QUEENS BENCH DIVISION
ADMINISTRATIVE COURT
Strand, London, WC2A 2LL Judgement handed down at The Law Courts Openshaw Place Ringway Preston PR1 2LL |
||
B e f o r e :
____________________
THE QUEEN (ON THE APPLICATION OF ROCKWARE GLASS LIMITED) |
Claimant |
|
- and - |
||
CHESTER CITY COUNCIL |
Defendant |
|
-and- QUINN GLASS LIMITED |
Interested Party |
____________________
Timothy Horlock QC and Robert Darbyshire (instructed by Eversheds, Nottingham) for the Defendant
Reuben Taylor (instructed by Cameron Smith Mckenna, London) for the Interested Party
Hearing dates : 27th, 28th, 29th, 30th September, 24th October 2005
____________________
HTML VERSION OF JUDGMENT
Crown Copyright ©
Summary |
Judgment |
Appendix 1 |
Appendix 2 |
Appendix 3 |
Order |
JUDGE GILBART QC:
Introduction
(a) Mr Durham had no authority to decide to issue the permit(b) The Council had failed properly to interpret and apply the relevant EU Directive (Directive 96/61/EC relating to Integrated Pollution Prevention and Control ) and the Pollution Prevention and Control (England and Wales) Regulations 2000 SI No 1973, (" PPC Regs") which were made pursuant to the Pollution Prevention and Control Act 1999
(c) The Council had misinterpreted the statutory guidance note SG2 issued by the Secretary of State for the Environment pursuant to the PPC Regs.
(d) The Council had taken irrelevant considerations into account and had failed to take material considerations into account
(e) It was irrational to have reached a decision on the application for a permit when he did not take steps to determine whether the concurrent planning application had been called in for determination by the First Secretary of State
Structure of judgement
(a) Identifying the central issues
(b) Engineering context
(c) The Application in question and its consideration by Chester City Council.
(d) Decision making by the Local Authority as Regulator- Legal Principles
(e) The Pollution Prevention and Control Code (1) Legislation
(f) The Pollution Prevention and Control Code (2) Published guidance
(g) New or existing installations: some differences in regulation and standards
(h) Must the regulator take the furnace size, configuration and the choice of process as a given when considering the application ?
(i) The reasoning of Chester City Council
(j) The scope of the Chief Executive's authority
(k) The relationship to the call in
(l) Whether Rockware have sufficient interest to seek or obtain judicial review
(m) Delay arguments
(n) Discretion generally
(o) Conclusion.
(a) As I describe below, the central issue in this litigation is one where no authority currently exists, and I have been asked by the regulator to give guidance for future applications;
(b) The case involves the interpretation and application of an important part of the European and UK legislation designed to protect the environment from industrial pollution;
(c) The process concerned has involved major investment, and shutting it down would involve substantial further costs (estimated by Quinn at £110,000 plus a shortening of the life of the installation at a cost of £ 2.2 million, plus costs of lost production (£ 100,000 per month) payments to suppliers (£ 64,000 per month) ) and a loss of profit, estimated by Quinn at £ 2 million . It is also said that there would be ongoing losses of interest on capital expenditure;
(d) Quinn have taken on a workforce of 220 people, and contend that it would have to lay them off if the permit were quashed. The costs of doing so would be some £ 1.1 million;
(e) It follows that there are powerful reasons why the judgement in this matter should be considered and thorough.
The central issues
(a) the degree to which the technique, production capacity and process configuration proposed by the applicant is determinative of the process, criteria and considerations by which the application is to be judged by the regulator;
(b) whether the process of consideration and reasoning of the regulator in this case was flawed;
(c) whether authority rested in the Chief Executive of the regulator to make the decision;
(d) whether he should have made a decision or waited until he knew that the concurrent planning application had been called in.
(e) whether Rockware has a sufficient interest
(f) whether the application was made promptly
(g) whether, if I find that any of the substantive grounds for challenge are made out, I should exercise my discretion to grant relief
. Engineering context
"NITROGEN DIOXIDE
Objectives
188. Objectives for nitrogen dioxide reflect evidence that it may have both acute (short-term) and chronic (long-term) effects on health, particularly in people with asthma. As a result, the Government and the devolved administrations have set two provisional objectives:
200΅g/m3 (105ppb) as a 1 hour mean, not to be exceeded more than 18 times per year; and
40΅g/m3 (21ppb) as an annual mean.
189. Both are to be achieved by the end of 2005. We have also set a further objective for the protection of vegetation of 30΅g/m3 (16ppb) NOx as a national objective, to be achieved by 31 December 2000. This will not be included in regulations for the purposes of LAQM. This is explained in paragraphs 303-305."
(a) Because of its transboundary nature, concerted action is needed in the EU to reduce ambient levels of ozone (paragraph 216)
(b) Ozone in the lower atmosphere is primarily formed by chemical reactions, caused by sunlight, whereby NOx and VOCs (volatile organic compounds), derived mainly from man-made sources, react to form it. NOx and VOCs, which are produced by industrial and other processes, are the most important precursors of ozone (219). As that paragraph says:
" Ozone is also a greenhouse gas, so NOx and VOCs can be considered greenhouse gases"
(c) The chemical reactions involved take a long time (from several hours into several days) and the ozone may persist for several days so that ozone measured at one location may actually have arisen from VOC or NOx emissions many hundreds or even thousands of kilometres away, and may then travel further for similar distances (220);
(d) In NW Europe the problem is an international one (223)
(e) It is intended that UK measures to reduce NOx and VOC emissions will have a significant impact on domestically generated ozone (233) .
(a) An amount of substance x will be emitted per unit of time say x grams of NOx per second;
(b) An amount of a substance will be emitted according to the amount of glass manufactured say y grams of NOx per tonne of glass manufactured;
(c) A proportion of the total emitted from the stack- say z mg per Nm3 of exhaust volume (remembering always that the stack will be emitting so many Nm3 per second) (NB the prefix N before m3 stands for Normal pressure, so that comparisons can be made on a like for like basis)
(a) Cross fired regenerative
(b) Oxyfuel
The Application In Question and its consideration by Chester City Council.
First Quinn Glass planning application made for site at Ince - for plant with three oxyfuel furnaces of 400 tonnes per day each | May 2000 |
Amended Quinn Glass planning application made - for plant with two oxyfuel furnaces of 600 tonnes per day each | August 2000 |
Meeting between Quinn and Chester where Quinn state desire to start building at start of 2004 and commence production in February 2005. | 23 October 2003 |
Application made by Quinn Glass for revised planning permission - for plant with two furnaces (no longer oxyfuel) and production lines increased from 8 to 13 lines | 12 December 2003 |
Principal construction activities start on site | January 2004 |
Plant granted revised planning permission | 3 March 2004 |
Rockware Glass issue challenge to revised planning permission on the grounds that no Environmental Assessment carried out/submitted | 19 May 2004 |
Quinn's solicitor confirms that the plant is already programmed to open in 2005 | 28 June 2004 |
Revised planning permission quashed by consent (by Harrison J) | 22 July 2004 |
Further application made by Quinn Glass for revised planning permission, with new Environmental Statement | On or around 23 July 2004 |
Initial application for IPPC Permit made by Quinn Glass to Chester City Council | 10 August 2004 |
DLA Piper, Solicitors, write on behalf of Rockware Glass to seek call in by the First Secretary of State of the 2004 revised Quinn Glass planning application | 10 August 2004 |
Quinn Glass lodged amended application for IPPC Permit. | 15 October 2004 |
Meeting between Quinn and Chester (attended by Mr David Hosker and others) where change in furnace type discussed | 4 November 2004 |
Mr Hosker wrote to Quinn Glass indicating that their application did not comply with SG2 | 24 November 2004 |
Meeting between Quinn Glass and Mr Hosker and submission of revised NOx emission abatement proposals by Quinn Glass | 26 November 2004 |
Mr Hosker prepared a report to Chester City Council members on Quinn Glass' IPPC application. | November 2004 |
Quinn confirms to Chester CC that it has "significant and confirmed trade orders" for produce from the site | December 2004 |
Mr Hosker prepared a further report to Chester City Council members on Quinn Glass' IPPC application. | February 2005 |
Report written for consideration by Chester CC by Brian Hughes, its Development Co-ordination Manager, i.e. the Planning Officer at the Defendant responsible for the Quinn planning application. | February 2005 |
Mr Hosker meets Chief Executive of Chester CC (Mr Paul Durham), and permit is issued by Chief Executive | 2nd March 2005 |
Government Office for North West ( "GONW") notifies Chester CC that planning application called in for determination by First Secretary of State | 2nd March 2005 |
Date of Planning Board meeting of Chester CC at which planning application was to have been considered | 3rd March 2005 |
Rockware's solicitors warn Quinn's solicitors that they were instructed to get the permit withdrawn or have it quashed | 9th March 2005 |
Quinn's solicitors write that " .the development .has been proceeding uninterrupted since October 2003. At the time of your challenge to the approval of amendments to the ..planning permission .our clients have made it abundantly clear that they intended to continue with their development. our clients have made long term contractual commitments to suppliers of materials, plant and equipment, and to glass purchasers, and have employed 118 full time glass manufacturing staff, most of whom are close to completing full-time training the start of production is imminent." | 11th March 2005 |
Quinn fire up furnaces | 11th April 2005 |
" to deal with matters where a decision nominally to be made by the Council is governed substantially by matters of fact or technical factors so that there is no real discretion."
Decision making by the Local Authority As Regulator- Legal Principles
(a) Since the statutory guidance sets out government policy for the exercise of powers under the PPC Regulations, the regulator must give clear and cogent reasons for departing from it: Gransden (EC) v SSE [1986] JPL 519 at 521. Although that is a planning case where there are express statutory duties relating to the giving of reasons and taking material considerations into account, its principles have been applied to all types of decisions. This is particularly important in the context of technical guidance relating to national industry, where the bodies being regulated can reasonably expect decisions to be guided by consistent and scientifically informed national policy: R v Tandridge DC ex parte Al Fayed [2000] 79 P&CR 227 at 232 per Carnwath J.
