Neutral Citation Number: [2019] EWHC 1495 (Ch)
Case No: PT-2017-000163
IN THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND & WALES
PROPERTY TRUSTS AND PROBATE LIST (ChD)
Rolls Building
Fetter Lane, London, EC4A 1NL
Date: Thursday 13 th June 2019
Before :
THE HONOURABLE MR JUSTICE BARLING
- - - - - - - - - - - - - - - - - - - - -
Between :
THE MANCHESTER SHIP CANAL COMPANY LIMITED
Claimant
-and-
UNITED UTILITIES WATER LIMITED
Defendant
- - - - - - - - - - - - - - - - - - - - -
- - - - - - - - - - - - - - - - - - - - -
Charles Morgan and Nicholas Ostrowski (instructed by BDB Pitmans LLP ) for the Claimant
Jonathan Karas QC, Julian Greenhill QC and James McCreath (instructed by Pinsent Masons LLP ) for the Defendant
Hearing dates: 13 - 16 November 2018
- - - - - - - - - - - - - - - - - - - - -
JUDGMENT
INDEX
HEADING |
PAGE NO. |
Introduction
| |
Background
| |
Relevant legislation
| |
The 2010 Claim
Judgment and Order of the Supreme Court
Judgment and Order of Newey J on the matter being remitted |
|
UU’s strike out/summary judgment application Preliminary observations (1) The effect of the SC Decision
The parties’ submissions Discussion and conclusion (2) Cause of action estoppel
Cause of action estoppel: the case law
Cause of action estoppel: discussion and conclusions
(3) Issue Estoppel
(4) Henderson v Henderson abuse of process
(5) Other issues relating to the Present Claim
|
|
MSC’s amendment application
Introduction
Principles relating to amendment
Section 186 of the 1991 Act
The s.186 Point
The application
Estoppel arguments
Henderson v Henderson argument
Other issues relating to s.186 Point
|
|
Overall conclusion | |
Annex |
GLOSSARY OF ABBREVIATED TERMS
PARA WHERE FIRST DESCRIBED |
EXPLANATION | |
“the Canal” |
2 |
The Manchester Ship Canal
|
“Couch 1” |
6 |
The first witness statement of Mr Graeme Couch, solicitor for MSC
|
“Couch 2” |
6 |
The second witness of Mr Graeme Couch, solicitor for MSC
|
“Couch 3” |
6 |
The third witness statement of Mr Graeme Couch, solicitor for MSC
|
“the Deeming Provision” |
149 |
Subsection 186(2) of the Water Industry Act 1991
|
“the Davyhulme Works” |
2 |
Davyhulme Waste Water Treatment Works based in Urmston, Greater Manchester
|
“the Marshbrook Sewer” |
3 |
A sewer adopted as part of its public network by UU on 5 October 2007 pursuant to an agreement with a developer, which drained waste water and effluent from properties at Marshbrook Drive, Manchester. The sewer may have been connected to the public network prior to that date.
|
“MSC” |
1 |
Manchester Ship Canal Company Limited, the Claimant in the Present Claim and the 2010 Claim
|
“New Outfalls”
|
9 |
Outfalls commissioned by sewerage undertakers on or after 1 December 1991 discharging treated waste water and effluent into waterways
|
“New Sewers” |
9 |
Sewers constructed by sewerage undertakers on or after 1 December 1991
|
“Newly-Adopted Outfalls” |
9 |
Outfalls not constructed by sewerage undertakers themselves, but adopted by them under the relevant statutory provisions on or after 1 December 1991.These outfalls may have been constructed either before or after this date.
|
“Newly-Adopted Sewers” |
9 |
Sewers not constructed by sewerage undertakers themselves, but adopted by them under the relevant statutory provisions on or after 1 December 1991. These sewers may have been constructed either before or after this date.
|
“Old Outfalls” |
9 |
Outfalls which were either constructed or adopted by sewerage undertakers (or by their statutory predecessors) and in use for the discharge of treated waste water and effluent into waterways before 1 December 1991
|
“Old Sewers” |
9 |
Sewers which were either constructed or adopted by sewerage undertakers (or by their statutory predecessors) and in use before 1 December 1991
|
“the Origin Point” |
3 |
The argument forming the basis of the Present Claim, to the effect that the right of discharge held by the SC Decision to exist in respect of Old Outfalls such as Outfall 61 does not apply to waste material originating in a Newly-Adopted Sewer such as the Marshbrook Sewer, with the result that discharge of such material into the Canal via Outfall 61 is a trespass by UU
|
“Outfall 61” |
3 |
An Old Outfall in use since about 1957 for the discharge into the Canal of treated waste water and effluent from the Davyhulme Works
|
“the Present Claim” |
1 |
A Part 8 claim brought by MSC against UU in respect of an alleged trespass by reason of the discharge into the Canal via Outfall 61 of treated waste water and effluent originating in the Marshbrook Sewer
|
“RSP” |
149 |
Relevant sewerage provision within the meaning of section 219 of the 1991 Act
|
“RSPs” |
149 |
Relevant sewerage provisions within the meaning of section 219 of the 1991 Act
|
“Smith 1” |
6 |
The first witness statement of Mr Michael Smith, solicitor for UU
|
“Smith 2” |
6 |
The second witness statement of Mr Michael Smith, solicitor for UU
|
“UU” |
1 |
United Utilities Water Limited, the Defendant in the Present Claim and the 2010 Claim
|
“the s.186 Point” |
139 |
A proposed additional ground, by way of a test case, for the allegation by MSC that MSC’s consent is required by virtue of section 186 of the 1991 Act for the discharge into the Canal via Outfall 61 of treated waste water originating in the Marshbrook Sewer, and that such discharge without consent is a trespass by UU
|
“the 1936 Act” |
17 |
The Public Health Act 1936
|
“the 1989 Act” |
17 |
The Water Act 1989
|
“the 1991 Act” |
2 |
Water Industry Act 1991
|
“the 2010 Claim” |
6 |
A Part 7 claim brought by MSC against UU for trespass, claiming inter alia damages in lieu of an injunction in respect of the discharge of treated waste water and effluent into the Canal via a number of outfalls, including Outfall 61
|
Mr Justice Barling:
Introduction
3. The claim form, issued on 28 November 2017, seeks a declaration that the discharge by UU of water and other materials into the Canal through an outfall situated near the Davyhulme Works (“Outfall 61”) is a trespass against MSC to the extent that the water and other materials so discharged include water and materials which originate from a sewer constructed or adopted [1] by UU in or about 2007 to receive water from properties developed at or about that time at Marshbrook Drive, Manchester M9 2NN (“the Marshbrook Sewer”). I shall refer to the argument which is the basis of the Present Claim as “the Origin Point”.
Background
8. Sewers may be public or private. Public sewers are those which vested in a sewerage undertaker on privatisation in 1989. A sewer also becomes a public sewer when a sewerage undertaker constructs it, or adopts an existing but previously private sewer. Public sewers are the subject of certain statutory rights and obligations. Private sewers are the property of persons other than sewerage undertakers, and are not subject to the same statutory rights and obligations that affect public sewers.
“7. Davyhulme WwTW is the principal WwTW serving Greater Manchester with a catchment area of approximately 185.8 sq km and discharged a total of 111,390.3 Mega-litres (ie over 111 billion litres) into the Canal in 2017. Davyhulme WwTW itself comprises a wastewater treatment facility covering 73.6 hectares, ... Davyhulme WwTW is a very large, complex facility which treats incoming flows of sewage from an upstream network of public sewers serving an "Annual Average Resident Connected Population" as at June 2017 of 780,620 persons and a population equivalent (ie including trade waste) of 1.2 million persons with a flow rate up to 8,264 litres per second. The WwTW comprises infrastructure performing the following functions: grit removal, screening, storm water storage, primary settlement, secondary activated sludge plant and tertiary ammonia removal, and sludge digestion with thermal hydrolysis. Each of these processes has multiple separate process streams to provide security of service and to facilitate maintenance. All flows received at the Davyhulme WwTW inlet are discharged to the Canal at Outfall 61. The outfall is a reinforced concrete conduit equivalent to a 3,700mm diameter pipe with a cascade and spillway apron at the discharge point.
….
33… Davyhulme serves most of the City of Manchester and large parts of Oldham, Middleton, Stretford, Dale, Urmston and Bucklow as well as smaller parts of other areas. Davyhulme is the largest WwTW in UU's north-west region, the second largest WwTW in England after Beckton in East London, and among the largest WwTWs in Europe.”
“… the Marshbrook Drive area… constitutes one very small part of the total catchment area that is being drained to and treated at Davyhulme WwTW and the effluent from which is discharged into the Canal from Outfall 61. Mr Rathbone informs me that the area of the Marshbrook Road development comprises 0.12 square km. As a proportion of the Davyhulme WwTW catchment area as a whole of 185.5 square kilometres, Marshbrook Road therefore constitutes 0.065% of the total catchment area. … [T]he new sewer at Marshbrook Drive, … was first laid and used after 1 December 1991 and was adopted by UU on 5 October 2007.”
“I attach at page [3] a table and graphs charting the quantity of potential pollutants actually discharged from Outfall 61 in each of the years from 1989 to 2017. It can be seen from this that the overall quantum of potential pollutant actually being discharged into the Canal from Outfall 61 has fallen dramatically over the period since 1989 regardless of the new sewer connections.
Since 1989 there has been a steady increase in the impermeable developed area within the Davyhulme catchment from which surface water will drain to Davyhulme WwTW through combined sewers. For this reason the total volume of treated effluent discharged from Outfall 61 has increased since 1989. However, for the reasons just given the quantum of potential pollutants in that treated effluent is significantly less than in 1989.
New sewer connections are not the determining factor in the volume of treated effluent or potential pollutant entering the Canal from Outfall 61. Of far greater importance are long term changes in population, industry and the sewage treatment process.
