If you found BAILII useful today, could you please make a contribution?
Your donation will help us maintain and extend our databases of legal information. No contribution is too small. If every visitor this month donates, it will have a significant impact on BAILII's ability to continue providing free access to the law.
Thank you very much for your support!
KING'S BENCH DIVISION
PLANNING COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE KING on the application of SUBSTATION ACTION SAVE EAST SUFFOLK LIMITED |
Claimant |
|
- and - |
||
SECRETARY OF STATE FOR BUSINESS, ENERGY AND INDUSTRIAL STRATEGY |
Defendant |
|
(1) EAST ANGLIA ONE NORTH LIMITED (2) EAST ANGLIA TWO LIMITED |
Interested Parties |
____________________
Mark Westmoreland Smith and Jonathan Welch (instructed by the Government Legal Department) for the Defendant
Hereward Phillpot KC and Hugh Flanagan (instructed by Shepherd and Wedderburn LLP) for the Interested Parties
Hearing dates: 15 & 16 November 2022
____________________
Crown Copyright ©
Mrs Justice Lang :
Grounds of challenge
i) the sequential test, properly applied, requires assessment of all sources of flooding at the stage of site selection;
ii) the Defendant did not properly apply the sequential test at the stage of site selection, rather than at the stage of design after site selection; and
iii) he otherwise acted irrationally in reaching his conclusions on flood risk.
i) he substantively adopted the ExA's reasoning which was based on an unlawful interpretation of the Infrastructure Planning (Decisions) Regulations 2010 ("the Decisions Regulations 2010"), which consequently infected the Defendant's analysis of heritage harm; and/or
ii) while the Defendant purported to give heritage harm "considerable importance and weight", such weight was not reflected in the overall planning balance, which followed the ExA's analysis, and which unlawfully attributed only "medium" weight, contrary to the legal requirement.
i) failed to take into account that his conclusions on noise necessarily entailed a conflict with paragraph 5.11.9 of National Policy Statement ("NPS") EN-1;
ii) relied on the imposition of a requirement which was in all the circumstances unreasonable in that it had not been shown to be workable; and/or
iii) failed to take into account the impact of noise from switchgear/circuit breakers in the National Grid substation.
i) failed to take into account representations made by the Claimant in respect of the need to secure a minimum generating capacity in the DCO and/or failed to give reasons for rejecting those representations; and/or
ii) took into account an irrelevant consideration, namely the total proposed generating capacity of the Development when this was not secured by a requirement in the DCO.
Factual background
i) Bramford 400kV substation;
ii) Sizewell 400kV substation;
iii) Leiston 400kV substation; and
iv) Norwich Main 400kV substation.
"25.3.13 In summary terms, the Friston location was viewed by the Applicant as the preferred substation location. Its main benefits were seen as its location outside the Suffolk Coast and Heaths AONB, the availability of a substantial body of land in which all substation infrastructure could be co-located, taking significant screening benefits from established woodland and the avoidance of possible conflicts with construction, operation or decommissioning in relation to Sizewell nuclear power stations. The disbenefit of the location was the need for a significant additional extent of onshore cable corridor to connect it to the landfall location."
"28.4 OVERALL CONCLUSION ON THE CASE FOR DEVELOPMENT
28.4.1. Because the Proposed Development meets specific relevant Government policy set out in NPS EN-1, NPS EN-3, and NPS EN-5, as a matter of law, a decision on the application in accordance with any relevant NPS (PA 2008 S104(2)(a) and S104(3)) also indicates that development consent should be granted unless a relevant consideration arising from the following subsections of the Act (PA 2008 S104 (4) to (8)) applies.
28.4.2. The Proposed Development is also broadly compliant with the MPS. Regard has been had to the Marine Plans in force and again, the Proposed Developments broadly comply (PA 2008 s104(2) (aa)).
28.4.3. Regard has been had to the LIR (PA2008 s104(2)(b), to prescribed matters (PA 2008 s104(2)(c)) and to all other important and relevant policy (including but not limited to the Development Plan) and to other important and relevant matters identified in this Report (PA 2008 s104(2)(d).
28.4.4. In the ExA's judgement, the benefits of the Proposed Development at the national scale, providing highly significant additional renewable energy generation capacity in scalar terms and in a timely manner to meet need, are sufficient to outweigh the negative impacts that that have been identified in relation to the construction and operation of the Proposed Development at the local scale. The local harm that the ExA has identified is substantial and should not be under-estimated in effect. Its mitigation has in certain key respects been found to be only just sufficient on balance. However, the benefits of the Proposed Development principally in terms of addressing the need for renewable energy development identified in NPS EN-1 outweigh those effects. In terms of PA 2008 s104(7) the ExA specifically finds that the benefits of the Proposed Development do on balance outweigh its adverse impacts.
28.4.5. In reaching this conclusion, the ExA has had regard to the effect of the Proposed Development cumulatively with the other East Anglia development and with such other relevant policies and proposals as might affect its development, operation or decommissioning and in respect of which there is information in the public domain. In that regard, the ExA observes that effects of the cumulative delivery of the Proposed Development with the other East Anglia development on the transmission connection site near Friston are so substantially adverse that utmost care will be required in the consideration of any amendments or additions to those elements of the Proposed Development in this location. This ExA does not seek to fetter the discretion of future decision-makers about additional development proposals at this location. However, it can and does set out a strong view that the most substantial and innovative attention to siting, scale, appearance and the mitigation of adverse effects within design processes would be required if anything but immaterial additional development were to be proposed in this location.
28.4.6. In relation to this conclusion, the ExA observes that particular regard needs to be had at this location to flood and drainage effects (where additional impermeable surfaces within the existing development site have the potential to affect the proposed flood management solution), to landscape and visual impacts and to impacts on the historic built environment, should these arise from additional development proposals in the future.
28.4.7. The ExA concludes overall that, for the reasons set out in the preceding chapters and summarised above, the SoS should decide to grant development consent.
28.4.8. The ExA acknowledges that this is a conclusion that may well meet with considerable dismay amongst many local residents and businesses who became IPs and contributed positively and passionately to the Examination across a broad range of matters and issues. To them the ExA observes that their concerns are real and that the planning system provided a table to which they could be brought. However, highly weighty global and national considerations about the need for large and timely additional renewable energy generating capacity to meet need and to materially assist in the mitigation of adverse climate effects due to carbon emissions have to be accorded their due place in the planning balance. In the judgment of the ExA, these matters must tip a finely balanced equation in favour of the decision to grant development consent for the Proposed Development."
"27 The Secretary of State's Consideration of the Planning Balance
27.1 The ExA considered all the merits and disbenefits of the Proposed Development and concluded that in the planning balance, the case for development consent has been made and that the benefits of the Proposed Development would outweigh its adverse effects [ER 28.4.4]. The ExA judged that the benefits of the Proposed Development at the national scale, providing highly significant additional renewable energy generation capacity in scalar terms and in a timely manner to meet the need for such development (as identified in NPS EN-1), are sufficient to outweigh the negative impacts that have been identified in relation to the construction and operation of the Proposed Development at the local scale. In reaching this conclusion, the ExA had regard to the effect of the Proposed Development cumulatively with the East Anglia TWO development and with such other relevant policies and proposals as might affect its development, operation or decommissioning and in respect of which there is information in the public domain. The Secretary of State agrees with the ExA's overall conclusion on the case for development.
27.2 Because of the existence of three relevant NPSs, NPS EN-1, NPS EN-3, and NPS EN-5, the Secretary of State is required to determine this application against section 104 of the Planning Act 2008. Section 104(2) requires the Secretary of State to have regard to:
• any local impact report (within the meaning given by section 60(3)),
• any matters prescribed in relation to development of the description to which the application relates, and
• any other matters which the Secretary of State thinks are both important and relevant to the decision.
27.3 The Secretary of State acknowledges and adopts the substantial weight the ExA gives to the contribution to meeting the need for electricity generation demonstrated by NPS EN-1 and its significant contribution towards satisfying the need for offshore wind [ER 28.4.4]. He further notes that the ExA has identified that the Proposed Development would be consistent with the Climate Change Act 2008 (2050 Target Amendment) Order 2019 which amended the Climate Change Act 2008 to set a legally binding target of 100% below the 1990 baseline. The Secretary of State notes that the designated energy NPSs continue to form the basis for decision-making under the Planning Act 2008. The Secretary of State considers, therefore, that the ongoing need for the Proposed Development is established as it is in line with the national need for offshore wind as part of the transition to a low carbon economy, and that granting the Order would be compatible with the amendment to the Climate Change Act 2008.
27.4 After reviewing the ExA Report, the Secretary of State has reached the following conclusions on the weight of other individual topics to be taken forward into the planning balance: flooding & drainage - high negative weighting; landscapes & visual amenity - medium negative weighting; onshore historic environment - medium negative weighting; seascapes - neutral weighting; onshore ecology - low negative weighting; coastal processes – neutral weighting; onshore water quality & resources; noise and vibration - medium negative weighting; air quality, light pollution, and impacts on human health - low negative weighting; transport & traffic - medium negative weighting; socio economic effects onshore – medium positive weighting; land use effects - medium negative weighting; offshore ornithology - medium negative weighting; marine mammals - low negative weighting; other offshore biodiversity - low negative weighting; marine physical effects & water quality - low negative weighting; offshore historic environment - low negative weighting; offshore socio-economic & other effects - neutral weighting; good design - low negative weighting; other overarching matters – neutral weighting.
27.5 Following his consideration of the various submissions relating to the potential for the OTNR to provide an alternative onshore grid connection for the Proposed Development (see paragraphs 3.13 to 3.19 above), the Secretary of State has decided to accord limited weight to the OTNR against granting the Proposed Development.
27.6 The Secretary of State has considered all the merits and disbenefits of the Proposed Development and concluded that, on balance, the benefits of the Proposed Development outweigh its negative impacts.
27.7 For the reasons given in this letter, the Secretary of State considers that there is a strong case for granting development consent for the East Anglia ONE North Offshore Wind Farm. Given the national need for the development, as set out in the relevant NPSs, the Secretary of State does not believe that this is outweighed by the Proposed Development's potential adverse impacts, as mitigated by the proposed terms of the Order.