(b) He must interpret the policy correctly. A failure to do so amounts to a failure to have regard to a material consideration: see Gransden above
(c) Whether or not reasons are required in law, where they are given their adequacy falls to be tested against the same criteria as if they were legally required: R v Criminal Injuries Compensation Board ex parte Moore [1999] 2 All ER 90 at 95j
(d) Reasons must be adequate , intelligible, and must deal with the principal relevant issues.
The Pollution Prevention and Control Code (1) Legislation
The recitals in 96/61/EC (all of which are relevant in some way to this case)
appear in Appendix 1 to this judgement.
"Article 1
Purpose and scope
The purpose of this Directive is to achieve integrated prevention and control of pollution arising from the activities listed in Annex I. It lays down measures designed to prevent or, where that is not practicable, to reduce emissions in the air, water and land from the abovementioned activities, including measures concerning waste, in order to achieve a high level of protection of the environment taken as a whole, without prejudice to Directive 85/337/EEC and other relevant Community provisions."
"ANNEX I
CATEGORIES OF INDUSTRIAL ACTIVITIES REFERRED TO IN ARTICLE 1
1
2 .
3. Mineral industry
3.1. Installations for the production of cement clinker in rotary kilns with a production capacity exceeding 500 tonnes per day or lime in rotary kilns with a production capacity exceeding 50 tonnes per day or in other furnaces with a production capacity exceeding 50 tonnes per day
3.2. Installations for the production of asbestos and the manufacture of asbestos-based products
3.3. Installations for the manufacture of glass including glass fibre with a melting capacity exceeding 20 tonnes per day
3.4. Installations for melting mineral substances including the production of mineral fibres with a melting capacity exceeding 20 tonnes per day
3.5. Installations for the manufacture of ceramic products by firing, in particular roofing tiles, bricks, refractory bricks, tiles, stoneware or porcelain, with a production capacity exceeding 75 tonnes per day, and/or with a kiln capacity exceeding 4 m³ and with a setting density per kiln exceeding 300 kg/m³ "
It will be noted that those are descriptions of types of process.
"Article 3
General principles governing the basic obligations of the operator
Member States shall take the necessary measures to provide that the competent authorities ensure that installations are operated in such a way that:
(a) all the appropriate preventive(sic) measures are taken against pollution, in particular through application of the best available techniques;
(b) no significant pollution is caused;
(c) ..
(d) energy is used efficiently;
(e) the necessary measures are taken to prevent accidents and limit their consequences;
(f) .
For the purposes of compliance with this Article, it shall be sufficient if Member States ensure that the competent authorities take account of the general principles set out in this Article when they determine the conditions of the permit.
Article 4
Permits for new installations
Member States shall take the necessary measures to ensure that no new installation is operated without a permit issued in accordance with this Directive, ."
11. 'best available techniques` shall mean the most effective and advanced
stage in the development of activities and their methods of operation which
indicate the practical suitability of particular techniques for providing in
principle the basis for emission limit values designed to prevent and, where
that is not practicable, generally to reduce emissions and the impact on the
environment as a whole:
- 'techniques` shall include both the technology used and the way in
which the installation is designed, built, maintained, operated and
decommissioned,
- 'available` techniques shall mean those developed on a scale which
allows implementation in the relevant industrial sector, under
economically and technically viable conditions, taking into
consideration the costs and advantages, whether or not the
techniques are used or produced inside the Member State in
question, as long as they are reasonably accessible to the operator,
- 'best` shall mean most effective in achieving a high general level of
protection of the environment as a whole.
In determining the best available techniques, special consideration should be
given to the items listed in Annex IV"
"ANNEX IV
Considerations to be taken into account generally or in specific cases when determining best available techniques, as defined in Article 2 (11), bearing in mind the likely costs and benefits of a measure and the principles of precaution and prevention:
1. the use of low-waste technology;
2. the use of less hazardous substances;
3. the furthering of recovery and recycling of substances generated and used in the process and of waste, where appropriate;
4. comparable processes, facilities or methods of operation which have been tried with success on an industrial scale;
5. technological advances and changes in scientific knowledge and understanding;
6. the nature, effects and volume of the emissions concerned;
7. the commissioning dates for new or existing installations;
8. the length of time needed to introduce the best available technique;
9. the consumption and nature of raw materials (including water) used in the process and their energy efficiency;
10. the need to prevent or reduce to a minimum the overall impact of the emissions on the environment and the risks to it;
11. the need to prevent accidents and to minimize the consequences for the environment;
12. the information published by the Commission pursuant to Article 16 (2) or by international organizations."
The emphasis on reducing emissions as far as possible reappears in Article 6 on applications for permits
Article 6
Applications for permits
1. Member States shall take the necessary measures to ensure that an application to the competent authority for a permit includes a description of:
- the installation and its activities,
- the raw and auxiliary materials, other substances and the energy used in or generated by the installation,
- the sources of emissions from the installation,
- the conditions of the site of the installation,
- the nature and quantities of foreseeable emissions from the installation into each medium as well as identification of significant effects of the emissions on the environment,
- the proposed technology and other techniques for preventing or, where this not possible, reducing emissions from the installation,
- where necessary, measures for the prevention and recovery of waste generated by the installation,
- further measures planned to comply with the general principles of the basic obligations of the operator as provided for in Article 3,
- measures planned to monitor emissions into the environment.
An application for a permit shall also include a non-technical summary of the details referred to in the above indents.
2. ."
"Article 8
Decisions
Without prejudice to other requirements laid down in national or Community legislation, the competent authority shall grant a permit containing conditions guaranteeing that the installation complies with the requirements of this Directive or, if it does not, shall refuse to grant the permit.
All permits granted and modified permits must include details of the arrangements made for air, water and land protection as referred to in this Directive."
I shall return to this Article below.
"Article 9
Conditions of the permit
1. Member States shall ensure that the permit includes all measures necessary for compliance with the requirements of Articles 3 and 10 for the granting of permits in order to achieve a high level of protection for the environment as a whole by means of protection of the air, water and land.
2. In the case of a new installation or a substantial change where Article 4 of Directive 85/337/EEC applies, any relevant information obtained or conclusion arrived at pursuant to Articles 5, 6 and 7 of that Directive shall be taken into consideration for the purposes of granting the permit.
3. The permit shall include emission limit values for pollutants, in particular, those listed in Annex III, likely to be emitted from the installation concerned in significant quantities, having regard to their nature and their potential to transfer pollution from one medium to another (water, air and land). If necessary, the permit shall include appropriate requirements ensuring protection of the soil and ground water and measures concerning the management of waste generated by the installation. Where appropriate, limit values may be supplemented or replaced by equivalent parameters or technical measures.
For installations under subheading 6.6 in Annex I, emission limit values laid down in accordance with this paragraph shall take into account practical considerations appropriate to these categories of installation.
4. Without prejudice to Article 10, the emission limit values and the equivalent parameters and technical measures referred to in paragraph 3 shall be based on the best available techniques, without prescribing the use of any technique or specific technology, but taking into account the technical characteristics of the installation concerned, its geographical location and the local environmental conditions. In all circumstances, the conditions of the permit shall contain provisions on the minimization of long-distance or transboundary pollution and ensure a high level of protection for the environment as a whole.
5. The permit shall contain suitable release monitoring requirements, specifying measurement methodology and frequency, evaluation procedure and an obligation to supply the competent authority with data required for checking compliance with the permit.
For installations under subheading 6.6 in Annex I, the measures referred to in this paragraph may take account of costs and benefits.
6. The permit shall contain measures relating to conditions other than normal operating conditions. Thus, where there is a risk that the environment may be affected, appropriate provision shall be made for start-up, leaks malfunctions, momentary stoppages and definitive cessation of operations.
The permit may also contain temporary derogations from the requirements of paragraph 4 if a rehabilitation plan approved by the competent authority ensures that these requirements will be met within six months and if the project leads to a reduction of pollution.
7. The permit may contain such other specific conditions for the purposes of this Directive as the Member State or competent authority may think fit.
8. Without prejudice to the obligation to implement a permit procedure pursuant to this Directive, Member States may prescribe certain requirements for certain categories of installations in general binding rules instead of including them in individual permit conditions, provided that an integrated approach and an equivalent high level of environmental protection as a whole are ensured."
"Article 10
Best available techniques and environmental quality standards
Where an environmental quality standard requires stricter conditions than those achievable by the use of the best available techniques, additional measures shall in particular be required in the permit, without prejudice to other measures which might be taken to comply with environmental quality standards."
Developments in best available techniques
Member States shall ensure that the competent authority follows or is informed of developments in best available techniques.
"6. 'emission limit values` shall mean the mass, expressed in terms of certain specific parameters, concentration and/or level of an emission, which may not be exceeded during one or more periods of time. Emission limit values may also be laid down for certain groups, families or categories of substances, in particular for those listed in Annex III.
The emission limit values for substances shall normally apply at the point where the emissions leave the installation, any dilution being disregarded when determining them "
NOx (but not Carbon Dioxide (CO2) - a point of relevance for reasons which appear later) is one of the Annex III substances relevant to emissions to air, described as
"INDICATIVE LIST OF THE MAIN POLLUTING SUBSTANCES TO BE TAKEN INTO ACCOUNT IF THEY ARE RELEVANT FOR FIXING EMISSION LIMIT VALUES"
"7 Applications
(1) A regulator may require any application or type of application made to it under any provision of these Regulations to be made on a form made available by the regulator.
(2) A form made available by a regulator under paragraph (1) shall specify the information required by the regulator to determine the application, which shall include any information required to be contained in the application by the provision of these Regulations under which the application is made.
(3)- (6) .."
