QUEEN'S BENCH DIVISION
PLANNING COURT
Strand, London, WC2A 2LL |
||
B e f o r e :
____________________
THE QUEEN on the application of CAMILLA SWIRE |
Claimant |
|
- and - |
||
SECRETARY OF STATE FOR HOUSING, COMMUNITIES AND LOCAL GOVERNMENT |
Defendant |
|
(1) ASHFORD BOROUGH COUNCIL (2) TREVOR HEATHCOTE LLP |
Interested Parties |
____________________
Richard Honey and Ashley Bowes (instructed by the Government Legal Department) for the Defendant
The Interested Parties did not appear and were not represented
Hearing dates: 29 & 30 April 2020
____________________
Crown Copyright ©
Mrs Justice Lang :
Facts
"Recommendations
Limited site investigation works have been conducted that the site to date, gaps are evident within the data set provided and a supplementary intrusive environmental assessment is required to enable a Detailed Quantitative Risk Assessment (DQRA) to be completed to facilitate the residential redevelopment of the site. The completion of the DQRA will enable appropriate remediation targeted criteria to be derived for both soils and groundwater and agreed with the Local Authority and Environment Agency.
Following the completion and regulatory agreement the DQRA a Detailed Remediation Strategy and Validation Plan, inclusive of a Safe System of Works (SSOW) to mitigate against the potential release of in-ground fibres will require preparing and agreeing to satisfy anticipated Planning Conditions for the residential redevelopment."
"Based on the submitted information we consider that planning permission could be granted for the proposed development if the following planning conditions are included as set out below. Without these conditions, the proposed development poses an unacceptable risk to the environment and we would object to the application."
It confirmed CET's own position that its Ground Investigation and Risk Assessment report only provided a preliminary risk assessment and a fuller site investigation would be required. It also stated that it could not accept the remediation statement as submitted.
"Whilst compiling information and data for Preliminary Risk Assessment Reports (desk top of phase one studies) CET use many differing sources of information. Some of these sources of evidence are taken directly from known agencies and societies such as the British Geological Survey (BGS) for soil and geological information, and the Environment Agency for Hydrology, pollution incidents etc. For information on pollution events and licences for known processes we use the Envirocheck report from Landmark which encompasses information on licenced processes such as that of animal rendering plants. Because much of this information is taken from stakeholders such as the Environment Agency, any information on special arrangements for the safe rendering and disposal of cattle infected with BSE, would have been, or should have been, contained and provided for in the Landmark Envirocheck report.
Given the fact that any such premises will have been governed by licence, and have had to have been approved by the Government, would mean strict controls in working practices for such a plant would be in place. If any breach of these licence conditions was realised then it would have triggered an entry into the accessible database that is utilised by the likes of Landmark Envirocheck. It is therefore reasonable to assume that any such incident would have been, or even should have been reported and as such, would have been available for scrutiny by any company or organisation purchasing such a report from Envirocheck. CET have no idea why this was not the case for Thruxted Mill."
"The government guidance on how Creutzfeldt-Jacob Disease (CJD) the human variant of BSE is very clear. The prions which have the defective proteins that cause CJD, need to be either injected or enter the body by the consumption of brain and/or nervous tissue. There is no evidence that CJD can be spread through normal every day processes or activities. The laboratory analysis of the generic risk assessment did not return positive results from any of the commissioned microbiological tests that may have given an indication that there was a microbiological problem at the site.
Given the underlying geology of the site as being predominantly sandy gravelly clay over chalk and flint, the recharge rate of the groundwater is likely to be relatively high and so any potential bacterial contamination if present at any time in the past will be significantly diluted in the near surface water and certainly within the chalk aquifer. It is noted that the CET report recommends further investigation of areas of contamination which includes that of the groundwater. It should also be noted that there are no mechanisms for detecting CJD in the soil at this moment.
Given the above, it is reasonable to presume that at the moment the risks from acquiring CJD from the land or water in or under the site is negligible."
" . You may recall that my concern was with the fact that the hazard risk assessment completely failed to pick up the fact that this site was where BSE infected cattle had been rendered from 1998. At that time there had been a major inquiry into the suitability of this site given the potentially toxic prions that might have been released into the environment. The fact that the hazard risk assessment had not picked up on any of this clearly indicated that ABC's hazard risk procedures appear to be very inadequate or alternatively there may have been some other reason for not wishing this information to be divulged. I have had no reply to my request from any of the four people I wrote to, and until I hear to the contrary, I must put my own interpretation on this.
However, I now see that Mr Michael McNaughton (CET-UK) has placed a clarification statement on the list of "plans and documents" made about this planning application (dated 23rd Feb). While some of this material might indeed be correct it does not state a reason why ABC planning procedures failed to pick up on this matter. Mr McNaughton mentions the fact that rendering plants need to be governed by licence, and the documents on the planning application site do contain a permit issued by ABC in August 2004. However, this site was dealing with BSE infected cattle from 1998 so the developer needs to show ABC Planning the licence to do this from that time. This earlier permission may in fact show what activities were allowed and whether any stipulations were made regarding cleaning up the site at some future date.
It must be remembered that concern about the use of this plant for rendering cattle was of national importance at the time and many people gave lucid statements at the inquiry as to why disposal of wastes from the mill onto adjacent fields was a dangerously risky solution. I have spent some time reviewing online articles, papers, etc on prions and contrary to what Mr McNaughton says there is ample evidence that prions can survive for a lengthy time period and that they may have possibly dangerous consequences. Here are three examples: .."
The examples provided by Dr Meaden in his letter are set out at paragraph 96 of my judgment below.
"I request the application of conditions EO23 and EO26 in terms of contamination, and this requires full investigation and reporting before and after any works have been carried out. I would, of course, be expecting full discussion of any potential contamination related to the past use of the site in these reports, including prions associated with BSE/CJD (I mention this in particular as it has been highlighted as a particular concern by some objectors). I would expect that reference would be made to the DoE Industry Profile for Animal and Animal Products Processing Works also."