27.8 The Secretary of State has also considered the proposal supported by multiple interested parties that there should be a split decision or partial consent in respect to proposed onshore and offshore development, but after careful consideration agrees with the ExA's position that the East Anglia ONE North and East Anglia TWO developments are entitled to be evaluated under the policy framework that is in place rather than the prospect of a new one, and that the great weight to be accorded to delivering substantial and timely carbon and climate benefits also weighs in favour of not taking split decisions driven by other elements of further possible policy changes.
27.9 The Secretary of State has therefore decided to accept the ExA's recommendation to make the Order granting development consent [ER 28.4.7] to include modifications set out below in section 29 below. In reaching this decision, the Secretary of State confirms regard has been given to the ExA's Report, the joint LIR submitted by East Suffolk Council and Suffolk County Council, the NPSs, and to all other matters which are considered important and relevant to the Secretary of State's decision as required by section 104 of the Planning Act 2008. The Secretary of State confirms for the purposes of regulation 3(2) of the ExA Planning (Environmental Impact Assessment) Regulations 2017 that the environmental information as defined in regulation 2(1) of those Regulations has been taken into consideration."
Statutory and policy framework
Planning Act 2008
"104 Decisions in cases where national policy statement has effect
(1) This section applies in relation to an application for an order granting development consent if a national policy statement has effect in relation to development of the description to which the application relates.
(2) In deciding the application the Secretary of State must have regard to—
(a) any national policy statement which has effect in relation to development of the description to which the application relates (a "relevant national policy statement"),
(aa) the appropriate marine policy documents (if any), determined in accordance with section 59 of the Marine and Coastal Access Act 2009,
(b) any local impact report (within the meaning given by section 60(3)) submitted to the Secretary of State before the deadline specified in a notice under section 60(2),
(c) any matters prescribed in relation to development of the description to which the application relates, and
(d) any other matters which the Secretary of State thinks are both important and relevant to the Secretary of State's decision.
(3) The Secretary of State must decide the application in accordance with any relevant national policy statement, except to the extent that one or more of subsections (4) to (8) applies.
(4) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the United Kingdom being in breach of any of its international obligations.
(5) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would lead to the Secretary of State being in breach of any duty imposed on the Secretary of State by or under any enactment.
(6) This subsection applies if the Secretary of State is satisfied that deciding the application in accordance with any relevant national policy statement would be unlawful by virtue of any enactment.
(7) This subsection applies if the Secretary of State is satisfied that the adverse impact of the proposed development would outweigh its benefits.
(8) This subsection applies if the Secretary of State is satisfied that any condition prescribed for deciding an application otherwise than in accordance with a national policy statement is met.
(9) For the avoidance of doubt, the fact that any relevant national policy statement identifies a location as suitable (or potentially suitable) for a particular description of development does not prevent one or more of subsections (4) to (8) from applying."
National Policy Statements
"19. The court's general approach to the interpretation of planning policy is well established and clear (see the decision of the Supreme Court in Tesco Stores Ltd v Dundee City Council (Asda Stores Ltd intervening) [2012] UKSC 13; [2012] PTSR 983, in particular the judgment of Lord Reed JSC at paras 17–19). The same approach applies both to development plan policy and statements of government policy (see the judgment of Lord Carnwath in Suffolk Coastal District Council v Hopkins Homes Ltd and Richborough Estates Partnership LLP v Cheshire East Borough Council [2017] UKSC 37; [2017] 1 WLR 1865 at [22]–[26]). Statements of policy are to be interpreted objectively in accordance with the language used, read in its proper context (see para 18 of Lord Reed's judgment in Tesco Stores v Dundee City Council). The author of a planning policy is not free to interpret the policy so as to give it whatever meaning he might choose in a particular case. The interpretation of planning policy is, in the end, a matter for the court (see para 18 of Lord Reed's judgment in Tesco Stores v Dundee City Council). But the role of the court should not be overstated. Even when dispute arises over the interpretation of policy, it may not be decisive in the outcome of the proceedings. It is always important to distinguish issues of the interpretation of policy, which are appropriate for judicial analysis, from issues of planning judgment in the application of that policy, which are for the decision-maker, whose exercise of planning judgment is subject only to review on public law grounds (see paras 24–26 of Lord Carnwath's judgment in Suffolk Coastal District Council). It is not suggested that those basic principles are inapplicable to the NPS—notwithstanding the particular statutory framework within which it was prepared and is to be used in decision-making."
National Planning Policy Framework and Planning Practice Guidance
Ground 1: Flood risk (as amended)
Claimant's submissions
Defendant and Applicants' submissions
Conclusions
Policies and guidance
"5.7.9 In determining an application for development consent, the IPC should be satisfied that where relevant:
• the application is supported by an appropriate FRA;
• the Sequential Test has been applied as part of site selection;
• a sequential approach has been applied at the site level to minimise risk by directing the most vulnerable uses to areas of lowest flood risk;
• the proposal is in line with any relevant national and local flood risk management strategy [Footnote 114: As provided for in section 9(1) of the Flood and Water Management Act 2010.];
• priority has been given to the use of sustainable drainage systems (SuDs) (as required in the next paragraph on National Standards); and
• in flood risk areas the project is appropriately flood resilient and resistant, including safe access and escape routes where required, and that any residual risk can be safely managed over the lifetime of the development.
……
5.7.12 The IPC should not consent development in Flood Zone 2 in England ….unless it is satisfied that the sequential test requirements have been met. It should not consent development in Flood Zone 3 or Zone C unless it is satisfied that the Sequential and Exception Test requirements have been met….."
"The Sequential Test
5.7.13 Preference should be given to locating projects in Flood Zone 1 in England ….If there is no reasonably available site in Flood Zone 1 ….. then projects can be located in Flood Zone 2 ….. If there is no reasonably available site in Flood Zones 1 or 2 then nationally significant energy infrastructure projects can be located in Flood Zone 3 or Zone C subject to the Exception Test. Consideration of alternative sites should take account of the policy on alternatives set out in Section 4.4 above."
"Planning and flood risk
159. Inappropriate development in areas at risk of flooding should be avoided by directing development away from areas at highest risk (whether existing or future). Where development is necessary in such areas, the development should be made safe for its lifetime without increasing flood risk elsewhere.
160. Strategic policies should be informed by a strategic flood risk assessment, and should manage flood risk from all sources. They should consider cumulative impacts in, or affecting, local areas susceptible to flooding, and take account of advice from the Environment Agency and other relevant flood risk management authorities, such as lead local flood authorities and internal drainage boards.
161. All plans should apply a sequential, risk-based approach to the location of development - taking into account all sources of flood risk and the current and future impacts of climate change - so as to avoid, where possible, flood risk to people and property. They should do this, and manage any residual risk, by:
a) applying the sequential test and then, if necessary, the exception test as set out below;
b) safeguarding land from development that is required, or likely to be required, for current or future flood management;
c) using opportunities provided by new development and improvements in green and other infrastructure to reduce the causes and impacts of flooding, ... making as much use as possible of natural flood management techniques as part of an integrated approach to flood risk management); and
d) where climate change is expected to increase flood risk so that some existing development may not be sustainable in the long-term, seeking opportunities to relocate development, including housing, to more sustainable locations.
162. The aim of the sequential test is to steer new development to areas with the lowest risk of flooding from any source. Development should not be allocated or permitted if there are reasonably available sites appropriate for the proposed development in areas with a lower risk of flooding. The strategic flood risk assessment will provide the basis for applying this test. The sequential approach should be used in areas known to be at risk now or in the future from any form of flooding.
163. If it is not possible for development to be located in areas with a lower risk of flooding (taking into account wider sustainable development objectives), the exception test may have to be applied. The need for the exception test will depend on the potential vulnerability of the site and of the development proposed, in line with the Flood Risk Vulnerability Classification set out in Annex 3.
164. The application of the exception test should be informed by a strategic or site-specific flood risk assessment, depending on whether it is being applied during plan production or at the application stage. To pass the exception test it should be demonstrated that:
a) the development would provide wider sustainability benefits to the community that outweigh the flood risk; and
b) the development will be safe for its lifetime taking account of the vulnerability of its users, without increasing flood risk elsewhere, and, where possible, will reduce flood risk overall.
165. Both elements of the exception test should be satisfied for development to be allocated or permitted.
166. Where planning applications come forward on sites allocated in the development plan through the sequential test, applicants need not apply the sequential test again. However, the exception test may need to be reapplied if relevant aspects of the proposal had not been considered when the test was applied at the plan-making stage, or if more recent information about existing or potential flood risk should be taken into account.
167. When determining any planning applications, local planning authorities should ensure that flood risk is not increased elsewhere. Where appropriate, applications should be supported by a site-specific flood-risk assessment [Footnote 55: A site-specific flood risk assessment should be provided for all development in Flood Zones 2 and 3. In Flood Zone 1, an assessment should accompany all proposals involving: sites of 1 hectare or more; land which has been identified by the Environment Agency as having critical drainage problems; land identified in a strategic flood risk assessment as being at increased flood risk in future; or land that may be subject to other sources of flooding, where its development would introduce a more vulnerable use.]. Development should only be allowed in areas at risk of flooding where, in the light of this assessment (and the sequential and exception tests, as applicable) it can be demonstrated that:
a) within the site, the most vulnerable development is located in areas of lowest flood risk, unless there are overriding reasons to prefer a different location;
b) the development is appropriately flood resistant and resilient such that, in the event of a flood, it could be quickly brought back into use without significant refurbishment;
c) it incorporates sustainable drainage systems, unless there is clear evidence that this would be inappropriate;
d) any residual risk can be safely managed; and
e) safe access and escape routes are included where appropriate, as part of an agreed emergency plan.
168. Applications for some minor development and changes of use [Footnote 56: This includes householder development, small non-residential extensions (with a footprint of less than 250m2 ) and changes of use; except for changes of use to a caravan, camping or chalet site, or to a mobile home or park home site, where the sequential and exception tests should be applied as appropriate.] should not be subject to the sequential or exception tests but should still meet the requirements for site-specific flood risk assessments set out in footnote 55.
169. Major developments should incorporate sustainable drainage systems unless there is clear evidence that this would be inappropriate. The systems used should:
a) take account of advice from the lead local flood authority;
b) have appropriate proposed minimum operational standards;
c) have maintenance arrangements in place to ensure an acceptable standard of operation for the lifetime of the development; and
d) where possible, provide multifunctional benefits."
"The aim of the Sequential Test
What is the aim of the Sequential Test for the location of development?