"shall be exercisable for the purpose of achieving a high level of protection of the environment taken as a whole by, in particular, preventing or, where that is not practicable, reducing emissions into the air, water and land." (Reg 8(3))
It is also the duty of a regulator " to follow developments in best available techniques"
(Reg 8(14))
(a) General provisions relating to permits : Reg 10
(b) General principles relating to conditions: Reg 11
(c) Conditions of permits- specific requirements : Reg 12
(d) (12A, 14)- not relevant here)
(e) Review by regulators of conditions of permits: Reg 15
(f) (16 not relevant here)
(g) Variation of conditions of permits; Reg 17.
(h) (18-20 not relevant here)
(i) Revocation without compensation: Reg 21.
"10 (2) Subject to paragraphs (3) and (4), where an application is duly made to the regulator, the regulator shall either grant the permit subject to the conditions required or authorised to be imposed by [regulation 12 or 12A] [below (or regulation 8 of the 2002 Regulations)] or refuse the permit."
By Regulation 11 (1),
(1) When determining the conditions of a permit, the regulator shall take account of the general principles set out in paragraph (2) and, in the case of a permit authorising the operation of a Part A installation or Part A mobile plant, the additional general principles set out in paragraph (3).
(2) The general principles referred to in paragraph (1) are that installations and mobile plant should be operated in such a way that
(a) all the appropriate preventative measures are taken against pollution, in particular through application of the best available techniques; and
(b) no significant pollution is caused.
(3) The additional general principles referred to in paragraph (1) in relation to a permit authorising the operation of a Part A installation or a Part A mobile plant are that the installation or mobile plant should be operated in such a way that
(a) waste production is avoided in accordance with Council Directive 75/442/EEC on waste; and where waste is produced, it is recovered or, where that is technically and economically impossible, it is disposed of while avoiding or reducing any impact on the environment;
(b) energy is used efficiently;
(c) the necessary measures are taken to prevent accidents and limit their consequences,
and that, upon the definitive cessation of activities, the necessary measures should be taken to avoid any pollution risk and to return the site of the installation or mobile plant to a satisfactory state.
Regulation 12 deals with specific requirements
(1) Subject to paragraphs (15) and (16) and regulations 13 and 14, there shall be included in a permit
(a) such conditions as the regulator considers appropriate to comply with paragraphs (2) to (8); and
(b) in relation to any Part A installation or Part A mobile plant authorised by the permit
(i) , and
(ii) such other conditions (if any) applying in relation to the Part A installation or Part A mobile plant, in addition to those required by sub-paragraphs (a) and (b)(i), as appear to the regulator to be appropriate, when taken with the condition implied by paragraph (10), for the purpose of ensuring a high level of protection for the environment as a whole, taking into account, in particular, the general principles set out in regulation 11;
(c ) .
(2) Subject to [paragraphs (8) and (8A)], a permit shall include emission
limit values for pollutants, in particular those listed in Schedule 5, likely to be
emitted from the installation or mobile plant in significant quantities, having
regard to their nature and, in the case of emissions from a Part A installation
or a Part A mobile plant, their potential to transfer pollution from one
environmental medium to another.
(3) Where appropriate, the emission limit values required by paragraph (2)
may apply to groups of pollutants rather than to individual pollutants.
(4) The emission limit values required by paragraph (2) shall normally
apply at the point at which the emissions leave the installation or mobile plant, any dilution being disregarded when determining them.
(5) ..
(6) Subject to paragraph (7), the emission limit values required by paragraph (2) shall be based on the best available techniques for the description of installation or mobile plant concerned but shall take account of the technical characteristics of the particular installation or mobile plant being permitted, and, in the case of an installation or Part A mobile plant, its geographical location and the local environmental conditions.
(7) Where an environmental quality standard requires stricter emission limit values than those that would be imposed pursuant to paragraph (6), paragraph (2) shall require those stricter emission limit values; and for the purpose of this paragraph "environmental quality standard" means the set of requirements which must be fulfilled at a given time by a given environment or particular part thereof, as set out in Community legislation.
(8) Where appropriate [subject to paragraph (8A)], the emission limit values required by paragraph (2) may be supplemented or replaced by equivalent parameters or technical measures.
" Interpretation: "best available techniques"
(1) For the purpose of these Regulations, "best available techniques"
means the most effective and advanced stage in the development of
activities and their methods of operation which indicates the
practical suitability of particular techniques for providing in
principle the basis for emission limit values designed to prevent and,
where that is not practicable, generally to reduce emissions and the
impact on the environment as a whole; and for the purpose of this
definition
(a) "available techniques" means those techniques which have been developed on a scale which allows implementation in the relevant industrial sector, under economically and technically viable conditions, taking into consideration the cost and advantages, whether or not the techniques are used or produced inside the United Kingdom, as long as they are reasonably accessible to the operator;
(b) "best" means, in relation to techniques, the most effective in achieving a high general level of protection of the environment as a whole;
(c) "techniques" includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned.
(2) Schedule 2 shall have effect in relation to the determination of best available techniques."
Schedule 2 (1) reads
" SCHEDULE 2
BEST AVAILABLE TECHNIQUES
Regulation 3
1 Subject to paragraph 2, in determining best available techniques special consideration shall be given to the following matters, bearing in mind the likely costs and benefits of a measure and the principles of precaution and prevention
(1) the use of low-waste technology;
(2) the use of less hazardous substances;
(3) the furthering of recovery and recycling of substances generated and used in the process and of waste, where appropriate;
(4) comparable processes, facilities or methods of operation which have been tried with success on an industrial scale;
(5) technological advances and changes in scientific knowledge and understanding;
(6) the nature, effects and volume of the emissions concerned;
(7) the commissioning dates for new or existing installations or mobile plant;
(8) the length of time needed to introduce the best available technique;
(9) the consumption and nature of raw materials (including water) used in the process and the energy efficiency of the process;
(10) the need to prevent or reduce to a minimum the overall impact of the emissions on the environment and the risks to it;
(11) the need to prevent accidents and to minimise the consequences for the environment;
(12) the information published by the Commission pursuant to Article 16(2) of [the IPPC Directive] or by international organisations.
2 .."
The Pollution Prevention and Control Code (2) Published guidance
(a) Pursuant to Article 16(2) of 96/61/EC and Schedule 2 paragraph 1(12) of the PPC Regs: a document referred to in the case as BREF, published in July 2000. BREF is important in dealing with technical information. I shall draw attention to aspects of it in due course.
(b) Pursuant to regulation 37(2) of the PPC Regs; two documents, entitled
(a) "Secretary of State's Guidance; General Guidance Manual on Policy and Procedures for A2 and B Installations" (March 2003) which I shall call " The Manual"
(b) "Sector Guidance Note IPPC SG2 : Secretary of State's Guidance for Glass manufacturing Activities with Melting Capacity More than 20 Tonnes per day" (June 2003) , which is defined in its paragraph 1.2 as statutory guidance
" on the integrated pollution control standards appropriate for the generality of new and existing A2 installations in the glass manufacturing sector"
I shall refer to it as "SG 2."
"How to use this guidance
1.12 This guidance is a guide to issues and procedures relating to the making of
applications, writing and granting permits, and regulating approved installations under the PPC Regulations (as amended). The guidance should be used in conjunction with the series of notes on Best Available Techniques (BAT) and Best Available Techniques Not Entailing Excessive Cost (BATNEEC). It is aimed at providing a strong framework for consistent and transparent regulation of activities and installations. This guidance should be read in conjunction with the Pollution Prevention and Control (England and Wales) Regulations 2000, as amended from time to time. Additional guidance will be issued as the need arises.
Who should use this guidance document?
1.13 This guidance is intended to fulfil a number of functions. It constitutes statutory guidance issued by Government to local authority regulators under regulation 37 of the PPC Regulations. As such, local authorities must have regard to it in carrying out their regulatory functions. It is intended to explain the main functions, procedures and terminology contained in the legislation and to serve as a manual which helps local authorities to be effective, efficient and consistent in discharging their new responsibilities. Environment Agency regulators need not have regard to the manual other than to the extent that it clarifies its relationship with local authorities under the Regulations.
1.14 It is intended to provide firms operating, or planning to operate, A2 or Part B
installations and mobile plant with a guide to the steps they will need to take in order to obtain and comply with the necessary permit.
1.15 It is also designed to be of value to members of the public who have an interest in industrial pollution control whether generally or in relation to a specific proposal or installation. The aim is to provide both a generalised introduction to the systems as well as a detailed summary for anyone who wants to know where to go for further information.
1.16 .
1.17
1.18 The manual does not purport to address every question on all procedures under the LA-IPPC and LAPPC regimes. Where, in the light of experience, feedback or other developments, guidance is considered necessary on further matters, Defra will use the system of additional guidance ("AQ") notes, which are employed now under the LAPC system, to provide ad hoc supplementary advice ...
1.19 The manual, together with the sector guidance notes advising on BAT for each sector, should provide the necessary basis for decisions in most cases. Where, however, an installation raises, for example, particularly complex or contentious issues , local authorities may need to take account of the more extensive guidance produced by the Environment Agency and listed in Annex I. Such guidance will be updated from time to time ..
Section 12 addresses BAT. I have attached it as Annex 2 to this judgement. I shall note passages of relevance as I deal with the various issues.
" .one of a series of such guidance notes aimed at providing a strong framework for consistent and transparent regulation of LA-IPPC installations".
It gives particular advice on BAT at paragraphs 1.6 1.7
Best Available Techniques (BAT)
1.6 BAT is the main basis for determining standards in LA-IPPC. This sector
guidance note addresses what is considered by the Secretary of State/WAG to
constitute BAT for glass manufacturing activities with melting capacity more than 20
tonnes/day. This sector guidance note takes into account information contained in the
BREF (Ref 3)
As made clear in chapter 12 of the General Guidance Manual, BAT for each
installation should be assessed by reference to the appropriate sector guidance note,
and these notes should be regarded by local authorities as their primary reference
document for determining BAT drawing up permits. In general terms what is BAT
for one installation is likely to be BAT for a comparable installation.