"Please be advised that we only comment on issues relating to groundwater protection: the issues relating to human health are addressed by the Local Authority's Environmental Health Officer. Also it does not fall within our remit to indicate how the site is to be remediated. The remediation method will be proposed by the applicant based on the results of the ground investigation."
"97. As stated above the extent of contamination on the site is relatively unknown although given the previous uses of the site the extent of contamination will be significant. The applicant has commissioned a Phase 1 preliminary report which states that the site will be heavily polluted as a result of its previous use and that a comprehensive site investigation and risk assessment will be needed. From there significant remediation works will be required. The results to date have not shown there to be widespread contamination and the concentrations did not exceed thresholds that consider a residential use unacceptable in principle. Heavy levels of contamination were found around existing sceptic tanks on the site. Further investigation is needed to see if these are localised hotspots or whether the contamination of hydrocarbons is more widespread. Brown and white asbestos were also revealed on the site.
98. Environmental Services were consulted on this information and raise no objection acknowledging it is an opportunity to address and remediate this contaminated site. They suggest conditions covering ground contamination, unexpected contamination and sewage disposal. They require further reports to establish potential contamination of the site including prions associated with BSE/CJD. The site does currently have an Environmental Permit (currently dormant) but has been kept 'alive' as to surrender it would result in relevant conditions of the permit to remediate the site becoming enforceable. If redevelopment does take place, the permit is surrendered and these works would have to take place under the requirements of the permit as well as any conditions on the grant of planning permission. The remediation required under the planning permission is likely to go further than those on the permit as it would introduce residential use on the site. The owner is entitled to keep renewing the permit in perpetuity which would mean the remediation conditions would not come into force."
"21. The development hereby permitted shall not be begun until a scheme to deal with contamination of land and/or groundwater has been submitted and approved by the Local Planning Authority and until the measures approved in that scheme have been implemented. The investigation report shall be conducted and presented in accordance with the guidance in CLR11 "Model Procedures for the Management of contaminated land" published by the Environment Agency. The scheme shall include all of the following measures unless the Local Planning Authority dispenses with any such requirement specifically and in writing:
A desk-top study carried out by a recognised expert in the field to identify and evaluate all potential sources and impacts of land and/or groundwater contamination relevant to the site. The requirements of the Local Planning Authority in consultation with other relevant agencies shall be fully established before the desk-top study is commenced and it shall conform to any such requirement. Two full copies of the desk-top study and a nontechnical summary shall be submitted to the Local Planning Authority without delay upon completion.
A site investigation shall be carried out by a recognised expert in the field to fully and effectively characterise the nature and extent of any land and/or groundwater contamination, and its implications. The site investigation shall not be commenced until:
i) A desk-top study has been completed, satisfying the requirements of paragraph (1) above.
ii) The requirements of the Local Planning Authority for site investigations have been fully established, and
iii) The extent and methodology have been agreed in writing with the Local Planning Authority. Two full copies of a report on the completed site investigation shall be submitted to the Local Planning Authority without delay upon completion.
A written method statement for the remediation of land and/or groundwater contamination affecting the site shall be agreed in writing with the Local Planning Authority prior to commencement, and all requirements shall be implemented and completed to the satisfaction of the Local Planning Authority by a competent person. No deviation shall be made from this scheme without the express written agreement of the Local Planning Authority. Two full copies of a full completion report confirming the objectives, methods, results and conclusions of all remediation works shall be submitted to the Local Planning Authority.
Reason: To control pollution of land or water in the interests of the environment and public safety.
22. If unexpected contamination is found at any time when carrying out the approved development it must be reported in writing to the Local Planning Authority. An investigation and risk assessment must be undertaken, and where remediation is necessary a remediation scheme must be prepared.
Following completion of the remediation scheme a verification report that demonstrates the effectiveness of the remediation carried out must be prepared and submitted for approval in writing by the Local Planning Authority.
Reason: To ensure that risks from land contamination to the future users of land and neighbouring land are minimised, together with those to controlled waters, property and ecological systems, and to ensure that the development can be carried out safely without unacceptable risks to workers, neighbours and other offsite receptors."
"Conditions are proposed that ensure:
Contamination of the site is to be remediated to a standard acceptable for residential development. Specialist advice will be sought to consider the remediation of Prions associated with CJD/BSE. This may require removal of contaminated soil by specialist contractors and replacement with uncontaminated top soil. This is a matter that will be dealt with fully and in detail through the suggested conditions. The Council's Environmental Services Section raise no objection subject to the imposition of such conditions.
Drainage conditions along with the contamination conditions would ensure that there would be no contamination of ground water (aquifer/ground water protection zone) .."
..
"g) Risk to Human Health (for example due to water contamination or air pollution)
Risk to human health will be improved through the remediation of contamination on the site (including possible BSE/CJD from the previous use of the site). This is a positive effect.
There are risks during the construction process in respect of contamination and prions associated with BSE/CJD as a result of the former use of the site however there are conditions that require the remediation of all contamination on the site to bring it up to a standard suitable for residential use to address these risks. This is a higher standard than that required by the Environmental permit which would take effect following the permanent cessation of the use of the site for animal rendering.
The cessation of the animal rendering use would ensure no further contamination of the site and noise/odour issues from the general industrial use.
In terms of the risk to human health due to the nature and scale of the development it is not considered likely to give rise to significant effects."
"We no longer respond to screening opinion consultations from Local Planning Authority's (LPAs). Our guidance (attached) advises LPAs when we should be consulted. We leave the decision on whether a proposal requires an EIA to the LPA to decide.