The Sequential Test ensures that a sequential approach is followed to steer new development to areas with the lowest probability of flooding. The flood zones as refined in the Strategic Flood Risk Assessment for the area provide the basis for applying the Test. The aim is to steer new development to Flood Zone 1 (areas with a low probability of river or sea flooding). Where there are no reasonably available sites in Flood Zone 1, local planning authorities in their decision making should take into account the flood risk vulnerability of land uses and consider reasonably available sites in Flood Zone 2 (areas with a medium probability of river or sea flooding), applying the Exception Test if required. Only where there are no reasonably available sites in Flood Zones 1 or 2 should the suitability of sites in Flood Zone 3 (areas with a high probability of river or sea flooding) be considered, taking into account the flood risk vulnerability of land uses and applying the Exception Test if required.
….
Within each flood zone, surface water and other sources of flooding also need to be taken into account in applying the sequential approach to the location of development.
Paragraph: 019 Reference ID: 7-019-20140306
Revision date: 06 03 2014"
"Applying the Sequential Test to individual planning applications
How should the Sequential Test be applied to planning applications?
See advice on the sequential approach to development and the aim of the sequential test.
The Sequential Test does not need to be applied for individual developments on sites which have been allocated in development plans through the Sequential Test, or for applications for minor development or change of use (except for a change of use to a caravan, camping or chalet site, or to a mobile home or park home site).
Nor should it normally be necessary to apply the Sequential Test to development proposals in Flood Zone 1 (land with a low probability of flooding from rivers or the sea), unless the Strategic Flood Risk Assessment for the area, or other more recent information, indicates there may be flooding issues now or in the future (for example, through the impact of climate change).
For individual planning applications where there has been no sequential testing of the allocations in the development plan, or where the use of the site being proposed is not in accordance with the development plan, the area to apply the Sequential Test across will be defined by local circumstances relating to the catchment area for the type of development proposed. For some developments this may be clear, for example, the catchment area for a school. In other cases it may be identified from other Local Plan policies, such as the need for affordable housing within a town centre, or a specific area identified for regeneration. For example, where there are large areas in Flood Zones 2 and 3 (medium to high probability of flooding) and development is needed in those areas to sustain the existing community, sites outside them are unlikely to provide reasonable alternatives.
When applying the Sequential Test, a pragmatic approach on the availability of alternatives should be taken. For example, in considering planning applications for extensions to existing business premises it might be impractical to suggest that there are more suitable alternative locations for that development elsewhere. For nationally or regionally important infrastructure the area of search to which the Sequential Test could be applied will be wider than the local planning authority boundary.
Any development proposal should take into account the likelihood of flooding from other sources, as well as from rivers and the sea. The sequential approach to locating development in areas at lower flood risk should be applied to all sources of flooding, including development in an area which has critical drainage problems, as notified to the local planning authority by the Environment Agency, and where the proposed location of the development would increase flood risk elsewhere.
See also advice on who is responsible for deciding whether an application passes the Sequential Test and further advice on the Sequential Test process available from the Environment Agency (flood risk standing advice).
Paragraph: 033 Reference ID: 7-033-20140306
Revision date: 06 03 2014"
"Who is responsible for deciding whether an application passes the Sequential Test?
It is for local planning authorities, taking advice from the Environment Agency as appropriate, to consider the extent to which Sequential Test considerations have been satisfied, taking into account the particular circumstances in any given case. The developer should justify with evidence to the local planning authority what area of search has been used when making the application. Ultimately the local planning authority needs to be satisfied in all cases that the proposed development would be safe and not lead to increased flood risk elsewhere.
Paragraph: 034 Reference ID: 7-034-20140306
Revision date: 06 03 2014"
The decisions
"Updates to the National Planning Policy Framework: Post Examination Consultation
4.27 The Secretary of State consulted on the issue of updates to the NPPF on 2 November 2021 and 20 December 2021, the key responses are summarised below:
• SCC (the Lead Local Flood Authority) – the changes to the NPPF would require the Applicant to undertake a Sequential Test, and if necessary, an Exception Test. However, SCC acknowledge that as the PPG has not been updated, it is not clear how the Sequential and Exception Tests would be applied.
• ESC – states that the reference in the updated NPPF has the potential to have important implications for the East Anglia ONE North and East Anglia TWO projects. However, they also acknowledge that as the PPG has not been updated, it is not clear how the Sequential and Exception Tests would be applied.
• SASES – consider that it is clear from the Applicant's submissions that surface water and ground water were not taken into account during the site selection process and, consequently, the Sequential test was not properly applied. Additionally, SASES consider that the updates to the NPPF do not impose any new policy requirement but rather reinforce the existing requirements. SASES also reiterated that they considered the infiltration testing conducted by the Applicant was insufficient and had concerns about the Applicant's approach to applying the Sequential Test. Overall, SASES considered that because of the defects of the Applicant's approach, that policy requirements had not been met.
• The Applicant – acknowledges that the updated NPPF is more explicit in the use of the term 'any source' of flooding but note that the criteria for the assessment and application of the Sequential Test remains unchanged, and that the PPG does not provide any criteria for the assessment of suitability of a location to determine whether a development is appropriate or not. The Applicant also highlighted:
(i) they have considered all sources of flooding in the design of the Proposed Development;
(ii) the substation site and National Grid infrastructure have been located in an area at low risk of surface water flooding;
(iii) appropriate mitigation measures have been adopted to address any remaining surface water flood risk concerns;
(iv) SCC had already given surface water flooding equal weighting when reviewing the Proposed Development's assessment of flood risk throughout the examination;
(v) that the emphasis in the updated NPPF to move away from hard engineered flood solutions is not considered by the Applicant to be a fundamental change that would alter their proposed drainage strategy or adoption of SuDS measures;
(vi) that the extensive landscape planting proposed would reduce the speed of surface water runoff compared to that currently experienced, as well as soil erosion and silt levels in runoff;
(vii) modelling undertaken for the Friston Surface Water Flood Study15 confirms that surface water flooding within Friston primarily results from surface water flow from a number of locations unrelated to the substation site; and
(viii) by attenuating surface water and ensuring a controlled discharge rate from the site there is no increase in flood risk to the surrounding area, specifically Friston."
"4.28 The Secretary of State notes that all sources of flooding have been considered by the Applicant in the design of the Proposed Development, he also notes the surface water mitigation measures which the Applicant has proposed to address flood risk concerns. Furthermore, the Secretary of State has considered all the consultation responses relevant to the NPPF updates and, noting that the guidance on how the Sequential Test should be applied in respect of all sources of flooding has not been updated, is satisfied that the Applicant has (as it is currently defined) applied the Sequential Test as part of site selection. As such, the Secretary of State considers that the FRA is appropriate for the Application."
"23. While the Applicants have considered all sources of flooding, in the absence of any criteria as to how this should be implemented, they have sought to address the potential risk from surface water flooding by locating the onshore substations and National Grid infrastructure in an area at low risk of surface water flooding, and by adopting appropriate mitigation measures within the design to address any remaining surface water flood risk concerns.
24. In considering the revised wording it is also noted that SCC (as the LLFA) had already given surface water flooding equal weighting when reviewing the Projects' assessment of flood risk throughout the DCO examinations and prior to the publication of the updated NPPF.
25. All development sites have an element of potential surface water flood risk and any development that changes the surface of a site so that it is more impermeable will need to address this matter through the application of appropriate mitigation measures. There is greater emphasis in the updated NPPF on "…making as much use as possible of natural flood management techniques as part of an integrated approach to flood risk management…", which is part of the shift in focus away from hard engineering solutions. However, this is not considered to be a fundamental change that would alter the Projects' Drainage Strategy or the adoption of the proposed SuDS measures. It should also be noted that the extensive landscape planting being proposed as part of the Projects' landscape mitigation strategy would reduce the speed of surface water runoff compared to that currently experienced, as well as soil erosion and silt levels in runoff. On this basis, the landscape mitigation strategy will afford opportunities for further flood mitigation over and above that already included within the concept drainage design.
26. Regarding surface water flooding, the onshore substation and National Grid infrastructure locations were reviewed against the Environment Agency's surface water flood risk mapping and identified as being predominantly located in an area at very low risk of surface water flooding. Furthermore, the National Grid substation location was selected in full cognisance of the presence of a shallow surface water flow route (comprising approximately 4cm of water depth during a 1 in 100 year storm event), noting that such features can be diverted, and their continued conveyance ensured using well established and proven techniques. A commitment to this is made within the OODMP (REP13-020), along with a commitment to offset any reduction in volume relating to other existing surface water features in the vicinity of the substation locations.
27. Additionally, a review of the modelling undertaken for the Friston Surface Water Flood Study (BMT, 2020) further confirmed that the surface water conveyance routes onsite do not constitute a significant risk to the onshore substations or National Grid infrastructure, and that the risk falls well below the lowest hazard."
Ground 2: Heritage assets
Claimant's submissions
i) he substantively adopted the ExA's reasoning which was based on an unlawful interpretation of the Decisions Regulations 2010, which consequently infected the Defendant's analysis of heritage harm; and/or
ii) while the Defendant purports to give heritage harm "considerable importance and weight", such weight was not reflected in the overall planning balance, which follows the ExA's analysis, and which unlawfully attributed only "medium" weight, contrary to the legal requirement.
Defendant's and Applicants' submissions
Conclusions
The tests to be applied
"(1) When deciding an application which affects a listed building or its setting, the Secretary of State must have regard to the desirability of preserving the listed building or its setting or any features of special architectural or historic interest which it possesses.
(2) When deciding an application relating to a conservation area, the Secretary of State must have regard to the desirability of preserving or enhancing the character or appearance of that area.
(3) When deciding an application for development consent which affects or is likely to affect a scheduled monument or its setting, the Secretary of State must have regard to the desirability of preserving the scheduled monument or its setting."
"5.8.13 The [Secretary of State] should take into account the desirability of sustaining and, where appropriate, enhancing the significance of heritage assets, the contribution of their settings and the positive contribution they can make to sustainable communities and economic vitality …
5.8.14 There should be a presumption in favour of the conservation of designated heritage assets and the more significant the designated heritage asset, the greater the presumption in favour of its conservation should be…"
"66. General duty as respects listed buildings in exercise of planning functions
(1) In considering whether to grant planning permission for development which affects a listed building or its setting, the local planning authority or, as the case may be, the Secretary of State shall have special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest which it possesses.
