until after discussions on 17 April.
Mr Rackham arranged for residues of the (retained and broached) individual load port shore tank samples at Coryton to be located and sent to West Thurrock for testing in a Grabner machine of the type used under ASTM D5191 (the "Cooper re-tests"). Neither Mobil nor ITS were informed of the re-tests.
Mr Rackham's logbook contained an entry at 11.00 hours "LD re-test Regular unleaded. RVP Ceta 8.67. ASTM D5191 Grabner 8.57".
Mr Rackham's logbook contained an entry at 13.33 hours "JC re Kriti Palm. Harass UK need low RVP."
Mr Rackham sent an email to Mr Johnston and Mr Balogh (cc Mr Stokes) in which he tabulated the load port results stated in ITS' certificates and said "We are very sure at this end that overall vessel will show RVP under 9.0".
Mr Rackham responded to an email from Mr Ris of ITS Rotterdam, which had offered assistance. Mr Rackham said "at present indications are that situation is resolved".
Pursuant to Mr Rackham's directions, 10 partially filled sample bottles were sent from Coryton to West Thurrock. Each bottle was marked with the shore tank number from which the Kriti Palm cargoes had been drawn. Mr Cooper conducted re-tests on these residues using the Grabner machine. He recorded the Cooper re-test results in a one-page manuscript note. The note recorded that he ran 2 preliminary tests through the Grabner machine with a sample of a compound known as "22DMB" in order to construct a "correction factor" for the machine. The results for the regular cargo were as follows:
75x1 (2nd) Corrected DVPE 8.47/8.69 psi (compared to 7.7 psi as the approximate figure stated in the CofQ).
100x1 Corrected DVPE 9.43/9.46 psi (compared to 7.8 psi as the approximate figure stated in the CofQ).
61x4 Corrected DVPE of 8.67/8.66 psi (compared to 8.85/9.01 psi as the figures stated in the CofQ).
75x1(1st) - Correct DVPE 9.30/9.39 psi (compared to 8.9 psi as the approximate figure stated in the CofQ).
The manuscript note also recorded "Sample bottles 500ml glass all 50-75% full".
Mr Rackham tabulated the Cooper re-test results and calculated some kind of an average ASTM D5191 corrected figure of 9.16 psi. He also applied an EPA seasonal correction factor to produce an average of 9.33 psi.
Galaxy demanded from AIC a discount of US$230,000 to resume discharge of cargoes. Galaxy refused to discharge the regular cargo in the absence of a price discount.
AIC put Mobil (cc ITS) on notice of a possible claim and called for Mobil's prompt intervention.
AIC responded to Galaxy. Galaxy took issue with AIC's response.
A Saybolt report was sent to AIC, as to witnessing the tests performed by ITS USA on load port samples transported on board (not tests for RVP).
Mr Rackham sent an email to Mr Chalmers and Mr Loughead. The hard copy document timed 0551 had "VNL" (Mr Lucas' initials) written in manuscript upon it next to "CC." The email said: -
"Current situation is that MV Kriti Palm loaded two grades Prem/Reg ums at Coryton a/c Mobil / A.I.C. AIC purchased FOB on Load C of Q
Quality by ITS at Coryton to C.P.C. spec grades R2/M2
On arrival New York AIC had sold to Galaxy and ITS appointed for Q and Q
Regular pcl at disport found off on RVP. spec max 9.0 load C of Q states 8.22.
Checking with our Mobil Lab tech it appears RVP done by ASTM D 393 and NOT 5191 as per CPC. C of Q checked and passed by local inspection office and C of Q states 393. This has been queried but I have not responded as yet.
AIC called in Saybolt to witness ITS in New York. Galaxy then appointed SGS.
Vessel has discharged premium pcl but Galaxy refuse to accept reg. pcl.
Vessel remains alongside on demurrage.
Late PM yesterday AIC served written telex notice of claim against Mobil London with cc copy to me at West Thurrock.
To date no admission of liability by ITS has been made. Have managed to obtain original RVP samples ex Coryton and whilst these have been broached for original tests have had Grabner RVPs conducted at West Thurrock and overall average for four tanks loaded ex shore onto 17 ship tanks find RVP to be 9.33.
Trying to stall AIC/Mobil questions but things becoming very heated"
Mobil in a message to AIC (cc. ITS) rejected AIC's contention that the cargo was off-specification. Mobil maintained that the products met contractual specification.
ITS USA forwarded to Mr Rackham RVP results obtained at discharge port from analysis of individual ship tank samples.
AIC called upon Galaxy to recommence discharge.
Mr Rackham's logbook contained an entry at 10.55hrs as to a telephone conversation between Mr Whitaker and Mr Rackham. "AIC $1m v/l sitting on berth". Mr Rackham recorded that Mr Whitaker insisted on speaking to somebody "NOW".
Mr Rackham arranged a telephone call between Mr Whitaker of AIC and Mr Lucas of ITS. He briefed Mr Lucas before the call.
Mr Rackham listened in to the telephone call between Mr Lucas and Mr Whitaker but did not talk. Mr Lucas recorded part of the call on his dictaphone. His secretary subsequently typed up a transcript. This telephone conversation is of central importance in this case.
(1) Mr Lucas said "It is impossible to go back into any of the samples because no samples are kept under ice."
(2) (In answer to Mr Whitaker's statement "I have to find out some way of proving that it actually is off-specification you are telling me that I cannot do that") Mr Lucas said "Not to the load port, but you can at the discharge port".
(3) (In answer to a statement from Mr Whitaker "I have a Quality Certificate from you that says it is on-specification") Mr Lucas replied "we will be standing by that certificate".
(4) (In answer to a question from Mr Whitaker "well if the test 323 was done where test 5191 should have been done do you not see that as inaccurate?") Mr Lucas said "I can't say whether it is inaccurate or not".
In a telephone conversation between AIC and Galaxy, AIC offered to pay money into escrow, and then offered a discount of US$100,000 to resolve the impasse at discharge port. Galaxy rejected AIC's proposals and demanded US$230,000.
Mr Lucas faxed Mr Whitaker referring to the latter's request during the telephone call either to change the CofQ or face legal action. Mr Lucas refused to change the CofQ because that "would be a fraudulent act".
ITS provided AIC with a "statement of facts" and duplicate copies of all six CofQs and loading report.
An ITS internal note from Mr Johnston (of ITS) to Mr Rackham instructed that load port samples were to be sealed. This was implemented.
Mr Whitaker replied to the fax of 17 April from Mr Lucas. AIC provided further contact details of its London and New York lawyers.
In view of Galaxy's continuing refusal to accept the regular cargo, AIC ordered the Kriti Palm to discharge the balance of the cargoes at IMTT Bayonne for the account of Galaxy. The vessel shifted to berth and commenced discharge.
Payment on behalf of AIC was made by Banque Paribas to Mobil. Under the terms of the purchase contract between AIC and Mobil, AIC was bound to pay Mobil in full without offset or deduction.
A telephone conversation took place between Mobil (Mr Bradshaw/Mr Fraser) and AIC (Mr Hatcher/Mr Whitaker). Mobil said that they intended to re-test retained load port samples to investigate the validity of the RVP figures obtained at the discharge port. Mr Hatcher referred to the fact that AIC had spoken with ITS and that ITS had admitted that it may have erred in its "test report for RVP, the test method they ran on the cargo".
Mr Lucas responded to Mr Whitaker's fax of 18 April saying that ITS was "unable to produce a report stating a result which we did not obtain by a test method which we did not use." ITS provided AIC with contact details for its London lawyers.
Mobil requested Inspectorate Witham to perform ASTM D5191 test on shore tank retained samples.
In a message from Mobil to AIC (cc. ITS) Mobil rejected the claim that the product was off-specification.
Saybolt informed AIC of the results of an analysis of samples taken from ship's tanks at IMTT Bayonne prior to discharge. The RVP tested by ASTM D5191 was 9.38-9.73 psi.
AIC instructed Banque Paribas to seek payment under the Galaxy letter of credit opened by Credit Agricole.
AIC telexed Galaxy denying breach of contract, and refusing to agree to a USD 230,000 discount. "We attempted one last time thru FNOB to mitigate damages by offering a USD 100,000 discount This offer was refused."
Banque Paribas presented a commercial invoice, quantity certificates and LOI to Credit Agricole and asked for payment. The ITS quality certificates were not among the documents presented.
Galaxy obtained a temporary injunction (following a without notice hearing) from the Tribunal of First Instance of Geneva, restraining Credit Agricole from making payment to AIC under the Galaxy letter of credit.
Galaxy complained to AIC that despite repeated requests AIC still refused to provide a copy of the certificate for tank 61x4.
Galaxy thereafter took delivery of the cargo which had been in storage at IMTT, Bayonne, New Jersey.
"Handwritten notes dated 16 April apparently signed by M. Cooper. These are, I think a note of the test results obtained when the retained samples were subjected to an ASTM D5191 test once problems emerged in New York. These results are "invalid" because the samples had been broached for testing at an earlier stage, but still somewhat alarming because they showed a number of results over 9 (when one would have expected the pressure to have reduced consequent upon the samples being broached). "
The contract related to gasoline M 2 for the US market which had to be in conformity with the CPS.
Galaxy received in New York gasoline which was not on-specification. The gasoline was not compatible with the figures resulting from the test made in Coryton by ITS communicated to Galaxy by fax of 4 April 1996.
The test of the quality at load port was erroneous. The product did not meet the contractual specifications (the CPS). The product was either an aliud or a product which bore a defect or an absence of promised guarantee.
The Regular M 2 constituted a debt in kind.
The failure to comply with the conditions as to RVP had the consequence that the gasoline M 2 did not conform to the CPS, but was another product which had to be sold as another product by Galaxy.
By delivering an aliud, AIC did not perform its obligations. The delivery of an aliud constitutes a violation of the contract.
It was for the debtor (AIC) to demonstrate that if it did not execute the contract properly, AIC did it without fault.