…
Although the amount of surface water being discharged from Outfall 61 has increased since privatisation this is surface water all or most of which would have found its way naturally into the Canal in any event. Furthermore, up to 60% of the water in the Canal is comprised of effluent from UU's WwTWs. This point was made in MSCC's own evidence from John Rhodes OBE BSc RICS to the ongoing CPO Inquiry in relation to the nearby Eccles WwTW (John Rhodes Proof of Evidence, paragraph 3.65), an extract of which I attach at page [4] Davyhulme WwTW is by far the largest single contributor of water to the Canal. The Canal is dependent upon the receipt of treated effluent from UU's WwTWs which enables MSCC to maintain the water levels necessary for navigation, facilitates the operation of locks, especially in dry weather, and provides sufficient water to enable MSCC to grant abstraction licences.”
(See paragraphs 8 (5) to (7), and 10).
The suggestion that the treated water from the Davyhulme Works is needed for the Canal to fulfil its function is disputed by MSC. [2]
Relevant legislation
· Sections 158 and 159, give sewerage and water undertakers the powers to lay pipes "in streets" and "in other land".
· Section 94 provides:
“ General duty to provide sewerage system.
(1) It shall be the duty of every sewerage undertaker—
(a) to provide, improve and extend such a system of public sewers (whether inside its area or elsewhere) and so to cleanse and maintain those sewers as to ensure that that area is and continues to be effectually drained; and
(b) to make provision for the emptying of those sewers and such further provision (whether inside its area or elsewhere) as is necessary from time to time for effectually dealing, by means of sewage disposal works or otherwise, with the contents of those sewers.”
· Section 105A provides:
“ Schemes for the adoption of sewers, lateral drains and sewage disposal works
(1) The Secretary of State may by regulations provide for him to make schemes for the adoption by sewerage undertakers of sewers, lateral drains and sewage disposal works of the descriptions set out in paragraphs (a), (aa) and (b) of section 102(1) above.
(2) The regulations may require sewerage undertakers to prepare draft schemes and to submit them to the Secretary of State.
(3) Each scheme shall relate to—
(a) the area of a sewerage undertaker, or part or parts of it; or
(b) the areas of more than one sewerage undertaker, or part or parts of them.
(4) It shall be the duty of a sewerage undertaker, in specified circumstances, to exercise its powers under section 102 above with a view to making the declaration referred to in subsection (1) of that section in relation to sewers, lateral drains or sewage disposal works which—
(a) fall within the area to which a scheme relates; and
(b) satisfy specified criteria.”
· Section 106 provides:
“ Right to communicate with public sewers
(1) Subject to the provisions of this section—
(a) the owner or occupier of any premises in the area of a sewerage undertaker; or
(b) the owner of any private sewer draining premises in the area of any such undertaker,
shall be entitled to have his drains or sewer communicate with the public sewers of that undertaker and thereby to discharge foul water and surface water from those premises or that private sewer.”
· Section 116 provides:
“ Power to close or restrict use of public sewer
(1) Subject to subsection (3) below, a sewerage undertaker may discontinue and prohibit the use of any public sewer which is vested in the undertaker.
(2) A discontinuance or prohibition under this section may be for all purposes, for the purpose of foul water drainage or for the purpose of surface water drainage.
(3) Before any person who is lawfully using a sewer for any purpose is deprived under this section by a sewerage undertaker of the use of the sewer for that purpose, the undertaker shall—
(a) provide a sewer which is equally effective for his use for that purpose; and
(b) at the undertaker’s own expense, carry out any work necessary to make that person’s drains or sewers communicate with the sewer provided in pursuance of this subsection.”
· Section 117 provides:
“ Interpretation of Chapter II.
…
(5) Nothing in sections 102 to 109 above or in sections 111 to 116 above shall be construed as authorising a sewerage undertaker to construct or use any public or other sewer, or any drain or outfall—
(a)…
(b) for the purpose of conveying foul water into any natural or artificial stream, watercourse, canal, pond or lake, without the water having been so treated as not to affect prejudicially the purity and quality of the water in the stream, watercourse, canal, pond or lake.
(6) A sewerage undertaker shall so carry out its functions under sections 102 to 105, 112, 115 and 116 above as not to create a nuisance.”
· Section 219 provides:
“ General interpretation .
In this Act, except in so far as the context otherwise requires—
…
“the relevant sewerage provisions” means the following provisions of this Act, that is to say—
(a) Chapters II and III of Part IV (except sections 98 to 101 and 110 and so much of Chapter III of that Part as provides for regulations under section 138 or has effect by virtue of any such regulations);
(b) sections 160, 171, 172(4), 178, 184, 189, 196 and 204 and paragraph 4 of Schedule 12; and
(c) the other provisions of this Act so far as they have effect for the purposes of any provision falling within paragraph (a) or (b) of this definition”
19. Certain other provisions of the 1991 Act which are relevant to MSC’s application to amend the Present Claim are set out later in this judgment. [3]
20. I now turn to consider the 2010 Claim.
The 2010 claim
22. The basis of the trespass allegation, as pleaded in the Amended Particulars of Claim served in the 2010 Claim, [4] was as follows:
“8. Since the Canal was constructed and at all material times until 1 December 1991, the Defendant's respective predecessors in title and the Defendant have had statutory authorisation under the Public Health Acts 1875 and 1936 to discharge water into the Canal so long as the water discharged did not prejudicially affect the purity and quality of the water in the Canal.
9. Since 1 December 1991 the statutory scheme governing sewerage undertakers has been contained in the Water Industry Act 1991. In British Waterways Board v Severn Trent Water Ltd [2001] Ch 31, the Court of Appeal held that a sewerage undertaker, such as the Defendant, does not have statutory power to discharge water or other matter from its drainage pipes onto the land or into the waters of others. Accordingly, any discharge now made by a sewerage undertaker without the permission of a relevant land owner constitutes a trespass.”
23. MSC contended that in respect of relevant discharges UU did not have the benefit of any express or implied agreement, or statutory or common law right, entitling it to make such discharges into the Canal, and that each individual discharge from the outfalls in question (which included Outfall 61) was a trespass actionable by MSC. [5] At paragraph 40 there was an allegation that MSC was suffering loss and damage as a result of the trespass, and was entitled to an award of damages. In addition, at paragraph 43, the pleading asserted MSC’s entitlement to a final injunction in respect of all the unlawful discharges:
“to restrain [UU] from causing, permitting or suffering the discharges to be made or to continue…
[MSC] does not claim such an injunction but pursuant to s.50 of the Senior Courts Act 1981 claims damages in lieu of an injunction.”
In the prayer, the relief sought included a declaration that UU was not entitled to make any of the discharges identified in the pleading, other than with the consent of MSC, and damages for trespass, including damages “in lieu of an injunction under s.50 of the Senior Courts Act 1981 , to be assessed".
24. Mr Karas submitted, and Mr Morgan did not dispute that (1) whatever element of the discharges from Outfall 61 originated in Marshbrook Drive was within the scope of the general allegation of trespass, given that the Marshbrook Sewer had been adopted some three years before the 2010 Claim was commenced; and (2) the compensation for past and future trespasses sought by MSC in the 2010 Claim included damages in respect of the part of the discharge originating in Marshbrook Drive.
25. In its Amended Defence and Counterclaim, UU denied that any discharge then made by a sewerage undertaker without the permission of a relevant land owner constituted a trespass, and that the discharges identified in the Amended Particulars of Claim, including from Outfall 61, constituted a trespass. [6] A number of defences were relied upon. [7] Among these was the contention that notwithstanding the decision of the Court of Appeal in British Waterways Board v Severn Trent Water Ltd [2001] Ch 31, the statutory authorisation which admittedly existed under the legislation in force prior to the 1991 Act, continued under that enactment in respect of discharges from outfalls constructed prior to its coming into force on 1 December 1991. [8] UU’s Counterclaim sought a declaration reflecting that contention.
26. Thus, the 2010 Claim included an issue whether or not the discharge by UU after 1 December 1991 of treated waste water and material into the Canal from outfalls in use before that date, including Outfall 61, constituted an actionable trespass or, as UU contended, continued to be authorised by statute after that date. This issue went to the Supreme Court, [9] which accepted UU’s submission that the Court of Appeal in British Waterways Board (above) had reached no binding decision on whether a sewerage undertaker continued to have statutory authorisation to discharge water or other matter into the waters of a canal or watercourse where the said discharge was authorised before 1 December 1991.
Judgment and Order of the Supreme Court
30. Lord Sumption pointed out that the 1989 Act expressly incorporated all the provisions of the 1936 Act previously found in its Victorian predecessor, the Public Health Act 1875. These were the provisions on which the Court of Appeal in Durrant v Branksome Urban District Council [1897] 2 Ch 291 had relied in order to find that a right to discharge surface water and treated effluent into private watercourses was impliedly granted to local authorities by the Act of 1875. The provisions in question were: that which prevented undertakers from discontinuing the use of a sewer without providing an alternative sewer, that which afforded protection against the discharge of foul water into watercourses, that which granted to the owner or occupier of any premises the right to void his drains or sewers into a public sewer, and that which imposed the obligation to make full compensation for any damage sustained by the exercise of the undertaker's powers (see Schedule 8, paragraph 1 to the 1989 Act). For that reason, Lord Sumption concluded that the draftsman of the 1989 Act must have intended that that implied right should subsist (see paragraphs 6-8 of the SC Decision).