(2) Without prejudice to section 72, in the exercise of the powers of appropriation, disposal and development (including redevelopment) conferred by the provisions of section 232, 233 and 235(1) of the principal Act, a local authority shall have regard to the desirability of preserving features of special architectural or historic interest, and in particular, listed buildings."
"199. When considering the impact of a proposed development on the significance of a designated heritage asset, great weight should be given to the asset's conservation (and the more important the asset, the greater the weight should be). This is irrespective of whether any potential harm amounts to substantial harm, total loss or less than substantial harm to its significance."
"42. This first ground of challenge is that the Inspector made an error of law in misinterpreting his duty with respect to the Broads. Under section 17A of the 1988 Act, in exercising or performing any functions in relation to, or so as to affect, land in the Broads, the Secretary of State (and hence the Inspector)
"shall have regard to the purposes of—
(a) conserving and enhancing the natural beauty, wildlife and cultural heritage of the Broads;
(b) promoting opportunities for the understanding and enjoyment of the special qualities of the Broads by the public; and
(c) protecting the interests of navigation."
…
45. Mr Harwood submitted that the Inspector had fallen into the same trap as had occurred in East Northamptonshire DC v Secretary of State for Communities and Local Government [2014] EWCA Civ 137; [2014] 1 P & CR 22. That was a case involving a listed building. Section 66(1) of the Planning (Listed Buildings and Conservation Areas) Act 1990 provides for the general duty as respects granting planning permission for development which affects a listed building or its setting: the planning authority must "have special regard to the desirability of preserving the building or its setting or any features of special architectural or historic interest which it possesses." In that case it was common ground between the parties that "preserving" meant doing no harm: [16]. That did not mean that no harm could be done: however, there was a presumption against the grant of planning permission and considerable importance and weight had to be given to the desirability of preserving the setting of heritage assets when balancing the proposal against other material considerations: [27]-[28]. The planning inspector in that case had not done that.
46. In my judgment the East Northamptonshire DC case is not directly applicable in this case since the 1988 Act requires the planning authority not to have "special regard" to the matter as does section 66(1), but simply to have regard to it. In this respect the 1988 Act follows other planning legislation, for example, the Town and Country Planning Act 1990, s. 70(2); the National Parks and Access to the Countryside Act 1949, s. 11A(2); and the National Environment and Rural Communities Act 2006, s. 40(1). To have regard to a matter means simply that that matter must be specifically considered, not that it must be given greater weight than other matters, certainly not that it is some sort of trump card. It does not impose a presumption in favour of particular result or a duty to achieve that result. In the circumstances of the case other matters may outweigh it in the balance of decision-making. On careful consideration the matter may be given little, if any, weight."
"5.9.21 When considering the impact of a proposed development on the significance of a designated heritage asset, the Secretary of State should give great weight to the asset's conservation. The more important the asset, the greater the weight should be. This is irrespective of whether any potential harm amounts to substantial harm, total loss, or less than substantial harm to its significance."
Decision
"8.5.9. In particular, the phrase 'great weight' which appears within the NPPF does not appear in NPS EN-1. This is at odds with later NPSs for different sectors, such as for instance, the Airports NPS (2018) or the Geological Disposal Infrastructure NPS (2019). Such wording complies with the findings of the Barnwell Manor judgement in 2014 (referred to by SASES [REP1-366]) which states that any harm to a heritage asset must be given 'considerable importance and weight'.
8.5.10. The Applicant notes in its response to ExQ1.8.1 that the NPPF does not contain specific policies for NSIPs, and that these are determined in accordance with the Planning Act 2008. It notes that the policy of 'great weight' set out in the NPPF is not reflected in NPS EN-1 and that the test of having 'special regard' [to the desirability of preserving a listed building or its setting or any features of special architectural or historic interest which it possesses] as set out in section 66 of the Planning (Listed Buildings and Conservation areas) Act 1990 is reduced to having 'regard' through regulation 3 of the Infrastructure Planning (Decisions) Regulations 2010.
8.5.11. The ExA agree with the Applicant's reasoning and interpretation of the law. However, it also considers that the 'direction of travel' of policy including the later wording of the NPPF and the policy of 'great weight' to be important and relevant, noting the Barnwell decision and the text of later NPSs in this regard."
"• The ExA has had regard to the desirability of preserving the settings of the identified Listed Buildings and any features of special architectural or historic interest which they possess. Harmful impacts on the significance of various designated heritage assets have been identified, as well as to a non-designated heritage asset. NPS EN-1 requires such harm to be weighed against the public benefits of development – this assessment is carried out in Chapter 28, the Planning Balance.
• Harm caused to the onshore historic environment has a medium negative weighting to be carried forward in the planning balance.
• Cumulative effects with the other East Anglia application increase this harm.
• Medium levels of harm are found as opposed to high due to the fact that harm to heritage assets has been found to be less than substantial. However, for several heritage assets the harm within this scale is at the higher end (including to a Grade II* listed building) and there would be substantial harm to a non-designated heritage asset. The ExA consider therefore that harm within the medium level of harm is at the top end of the scale.
……."
"6.30 Overall, the ExA concluded that harm caused to the onshore historic environment had a medium negative weighting to be carried forward in the planning balance. The Secretary of State is aware that where there is an identified harm to a heritage asset he must give that harm considerable importance and weight and he does so in this case. Overall, the Secretary of State agrees with the ExA's conclusions on Onshore Historic Environment and in light of the public benefit of the Proposed Development is of the view that onshore historical environment matters do not provide a justification not to make the Order."
Ground 3: Noise
Claimant's submissions
i) failed to take into account that his conclusions on noise necessarily entailed a conflict with paragraph 5.11.9 of NPS EN-1;
ii) relied on the imposition of a requirement which was in all the circumstances unreasonable in that it had not been shown to be workable; and/or
iii) failed to take into account the impact of noise from switchgear/circuit breakers in the National Grid substation.
Sub-paragraph (i)
Sub-paragraph (ii)
Sub-paragraph (iii)
Defendant and Applicants' submissions
Sub-paragraph (i)
Sub-paragraph (ii)
Sub-paragraph (iii)
Conclusions
Sub-paragraph (i)
"5.11.9 The IPC should not grant development consent unless it is satisfied that the proposals will meet the following aims:
• avoid significant adverse impacts on health and quality of life from noise;
• mitigate and minimise other adverse impacts on health and quality of life from noise; and
• where possible, contribute to improvements to health and quality of life through the effective management and control of noise.
5.11.10 When preparing the development consent order, the IPC should consider including measurable requirements or specifying the mitigation measures to be put in place to ensure that noise levels do not exceed any limits specified in the development consent."
i) In respect of operational noise, it concluded:
"the Applicant's commitment to adopt Best Practicable Means (BPM) and the reduced operational noise limits now specified in Requirement 27 in the dDCO are consistent with national policy" (ER 13.2.116)
"… notwithstanding the differences of opinion, the ExA is satisfied that the Requirements in the dDCO must nevertheless be met, and consequently the ExA concludes that operational noise impacts can be satisfactorily mitigated." (ER 13.2.118)
ii) In respect of construction noise it concluded:
"there are no significant outstanding issues in respect of construction noise which are not capable of satisfactory mitigation through Requirement 22 in the final version of the dDCO" (ER 13.2.117).
Sub-paragraph (ii)
"The IPC should only impose requirements in relation to development consent that are necessary, relevant to planning, relevant to the development to be consented, enforceable, precise, and reasonable in all other respects. The IPC should take into account the guidance in Circular 11/95, as revised, on "The Use of Conditions in Planning Permissions" or any successor to it."
"SASES then go on to make the claim that the EA1 substation is not directly comparable with those proposed for EA1N or EA2 and infer that the noise monitoring report is of little or no relevance. Again, this position lacks balance. Of course, there are differences but there are also similarities between EA1 and the proposed substations. The findings of the noise monitoring report for EA1 provides a useful indication of the likelihood of the presence of tones associated with substations incorporating modern technology.
In my opinion, the Examining Authority can be confident that the Projects can be designed to avoid any highly perceptible or clearly perceptible tones and it is likely that any tones can be avoided altogether.
If any tones are perceptible at the receiver locations, it would attract a correction in accordance with the BS4142 method and this would be accounted for in the proposed noise limit. This will drive the designers to minimise tonal features or eliminate them altogether. As explained earlier, this is a perfectly normal and acceptable way of controlling noise from commercial and industrial noise. Standing waves and interference patterns are also raised as a potential issue. These points, no doubt, are intended to cast doubt on the confidence that the Examining Authority can have in relation to these types of features. I agree in as much that this effect cannot be dismissed as a possibility, but it is highly improbable in my view. This is a matter that can be adequately addressed during the detailed design of the substations. …"
Sub-paragraph (iii)
"Operational impacts were assessed using BS4142. The dominant operational noise sources are substation transformers, shunt reactors and rotating plant such as transformer coolers. The National Grid infrastructure does not contain any of these, so operational noise would come from switchgear and control systems, with noise levels imperceptible at the nearest NSR [noise sensitive receptor]. …"
"37. As the predicted noise level generated by the switchgear is below both the prevailing background and the maximum noise levels currently experienced at the agreed noise sensitive locations above, and due to the low occurrence of this item of equipment being operated, this item of National Grid Infrastructure has not been included or assessed further in the updated noise model."
Ground 4: Generating capacity
Claimant's submissions
Defendant and Applicants' submissions
Conclusions
"an offshore wind turbine generating station with a gross electrical output capacity of over 100MW comprising up to 67 wind turbine generators … situated within the area shown on the works plans."
i) The Applicants' intention was "to build out both projects to their maximum capacity" and they "have engaged extensively with the turbine and grid supply chains on this basis" (Applicants' Comments on the Claimant's Deadline 11 Submissions).
ii) It was important to retain some element of flexibility as to the ultimate generating capacity to be built, having regard to the way in which offshore windfarms are financed through the Contract for Difference ("CfD") Auction process, and an example was given of how the market mechanism can operate so as to require individual projects to make use of the flexibility within DCOs as to how much generating capacity to build out at any one time (Applicants' Comments on the ExA's Commentary on the draft DCO dated 24 February 2021).
iii) The market mechanism nevertheless operates so as to drive delivery towards the higher end of the transmission capacity created in order to achieve the price reductions reported in the Energy White Paper (the Applicants explained the economic factors that lie behind that effect) (Applicants' Comments on the ExA's Commentary on the draft DCO dated 24 February 2021).
iv) The factors that lay behind previous significant reductions in capacity were explained as being the "considerable uncertainty regarding both turbine and grid technologies" which had existed at that earlier stage, but this "is no longer the case" (Applicants' Comments on the Claimant's Deadline 11 Submissions).
v) The increased Government targets for the deployment of offshore generating capacity to 40GW by 2030 was a clear signal to the market that there would be an acceleration of opportunity and that the future CfD Auction rounds were likely to increase in capacity (Applicants' Comments on the ExA's Commentary on the draft DCO dated 24 February 2021).
vi) A significant reduction in capacity below that planned would make the proposed development unviable, essentially because the income generated by the station would not be sufficient to justify the costs incurred in developing and operating the assets (Post-examination submissions to the Defendant dated 31 January 2022).