However, we were consulted on the planning application 17/01919/AS. In such matters as with this site, we only comment on issues within our remit, in this instance these related to protection of soil (where this relates to potential impacts on the water environment or regulation of waste) and to groundwater protection. The issues related to human health are addressed by the Local Authority's Environmental Health Officer. In our response to the consultation we advised that LPA that we had no objection subject to conditions being included in any permission granted. From our perspective we consider this would be satisfactory to mitigate against potential adverse impact of the groundwater.
Having reviewed the solicitors letter (paragraphs 13-16) their main concern appears to be impact on human health, which as previously advised is a matter for the LPAs Environmental Health Officer. We did find the applicant proposed remediation statement inadequate as stated in their letter, paragraph 15, but we have requested conditions that will require them to submit appropriate information for sign off before any construction works can start. Written approval would be required from the LPA (in consultation with us).
They also state in paragraph 16 that we state there could be "a risk of contamination as a result of previous use of the site during construction stage". This is correct but it should be noted that this is a paragraph we use for any proposal where the previous use of the site, or historical use of the site could have resulted in land contamination. Hence the conditions we requested for site investigations.
I hope the information clarifies our position in relation to this site ."
"Potential contamination issues
..
The Council's Environmental Protection Team and the Environment Agency have considered the contamination issue in detail as part of the processing of the planning application and have offered no objections to the proposal on grounds of contamination, subject to specific conditions requiring the remediation of the site to a suitable standard for residential development and a verification report to consider it. On the recommendation of both parties, the Council has agreed to impose a series of stringent environmental conditions to ensure development shall not begin until a scheme to deal with contamination of land and /groundwater has been submitted and approved by the local planning authority and until measures approved in the scheme have been implemented; if unexpected contamination is found during the investigation an risk assessment must be undertaken and where necessary a remediation scheme must be prepared; restricting the infiltration of surface water drainage into the ground and precluding piling and any other foundation designs using penetrative methods (proposed conditions 18, 19 and 21 to 24).
The Secretary of State has considered fully the third parties representations, the comments and advice of the Council's Environmental Protection Section and the Environment Agency, the Government specialist advisers on pollution and water quality issues, and the detailed list of conditions proposed by the local planning authority to manage, mitigate and safeguard the development and minimise any environmental impacts. Having considered all these issues the Secretary of State is satisfied that the proposed measures would satisfactorily safeguard and address potential problems of contamination."
"Potential impact on groundwater
The application site lies within a Ground Source Protection Zone, an area of Ground Water Vulnerability over principal acquifer. The Environment Agency has advised that there could be a risk of contamination from the previous use of the site during construction and this is a sensitive location being on a principal acquifer and just outside Source Protection Zone 3. The Agency has, however, offered no objections to the proposal subject to imposition of conditions covering a site investigation scheme, risk assessment and verification plan, which the Council has incorporated into the proposed grant of planning permission. The Agency is dissatisfied with the submitted remediation strategy and requires further investigation. In response the Council has imposed a planning condition requiring the submission of a revised remediation strategy, which would have to be agreed by the Agency, prior to it being discharged.
The Secretary of State has considered fully the third parties representations, the comments and advice of the Environment Agency, the Government specialist advisers on pollution and water quality issues, the Council's Environmental Protection Team and the detailed list of conditions proposed by the local planning authority to manage, mitigate and safeguard the development and minimise any environmental impacts. Having considered all these issues the Secretary of State is satisfied that the proposed conditions would ensure that the development does not affect the principal acquifer and groundwater."
"Potential harm to human health
The application site currently contains the remnants of Thruxted Mill which was an animal rendering processing facility and has been vacant for over 10 years. The third party, referring to representations submitted by a local doctor, contends that the redevelopment proposal represents a risk to human health and BSE contamination arising from its use as one of four UK sites for the disposal of BSE cattle. The Council contends that the risk to human health will be diminished through the remediation of contamination on the site, which is a positive effect. It acknowledges that there are risks during the construction process in respect of contamination and prions associated with BSE/CJD as a result of its former use but considers that the proposed conditions 21 & 22, which require the remediation of all contamination on the site, will bring it up to a standard suitable for residential use, would provide appropriate mitigation.
The Secretary of State has considered fully the third parties representations, the comments and advice of the Council's Environmental Protection Team and the conditions proposed by the local planning authority to manage, mitigate and safeguard the development and minimise any environmental impacts. He is, therefore, satisfied that the proposed measures would safeguard the health of prospective residents of the development"
"Following receipt of the third party request, the Secretary of State has screened the proposal to determine whether it constitutes EIA development. He has considered the proposal in relation to the selection criteria identified in Schedule 3 of the EIA Regulations and the potential impacts, identified by the third party, considered above within this written statement. In preparing the Screening Direction, the Secretary of State has considered fully third parties representations. He has consulted Natural England, the Government's specialist advisers on landscape and ecological issues, the Environment Agency, the Government specialist advisers on flooding, pollution and water quality issues and Historic England, the Government's specialist advisers on heritage issues and given due consideration to their comments submitted both in relation to the EIA and the planning application. The Secretary of State has also considered the detailed comments submitted by the Borough Council's Environmental Protection Team, Kent County Council and other agencies. He has also considered carefully the proposed planning conditions which would accompany the proposed planning approval for the Thruxted Mill development and, in accordance with regulation 5 (5) (b) of the EIA Regulations 2017, to ascertain whether these measures would avoid or prevent what might otherwise have significant adverse effects on the environment.
Having considered carefully all these issues the Secretary of State is satisfied that the proposed measures to mitigate the environmental impacts and concluded that these are sufficient to obviate the need for an Environmental Impact Assessment."
"I have undertaken a forensic assessment of the case and the proposed planning conditions and conclude that they provide the necessary safeguards and fulfil the requirements of the aforementioned regulation 5. On this basis, I conclude that the proposal does not constitute EIA development and propose to issue a Direction to this effect."
Grounds of challenge
Statutory framework
"General provisions relating to screening
5(1) Subject to paragraph (3) and regulation 63, the occurrence of an event mentioned in paragraph (2) shall determine for the purpose of these Regulations that development is EIA development.