AIC failed to demonstrate absence of fault.
AIC knowingly loaded gasoline which did not conform to the CPS concerning the RVP. AIC knew that one of the tanks (61 x 4) contained gasoline which was not, with respect to RVP, in conformity with the contract (and with the CPS), the RVP being above 9psi (although the gasoline had been tested with an inadequate test).
AIC did not submit the certificate which related to tank 61 x 4 (which said it was off-specification). Galaxy, during the proceedings, was able to obtain the document in question directly from ITS.
It was never a contractual provision that only the shore composite blend would be determinative. Mr Whitaker admitted that AIC had received the certificate as to the tank which did not meet the specifications and the certificate as to the shore composite blend at the same time. He also admitted that he had been informed between 16 and 18 April that the test of the shore composite blend had been done in an erroneous way.
Although it appeared that a third test made by ITS Caleb Brett USA confirmed a high RVP above the limit of 9psi, AIC refused any discussion, any contradictory testing. AIC did not take the disputed product back as it should have done and, on the contrary, proceeded on its own initiative to discharge the regular cargo in the name of Galaxy, requesting in parallel the payment of the total amount of the letter of credit. Acting like that, AIC seriously violated its obligations.
The gasoline tested at load port included at least a tank which, according to the testing however inadequate, presented a RVP superior to 9psi.
AIC did not act properly following that discovery and proceeded to a shore composite blend which was found "acceptable". It gave the order to load the cargo on the Kriti Palm knowingly.
Contrary to its obligations, AIC refused to submit the certificate relating to tank 61 x 4 when it requested the payment of the letter of credit or later, demonstrating that AIC was conscious of acting in an incorrect way and that the product which had been loaded on the Kriti Palm was not on-specification.
As to the testing in New York at discharge, AIC could not be in any doubt that the M 2 did not conform to the contractual specifications and to the CPS. Its reaction vis-ΰ-vis ITS was the best proof of this.
AIC however withdrew very quickly behind the contractual clause according to which the binding quality was the one acknowledged at load port, alleging thereby a thesis which was contrary to the most elementary rules of good faith.
AIC then forced Galaxy by delivering the disputed product in the name of the latter in New York.
It follows that not only did AIC violate its contractual obligations, but it did so with fault.
[It should be remembered that the Geneva Court of Appeal (and AIC and Galaxy) did not know of the Cooper re-tests and the results thereof].
3. AIC'S CASE AND ITS' CASE
AIC'S CASE
AIC's case is as follows.
(1) To use reasonable skill and care;
(These duties included a duty to comply with the professional standards expected of an international inspection agency, a duty to notify clients in writing of any circumstance casting doubt on the validity of reported results and a duty to investigate and report on anomalies/enquiries/complaints and a duty to provide all relevant information concerning an error, consequences and doubt surrounding reported results).
(2) To seek permission before use of samples and to inform clients of the fact of such use and the consequences thereof;
(3) Not to make misrepresentations or deceive AIC; and
(4) To follow instructions.
(1) ITS were initially negligent.
(2) ITS made negligent misrepresentations on 17 April 1996.
(3) ITS negligently failed to correct/qualify/withdraw the certificate and negligently failed to disclose the Cooper re-tests and the results thereof on and after 17 April 1996.
(4) ITS were in breach of the contractual duty to disclose the Cooper re-tests and the results thereof.
(5) ITS were guilty of deceit.
As to Mr Chalmers, it is implausible that he regarded the Cooper re-tests and the results thereof as of no relevance or importance. Mr Chalmers knew that there was something wrong with the RVP results stated in the certificates. Mr Chalmers knew it was wrong and misleading for ITS to continue to stand by the RVP results stated in the certificates and to reiterate that those results were reliable. In failing to correct/qualify/withdraw the certificate for the regular cargo and/or the false statements made by ITS on 17 April 1996, Mr Chalmers was acting dishonestly or recklessly.
ITS' case
ITS disputes AIC's case as set out above. I will refer below to ITS' submissions in relation to some of the important issues.
4. WITNESSES
Witnesses called by the claimant
At the material time Mr Sampino's work for AIC primarily involved ship operations. When one of the traders at AIC agreed physical sale or purchase contracts, Mr Sampino would handle the nomination of vessels, the appointment of cargo inspectors and operations at load and discharge ports. (Mr Sampino is now the senior trader at AIC).
Hearsay Evidence
Statements not challenged
In July 1998 AIC instructed Dr Watt as an expert witness in the litigation in Switzerland between AIC and Galaxy. Galaxy's case in Switzerland was that ITS should have used D5191, but that either test method used properly would have shown that the RVP of the cargo of regular unleaded gasoline was too high. This argument was supported by an expert report prepared by Professor Riccardo Cosulich of Laboratorio Chimico Merceologico, which AIC asked Dr Watt to comment on. Dr Watt's final report dated December 1998 concluded that ITS' inspectors had been entitled to use ASTM D323 to test the RVP of the cargo prior to loading at Coryton.
During his testimony on 1 June 1999 Galaxy's lawyers showed Dr Watt some documents he had not previously seen. Dr Watt said that strictly speaking (as he explained in his report in the Swiss proceedings) there is only one test for Reid Vapour Pressure, and that is ASTM D323. In practice, however, the letters RVP are used to refer to Vapour Pressure generally, probably because the Reid method was the first reliable test for Vapour Pressure. On this basis, a chemist/cargo inspector who is asked simply to test the RVP of gasoline can choose between a number of methods. However, if the chemist/cargo inspector is directed to a particular test method, he should use it. If Dr Watt had seen certain documents when he was preparing his expert report in the Swiss proceedings, he would not have reached the same conclusions. His expert report was prepared on the basis that the inspectors at Coryton had not been directed to use the test methods specified in the CPS, and were therefore free to choose what method to use to test RVP. It is clear from the documents he had not seen that this was not the case, and that the inspectors were asked to test the RVP of the cargo using ASTM D5191. Their instructions could not have been interpreted differently.
Dr Watt said that he had recently been informed that on about 16 April 1996 ITS re-tested the original cargo samples using ASTM D5191, and found that the RVP of these samples exceeded the maximum of 9 psi that is permitted under the CPS. He said: -
"If I had had this information when preparing my expert report for the Swiss proceedings, my conclusions might have been very different. testing gasoline samples that have already been tested cannot produce reliable results for RVP because Vapour Pressure will have been lost when the samples were first tested. However, the RVP at the time of such re-tests will inevitably be lower than it was at the time of the original tests. The results of ITS' re-tests on samples of the regular unleaded gasoline therefore call into question the reliability of all the RVP results from their original tests on this part of the cargo. I find it particularly striking that the RVP of one of the samples of regular unleaded gasoline when re-tested was 9.43/9.46, whereas its RVP when originally tested at Coryton was recorded as 7.8 psi. This appears to be inexplicable."
Witnesses called by the defendant
Mr Lucas said if he had known (a) that Mr Mailey was not involved in the blending exercise and (b) of the Cooper re-tests and the results thereof, he "would have stood by the certificate, but we would have got into a much bigger argument then about what the Cooper results actually meant. We would have had to get into a three-cornered discussion with Mobil, AIC and ourselves to try and see what this actually would mean by way of a decision."
"Q. should ITS have stood by [the certificate] or should they have written a letter withdrawing it or what should they have done?
A. I think we should have been much clearer in what we were saying. We did tell them the wrong tests had been used. Sitting here today, I think I agree that we could have written them a letter spelling out exactly that, that the wrong tests had been used and that there was therefore, in view of the other tests in America and the result we have here, an area of doubt.
Q. And "the result we have here" means what?
A. The RVP result
Q. Are you saying that as of today you recognise that you should have written a letter saying, "We can no longer stand by this certificate"?
A. Sitting here today, I think I would have to recognise that."
At the material time Mr Cooper was a Senior Technician responsible for the day to day running of the ITS laboratory in West Thurrock.
Mr Adams was employed by ITS as a chemist inspector. His task was to oversee the loading operation and at the end of that operation to provide the correct documentation and samples.
Mr Twyford was employed by ITS as an Inspection Co-ordinator.
Hearsay Evidence
Witnesses who provided statements to both sides
[I gave a direction by consent as to the procedure to be adopted and the order of cross-examination in relation to this evidence.]
Mr Mailey was employed by ITS as a chemist inspector in the laboratory at Mobil's Coryton refinery. Mr Mailey found that a parcel of cargo was off-specification. He reported this to Mobil's Production Control Office and Mr Twyford. The Production Control Office could then re-blend the parcel in question and ask him to test it again.
Mr Wyllie was at the material time a Senior Inspector employed by ITS.
Expert Evidence
Dr Marshman worked for Intertek between March 2002 and November 2003, but not on the inspection side. She has never been involved on the inspection side. She has never attended a commercial vessel loading. Mr Revell was accordingly better placed to provide assistance to the Court in these respects.
(1) Some of the test methods set out in the certificates of quality were not those called for in the Colonial Pipeline Specification. The test methods set out on the certificates included the testing of Vapour Pressure using ASTM D323, rather than the required method ASTM D5191. In addition the Benzene result was expressed as % volume when the CPS stated % weight.
(2) There were no Oxygenates results for any of the regular motor gasoline shore tanks. The CPS required the regular motor gasoline to have no Oxygenates.
[Mr Revell was of the opinion that due to the fact that there were no Oxygenates results and the use of alternative test methods to those stated in the CPS, ITS were not in a position to state "Fuel meets Specification".]
(3) If the tests ASTM D323 and ASTM D5191 had been performed correctly the results should be comparable.
(4) The EPA equation would give a Vapour Pressure result between 0.1 to 0.2 psi higher than the ASTM D5191 equation. The fact that the cargo was to be tested to CPS indicates it was destined for the USA. However, the application of the EPA equation is only required in certain circumstances.
(5) ASTM D323 will be prone to greater variations as indicated by the higher reproducibility.
