CHANCERY DIVISION
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
MULTI VESTE 226 B.V. |
Claimant |
|
- and - |
||
(1) NI SUMMER ROW UNITHOLDER B.V. (2) MAR PROPERTIES LIMITED (3) WINDSOR SECURITIES LIMITED (4) MR MICHAEL LAGAN (5) MR JOHN PATRICK KEVIN LAGAN |
Defendants |
____________________
Mr. Jonathan Gaunt QC and Mr. James Cutress (instructed by SNR Denton UK LLP) for the Defendants
Hearing dates: 13,14,15,16,17,20,21,22,23,24,27,28,29,30 June,
1,4,5,13 July 2011
____________________
Crown Copyright ©
Mr Justice Lewison:
Paragraph | |
Introduction | 1 |
Multi's governance | 7 |
Burden of proof | 10 |
Approach to the evidence | 14 |
Retailing in Wolverhampton | 16 |
The factual background | 18 |
The USA | 32 |
Bank funding | 47 |
Multi's assessment of the viability of the scheme | 49 |
The run up to termination of the USA | 93 |
The affordable housing | 116 |
The Bank loan | 122 |
Mezzanine finance | 134 |
Appraisals and valuations | 137 |
The DTZ Development Team | 137 |
Cushman & Wakefield | 140 |
Mr Harris | 142 |
The DTZ Viability Appraisal | 143 |
HBA-25 | 149 |
The expert evidence | 153 |
The outlines | 153 |
Zone A rental values | 155 |
Tenant incentives in December 2008 | 161 |
Extent of pre-letting | 163 |
Permanent voids | 164 |
Mall Income | 165 |
Car parking income | 168 |
Yields | 169 |
Residential | 176 |
Purchaser's costs | 179 |
Developer's contingency | 180 |
Value in December 2008 | 182 |
Viability | 183 |
Did Multi lawfully terminate the USA? | 186 |
If the NI Investors had provided the bank guarantees would the project have gone ahead? | 206 |
Multi's position | 206 |
Would the banks have lent at all? | 210 |
If the banks had lent how much would they have lent? | 214 |
Would Apollo have lent money? | 216 |
Would the Council have agreed to waiver of the Commercial Conditions? | 217 |
What would Multi have done? | 222 |
If Summer Row had been build would Multi have made a profit? | 235 |
The framework | 235 |
Rental values in Q4 2011 | 239 |
Tenant incentives in Q4 2011 | 247 |
Permanent voids | 248 |
Yields in Q4 2011 | 249 |
Residential | 253 |
Value | 254 |
Finance costs | 255 |
Interest | 255 |
Multi's cost of capital | 256 |
The £28 million subscription | 267 |
The overall loss | 273 |
Result | 275 |
Introduction
i) Was Multi 226 entitled to terminate the USA when it purported to do so?
ii) Would the development have been built out if the bank guarantees had been provided?
iii) If the development had been built out would it have been profitable?
Multi's governance
Burden of proof
i) Where the wrong consists of an omission (as in the present case) causation depends, not upon a question of historical fact, but on the answer to the hypothetical question, what would the claimant have done if the wrong had not been committed? This can only be a matter of inference to be determined from all the circumstances. The claimant's own evidence that he would have acted to obtain the benefit or avoid the risk, while important, may not be believed by the judge, especially if there is compelling evidence that he would not. Although the question is a hypothetical one, the claimant must prove on balance of probability that he would have taken action to obtain the benefit or avoid the risk. But if he does establish that, there is no discount because the balance is only just tipped in his favour.
ii) In many cases the claimant's loss depends on the hypothetical action of a third party, either in addition to action by the claimant, as in this case, or independently of it. In such a case, the claimant can succeed provided he shows that he had a substantial chance rather than a speculative one, the evaluation of the substantial chance being a question of quantification of damages.
i) Whether the banks would have lent in accordance with the terms of the draft facility letter is to be decided on the balance of probabilities;
ii) Whether the Council would have agreed to the waiver of the conditions precedent; or would have agreed to remove any requirement in the Development Agreement for building the residential component; or would have agreed to the removable of affordable homes, is to be decided according to the lower threshold of a substantial or significant chance;
iii) Whether mezzanine finance would have been available (if needed) is to be decided according to the lower threshold of a substantial or significant chance.