31. In the next section of his judgment, he pointed out that the same features “can be traced through the labyrinthine scheme of amendments, repeals and re-enactments into the legislation of 1991, but with significant changes of both form and context.” (See paragraphs 9-11 of his judgment.) Those changes in the legislation led him to dismiss UU’s argument that a general right of discharge through outfalls into private watercourses, regardless of whether those outfalls were in use at the time of the coming into force of the 1991 Act or were future outfalls, could be implied into the 1991 Act. He considered that the much more elaborate statutory scheme in the 1991 Act made the implication more difficult, and he was of the view that for this reason the Court of Appeal in British Waterways Board (above) had rejected the same argument. Lord Sumption cited the Court of Appeal’s conclusion, as summarised by Chadwick LJ at paragraph 71 of the judgment in that case:
“The fallacy, as it seems to me, lies in the underlying (but unspoken) premise that Parliament must have intended that sewerage undertakers should have facilities to discharge (which, plainly, they do require in order to carry out their functions) without paying for those facilities. Whether or not that premise could have been supported in the context of a public authority charged with functions imposed in the interests of public health, it cannot be supported, as it seems to me, in the context of legislation enacted following a decision to privatise the water industry."
Lord Sumption declined UU’s invitation to hold that the decision was wrongly decided. He considered that the Court of Appeal’s reasoning for rejecting the only argument before them, viz that a general power to discharge was derived from section 94(1) and 159 of the 1991 Act, was “compelling”. (See paragraphs 13-15 of the SC Decision.)
“After well over a century in which sewerage authorities were entitled as of right to construct and discharge from such outfalls one would expect the degree of dependence to be significant. Unless the entitlement to discharge from existing outfalls into private watercourses survives the transfer to privatised water undertakers, the consequence is that in law such discharge must cease forthwith on 1 December 1991. Any continuing discharge thereafter will become tortious from that date.
18. Under the Water Industry Act, the statutory duties of a sewerage undertaker include a duty to operate the system of public sewers so as effectually to drain their area (section 94) and a duty to allow the owners or occupiers of premises to connect to the public sewer system (section 106). Moreover, the undertaker is not permitted to discontinue the use of a sewer until it has provided an alternative sewer capable of serving as effectually (section 116). The result, if the right to discharge into private watercourses ceases as the canal owners suggest, is to make it impossible for the sewerage undertakers lawfully to perform their statutory functions or observe the statutory restrictions on the discontinuance of existing sewers from the moment that the new Act comes into force.”
“19. In my opinion, when the Water Industry Act 1991 (i) imposed on the privatised sewerage undertakers duties which it could perform only by continuing for a substantial period to discharge from existing outfalls into private watercourses, (ii) at the same time applied to them the statutory restrictions in section 116 on discontinuing the use of existing sewers, it implicitly authorised the continued use of existing sewers. A restriction on discontinuing the use of an existing sewer until an alternative has been constructed is not consistent with an obligation to discontinue its use forthwith under the law of tort. The inescapable inference is that although there is no provision of the Act of 1991 from which a general right of discharge into private watercourses can be implied, those rights of discharge which had already accrued in relation to existing outfalls under previous statutory regimes survived.
20. The basis of this implication is not section 30 of the Public Health Act 1936, whose statutory predecessor was the basis of the decision in the Durrant case, but section 116 of the 1991 Act viewed against the background of the general duties of sewerage undertakers under the Act. It follows that the repeal of section 30 by the Water Consolidation (Consequential Provisions) Act 1991 is irrelevant. In any event, its repeal would not affect rights of discharge which had already accrued by virtue of the use of existing outfalls: see section 16(1)(c) of the Interpretation Act 1978.
(See paragraphs 17-21 of the SC Decision)
“ I would accordingly allow the appeal to the extent of declaring that subject to section 117(5) of the Water Industry Act 1991, the Appellants are entitled to discharge into the Respondents' canals from any sewer outfall which was in use on or before 1 December 1991.”
“sewerage undertakers are impliedly empowered to continue to discharge surface water and other non-pollutant water through sewers vested in them into watercourses to which they were already discharging at the time the Act came into force, but have no right to create new outfalls into canals or rivers without the agreement of the body which owns or is responsible for the canal or river.”
(See paragraphs 24-5 of the SC Decision.)
“… sewerage undertakers have the statutory right to discharge surface water and treated effluent into streams and canals (subject to payment of compensation for any damage thereby caused), but only in respect of outfalls in existence before the coming into force of the 1991 Act. I agree with the reasons given by Lord Sumption and Lord Toulson although I would place greater weight on the assistance which can be gained from the provisions of the earlier legislation relating to public sewers and the Interpretation Act 1978 ("the 1978 Act").”
“…there are two alternative reasons for concluding that the new water undertakers had the right to discharge from existing outfalls under the 1989 Act, and one reason for concluding that that right continued under the 1991 Act.”
(Paragraph 60 of the SC Decision)
38. As to the two possible routes to an implied right under the 1989 Act, Lord Neuberger said:
“Accordingly, it seems to me to follow that the sewerage undertakers had an implied right (subject to payment of compensation in case of damage) to discharge from existing outfalls from the sewers vested in them in 1989, because (i) the provisions of the 1989 Act conferred such a right on them by implication in accordance with the reasoning in Durrant or, if that is wrong, (ii) the implied right to discharge from those outfalls enjoyed just before the 1989 Act came into force was transferred by the water authorities to them. The effect of conclusion (i) is, as I see it, that the right to discharge applied to outfalls created after 1989, including those from sewers brought into use after the 1989 Act came into force, as section 30 (as amended to apply to the sewerage undertakers) continued in force, and, following the reasoning in Durrant , so did the right to discharge.”
(Paragraph 70 of the SC Decision)
40. For those reasons Lord Neuberger concluded:
“that sewerage undertakers had, and therefore continue to have, a statutory right to discharge surface water and treated effluent from existing outfalls from sewers which had been vested in them by the time that the 1991 Act came into force, but not from subsequently created outfalls or outfalls from sewers which they may have laid after that date.”
(Paragraph 75)
Judgment and Order of Newey J on the matter being remitted
“16C.3 the statutory right impliedly conferred by the [1991 Act] to continue to discharge from Pre-1991 Outfalls does not authorise discharges of water and other materials through outfalls where the water and materials originate from sewers laid or adopted by [UU] on or after 1 December 1991, or from new connections made to existing sewers after 1 December 1991”
“ MSCC could be expected to have put forward by that stage all the points that it wished to advance as entitling it to be allowed to continue the proceedings in respect of the 106 outfalls, the more so since Floyd J had directed MSCC to serve its evidence in answer to the application to [ sic ] for summary judgment by 18 November 2011. Further, as I recorded in my judgment, counsel then appearing for MSCC accepted at the hearing before me that the parties had had an adequate opportunity to address the issues and did not suggest that I lacked any relevant evidence.
The claims that would be introduced by the proposed amendments could all have been put forward in time for the hearing before me in 2012. The Class 2 amendments have, I gather, been prompted by paragraph 75 of Lord Neuberger's judgment in the Supreme Court, but the passage in question did no more than suggest to MSCC a legal argument that had always been available to it… In short, the amendments were not dependent on the Supreme Court's decision;
…The fact that additional arguments may have occurred to new counsel does not normally represent a compelling reason for granting permission to amend…
The amendments would put United Utilities to a very great deal of work. A witness statement explains that, if the amendments were permitted, United Utilities:
"would be required to undertake very substantial investigations into facts which it has not had to investigate as a result of any of the allegations raised in these proceedings to date, including without limitation as to the date of construction of sewers and properties which ultimately connect to sewers discharging through the outfalls in issue, as to the frequency and extent with which individual discharges can be said to have exceeded the statutory limits on [United Utilities'] authority to discharge, and as to its tankering operations…”
It is, moreover, reasonable to assume, I think, that Mr Karas is correct that past work would be wasted (because some would inevitably need to be done again in going over historic documents)…
The fact that, if denied permission to amend, MSCC may seek to litigate some or all of the points raised by the proposed amendments in fresh proceedings does not seem to me to provide an adequate justification for allowing it to introduce them into proceedings issued nearly six years ago, especially since the points have not been the subject of pre-action correspondence.”
“The Class 2 amendments are, as I have mentioned, prompted by paragraph 75 of Lord Neuberger's judgment in the Supreme Court. He referred to sewerage undertakers having the right to discharge from "existing outfalls from sewers which had been vested in them by the time the 1991 Act came into force, but not from subsequently created outfalls or outfalls from sewers which they may have laid after that date ". MSCC contends that the words I have underlined indicate a limitation on United Utilities' entitlement to discharge through Pre-1991 Outfalls. It maintains, moreover, that such a restriction is consistent with the scheme of the WIA and the basis on which the Supreme Court held sewerage undertakers to have implied rights of discharge.
Mr Karas suggested that I should decline to allow the Class 2 amendments on the basis that MSCC's argument is wrong in law. It would, he argued, be legally incoherent to suppose that discharges of material originating from connections to United Utilities' sewers after 1 December 1991 are unlawful. In this connection, he stressed section 106 of the WIA, which (he said) confers an "absolute right" to connect premises to a public sewer (as to which, see Barratt Homes Ltd v Dwr Cymru Cyf (Welsh Water) [2009] UKSC 13, [2010] 1 All ER 965).
In my view, however, it would not be appropriate for me to attempt to determine whether United Utilities' rights of discharge are (or are not) restricted in the way suggested by MSCC. For understandable reasons, argument on the point was quite limited before me. I am not confident that the issue was addressed fully. I do not, in the circumstances, feel that I should "grasp the nettle" and decide it.
However, other objections that Mr Karas put forward to the Class 2 amendments strike me as more compelling. It is fair to say (as Mr Karas did) that the amendments are wholly unparticularised: MSCC baldly asserts in respect of the 90 relevant outfalls that the discharge from each of them "is now in whole or in part from new sewers laid or adopted by [United Utilities] on or after 1 December 1991". Further, Mr Karas must surely be right that, unless at least MSCC's claim were dismissed as legally unsustainable at a very early stage, the Class 1 [ sic ] amendments would put United Utilities to a great deal of work. As to this, a witness statement filed on behalf of United Utilities says:
"Even if proper particulars are provided, I understand from [United Utilities] that, at present, there is no obviously satisfactory way of establishing which sewers connecting into sewers discharging into the Canal were constructed after that date. If this amendment were to be permitted, it is at this stage unclear to [United Utilities] precisely what factual investigations would be best undertaken. However, whatever method was chosen, given the sheer amount of infrastructure in issue, it is clear that a very significant amount of investigation would be necessary, and [United Utilities] would request an initial period of 6 months to respond following the provision of proper particulars, although anticipates that a request for a further extension is likely to be necessary."