(2) The events referred to in paragraph (1) are -
(a) the submission by the applicant or appellant in relation to that development of a statement referred to by the applicant or appellant as an environmental statement for the purposes of these Regulations; or
(b) the adoption by the relevant planning authority of a screening opinion to the effect that the development is EIA development.
(3) A direction of the Secretary of State shall determine for the purpose of these Regulations whether development is or is not EIA development.
(4) Where a relevant planning authority or the Secretary of State has to decide under these Regulations whether Schedule 2 development is EIA development, the relevant planning authority or Secretary of State must take into account in making that decision -
(a) any information provided by the applicant;
(b) the results of any relevant EU environmental assessment which are reasonably available to the relevant planning authority or the Secretary of State; and
(c) such of the selection criteria set out in Schedule 3 as are relevant to the development.
(5) Where a relevant planning authority adopts a screening opinion under regulation 6(6), or the Secretary of State makes a screening direction under regulation 7(5), the authority or the Secretary of State, as the case may be, must
(a) state the main reasons for their conclusion with reference to the relevant criteria listed in Schedule 3;
(b) if it is determined that proposed development is not EIA development, state any features of the proposed development and measures envisaged to avoid, or prevent what might otherwise have been, significant adverse effects on the environment; and
(c) send a copy of the opinion or direction to the person who proposes to carry out, or who has carried out, the development in question.
(6) The Secretary of State may make a screening direction either -
(a) of the Secretary of State's own volition; or
(b) if requested to do so in writing by any person.
(7) The Secretary of State may direct that particular development of a description mentioned in column 1 of the table in Schedule 2 is EIA development whether or not the conditions contained in sub-paragraphs (a) and (b) of the definition of "Schedule 2 development" are satisfied in relation to that development.
(8) Where the Secretary of State makes a screening direction in accordance with paragraph (6), the Secretary of State must
(a) take such steps as appear to be reasonable to the Secretary of State in the circumstances, having regard to the requirements of regulation 6(2) and (3), to obtain information about the proposed development in order to inform a screening direction;
(b) take into account in making that screening direction
(i) the information gathered in accordance with sub-paragraph (a);
(ii) the results of any relevant EU environmental assessment which are reasonably available to the Secretary of State; and
(iii) such of the selection criteria set out in Schedule 3 as are relevant to the development.
.."
"SELECTION CRITERIA FOR SCREENING SCHEDULE 2 DEVELOPMENT
Characteristics of development
1. The characteristics of development must be considered with particular regard to
(a) the size and design of the whole development;
(b) cumulation with other existing development and/or approved development;
(c) the use of natural resources, in particular land, soil, water and biodiversity;
(d) the production of waste;
(e) pollution and nuisances;
(f) the risk of major accidents and/or disasters relevant to the development concerned, including those caused by climate change, in accordance with scientific knowledge;
(g) the risks to human health (for example, due to water contamination or air pollution).
Location of development
2 (1) The environmental sensitivity of geographical areas likely to be affected by development must be considered, with particular regard, to
(a) the existing and approved land use;
(b) the relative abundance, availability, quality and regenerative capacity of natural resources (including soil, land, water and biodiversity) in the area and its underground;
(c) the absorption capacity of the natural environment, paying particular attention to the following areas
(i) wetlands, riparian areas, river mouths;
(ii) coastal zones and the marine environment;
(iii) mountain and forest areas;
(iv) nature reserves and parks;
(v) European sites and other areas classified or protected under national legislation;
(vi) areas in which there has already been a failure to meet the environmental quality standards, laid down in Union legislation and relevant to the project, or in which it is considered that there is such a failure;
(vii) densely populated areas;
(viii) landscapes and sites of historical, cultural or archaeological significance.
Types and characteristics of the potential impact
3. The likely significant effects of the development on the environment must be considered in relation to criteria set out in paragraphs 1 and 2 above, with regard to the impact of the development on the factors specified in regulation 4(2), taking into account -
(a) the magnitude and spatial extent of the impact (for example geographical area and size of the population likely to be affected);
(b) the nature of the impact;
(c) the transboundary nature of the impact;
(d) the intensity and complexity of the impact;
(e) the probability of the impact;
(f) the expected onset, duration, frequency and reversibility of the impact;
(g) the cumulation of the impact with the impact of other existing and/or approved development;
(h) the possibility of effectively reducing the impact."
"(a) a description of the proposed development comprising information on the site, design, size and other relevant features of the development;
(b) a description of the likely significant effects of the proposed development on the environment;
(c) a description of any features of the proposed development, or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;
(d) a description of the reasonable alternatives studied by the developer, which are relevant to the proposed development and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the effects of the development on the environment;
(e) a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and
(f) any additional information specified in Schedule 4 relevant to the specific characteristics of the particular development or type of development and to the environmental features likely to be significantly affected."
"6. A description of the forecasting methods or evidence, used to identify and assess the significant effects on the environment, including details of difficulties (for example technical deficiencies or lack of knowledge) encountered compiling the required information and the main uncertainties involved.
7. A description of the measures envisaged to avoid, prevent, reduce or, if possible, offset any identified significant adverse effects on the environment and, where appropriate, of any proposed monitoring arrangements (for example the preparation of a post-project analysis). That description should explain the extent, to which significant adverse effects on the environment are avoided, prevented, reduced or offset, and should cover both the construction and operational phases."
Conclusions
(1) The Court's role
"23. In R. (on the application of Jones) v Mansfield District Council [2004] Env. L.R. 21 Carnwath L.J., as he then was, emphasised (in paragraph 58 of his judgment) that "the EIA process is intended to be an aid to efficient and inclusive decision-making in special cases, not an obstacle race", and that "it does not detract from the authority's ordinary duty, in the case of any planning application, to inform itself of all relevant matters, and take them properly into account in deciding the case."