However,determination of what is BAT is ultimately a matter for case by-case
decision taking into account that individual circumstances may affect BAT
judgements and what are the appropriate permit conditions. Thus, for each glass
manufacturing installation, local authorities (subject to appeal to the Secretary of
State / WAG) should regard this guidance note as a baseline, but ensure they take
into account any relevant case-specific factors such as the individual process
configuration and other characteristics, its size, location, and any other relevant
features of the particular installation. Further guidance on this, including the issue of
taking account of operators' individual financial position, is contained in chapter 12
of the General Guidance Manual.
1.7 If there are any applicable mandatory EU emission limits, these must be met,
although BAT may go further."
It sets different standards for new as opposed to existing installations (dealt with below) and sets a standard for NOx emissions from new plants (such as this one) of 500 mg/Nm3 (see Table 3). It describes that as
" achievable ..using the best combination of techniques" (paragraph 2.2)
"3.1 This section summarises, in the outlined BAT boxes, what BAT should be in
most circumstances. The boxes should not be taken as the only source of permit
conditions; compliance with emission limits and other provisions contained in this
guidance note together with any relevant case-specific considerations will also need
to be taken into account."
3.2 The standards cover the techniques and measures which, in combination with
those in the relevant previous (LAPC/IPC/Waste) guidance, have been identified as
representing BAT in a general sense. They also cover the other requirements of the
Pollution Prevention and Control (England and Wales) Regulations 2000 and
requirements of other regulations, such as the Waste Management Licensing
Regulations and the Groundwater Regulations insofar as they are relevant to an IPPC
Permit. For the sake of brevity these boxes simply use the term "BAT".
3.3 Where techniques or operating conditions are referred to in the BAT boxes
below, provided that it is demonstrated to the satisfaction of the regulator that an
equivalent or better level of control of environmental impacts will be achieved, then
other techniques or operating conditions may be used."
SG 2 Table 5 describes " Furnace Types" of which 8 are listed including " Cross fired regenerative " (i.e. as Quinn proposed) and 7 others including " Oxy-fuel fired". The introduction in 3.11 reads
"3.11 There are many furnace designs in use and they are usually distinguished from each other in terms of the method of heating, the combustion air preheating system employed and burner positioning. The main types of furnace are described in Table 5 below. Typically the residence time of material within the furnace is 24 hours for container furnaces and 72 hours for float glass furnaces."
A section then follows entitled " Emissions Control." Having identified NOx as an emission which is to be controlled, it then continues :
Control of point source emissions from furnaces
3.13 The environmental performance of the furnace is a result of a combination of the choice of melting technique, fuel used, the internal design of the furnace, the method of operation, and the provision of secondary abatement measures.
3.14 From an environmental perspective, techniques that are inherently less polluting or that can be controlled by primary means (e.g. method of operation) are generally preferred to those that rely on secondary abatement to control emissions. The economic and technical limit of primary measures which prevent or minimise pollution at source should be fully considered and a balance between these and secondary abatement made, to achieve the most viable means to attain the emission limit values.
Selection of furnace configuration
3.15 The choice of furnace configuration and melting technique should be that which is suitable for the combination of production capacity, glass formulation, fuel prices and existing infrastructure, and will deliver the best environmental performance."
It then notes that in practice a combination of fuels is used (3.19) and notes that
" oxy-fuel melting has a number of advantages including furnace energy savings, reduction of waste gas volume, and significantly reduced NOx emissions
3.20 Achieving the best furnace efficiency means less fuel is used per tonne of glass produced which therefore yields less CO2, NOx and SOx. Less air is required to burn less fuel, so there is less turbulence on the surface of the molten glass. Thus the mass emission of particles is also reduced."
It then addresses the control of NOx. I set out paragraphs 3.21 -22 and the subsequent " BAT box"
Controlling emissions of oxides of nitrogen (NOx)
3.21 NOx in furnace emissions can arise as a result of breakdown of nitrates in the feed material or oxidation of nitrogen contained in fuel (which is typically very small). The vast majority however is thermal NOx, generated by the oxidation of nitrogen in the high temperature combustion atmosphere present in the glass furnaces (typically 1650 - 2000oC).
3.22 Reduction of NOx can be achieved to a large extent at source by special furnace designs or by primary means of combustion control applied on conventional furnaces. In general however a combination of these with secondary techniques is required to achieve the emission limit.
[Diagram or picture not reproduced in HTML version - see original .rtf file to view diagram or picture]
New or existing installations; some differences in regulation and standards
(a) A wholly new installation
(b) An existing installation to which "a substantial change" will be made (for the definition see PPC Regs regulation 2(1))
(c) An existing installation to which no change is made.
The PPC Regulations contain transitional provisions (see Schedule 3). They set a timetable for bringing existing installations (i.e. type (c )) under IPPC control. However one may have the case (type (b)) where an existing installation is the subject of a substantial change. While such changes are still subject to IPPC control, the Secretary of State has recognized that the technical and economic implications of altering a part of an installation are different to building one from scratch .
"Review and Upgrading Periods
Existing installations or activities
Upgrading
1.14 The previous guidance PG 3/3 (95) Secretary of State's Guidance Note for
Glass (excluding lead glass) Manufacturing Processes, relating to emissions to air,
advised that upgrading to that standard should usually have been completed by 1st
October 2001. Requirements still outstanding from any existing upgrading
programme should be completed.
1.15 The new provisions of this note and the dates by which compliance with these
provisions is expected, are listed in Table 1 below, together with the paragraph
number where the relevant guidance is to be found. Compliance with the new
provisions should normally be achieved by the dates shown. Permits should be
drafted having regard to this compliance timetable.
(a) Where this guidance note specifies standards or requirements which are additional
to, higher than or different to those in PG note PG 3/3 (95), Secretary of State's
Guidance Note for Glass (excluding lead glass) Manufacturing Processes, only in
exceptional circumstances should upgrading of existing installations and activities
having regard to these additional/ higher/different standards or requirements be
completed later than the compliance date specified in Table 1 below. (This excludes
different standards or requirements which fall within the following paragraph.)
(b) Where standards or requirements in PG 3/3 (95), Secretary of State's Guidance
Note for Glass (excluding lead glass) Manufacturing Processes have been deleted in
this guidance note or where this guidance note specifies less stringent standards or
requirements than those in PG 3/3 (95) Secretary of State's Guidance Note for Glass
(excluding lead glass) Manufacturing Processes, the new LA-IPPC permit should
reflect this straightaway.
1.16 A programme for upgrading within the specified timescales, to those new /
additional provisions in this guidance which involve significant improvement work,
should be submitted to the relevant local authority regulator within 6 months of the
date of issue of the permit.
There then follows Table 1, which relates to changes to existing installations. The parts relevant to NOx emissions for container glass are:
"Table 1: Compliance requirements
Upgrading Requirement Compliance Date
NOx Abatement Primary Techniques :As soon as reasonably practicable, which in most cases would normally be within 24 months of publication of the note.
NOx Abatement Secondary Techniques (Container glass) 1 April 2009"
It then continues
"1.17 Where abatement technology is in place to meet an emission limit value, it should be commissioned as soon as practicable. Having been commissioned, it should be maintained and operated so as to comply with the emission limit value during all normal operating conditions.
1.18 Where an energy saving method of abatement is under trial which, once fully commissioned, will control particulate emissions to meet the emission limit value, then the following requirements replace the compliance date above:
as part of their permit application, the operator should demonstrate their intention to adopt an energy saving method of abatement, subject to successful research and development
the benchmarks and timetable for progressing this option should also be presented at the time of the permit application
in the light of these proposals, the regulator should allow upgrading to be completed after the April 2005 / 2006 deadline, provided that the operator informs the regulator at least once every year on progress in writing
in the event that the method under trial is rejected, then the operator should comply with the particulate emission limit value within 24 months, and contingency plans for this event
should be made in writing to the regulator at the time of the permit application
in any event, the emission limit value should be complied with no later than 2009
1.19 Replacement plant should normally be designed to meet the appropriate standards specified for new installations or activities.
New installations or activities
1.20 For new installations or activities - from the first day of operation the permit should have regard to the full standards of this guidance.
Substantially changed installations or activities
1.21 For substantially changed installations or activities - as from the first day of operation, the permit should normally have regard to the full standards of this guidance with respect to the parts of the installation that have been substantially changed and any part of the installation affected by the change.
"2.1 This section contains emission limits, mass release rates and other requirements that are judged for the generality of the activities within the sector to represent BAT.
Contained emissions to air associated with the use of BAT
2.2 Guidance is given below on emission limits and other requirements which are achievable for key substances using the best combination of techniques.
Table 3: Contained emissions to air associated with the use of BAT
Source / Determinand Limit (mg/m3)
Furnace 0perations NOx Annual average 500"
Must the regulator take the furnace size, configuration and the choice of process as a given when considering the application ?
"the degree to which the technique, production capacity and process configuration proposed by an applicant is determinative of the process, criteria and considerations by which the application is to be judged by the regulator."
I shall now deal with conclusions in that regard.
Type X: Smith : 750mg/NM3
Type Y: Brown: 500 mg/NM3
Type X: Jones: 500 mg/NM3
Type Y; White: 500 mg/NM3
Brown's, Jones' and White's installations are subject to NOx limits of 500 mg/NM3 in their respective permits.
Therefore Smith's Type A scheme will produce emissions at a rate higher than the rate achievable by another method, and/or by another configuration. The question which lies at the heart of this case is whether the regulator is entitled to refuse the permit for Smith's proposal for a Type X installation on the basis that use of a different size furnace, configuration or process from that proposed would generate lower emissions of a designated pollutant .
"achieving a high level of protection of the environment taken as a whole by preventing or, where that is not practicable, reducing emissions into the air, water and land."