Taking such matters in conjunction with the lateness of the application to amend (on which I have commented above), it seems to me that I should not grant MSCC permission to make the Class 2 amendments. The claim that MSCC wishes to put forward should, in my view, be pursued, if at all, in new proceedings.”
UU’s strike out/summary judgment application
Preliminary observations
50. In its application to strike out the Present Claim, UU relies upon the following main grounds:
(1) Cause of action estoppel.
(2) Issue estoppel.
(3) Henderson v Henderson abuse.
(4) The effect of the SC Decision, either as binding this court and/or as indicating that the present Claim has no real prospect of success and is bound to fail.
51. These grounds are not watertight and overlap to a certain extent.
(1) The effect of the SC Decision
The parties’ submissions
54. Nor, he submitted, was Lord Neuberger saying in paragraph 75 of his judgment [10] that discharges via Old Outfalls from sewers to which New or Newly-Adopted Sewers were connected were unlawful, as MSC suggested. That would be inconsistent with the reasoning of the Supreme Court, and in particular the acceptance by all its members that it was “incoherent” to suggest that sewerage undertakers could not lawfully continue to discharge effluent from Old Outfalls which they were unable lawfully to stop up by reason of section 116 of the 1991 Act. The fact that effluent originated in a New or Newly-Adopted Sewer did not prevent the application of the section.
56. Mr Morgan, in response, submitted that although the Supreme Court found an implied right of discharge to exist, which derived from inter alia the terms of section 116 and the obligation to make continuous provision of sewers to those lawfully using them, the Court had not determined the scope or limits of the implied right. Mr Morgan emphasised the following italicised [11] words in paragraph 19 of Lord Sumption’s judgment:
“The inescapable inference is that although there is no provision of the 1991 Act from which a general right of discharge into private watercourses can be implied, those rights of discharge which had already accrued in relation to existing outfalls under previous statutory regimes survived .”
61. In addition, Mr Morgan drew attention to Barratt Homes Ltd v Dwr Cymru Cyfyngedig (Welsh Water) (No 2) [2009] UKSC 13; [2013] 1 WLR 3486 as authority for the proposition that a sewerage undertaker was not liable in private law in respect of its unlawful refusal to accept a connection under section 106. Thus, if, after 1 December 1991, an undertaker were to delay making a connection under that section while procuring the necessary consents, there would be no question of tortious liability.
62. By his proposed amendment, Mr Morgan also seeks to raise a case, based on section 186 of the 1991 Act, which was not relied upon by MSC in the Supreme Court (although the section was discussed in the course of the hearing in that Court). Mr Morgan acknowledges that, if correct, this argument would cut through all these points, and render unlawful any discharge from Outfall 61, or from any other outfall, without the consent of MSC. He indicated that in the Present Claim this point would only be relied upon in respect of the discharge originating in the Marshbrook Sewer, as a test case. As stated earlier, I propose to examine that application for amendment separately. [12]
Discussion and conclusion
63. It is clear that in the 2010 Claim, and in the appeal to the Supreme Court, no point was taken by either side based on the origin of waste material discharged via an outfall.
64. Leaving aside paragraph 75 of the judgment of Lord Neuberger, it would be difficult to argue that the SC Decision did not decide that, provided the relevant outfall was already in use on 1 December 1991, the sewerage undertaker was entitled (subject to various protective provisions) to continue to discharge from it, regardless of the source of the waste water and material. The Supreme Court was very much alive to the fact that sewerage undertakers were required to accept new connections to private sewers by virtue of section 106 , and that by virtue of section 116 flows from any sewer, including from such new connections, could not be stopped without alternative arrangements being put in place. [13] Indeed, both those sections were expressly relied upon as part of the legislative context which persuaded the Court to find that there was an implied statutory right to continue to discharge through Old Outfalls. In each of the three judgments the right was expressed in terms which focussed solely on the outfall, and which were unqualified as to the source of waste water (see per Lord Sumption, at paragraphs 21 and 23, per Lord Toulson at paragraph 24, and per Lord Neuberger at paragraph 39). Had the Court intended the implied statutory right not to apply in respect of material originating from connections or adoptions occurring after 1 December 1991, the Court could not have adopted the reasoning it did, as the same “legal incoherence” would have arisen. Moreover, one would have expected such an important distinction to have been emphasised.
66. First, that limitation on the duty is at odds with the unqualified terms of section 106 itself. Further, the right to connect has been described as an "absolute right", and the sewerage undertaker “cannot refuse to permit the connection on the ground that the additional discharge into the system will overload it. The burden of dealing with the consequences of this additional discharge falls directly upon the undertaker and the consequent expense is shared by all who pay sewerage charges to the undertaker.” (See per Lord Phillips in Barratt Homes Ltd v Welsh Water [2009] UKSC 13, at paragraph 23.) In Marcic v Thames Water Utilities Ltd [2004] 2 AC, Lord Nicholls, at paragraph 34, pointed out that "every new house built has an absolute right to connect". In the same case Lord Hoffmann, at paragraph 53, stated that the sewerage undertaker has a duty "to accept whatever water and sewage the owners of property in their area choose to discharge." This absolute duty necessarily operates in respect of connections after the 1991 Act came into force.
69. There is certainly a difference in wording between Lord Neuberger’s unqualified “composite answer” in paragraph 39 [14] to the questions raised in the appeal, and paragraph 75 [15] of his judgment. It is not possible to be sure what was meant in the latter by “or outfalls from sewers which they may have laid after that date.” I agree with Mr Morgan that the syntax and the remainder of the sentence would support “outfalls” meaning “any outfalls, whether new or existing”. However, it would be difficult to reconcile that interpretation with the terms of paragraph 39 of the judgment or with his express agreement with the reasons of Lord Sumption and Lord Toulson. Mr Karas suggested that, since paragraph 75 refers only to “sewers which [sewerage undertakers] may have laid after that date”, it did not in any event affect new connections under section 106 or new adoptions of private sewers.
71. It follows that in the light of the SC Decision [16] there is no requirement for MSC’s consent to discharge via Outfall 61 treated water and material, including that originating in the Marshbrook Sewer, and that such discharge does not ipso facto amount to a trespass. Even if the SC Decision is not strictly binding, the reasoning, to which all the members of the Court subscribed, would strongly support a finding to that effect, so that there would be no real prospect of success in the Present Claim, as currently formulated.
Cause of action estoppel: the case law
74. The leading case on cause of action and issue estoppel is Virgin Atlantic Airways Ltd v Zodiac Seats UK Ltd [2013] UKSC 46 [2014] AC 160, in which, once again, judgments were delivered by Lord Sumption and Lord Neuberger, with both of whom the other members of the Supreme Court agreed. In the course of his judgment, at paragraph 17, Lord Sumption said:
“The first principle is that once a cause of action has been held to exist or not to exist, that outcome may not be challenged by either party in subsequent proceedings. This is "cause of action estoppel". It is properly described as a form of estoppel precluding a party from challenging the same cause of action in subsequent proceedings.
…
Fourth, there is the principle that even where the cause of action is not the same in the later action as it was in the earlier one, some issue which is necessarily common to both was decided on the earlier occasion and is binding on the parties: Duchess of Kingston's Case (1776) 20 St Tr 355. "Issue estoppel" was the expression devised to describe this principle by Higgins J in Hoysted v Federal Commissioner of Taxation (1921) 29 CLR 537, 561 and adopted by Diplock LJ in Thoday v Thoday [1964] P 181, 197-198.”
“Cause of action estoppel arises where the cause of action in the later proceedings is identical to that in the earlier proceedings, the latter having been between the same parties or their privies and having involved the same subject matter. In such a case the bar is absolute in relation to all points decided unless fraud or collusion is alleged, such as to justify setting aside the earlier judgment. The discovery of new factual matter which could not have been found out by reasonable diligence for use in the earlier proceedings does not, according to the law of England, permit the latter to be re-opened.
Issue estoppel may arise where a particular issue forming a necessary ingredient in a cause of action has been litigated and decided and in subsequent proceedings between the same parties involving a different cause of action to which the same issue is relevant one of the parties seeks to re-open that issue."
76. Lord Sumption continued, at paragraphs 20 and 22:
“The case before the committee was treated as one of issue estoppel, because the cause of action was concerned with a different rent review from the one considered by Walton J. But it is important to appreciate that the critical distinction in Arnold was not between issue estoppel and cause of action estoppel, but between a case where the relevant point had been considered and decided in the earlier occasion and a case where it had not been considered and decided but arguably should have been…
“ Arnold is accordingly authority for the following propositions: (1) Cause of action estoppel is absolute in relation to all points which had to be and were decided in order to establish the existence or non-existence of a cause of action. (2) Cause of action estoppel also bars the raising in subsequent proceedings of points essential to the existence or non-existence of a cause of action which were not decided because they were not raised in the earlier proceedings, if they could with reasonable diligence and should in all the circumstances have been raised. (3) Except in special circumstances where this would cause injustice, issue estoppel bars the raising in subsequent proceedings of points which (i) were not raised in the earlier proceedings or (ii) were raised but unsuccessfully. If the relevant point was not raised, the bar will usually be absolute if it could with reasonable diligence and should in all the circumstances have been raised.”
77. Finally, it is appropriate to cite his observations at paragraphs 25 -26:
“25…Res judicata and abuse of process are juridically very different. Res judicata is a rule of substantive law, while abuse of process is a concept which informs the exercise of the court's procedural powers. In my view, they are distinct although overlapping legal principles with the common underlying purpose of limiting abusive and duplicative litigation. That purpose makes it necessary to qualify the absolute character of both cause of action estoppel and issue estoppel where the conduct is not abusive. As Lord Keith put it in Arnold v National Westminster Bank at p 110G, "estoppel per rem judicatam, whether cause of action estoppel, or issue estoppel is essentially concerned with preventing abuse of process."