24. In R. (on the application of Bateman) v South Cambridgeshire District Council [2011] EWCA Civ 157 Moore-Bick L.J. said (in paragraph 20 of his judgment) that it was important to bear in mind "the nature of what is involved in giving a screening opinion". A screening opinion, he said, "is not intended to involve a detailed assessment of factors relevant to the grant of planning permission; that comes later and will ordinarily include an assessment of environmental factors, among others". Nor does it require "a full assessment of any identifiable environmental effects". What is involved in a screening process is "only a decision, almost inevitably on the basis of less than complete information, whether an EIA needs to be undertaken at all". The court should not, therefore, impose too high a burden on planning authorities in what is simply "a procedure intended to identify the relatively small number of cases in which the development is likely to have significant effects on the environment ". In the light of the decision of the European Court of Justice in Landelijke Vereniging tot Behoud van de Waddenzee v Staatssecretaris Van Lnadbouw, Natuurbeheer en Visserij [2004] ECR I-7405 and the Advocate General's opinion in R. (on the application of Mellor) v Secretary of State for Communities and Local Government [2010] Env LR 18 Moore-Bick L.J. said (in paragraph 17 of his judgment) that a likelihood in this context was "something more than a bare possibility though any serious possibility would suffice".
25. In R. (on the application of Loader) v Secretary of State for Communities and Local Government [2012] EWCA Civ 869, Pill L.J., with whom Toulson and Sullivan L.JJ. agreed, said (in paragraph 31 of his judgment) that there was "ample authority that the conventional Wednesbury approach applies to the court's adjudication of issues such as these". That principle is firmly established in the domestic jurisprudence. For example, in R. (on the application of Evans) v Secretary of State for Communities and Local Government [2013] EWCA Civ 114) Beatson L.J. said (in paragraph 22 of his judgment) that the "assessment of the significance of an impact or impacts on the environment has been described as essentially a fact-finding exercise which requires the exercise of judgment on the issues of "likelihood" and "significance"" (see also paragraph 40 of Laws L.J.'s judgment in Bowen-West v Secretary of State [2012] EWCA Civ 321). In Jones v Mansfield Carnwath L.J. said (at paragraph 61) that because the word "significant" does not lay down a precise legal test but requires the exercise of judgment on planning issues and consistency in the exercise of that judgment in different cases, the function is one for which the courts are ill-equipped."
"43. An appellant seeking to argue that the decision-maker . reached a conclusion for which there was no evidential basis invariably faces an uphill task. Such a task is made even more difficult in a situation like the present case, given that the screening direction is a preliminary, broad-based assessment of environmental impacts, undertaken by those with relevant training and planning expertise."
(2) Mitigating environmental effects
"45. Whilst each case will no doubt turn upon its own particular facts, and whilst it may well be perfectly reasonable to envisage the operation of standard conditions and a reasonably managed development, the underlying purpose of the Regulations in implementing the Directive is that the potentially significant impacts of a development are described together with a description of the measures envisaged to prevent, reduce and, where possible, offset any significant adverse effects on the environment. Thus the public is engaged in the process of assessing the efficacy of any mitigation measures.
46. It is not appropriate for a person charged with making a screening opinion to start from the premise that although there may be significant impacts, these can be reduced to insignificance as a result of the implementation of conditions of various kinds. The appropriate course in such a case is to require an environmental statement setting out the significant impacts and the measures which it is said will reduce their significance.
50. It must have been obvious that with a proposal of this kind there would need to be a number of non-standard planning conditions and enforceable obligations under s.106. It is precisely those sort of controls which should have been identified in a publicly-accessible way in an environmental statement prepared under the Regulations.
51. Thus the underlying approach adopted . was in error. In so far as one can discern the Council's reasoning, it was erroneous on the two grounds set out above: it was no answer to the need for an EIA to say the information would be supplied in some form in any event, and it was not right to approach the matter on the basis that the significant adverse effects could be rendered insignificant if suitable conditions were imposed. The proper approach was to say that potentially this is a development which has significant adverse environmental implications: what are the measures which should be included in order to reduce or offset those adverse effects?"
"Because of its previous use, the site is obviously contaminated to a significant degree. The type and extent of the contamination is not fully known at this stage. I am satisfied that sufficient basic information has been made available to the appellants to enable them and the Council to conclude on the most effective way to proceed with developing a programme for decontamination of the site whilst further submissions required by planning conditions are being prepared, subject to planning permission being granted. Further investigation such as a risk assessment would be undertaken prior to deciding on the most appropriate method of remediation. Environmental Impact Assessment was not required for the proposal as provided for under the appropriate regulations. The Council considers the imposition of an appropriately worded condition would ensure that the issue of contamination would be properly addressed. The Environment Agency accepts that contamination could be dealt with by planning conditions. PPG23 supports remediation strategies which address contamination in situ. Therefore, the tar tanks and the most contaminated land may well remain on the site depending what is found in the more detailed investigations. Nevertheless, despite the concerns of the Save Stepney Campaign ("SSC") and other local residents, decontamination procedures would be consistent with government policy in PPG23. I accept that the planning conditions as agreed between the appellants and the Council would provide for an appropriate remediation strategy for the site if planning permission were to be granted."
"20. The Secretary of State considers that there is sufficient information available to come to a view that the proposed development is unlikely to cause significant effect on the environment and therefore an environment assessment is not required having regard to the Town and Country Planning (Assessment of Environmental Effects) Regulations 1988. The Secretary of State is satisfied that the remediation work required can be dealt with by condition and that condition VI sets out the procedure to be followed by the developer and does not indicate the likelihood of significant effects on the environment."