Approach to the evidence
"Credibility involves wider problems than mere "demeanour" which is mostly concerned with whether the witness appears to be telling the truth as he now believes it to be. Credibility covers the following problems. First, is the witness a truthful or untruthful person? Secondly, is he, though a truthful person, telling something less than the truth on this issue, or, though an untruthful person, telling the truth on this issue? Thirdly, though he is a truthful person telling the truth as he sees it, did he register the intentions of the conversation correctly and, if so, has his memory correctly retained them? Also, has his recollection been subsequently altered by unconscious bias or wishful thinking or by overmuch discussion of it with others? Witnesses, especially those who are emotional, who think that they are morally in the right, tend very easily and unconsciously to conjure up a legal right that did not exist. It is a truism, often used in accident cases, that with every day that passes the memory becomes fainter and the imagination becomes more active. For that reason a witness, however honest, rarely persuades a Judge that his present recollection is preferable to that which was taken down in writing immediately after the accident occurred. Therefore, contemporary documents are always of the utmost importance. and lastly, although the honest witness believes he heard or saw this or that, is it so improbable that it is on balance more likely that he was mistaken? On this point it is essential that the balance of probability is put correctly into the scales in weighing the credibility of a witness, and motive is one aspect of probability. All these problems compendiously are entailed when a Judge assesses the credibility of a witness; they are all part of one judicial process and in the process contemporary documents and admitted or incontrovertible facts and probabilities must play their proper part."
Retailing in Wolverhampton
The factual background
i) Subject to the satisfaction of certain conditions precedent ("the Conditions Precedent"), the Council would grant to the Partnership the lease for the Site.
ii) Subject to the satisfaction of the Conditions Precedent, Multi would carry out or procure the carrying out of "the Developer's Works" (as defined).
i) The Planning Condition: obtaining of a Qualifying Planning Permission.
ii) The CPO Condition: the coming into existence of a Confirmed CPO (separately defined) or if sooner the parties acquiring the whole of the Site by way of Site Assembly to their reasonable satisfaction; and
iii) The Highway Condition: obtaining of the Highway Closure Order and the Highway Pedestrianisation Order (each separately defined), in each case subject only to such conditions as were reasonably acceptable to the Developer.
i) The Pre-Letting Condition: the Developer or Tenant entering into agreements for lease with prospective tenants in respect of (i) the Principal Department Store (separately defined) and (ii) other Commercial Units for which agreements for lease provided and secured (in the aggregate) 50% of the Estimated Rental Value.
ii) The Funding Condition: the Developer securing with an Approved Funder and on Approved Funding Terms funding for the carrying out of the Development upon the Site and that funding being or becoming unconditional, or conditional only on the satisfaction of the Conditions Precedent.
iii) The Minimum Return Condition: the Developer confirming that it expects to achieve a minimum anticipated return of 15% on anticipated Total Development Costs.
"the development of the Site to comprise a retail led mixed use scheme including the Minimum Development Requirements and broadly in accordance with the … Planning Brief and the Council's Objectives."
The USA
"Upon the Council Pre-Condition being satisfied the Partnership shall give the NI Unitholder written notice forthwith of that fact and 5 Business Days after that notice" the parties were to perform the obligations listed in clause 2.5.
i) The Development Cost Subscription Agreement required Multi to subscribe for units to meet the development costs incurred up to the Unconditional Date;
ii) The Post Unconditional Date Basic Subscription Agreement required both Multi and the NI Unitholder to subscribe for units up to a "cap" of £27 million each;
iii) The Cost Overrun Subscription Agreement required Multi to bear the costs of any cost overrun to the extent that the costs exceeded the £54 million required by the Post Unconditional Date Basic Subscription Agreement.
"IP = (1/2 x (VAC + PAC)) – PAC
where IP is the Initial Price; VAC is the aggregate amount subscribed by the Vendor for Units in the period up to Completion; and PAC is the aggregate amount subscribed by the NI Unitholder for Units in the period up to Completion."
"The Deferred Price shall be (i) one half of the Initial Investment Value less one half of the Estimated Development Costs less (ii) the aggregate of the Initial Price, the NI Subscription Price and the NI Priority Investment Return ..."