"5.2.10 In this context, the Proposed Development provides a substantial volume of renewable electricity generating capacity meeting a materially significant volume of projected national need and targets. In scalar terms, ES Chapter 2 [APP-050] indicatively calculates that, if developed, East Anglia ONE North would deliver some 2.5TWh/ year of effectively zero carbon renewable electricity. The Applicant's calculations (section 2.2.2 of [APP-050] indicate that the Proposed Development has the potential to meet approximately 3.5% of the UK cumulative deployment target for 2030, although the ExA does not adopt a precise percentage figure for a number of reasons…."
…..
5.2.13 It is also important to note that whilst the ES describes the effects on the receiving environment offshore of proposed generating station, it does not commit to a maximum renewable electricity yield for the Proposed Development. The Application Form [APP-002] identifies that the Proposed Development is expected to have a generating capacity of over 100MW (essential if the development is to be considered an NSIP under PA2008) but reserves adaptability around precise selection of turbine blades and generators, with a view to maximising the installed generating capacity and yield within the expected market framework of a Contract for Difference (CfD) auction."
Ground 5: Cumulative effects
Claimant's submissions
i) The Defendant was required to consider the likely significant cumulative effects of the proposed development together with other projects. The Extension Appraisal contained information in respect of those effects which had been expressly required to be provided. Failing to take that information into account was a breach of the EIA Regulations, and irrational: see Pearce v Secretary of State for Business, Energy and Industrial Strategy [2022] Env LR 4.
ii) The ExA's reasoning for not considering that information was irrational. The ExA said that the information was "environmental information" and for that reason did not need to be taken into account. However, environmental information must be taken into account in deciding whether to grant development consent.
iii) The reasons given were inadequate. It appears that the information was disregarded simply because the Applicants did not wish to describe the document as a "Cumulative Impact Assessment". However, the information could only be disregarded if it was not relevant, and accordingly these reasons were plainly inadequate.
Defendant and Applicants' submissions
Conclusions
The EIA Regulations 2017 and case law
"21.— Consideration of whether development consent should be granted
(1) When deciding whether to make an order granting development consent for EIA development the Secretary of State must—
(a) examine the environmental information;
(b) reach a reasoned conclusion on the significant effects of the proposed development on the environment, taking into account the examination referred to in sub-paragraph (a) and, where appropriate, any supplementary examination considered necessary;
(c) integrate that conclusion into the decision as to whether an order is to be granted; and
(d) if an order is to be made, consider whether it is appropriate to impose monitoring measures.…"
""environmental information" means the environmental statement (or in the case of a subsequent application, the updated environmental statement), including any further information and any other information, any representations made by any body required by these Regulations to be invited to make representations and any representations duly made by any other person about the environmental effects of the development and of any associated development;
"environmental statement" has the meaning given by regulation 14;
…
"further information" means additional information which, in the view of the Examining authority, the Secretary of State or the relevant authority, is directly relevant to reaching a reasoned conclusion on the significant effects of the development on the environment and which it is necessary to include in an environmental statement or updated environmental statement in order for it to satisfy the requirements of regulation 14(2);
…
"any other information" means any other substantive information provided by the applicant in relation to the environmental statement or updated environmental statement;".
"14.— Environmental statements
(1) An application for an order granting development consent for EIA development must be accompanied by an environmental statement.
(2) An environmental statement is a statement which includes at least—
(a) a description of the proposed development comprising information on the site, design, size and other relevant features of the development;
(b) a description of the likely significant effects of the proposed development on the environment;
(c) a description of any features of the proposed development, or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;
(d) a description of the reasonable alternatives studied by the applicant, which are relevant to the proposed development and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the development on the environment;
(e) a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and
(f) any additional information specified in Schedule 4 relevant to the specific characteristics of the particular development or type of development and to the environmental features likely to be significantly affected.
(3) The environmental statement referred to in paragraph (1) must—
(a) where a scoping opinion has been adopted, be based on the most recent scoping opinion adopted (so far as the proposed development remains materially the same as the proposed development which was subject to that opinion);
(b) include the information reasonably required for reaching a reasoned conclusion on the significant effects of the development on the environment, taking into account current knowledge and methods of assessment; and
(c) be prepared, taking into account the results of any relevant UK environmental assessment, which is reasonably available to the applicant with a view to avoiding duplication of assessment.
…….."
"108 Although it is a matter of judgment for the decision-maker as to what are the environmental effects of a proposed project and whether they are significant, EIA legislation proceeds on the basis that he is required to evaluate and weigh those effects he considers to be significant (and any related mitigation) in the decision on whether to grant development consent (see e.g. Commission v Ireland [2011] Env LR 25)……"
109 The next issue is whether consideration of an environmental effect can be deferred to a subsequent consenting process. If, for example, the decision-maker has judged that a particular environmental effect is not significant, but further information and a subsequent approval is required, a decision to defer consideration and control of that matter, for example, under a condition imposed on a planning permission, would not breach EIA legislation (see R. v Rochdale MBC Ex p. Milne [2000] Env. L.R. 1).
110 But the real question in the present case is whether the evaluation of an environmental effect can be deferred if the decision-maker treats the effect as being significant, or does not disagree with the "environmental information" before him that it is significant? A range, or spectrum, of situations may arise, which I will not attempt to describe exhaustively.
…..
114 In order to comply with the principle identified in Commission v Ireland, and illustrated by Tew and Hardy, consideration of the details of a project defined in an outline consent may be deferred to a subsequent process of approval, provided that: (1) the likely significant effects of that project are evaluated at the outset by adequate environmental information encompassing: (a) the parameters within which the proposed development would be constructed and operated (a "Rochdale envelope"); and (b) the flexibility to be allowed by that consent; and (2) the ambit of the consent granted is defined by those parameters (see ex parte Milne at [90] and[93]–[95]). Although in Milne the local planning authority had deferred a decision on some matters of detail, it had not deferred a decision on any matter which was likely to have a significant effect (see Sullivan J at [126]), a test upon which the Court of Appeal lay emphasis when refusing permission to appeal (C/2000/2851 on 21 December 2000 at [38]). Those matters which were likely to have such an effect had been adequately evaluated at the outline stage.
115 Sullivan J also held in ex parte Milne that EIA legislation plainly envisages that the decision-maker on an application for development consent will consider the adequacy of the environmental information, including the ES. He held that what became reg.3(2) of the 2009 Regulations imposes an obligation on the decision-maker to have regard to a "particularly material consideration", namely the "environmental information". Accordingly, if the decision-maker considers that the information about significant environmental effects is too uncertain or is inadequate, he can either require more detail or refuse consent ([94]–[95] and[106]–[111]). I would simply add that the issue of whether such information is truly inadequate in a particular case may be affected by the definition of "environmental statement", which has regard to the information which the applicant can "reasonably be required to compile" (reg.2(1) of the 2009 Regulations—see [19] above).
116 The principle underlying Tew, Milne and Hardy can also be seen in R. (Larkfleet Ltd) v South Kesteven DC [2016] Env. L.R. 76 when dealing with significant cumulative impacts. There, the Court of Appeal held that the local planning authority had been entitled to grant planning permission for a link road on the basis that it did not form part of a single project comprising an urban extension development. The court held:
(i) What is in substance and reality a single project cannot be "salami-sliced" into smaller projects which fall below the relevant threshold so as to avoid EIA scrutiny ([35]).
(ii) But the mere fact that two sets of proposed works may have a cumulative effect on the environment does not make them a single project for the purposes of EIA. They may instead constitute two projects the cumulative effects of which must be assessed ([36]).
(iii) Because the scrutiny of the cumulative effects of two projects may involve less information than if they had been treated as one (e.g. where one project is brought forward before another), a planning authority should be astute to see that the developer has not sliced up a single project in order to make it easier to obtain planning permission for the first project and to get a foot in the door for the second ([37]).
(iv) Where two or more linked sets of works are properly regarded as separate projects, the objective of environmental protection is sufficiently secured by consideration of their cumulative effects in the EIA scrutiny of the first project, so far as that is reasonably possible, combined with subsequent EIA scrutiny of those impacts for the second and any subsequent projects ([38]).
(v) The ES for the first project should contain appropriate data on likely significant cumulative impacts arising from the first and second projects to the level which an applicant could reasonably be required to provide, having regard to current knowledge and methods of assessment ([29]–[30], [34] and [56]).
117 However, in some cases these principles may allow a decision-maker properly to defer the assessment of cumulative impacts arising from the subsequent development of a separate site not forming part of the same project. In R.(Littlewood) v Bassetlaw DC [2009] Env. L.R. 407 the court held that it had not been irrational for the local authority to grant consent for a freestanding project, without assessing cumulative impacts arising from future development of the remaining part of the site, where that development was inchoate, no proposals had been formulated and there was not any, or any adequate, information available on which a cumulative assessment could have been based (pp.413–415 in particular [32]).
118 I agree with Mr Westaway that the circumstances of the present case are clearly distinguishable from Littlewood. Here, the two projects are closely linked, site selection was based on a strategy of co-location and the second project has followed on from the first after a relatively short interval. They share a considerable amount of infrastructure, they have a common location for connection to the National Grid at Necton (the cumulative impacts of which are required to be evaluated) and the DCO for the first project authorises enabling works for the second. In the present case, proposals for the second project have been formulated and the promoter of the first project has put forward what it considered to be sufficient information onthe second to enable cumulative impacts to be evaluated in the DCO decision on the first. This information was before the defendant. I reject the attempt by NVL to draw any analogy with the circumstances in Littlewood (at [32]) or with those in Preston New Road (at [75]). In any event, the decision-maker in the present case, unsurprisingly, did not rely upon any reasoning of that kind in his decision letter (nor did the Examining Authority in the ExAR).