21. Condition VI, in its final form, provided:
"Before any development commences a detailed site investigation shall be undertaken to establish the nature, extent and degree of the contamination present on the site. The scope, method and extent of this site investigation shall be submitted to and approved by the local planning authority prior to the commencement of the site investigation. The site investigation work shall also propose a scheme for remediation of this contamination, including measures to be taken to minimise risk to the public, the environment and prevention of contaminated ground and surface water from escaping during the remediation, together with provisions for monitoring during and after remediation. The detailed site investigation shall be submitted to and approved in writing by the local planning authority prior to the commencement of the remediation works on site and no remediation or development works on site shall proceed other than in accordance with the approved measures.""
"37. The Secretary of State has to make a practical judgment as to whether the project would be likely to have significant effects on the environment by virtue of factors such as its nature, size or location. The extent to which remedial measures are required to avoid significant effects on the environment, and the nature and complexity of such measures, will vary enormously but the Secretary of State is not as a matter of law required to ignore proposals for remedial measures included in the proposals before him when making his screening decision. In some cases the remedial measures will be modest in scope, or so plainly and easily achievable, that the Secretary of State can properly hold that the development project would not be likely to have significant effects on the environment even though, in the absence of the proposed remedial measures, it would be likely to have such effects. His decision is not in my judgment pre-determined either by the complexity of the project or by whether remedial measures are controversial though, in making the decision, the complexity of the project and of the proposed remedial measures may be important factors for consideration."
"40. In my judgment the Secretary of State erred in the test he has expressed in para.19 of his final decision letter. I read the second part of para.19 as including an assumption that condition VI provides a complete answer to the question whether significant effects on the environment are likely. That is too narrow an approach. In the circumstances, it was necessary to consider the stage which the site investigation had reached (condition VI requires a future site investigation in detail to be undertaken), the nature and extent of the scheme for remediation, including its uncertainties, the effects on the environment during the remediation and the likely final result. The condition is properly drafted but itself demonstrates the contingencies and uncertainties involved in the development proposal, as does the evidence of Mr Simmons already quoted.
41. When making the screening decision, these contingencies must be considered and it cannot be assumed that at each stage a favourable and satisfactory result will be achieved. There will be cases in which the uncertainties are such that, on the material available, a decision that a project is unlikely to have significant effects on the environment could not properly be reached. I am not concluding that the present case is necessarily one of these but only that the test applied was not the correct one. The error was in the assumption that the investigations and works contemplated in condition VI could be treated, at the time of the screening decision, as having had a successful outcome."
"46. ..Where the Secretary of State is contemplating an application for planning permission for development which, but for remedial measures, may or will have significant environmental effects, I do not say that he must inevitably cause an EIA to be conducted. Prospective remedial measures may have been put before him whose nature, availability and effectiveness are already plainly established and plainly uncontroversial; though I should have thought there is little likelihood of such a state of affairs in relation to a development of any complexity. But if prospective remedial measures are not plainly established and not plainly uncontroversial, then as it seems to me the case calls for an EIA. If then the Secretary of State were to decline to conduct an EIA, as it seems to me he would pre-empt the very form of enquiry contemplated by the Directive and Regulations; and to that extent he would frustrate the purpose of the legislation."
"38 .. It is clear that a planning authority cannot rely on conditions and undertakings as a surrogate for the EIA process. It cannot conclude that a development is unlikely to have significant effects on the environment simply because all such effects are likely to be eliminated by measures that will be carried out by the developer pursuant to conditions and/or undertakings. But the question whether a project is likely to have significant effect on the environment is one of degree which calls for the exercise of judgment. Thus, remedial measures contemplated by conditions and/or undertakings can be taken into account to a certain extent (see Gillespie). The effect on the environment must be "significant". Significance in this context is not a hard-edged concept: as I have said, the assessment of what is significant involves the exercise of judgment.
39 I accept that the authority must have sufficient information about the impact of the project to be able to make an informed judgment as to whether it is likely to have a significant effect on the environment. But this does not mean that all uncertainties have to be resolved or that a decision that an EIA is not required can only be made after a detailed and comprehensive assessment has been made of every aspect of the matter. As the judge said, the uncertainties may or may not make it impossible reasonably to conclude that there is no likelihood of significant environmental effect. It is possible in principle to have sufficient information to enable a decision reasonably to be made as to the likelihood of significant environmental effects even if certain details are not known and further surveys are to be undertaken. Everything depends on the circumstances of the individual case."
"53 This was plainly not a Gillespie case. The committee had a great deal of information about the likely effects of the development on the environment. It had representations from various consultees. It also had a number of ecological reports from the developer's consultants which described the various surveys that had been undertaken; and it had two comprehensive reports by the Head of Planning and Building Controls. The committee did not rely on the conditions and undertaking in order to arrive at its conclusion that the development was unlikely to have an environmental effect in relation to bats, golden plovers or birds generally. The judge was right to say that the imposition of conditions with regard to surveys, and the acceptance of the undertaking, did not preclude the council from being satisfied that it was unlikely that the project would have a significant effect on the environment. Having regard to the information already available, it was reasonable for the committee to decide that the development would be unlikely to have significant effects in relation to birds and bats .
54 The judge was also right to say that the comments by English Nature .. were important. The Officer was right to say, as he did in the first report, that these comments enabled him to advise the committee that the development would not have a significant environmental impact on the golden plover habitat. As the judge pointed out, English Nature did not suggest, still less request, that further investigations be carried out which might reveal the likelihood of a significant impact.
55 The members of the committee had to make a judgment on the material that was before them as to whether the proposed development would be likely to have a significant effect on the environment. For the reasons that I have given, which are substantially the same as those expressed by the judge, I am satisfied that they were entitled to conclude as they did ."
"27. . In Gillespie, the need for substantial future site investigation was crucial to the decision whether an EIA was required. I stated, at paragraph 39, that to consider the proposed development shorn of remedial measures incorporated into it "would be to ignore the 'actual characteristics' of some projects". Scrutiny of the likely effects of the particular development project is required: "All aspects of the development project must be considered; the relevant considerations may be different in a case where the central problem is the eventual effect of the development upon the environment and a case such as the present where the central problem arises from the current condition of the land."