"(A x 17.09) + (B x 11.963) – C
where A is the Achieved Rent for each Letting Unit on Practical Completion up to and including the Base Rent, B is the Achieved Rent for each Letting Unit let on Practical Completion in excess of the Base Rent, and C is the adjusted amount of Principal Rent foregone after Practical Completion as a result of any Rent Free Periods under the leases."
(A – B) + C
Where A is the Base Rent for the unlet Letting Unit, B is the amount of any receivable by the Partnership in respect of that Letting Unit for the Quarter then beginning by way of any insurance monies and all rent and other income of whatever nature derived from the use, enjoyment or occupation of the Site, and C is any amount by which the Mall Income (as defined) falls short of the Base Rent for the Mall Income as at the relevant date.
Bank funding
Multi's assessment of the viability of the scheme
"Fundamental to this is the viability of the scheme and following the submission and review of a draft paper I regret that the Multi Corporation Board has suspended any formal approval of the scheme unless the profit returns can be improved upon by the UK team."
"5.85% was used for calculating feasibility and yield. Market value is now closer to 6.5% (possibly slightly lower with M & S lease creating dual department store anchored scheme), so the profit of € 35 million is pressured and only held up due to 50% pre-sale to Irish investors. Backing out would mean taking a loss on € 25-30 million invested with at best small recovery. Solvency of Irish investors need to be checked.
A leasing hurdle of 40% with M & S is condition.
Alternatives for residential like hotel are being investigated.
The investment proposal is approved with the following conditions: critical review of pricing of residential, lease signed with M & S, financial viability check and willingness to close of Irish investors at 5.85% forward funding."
"We need to diplomatically say that we need confirmation from their bank (Ulster Bank) that they are good for the bank guarantee required in January!
We need to make an excuse and say for example we are being requested this from the council as we look to go unconditional and that they are asking us for similar confirmation of our current financial status due to the current economic climate.
Obviously it is Gouda that really wants this."
"After several recent conversations it is clearly apparent that Summer Row is potentially to be cancelled as an active project. I cannot sit by and let this happen without comment."
"I am not aware of the board's detailed debate and the reasoning behind this course of action. I am, although, fully conscious of the revised level of equity required to bring the project to fruition and the implication this has in the current financial marketplace."
"On cancelling the project it will be virtually impossible to keep this decision confidential in the market place as suppliers will immediately speculate. This will severely weaken our negotiating position if we intend to sell the project. It may also trigger NI to initiate legal proceedings for consequential loss."
"Hans van Veggel [the chairman] is of the opinion that the project should be sold now. Answering a question … Eric van Duren confirms that this project is not a green line project. The meeting supports the idea … to sell the project as soon as possible to get the invested equity back."
"To proceed we need to present the JV proposal and the abortive payments proposal as soon as possible to NI Investors. It is recommended that this is done during the week of 13th October."
"The proposal is not approved. Costs should go down."
"I confirm that I have updated the other members of the group about our meeting and I informed them that Multi is considering how to proceed in connection with the Scheme.
I look forward to receiving your proposals as and when available."
"These projects are now put on HOLD with all earlier Investment Committee approval rescinded; but will be the first projects allocated start approval as Multi undertakes to carefully manage its cash reserves. In order to proceed forward in making the necessary equity allocations, Excom is requesting a revised Investment Proposal explaining how each project can be moved forward and preserved with as small a current expenditure as possible in accordance with a new estimate of a future timeline for construction start."
"The design team is now on hold from 31st October until all funding arrangements with NI Investors are in place. On delivery of guarantees, Multi will prepare the necessary paperwork to a state to request unconditionality with [the Council]. This is expected at the Members meeting at the beginning of January 2009."
The run up to termination of the USA
"This investment proposal is to keep the project alive. Notice was sent to NI to post 27 million of bank guarantees per the forward purchase contract. Negative reaction is received. Land price with the Municipality cannot be changed without a new tender.
Investment proposal remains pending. Project is put on hold."
"… our client had set Monday, 24 November 2008 as the date upon which the actions required by clause 2.5 of the Unit Sale Agreement be undertaken. …
We will be in contact with you concerning the mechanics of completion and attendance in Amsterdam.
You should be aware that our client will not be offering any further extensions of time in relation to completion. It fully intends to comply with its obligations in relation to completion on Monday, 24 November and will expect your client to do likewise."