That reflects Article 1 of the Directive, which underlies
"measures designed to prevent or, where that is not practicable, to reduce emissions in the air, water and land from the abovementioned activities, including measures concerning waste, in order to achieve a high level of protection of the environment taken as a whole. "
"Article 3
General principles governing the basic obligations of the operator
Member States shall take the necessary measures to provide that the competent authorities ensure that installations are operated in such a way that:
(a) all the appropriate preventive(sic) measures are taken against pollution, in particular through application of the best available techniques;
(b) no significant pollution is caused"
I also consider that recitals 1, 6 and 8 of the Directive show that any decision must seek to prevent or minimise emissions to air. That being so, that question is as pertinent to the question of whether to grant or refuse as it is to the questions of which conditions should be applied.
(2) The general principles referred to in paragraph (1) are that installations and mobile plant should be operated in such a way that
(a) all the appropriate preventative measures are taken against pollution, in particular through application of the best available techniques; and
(b) no significant pollution is caused.
By Regulation 3(1)(c )
" "techniques" includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned"
"12.8 Availability: Where there is a choice, the technique that is best overall will
be BAT unless it is not an 'available technique'. There are two key aspects to the
availability test:
a) what is the balance of costs and advantages? This means that a
technique may be rejected as BAT if its costs would far outweigh its
environmental benefits; and
b) can the operator obtain the technique? This does not mean that the
technique has to be in general use. It would only need to have been
developed or proven as a pilot, provided that the industry could then
confidently introduce it. Nor does there need to be a competitive market
for it. It does not matter whether the technique is from outside the UK or
even the EU."
"Basic principles for determining BAT
12.10 As stated above, determination of what is BAT must ultimately be made on a case-by-case basis and taking into account that individual circumstances may affect BAT judgements and what are the appropriate permit conditions. The following paragraphs describe the steps that would be necessary if starting such an exercise from scratch.
However, where sector guidance notes are available, they will have taken account of options and it may be quite adequate to rely on those notes as a baseline for what is BAT (as well as, where appropriate, what is necessary to achieve the relevant EU Waste Framework Directive objectives), in a given situation. Any additional assessments and option identification should be undertaken as seems necessary having regard to the specific facts of the particular case, including the precise size and configuration of the installation and activities, the actual production process used, and the location of the installation. It is envisaged that such assessments are likely to be more extensive for LAIPPC installations, which will generally be more complex and are being regulated in relation to a wider range of environmental impacts. For LAPPC installations, it is envisaged that assessments will be similar in extent to those undertaken currently for LAPC and broadly-speaking what is BAT/BATNEEC for one activity in a sector is likely to be BAT/BATNEEC for a comparable activity. In all cases, local authorities, in determining applications, should take account of the relevant factors set out in Schedule 2 to the regulations .. They may in subsequent proceedings be required to demonstrate that they have done so and produce any written notes or report setting down the considerations relied on prior to taking their decision. Also, for the sake of transparency and accountability, they should be in a position to justify their decisions to the operator (see also paragraph 13.17).
12.11 The basic principles for determining BAT involve identifying options, assessing environmental effects and considering economics. The principles of precaution and prevention are also relevant factors for determinations. Determining BAT involves comparing the techniques that prevent or reduce emissions and identifying the best one in terms of the one which will have the lowest impact on the environment.
Alternatives should be compared both in terms of the primary techniques used to run the installation and the abatement techniques used to reduce emissions further.
Environmental assessment.
12.12 Once the options have been identified there should be an assessment of their environmental effects. It should focus particularly on the significant environmental effects both direct and indirect. It should also look at the major advantages and disadvantages of techniques used to deal with them. Account should be taken, in particular, of the various factors listed in Schedule 2 to the PPC Regulations, ..some of which are detailed in paragraph 12.15 below. This should help to rank techniques according to their overall environmental effects."
The same approach is apparent in Policy Guidance Note SG2 in the section on Emissions Control. Paragraphs 3.13, 3.14, 3.15 (and note the heading "Selection of Furnace Configuration") 3.19, 3.20. 3.21, 3.22 and the BAT box all show that a BAT analysis will consider all aspects of configuration and choice of technique. It will "take account of," or "have regard to", the individual characteristics of the proposed installation, but in my judgement it is not bound by them. The decision maker must also have regard to other configurations or designs which would result in lower levels of emissions.
"10. The planning and pollution control systems are separate but complementary. Pollution control is concerned with preventing pollution through the use of measures to prohibit or limit the release of substances to the environment from different sources to the lowest practicable level. It also ensures that ambient air and water quality meet standards that guard against impacts to the environment and human health. The planning system controls the development and use of land in the public interest. It plays an important role in determining the location of development which may give rise to pollution, either directly or from traffic generated, and in ensuring that other developments are, as far as possible, not affected by major existing, or potential sources of pollution. The planning system should focus on whether the development itself is an acceptable use of the land, and the impacts of those uses, rather than the control of processes or emissions themselves. Planning authorities should work on the assumption that the relevant pollution control regime will be properly applied and enforced. They should act to complement but not seek to duplicate it.
15. Development control decisions can have a significant effect on the environment, in some cases not only locally but also over considerable distances. LPAs must be satisfied that planning permission can be granted on land use grounds taking full account of environmental impacts. This will require close co-operation with the ..the pollution control authority, .., to ensure that in the case of potentially polluting developments;
- the relevant pollution control authority is satisfied that potential releases can be adequately regulated under the pollution control framework; and "
" ..Mr David Mole QC, for Gateshead, has referred us to two paragraphs in particular. These are:
125. It is not the job of the planning system to duplicate controls which are the statutory responsibility of other bodies(including local authorities in their non-planning functions). Planning controls are not an appropriate means of regulating the detailed characteristics of industrial processes. Nor should planning authorities substitute their won judgement on pollution control issues for that of the bodies with the relevant expertise and the responsibility for statutory control over these matters.
126 The dividing line between planning and pollution control is therefore not always clear-cut
Neither ..are statements of law. Nevertheless, it seems to me they are sound statements of common sense. Mr Mole submits, and I agree, that the extent to which discharges from a proposed plant will necessarily or probably pollute the atmosphere is a material consideration to be taken into account when deciding to grant planning permission. The deputy judge accepted that submission also. But the deputy judge said at p 17 of his judgement, and in this respect I also agree with him
" Just as the environmental impact of such emissions is a material consideration, so also is the existence of a stringent regime under the EPA" (Environmental Protection Act 1990) "for preventing or mitigating that impact (or) rendering any emissions harmless. It is too simplistic to say " the Secretary of State cannot leave the question of pollution to the EPA.""
(a) The Directive and the Regulations are explicit that the objective is prevention of an emission of NOx, or reduction as far as possible: see Directive Articles 1, 3 and 6(1) ("- the proposed technology and other techniques for preventing or, where this not possible, reducing emissions from the installation"), and Regulations 8, 11(2) and 3(1), all of which look to achieving the lowest possible levels of emissions without reference to EQS, and one should not look to a different test. In other words, what is "significant" is the reduction of emissions to the minimum.
(b) Regulation 12(7) does not undercut that conclusion. It requires the application of techniques beyond BAT if a BAT derived ELV would cause the EQS to be exceeded, and allows refusal if the EQS would still be breached despite their application. There may be many reasons from the list set out in Regulation 3 and Schedule 2 (or Annex IV of the Directive) why a lower ELV has not been chosen. For example, the technology needed to achieve lower ELVs may involve greater costs (see Schedule 2 preamble) or be based on relatively untried technology. Even then, a permit may be refused if the EQS is breached. Regulation 12(7) thus provides a backstop which permits refusal in connection with EQS standards even though BAT justified a higher ELV. I do not consider that that is inconsistent with the approach I have adopted to Regulation 10(2).
(c) The " high standard of protection of the environment as a whole" in Article 3 is not intended to be related to a particular figure. The phrase "high level" is a way of describing the objective in the first recital, which is to prevent or reduce to the irreducible minimum the emission of pollutants at source:
"Whereas the objectives and principles of the Community's environment policy, as set out in Article 130r of the Treaty, consist in particular of preventing, reducing and as far as possible eliminating pollution by giving priority to intervention at source and ensuring prudent management of natural resources, in compliance with the 'polluter pays` principle and the principle of pollution prevention" (my italics) .
I refer also to Recital 8 and Article 1.
(d) The dangers of Mr Taylor's arguments can be seen from this case. A proposed ELV for NOx of 500mg/NM3 in SG2 was not applied here from the outset, but instead there was applied an ELV of 1100 mg/NM3, reducing to 500 mg/NM3 after 4 years. Mr Taylor seeks to draw comfort from the fact that the local EQS was not breached. By interpreting the Directive and Regulations narrowly so as to avoid comparison with other techniques, designs, configurations or sizes, by his arguments a more polluting choice of design/configuration is thus approved by pointing out that there is headroom below the EQS in terms of local air quality. In my judgement that is not what the code intended, and indeed is something it seeks to prevent.
(e) I would also regard Mr Taylor's submissions, even if I judged them otherwise acceptable, as undermining a very important piece of the interlocking matrix of environmental policies. It will be recalled from an earlier passage in this judgement that NOx has both direct and indirect effects, and that the latter (the generation of ozone) are felt over great distances and are not adequately reflected by local measurements of air quality. It follows that downwards pressure on the generation of NOx is important in its own right, irrespective of local EQS readings. That coincides with what in my judgement is the true interpretation of the both the EU and domestic legislation.
The reasoning of Chester City Council
(a) The application for a permit and a copy of its advertisement in the London Gazette and in local newspapers.
(b) A check list of steps to be taken, drawn up by an officer of Chester City Council.
(c) Documents relating to objections of English Nature, later withdrawn relating to various local air quality issues as the would affect the Mersey Estuary SSSI, including NOx. They included a response from Quinn and a letter of 7th February 2005.
(d) Correspondence with the local sewerage authority about effluent and with the local Primary Care Trust , neither of which related to NOx.
