ON APPEAL FROM THE HIGH COURT OF JUSTICE
ADMINISTRATIVE COURT
PLANNING COURT
THE HONOURABLE MRS JUSTICE LANG DBE
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE LEWIS
and
LORD JUSTICE WILLIAM DAVIS
____________________
THE KING (on the application of Substation Action Save East Suffolk Ltd.) |
Appellant |
|
- and - |
||
(1) SECRETARY OF STATE FOR ENERGY SECURITY AND NET ZERO (2) EAST ANGLIA ONE NORTH LTD (3) EAST ANGLIA TWO LTD. |
Respondents |
____________________
Mark Westmoreland Smith and Jonathan Welch (instructed by Government Legal Department) for the First Respondent
Hereward Phillpot KC and Hugh Flanagan (instructed by Shepherd and Wedderburn) for the Second and Third Respondents
Hearing date: 6 December 2023
____________________
Crown Copyright ©
LORD JUSTICE LEWIS:
INTRODUCTION
(1) The judge erred in her decision on the flood risk ground, namely:
(a) she regarded the application of the sequential test in respect of flood risk as a lawful exercise of planning judgment, in circumstances where no "sequential" approach was applied at all; and
(b) she made a perverse error of fact in finding that no part of the site was in an area at high risk of surface water flooding, contrary to the evidence and agreement of the parties.
(2) The judge erred in her decision on the cumulative impacts ground namely:
(a) she erred in failing to recognise that the respondent was under a statutory duty to take into account the Extension Appraisal as environmental information and could not disavow it as an irrelevant consideration;
(b) she wrongly elided the potential effects of the Nautilus and Eurolink schemes with the potential effects of the National Grid substation to accommodate those schemes, which was the point in issue.
THE LEGAL FRAMEWORK
The 2008 Act
"(2) In deciding the application the Secretary of State must have regard to—
(a) any national policy statement which has effect in relation to development of the description to which the application relates (a 'relevant national policy statement')
…..
and
(d) any other matters which the Secretary of State thinks are both important and relevant to the Secretary of State's decision.
(3) The Secretary of State must decide the application in accordance with any relevant national policy statement, except to the extent that one or more of subsections (4) to (8) applies.
The National Policy Statement
"5.7. Flood Risk
Introduction
…..
5.7.3 The aims of planning policy on development and flood risk are to ensure that flood risk from all sources of flooding is taken into account at all stages in the planning process to avoid inappropriate development in areas at risk of flooding and to direct development away from areas at highest risk. Where new energy infrastructure is exceptionally necessary in such areas, policy aims to make it safe without increasing flood risk elsewhere and, where possible, by reducing flood risk overall.
Applicant's assessment
5.7.4. Applications for energy projects of 1 hectare or greater in Flood Zone 1 in England … and all proposals for energy projects located in Flood Zones 2 and 3 in England … should be accompanied by a flood risk assessment (FRA). An FRA will also be required where an energy project less than 1 hectare may be subject to sources of flooding other than rivers and the sea (for example surface water) … This should identify and assess the risks of all forms of flooding to and from the project and demonstrate how the flood risk will be managed, taking climate change into account.
…..
5.7.6 Further guidance can be found in the Practice Guide which accompanies Planning Policy Statement 25 (PPS25), TAN15 for Wales or successor documents.
…..
IPC Decision Making
5.7.9 In determining an application for development consent, the IPC should be satisfied that where relevant:
• the application is supported by an appropriate FRA;
• the Sequential Test has been applied as part of site selection;
• a sequential approach has been applied at the site level to minimise risk by directing the most vulnerable uses to areas of lowest flood risk;
• the proposal is in line with any relevant national and local flood risk management strategy
• priority has been given to the use of sustainable drainage systems (SuDs) (as required in the next paragraph on National Standards); and
• in flood risk areas the project is appropriately flood resilient and resistant, including safe access and escape routes where required, and that any residual risk can be safely managed over the lifetime of the development.