"We … put you on notice that in our view any failure by your clients to fulfil their obligations pursuant to clause 2.5 and to complete this stage of the transaction on Monday afternoon at our office in Amsterdam at 3 pm will amount to a repudiatory breach of the USA and we shall so advise our client."
"You should be aware that if completion does not take place as planned, our clients will look to enforce their contractual rights by way of an action for specific performance in relation to the provision of the NI Guarantees and/or by a claim for damages resulting from your clients' repudiatory breach."
"If completion does not take place tomorrow … our client will enforce its contractual rights against your client in the manner envisaged in my letter to you of 25 November."
"It is already clear to us that with the further deterioration of the economic climate since our last press release in December that a start on site this year will not be achievable. It is questionable if the current scheme, designed in a dramatically different economic climate, is deliverable at all without substantial redesign."
The affordable housing
"The Wolverhampton Affordable Housing SPD states that "Where a developer considers that there are major inhibiting factor which would so threaten the economic viability of their proposal, that only a mitigation of the affordable housing requirement can resolve, then they should submit to the Council a full and comprehensive Financial Viability Assessment (FVA) for the Council to appraise and come to a decision whether mitigation is justified. The Council will appoint its own assessors for this purpose to provide professional and impartial advice."
The Bank loan
i) Evidence of the source, availability and application of all sums (being not less than the borrower's commitment) required in addition to the facilities to complete the transaction and meet all costs and tax associated with it; and
ii) Evidence that the borrower has paid from its own resources towards the total costs the amount by which the borrower's commitment exceeds £67.3 million;
iii) The NI bank guarantee;
iv) A formal valuation including the market value of the property prior to development, gross development value, reinstatement value assuming completion of the development and ERV assuming completion of the development;
v) A development appraisal from the banks' monitoring surveyor.
"As long as the ERV hits £18m, the yield stays at 6.5% and the resi sells for £18m we should be ok."
"… first NI, and then close the deal."
Mezzanine finance
Appraisals and valuations
The DTZ Development Team
Cushman & Wakefield
Mr Harris
The DTZ Viability Appraisal
"The principal obstacle we see at the present time is the current economic situation which is likely to mean that retailers will decline to commit to additional representation, and if they do decide to proceed, will require increased incentives to do so."
HBA-25
The expert evidence
The outlines
Zone A rental values
i) Derby is a more affluent city than Wolverhampton, which was below the national average;
ii) Derby has a larger potential shopping population than Wolverhampton;
iii) Derby has no competing shopping centre, whereas Wolverhampton has two;
iv) Derby has no competing department store, whereas Wolverhampton has one;
v) Even without Summer Row, there is more retail space in Wolverhampton than in Derby;
vi) The Westfield Centre at Derby is a covered shopping centre, whereas Summer Row would not have been;
vii) Rents at the Westfield Centre Derby were established in 2006 and 2007 when the market was much stronger than it was in December 2008.
Tenant incentives in December 2008
Extent of pre-letting
Permanent voids
Mall Income
Car parking income
Yields
Residential
Purchaser's costs
Developer's contingency
Value in December 2008
Viability
"Given the amount of Bank funding that would have been provided, and given the overall future costs of the Development, there would have been a shortfall. Provided that the shortfall could be met by Multi or other parties, then the scheme was viable."
Did Multi lawfully terminate the USA?
i) Time was of the essence of the obligation under clause 2.5 to provide the bank guarantees and to complete the other documents;
ii) Alternatively, time was made of the essence by one or other of Norton Rose's communications to Semple Fraser.
"As to such a clause there is only one kind of breach possible, namely to be late, and the questions to be asked are: first what importance have the parties expressly ascribed to this consequence? And, second, in the absence of expressed agreement, what consequence ought to be attached to it having regard to the contract as a whole?"
"It is by construing a contract (which can be done as soon as the contract is made) that one decides whether a term is, either expressly or by necessary implication, a condition, and not by considering the gravity of the breach of that term (which cannot be done until the breach is imminent or has occurred)."