(6) From the ship/shore quantity figures any contamination would have been very limited and would not have caused a significant increase in the Vapour Pressure. It was calculated that a 1% contamination, representing a volume of 390 cubic metres, from previous gasoline/naphtha cargoes, having a Vapour Pressure as high as 15 psi, would increase the Vapour Pressure of the overall cargo by less than 0.1 psi.
[Mr Revell was of the opinion that any increase in Vapour Pressure due to trace amounts of previous cargoes, such as gasoline or naphtha, would have been less than 0.05 psi.].
(7) As to why the test methods state 'do not perform tests on broached samples', it is accepted that generally the results on broached samples will be lower.
[Dr Marshman was of the opinion that in some cases the results have been found to be higher].
(8) The disport results confirmed that the cargo on board the "Kriti Palm" was off-specification in respect of Vapour Pressure at disport.
(9) The cargo was off-specification at disport.
(10) There was no evidence of contamination during the voyage.
(11) There was no evidence of contamination from the shoreline system.
(12) [As to whether the cargo was off-grade at load port, Mr Revell was of the opinion that it was off-grade at load port due to the fact that it was off-grade at disport, there being no evidence of contamination during the voyage or from the shoreline system. Dr Marshman could not confirm whether the cargo was off-grade at load port or not].
(13) The definition of Outliers is a result far enough in magnitude from other results to be considered not part of the set. The reasons for such a result are not always known.
(14) The two sets of results (Mr Mailey's results and Mr Cooper's re-test results) were so far apart that both should be considered suspect (IP 367).
[Mr Revell was of the opinion that the Cooper re-test results gained credibility by comparison with the results found at disport. Dr Marshman was of the opinion that the Cooper re-test results were invalid and that in comparing results from load port and disport the samples were not identical].
(15) The certificates stated the test methods used by ITS and the results found at the time, with the exception that the certificate for the shore tanks composite did not state that the RVP had been calculated, rather than determined directly by ASTM D323. [However, Dr Marshman stated that this was common industry practice].
(16) The certificate should not have stated that the "Fuel meets Specification".
(17) For non-oxygenated gasoline samples the RVP results obtained by ASTM D323 and ASTM D5191 should be comparable. 95% of the results would be expected to be within the reproducibility of ASTM D323, which is the greater.
(18) [As to the test procedures used by Mr Mailey, Mr Revell believed the tests were not performed in accordance with ASTM D323 procedures with respect to calibration and in some cases sample handling. Dr Marshman was of the opinion that sample handling was in accordance with ASTM D323 procedures and that appropriate calibration procedures were followed].
International Standards
ISO 9001 and ISO 17025
The Quality Management Systems standards ISO 9001 and ISO 17025 were developed from the Ministry of Defence AQAP procedures for monitoring the quality of products and processes of their suppliers particularly for critical applications or products. AQAPs originated in about the 1950s. AQAPs were superseded by the ISO and NAMAS quality procedures in the 1990s.
ITS West Thurrock NAMAS accreditation. M10
ITS Inspection ISO 9002:1994
Mobil Laboratory ISO 9001:1994
ISO 9001 Requirements
i) Receipt of request: check requirements (methods, timescales, availability of personnel) can be met, acknowledge receipt of request, log request on system
ii) Receipt of samples: log samples on system, pass to relevant personnel or laboratory
iii) Check equipment is in calibration
iv) Analyse sample in duplicate, check results against calibration data
v) Report results.
ISO 17025 Requirements
5. LIST OF MAIN ISSUES IN DISPUTE
1. To what extent was AIC experienced with the purchase and sale of gasoline at the time of the transactions to which the claim relates?
2. Was ITS retained by Mobil and AIC in any kind of advisory capacity? What was the proper scope of the contractual duties owed by ITS to AIC?
3. What were ITS' instructions with regard to testing for RVP? Did ITS reasonably interpret its instructions with regard to testing for RVP? Did ITS carry out its instructions with regard to testing for RVP?
4. Were the RVP results by test method ASTM D323 ('D323') stated in the ITS certificates of quality for the regular cargo:
(i) accurate and/or accurately stated?
(ii) wrong?
5. Can it be shown whether the regular cargo would have been on- or off-specification in the shore tanks, if DVPE had been tested in accordance with ASTM D5191? If so: Was the regular cargo off-specification in the shore tanks and, if so, did ITS know that the cargo would have been shown to be off-specification, if DVPE had been tested in accordance with D5191?
6. Was ITS negligent in its initial analysis of the regular cargo:
(i) in omitting to clarify whether it should use D323 or D5191 before the analysis?
(ii) in using the test method D323?; and/or
(iii) in failing properly and/or adequately to perform test D323?
7. Did ITS fail to have in place any proper system to check the certificates of quality before they were issued? Was ITS negligent in failing to have in place any proper system to check the certificates of quality before they were issued?
8. What statements were contained in the Certificates of Quality? Did the Certificates of Quality contain false statement(s)? In the Certificates, did ITS misrepresent or misreport the results of what it had done?
9. Was ITS negligent in issuing certificates of quality that stated "FUEL MEETS SPECIFICATION" when ITS had used test D323 to test the fuel for RVP?
10. As of 18 April 1996, or thereafter, did AIC in fact rely on the Certificates?
11. As of 18 April 1996, or thereafter, could AIC reasonably rely on the statements in the Certificates that "fuel meets specification" (where applicable)? Further or alternatively, could AIC reasonably rely on the statements in the Certificates that "fuel meets specification" (where applicable), if what AIC had intended to instruct ITS to carry out was a test for DVPE such as that for which D5191 is required?
12. What is/was the uniform practice of arriving at the RVP result of a shore composite blend? What is/was the due method of arriving at the RVP result of a shore composite blend? Did the shore composite blend certificate represent that the RVP result stated therein had been obtained by analysis of a shore composite sample using test D323 and, if so, was ITS negligent in issuing a certificate in that form?
13. Did Galaxy rely upon ITS' certification of the regular cargo when entering into the AIC/Galaxy contract?
14. What RVP samples were taken by ITS?
15. What was ITS' standard practice as regards sample retention? What material was subject to ITS' sample retention standards?
16. What RVP samples were kept by ITS, if any; and in what condition? What residues of samples were kept by ITS; and in what condition?
17. What material was the subject-matter of the re-tests by Mr Cooper on 16 April 1996?
18. Was the material re-tested by Mr Cooper being held by ITS on behalf of AIC and Mobil?
19. Was the material re-tested by Mr Cooper properly to be regarded as the joint property of AIC and Mobil?
20. Should ITS have sought AIC's and Mobil's permission before conducting such re-tests and was ITS in breach of duty in failing so to do?
21. Are/were the results of the re-tests to be relied on for any purpose? Should ITS have informed AIC and Mobil about the fact of the re-tests and the results thereof and was ITS in breach of duty in failing so to do?
22. Should ITS have informed AIC about the fact of the re-tests and the results thereof in the telcon on 17 April 1996, and/or subsequent to the telcon, and was ITS in breach of duty in failing so to do?
23. Did Mr Lucas know of the re-tests and the results thereof (i) by the time of the telcon on 17 April 1996 and (ii) thereafter?
24. What was Mr Chalmers' knowledge of the re-tests and the results thereof by 17 April 1996 and thereafter?
25. Was what was said (and not said) by Mr Lucas in the telcon on 17 April 1996 false and misleading?
26. Was Mr Lucas negligent in what he said (and did not say) during the telcon on 17 April 1996?
27. Was Mr Lucas dishonest in what he said (and did not say) during the telcon on 17 April 1996?
28. Did Mr Lucas intend AIC to rely upon what he said during the telcon on 17 April 1996?
29. On or after 17 April 1996 was ITS negligent in failing to correct or qualify or withdraw what had been stated in the certificates of quality?
30. On or after 17 April 1996 were Mr Lucas and/or Mr Chalmers dishonest in failing to correct or qualify or withdraw what had been stated in the certificates of quality?
31. Did Mr Lucas and/or Mr Chalmers make a deliberate decision not to disclose the fact of the Cooper re-tests and/or the results thereof to AIC and Mobil in circumstances where the re-tests and/or the results thereof should have been disclosed to AIC and Mobil and/or Mr Lucas and/or Mr Chalmers knew that the re-tests and/or the results thereof should have been disclosed to AIC and Mobil?
32. If and to the extent that ITS was under a duty to disclose the fact of the Cooper re-tests and/or the results thereof (see issue 22 above), on or after 17 April 1996 were Mr Lucas and/or Mr Chalmers aware that ITS was under such a duty and did Mr Lucas and/or Mr Chalmers make a deliberate decision not to disclose the same?
33. Did ITS deliberately conceal a fact relevant to AIC's right of action against ITS?
34. If ITS did deliberately conceal a fact relevant to AIC's right of action against ITS, should AIC nevertheless have found out that fact by the exercise of reasonable diligence prior to 17 May 1996?
35. Are AIC's claims time-barred under section 2 and/or 5 of the Limitation Act 1980, save for the contribution claim?
36. Did AIC rely upon what was said (and not said) during the telcon on 17 April 1996 and, if so, in what way did AIC so rely?
37. What (if any) difference would it have made to AIC's conduct if ITS had disclosed the Cooper re-tests and the results thereof on 17 April 1996 or thereafter?
38. What (if any) difference would it have made to AIC's conduct if, on or after 17 April 1996, ITS had qualified or withdrawn its certificate(s) of quality for the regular cargo?
39. What loss (if any) has been caused by any breaches of contract and/or duty by ITS?
40. Did AIC fail to mitigate and/or did AIC aggravate its loss, and if so to what extent, by:
i) not disclosing certificate of quality for shore tank 61x4 to Galaxy and/or by drawing on Galaxy's letter of credit in the knowledge that the Certificates certified that the cargo had been tested to method D323?
ii) failing to reblend the cargo, or to cause the cargo to be reblended, prior to requesting payment from Galaxy and/or drawing on Galaxy's letter of credit?
iii) failing to agree a cargo discount with Galaxy?
iv) failing to resell the cargo in its existing condition at the prevailing market rates?
v) pursuing unsuccessful legal proceedings in Switzerland against Galaxy, whereby AIC was held liable on Galaxy's cross-claims and incurred legal costs?