…..
5.7.12 The IPC should not consent development in Flood Zone 2 in England … unless it is satisfied that the sequential test requirements have been met. It should not consent development in Flood Zone 3 or Zone C unless it is satisfied that the Sequential and Exception Test requirements have been met …"
The Sequential Test
5.7.13 Preference should be given to locating projects in Flood Zone 1 in England … If there is no reasonably available site in Flood Zone 1 … then projects can be located in Flood Zone 2 … If there is no reasonably available site in Flood Zones 1 or 2 then nationally significant energy infrastructure projects can be located in Flood Zone 3 … subject to the Exception Test. Consideration of alternative sites should take account of the policy on alternatives set out in section 4.4 above."
The National Planning Policy Framework ("the Framework")
"Planning and flood risk
159. Inappropriate development in areas at risk of flooding should be avoided by directing development away from areas at highest risk (whether existing or future). Where development is necessary in such areas, the development should be made safe for its lifetime without increasing flood risk elsewhere.
160. Strategic policies should be informed by a strategic flood risk assessment, and should manage flood risk from all sources. They should consider cumulative impacts in, or affecting, local areas susceptible to flooding, and take account of advice from the Environment Agency and other relevant flood risk management authorities, such as lead local flood authorities and internal drainage boards.
161. All plans should apply a sequential, risk-based approach to the location of development—taking into account all sources of flood risk and the current and future impacts of climate change—so as to avoid, where possible, flood risk to people and property. They should do this, and manage any residual risk, by:
(a) applying the sequential test and then, if necessary, the exception test as set out below;
(b) safeguarding land from development that is required, or likely to be required, for current or future flood management;
(c) using opportunities provided by new development and improvements in green and other infrastructure to reduce the causes and impacts of flooding, (making as much use as possible of natural flood management techniques as part of an integrated approach to flood risk management); and
(d) where climate change is expected to increase flood risk so that some existing development may not be sustainable in the long-term, seeking opportunities to relocate development, including housing, to more sustainable locations.
162. The aim of the sequential test is to steer new development to areas with the lowest risk of flooding from any source. Development should not be allocated or permitted if there are reasonably available sites appropriate for the proposed development in areas with a lower risk of flooding. The strategic flood risk assessment will provide the basis for applying this test. The sequential approach should be used in areas known to be at risk now or in the future from any form of flooding.
163. If it is not possible for development to be located in areas with a lower risk of flooding (taking into account wider sustainable development objectives), the exception test may have to be applied. The need for the exception test will depend on the potential vulnerability of the site and of the development proposed, in line with the Flood Risk Vulnerability Classification set out in Annex 3.
…..
167. When determining any planning applications, local planning authorities should ensure that flood risk is not increased elsewhere. Where appropriate, applications should be supported by a site-specific flood-risk assessment. Development should only be allowed in areas at risk of flooding where, in the light of this assessment (and the sequential and exception tests, as applicable) it can be demonstrated that:
(a) within the site, the most vulnerable development is located in areas of lowest flood risk, unless there are overriding reasons to prefer a different location;
(b) the development is appropriately flood resistant and resilient such that, in the event of a flood, it could be quickly brought back into use without significant refurbishment;
(c) it incorporates sustainable drainage systems, unless there is clear evidence that this would be inappropriate;
(d) any residual risk can be safely managed; and
(e) safe access and escape routes are included where appropriate, as part of an agreed emergency plan."
The Planning Policy Guidance ("PPG")
"7.002 What is "flood risk"?
For the purposes of applying the National Planning Policy Framework, "flood risk" is a combination of the probability and the potential consequences of flooding from all sources – including from rivers and the sea, directly from rainfall on the ground surface and rising groundwater overwhelmed sewers and drainage systems, and from reservoirs, canals and lakes and other artificial sources.
…..