"In equity, and now in the fused system, performance had or has, in the absence of time being made of the essence, to be within a reasonable time. What is reasonable time is a question of fact to be determined in the light of all the circumstances. After the lapse of a reasonable time the promisee could and can give notice fixing a time for performance. This must itself be reasonable, notwithstanding that ex hypothesi a reasonable time for performance has already elapsed in the view of the promisee. The notice operates as evidence that the promisee considers that a reasonable time for performance has elapsed by the date of the notice and as evidence of the date by which the promisee now considers it reasonable for the contractual obligation to be performed. The promisor is put upon notice of these matters. It is only in this sense that time is made of the essence of a contract in which it was previously non-essential. The promisee is really saying, "Unless you perform by such-and-such a date, I shall treat your failure as a repudiation of the contract." The court may still find that the notice stipulating a date for performance was given prematurely, and/or that the date fixed for performance was unreasonably soon in all the circumstances. The fact that the parties have been in negotiation will be a weighty factor in the court's determination. …To say that "time can be made of the essence of a contract by notice," except in the limited sense indicated above, would be to permit one party to the contract unilaterally by notice to introduce a new term into it."
"First there is nothing in Federal Commerce v Molena Alpha [1979] AC 757 to suggest that the principles expressed, particularly by Lord Wilberforce at pp. 778–779, have no application to stipulations in respect of which time is originally, or is made, of the essence. Second, if the effect of making time of the essence is, as described by Nourse LJ in Behzadi v Shaftesbury Hotels Ltd, to remove equity's interference with the legal rights of the parties, the natural inference is that those rights arise from the ordinary principles of the common law and are not something special consequential on the removal of that interference. Third, and arising from the second consideration, if failure to comply with a notice making time of the essence of itself constitutes a repudiation irrespective of the consequence of the breach, then contrary to the statement of Lord Denning in Eshun v Moorgate Mercantile [1971] 1 WLR 722 at p. 726 it is possible to put upon another a repudiation which he has never committed. Fourth, there is no suggestion in Universal Cargo Carriers Corp v Citati [1957] 2 QB 401 that the delay in providing the cargo would have been a ground of rescission if notice had been given making time of the essence."
"The failure to pay did not deprive BSI of anything of value to BSI. BSI was not and is not liable to the landlord under the Devonshire Square leases. The evidence of Mr Hacker, a director of BSI, pointed out that BSI was not the tenant but he provided no evidence to suggest that BSI is in any way liable to the landlord or to Bear Stearns International Corp by way of indemnity against the liabilities arising from the Devonshire Square leases. So far as BSI is concerned the unperformed obligations of the parties under the agreement to lease are the grant and acceptance of the underlease of floor 25. The underlease of floor 25 is the benefit to BSI to which it is entitled. The breach on which BSI relies does not affect these obligations and does not deprive BSI of this benefit."
"If the defaulting party fails to perform after service of such a notice, the failure is not automatically a repudiation of the contract, giving rise to a right to terminate. The breach must go to the root of the contract."
"If one party declares his inability to perform some, but not all, of his obligations under the contract, then the right of the other party to treat himself as discharged depends on whether the non-performance of those obligations will amount to a breach of a condition of the contract or deprive him of substantially the whole benefit which it was the intention of the parties that he should obtain from the obligations of the parties under the contract then remaining unperformed."
"The result of non-compliance with the notice is that the party in default is guilty of unreasonable delay in complying with a non-essential time stipulation. The unreasonable delay amounts to a repudiation and this justifies rescission."
"This was said in reference to the completion of contracts for the sale of land. Thus although the contractual date for completion may be inessential, failure to complete at all will go to the root of the contact. Accordingly, Mason J was not considering the case of a term which was inessential in that sense. What was initially non-essential was the stipulation as to time not nature of the term, which plainly was a term breach of which was capable of going to the root of the contract."
"… the Court should not adopt an unduly technical approach to deciding whether the injured party has affirmed the contract and should not be willing to hold that the contract has been affirmed without very clear evidence that the injured party has indeed chosen to go on with the contract notwithstanding the other party's repudiation. In my view, the Court should generally be slow to accept that the injured party has committed himself irrevocably to continuing with the contract in the knowledge that if, without finally committing himself, the injured party has made an unequivocal statement of some kind on which the party in repudiation has relied, the doctrine of estoppel is likely to prevent any injustice being done.