41. What were the foreseeable consequences of the alleged breaches of duty? Are the losses (or any of them) claimed by AIC too remote in law to be recoverable?
42. Did AIC cause its loss in whole or in part by acting in bad faith in not disclosing certificate of quality for shore tank 61x4 to Galaxy and/or by drawing on Galaxy's letter of credit in the knowledge that the Certificates certified that the cargo had been tested to method D323?
43. Was ITS liable to Galaxy in tort (in negligence or deceit)?
44. Was ITS liable to Galaxy for the "same damage" in relation to which AIC was held liable to Galaxy in the Swiss proceedings?
45. Is ITS liable to provide an indemnity to AIC in respect of AIC's liability to Galaxy (as established in the Swiss proceedings)?
46. Is ITS liable to provide a contribution to AIC in respect of AIC's liability to Galaxy (as established in the Swiss proceedings) and, if so, what level of contribution is fair and just in all the circumstances?
6. MISTAKE AND DEPARTURE FROM INSTRUCTIONS CONTRASTED
" to be determined by a mutually agreed independent inspector at the loading installation [Antwerp] in the manner customary at such installation such determination shall be final and binding for both parties save fraud or manifest error "
Under clause 4 of the contract against the marginal heading "PRODUCT/QUALITY" the following words appeared:
"Gasoil meeting the following guaranteed specifications:
Test Limit Method ASTM
Density at 15 deg. C +0.876 kg/1 max D1298."
Morison J held that Caleb Brett had been asked to determine the quality of the gasoil using method D 1298; they had not done so and the parties had not agreed to be bound by a determination as to quality by any other method; there was a manifest error due to the wrong test being used; and clause 10 could not operate unless the determination had been made in accordance with the method stipulated in clause 4. The defendants' application for summary dismissal of the claim brought against them was dismissed.
"(i) A mistake is one thing; a departure from instructions quite another. A mistake is made when an expert goes wrong in the course of carrying out his instructions. The difference between that and an expert not carrying out his instructions is obvious.
(ii) Under the old law a mistake would vitiate the expert's determination if it could be shown that it affected the result. That was the concept of material mistake established in Dean v Prince and Frank H. Wright (Constructions) Limited v Frodoor. Not so, however, with regard to a departure from instructions see Ungoed-Thomas J's judgment in Jones v Jones
(iii) Under the modern law the position is the same as it was with regard to a departure from instructions, different with regard to mistakes. As Lord Denning explained in Campbell v Edwards, if an expert makes a mistake whilst carrying out his instructions, the parties are nevertheless bound by it for the very good reason that they have agreed to be bound by it. Where, however, the expert departs from his instructions, the position is very different: in those circumstances the parties have not agreed to be bound.
(iv) The test of materiality devised for identifying vitiating mistakes does not carry across to the quite separate field of departures from instructions. This seems to me so both as a matter of principle and of authority. The position is as stated in Jones v Jones and in Dillon LJ's judgment in Jones v Sherwood at p.287 where he illustrates the principle by reference to Jones v Jones.
(v) Dean v Prince and Frank H. Wright (Constructions) Limited v Frodoor although on any view rightly decided should no longer be regarded as authoritative with regard to experts' mistakes. That for the most part was made clear in Jones v Sherwood. The contrary is not to be inferred from the dictum in Dillon LJ's judgment at p.288 (the other line of reasoning on which he did not found his judgment) referring back to Frank H. Wright (Constructions) Limited v Frodoor. It is time that Dean v Prince and Frank H. Wright (Constructions) Limited v Frodoor received their quietus.
(vi) Once a material departure from instructions is established, the court is not concerned with its effect on the result. The position is accurately stated in paragraph 98 of Lloyd J's judgment in Shell UK v Enterprise Oil: the determination in those circumstances is simply not binding on the parties. Given that a material departure vitiates the determination whether or not it affects the result, it could hardly be the effect on the result which determines the materiality of the departure in the first place. Rather I would hold any departure to be material unless it can truly be characterised as trivial or de minimis in the sense of it being obvious that it could make no possible difference to either party."
I turn to consider the agreed issues in turn.
7. ANALYSIS AND DISCUSSION OF AND CONCLUSIONS AS TO THE AGREED ISSUES
1. To what extent was AIC experienced with the purchase and sale of gasoline at the time of the transactions to which the claim relates?
2. Was ITS retained by Mobil and AIC in any kind of advisory capacity? What was the proper scope of the contractual duties owed by ITS to AIC?
ITS West Thurrock - NAMAS accreditation. M10
ITS Inspection - ISO 9002:1994
"8 METHODS AND PROCEDURES FOR CALIBRATIONS AND TESTS
8.3 The Laboratory shall take all steps to ensure that the Client's requirements are clearly prescribed and understood.
12 CALIBRATION CERTIFICATES, TEST REPORTS AND TEST CERTIFICATES
12.1 The results of each calibration, test or series of calibrations or tests shall be reported accurately, clearly, unambiguously and objectively to the Client. The results shall be reported in a calibration certificate, test report or test certificate. Subject to the agreement of NAMAS the certificate or report may be issued as hard copy or by electronic data transfer. Unless otherwise stated, the requirements of 12 of this Standard apply to all forms of presentation of calibration and/or test results. The certificate or report shall include all information relevant to the validity and application of the calibration or test results and all information required by the calibration or test method and procedure used. This information shall be set out with due regard to ease of assimilation by the reader.
12.2 The certificate or report shall be factually correct and shall be checked before issue.
12.4 The certificate or report shall make it clear whether the results reported refer to calibrations or tests carried out on a single item, or on a batch of items. Where relevant, details of any sampling carried out shall be included.
12.11 Each calibration certificate and test report or test certificate shall also convey at least the following information:
(i) any abnormalities or departures from standard condition;
(j) reference to calibration or test method and procedure used;
(k) any standard or other specification relevant to the calibration or test method or procedure, and deviations, additions to or exclusions from the specification concerned;
(n) any design or performance specifications met or failed;
(p) any other available information requested by a client, relevant to the validity or applicability of the calibration or test result.
12.12 Material amendments to a calibration certificate, test report, or test certificate after issue shall be made only in the form of a further document, or data transfer including the statement, "Supplement to Calibration Certificate, Test Report or Test Certificate, serial number --- (or as otherwise identified)", or equivalent form of wording. Such amendment shall meet all the relevant requirements of 12 of this Standard.
12.13 The Laboratory shall notify clients promptly, in writing, of any event such as the identification of defective measuring or test equipment that casts doubt on the validity of results given in any calibration certificate, test report or test certificate or amendment to a report or certificate.
13 HANDLING OF COMPLAINTS AND ANOMALIES
13.1 The Laboratory shall have documented policy and procedures for the resolution of complaints received from clients or other parties about the Laboratory's accredited activities. A record shall be maintained of all complaints and of the actions taken by the Laboratory.
13.2 Where a complaint, or any other circumstance, raises doubt concerning the Laboratory's compliance with the Laboratory's policies or procedures, or with the requirements of this Standard, or otherwise concerning the quality of the Laboratory's calibrations or tests, the Laboratory shall ensure that those areas of activity and responsibility involved are promptly audited in accordance with 4 of this Standard.
13.3 Where the audit findings cast doubt on the correctness or validity of the Laboratory's calibration or test results, the Laboratory shall immediately notify, in writing, any client whose work may have been affected."
"11.1 Policy
The results of each test or series of tests shall be reported accurately, clearly, unambiguously and objectively to the Client in the form of a test report or test certificate. UKAS requirements shall apply to all forms of presentation of test results. The certificate or report shall include all information relevant to the validity and application of the test results and all information required by the test method and procedure used. This information shall be set out in a manner such as to allow ease of assimilation by the reader
11.2 Authorisation
The certificate or report shall be factually correct and shall be checked and approved before issue
11.4 Supplementary Certificates/Reports
Where amendments to test reports or test certificates are required after issue these shall be in the form of a separate document and should be clearly identified. Supplementary reports and amendments shall meet all other requirements with respect to reporting as described above, including the need for authorisation and signature.
11.5 Validity of Certificates/Reports
The Laboratory shall notify clients in writing of any circumstance, which casts doubt on the validity of results given in any test report or certificate, and, where possible, following corrective action, repeat the tests affected and re-issue an amended report or certificate.
HANDLING OF COMPLAINTS AND ANOMALIES
12.2 Procedure
The following procedure shall be followed to record all client enquiries and complaints if they relate to the quality of service received or when the validity or accuracy of results is in question. This procedure is also applicable to anomalies that have been identified/raised within the laboratory:
c) Subsequent investigation of the complaint shall be undertaken as soon as possible. All findings and resulting actions shall be recorded and the client notified appropriately, preferably in writing. If necessary, corrected versions of reports shall be submitted. All other clients whose work may have been similarly affected shall be notified in writing and again corrected versions of reports submitted."
i) to determine whether Mobil had performed its contract with AIC in the relevant respects, applying the test methods ITS was instructed to apply.
ii) to exercise independent and impartial judgment and to act as an independent and impartial inspection company at all material times.
iii) to report the results of tests independently, accurately, clearly, unambiguously and objectively.
iv) to include in any certificate all information relevant to the validity and application of the test results and all information required by the test method and procedure used.
v) to make it clear whether the results reported referred to tests carried out on a single item, or on a batch of items, including where relevant details of any sampling carried out.
vi) to include in any certificate: - any departures from standard condition; reference to the test method and procedure used; any standard or other specification relevant to the test method or procedure and deviations, additions to or exclusions from the specification concerned.
vii) to issue material amendments to any certificate in the form of a further document by way of a Supplement to the certificate, with a statement to the effect that the same should be passed onto any person to whom the original certificate had been provided.
viii) where a complaint or any other circumstance raised doubt concerning the quality of the tests, to ensure that the relevant work/tests were promptly audited/reviewed. Where the audit/review findings cast doubt on the correctness or validity of the test results such as to necessitate a Supplement to the certificate, to write to Mobil and AIC immediately enclosing the Supplement, with a statement to the effect that the Supplement to the certificate should be passed onto any person to whom the original certificate had been provided.