119 Instead, this case bears many similarities with the circumstances in Larkfleet. If anything, the ability to assess cumulative impacts from the two projects in the decision on the first project was much more straightforward here and the legal requirement to make an evaluation of those impacts decidedly stronger. First, the promoter carried out an assessment identifying significant cumulative effects at Necton and it is common ground that, for this purpose, essentially the same information was provided on the two projects (see e.g. [52]–[53] above). Secondly, there were strong links between the two projects which were directly relevant to this subject (see [118] above).
120 The effect of Directive 2011/92, the 2009 Regulations and the case law is that, as a matter of general principle, a decision-maker may not grant a development consent without, firstly, being satisfied that he has sufficient information to enable him to evaluate and weigh the likely significant environmental effects of the proposal (having regard to any constraints on what an applicant could reasonably be required to provide) and secondly, making that evaluation. These decisions are matters of judgment for the decision-maker, subject to review on Wednesbury grounds. Properly understood, the decision in Littlewood was no more than an application of this principle.
……"
"In the circumstances of this case, I am in no doubt that the defendant did act in breach of the 2009 Regulations by failing to evaluate the information before him on the cumulative impacts of the Vanguard and Boreas substation development, which had been assessed by NVL as likely to be significant adverse environmental effects. The defendant unlawfully deferred his evaluation of those effects simply because he considered the information on the development for connecting Boreas to the National Grid was "limited". The defendant did not go so far as to conclude that an evaluation of cumulative impacts could not be made on the information available, or that it was "inadequate" for that purpose. He did not give any properly reasoned conclusion on that aspect. I would add that because he did not address those matters, the defendant also failed to consider requiring NVL to provide any details he considered to be lacking, or whether NVL could not reasonably be required to provide them under the 2009 Regulations as part of the ES for Vanguard. It follows the defendant could not have lawfully decided not to evaluate the cumulative impacts at Necton in the decision he took on the application for the Vanguard DCO. For these reasons, as well as those given previously, the present circumstances are wholly unlike those in Littlewood."
Decision
"6. The Overarching National Policy Statement for Energy (EN-1) paragraph 4.2.5 states that "When considering cumulative effects, the ES should provide information on how the effects of the applicant's proposal would combine and interact with the effects of other development (including projects for which consent has been sought or granted, as well as those already in existence)".
7. Advice note seventeen: Cumulative effects assessment relevant to nationally significant infrastructure projects (AN17) sets out a cumulative assessment process with the stages of longlisting and shortlisting projects, information gathering and assessment.
8. Information gathering "requires the applicant to gather information on each of the 'other existing development and/or approved development' shortlisted at Stage 2. As part of the Stage 3 process the applicant is expected to compile detailed information, to inform the Stage 4 assessment. The information captured should include but not be limited to:
• Proposed design and location information;
• Proposed programme of construction, operation and decommissioning; and
• Environmental assessments that set out baseline data and effects arising from the 'other existing development and/or approved development".
9. The Applicants maintain that for the remaining projects being considered for potential connection in the vicinity of Leiston (Nautilus and Eurolink) little to none of the information specified in Advice Note seventeen is available."
"5.12 In response to significant concerns from a number of parties (including the Councils') about future projects, the Applicant submitted an Extension of National Grid Substation Appraisal [ExA Ref: REP8-074]. This Appraisal assessed the potential effects of extending the National Grid substation to accommodate future projects, including: Nautilus interconnector, EuroLink interconnector, North Falls and Five Estuaries offshore wind farms. However, the Appraisal states "it has been confirmed by both the proposed North Falls [ExA Ref: REP7-066] and Five Estuaries projects that they will not connect near Leiston."
5.13 The Secretary of State notes that the future projects considered are in the following stages of development:
• Nautilus interconnector – National Grid Ventures requested a section 35 direction under the Planning Act 2008 on 4 March 2019, the Secretary of State received further information from National Grid Ventures on 4 April 2019 and a direction was made by the Secretary of State on 29 April 2019. The application is expected to be submitted to the Planning Inspectorate Q2 2023.
• EuroLink interconnector - is a proposal by National Grid Ventures to build a HVDC transmission cable between the UK and the Netherlands. The capacity of the link will be 1.4 GW and the project is still in the very early stages of development. No information on this project has currently been submitted to the Planning Inspectorate or the Secretary of State.
5.14 Currently, the only documentation available on the Planning Inspectorate's website for the Nautilus interconnector project is the Section 35 Direction made by the Secretary of State for the proposed development to be treated as development for which development consent is required under the 2008 Act. The Eurolink interconnector project is earlier in the development consent process than Nautilus, and no documentation has been submitted to the Planning Inspectorate. Consequently, there is very limited environmental information available which would allow the Applicant to conduct a cumulative assessment. The Applicant's decision not to include these proposed projects in its cumulative effects assessment is also supported by the Planning Inspectorate's Advice Note Seventeen: Cumulative effects assessment relevant to nationally significant infrastructure projects. Paragraph 3.3.1 of the Advice Note lists the information required to conduct stage 4 of a cumulative effects assessment:
• proposed design and location information;
• proposed programme of construction, operation and decommissioning; and
• environmental assessments that set out baseline data and effects arising from the 'other existing development and/or approved development'.
5.15 As none of the above information was available prior to the close of the East Anglia ONE North and East Anglia TWO examination period for either the Nautilus or Eurolink projects, the Secretary of State is content that it was not necessary for the Applicant to include these proposed projects in its cumulative effects assessment. Further details of the Secretary of State's position on the inclusion of these projects in the Applicant's cumulative assessment can be found in paragraph 12.14 of this document.
5.16 The ExA [ER 7.6.1] concludes that:
"The extension of National Grid Substation Appraisal [ExA Ref: REP8-074] demonstrates a significant worsening of potential adverse effects for relevant VPs [Viewpoints] and for landscape character. The extension of the NG substation would intensify and worsen the effects of the Proposed Development on both the local landscape and on visual receptors. Such an effect would be added to in an unknown way by the provision of required surface water drainage."
……
5.22 In reaching the above conclusions the ExA has not considered the Extension of National Grid Substation Appraisal, noting that the Applicant acknowledges that the Appraisal is 'environmental information' and is not intended to comprise a Cumulative Impact Assessment.
5.23 The Secretary of State agrees with the ExA's conclusions on Landscape and Visual Amenity."
"Cumulative Impacts with the Potential National Grid Extension
6.26 The Applicant submitted a National Grid Substation Appraisal during the examination which indicated the potential effects which would result from extending the National Grid substation to accommodate future projects. The Appraisal indicated that this would result in an increase in the overall length of the National Grid Substation [ER 8.5.69]. The ExA considered that an extension to the National Grid substation would increase the magnitude of harm to Little Moor Farm (Grade II), the Church of St Mary (Grade II*), Friston House (Grade II), Woodside Farm House (Grade II) and High House Farm (Grade II). However, the increase in magnitude would not result in an increase to the overall levels of less than substantial harm it had assigned, as such, the levels would remain the same as detailed in paragraph 6.17. The ExA considered that the overall level of less than substantial harm for the Friston War Memorial would potentially increase to a medium level of less than substantial harm [ER 8.5.72; 8.6.1].
6.27 The ExA stated [ER 8.6.1] that it had not considered the National Grid Substation Appraisal in reaching its overall conclusion on Onshore Historic Environment—noting that the Applicant acknowledged that the Appraisal is "environmental information" and is not intended to comprise a Cumulative Impact Assessment."
"12.14 With regards to the inclusion of the Nautilus and Eurolink interconnector projects in the cumulative effects assessment, the Secretary of State notes that Friston is a potential connection point for the National Grid Ventures interconnector projects [ER 14.5.15]. However, the Secretary of State disagrees with the ExA's statement [ER 14.5.17] that satisfactory assumptions could have been made to allow the Nautilus and Eurolink interconnector projects to be included in the Applicant's cumulative impact assessment.
12.15 Predicting the future traffic effects of projects for which very few details are available would not be helpful in determining the cumulative effects of the East Anglia ONE North and East Anglia TWO developments, as the elements of the future projects which would contribute to adverse traffic effects are likely to change significantly before their applications are submitted to the Planning Inspectorate. Attempting to predict the traffic movements at this early stage in the projects' lifecycle would rely on ambiguous assumptions and would not result in predictions which accurately represent the cumulative effects of the projects in question, or in mitigation which would adequately reduce the effects. In contrast, when the applications for the Nautilus and Eurolink interconnector projects are further progressed, accurate up-to-date construction programme and traffic and transport information will be available for the East Anglia ONE North, East Anglia TWO and Sizewell C projects which would allow effective mitigation measures to be implemented by the respective developers.
12.16 The Secretary of State refers to paragraph 44 of the recent ruling from Mr Justice Holgate on the Norfolk Vanguard offshore windfarm in relation to cumulative effects which states:
"By the time the ES for the Vanguard project was submitted in June 2018, substantial progress had already been made on Boreas. Grid connection agreements at Necton had been entered into for Vanguard in July 2016 and Boreas in November 2016. The site selection process had already identified preferred substation footprints for both Vanguard and Boreas. The decision had been taken to use HVDC technology for both developments, determining the nature and scale of onshore infrastructure, including substations at Necton. The Boreas team had a pre-application meeting with the Planning Inspectorate on 24 January 2017, a request for a scoping opinion in respect of Boreas was made in May 2017 and the opinion issued in June 2017."
12.17 Unlike the Norfolk Boreas Offshore Wind Farm project, no scoping opinion request has been submitted to the Planning Inspectorate for the Nautilus interconnector project, and it is currently in the early stages of the pre-application phase of the development consent process. So far, the only documentation available on the Planning Inspectorate's website for the Nautilus project is the Section 35 Direction. The Eurolink interconnector project is earlier in the development consent process than Nautilus, and no documentation has yet been submitted to the Planning Inspectorate.
12.18 The Secretary of State also notes that the Applicant's decision not to include these proposed projects in its cumulative effects assessment is supported by the Planning Inspectorate's Advice Note Seventeen: Cumulative effects assessment relevant to nationally significant infrastructure projects. Paragraph 3.3.1 of the Advice Note lists the information required to conduct stage 4 of a cumulative effects assessment:
• proposed design and location information;
• proposed programme of construction, operation and decommissioning; and
• environmental assessments that set out baseline data and effects arising from the 'other existing development and/or approved development'.