(e) Extracts from the October 2000 version of BREF.
(f) A paper supplied to Chester City Council by Quinn, which purported to be a paper produced by " Glass Technology Services" in January 2005. It addressed " Increases in CO2 emissions associated with NOx Abatement from Glass manufacturing Sites". The document supplied by Quinn to Chester CC was not what it said it was. "Glass Technology Services" is the name of a company owned by British Glass, which provides consulting and related technical services to the various companies in this industrial sector. I find, based on the unchallenged evidence of Mr Paul Stone, partner in DLA, and on the evidence of Mr Barry O'Reilly, Health and Safety Environment Manager of Quinn, that it is based on an internal paper which was never published because there were technical objections within British Glass to its contents. It was therefore extraordinary that it was supplied to Chester City Council as though it had been endorsed and published by Glass Technology Services. But the document is problematic for other reasons. Although purporting to be dated January 2005, its conclusions are written so as to refer to the draft SG 2 guidance, which were and are written so as to seek a limit of 800 mg/Nm3 for NOx instead of 500 mg/Nm3 in the eventually approved final version, which was issued as long ago as June 2003. While Mr Hosker had no reason to know that the document was not one endorsed and published by Glass Technology Services, the problems with its date must have been apparent to him.
(g) An extract from the Environmental Statement filed by Quinn, entitled " The Need for the Facility and Alternatives considered" and dated 19th July 2004.
(h) Some papers setting out histograms showing NOx emissions from UK cross-fired furnaces , and end fired furnaces.
(i) Secretary of State's Guidance Note SG2.
(j) Quinn's modelling of the expected ground level concentrations caused by expected NOx emissions from the proposed plant, of 23rd December 2004.
(k) An extract from Planning Policy Statement PS 23 " Planning and Pollution Control."
(l) Some sheets setting out other container glass plants, identifying whether a permit had been issued, and if so what NOx emissions were specified, and notes on abatement processes in use at some other installations.
(a) There were no oxyfuel furnaces on the world of the size proposed by Quinn in this installation;
(b) The use of oxygen would require storage of oxygen on site , which would make the site subject to COMAH regulations, and there were already two COMAH sites in the area. He did not however assess the degree of hazard;
(c) The electricity required to generate the oxygen would generate an unquantified extra amount of CO2, a greenhouse gas. He did not address the fact that NOx (indirectly) has an effect on greenhouse gases.
He states that it was reasons (a) and (b) which were the significant ones see paragraph 40.
At paragraph 41 ff Mr Hosker sets out the discussions he had with Quinn about secondary measures (i.e. abatement between the furnace and the release to atmosphere) to reduce emissions to 500 mg/ Nm3. He rejected all secondary means of doing so, and , according to his paragraph 45
" Taking all the above into account, my focus was on trying all primary techniques first and adjusting these to get emission levels down as far as possible. Having done this in consultation with Quinn, I concluded that a concentration of 1000 mg/Nm3 , reducing to 500 mg/Nm3 (SG 2 levels) by 2009 was the best that could realistically be achieved."
I shall consider below whether that stated reason withstands scrutiny.
.
"weighing up all of the considerations I have outlined above, I felt that the level of emissions (which would, importantly, reduce over time) the likely impact on the environment and environmental monitoring which was to be put in place justified temporary departure from SG 2. I considered the use of different technologies and there were site specific issues relating to the use of oxyfuel technology which concerned me. Greatly. (sic) My key concern was the huge volume of oxygen which would have to be stored on site for furnaces of the size proposed by Quinn. I concluded that cross fired furnaces, and not oxyfuel fired furnaces, would be BAT for this site."
"13 .. there were a number of issues. In particular , a brand new system starting up would not meet those standards immediately. This would be exacerbated by the fact that it would need to build up the volume of raw material it was heating. It could be several years before the plant was operating at 100% capacity. It was possible also that the equipment designed to reduce emissions might need fine tuning in its early days. For these reasons we could not require 100% compliance from day one ."
Mr Durham also says that he knew that oxyfuel had been considered. He repeats the same points which Mr Hosker had set out
(a) No oxyfuel furnaces of this size
(b) Need to store oxygen and designation as COMAH site
(c) Additional CO2 emissions.
He refers to the first two issues as " site specific." He records that Mr Hosker showed him that higher standards would be achieved than at other glass manufacturing plants.
He then states at paragraph 21 that Mr Hosker had set levels in the permit which would be met
" over a reasonable period of time, and this had been agreed by Quinn after negotiation. He had established that there were valid site specific reasons which I believed justified why these levels could not be met immediately .David had regard to BAT in coming to his conclusion and in negotiating and assessing the timetable for full compliance. The permit I was deciding on reflected all of this."
He considered that he had no discretion in the decision. However at paragraph 25 in his conclusion he stated
" .The only departure from SG 2 was in relation to nitrogen dioxide emissions and it did achieve compliance with this after a period of time that seemed reasonable in the circumstances."
In his second witness statement at paragraph 25 he states that Mr Hosker had
" looked at alternatives .David had negotiated standards that reflected BAT and were higher than had been achieved anywhere .."
(a) Achievable limits for NOx: 1000 mg/Nm3 reducing to 500 mg/Nm3 after 4 years (i.e. by March 2009). Lower limits were not possible because of lower use of capacity in early years.
(b) Oxyfuel alternative dismissed because of
(a) "site specific" reason that no oxyfuel furnace of similar size existed elsewhere
(b) "site specific" reason that site would be a COMAH designated site
(c) increased emissions of greenhouse gases
(c) levels lower than at other glass manufacturing installations
(d) support from BREF
(e) no exceedance of air quality standards
(f) levels set represent standards
(g) temporary departure from SG 2.
Chester CC's conduct on and after the 2nd March 2005
" to deal with matters where a decision nominally to be made by the Council is governed substantially by matters of fact or technical factors so that there is no real discretion."
" 12.10 .. In all cases, local authorities, in determining applications, should take account of the relevant factors set out in Schedule 2 to the regulations (see Annex VIII). They may in subsequent proceedings be required to demonstrate that they have done so and produce any written notes or report setting down the considerations relied on prior to taking their decision. Also, for the sake of transparency and accountability, they should be in a position to justify their decisions to the operator (see also paragraph 13.17)."
1000 mg/Nm3 by end of Year 1
900 mg/Nm3 by end of Year 2
750 mg/Nm3 by end of Year 3
500 mg/Nm3 by end of Year 4
" In determining the application the Council has had regard to the relevant general and specific sector guidance and those items contained within the indexed ring binder appended hereto.
I am satisfied that this decision is governed substantially by matters of fact and technical factors and so there is no real discretion to be exercised that requires this matter to be referred to the Cabinet for discussion"
(a) dealt with the EA letter (in my judgement, nothing turns on that)
(b) in the case of the Technoglas letter said that it was not a document relied on in the decision to issue the certificate. (I interpose to observe that it is strange then that either Chester CC or Eversheds could ever have thought it appropriate to include it)
(c) in the case of the other material, accepted that it post-dated the decision, but asserted that " they were considered or at least the content was known about, when the decision to issue the certificate was made"
"3 In this statement I refer to a number of documents which can be found in the Council's file of papers collated to justify its decision to issue the IPPC Permit. I shall refer to this file as the Justification File .."
20 I spoke to most of the regulators responsible for container glass manufacturing installations .
22 Where possible I reviewed copies of relevant IPPC permits. I was able to review 4 permits which have been issued in the last 4 months (he then lists various permits all in fact for existing installations)
23 At tab 10 of the Justification File, there is a summary of the information my research established
24 DEFRA has highlighted United Glass' Harlow site as achieving best practice ..
48 (Mr Hosker records having received information from Ellesmere Port and Neston BC after the issue of the permit) and states " This letter post-dates issue of the permit and for this reason is not contained in the Justification File"
(a) Emissions data for Rockware Worksop, obtained on 3rd March 2005
(b) Emissions data for plants in Barnsley, obtained on 9th March 2005
(c) Extracts from DEFRA website, obtained 9th March 2005. It was a guidance note from DEFRA (AQ20(04)) on the timescale for making decisions.
Each of those documents bears on its face a date later than the 2nd March 2005, and were obtained by Mr Hosker. Two of them were obtained and inserted into the file when Mr Hosker already knew that a request had been made for copies of the documents in the file, and after Mr Shutler had inspected it on 4th March 2005.
" 2 I refer to a number of documents which can be found in the Council's file of papers collated to justify its decision to issue the IPPC permit . I shall refer to this file as the Justification File"
The existing/new installations point, and the conflicting accounts of whether there was a departure
"The Defendant does not accept that it departed from SG2 guidance. Paragraph 1.15
of the Guidance provides that "Compliance with the new provisions should
normally be achieved by the dates shown. Permits should be drafted having regard to
this compliance timetable." The date shown for compliance on Table 1 of the
guidance for container glass, of the type manufactured at the plant was 1st April
2009. The annual average was fixed at 500 mg/Nm3. This was precisely the
condition imposed in the licence"
If that statement is true, it shows that Chester CC had made at least two fundamental errors about the meaning of SG 2
(a) Paragraph 1.15 of SG 2 has nothing to do with this application, which was for a new installation. It related to the date by which existing unchanged installations would be subject to control;
(b) Table 1 is also irrelevant for the same reason.
"In summary it is considered that the scale of the emissions, their likely significance on the environment, and the proposed controls that will be in place, with continued improvement through the life of the installation, justify a temporary departure from the emissions limits indicated in Guidance Note SG2" (my italics).
"temporary departures from SG 2"
Mr Durham in his first statement says (at paragraph 58) that the level of emissions, which would reduce in time and the provision of environmental monitoring
" justified temporary departure from SG2"
It is thus surprising to read in the Acknowledgement of Service, as set out above, that
"The Defendant does not accept that it departed from SG2 guidance"
and even more so to read in Mr Hosker's second witness statement at paragraph 25 that
" the function of the regulator is to ensure that the standards set (such as emission levels) are achieved. In the case of the Quinn installation the IPPC permit issued ensures that all the standards set in SG2 are achieved by the due dates and the permit had regard to the full standards of the guidance."