26. It may be said that if this is the principle it should apply equally to the one area hitherto regarded as absolute, namely cases of cause of action estoppel where it is sought to reargue a point which was raised and rejected on the earlier occasion. But this point was addressed in Arnold , and to my mind the distinction made by Lord Keith remains a compelling one. Where the existence or non-existence of a cause of action has been decided in earlier proceedings, to allow a direct challenge to the outcome, even in changed circumstances and with material not available before, offends the core policy against the re-litigation of identical claims.”
Cause of action estoppel: discussion and conclusions
78. In relation to the nature of a cause of action, I was referred [17] to a number of cases. In Hoechst United Kingdom Limited and another v IRC and another [2003] EWHC 1002 (Ch), Park J said, at paragraph 24:
“Two critical concepts which feature in the foregoing formulations of the legal position are those of a cause of action and of the limitation period. A cause of action in this context is not so much the label attaching to a claimant's claim (for example "breach of statutory duty" or "money paid under a mistake of law"). Rather, it is the set of facts which entitles the claimant to relief:-
"Every fact which is material to be proved to entitle the plaintiff to succeed - every fact which the defendant would have a right to traverse".
(Brett, J. in Cooke v Gill (1873) 8 CP 107 at 116). See also Diplock, LJ in Letang v Cooper [1965] 1 QB 232 at 242-3:
"A cause of action is simply a factual situation, the existence of which entitles one person to obtain from the court a remedy against another person".”
79. My attention was also drawn to the statement by Millett LJ (as he then was) in Paragon Finance Plc v DB Thakerar & Co [1999] 1 All ER 400, at page 405:
“The classic definition of a cause of action was given by Brett J in Cooke v Gill (1873) LR 8 CP 107 at p. 116:-
“Cause of action” has been held from the earliest times to mean every fact which is material to be proved to entitle the plaintiff to succeed - every fact which the defendant would have a right to traverse” (my emphasis).
In the Thakerar case Chadwick J cited the more recent definition offered by Diplock LJ in Letang v Cooper [1965] 1 QB 232 CA at pp. 242-3 and approved in Steamship Mutual Underwriting Association v Trollop & Colls [1986] 33 BLR 77 at p. 92:-
“A cause of action is simply a factual situation the existence of which entitles one person to obtain from the court a remedy against another person”
I do not think that Diplock LJ was intending a different definition from that of Brett J. However it is formulated, only those facts which are material to be proved are to be taken into account. The pleading of unnecessary allegations or the addition of further instances or better particulars do not amount to a distinct cause of action. The selection of the material facts to define the cause of action must be made at the highest level of abstraction.”
80. In Diamandis v Wills and another [2015] EWHC 312 (Ch), a decision of Mr Stephen Morris QC sitting as a Deputy High Court Judge, there is a helpful compilation of the principles derived from those and other cases dealing with the nature of a “cause of action”, in the context of section 35 of the Limitation Act 1980. At paragraph 48, the Deputy Judge said:
“As regards Stage 2 (new cause of action) from the recent analysis of the authorities by Longmore LJ in Berezovsky v Abramovich §§59 to 69, the following principles arise:
(1) The "cause of action" is that combination of facts which gives rise to a legal right; (it is the "factual situation" rather than a form of action used as a convenient description of a particular category of factual situation: Lloyds Bank v Rogers at 85F and Aldi Stores at 21).
(2) Where a claim is based on a breach of duty, whether arising in contract or tort, the question whether an amendment pleads a new cause of action requires comparison of the unamended and amended pleading to determine (a) whether a different duty is pleaded (b) whether the breaches pleaded differ substantially and (c) where appropriate the nature and extent of the damage of which complaint is made: Darlington at 370C-D and see also Berezovsky §59. (Where it is the same duty and same breach, new or different loss will not be new cause of action. But where it is a different duty or a different breach, then it is likely to be a new cause of action).
(3) The cause of action is every fact which is material to be proved to entitle the claimant to succeed. Only those facts which are material to be proved are to be taken into account; the pleading of unnecessary allegations or the addition of further instances does not amount to a distinct cause of action. At this stage, the selection of the material facts to define the cause of action must be made at the highest level of abstraction. Berezovsky §60 citing Cooke v Gill (1873) LR 8 CP 107 and Paragon Finance , supra.
(4) In identifying a new cause of action the bare minimum of essential facts abstracted from the original pleading is to be compared with the minimum as it would be constituted under the amended pleading: Berezovsky §§61 and 62.
(5) The addition or substitution of a new loss is by no means necessarily the addition of a new cause of action: Berezovsky §64 and Aldi §26. Nor is the addition of a new remedy, particularly where the amendment does not add to the "factual situation" already pleaded: Lloyds Bank v Rogers per Auld LJ at 85K.”
81. I have already described [18] in some detail the nature of the 2010 Claim. The cause of action in both that claim and the Present Claim is trespass. It is common ground that the trespass alleged in the 2010 Claim included the whole of the discharge via Outfall 61. Mr Morgan does not dispute that the waste water and material originating in the Marshbrook Sewer was within the scope of the 2010 Claim. Nor is there any issue that the compensation for trespass claimed by MSC in that action included past and future damages in respect of the Marshbrook Sewer element of the discharge via Outfall 61. For the remedy sought in respect of future trespasses was not an injunction, but damages in lieu of an injunction. That remedy enables compensation to be awarded in respect of loss and damage that will be suffered in the future in the absence of an injunction (see, for example, Jaggard v Sawyer [1995] 1 WLR 269, at pp. 276 - 277 and 286, per Sir Thomas Bingham MR and Millett LJ). It is, therefore, not disputed by MSC that had the 2010 Claim succeeded and had the claimed damages in lieu of an injunction been awarded, such compensation would have included an element for past and future trespasses resulting from the Marshbrook Sewer element being discharged via Outfall 61. As we have seen, the 2010 Claim failed in that respect, the claim for trespass being ultimately dismissed by Newey J. [19]
“The court can properly award damages once and for all in respect of future infringements because it awards them in substitution for an injunction and to compensate for those future wrongs which an injunction would have prevented. Since the practical consequence of withholding injunctive relief is to authorise the continuance of an unlawful state of affairs, the doctrine of res judicata operates to prevent the claimant and their successors in title from bringing proceedings thereafter to recover even nominal damages in respect of further wrongs for which the claimant has been fully compensated.”
84. In so far as MSC wishes to raise a new point relating to the origin of effluent, in order to argue that some of the discharge from Outfall 61 constituted and continues to constitute a trespass, UU submits that MSC falls foul of the principle in Arnold , as interpreted by Lord Sumption in Virgin Atlantic , viz. that cause of action estoppel bars the raising in subsequent proceedings of points essential to the existence or non-existence of a cause of action which were not decided because they were not raised in the earlier proceedings, if they could with reasonable diligence and should in all the circumstances have been raised. In that regard Mr Karas relied upon the findings of Newey J [20] that MSC “could be expected to have put forward by [the time of the hearing in January 2012] all the points that it wished to advance”, and that the proposed amendments were “prompted by paragraph 75 of Lord Neuberger's judgment” but “the passage in question did no more than suggest to [MSC] a legal argument that had always been available to it…. [T]he amendments were not dependent on the Supreme Court's decision”. Newey J went on to hold that the fact that further arguments had occurred to new counsel was not “a compelling reason” to grant permission to amend.
86. Mr Morgan submits, first, that cause of action estoppel is not an absolute principle. He relied upon an obiter dictum of Arden LJ (as she then was) in Lemas v Williams [2013] EWCA Civ 1433. Having referred to the speech of Lord Keith in Arnold (see above), Arden LJ said:
“Where, as here, a cause of action or issue was not raised in the previous proceedings but could have been so raised, the court has a discretion not to apply cause of action estoppel or issue estoppel if there are "special circumstances". The judge relied on this exception in relation to Mr Sealy. There is, of course, no exhaustive definition of what constitute special circumstances but they must by definition be circumstances which make it unjust to insist on the estoppel applying. This may occur where a party obtains relevant new material which was not previously available, as in Arnold itself. Sometimes the same result is achieved by granting permission to appeal out of time from the first decision.”
90. In its written submissions [21] MSC relied on the first proposition to argue that there can be no cause of action estoppel here because the trespass in respect of which a declaration is sought in the Present Claim is a separate trespass, and therefore a separate cause of action, from the trespass alleged in the 2010 Claim which was limited to those trespasses which had occurred at the time of the determination of that claim. However, this point is not in my view a good one. The 2010 Claim was clearly also prospective, in that it included a claim in damages in lieu of an injunction for future trespasses in respect of the discharge from, inter alia , Outfall 61. I did not understand Mr Morgan to be contesting that when he made his oral submissions.
“Secondly, there is the principle, which is not easily described as a species of estoppel, that where the claimant succeeded in the first action and does not challenge the outcome, he may not bring a second action on the same cause of action, for example to recover further damages: see Conquer v Boot [1928] 2 KB 336.”
97. Be that as it may, in my view a more compelling factor relates to the facts which define the cause of action in question, namely trespass to land. One bears in mind that these facts are to be taken “at the highest level of abstraction.” [22] Applying this to the tort of trespass to land, a claimant needs to show, first, that he is in possession, or is entitled to possession, of the land in question, and second, that the defendant has interfered with that possession or right to possession by a direct and immediate physical interference. (See, for example, Southport Corporation v Esso Petroleum C o. [1954] 2 QB 182.) Once wrongful interference with the claimant’s land is alleged, it is for the defendant to establish by way of defence, if he can, that the interference was lawfully authorised and therefore not wrongful. It does not fall to the claimant to establish an absence of authority i.e. to prove a negative. The existence of lawful authority for what would otherwise be wrongful interference is a matter for the defendant.