12.19 As none of the above information was available prior to the close of the East Anglia ONE North and East Anglia TWO examination period for either the Nautilus or Eurolink interconnector projects, the Secretary of State is content that it was not necessary for the Applicant to include these projects in its cumulative effects assessment."
Ground 6: Alternative sites
Claimant's submissions
Defendant and Applicants' submissions
Conclusions
Law and policy
"268 The principles on whether alternative sites or options may permissibly be taken into account or whether, going further, they are an "obviously material consideration" which must be taken into account, are well established and need only be summarised here.
269 The analysis by Simon Brown J (as he then was) in Trusthouse Forte Hotels Ltd v Secretary of State for the Environment (1986) 53 P & CR 293,299–300 has subsequently been endorsed in several authorities. First, land may be developed in any way which is acceptable for planning purposes. The fact that other land exists upon which the development proposed would be yet more acceptable for such purposes would not justify the refusal of planning permission for that proposal. But, secondly, where there are clear planning objections to development upon a particular site then "it may well be relevant and indeed necessary" to consider whether there is a more appropriate site elsewhere. "This is particularly so where the development is bound to have significant adverse effects and where the major argument advanced in support of the application is that the need for the development outweighs the planning disadvantages inherent in it." Examples of this second situation may include infrastructure projects of national importance. The judge added that, even in some cases which have these characteristics, it may not be necessary to consider alternatives if the environmental impact is relatively slight and the objections not especially strong.
270 The Court of Appeal approved a similar set of principles in R (Mount Cook Land Ltd) v Westminster City Council [2017] PTSR 1166, at para 30. Thus, in the absence of conflict with planning policy and/or other planning harm, the relative advantages of alternative uses on the application site or of the same use on alternative sites are normally irrelevant. In those "exceptional circumstances" where alternatives might be relevant, vague or inchoate schemes, or which have no real possibility of coming about, are either irrelevant or, where relevant, should be given little or no weight.
271 Essentially the same approach was set out by the Court of Appeal in R (Jones) v North Warwickshire Borough Council [2001] 2 P LR 59, paras 22–30. At para 30 Laws LJ stated:
"it seems to me that all these materials broadly point to a general proposition, which is that consideration of alternative sites would only be relevant to a planning application in exceptional circumstances. Generally speaking—and I lay down no fixed rule, any more than did Oliver LJ or Simon Brown J—such circumstances will particularly arise where the proposed development, though desirable in itself, involves on the site proposed such conspicuous adverse effects that the possibility of an alternative site lacking such drawbacks necessarily itself becomes, in the mind of a reasonable local authority, a relevant planning consideration upon the application in question."
272 In Derbyshire Dales District Council v Secretary of State for Communities and Local Government [2010] 1 P & CR 19 Carnwath LJ emphasised the need to draw a distinction between two categories of legal error: first, where it is said that the decision-maker erred by taking alternatives into account and second, where it is said that he had erred" "by failing to take them into account (paras 17 and 35). In the second category an error of law cannot arise unless there was a legal or policy requirement to take alternatives into account, or such alternatives were an "obviously material" consideration in the case so that it was irrational not to take them into account (paras 16–28).
273 In R (Langley Park School for Girls) v Bromley London Borough Council [2010] 1 P & CR 10 the Court of Appeal was concerned with alternative options within the same area of land as the application site, rather than alternative sites for the same development. In that case it was necessary for the decision-maker to consider whether the openness and visual amenity of metropolitan open land ("MOL") would be harmed by a proposal to erect new school buildings. MOL policy is very similar to that applied within a Green Belt. The local planning authority did not take into account the claimant's contention that the proposed buildings could be located in a less open part of the application site resulting in less harm to the MOL. Sullivan LJ referred to the second principle in Trusthouse Forte and said that it must apply with equal, if not greater, force where the alternative suggested relates to different siting within the same application site rather than a different site altogether (paras 45–46). He added that no "exceptional circumstances" had to be shown in such a case (para 40).
274 At paras 52–53 Sullivan LJ stated:
"52. It does not follow that in every case the 'mere' possibility that an alternative scheme might do less harm must be given no weight. In the Trusthouse Forte case the Secretary of State was entitled to conclude that the normal forces of supply and demand would operate to meet the need for hotel accommodation on another site in the Bristol area even though no specific alternative site had been identified. There is no 'one size fits all' rule. The starting point must be the extent of the harm in planning terms (conflict with policy etc) that would be caused by the application. If little or no harm would be caused by granting permission there would be no need to consider whether the harm (or the lack of it) might be avoided. The less the harm the more likely it would be (all other things being equal) that the local planning authority would need to be thoroughly persuaded of the merits of avoiding or reducing it by adopting an alternative scheme. At the other end of the spectrum, if a local planning authority considered that a proposed development would do really serious harm it would be entitled to refuse planning permission if it had not been persuaded by the applicant that there was no possibility, whether by adopting an alternative scheme, or otherwise, of avoiding or reducing that harm."
"53. Where any particular application falls within this spectrum; whether there is a need to consider the possibility of avoiding or reducing the planning harm that would be caused by a particular proposal; and if so, how far evidence in support of that possibility, or the lack of it, should have been worked up in detail by the objectors or the applicant for permission; are all matters of planning judgment for the local planning authority. In the present case the members were not asked to make that judgment. They were effectively told at the onset that they could ignore Point (b), and did so simply because the application for planning permission did not include the alternative siting for which the objectors were contending, and the members were considering the merits of that application."
275 The decision cited by Mr Taylor in First Secretary of State v Sainsbury's Supermarkets Ltd [2008] JPL 973 is entirely consistent with the principles set out above. In that case, the Secretary of State did in fact take the alternative scheme promoted by Sainsbury's into account. He did not treat it as irrelevant. He decided that it should be given little weight, which was a matter of judgment and not irrational (paras 30 and 32). Accordingly, that was not a case, like the present one, where the error of law under consideration fell within the second of the two categories identified by Carnwath LJ in Derbyshire Dales District Council (see para 272 above).
276 The wider issue which the Court of Appeal went on to address at paras 33–38 of the Sainsbury's case does not arise in our case, namely, must planning permission be refused for a proposal which is judged to be "acceptable" because there is an alternative scheme which is considered to be more acceptable. True enough, the decision on acceptability in that case was a balanced judgment which had regard to harm to heritage assets but that was, undoubtedly, an example of the first principle stated in Trusthouse Forte (see para 269 above). The court did not have to consider the second principle, which is concerned with whether a decision-maker may be obliged to take an alternative into account. Indeed, in the present case, there is no issue about whether alternatives for the western cutting should have been taken into account. As I have said, the issue here is narrower and case-specific. Was the SST entitled to go no further, in substance, than the approach set out in paragraph 4.27 of the NPSNN and PR 5.4.71?"
"277 In my judgment, the clear and firm answer to that question is "no". The relevant circumstances of the present case are wholly exceptional. In this case the relative merits of the alternative tunnel options compared to the western cutting and portals were an obviously material consideration which the SST was required to assess. It was irrational not to do so. This was not merely a relevant consideration which the SST could choose whether or not to take into account. I reach this conclusion for a number of reasons, the cumulative effect of which I judge to be overwhelming.
278 First, the designation of the WHS is a declaration that the asset has "outstanding universal value" for the cultural heritage of the world as well as the UK. There is a duty to protect and conserve the asset (article 4 of the Convention) and there is the objective inter alia to take effective and active measures for its "protection, conservation, presentation and rehabilitation" (article 5). The NPSNN treats a World Heritage Site as an asset of "the highest significance" (paragraph 5.131).
279 Second, the SST accepted the specific findings of the Panel on the harm to the settings of designated heritage assets (e g scheduled ancient monuments) that would be caused by the western cutting in the proposed scheme. He also accepted the Panel's specific findings that OUV attributes, integrity and authenticity of the WHS would be harmed by that proposal. The Panel concluded that that overall impact would be "significantly adverse", the SST repeated that (DL 28) and did not disagree (see paras 137,139 and 144 above).
280 Third, the western cutting involves large scale civil engineering works, as described by the Panel. The harm described by the Panel would be permanent and irreversible.
281 Fourth, the western cutting has attracted strong criticism from the WHC and interested parties at the Examination, as well as in findings by the Panel which the SST has accepted. These criticisms are reinforced by the protection given to the WHS by the objectives of articles 4 and 5 of the Convention, the more specific heritage policies contained in the NPSNN and by regulation 3 of the 2010 Regulations.
282 Fifth, this is not a case where no harm would be caused to heritage assets (see Bramshill at para 78). The SST proceeded on the basis that the heritage benefits of the scheme, in particular the benefits to the OUV of the WHS, did not outweigh the harm that would be caused to heritage assets. The scheme would not produce an overall net benefit for the WHS. In that sense, it is not acceptable per se. The acceptability of the scheme depended upon the SST deciding that the heritage harm (and in the overall balancing exercise all disbenefits) were outweighed by the need for the new road and all its other benefits. This case fell fairly and squarely within the exceptional category of cases identified in, for example, Trusthouse Forte, where an assessment of relevant alternatives to the western cutting was required (see para 269 above).
283 The submission of Mr Strachan that the SST has decided that the proposed scheme is "acceptable", so that the general principle applies that alternatives are irrelevant is untenable. The case law makes it clear that that principle does not apply where the scheme proposed would cause significant planning harm, as here, and the grant of consent depends upon its adverse impacts being outweighed by need and other benefits (as in paragraph 5.134 of the NPSNN).
284 I reach that conclusion without having to rely upon the points on which the claimant has succeeded under ground 1(iv). But the additional effect of that legal error is that the planning balance was not struck lawfully and so, for that separate reason, the basis upon which Mr Strachan says that the SST found the scheme to be acceptable collapses.
285 Sixth, it has been accepted in this case that alternatives should be considered in accordance with paragraphs 4.26 and 4.27 of the NPSNN. But the Panel and the SST misdirected themselves in concluding that the carrying out of the options appraisal for the purposes of the RIS made it unnecessary for them to consider the merits of alternatives for themselves. IP1's view that the tunnel alternatives would provide only "minimal benefit" in heritage terms was predicated on its assessments that no substantial harm would be caused to any designated heritage asset and that the scheme would have slightly beneficial (not adverse) effects on the OUV attributes, integrity and authenticity of the WHS. The fact that the SST accepted that there would be net harm to the OUV attributes, integrity and authenticity of the WHS (see paras 139 and 144 above) made it irrational or logically impossible for him to treat IP1's options appraisal as making it unnecessary for him to consider the relative merits of the tunnel alternatives. The options testing by IP1 dealt with those heritage impacts on a basis which is inconsistent with that adopted by the SST.