3. What were ITS' instructions with regard to testing for RVP? Did ITS reasonably interpret its instructions with regard to testing for RVP? Did ITS carry out its instructions with regard to testing for RVP?
4 Were the RVP results by test method ASTM D323 stated in the ITS certificates of quality for the regular cargo:
i) accurate and/or accurately stated?
ii) wrong?
5. Can it be shown whether the regular cargo would have been on- or off-specification in the shore tanks, if DVPE had been tested in accordance with ASTM D5191? If so: Was the regular cargo off-specification in the shore tanks and, if so, did ITS know that the cargo would have been shown to be off-specification, if DVPE had been tested in accordance with D5191?
6. Was ITS negligent in its initial analysis of the regular cargo:
i) in omitting to clarify whether it should use D323 or D5191 before the analysis?
ii) in using the test method D323?; and/or
iii) in failing properly and/or adequately to perform test D323?
"It appears from ITS' load port certificates of quality that several of the test methods reportedly used for the Kriti Palm cargo at Coryton were not the methods required by the CPS:
Test Parameter CPS test method Test method ITS
used
Vapour Pressure ASTM D5191 ASTM D323
Benzene Content ASTM D3606/4053 ASTM D2267/
4815
(Benzene Results % Weight % volume)
Copper Corrosion ASTM D130* IP 154*
Existent Gum ASTM D381* IP 131*
API Gravity ASTM D287/1298 IP 365
Oxidation Stab ASTM D525* IP 40*
Distillation ASTM D86* IP 123*
Oxygenates ASTM D4815 Not tested
Lead Content ASTM D3237 Not stated
(*Indicate test methods used by ITS that are technically equivalent to the CPS test methods for the relevant parameters and would be expected to give results that are not significantly different)."
7. Did ITS fail to have in place any proper system to check the certificates of quality before they were issued? Was ITS negligent in failing to have in place any proper system to check the certificates of quality before they were issued?
8. What statements were contained in the Certificates of Quality? Did the Certificates of Quality contain false statement(s)? In the Certificates, did ITS misrepresent or misreport the results of what it had done?
9. Was ITS negligent in issuing certificates of quality that stated "FUEL MEETS SPECIFICATION" when ITS had used test D323 to test the fuel for RVP?
10. As of 18 April 1996, or thereafter, did AIC in fact rely on the Certificates?
11. As of 18 April 1996, or thereafter, could AIC reasonably rely on the statements in the Certificates that "fuel meets specification" (where applicable)? Further or alternatively, could AIC reasonably rely on the statements in the Certificates that "fuel meets specification" (where applicable), if what AIC had intended to instruct ITS to carry out was a test for DVPE such as that for which D5191 is required?
12. What is/was the uniform practice of arriving at the RVP result of a shore composite blend? What is/was the due method of arriving at the RVP result of a shore composite blend? Did the shore composite blend certificate represent that the RVP result stated therein had been obtained by analysis of a shore composite sample using test D323 and, if so, was ITS negligent in issuing a certificate in that form?
"The certificate or report shall make it clear whether the results reported refer to tests carried out on a single item, or on a batch of items. Where relevant, details of any sampling carried out shall be included".
13. Did Galaxy rely upon ITS' certification of the regular cargo when entering into the AIC/Galaxy contract?
14. What RVP samples were taken by ITS?
2 x 500ml samples for RVP
3 x 16oz (450ml) samples for other tests including density
1 x 2.5 litre (may have been 5 litre) sample sent to West Thurrock for testing.
The 500ml and 16oz samples would have been retained at Mobil Coryton in an unsealed condition post testing.
Mr Adams took:
2 x 2.5 litre samples for each shore tank
17 x 450ml individual ship tank samples and 2 x 5 litre ships composite for the regular gasoline parcel
In-line sample for retention
Mr Adams also prepared a 5 litre shore tank composite from the individual 2.5 litre samples.
The samples (RVP and 16oz) jointly sealed by ITS and SGS included the samples originally tested by Mr Mailey.
(The contents of this paragraph were agreed as between the experts).
"Distribution/Disposal of Samples:
Retained samples are intended to be held for a period of 90 days."
15. What was ITS' standard practice as regards sample retention? What material was subject to ITS' sample retention standards?
"4.0 RESPONSIBILITY
4.1 It is the responsibility of the chemist/inspector to transport samples safely to the area office reception point. It is also his responsibility to carry out registration, labelling, and analysis requirements documentation. If samples are not required for testing, it is the responsibility of the Inspector to place them in the location's sample store. It is the laboratory supervisor/chemist's responsibility to receive samples for testing and comply with laboratory booking in arrangements. Subsequent to testing, it is the laboratory staff's responsibility to place unused surplus sample material in the location's sample storage.
5.6 Samples shall be retained in storage for a minimum period of 90 days, unless the client's agreement to change this period can be obtained. It may be permitted to dispose of samples before the minimum period if causing a hazard or potential health problem.
5.7 Where it becomes necessary within the 90 minimum retention period to dispose of any sample due to either a risk arising form the hazardous nature of a sample [or] a potential health risk then the client on behalf of whom the sample is being retained shall be informed as soon as is reasonably practicable.
5.8 Where a client requests an extended period of retention beyond the 90 days normally granted and where this is agreed, such samples shall be segregated and clearly marked for extended retention.
5.9 Agreement to extend the normal retention time beyond the ninety day period normally granted shall be in writing and the disposal date now accepted shall be stated in the agreement.
5.10 On a monthly basis, samples are disposed of in accordance with local and statutory requirements."
"Distribution/Disposal of Samples:
Retained samples are intended to be held for a period of 90 days."
16. What RVP samples were kept by ITS, if any; and in what condition? What residues of samples were kept by ITS; and in what condition?
17. What material was the subject-matter of the re-tests by Mr Cooper on 16 April 1996?
18. Was the material re-tested by Mr Cooper being held by ITS on behalf of AIC and Mobil?
19. Was the material re-tested by Mr Cooper properly to be regarded as the joint property of AIC and Mobil?
20. Should ITS have sought AIC's and Mobil's permission before conducting such re-tests and was ITS in breach of duty in failing so to do?
ITS was under a distinct contractual duty to inform its clients about the Cooper re-tests and the results thereof. This duty arose because the RVP samples which were tested by Mr Cooper were being retained on behalf of the clients and/or were properly to be regarded as the joint property of the clients and/or were potentially important to a known dispute between the clients. In such circumstances, ITS should not have re-tested the samples without first seeking its clients' permission and, if it did test or use the samples without its clients' permission, it came under a duty to inform the clients of the fact and consequences thereof.
The RVP samples were retain samples.
Even remnants of testing samples should be retained according to ITS' own procedures, and are in fact retained, by ITS. This is because they may be potentially relevant to the clients, as accepted by Mr Loughead and, at least in part, by Mr Lucas. In such circumstances, the duty is clear and was admitted by Mr Lucas in his evidence.
Even if the RVP samples were not retain samples, the fact is that they had been kept by ITS in a sample crate at the back of the store at the Coryton laboratory. Given that a dispute had arisen involving ITS' clients and given that the samples were potentially important to that dispute, as acknowledged by Mr Loughead and Mr Lucas, the same duty applied. Even Mr Chalmers accepted that the duty would apply to any potentially important samples.
In any event, the RVP samples tested by Mr Cooper are properly to be regarded as the joint property of AIC and Mobil. On no view can they be regarded as ITS' property. The product in the shore tanks was Mobil's property. Property in the product passed to AIC at the ship's manifold. Once loading of cargo commenced, samples taken and analysed and on the basis of which the cargo was certified for loading, became the joint property of AIC and Mobil. If the samples were the joint property of AIC and Mobil as at 16 April 1996, ITS was under a clear duty not to use those samples in any way without permission and, having done so on 16 April 1996, was under a duty to communicate to its clients the fact and consequences thereof.
ITS' instructions were to carry out "full static shore tank samples and analysis" and to take certain other samples. ITS accepted those instructions and pursuant thereto provided the loading report. The loading report listed the samples which had been taken pursuant to the instruction to take samples and undertook to hold them for 90 days. The list included all the specific samples which ITS had been instructed to take, including not only the shore tank samples but also the inline samples and the ship's cargo tank samples. There has never been any suggestion from AIC that that list was non-compliant with its instructions or that AIC required anything else to be retained. The express terms of the contractual bargain were that ITS would retain for 90 days the samples listed in the loading report.
The samples agreed to be retained and listed in the loading report were sealed by ITS and given ITS seal numbers. Following Mr Sampino's request on the evening of 17 April 1996 the samples being retained by ITS pursuant to the above contractual obligations were double sealed by SGS.
The samples listed in the loading report were retained un-touched for at least 90 days. All of these were complete virgin un-broached original samples. These are not the residues of samples tested by Mr Mailey and then re-tested by Mr Cooper.
The retain samples listed in the loading report were the samples which ITS and AIC had contractually agreed to retain for the purposes of AIC's commercial interest in being able to investigate subsequent quality disputes.
In relation to the retain samples listed in the loading report, ITS accepts that it is normal inspection procedure to take a retain sample, that ITS' contract with Mobil required this to be done and that it would be standard industry practice to take such retain samples. It is unnecessary to imply a term that such samples be retained because the matter is regulated by the express terms of the bargain.