" ..the IPPC permit issued ensures that all the standards set in SG2 are achieved by the due dates and the permit had regard to the full standards of the guidance (my italics)
shows in my judgement that, contrary to what was urged on me by Mr Horlock QC, the Acknowledgement of Service was correct as to Mr Hosker's reasoning. The idea of " due dates" could only come from the misuse of Table 1, which was the part of the document the Acknowledgement of Service says was followed. Eversheds could only have known that that is what he did from Chester City Council officers. I find on the balance of probabilities that that is what he did do. I therefore reject those parts of his evidence which contend that he set the limits by reference to what was achievable in fact.
Whether the limits set were actually the lowest achievable
(a) Quinn's own case as put to Chester CC was that lower levels of NOx emission were achievable . In the justification file at tab 5 appears an extract from the Environmental Statement (page 86 in the Courts Bundle 3) for the planning application which was before the Council. It records that
" Quinn Glass recognises that further secondary techniques may be selected to meet future emissions limits, such as enriched oxygen firing or selective non-catalytic reduction, but that the installation of such technology at the outset is not necessary"
The permit itself shows that technology existed which could reduce emissions further. At page 3 (page 7 of the Courts Bundle 3) it reads
"Additionally , the furnace will be equipped from day one to incorporate a retrofit of proven NOx reduction technology if required in the future."
(b) Mr Hosker himself records at paragraph 31 of his first witness statement that the plant had been designed to achieve 1000 mg/Nm3, and had "headroom built in" by the supplier.
(c) The paper of dubious provenance supplied by Quinn (i.e. the " Glass Technology Services January 2005" document) also shows that limits below those permitted were achievable. It states in its conclusions that while (my underlining but italics as per the document)
.currently the majority of the UK glass-making furnaces is emitting NOx in the range 1000-2000 mg/Nm3. A range of technologies are (sic) available to reduce these emissions. The most effective technologies could reduce emissions to below 500 mg/Nm3 but these technologies incur energy penalties and greatly increase CO2 emissions .."
It then argues against 500 mg/Nm3 as a limit, argues against oxyfuel technology as generating CO2 and continues
" A limit of 800 mg/Nm3 would still represent a 40% reduction in NOx emissions and this could be achieved by those primary means which achieve a very small CO2 penalty. 800mg/Nm3 is being achieved by the best operators in Germany and is also the basis for the limit being used for that country .The conclusions drawn from this brief paper is (sic) that a limit for all soda lime glass melters of 800 mg/Nm3 for the emission of NOx from glass manufacturing plants represents the best environmental option at this time."
(d) That is no doubt why its first page states that
" Germany has put a NOx limit of 800mg/m3 on its glass manufacturers. The leading container operators are confident that they can operate within this limit by the use of the latest primary technology." (My underlining)
(e) I refer below to Table 2 of that document when I turn to consider Mr Hosker's assumptions on the effect on greenhouse gases. It shows what happens with an installation which is not fitted secondary abatement (called " primary measures") and after such abatement. It shows that the type of process proposed by Quinn (albeit in a 300 tpd furnace) would produce substantial reductions in NOx even if unabated at the secondary stage ("primary measures") at 800 mg/Nm3 (37% less than at 1300/mg/Nm3) and even greater ones at 500 mg/Nm3 after abatement (57% less) with little difference in CO2 emissions up 2% and 5.4% respectively. (The 300 tpd furnace example was used in that paper and relied on by Quinn and Mr Hosker- as showing the proportionate differences in levels of NOx and CO2 between types of process).
(f) The extracts from the BREF document to which Mr Hosker refers in paragraph 27 of his witness statement also show, and do so beyond argument, that lower levels were achievable with the type of furnace proposed by Quinn. I deal below with the errors Mr Hosker made in connection with BREF.
(g) It follows that either Mr Hosker's evidence is incorrect when it records that he considered that the emissions limits were the lowest that could be achieved, or he had misunderstood what was before him, or failed to take it into account. His reliance on emission control in the primary phase alone is especially unfortunate given the fact that SG 2 specifically drew attention to the importance of secondary abatement techniques in paragraph 3.22 and the subsequent "BAT box." The Glass Technology paper itself showed major reductions once abatement techniques were employed.
(h) The argument that the furnace would produce more NOx because less of its capacity would be taken up by melting glass, and more by air, is hard to reconcile with the description of Furnace Operations in the permit, which show that the amount of air let into the furnace is controlled (my italics)
This furnace type and configuration will enable Quinn Glass to adopt a continuing programme of lowering NOx emissions via primary methods. As .. SG2 states "Achieving the best furnace efficiency means less fuel is used per tonne of glass, which therefore yields less .NOx .. less air is required to burn less fuel so there is less turbulence on the surface of the molten glass. Thus the mass emission of particles is also reduced." Key features of the furnace , providing the means by which such efficiency is achieved, are briefly described below ..
The furnace incorporates sealed low NOx underport low momentum burners. These burners eliminate any secondary air ingress around the gas injector. They also promote staged combustion leading to less NOx .
The furnace atmosphere is tightly controlled. The furnace pressure is measured and controlled to be always positive thus eliminating any air ingress. The furnace has ..regenerators .which allows for accurate measurement of airflow per port. The gas flow is controlled per port in ration with the air. These, combined with continuous oxygen monitoring .allow the very tight control of optimum firing conditions .
The reduction of NOx can be significantly affected by how the furnace is operated. It is important that flame temperatures are kept to a minimum .(methods are then described) ..."
1000 mg/Nm3 by end of Year 1
900 mg/Nm3 by end of Year 2
750 mg/Nm3 by end of Year 3
500 mg/Nm3 by end of Year 4
did not represent the lowest NOx limits that could be achieved, nor did they represent BAT. Indeed on the evidence before him, the installation could certainly achieve 800 mg /Nm3 from the outset, and if the Quinn supplied Glass Technology paper was accepted, probably 500 mg/Nm3 .
" were a reasonable compromise, particularly taking into account that the remaining emissions of pollutants were predicted to be within the standards set by SG 2" (paragraph 8)
" ..they are already very conscious of the concerns about lax NOx standards and the implications for them as well as generally, which is helpful.
I explained I couldn't comment on detail because of appellate position, which he accepted. Seems that there could be a prospect of staged reductions down to 500, which might possibly satisfy BAT and all the parties. Chester will be clearing any proposed decision with their lawyers "
I accept Mr Hosker's evidence that he took Mr Etkind's reaction as one of support for a compromise. In my judgement however Chester CC's fear of another legal challenge played its part. But whichever version is true, the fact is that Mr Hosker and Mr Durham saw the process as in part a negotiation. That lies outwith any of the processes required or permitted under the Directive or the Regulations.
The oxyfuel issue
(a) The COMAH hazard point
(b) The creation of CO2.
Senario (sic) | Units | Unabated | Primary measures |
3R | Oxy-gas |
Furnace emissions | |||||
CO2 | Tonne/year | 30,700 | 31,300 | 32,830 | 26,100 |
NOx concentration |
Mg/m3 | 1300 | 800 | 500 | 500 |
NOx | Tonne/year | 300 | 188 | 123 | 98 |
Generator emissions | |||||
CO2 | Tonne/year | n/a | n/a | n/a | 9051 |
NOx | Tonne/year | n/a | n/a | n/a | 17 |
NOx reduction | Tonne/year | n/a | 112 | 177 | 219 |
CO2 penalty | Tonne/year | n/a | 600 | 2130 | 4451 |
Ratio | n/a | 5:1 | 12:1 | 20:1 |
A: Primary measures @800 mg/Nm3 vs oxy-gas @ 500 mg/Nm3
Senario (sic) | Units | Unabated | Primary measures |
3R | Oxy-gas |
NOx reduction | Tonne/year | - | 0 | ----- | 73 |
CO2 penalty | Tonne/year | n/a | 0 | ------ | 3851 |
Ratio | n/a | 0 | ------ | 53:1 |
B: Primary measures @800 mg/Nm3 vs 3R @ 500 mg/Nm3
Senario (sic) | Units | Unabated | Primary measures |
3R | Oxy-gas |
NOx reduction | Tonne/year | - | 0 | 65 | - |
CO2 penalty | Tonne/year | n/a | 0 | 1530 | - |
Ratio | n/a | 0 | 26:1 | - |
C: 3R @500 mg/Nm3 vs oxy-gas @ 500 mg/Nm3
Senario (sic) | Units | Unabated | Primary measures |
3R | Oxy-gas |
NOx reduction | Tonne/year | - | - | 0 | 35 |
CO2 penalty | Tonne/year | n/a | - | 0 | 2321 |
Ratio | n/a | - | 0 | 66:1 |
" ..nitrogen dioxide is not a global pollutant. It does not, for example, contribute towards global warming. Therefore , local air quality monitoring gives a good picture of any effects emissions from the installation may be having on the environment"
Use of BREF
(a) "I understand that UK standards are tighter than standards in other EU countries. The European Commission has produced its own guidance note, known as a BREF note, which provides recommended levels of 500 to 1100 mg/m3 . In opting for a level of 500 mg /m3 the UK has gone for the tightest possible standard. An extract of the BREF note is at tab 3 of the Justification File" (My italics)
" 650-1100 mg/Nm3 have been achieved in some applications"
However it then went on, in the case of regenerative furnaces like that proposed here to state that , in the case of chemical reduction by fuel (i.e. a secondary measure)
" The 3R process can achieve emission levels of less than 500 mg/Nm3 corresponding to an increase of fuel usage of 6-10% ..the Reburning process is hoped to achieve comparable emission levels following development "
It then describes reductions to below 500 mg/Nm3 as a result of Selective Catalytic Reduction (SCR) and almost as much via Selective Non- Catalytic Reduction (SNCR). I draw attention to the very similar advice given in SG 2. BREF then goes on to state that
" For .container glass it is considered that the emission levels for .(..NOx) associated with the techniques that will generally constitute BAT is 500- 700 mg/Nm3 .."