99. The pleadings in the 2010 Claim reflect these features of the cause of action. Thus, the claim form claims declarations and damages for “various trespasses being discharges of water and sewage made unlawfully and without permission by the defendant onto and into land and water owned by or vested in the claimant…” The particulars of claim allege that each of the discharges in question, including that from Outfall 61, is made without authority or consent and is an actionable trespass. [23] As seen, the 2010 Claim necessarily included the Marshbrook Sewer discharges within the allegation of trespass. In its defence and counterclaim UU set up various defences, including the existence of statutory authority to make the discharges.
102. I am also of the view that, for the reasons given below [24] in relation to the Henderson v Henderson issue, the Origin Point could with reasonable diligence and should in all the circumstances have been raised in that claim. It was not dependent on the SC Decision, as submitted by MSC. There being, as I have said, no wider discretion in respect of cause of action estoppel, there exists an absolute bar to the Present Claim, as that claim is currently formulated.
(3) Issue estoppel
104. Issue estoppel is described by Lord Sumption in the extracts from his judgment in Virgin Atlantic cited above. [25] It arises where the cause of action is not the same in the later action as in the earlier one, but an issue necessarily common to both actions was decided on the earlier occasion. The decision on that issue is binding on the parties, except in special circumstances where injustice would be caused. Issue estoppel also operates as a bar to points which were not raised if they could with reasonable diligence and should have been raised (see Virgin Atlantic , at paragraphs 17-22).
106. Thus, issue estoppel was put as an alternative to UU’s cause of action estoppel argument. Moreover, Mr Morgan in his submissions [26] put his case on issue estoppel very much in conjunction with his arguments on UU’s Henderson v Henderson challenge, even though they are conceptually separate grounds. In the circumstances, including my findings in relation to cause of action estoppel, I do not consider it necessary to deal separately with issue estoppel.
(4) Henderson v Henderson abuse of process
107. UU argues that the Present Claim is abusive within the principle formulated in Henderson v Henderson 3 Hare 100 and that, consistently with Newey J's conclusions, [27] the proper place for the Origin Point to be taken was in the 2010 Claim.
“In trying this question I believe I state the rule of the Court correctly when I say that, where a given matter becomes the subject of litigation in, and of adjudication by, a Court of competent jurisdiction, the Court requires the parties to that litigation to bring forward their whole case, and will not (except under special circumstances) permit the same parties to open the same subject of litigation in respect of matter which might have been brought forward as part of the subject in contest, but which was not brought forward, only because they have, from negligence, inadvertence, or even accident, omitted part of their case. The plea of res judicata applies, except in special cases, not only to points upon which the Court was actually required by the parties to form an opinion and pronounce a judgment, but to every point which properly belonged to the subject of litigation, and which the parties, exercising reasonable diligence, might have brought forward at the time... Now, undoubtedly the whole of the case made by this bill might have been adjudicated upon in the suit in Newfoundland, for it was of the very substance of the case there, and prima facie, therefore, the whole is settled. The question then is whether the special circumstances appearing upon the face of this bill are sufficient to take the case out of the operation of the general rule."
109. It is acknowledged by both parties that the principle was authoritatively re-stated by Lord Bingham of Cornhill (with whom, either in terms or in substance, the other members of the House of Lords agreed) in Johnson v Gore Wood & Co [2002] 2 AC 1, at page 31:
“ Henderson v Henderson abuse of process, as now understood, although separate and distinct from cause of action estoppel and issue estoppel, has much in common with them. The underlying public interest is the same: that there should be finality in litigation and that a party should not be twice vexed in the same matter. This public interest is reinforced by the current emphasis on efficiency and economy in the conduct of litigation, in the interests of the parties and the public as a whole. The bringing of a claim or the raising of a defence in later proceedings may, without more, amount to abuse if the court is satisfied (the onus being on the party alleging abuse) that the claim or defence should have been raised in the earlier proceedings if it was to be raised at all. I would not accept that it is necessary, before abuse may be found, to identify any additional element such as a collateral attack on a previous decision or some dishonesty, but where those elements are present the later proceedings will be much more obviously abusive, and there will rarely be a finding of abuse unless the later proceeding involves what the court regards as unjust harassment of a party. It is, however, wrong to hold that because a matter could have been raised in earlier proceedings it should have been, so as to render the raising of it in later proceedings necessarily abusive. That is to adopt too dogmatic an approach to what should in my opinion be a broad, merits-based judgment which takes account of the public and private interests involved and also takes account of all the facts of the case, focusing attention on the crucial question whether, in all the circumstances, a party is misusing or abusing the process of the court by seeking to raise before it the issue which could have been raised before. As one cannot comprehensively list all possible forms of abuse, so one cannot formulate any hard and fast rule to determine whether, on given facts, abuse is to be found or not.”
110. Lord Millet, at page 59, said:
"In Brisbane City Council v Attorney General for Queensland [1979] AC 411, 425 Lord Wilberforce, giving the advice of the Judicial Committee of the Privy Council, explained that the true basis of the rule in Henderson v Henderson 3 Hare 100 is abuse of process and observed that it "ought only to be applied when the facts are such as to amount to an abuse: otherwise there is a danger of a party being shut out from bringing forward a genuine subject of litigation" There is, therefore, only one question to be considered in the present case: whether it was oppressive or otherwise an abuse of the process of the court for Mr Johnson to bring his own proceedings against the firm when he could have brought them as part of or at the same time as the company's action. This question must be determined as at the time when Mr Johnson brought the present proceedings and in the light of everything that had then happened. There is, of course, no doubt that Mr Johnson could have brought his action as part of or at the same time as the company's action. But it does not at all follow that he should have done so or that his failure to do so renders the present action oppressive to the firm or an abuse of the process of the court.".
115. UU also disputes that the Origin Point was dependent on anything said in the SC Decision. In that regard reliance is placed on Newey J's express finding to the contrary in his February 2016 judgment, at paragraph 35. [28] Further, UU argues that if, as Newey J held, the fact that a legal point has only occurred to lawyers late in a case is not normally a compelling reason to grant permission to amend in order to plead that point in existing proceedings, then, a fortiori it cannot be a good reason for allowing MSC to raise that point by way of wholly new proceedings.
116. In response, MSC began by pointing to Lord Bingham’s statement in Johnson v Gore Wood & Co (above), that because a matter could have been raised in earlier proceedings, it does not mean it should have been raised, so as to render the raising of it in later proceedings necessarily abusive, and that a broad, merits-based approach should be applied to the issue of abuse, taking account of the public and private interests involved and of all the facts of the case. MSC also referred to Davies v Carillion Energy Services Ltd [2018] 1 WLR 1734, per Morris J at paragraph 53, as indicating that the broad, merits-based approach is not a matter of discretion but a judgment to be made by assessing and balancing all the relevant factors in the case. Further, even if there were a finding of abuse of process, MSC submitted that the court had a residual discretion not to strike out the claim, albeit that would only apply in unusual circumstances: Stuart v Goldberg Linde [2008] 1 WLR 823, at page 832.
117. MSC pointed out that, as with the other res judicata grounds, the burden is on UU to establish that it is oppressive or an abuse of process to be subjected to the present Claim (per Lord Bingham in Johnson v Gore Wood & Co ). [29]
118. I understand those statements of principle to be common ground.
121. Attractively though this submission was presented, I do not feel able to accept it, any more than Newey J did. In its Defence and Counterclaim in the 2010 Claim, UU was already contending [30] that in the British Waterways Board case the Court of Appeal had reached no binding decision about whether a sewerage undertaker continued to be entitled to discharge where such discharge was authorised by statute immediately prior to the 1991 Act coming into force, and that its decision only related to authorisation to discharge from outfalls created after that date. As Mr Karas pointed out, UU’s case took that form until the matter reached the Supreme Court. There, for the first time, UU was also able to argue (albeit unsuccessfully) that the Court of Appeal had been wrong in respect of New Outfalls. The Court rejected UU’s contention that the Court of Appeal had been in error about post-1 December 1991 outfalls. However, the Court agreed with UU’s submission as to the scope of the Court of Appeal judgment.
134. Weighing these considerations, along with the other points urged upon me by both parties, and all the surrounding circumstances, I have come to the conclusion that the Origin Point not only could but should have been raised in the 2010 Claim, and that the Present Claim is oppressive to UU and an abuse of process, as explained by Lord Bingham in Johnson . I have considered carefully whether there is any exceptional feature of this case which would justify the exercise of any residual discretion not to strike out a claim which could and should have been brought in earlier proceedings and is an abuse of process. I have not identified such a feature. I would therefore strike out the Present Claim pursuant to the principle in Henderson v Henderson .
(5) Other issues relating to the Present Claim
137. These points were not developed to any great extent in Mr Karas’s oral submissions, and it was not entirely clear whether they are put forward as a further ground on which the Present Claim should be struck out, or are setting the scene for further debate and directions should the claim not be struck out. [31] For his part Mr Morgan indicated that there would not necessarily be any objection on MSC’s part to the matter proceeding as a Part 7 claim.
MSC’s amendment application
Introduction
139. I have already referred to MSC’s application to amend the claim form in the Present Claim. [32] The latest version of the proposed amendment, submitted to the court on the final day of the hearing, is set out in the Annex to this judgment. Essentially it seeks to add a further ground for the declaration that the discharge via Outfall 61 of treated waste originating in the Marshbrook Sewer is a trespass: the proposed new ground is that the consent of MSC pursuant to subsection 186(1) of the 1991 Act has not been sought or obtained by UU. The proposed amendment also contains the assertion that MSC “uses [the Canal] for draining land under the provisions of the Manchester Ship Canal Act 1885”. I will refer to the proposed ground as “the s.186 Point”.