AIC's case that in addition to the retain samples covered by the express terms of the agreement a term should be implied that ITS would retain "all samples taken ... in relation to the cargo", including the residues of RVP testing samples left over from Mr Mailey's RVP tests, is wrong. Not only does it involve an attempt to legislate by a process of implication for something which is already covered by the express terms of the bargain. It is also unnecessary because AIC's commercial interest in being able to investigate subsequent quality disputes is sufficiently and better covered by the unbroached virgin samples the subject of the express retention obligation.
Further and in any event there is no evidence that industry practice in relation to the retention and disposal of residues is uniform.
Where a complaint or any other circumstance raised doubt concerning the quality of the tests, to ensure that the relevant work/tests were promptly audited/reviewed. Where the audit/review findings cast doubt on the correctness or validity of the test results such as to necessitate a Supplement to the certificate, to write to Mobil and AIC immediately enclosing the Supplement, with a statement to the effect that the Supplement to the certificate should be passed onto any person to whom the original certificate had been provided.
"RVP was tested by ITS Lab Tech at Coryton to ASTM D323 as an oversight and error not picked up at reporting stage by Inspection office".
"Distribution/Disposal of Samples:
Retained samples are intended to be held for a period of 90 days."
i) if the results supported the contention that the cargo was on-specification, the results would be disclosed to Mobil/AIC, but
ii) if the results did not support the contention that the cargo was on-specification, the results would not be disclosed to Mobil/AIC.
21. Are/were the results of the re-tests to be relied on for any purpose? Should ITS have informed AIC and Mobil about the fact of the re-tests and the results thereof and was ITS in breach of duty in failing so to do?
i) if the results supported the contention that the cargo was on-specification, the results would be disclosed to Mobil/AIC, but
ii) if the results did not support the contention that the cargo was on-specification, the results would not be disclosed to Mobil/AIC.
22. Should ITS have informed AIC about the fact of the re-tests and the results thereof in the telcon on 17 April 1996, and/or subsequent to the telcon, and was ITS in breach of duty in failing so to do?
23. Did Mr Lucas know of the re-tests and the results thereof (i) by the time of the telcon on 17 April 1996 and (ii) thereafter?
24. What was Mr Chalmers' knowledge of the re-tests and the results thereof by 17 April 1996 and thereafter?
25. Was what was said (and not said) by Mr Lucas in the telcon on 17 April 1996 false and misleading?
26. Was Mr Lucas negligent in what he said (and did not say) during the telcon on 17 April 1996?
27. Was Mr Lucas dishonest in what he said (and did not say) during the telcon on 17 April 1996?
28. Did Mr Lucas intend AIC to rely upon what he said during the telcon on 17 April 1996?
29. On or after 17 April 1996 was ITS negligent in failing to correct or qualify or withdraw what had been stated in the certificates of quality?
30. On or after 17 April 1996 were Mr Lucas and/or Mr Chalmers dishonest in failing to correct or qualify or withdraw what had been stated in the certificates of quality?
Mr Lucas was criticised for "standing by the certificate". If that oral remark had stood on its own it would raise high level policy issues. In fact it did not stand on its own because Mr Lucas threw the certificate back into doubt by refusing to comment on whether the certificate was inaccurate, saying he did not know whether the certificate was inaccurate information, refusing to say whether the certificate was inaccurate or not, and actively encouraging Mr Whitaker to put matters into the hands of AIC's lawyers. Early in the conversation, Mr Whitaker said he was looking for written confirmation that the wrong method had been used and "some sort of compensation from yourselves (ITS) for this amount of money I am going to have to pay in order to get this cargo discharged". This is not the language of somebody who is saying: "I do not know which way to jump. Will you please advise me." In this context Mr Lucas was not to trying to mislead Mr Whitaker into taking an erroneous position within the sale chain.
(1) Mr Lucas said "It is impossible to go back into any of the samples because no samples are kept under ice."
(2) (In answer to Mr Whitaker's statement "I have to find out some way of proving that it actually is off-specification you are telling me that I cannot do that") Mr Lucas said "Not to the load port, but you can at the discharge port".
(3) (In answer to a statement from Mr Whitaker "I have a Quality Certificate from you that says it is on-specification") Mr Lucas replied "we will be standing by that certificate".
(4) (In answer to a question from Mr Whitaker "well if the test 323 was done where test 5191 should have been done do you not see that as inaccurate?") Mr Lucas said "I can't say whether it is inaccurate or not".
i) the contract between Mobil and AIC; and
ii) any letter of credit in relation to the contract between Mobil and AIC; and
iii) the contract between AIC and its sub-buyer (Galaxy); and
iv) any letter of credit in relation to the contract between AIC and its sub-buyer,
it was essential for all concerned to know whether ITS' certificate stood or did not stand.
On 17 April Mr Lucas represented (i) that the shore composite blend certificate was and remained a good and valid certificate and (ii) that it was "impossible to go back into any of the samples because no samples [were] kept under ice" when
a) ITS' duties as an independent inspection company were as set out in paragraph [192] above; and
b) Mr Lucas knew (and confirmed to Mr Whitaker) that ITS had tested Vapour Pressure by test D323 instead of D5191; and
c) The overwhelming probability is that Mr Rackham informed Mr Lucas of the Cooper re-tests and the results thereof (and the ITS (US) and SGS D5191 disport results) in the course of briefing Mr Lucas prior to the telephone conversation on 17 April; and
d) Mr Lucas knew that the results of the Cooper re-tests established on a balance of probabilities that the tests ITS carried out before loading significantly understated the Vapour Pressure of the regular grade gasoline; and
e) Mr Lucas knew that the Cooper re-test results indicated that the original D323 tests carried out by Mr Mailey were not in accordance with the stated test procedures and that at least some of the D323 results, as reported by ITS, were probably incorrect and significantly understated the Vapour Pressure of the gasoline in at least two of the shore tanks at Mobil Coryton; and
f) Mr Lucas knew that the ITS (US) and SGS Vapour Pressure results broadly corroborated each other and when viewed together with the Cooper re-test results confirmed that the regular motor gasoline on board the Kriti Palm was probably off-specification; and
g) Mr Lucas knew that the Vapour Pressure results by test method D323 stated in the ITS certificates of quality for the regular cargo were probably wrong and that the results of the Cooper re-tests were a key piece of evidence, highly relevant to this conclusion; and
h) Mr Lucas knew from the results of the Cooper re-tests that the cargo would probably have been shown to be off-specification, if DVPE had been tested in accordance with D5191; and
i) Mr Lucas knew that in all the circumstances then known to him it was wrong for ITS to maintain that a certificate which said "Fuel meets Specification" was and remained a good valid and certificate.
"Q If you had known that ITS had themselves just carried out tests in relation to load port, it would have been misleading to tell them there is nothing you can do?
A. Firstly I did not know about the Cooper results. Secondly the Cooper results themselves would have caused a further problem of communication, because I could not have raised the certificate on the Cooper results.
Q. You are agreeing with me that had you known about those results, you would have had to qualify the statement you are making there?
A. That is right. But I think it shows that I did not know about the results.
Q ... So when he says to you, "I have a Quality Certificate that says it is on specification", and you say that you will be standing by that certificate, you are telling him that as far as you were concerned it is and remains a good certificate yes?
A. Yes.
Q. And that it remains a certificate that says it is on specification?
A. That is exactly what I felt I said.
Q. So you were convinced it was on-spec, you were convinced that what was loaded on board was on-spec?
A. I was convinced that the shore tank analysis showed that the cargo was on specification.
A. I knew nothing about the correlation between D323 and D5191 .
Q. So are you saying that you do not know whether the result is inaccurate or not because you do not know what the result would be by D5191?
A. That is quite true.
Q. But if you had been aware that Mr Cooper had just done his tests using D5191 and had found that the cargo was off-spec, then again it would have been misleading to say that you simply cannot say whether it was inaccurate or not because you had further information?
A. That would be true, but also it would be true to say that if I'd known about the other cargo, I could have pointed out that there appeared to be quite a correlation between D323 and D5191.
Q. Did it not occur to you that when you did learn about the re-tests a day or so later, that you ought to have put the record straight so far as Mr Whitaker was concerned?
A. Let me stop you right there, if I may. Once you are under notice of a claim, that is the end of the communications, you just stop. That is how we do things in Caleb Brett."
31. Did Mr Lucas and/or Mr Chalmers make a deliberate decision not to disclose the fact of the Cooper re-tests and/or the results thereof to AIC and Mobil in circumstances where the re-tests and/or the results thereof should have been disclosed to AIC and Mobil and/or Mr Lucas and/or Mr Chalmers knew that the re-tests and/or the results thereof should have been disclosed to AIC and Mobil?
32. If and to the extent that ITS was under a duty to disclose the fact of the Cooper re-tests and/or the results thereof (see issue 22 above), on or after 17 April 1996 were Mr Lucas and/or Mr Chalmers aware that ITS was under such a duty and did Mr Lucas and/or Mr Chalmers make a deliberate decision not to disclose the same?
33.Did ITS deliberately conceal a fact relevant to AIC's right of action against ITS?
34. If ITS did deliberately conceal a fact relevant to AIC's right of action against ITS, should AIC nevertheless have found out that fact by the exercise of reasonable diligence prior to 17 May 1996?
"Postponement of limitation period in case of fraud, concealment or mistake
(1) where in the case of any action for which a period of limitation is prescribed by this Act, either
(a) the action is based upon the fraud of the defendant; or
(b) any fact relevant to the plaintiff's right of action has been deliberately concealed from him by the defendant;
the period of limitation shall not begin to run unitl the plaintiff has discovered the fraud [or] concealment (as the case may be) or could with reasonable diligence have discovered it.
(2) For the purposes of subsection (1) above, deliberate commission of a breach of duty in circumstances in which it is unlikely to be discovered for some time amounts to deliberate concealment of the facts involved in that breach of duty."