..
33. This is a very different development from that proposed in Gillespie. Developments come in all forms and the approach to the screening opinion must have regard to the development proposed. There will be cases, such as Gillespie, where the uncertainties present, whether inherent or sought to be resolved by conditions, are such that their favourable implementation cannot be assumed when the screening opinion is formed.
34. On the other hand, there will be cases where the likely effectiveness of conditions or proposed remedial or ameliorative measures can be predicted with confidence. There may also be cases where the nature, size and location of the development are such that the likely effectiveness of such measures is not crucial to forming the opinion. It is not sufficient for a party to point to an uncertainty arising from the implementation of the development, or the need for a planning condition, and conclude that an EIA is necessarily required. An assessment, which almost inevitably involves a degree of prediction, is required as to the effect of the particular proposal on the environment, and a planning judgment made. (See also the judgment of Ouseley J. in Younger Homes (Northern) Ltd v First Secretary of State [2003] EWHC 3058; [2004] JPL 950 at [59][62] citing Dyson L.J. in R. (on the application of Jones) v Mansfield DC [2003] EWCA Civ 1408).
..
37. When forming a screening opinion, the Council were not required to ignore either the conditions proposed to limit the scope of the development or the conditions providing for ameliorative or remedial measures. The consequences of providing the additional seating, and other changes, could not be predicted with certainty but, as Collins J. noted, the Council had extensive knowledge and experience, supported by surveys, of the impact of existing football league and cup matches upon the environment. On the basis of that, and the studies into future impact, they were entitled to assess the likely impact of the additional capacity proposed in the context of the continuing ameliorative measures also proposed and to form the screening opinion they did."
"43. . The decision-maker must have regard to the precautionary principle and to the degree of uncertainty as to environmental impact at the date of the decision. Depending on the information available, the decision-maker may or may not be able to make a judgment as to the likelihood of significant effects on the environment. There may be cases where the uncertainties are such that a negative decision cannot be taken. Subject to that, proposals for ameliorative or remedial measures may be taken into account by the decision-maker.
..
47. Applying that approach to the present facts, I have no doubt that the inspectorate was entitled to conclude that the proposed development would not have significant effects on the environment. A checklist was completed and no complaint is made about its contents. Judgment was exercised and reasons given for the decision .which justify the conclusion reached. It may be added that the application for planning permission in this case did not involve the uncertainties which have presented difficulties of analysis in some of the cases considered. Moreover, judgment was exercised, not at the early stage of the procedure when such decisions are often made, but after full consideration of the planning issues by the local planning authority and also by an inspector appointed by the Secretary of State. Full information as to the nature of the proposal and its likely effects was available."
"Subject to the applicant/agent ensuring that appropriate mitigation and safeguarding measures are put in place to prevent the possible discharge of pollutants and contamination from the site in the River Wensum (SAC & SSSI). Advice received from Natural England (Mike Meadow) that subject to pollution prevent measures being clearly identified and addressed, EIA would not be necessary."
"46. In the present case, there is no disagreement that it was appropriate for the authority to undertake a screening exercise in April 2010, once the application was formally registered. Nor is it now in dispute that the exercise was legally defective. As [Mr James Dingemans QC, sitting as a Deputy High Court Judge] said:
"in circumstances where the pollution prevention measures had not been fully identified at that stage the council could not be satisfied that the mitigation measures would prevent a risk of pollutants entering the river, when the mitigation measures were not known." (para 60)
Mr Lyon evidently relied on his understanding of the advice of Mr Meadows, but he in turn had not regarded it as a formal consultation, and it was not part of his role to advise on EIA issues. More importantly, it was impossible at that stage to reach the view that there was no risk of significant adverse effects to the river. All the expert opinion, including that of CMGL's own advisers, was to the effect that there were potential risks, and that more work was needed to resolve them. It was also clear that the mitigation measures as then proposed had not been worked up to an extent that they could be regarded as removing that risk. This could be regarded as an archetypal case for environmental assessment under the EIA Regulations, so that the risks and the measures intended to address them could be set out in the environmental statement and subject to consultation and investigation in that context.
47. In my view that defect was not remedied by what followed. It is intrinsic to the scheme of the EIA Directive and the Regulations that the classification of the proposal is governed by the characteristics and effects of the proposal as presented to the authority, not by reference to steps subsequently taken to address those effects. No point having been taken about delay since the date of the defective screening opinion (an issue to which I shall return), Mr Buxton's request in June 2011 that the development should be reclassified as EIA development was in principle well founded. It was not enough to say that the potential adverse effects had now been addressed in other ways."
"Even if that exercise results in the development of mitigation measures which are in themselves satisfactory, it would subvert the purposes of the EIA Directive for that to be conducted outside the procedural framework (including the environment statement and consultation) set up by the Regulations."
"51. Those passages to my mind fairly reflect the balancing considerations which are implicit in the EIA Directive: on the one hand, that there is nothing to rule out consideration of mitigating measures at the screening stage; but, on the other, that the EIA Directive and the Regulations expressly envisage that mitigation measures will where appropriate be included in the environmental statement. Application of the precautionary principle, which underlies the EIA Directive, implies that cases of material doubt should generally be resolved in favour of EIA."