The relevance of EQS
(a) As Mr Gordon QC submitted, if Mr Hosker and Mr Durham did not consider that they were departing from standards, then the existence of reasons to do so is irrelevant;
(b) In any event, they must consider the effect on EQS in the right context. They must do so against a proper appreciation of the Directive, the Regulations, SG 2 and the material before them, not forgetting the fact that emissions of NOx can be harmful for reasons which cannot be monitored locally;
(c) Mr Hosker's understanding and application of the law, European guidance, national statutory guidance and the evidence before him was so inadequate, for the reasons already given, that the context in which he addressed EQS was itself flawed.
I conclude that Chester City Council
(a) wrongly failed to consider whether alternative configurations, size or design to that proposed would have produced lower emissions of specified pollutants, and in particular oxides of nitrogen (NOx), either in the context of a BAT analysis, or in determining whether the permit should be refused or granted;
(b) in particular, failed to consider whether the use of an oxyfuel process with a different number and size of furnaces would produce lower emission levels of oxides of nitrogen (NOx), and/or would constitute BAT;
(c) misinterpreted and misapplied statutory note SG 2 when considering the date at which the SG 2 recommended emission limit of 500 mg/Nm3 was to be applied to a new installation for the manufacture of container glass;
(d) Took into account an immaterial consideration, namely the emission limits set at other existing UK plants, when considering whether the levels permitted at the application site were BAT for the purposes of the European and UK statutory codes and statutory guidance;
(e) misinterpreted and misapplied the BREF document on achievable emission limits and achieved levels;
(f) acted in breach of the statutory European and UK codes for pollution control by imposing emission limits for oxides of nitrogen (NOx) which were higher than those which were achievable
(g) alternatively, failed to have regard to a material consideration, namely the evidence before it that lower emission limits were achievable for oxides of nitrogen (NOx) if alternative primary secondary techniques were used, and/or if secondary techniques were applied;
(h) when considering the relationship between emissions of CO2 and NOx failed to take into account a material consideration, namely whether oxides of nitrogen (NOx) are global pollutants or are to be treated as greenhouse gases;
(i) failed to give adequate or intelligible reasoning for its conclusions on the above topics
(j) failed to give adequate or intelligible reasoning for its conclusions that the storage of oxygen on site in an oxyfuel process was a matter that justified rejecting that process
(k) failed to give adequate or intelligible reasoning for its conclusions concerning the effects on air quality.
The scope of the Chief Executive's authority
"power to deal with matters where a decision is nominally to be made by the Council is governed substantially by matters of fact or technical factors so that there is no real discretion."
" The only departure from SG2 was in relation to nitrogen dioxide emissions and it did achieve compliance with this after a period of time that seemed reasonable in the circumstances." (my italics)
Relationship to call in
Whether Rockware have sufficient interest to seek or obtain judicial review
(a) Sufficiency of interest should be considered in the context of the facts of the particular case;
(b) The relationship to be considered is that between the claimant/applicant and the subject matter of the decision;
(c) It is not necessary in establishing a sufficiency of interest to show that he has been unfairly discriminated against;
(d) Provided that the threshold is passed of being more than a mere busybody, the question of sufficiency of interest goes to the exercise of discretion.
"..If a claimant has no sufficient private interest to support a claim to standing, then he should not be accorded standing merely because he raises an issue in which there is, objectively speaking, a public interest. As Sedley J said in R v Somerset County Council and ARC Southern Ltd, ex p Dixon [1997] Env LR 111, when considering the issue of standing, the court had to ensure that the claimant was not prompted by an ill-motive, and was not a mere busybody or a trouble-maker. Thus, if a claimant seeks to challenge a decision in which he has no private law interest, it is difficult to conceive of circumstances in which the court will accord him standing, even where there is a public interest in testing the lawfulness of the decision, if the claimant is acting out of ill-will or for some other improper purpose. It is an abuse of process to permit a claimant to bring a claim in such circumstances. If the real reason why a claimant wishes to challenge a decision in which, objectively, there is a public interest is not that he has a genuine concern about the decision, but some other reason, then that is material to the question whether he should be accorded standing."
In R(on the application of Noble Organisation Limited) v Thanet D C [2005] EWCA Civ 782 Auld LJ said
"I would dismiss the appeal. In doing so I add a note of dissatisfaction at the way the availability of the remedy of judicial review can be exploited some might say abused as a commercial weapon by rival potential developers to frustrate and delay their competitors' approved developments, rather than for any demonstrated concern about potential environmental or other planning harm. By the time of the hearing of this appeal, as is often the case, the approved scheme in issue is clearly of a piece with surrounding and much larger approved proposals already taking shape around it. It could not conceivably be regarded as a significant addition to the overall environmental impact of such development. This may be the cause of great economic harm to individual developers and, more importantly, it is likely to frustrate the public interest in much needed regeneration in areas such as the Isle of Thanet. However seemingly complicated the issues are, or how sophisticated and technical the statement of facts and grounds supporting the initial claim for judicial review, they should be subject to rigorous examination by the single judge at the permission stage of a claim for judicial review."
" 30 In practice therefore, the Claimant has a considerable interest in how the IPPC regime is administered. Any glass manufacturer , subject to the IPPC regime, is entitled to expect that it will be enforced in a fair, consistent and even-handed manner. Paragraph 1.12 of the ..Manual for A2 installations speaks of the need to provide " a strong framework for consistent and transparent regulation of activities and installations." .
31 The effect of the IPPC permit is that Quinn is given the advantage of being treated as an existing plant for the purposes of SG2 guidance and NOx emissions, even though it suffers from none of the disadvantages under which existing plants can operate. On the contrary, as a new installation Quinn can design its plant so as to readily accommodate now the secondary abatement techniques that it will have to install to bring NOx emissions down to the levels prescribed in SG 2 from the outset of operations, and required in the permit in 2009.
32 In effect, Quinn will have had a 5 year period of grace. Perversely, Quinn will be allowed as long to comply as existing manufacturers."
Delay
"(1) The claim form must be filed-
(a) promptly; and
(b) in any event not later than 3 months after the grounds to make the claim first arose."
(a) the claimant's solicitors wrote to Quinn's solicitors on 9th March 2005 warning them that it was seeking to challenge the permit on the ground that it conflicted with the call in by the Secretary of State. Although that ground is one I have rejected, there can be no doubt that Quinn was on notice of an impending challenge;
(b) as I have already recorded, on 11th March 2005, Quinn's solicitors replied, making it clear that
" .the development .has been proceeding uninterrupted since October 2003. At the time of your challenge to the approval of amendments to the ..planning permission .our clients have made it abundantly clear that they intended to continue with their development. our clients have made long term contractual commitments to suppliers of materials, plant and equipment, and to glass purchasers, and have employed 118 full time glass manufacturing staff, most of whom are close to completing full-time training the start of production is imminent."
I find that the plans were well advanced before the date of the permit;
(c) as noted above, it was not until 17th March 2005 that Rockware's solicitors received the Justification File after unacceptable delays by Chester CC's solicitors;
(d) Rockware's solicitors sought information from Chester CC's solicitors by letter of 24th March 2005 relating to various important issues; the Glass Technology paper, the relevance of NOx emissions results from other sites in the UK, whether there had been any written report to the Chief Executive or any meetings, conversations, or other exchanges with him before he made his decision, where the Council's reasons were for not complying with SG 2, where the assessment of BAT was to be found, and where the reasons for not using oxy-fuel furnaces were to be found. Each of those questions was very relevant indeed, as subsequent events have shown. Despite chasing letters of 4th April, 6th April and 18th April 2005, it was not until 21st April 2005 that Eversheds got round to replying, and did so in very cursory form. I regard that delay as quite unacceptable.
(e) On 25th April 2005, so just 4 days after getting the reply, DLA sent a letter before claim setting out details of the proposed claim over 10 pages. A copy was also sent to Quinn's solicitors, who replied in very short but robust form on 4th May 2005.
(f) Eversheds replied on 10th May 2005 (over two weeks later) setting out a great deal of information not provided before, over 9 pages. They also attached copies of what are now the first witness statements from Messrs Hosker and Durham. Quinn's solicitors wrote again on 19th May 2005, setting out its case succinctly but again robustly;.
(g) The proceedings were lodged on 24th May 2005, within 14 days of the Eversheds response and receipt of the witness statements, within 6 days of the Quinn response, and within 3 months of the 2nd March 2005.
(h) Meanwhile, Quinn had fired up the furnaces on 11th April 2005. As Mr Taylor accepted, none of the delay after then added at all to any disadvantage sustained by Quinn.
Discretion generally
" principle and pragmatism combine to emphasis the legal fact that judicial review is a remedy of last resort. Where there is set in place an elaborate statutory structure for challenge to, and review of , and administrative decision, the structure must in the ordinary way be fully invoked before seeking to engage the judicial review jurisdiction. There may be exceptional circumstances; a point of principle may need to be determined which, in some cases, can most conveniently be done upon judicial review even before all statutory appeal or review rights have been exhausted."
In this case, unlike the Sandwell case Rockware has no right of appeal or right to statutory review. It seeks to establish an important point of principle on the interpretation of the statutory codes and the application of the statutory guidance. Chester CC has through its counsel asked this court to give guidance. I consider that the circumstances here are ones where judicial review is, by contrast, the route by which those legal principles may be most quickly and efficiently established.
Conclusion
(a) grant permission for Rockware to seek judicial review of the IPPC permit Number IPPC/A2/01/04 issued by Chester City Council on 2nd March 2005 to Quinn Glass Limited to operate an installation at Quinn Business Park, Ash Road, Elton, Cheshire, CH2 4LF
(b) quash the said permit.