"For my part I accept [the] submission that, in construing the section, there is no middle ground between facts and evidence Facts which improve prospects of success are not, as it seems to me, facts relevant to the right of action I accept that the construction proposed is a narrow one, but unless it is correct it is difficult to see what purpose is served by the special provisions with regard to personal injury actions which are contained in section 33 of the Act."
Rose LJ accepted the statement of claim test, that it is knowledge of the facts which should be pleaded in the statement of claim.
"In order to give relief to the plaintiff any new fact must be relevant to the plaintiff's 'right of action' and is to be contrasted with the facts relevant, for example, to 'the plaintiff's action' or 'his case' or 'his right to damages.' The right of action in this case was complete at the moment of arrest. No other ingredient was necessary to complete the right of action. Accordingly, whilst I acknowledge that new facts might make the plaintiff's case stronger or his right to damages more readily capable of proof they do not in my view bite upon the 'right of action' itself. They do not affect the 'right of action,' which was already complete, and consequently in my judgment are not relevant to it."
"In one sense it is true to say that the tort of false imprisonment has two ingredients; the fact of imprisonment and the absence of lawful authority to justify it. But as I understand the law, the gist of the action of false imprisonment is the mere imprisonment. The plaintiff need not prove that the imprisonment was unlawful or malicious; he establishes a prima facie case if he proves he was imprisoned by the defendant. The onus is then shifted to the defendant to prove some justification for it. If that be right, one looks at the words in section 32 (1) (b), 'any fact relevant to the plaintiff's right of action.' It seems to me that those words must mean any fact which the plaintiff has to prove to establish a prima facie case."
"In my judgment, the decision in Johnson, which is of course binding upon this court, must be applied to the relevant expression in section 32A as it applies to the expression in section 32 (1) (b). The relevant facts are those which the plaintiff has to prove to establish a prima facie case. That being so, the fact alleged to have come known to the plaintiff only in August 1993, that drug smuggling had not been mentioned in court, is not a relevant fact within the meaning of section 32A.
As well as being bound by it, I respectfully agree with the decision in Johnson. In section 32A Parliament has for actions for libel or slander breached the protection which a period of limitation ordinarily gives to a defendant. I do not consider that Parliament has intended, in the words used in section 32A, to create a breach so wide as to enable facts relevant to possible defences to the action to be a relevant consideration. Given the public interest in finality and the importance of certainty in the law of limitation, I would have expected Parliament to use words different and more general had the broad construction, with the uncertainties it involves, been intended. The facts relevant to the cause of action are confined to the limited class of facts contemplated in Johnson."
"In my opinion, section 32 deprives a defendant of a limitation defence in two situations: (i) where he takes active steps to conceal his own breach of duty after he has become aware of it; and (ii) where he is guilty of deliberate wrongdoing and conceals or fails to disclose it in circumstances where it is unlikely to be discovered for some time. But it does not deprive a defendant of a limitation defence where he is charged with negligence if, being unaware of his error or that he has failed to take proper care, there has been nothing for him to disclose."
" deliberate concealment for section 32(1)(b) purposes may be brought about by an act or an omission and that, in either case, the result of the act or omission, i e, the concealment, must be an intended result. But I do not agree that that renders subsection (2) otiose. A claimant who proposes to invoke section 32(1)(b) in order to defeat a Limitation Act defence must prove the facts necessary to bring the case within the paragraph. He can do so if he can show that some fact relevant to his right of action has been concealed from him either by a positive act of concealment or by a withholding of relevant information, but, in either case, with the intention of concealing the fact or facts in question. In many cases the requisite proof of intention might be quite difficult to provide. The standard of proof would be the usual balance of probabilities standard and inferences could of course be drawn from suitable primary facts but, nonetheless, proof of intention, particularly where an omission rather than a positive act is relied on, is often very difficult. Subsection (2), however, provides an alternative route. The claimant need not concentrate on the allegedly concealed facts but can instead concentrate on the commission of the breach of duty. If the claimant can show that the defendant knew he was committing a breach of duty, or intended to commit the breach of duty - I can discern no difference between the two formulations; each would constitute, in my opinion, a deliberate commission of the breach - then, if the circumstances are such that the claimant is unlikely to discover for some time that the breach of duty has been committed, the facts involved in the breach are taken to have been deliberately concealed for subsection (1)(b) purposes. I do not agree with Mr Doctor that the subsection, thus construed, adds nothing. It provides an alternative, and in some cases what may well be an easier, means of establishing the facts necessary to bring the case within section 32(1)(b)."
"I begin with the specific terms of s.32(1)(b): 'any fact relevant to the plaintiff's right of action has been deliberately concealed from him by the defendant'. Those words describe the condition which must exist before the operative part of s.32(1) takes effect. There are four points on the wording of the paragraph which should be noted.
i) The paragraph does not say that the right of action must have been concealed from the claimant: it says only that a fact relevant to the right of action should have been concealed from the claimant.
ii) Although the concealed fact must have been relevant to the right of action, the paragraph does not say, and in my judgment does not require, that the defendant must have known that the fact was relevant to the right of action. In most cases where s.32(1)(b) applies the defendant probably will have known that the fact or facts which he concealed were relevant, but that is not essential. All that is essential is that the fact must actually have been relevant, whether the defendant knew that or not. The paragraph does of course require that the fact was one which the defendant knew, because otherwise he could not have concealed it. But it is not necessary in addition that the defendant knew that the fact was relevant to the claimant's right of action.
iii) The paragraph requires only that any fact relevant to the right of action is concealed. It does not require that all facts relevant to the right of action are concealed.
iv) The requirement is that the fact must be 'deliberately concealed'. It is, I think, plain that, for concealment to be deliberate, the defendant must have considered whether to inform the claimant of the fact and decided not to. I would go further and accept that the fact which he decides not to disclose either must be one which it was his duty to disclose, or must at least be one which he would ordinarily have disclosed in the normal course of his relationship with the claimant, but in the case of which he consciously decided to depart from what he would normally have done and to keep quiet about it."
"The wording of s.32(1)(b) refers to a situation in which:
"any fact relevant to the plaintiff's cause of action has been deliberately concealed from him by the defendant."
This wording is open to differing interpretations. We have to consider what the words "deliberately concealed" require by way of (a) mental element and (b) conduct. The wording requires the defendant to know some fact, and the fact must be relevant to the plaintiff's cause of action. The wording clearly also requires a conscious decision by the defendant not to communicate that fact to the plaintiff. But those factors cannot be enough. A defendant may know a fact and may consciously decide not to communicate it for innocent reasons, e.g. because he fails to realise that it has any relevance whatever to the plaintiff. Must the defendant therefore realise that the fact is "relevant to the plaintiff's cause of action" against himself or herself? If so, this would seem to mean that the defendant must at least have in mind the possibility of an actual or potential cause of action against him, realise that there was a fact relevant to it and then conceal that. Or is the sole additional element to be found in the nature of the conduct, or of the context, implicit in the word "concealment"?"
"There are, as I have already indicated, two possible interpretations of the mental element required under s.32(1)(b). On the (slightly) more limited reading, s.32(1)(b) is confined to the typical situation; it therefore requires deliberate concealment of a fact in circumstances where the defendant realises that the fact has some relevance to an actual or potential claim against him (or is reckless as to whether or not it does). So read, s.32(1)(b) and s.32(2) can be said to present a more coherent scheme; and the running of a limitation period would not be postponed by a deliberate concealment of a fact by a defendant, which was in breach of a duty unrelated to the wrongdoing in respect of which the claimant later claims and which occurred in circumstances where the defendant did not realise that the fact suppressed had relevance to any such wrongdoing (and was not reckless in not realising this). The wider reading is that any deliberate concealment should carry the consequence attributed by s.32(1)(b), even though the defendant did not (and it may be could not) realise that the fact concealed had any relevance to any actual or potential wrongdoing. Deliberate concealment, at least if that means active misleading or knowing breach of a duty to speak, is a particularly serious matter; if a person is as a result kept in ignorance of a fact which later proves to be relevant to a cause of action against the person concealing the fact, it may be thought just that the limitation period should not run against that defendant, even though he or she did not realise the relevance of the fact to any cause of action. On the other hand, that conclusion could lead to cases where, for example, a solicitor's deliberate decision out of, for example, laziness to delay communication of information about the general conduct of a matter for a month while he went on holiday would, if the information later proved relevant to some wholly unsuspected cause of action for negligence involving him or indeed some other member of the same firm, have the effect of restarting a limitation period as against his firm."
"I see the force of the argument that any intentional concealment should be sufficient, at least if concealment involves active misconduct or breach of a duty to speak. However it is also possible to argue that the rationale and wording of the statute tend to point to the (slightly) more limited reading that I have mentioned. Whether the wider or the more limited reading should be preferred may perhaps also be influenced by the proper resolution of the potential difference between Lord Millett's and Lord Scott's formulation of the nature of the conduct involved in concealment that is, by whether mere silent withholding suffices or whether there must be active concealment or breach of a duty to speak. This latter aspect was not explored before us. In these circumstances, and since I consider that it unnecessary on this appeal to arrive at any final view as to whether the wider or narrower meaning should be preferred, I prefer not to do so."
"The claimant did not know a fact relevant to her cause of action until a date less than six years before this action was brought, and the reason why she did not know it was that Mr Brown intentionally concealed it from her when he was under a duty to tell her about it. These facts appear to me to fall within the compass of Lord Scott's exposition of the effect of section 32(1)(b) of the 1980 Act in paragraph 60 of his speech in Cave."
The Cooper re-tests and results are directly relevant to a number of AIC's causes of action.
First, they are relevant to, and indeed form the foundation of, AIC's contractual cause of action that it should have been informed of the re-tests and the results, since they related to samples being retained for their benefit.
This is a cause of action of which AIC was not and could not have been aware until the Cooper re-tests were (finally) disclosed. It is therefore an a fortiori case of a "fact relevant to the plaintiff's right of action" being concealed.