52. We were shown various statements on the same issue, with arguably differing shades of emphasis, in a number of judgments of the Court of Appeal: Gillespie v First Secretary of State [2003] Env LR 663, paras 37, 48, 49; R (Jones) v Mansfield District Council [2004] Env LR 391, paras 38-39 and R (Catt) v Brighton and Hove City Council [2007] Env LR 691, paras 33-35. Some were cited by the Court of Appeal in the present case. Mr Lockhart-Mummery, rightly in my view, did not rely on any of those statements as representing a material departure from the approach of Sullivan J. They simply illustrate the point that each case must depend on its own facts. In R (Jones) v Mansfield District Council (in a judgment with which I agreed), Dyson LJ said, at para 39:
"39. I accept that the authority must have sufficient information about the impact of the project to be able to make an informed judgment as to whether it is likely to have a significant effect on the environment. But this does not mean that all uncertainties have to be resolved or that a decision that an EIA is not required can only be made after a detailed and comprehensive assessment has been made of every aspect of the matter. As the judge said, the uncertainties may or may not make it impossible reasonably to conclude that there is no likelihood of significant environmental effect. It is possible in principle to have sufficient information to enable a decision reasonably to be made as to the likelihood of significant environmental effects even if certain details are not known and further surveys are to be undertaken. Everything depends on the circumstances of the individual case."
53. As far as concerns the present case, it is not now in dispute that the screening opinion should have gone the other way. The mitigation measures as then proposed were not straightforward, and there were significant doubts as to how they would be resolved. I do not ignore Mr Meadows' evidence to the court that the proposed mitigation did not represent "novel or untested techniques" and that "similar methods have and are being successfully used around the country". But that was said in the light of the further reports produced in July 2010, and even then there remained unresolved problems for the Environment Agency and the council's own officers, for example in relation to the maintenance regime. The fact that they were ultimately resolved to the satisfaction of Natural England and others did not mean that there had been no need for EIA. The failure to treat this proposal as EIA development was a procedural irregularity which was not cured by the final decision."
(3) The Defendant's decision in this case
"It must be remembered that concern about the use of this plant for rendering cattle was of national importance at the time and many people gave lucid statements at the inquiry as to why disposal of wastes from the mill onto adjacent fields was a dangerously risky solution. I have spent some time reviewing online articles, papers, etc on prions and contrary to what Mr McNaughton says there is ample evidence that prions can survive for a lengthy time period and that they may have possibly dangerous consequences. Here are three examples:
"A University of California research team, led by Nobel Prize winner Stanley Prusiner, has provided evidence for the theory that infection can occur from prions in manure. And, since manure is present in many areas surrounding water reservoirs, as well as used on many crop fields, it raises the possibility of widespread transmission." (See https://clubalthea.com/2018/ 02/09/infected-waterfrom-animal-manure-prion-disease-and-parkinson/ )
"In 2015, researchers at The University of Texas Health Science Center at Houston found that plants can be a vector for prions. When researchers fed hamsters grass that grew on ground where a deer that died with chronic wasting disease (CWD) was buried, the hamsters became ill with CWD, suggesting that prions can bind to plants, which then take them up into the leaf and stem structure, where they can be eaten by herbivores, thus completing the cycle. It is thus possible that there is a progressively accumulating number of prions in the environment." (See https://phys.org/news/2015-05-grass-infectious-prions.html )
"Bovine spongiform encephalopathy (BSE), commonly known as mad cow disease, and other infectious diseases caused by prions have long been thought to spread almost exclusively by ingestion and direct inoculation. That assumption has now been challenged by results of a study by Haybaeck and colleagues, who conducted a series of experiments demonstrating airborne transmission of the prion disease, scrapie, to mice." (See http://www.upmc-cbn.org/report_archive/2011/cbnreport_0121 2011.html)
It may also [be] worth looking at Kovacs G.G. (2014) Neuropathology of Neurodegenerative Diseases for accounts of the transmissity and infectivity of prions, and an extensive Prion Exposure Protocol that is detailed at http://ehs.ucsf.edu/prion-exposure-protocol
My reading of the situation is that the utmost caution needs still to be taken when dealing with situations such as that existing at Thruxted Mill "
"I have requested the application of conditions EO23 and EO26 in terms of contamination, and this requires full investigation and reporting before and after any works have been carried out. I would, of course, be expecting full discussion of any potential contamination related to the past use of the site in these reports, including prions associated with BSE/CJD (I mention this in particular as it has been highlighted as a particular concern by some objectors). I would expect that reference would be made to the DoE Industry Profile for Animal and Animal Products Processing Works also."
"On the recommendation of both parties [the Council's Environmental Protection team and the Environment Agency], the Council has agreed to impose a series of stringent environmental conditions to ensure that development shall not begin until a scheme to deal with contamination of land and groundwater has been submitted and approved by the local planning authority and until measures approved in the scheme have been implemented; if unexpected contamination is found during the investigation [a] risk assessment must be undertaken and where necessary a remediation scheme must be prepared "
"The application site currently contains the remnants of Thruxted Mill which was an animal rendering processing facility and has been vacant for over 10 years. The third party, referring to representations submitted by a local doctor, contends that the redevelopment proposal represents a risk to human health and BSE contamination arising from its use as one of four UK sites for the disposal of BSE cattle. The Council contends that the risk to human health will be diminished through the remediation of contamination on the site, which is a positive effect. It acknowledges that there are risks during the construction process in respect of contamination and prions associated with BSE/CJD as a result of its former use but considers that the proposed conditions 21 & 22, which require the remediation of all contamination on the site, will bring it up to a standard suitable for residential use, would provide appropriate mitigation.
The Secretary of State has considered fully the third parties representations, the comments and advice of the Council's Environmental Protection Team and the conditions proposed by the local planning authority to manage, mitigate and safeguard the development and minimise any environmental impacts. He is, therefore, satisfied that the proposed measures would safeguard the health of prospective residents of the development."
"I acknowledge that this case is quite finely balanced. I am, however, not convinced by what would be achieved by issuing a positive Screening Direction as all the issues have been thoroughly investigated in detailed studies/assessments submitted as part of the planning application process, other than giving the objectors "another bite of the cherry"."
Plainly he was mistaken in believing that the issue of BSE contamination had been thoroughly investigated in the reports submitted with the planning application, as they were all completed before the developer became aware that BSE-infected carcasses had previously been disposed of at the Site. If this view informed his decision-making, it was a significant error.