Principles relating to amendment
“(a) ensuring that the parties are on an equal footing;
(b) saving expense;
(c) dealing with the case in ways which are proportionate -
(i) to the amount of money involved;
(ii) to the importance of the case;
(iii) to the complexity of the issues; and
(iv) to the financial position of each party;
(d) ensuring that it is dealt with expeditiously and fairly;
(e) allotting to it an appropriate share of the court's resources, while taking into account the need to allot resources to other cases; and
(f) enforcing compliance with rules, practice directions and orders.”
146. Mr Morgan submitted that each of these factors militated in favour of MSC’s application.
Section 186 of the 1991 Act
“ Protective provisions in respect of flood defence works and watercourses etc.
(1) Nothing in this Act shall confer power on any person to do anything, except with the consent of the person who so uses them, which interferes—
(a) with any sluices, floodgates, groynes, sea defences or other works used by any person for draining, preserving or improving any land under any local statutory provision; or
(b) with any such works used by any person for irrigating any land.
(2) Without prejudice to the construction of subsection (1) above for the purposes of its application in relation to the other provisions of this Act, that subsection shall have effect in its application in relation to the relevant sewerage provisions as if any use of or injury to any such works as are mentioned in paragraph (a) or (b) of that subsection were such an interference as is mentioned in that subsection.
(3) Nothing in the relevant sewerage provisions shall authorise a sewerage undertaker injuriously to affect—
(a) any reservoir, canal, watercourse, river or stream, or any feeder thereof; or
(b) the supply, quality or fall of water contained in, or in any feeder of, any reservoir, canal, watercourse, river or stream,
without the consent of any person who would, apart from this Act, have been entitled by law to prevent, or be relieved against, the injurious affection of, or of the supply, quality or fall of water contained in, that reservoir, canal, watercourse, river, stream or feeder.
…
(6) A consent for the purposes of subsection (1) above may be given subject to reasonable conditions but shall not be unreasonably withheld.
(7) Any dispute—
(a) as to whether anything done or proposed to be done interferes or will interfere as mentioned in subsection (1) above;
(b) as to whether any consent for the purposes of this section is being unreasonably withheld;
(c) as to whether any condition subject to which any such consent has been given was reasonable; or
(d) as to whether the supply, quality or fall of water in any reservoir, canal, watercourse, river, stream or feeder is injuriously affected by the exercise of powers under the relevant sewerage provisions,
shall be referred (in the case of a dispute falling within paragraph (d) above, at the option of the party complaining) to the arbitration of a single arbitrator to be appointed by agreement between the parties or, in default of agreement, by the President of the Institution of Civil Engineers.”
The s.186 Point
(i) MSC is a person who “uses” a relevant facility and whose consent is required under the subsection;
(ii) UU is a person who is prohibited from “do[ing] anything…which interferes” with that relevant facility without MSC’s consent;
(iii) the relevant facility includes “sluices” and also “other works”, namely, the Canal;
(iv) the Canal (including relevant sluices) is used by MSC “for draining…any land under any local statutory provision”
(v) the local statutory provision is the Manchester Ship Canal Act 1885.
153. In order to support the assertions, referred to under sub-paragraphs 148 (iv) and (v) above, that the Canal is used by MSC “for draining…any land under” the Manchester Ship Canal Act 1885, Mr Morgan referred to a factual account appearing in the judgment of Moses LJ in R (oao The Manchester Ship Canal Co Ltd) v Environment Agency [2013] EWCA Civ 542, at paragraphs 3-5:
“3. The Manchester Ship Canal Act 1885 was the first of the Manchester Ship Canal Acts and Orders 1885 to 2009 pursuant to which the Canal was constructed and maintained. The Canal allowed the heavy tariffs imposed by the Liverpool docks and railway companies to be avoided and, consequently, trade flourished in Manchester. The feature of its construction which is of particular significance in this appeal is that the river courses, particularly those of the Irwell and Mersey, were canalised. The Canal also intercepted or shared the flow of other rivers such as the Irk and the Medlock and, in the Lower Reaches, the Weaver.
4. The canalisation of the rivers gave the Canal another important role besides navigation. It enabled flood water to pass safely down the Canal to the Mersey Estuary and thus provided land drainage for the Manchester conurbation and beyond, a total catchment area of 3,000 km². Before the Canal was built there was a history of flooding in the Manchester to Warrington area (in 1729, Daniel Defoe described a bridge in Manchester built 'so high because floods could cause the river to rise four or five yards in a night'). Since 1894, when the Canal was completed, the canal structure and its associated systems have safely passed all flood flows to the Mersey Estuary. This success in flood prevention fulfilled and surpassed the statutory obligations of the undertaker, the Manchester Ship Canal Company Limited, to allow the passage, discharge and escape of flood waters from rivers and land, (see sections 71(13), 84(5), 84(16), 101(6), 114(1) and 118(2) of the 1885 Act). The width and depth of the channel formed by the Canal far exceeded the natural river channels it replaced; the Canal with its associated structures improved the flow of the rivers and thereby reduced the risk of flooding.
5. The sluices control the water level by enabling the waters which enter the Canal from rivers and other sources to pass down the Canal in a regulated manner. They are electrically powered and are normally operated automatically from a central control room, but can, as a back-up, be operated electrically, hydraulically or manually from equipment located on the structure of the sluices. The respondents emphasise the reliability of the sluices; the annual probability of all the sluices failing to operate in a 1% probability flood is less than 0.01%.”
155. When I put to Mr Morgan that if his argument was correct, the implied statutory right found by the Supreme Court to exist by virtue of sections 106 and 116 was not a “right” at all, as it could not be exercised without the consent of the owner of the waterway in question, he agreed. He also agreed that compliance (without trespass or other unlawfulness) with the sewerage undertaker’s statutory obligations under those sections would depend upon there being enough time to obtain that consent before the statutory obligation crystallised. [33]
156. At the hearing in the Supreme Court Mr Morgan was not representing MSC but an intervener, the Middle Level Commissioners, a body usually described as a “water level or flood management organisation” or an “internal drainage board”. In that capacity he seems to have raised a similar point on their behalf. In the application to intervene, it was argued by the Commissioners that they would be deprived of the protection of the Deeming Provision if the implied statutory right under discussion in the appeal were held to arise under section 94 and/or section 159, as those were not RSPs. [34] I have been shown a transcript of part of the hearing in the Supreme Court. Section 186 was considered at some length in exchanges between counsel and the members of the Court. Various possibilities were put by the Court to counsel as to the circumstances in which the consent requirement under subsection 186(1) might be triggered if, for example, there arose an increased volume of discharge at an outfall. Nothing can properly be deduced from this debate, except that the Court was alive to the contents of section 186, and had had their attention specifically drawn to the Deeming Provision.
157. At no stage in those discussions, or at any other stage in those proceedings, did MSC rely upon or raise the s.186 Point as applicable to itself. It is common ground [35] between Mr Morgan and Mr Karas that, although the interveners before the Court included such bodies as the Canals and Rivers Trust, who intervened on behalf of canal and river owners generally, no-one suggested to the Court that subsection 186(1) might apply for the benefit of the Canal or any canal. Subsection 186(1) was discussed in the context of the Middle Level Commissioners’ intervention. There was no dispute that the subsection applied to such bodies.
The amendment application
158. Mr Morgan urged and I accept: (1) that this is not a late amendment in the sense that, if allowed, there would be a risk of disruption of the timetable for procedural steps and/or vacation of trial dates – the Present Claim is still in that sense at an early stage, although the application was not made as soon as it could have been; (2) that the application to amend did not jeopardise the hearing dates for the strike-out application, although it did add significantly to the length of the hearing and has meant that a second round of skeletons has been necessary; (3) that the amendment raises an issue which is of importance to both parties, and no doubt to others in a similar position – it is admittedly a test case; and (4) that, subject to UU’s argument as to the inadequacy of the claim form and the absence of supporting evidence, there has been no specific breach of a rule of court, practice direction or court order. Therefore, some of the authorities to which I was referred, such as Quah v Goldman Sachs International ]2015] EWHC 759 (Comm), and Soo Kim v Youg [2011] EWHC 1781 (QB), are not much in point.
Estoppel arguments
167. What of issue estoppel? As seen, [36] this normally operates as a bar where the cause of action is not the same in the later action, but an issue necessarily common to both actions was decided on the earlier occasion. It also operates as a bar to points which were not raised if they could with reasonable diligence and should have been raised. The bar may not operate in special circumstances where injustice would be caused.
169. Mr Morgan countered by arguing that a property owner or a drainage body could not be forever shut out from making a complaint about a discharge. He drew the distinction between a case where a claimant had succeeded in an action and obtained damages in lieu of an injunction, which might well represent finality, and a case where, as here, the original case had failed. He submitted that there was not the same sense of finality about failure. In this context he also referred me again to the dicta of Lord Sumption in the Virgin Atlantic case which emphasised that res judicata rules and abuse of process were distinct but overlapping principles, with the common purpose of limiting abusive and duplicative litigation, which qualified both cause of action and issue estoppel where the conduct was not abusive. [37]
170. Notwithstanding the skill of Mr Morgan’s submissions, I am of the view that issue estoppel would apply to bar the proposed amendment based on the s.186 Point. I have already found that the point could and should have been taken in the 2010 Claim. I accept Mr Karas’s contention that there is a common issue of statutory authorisation for the discharge via Outfall 61, to which this point would have been relevant. None of the factors urged by Mr Morgan amount to special circumstances such that injustice would be caused by imposing the estoppel. As stated in earlier parts of this judgment, MSC had adequate time to raise all the points it wished to raise in good time for them to be determined in the 2010 Claim. For the reasons I gave in relation to the Origin Point, [38] I consider that there would be injustice to UU if the amendment were allowed. It is not acceptable, and is not within the spirit of the overriding objective, for litigation to be conducted in a linear manner, with different points being taken seriatim over the course of several years, rather than together at the appropriate time.