Secondly, they are relevant to the tortious and contractual cause of action that pursuant to its duty of reasonable skill and care, ITS should have communicated the fact of the re-tests and the results. Again, this is a cause of action which plainly depends on knowledge of the Cooper re-tests.
Thirdly, they are relevant to the causes of action that there was an obligation (in the light of the re-test results) to correct or qualify or withdraw the certificates and/or representations made. The existence of the re-test results is clearly central to those causes of action.
The Cooper re-tests and the results also reveal facts relevant to the more general causes of action in negligence, negligent misrepresentation and deceit, namely: (1) that the cargo was off-spec on loading; (2) that the cargo would have been shown off-spec on loading if tested in accordance with D5191; (3) that something must have gone seriously wrong as regards the performance of the initial D323 tests; (4) that the original D323 results were not reliable; and (5) that ITS knew or should have known of these facts on or after 17 April 1996.
It is over-simplistic for ITS to say that a cause of action in negligence was pleaded before the Cooper re-tests were disclosed, and thus deliberate concealment is irrelevant to any claim in negligence.
One must focus carefully on the precise way in which the various causes of action in negligence and negligent misrepresentation are put. The causes of action premised on knowledge of the Cooper re-tests and results are significantly different from the causes of action originally pleaded. The basis of the original pleading was that the wrong test had been used and that, had the right test been used, the cargo would have been found to be off-specification because, as the defendant knew, the two tests gave different results with D323 giving lower readings than D5191. The basis of the case made in the light of the Cooper re-tests is that, although it is now accepted that the two test methods would be expected to give similar results, in this case they would not have done so because the original D323 tests were not reliable or accurate, as the Cooper re-tests demonstrate. The allegations of negligence and the allegations as to why statements made were false, and should have been known to be false, are now premised squarely on the Cooper re-tests and results.
Further, even if AIC had been able to plead in 2002 (following the Swiss proceedings and the analysis of the expert evidence adduced therein) that the cargo was probably off-spec on loading regardless of which test was used as opposed to because of the test which was used, and to do so without knowledge of the Cooper re-tests and results, that does not mean that AIC knew that the cargo was in fact off-spec in this sense before 17 May 1996. In fact, AIC did not know at any time prior to 17 May 1996 that the cargo was in fact off-spec at the load port. This is hardly surprising given that (1) Mr Lucas had told AIC on 17 April 1996 that the cargo was on-spec at the load port and that the results at the disport did not show the contrary and (2) Mobil had made the same points on 17 April 1996 and 19 April 1996. In such circumstances, applying Lord Millett's approach in Cave v. Robinson, ITS' deliberate concealment of the Cooper re-test results remained an operative concealment of the fact that the cargo was probably off-spec on loading (as revealed by the re-test results) up to and well beyond 17 May 1996, with the result that the commencement of the limitation period is postponed to at least that date.
The purpose behind section 32 (1) (b) of the 1980 Act is to cater for the case where, as a result of the deliberate concealment, the claimant lacks sufficient information to plead a complete cause of action. This is what is described as the "statement of claim" test. It is to be contrasted with the case where the information which has been deliberately concealed makes the claimant's case stronger or improves its prospects of success: Johnson v Chief Constable of Surrey (supra); C v Mirror Group Newspapers supra; see also Imperio v Heath [1999] 1 Lloyds Rep IR 571 at 593L.
It follows from the "statement of claim" test that s 32 (1) (b) can have no application to a case where the matters which are said to have been "deliberately concealed" emerge on disclosure during the proceedings. Such a case presupposes that the claimant had sufficient information to plead a statement of claim without the "concealed" material.
Section 32 (1) (b) cannot therefore apply to AIC's claim for "initial negligence" because this claim could be and was pleaded without access to the material (namely the Cooper re-tests) which is said to have been deliberately concealed.
The same applies to the pleas of negligent representation on 17 April 1996 and in the follow-up correspondence. This likewise was pleaded in the original Particulars of Claim. ITS did not need and did not rely on the Cooper re-tests in order to plead that the alleged misrepresentations on 17 April (and subsequently) were negligent, any more than it needed the Cooper re-tests to plead that the initial representation was negligent. The plea of negligent repetition of a previous misrepresentation adds nothing to AIC's case for limitation purposes.
If the plea of deceit is well founded then that claim would come within section 32 (1) (a) Limitation Act 1980. The alternative pleas in negligent misrepresentation fail the "statement of claim" test. With one exception the same applies to the pleas of breach of contract. AIC did not need the Cooper re-tests to plead breach of instructions to use method D5191. AIC knew about this in 1996. Nor did AIC need the Cooper re-tests to plead its case of contractual negligence in the conduct of the tests, nor its case as to the representations contained in the original certificates and said to have been repeated on and after 17 April.
The exception is the very recent contractual plea of an implied contractual duty to disclose the Cooper re-tests.
It is accepted that this is a different cause of action which could not have been pleaded without the Cooper re-tests. However the question under section 32 (1) (b) is whether the amendment introduces a different "right of action", having regard to the purpose behind that section.
"As at 17 April nobody knew whether the error was material or not Mobil was perfectly entitled to take the view that unless and until this departure from mandate is shown to have had a material effect on the end result and shown conclusively to have had that effect, we are entitled to rely upon it as being a binding published certificate."
35. Are AIC's claims time-barred under section 2 and/or 5 of the Limitation Act 1980, save for the contribution claim?
36. Did AIC rely upon what was said (and not said) during the telcon on 17 April 1996 and, if so, in what way did AIC so rely?
37. What (if any) difference would it have made to AIC's conduct if ITS had disclosed the Cooper re-tests and the results thereof on 17 April 1996 or thereafter?
38. What (if any) difference would it have made to AIC's conduct if, on or after 17 April 1996, ITS had qualified or withdrawn its certificate(s) of quality for the regular cargo?
39.What loss (if any) has been caused by any breaches of contract and/or duty by ITS?
In Smith Kline & French Laboratories v Long [1989] 1 WLR 1 CA, it was accepted that the correct measure of damages was the tortious measure and not the contractual.
In Smith New Court Securities v Scrimgeour Vickers, [1997] AC 254, the legal principles were reviewed and it was held that in the case of deceit, the loss need not have been reasonably foreseeable.
The relevant legal principles can be summarised as follows. (i) The measure of damages is that which serves to put the claimant into the position he would have been in if the false representation had not been made to him. (ii) The defendant wrongdoer is liable for all the loss directly flowing from the representation whether or not the loss was reasonably foreseeable. (iii) For the loss to be direct, it is not necessary to show that the false representation was the sole cause of the loss: it is sufficient to demonstrate that it made a material contribution to it. (iv) Contributory negligence is no defence.
1. Liability to Galaxy Energy (USA) Inc. | |
(1) | US$1,165,037.62 plus interest thereon at 5% per annum from 15 April 1996. |
(2) | US$51, 036.72 plus interest thereon at 5% per annum from 22 July 1996. |
(3) Total accrued interest on the date of payment (12.12.03) | US$465,771.82 |
(4) Costs CHF138,786.70 | (US$108,724). |
Total liability to Galaxy | US$1,681,846.10 plus CHF138,786.70 (US$108, 724) |
2. Expenses arising from Galaxy's refusal to accept cargo | |
(1) Demurrage at GATX terminal and IMTT-Bayonne terminal: | US$64,551.04 |
(2) Costs of storage at IMTT Bayonne terminal: | US$344,412.53 |
(3) US Customs duties: | US$9,567.35 |
Total expenses of Galaxy's refusal to accept cargo: | US$ 418, 530.92 |
3. Expenses arising from Galaxy injunction stopping payment under sale contract | |
Finance charges: | US$134,821.56 |
4. Costs in the Swiss proceedings | |
(1) Python Schifferli Peter & Associes - | CHF379,329.00 (US$297,163). |
(2) Winter & Partner - | CHF6,786.20 (US$5,316.26). |
Total costs in the Swiss proceedings- | CHF386,115.20 |
5. US lawyers' fees | |
(1) Curtis, Mallet-Prevost, Colt & Mosle- | US$40,294.17 |
(2) Richards, Layton & Finger, PA- | US$8,089.65 |
Total fees of US lawyers- | US$48,383.82 |
Total loss and damage | (1) US$2,283,582 |
(2) CHF524,901.90 |
40. Did AIC fail to mitigate and/or did AIC aggravate its loss, and if so to what extent, by:
i) not disclosing certificate of quality for shore tank 61x4 to Galaxy and/or by drawing on Galaxy's letter of credit in the knowledge that the Certificates certified that the cargo had been tested to method D323?
ii) failing to reblend the cargo, or to cause the cargo to be reblended, prior to requesting payment from Galaxy and/or drawing on Galaxy's letter of credit?
iii) failing to agree a cargo discount with Galaxy?
iv) failing to resell the cargo in its existing condition at the prevailing market rates?
v) pursuing unsuccessful legal proceedings in Switzerland against Galaxy, whereby AIC was held liable on Galaxy's cross-claims and incurred legal costs?
41. What were the foreseeable consequences of the alleged breaches of duty? Are the losses (or any of them) claimed by AIC too remote in law to be recoverable?
42. Did AIC cause its loss in whole or in part by acting in bad faith in not disclosing certificate of quality for shore tank 61x4 to Galaxy and/or by drawing on Galaxy's letter of credit in the knowledge that the Certificates certified that the cargo had been tested to method D323?
43.Was ITS liable to Galaxy in tort (in negligence or deceit)?
44.Was ITS liable to Galaxy for the "same damage" in relation to which AIC was held liable to Galaxy in the Swiss proceedings?
45. Is ITS liable to provide an indemnity to AIC in respect of AIC's liability to Galaxy (as established in the Swiss proceedings)?
46. Is ITS liable to provide a contribution to AIC in respect of AIC's liability to Galaxy (as established in the Swiss proceedings) and, if so, what level of contribution is fair and just in all the circumstances?
8. CONCLUSION