Considerations of this kind are perhaps most likely to arise when the injured party's initial response to the renunciation of the contract has been to call on the other to change his mind, accept his obligations and perform the contract. That is often the most natural response and one which, in my view, the Court should do nothing to discourage. It would be highly unsatisfactory if, by responding in that way, the injured party were to put himself at risk of being held to have irrevocably affirmed the contract whatever the other's reaction might be, and in my judgment he does not do so. The law does not require an injured party to snatch at a repudiation and he does not automatically lose his right to treat the contract as discharged merely by calling on the other to reconsider his position and recognize his obligations."
"In my judgment, there is of course a middle ground between acceptance of repudiation and affirmation of the contract, and that is the period when the innocent party is making up his mind what to do. If he does nothing for too long, there may come a time when the law will treat him as having affirmed. If he maintains the contract in being for the moment, while reserving his right to treat it as repudiated if his contract partner persists in his repudiation, then he has not yet elected. As long as the contract remains alive, the innocent party runs the risk that a merely anticipatory repudiatory breach, a thing "writ in water" until acceptance can be overtaken by another event which prejudices the innocent party's rights under the contract - such as frustration or even his own breach. He also runs the risk, if that is the right word, that the party in repudiation will resume performance of the contract and thus end any continuing right in the innocent party to elect to accept the former repudiation as terminating the contract." (Emphasis added)
If the NI Investors had provided the bank guarantees would the project have gone ahead?
Multi's position
Would the banks have lent at all?
If the banks had lent how much would they have lent?
Would Apollo have lent money?
Would the Council have agreed to waiver of the Commercial Conditions?
"Where waiver is potentially possible in accordance with the Development Agreement the Council must be satisfied that the Developer can proceed with the Development. Where Multi, in confirming the status of the above conditions are indicating that waiver is being considered, Multi should advise on what basis they consider the development to be capable of being undertaken. For the avoidance of doubt the Council will expect compliance with the provisions of the development agreement in satisfying the conditions precedent."
What would Multi have done?
i) The Board did not want to put more equity into projects in acquisition or under development;
ii) This kind of project could only go forward on the basis of 100% guaranteed finding upfront;
iii) All previously approved budgets were rescinded;
iv) A project that was not a green line project would only go forward by a forward funded sale of the project against a newly determined exit yield;
If Summer Row had been build would Multi have made a profit?
The framework
i) The payments it would have received from NI Unitholder for a half share in the development, had Summer Row gone ahead, consisting of the Initial Price and the Deferred Price, less certain adjustments between Practical Completion and the Final Payment Date; plus
ii) the value of the half share in the completed development retained by Multi; less
iii) the costs to Multi of financing and building Summer Row.
Rental values in Q4 2011
Tenant incentives in Q4 2011
Permanent voids
Yields in Q4 2011
i) Plymouth is a regional centre rather than a sub-regional centre; and the latter are regarded as less dominant than the former;
ii) The shopping population of Plymouth is 345,000 compared to Wolverhampton's of 249,000. The corollary of this is that Plymouth has a greater penetration of its catchment area than Wolverhampton;
iii) Drake's Circus does not face the same level of competition from other retail centres as Wolverhampton as a whole; or indeed from internal competition within the town, whereas Summer Row would face competition from the Mander and Wulfrun Centres.
Residential
Value
Finance costs
Interest
Multi's cost of capital
"Multi would have funded any costs of the Development (beyond the amounts provided by the consortium of banks and the NI Unitholder) through its own funds, on the basis of its weighted costs of capital at 5.87%."
"Interest-bearing loans and borrowings only consist of group financing … Group financing is denominated in GBP and is repayable on demand. The weighted average interest rates paid is 8.72% (2007: 8.60%)."
The £28 million subscription
i) Procure that any loans made by members of the Multi group to the partnership were repaid; and
ii) Subscribe for units to finance that repayment.
The overall loss
i) I prefer Mr Chase's view of the level of capital incentives required to attract tenants;
ii) The centre would have been 80 per cent let at practical completion;
iii) If the development had been built out, it would have included the residential component (with the affordable housing); and Multi would have disposed of them individually rather than by block sale;
iv) Mr Chase was justified in adding a 3 per cent contingency;
v) If the development had been built out with a bank loan the maximum amount of the loan would have been £156.9 million;
vi) Multi would have had to buy units in the unit trust to finance the repayment of group loans;
vii) The appropriate WACC is 8.2%, compounded.
Result