Henderson v Henderson argument
172. I have determined [39] that the s.186 Point could with reasonable diligence, and should in all the circumstances, have been brought in the 2010 Claim. In considering the “should” element, I have adopted the broad merits-based approach identified by Lord Bingham in Johnson . There was no good reason not to include the argument as part of the 2010 Claim. Most of the factors which I found applicable to the Origin Point also apply here. (See, in particular, paragraphs 129-134 above.) For those reasons, I have reached the conclusion that to allow the s.186 Point to be litigated in the Present Claim would be unjust and oppressive to UU. The proposed amendment would in my view constitute an abuse of process within the Henderson v Henderson principles, and I do not consider that there is any exceptional feature which would justify the exercise of a residual discretion not to strike it out.
Other issues relating to s.186 Point
173. As seen, [40] it is common ground that permission to amend should only be granted if the claim which is the subject of the proposed amendment has a real (as distinct from fanciful) prospect of success. The test is the same as for summary judgment. I have detailed the nature of the s.186 Point. It is UU’s submission that it has no real prospect of success and is bound to fail, both because of a fatal lack of particularity and evidence, and on its substantive merits as a matter of statutory construction. Mr Karas has also raised an issue concerning the arbitration provision in subsection 186(7) and an issue about the utility of the relief sought.
175. UU refers to the fact that the Present Claim is a Part 8 claim, and that CPR 8.5(1) provides:
“The claimant must file any written evidence on which he intends to rely when he files his claim form”.
177. For example, MSC does not just rely on the Canal as a whole but also on “sluices” as being the infrastructure “interfered with”. Yet no sluice has been identified in evidence. Whilst MSC identifies itself as the person “using” the Canal and sluices for “draining land” under the provision of a local statutory provision, there is no evidence identifying any land which is said to be drained; nor any evidence explaining how the infrastructure in question is being “used” by MSC for that purpose, or how UU’s discharge at Outfall 61 interacts, if at all, with the relevant infrastructure so used. Nor has any evidence been adduced to identify any specific provision under which that use is said to be carried out. Only a blanket reference to the Manchester Ship Canal Act 1885 is made in the draft amended pleading. Although Mr Morgan referred in argument to some factual material in the judgment of Moses LJ in the Environment Agency case (above [41] ), in which there is a reference to certain sections of that Act, there is no evidence that really explains how any of these provisions is said to bring section 186 into play. Nor is there any explanation as to how any of the provisions in question, and the infrastructure or part of the Canal to which the provision applies, relates to the discharge at Outfall 61.
178. Mr Karas took me to these provisions in the 1885 Act. Subsection 71(13) appears to oblige MSC to provide remedial works, for the protection of the Trustees of the River Weaver Navigation, in respect of any obstruction to the passage of the flood waters of the River Weaver; subsection 84(5) requires MSC to maintain a lock and flood gates at Latchford; subsection 84(16) requires MSC to restore and make good the drainage of a riparian owner, the Bridgewater and the Ellesmere Trustees; subsection 101(6) requires MSC to provide and maintain culverts for a riparian owner, Henry Stanton, to take away certain brooks, and to construct infrastructure which prevents the Mersey flooding into those culverts; subsection 114(1) requires outlets to be constructed at the Dock at Warrington to allow the drainage of surrounding land; and subsection 118(2) requires MSC to maintain various apparatus in a particular part of the Canal.
182. He also referred me to In Soo Kim v Youg (above), a decision of Tugendhat J, and to the application of that decision by Master McCloud in Breeze v Chief Constable of Norfolk [2018] EWHC 485 QB This was a late application to amend without the proposed amended particulars of claim being available at the time of the application. At paragraph 37 the Master said:
"It seems to me that the decision whether to take a strict approach to pleading and therefore to bring this aspect of the claim to an end is essentially discretionary but must be exercised rationally, that is on some sensible basis. I do not in my judgment have to have, for example, a draft amended pleading before me. I take the view that in principle a credible request from counsel could in some circumstances be enough to persuade me to allow an effort to amend appropriately, but in this there is more material than that to go on."
184. In these circumstances it is difficult to form a firm view of whether there would be a real prospect of success if the case were properly particularised and evidenced. I have described the way in which MSC puts the s.186 Point, [42] and also the basis for UU’s submission that the point would have no realistic prospect of success as a matter of construction. [43] Whilst both parties have touched on certain question of statutory construction, the arguments addressed to me on those questions have not been as detailed as in relation to the Origin Point. I do not feel it would be sensible, on the basis of the material available and the arguments I have heard at this stage, to attempt to form a concluded view on whether the s.186 Point would be bound to fail or not, if there were a properly particularised statement of case.
Overall conclusion
187. I invite the parties to agree a draft order which reflects the conclusions I have reached.
ANNEX
Claim No. PT-2017-000163
IN THE HIGH COURT OF JUSTICE
BUSINESS AND PROPERTY COURTS OF ENGLAND WALES
PROPERTY TRUSTS AND PROBATE LIST (ChD): PROPERTY
BETWEEN:
THE MANCHESTER SHIP CANAL COMPANY LIMITED
Claimant
-AND-
UNITED UTILITIES WATER LIMITED
Defendant
Revised Draft / AMENDED CLAIM FORM 16 November 2018 |
Original proposed amendments are underlined. Revisions to the proposed amendments are shown in red.
The Claimant is the owner of the Manchester Ship Canal which it uses for draining land under the provision of the Manchester Ship Canal Act 1885 .
The Defendant is a sewerage undertaker for the purposes of the Water Industry Act 1991 and relevantly for the purposes of these proceedings, the owner and operator of Davyhulme Waste Water Treatment Works, Rivers Lane, Urmston M41 7JB. The Defendant is responsible for the discharge into the Manchester Ship Canal of water and sewage from an outlet pipe, drain or sewer known to the parties as Outfall 61, the location of which is described in the witness statement of Mr Graeme Andrew Couch made in support of this claim and dated 17 th November 2017.
For the reasons set out more fully in the witness statement of Mr Couch and/or pursuant to section 186 subsections (1) and (2) of the Water Industry Act 1991 , the Claimant seeks a declaration that the discharge by the Defendant of water and other materials into the Manchester Ship Canal through the outfall situated near Davyhulme Waste Water Treatment Works within the Metropolitan Borough of Trafford (known to the parties as outfall 61) is a trespass against the Claimant to the extent that the water and other materials so discharged include water and materials which originate from a sewer or sewers constructed or adopted by the Defendant in or about 2007 to receive water from properties developed at or about that time at Marshbrook Drive, Manchester M9 8NN, which additional water and materials are being discharged into the Manchester Ship Canal without the consent of the Claimant pursuant to section 186 subsection (1) of the Water Industry Act 1991 or otherwise having been either sought or obtained.
[1] In fact the sewer was adopted by UU on 5 October 2007 pursuant to an agreement with the developer. It may have been connected to the public network prior to that date.
[2] See Couch 3, at paragraph7.
[3] Section 186 is at paragraph 147 of this judgment.
[4] Although there is some interchangeability of usage in the pleadings in the 2010 Claim, when the parties refer to a “discharge” they appear in general to mean the substance which discharges from an outfall into a watercourse, and when they refer to “outfall” they appear in general to mean the physical structure (usually a pipe) from which a discharge emerges.
[5] Amended Particulars of Claim, paragraph 15.
[6] Amended Defence and Counterclaim , paragraph 15.
[7] In Smith 1, at paragraph 13, Mr Smith states that UU’s Defence and Counterclaim (amended in 31 May 2011), took seven and a half months to prepare, comprised a 26-page main pleading with three lengthy schedules and 117 separate fully-pleaded annexes pleading UU’s case in relation to each of the 117 outfalls in question.
[8] Amended Defence and Counterclaim, paragraphs 16-17.
[9] Manchester Ship Canal Co Ltd v United Utilities Water plc [2014] UKSC 40, [2014] 1WLR 2576 (“the SC Decision”).
[10] See paragraph 40 of this judgment.
[11] The emphasis was in MSC’s skeleton argument and not by Lord Sumption.
[12] See paragraphs 139ff of this judgment.
[13] See, for example, the discussion in the Supreme Court in the transcript for 7 May 2014, pages 116-154, in the context of the effect of section 186 of the 1991 Act.
[14] Cited at paragraph 36 of this judgment.
[15] Cited at paragraph 40 of this judgment.
[16] Subject to MSC’s argument based on section 186 of the 1991 Act, comprised in the proposed amendment to the claim form.
[17] See also the discussion of the caselaw in Warren J’s judgment in Harland & Woolff Trustees Ltd v Aon Consulting Ltd [2010] ICR 121, at paragraphs 39-68.
[18] See paragraph 21ff of this judgment.
[19] See paragraph 47 of this judgment.
[20] See paragraph 45 of this judgment.
[21] At paragraph 74 of MSC’s main skeleton argument.
[22] See the citation at paragraph 79 of this judgment.
[23] Paragraphs 10-15 of the particulars of claim in the 2010 Claim.
[24] See paragraphs 121 -134 of this judgment.
[25] See paragraph 76 of this judgment.
[26] At paragraphs 77ff of MSC’s main skeleton argument. See also transcript Day 3, pages 39-40.
[27] See paragraph 45 of this judgment.
[28] Paragraph 45 of this judgment.
[29] See paragraph 109 of this judgment.
[30] Defence and Counterclaim in the 2010 Claim, at paragraphs 16(4) and 17.
[31] See Transcript Day 2, pages 37-41.
[32] See paragraph 5 of this judgment.
[33] Transcript, Day 2, pages 76-78.
[34] Paragraph 38 of the application to intervene.
[35] Transcript, Day 2, pages 100-101.
[36] See paragraph 104 of this judgment.
[37] See paragraph 25 of the judgment in that case. See also paragraph 22.
[38] See paragraphs 102, and 121-134 of this judgment. See also paragraph 172.
[39] See paragraphs 161-163 of this judgment.
[40] See paragraph 144 of this judgment.
[41] Paragraph 153 of this judgment.
[42] Paragraphs 148-154 of this judgment.
[43] See paragraph 179 of this judgment.