286 Seventh, there is no dispute that the tunnel alternatives are located within the application site for the DCO. They involve the use of essentially the same route and certainly not a completely different site or route. Accordingly, as Sullivan LJ pointed out in Langley Park (see para 273 above), the second principle in Trusthouse Forte applies with equal, if not greater force.
287 Eighth, it is no answer for the SST to say that DL 11 records that the SST has had regard to the "environmental information" as defined in regulation 3(1) of the EIA Regulations 2017. Compliance with a requirement to take information into account does not address the specific obligation in the circumstances of this case to compare the relative merits of the alternative tunnel options.
288 Ninth, it is no answer for the SST to say that in DL 85 the SST found that the proposed scheme was in accordance with the NPSNN and so section 104(7) of the PA 2008 may not be used as a "back door" for challenging the policy in paragraph 4.27 of the NPSNN. I have previously explained why paragraph 4.27 does not override paragraph 4.26 of the NPSNN and does not disapply the common law principles on when alternatives are an obviously material consideration. But, in addition, the SST's finding that the proposal accords with the NPSNN for the purposes of section 104(3) of the PA 2008 is vitiated (a) by the legal error upheld under ground 1(iv) and, in any event, (b) by the legal impossibility of the SST deciding the application in accordance with paragraph 4.27 of the NPSNN.
289 I should add, for completeness, that neither the Panel nor the SST suggested that the extended tunnel options need not be considered because they were too vague or inchoate. That suggestion has not been raised in submissions."
"4.4 Alternatives
4.4.1 As in any planning case, the relevance or otherwise to the decision-making process of the existence (or alleged existence) of alternatives to the proposed development is in the first instance a matter of law, detailed guidance on which falls outside the scope of this NPS. From a policy perspective this NPS does not contain any general requirement to consider alternatives or to establish whether the proposed project represents the best option.
4.4.2 However:
• applicants are obliged to include in their ES, as a matter of fact, information about the main alternatives they have studied. This should include an indication of the main reasons for the applicant's choice, taking into account the environmental, social and economic effects and including, where relevant, technical and commercial feasibility;
• in some circumstances there are specific legislative requirements, notably under the Habitats Directive, for the IPC to consider alternatives. These should also be identified in the ES by the applicant; and
• in some circumstances, the relevant energy NPSs may impose a policy requirement to consider alternatives (as this NPS does in Sections 5.3 [biodiversity], 5.7 [flood risk] and 5.9 [landscape and visual]).
4.4.3 Where there is a policy or legal requirement to consider alternatives the applicant should describe the alternatives considered in compliance with these requirements. Given the level and urgency of need for new energy infrastructure, the IPC should, subject to any relevant legal requirements (e.g. under the Habitats Directive) which indicate otherwise, be guided by the following principles when deciding what weight should be given to alternatives:
• the consideration of alternatives in order to comply with policy requirements should be carried out in a proportionate manner;
• the IPC should be guided in considering alternative proposals by whether there is a realistic prospect of the alternative delivering the same infrastructure capacity (including energy security and climate change benefits) in the same timescale as the proposed development;
• where (as in the case of renewables) legislation imposes a specific quantitative target for particular technologies or (as in the case of nuclear) there is reason to suppose that the number of sites suitable for deployment of a technology on the scale and within the period of time envisaged by the relevant NPSs is constrained, the IPC should not reject an application for development on one site simply because fewer adverse impacts would result from developing similar infrastructure on another suitable site, and it should have regard as appropriate to the possibility that all suitable sites for energy infrastructure of the type proposed may be needed for future proposals;
• alternatives not among the main alternatives studied by the applicant (as reflected in the ES) should only be considered to the extent that the IPC thinks they are both important and relevant to its decision;
• as the IPC must decide an application in accordance with the relevant NPS (subject to the exceptions set out in the Planning Act 2008), if the IPC concludes that a decision to grant consent to a hypothetical alternative proposal would not be in accordance with the policies set out in the relevant NPS, the existence of that alternative is unlikely to be important and relevant to the IPC's decision;
• alternative proposals which mean the necessary development could not proceed, for example because the alternative proposals are not commercially viable or alternative proposals for sites would not be physically suitable, can be excluded on the grounds that they are not important and relevant to the IPC's decision;
• alternative proposals which are vague or inchoate can be excluded on the grounds that they are not important and relevant to the IPC's decision; and
• it is intended that potential alternatives to a proposed development should, wherever possible, be identified before an application is made to the IPC in respect of it (so as to allow appropriate consultation and the development of a suitable evidence base in relation to any alternatives which are particularly relevant). Therefore where an alternative is first put forward by a third party after an application has been made, the IPC may place the onus on the person proposing the alternative to provide the evidence for its suitability as such and the IPC should not necessarily expect the applicant to have assessed it."
Decision
"6.2 Connecting in the Bacton, Bradwell and Lowestoft areas on the coast, would require the extension of the National Grid transmission network out to the coast in addition to the construction of a new National Grid substation. A new double circuit overhead line, at minimum, from the existing 400kV network out to the coast across Norfolk, Essex or Suffolk - this would carry significant consenting and environmental challenges. Identifying route options, consulting about those, obtaining consent for them and then building new transmission lines would be environmentally challenging and would not be deliverable within the timescales the wind farms are looking to connect. For these reasons, connecting in the Bacton, Bradwell or Lowestoft areas was discounted.
6.3 Options to connect to the transmission network in North Norfolk, near Brandon, Shipdham, Dereham, Necton, Little Dunham, Kings Lynn or Walpole, were parked in the assessment, as other options compared more favourably in environmental and cost terms. [Footnote 4: 'Parked' means that the option is not subject to further analysis as there are better alternative options which have a similar system impact. It can still be reconsidered if the alternative(s) were later discounted due to reasons that are not affecting the parked options]. Each of these parked options would require much longer OFTO connecting cables in addition to new National Grid substations, with resultant greater environmental impacts and costs, as they are further from the offshore wind farms compared to other options.
6.4 Options to connect at Eye/Diss in Norfolk were similarly parked because of the longer distance. Those locations are further inland giving rise to greater environmental impact and cost associated with running OFTO cables from the wind farms to that location.
6.5 A connection at Norwich Main would require the extension of the existing substation and a new overhead transmission line from Pelham on the Hertfordshire/Essex border to Necton in Norfolk. The OFTO cables would also need to either navigate through the Norfolk Broads or north around the Norwich conurbation, to reach Norwich Main, with high consenting risks and a longer route than other connection options. There are also multiple offshore conservation zones between the wind farm and land falls towards Norwich.
6.6 Bramford was originally selected as the grid connection point for the East Anglia ONE offshore windfarm and two future East Anglia offshore projects. The onshore cable corridor for these projects was consented under the East Anglia ONE DCO consent. Following a design review of the East Anglia offshore projects (including the cable technology to be used to make the East Anglia ONE grid connection), it is only possible to accommodate the grid connections for East Anglia ONE and East Anglia THREE within the consented cable corridor. Any further connection at Bramford would require new cable routes to be developed and constructed.
6.7 The assessment initially indicated that connecting at Sizewell is the preferred option. This would have required the extension of the existing substation. However the substation is within the nuclear security perimeter zone, requiring the option to be under the rules of Civil Nuclear Constabulary. In addition to that, the potential site is highly constrained both physically and environmentally. Connecting there is therefore unlikely to be achievable.
6.8 A connection in the Leiston area is close to Sizewell and the coast, avoiding a longer cable route penetrating further inland through Suffolk to Bramford or elsewhere on the transmission network. A short cable route means the interaction between the project and other parties, such as crossings, protected areas and settlements, can be minimised.
6.9 For these reasons, when considering connections efficiency, coordination, economic and environmental impacts, the Leiston area compares more favourably than other connection options and forms the basis of the connection offers for the East Anglia ONE North and East Anglia TWO projects."
"It is clear that the ExA is not 'at large' in the territory of alternatives. The ExA must consider the merits of the application before it, including the consideration of alternatives with respect to the matters where they were relevant. It is sufficient in this respect to consider whether alternatives have as a matter of fact been appraised (and they have been)….."
"26.10 The ExA asked the Applicant about possible alternative sites raised in representations. The Applicant considered Bramford was unsuitable due to constraints of overhead lines, other undertakers' apparatus, areas required for planting for the East Anglia ONE and East Anglia THREE projects, the need for compulsory acquisition, pinch points along the route passing through three designated sites and the cost of the longer route using AC technology, and that the solution proposed by SASES would not work as the limit (1320MW) was insufficient for both projects; Bradwell would require extension of an overhead line with consequent environmental, timetabling and consenting challenges; Old Leiston airfield and Harrow Lane, Theberton have problems associated with the proximity of nearby residential property, caravan park, Leiston Abbey and Theberton village, the openness of the landscape and views and the absence of screening [ER 29.6.65]. The ExA was satisfied that these were not viable alternative sites [ER 29.5.146].
26.11 The ExA investigated the possibility of an alternative grid connection at Broom Covert which was initially suggested by NNB Generation (SZC) Company Limited, but which subsequently stated the land is being used for translocation of reptiles from the construction of the Sizewell C power station and was unavailable [ER 29.5.66 et seq]. Following queries from the ExA at Compulsory Acquisition Hearing 3 the Applicant explained that in July 2017 EDF Energy had advised that this land, or any land associated with the development of Sizewell C, was not available as it was allocated for ecological compensation and mitigation for reptiles, and the Applicant was satisfied that as EDF was a statutory undertaker, coupled with the importance of the land to Sizewell C and EDF's need to protect the safety and security of Sizewell B power station meant the land was not available; it had also considered the matter following requests from ESC and SCC and concluded that the policy and consenting challenges outweighed the increased cost of further cabling to Grove Wood. The ExA was satisfied with the Applicant's response and concluded that compulsory acquisition of the land to the west was necessary and proportionate [ER 29.5.69 et seq.]. The ExA concluded Broom Covert was not a viable alternative [ER 29.5.146]."
Final conclusion