7.018 What is the sequential, risk-based approach to the location of development?
This general approach is designed to ensure that areas at little or no risk of flooding from any source are developed in preference to areas at higher risk. The aim should be to keep development out of medium and high risk flooding areas (Flood Zones 2 and 3) and other areas affected by other sources of flooding where possible.
Application of the sequential approach in the plan-making process, in particular application of the Sequential Test, will help ensure that development can be safely and sustainably delivered and developers do not waste their time promoting proposals which are inappropriate on flood risk grounds.
7.019 The aim of the Sequential Test
What is the aim of the Sequential Test for the location of development?
The Sequential Test ensures that a sequential approach is followed to steer new development to areas with the lowest probability of flooding. The flood zones as refined in the Strategic Flood Risk Assessment for the area provide the basis for applying the Test. The aim is to steer new development to Flood Zone 1 (areas with a low probability of river or sea flooding). Where there are no reasonably available sites in Flood Zone 1, local planning authorities in their decision making should take into account the flood risk vulnerability of land uses and consider reasonably available sites in Flood Zone 2 (areas with a medium probability of river or sea flooding), applying the Exception Test if required. Only where there are no reasonably available sites in Flood Zones 1 or 2 should the suitability of sites in Flood Zone 3 (areas with a high probability of river or sea flooding) be considered, taking into account the flood risk vulnerability of land uses and applying the Exception Test if required.
Within each flood zone, surface water and other sources of flooding also need to be taken into account in applying the sequential approach to the location of development.
…..
Para 7.033 Applying the Sequential Test to individual planning applications
How should the Sequential Test be applied to planning applications?
See advice on the sequential approach to development and the aim of the sequential test.
The Sequential Test does not need to be applied for individual developments on sites which have been allocated in development plans through the Sequential Test, or for applications for minor development or change of use (except for a change of use to a caravan, camping or chalet site, or to a mobile home or park home site).
Nor should it normally be necessary to apply the Sequential Test to development proposals in Flood Zone 1 (land with a low probability of flooding from rivers or the sea), unless the Strategic Flood Risk Assessment for the area, or other more recent information, indicates there may be flooding issues now or in the future (for example, through the impact of climate change).
For individual planning applications where there has been no sequential testing of the allocations in the development plan, or where the use of the site being proposed is not in accordance with the development plan, the area to apply the Sequential Test across will be defined by local circumstances relating to the catchment area for the type of development proposed. For some developments this may be clear, for example, the catchment area for a school. In other cases it may be identified from other Local Plan policies, such as the need for affordable housing within a town centre, or a specific area identified for regeneration. For example, where there are large areas in Flood Zones 2 and 3 (medium to high probability of flooding) and development is needed in those areas to sustain the existing community, sites outside them are unlikely to provide reasonable alternatives.
When applying the Sequential Test, a pragmatic approach on the availability of alternatives should be taken. For example, in considering planning applications for extensions to existing business premises it might be impractical to suggest that there are more suitable alternative locations for that development elsewhere. For nationally or regionally important infrastructure the area of search to which the Sequential Test could be applied will be wider than the local planning authority boundary.
Any development proposal should take into account the likelihood of flooding from other sources, as well as from rivers and the sea. The sequential approach to locating development in areas at lower flood risk should be applied to all sources of flooding, including development in an area which has critical drainage problems, as notified to the local planning authority by the Environment Agency, and where the proposed location of the development would increase flood risk elsewhere.
See also advice on who is responsible for deciding whether an application passes the Sequential Test and further advice on the Sequential Test process available from the Environment Agency (flood risk standing advice).
7.034 "Who is responsible for deciding whether an application passes the Sequential Test?
It is for local planning authorities, taking advice from the Environment Agency as appropriate, to consider the extent to which Sequential Test considerations have been satisfied, taking into account the particular circumstances in any given case. The developer should justify with evidence to the local planning authority what area of search has been used when making the application. Ultimately the local planning authority needs to be satisfied in all cases that the proposed development would be safe and not lead to increased flood risk elsewhere."
The Regulations
"21 Consideration of whether development consent should be granted
(1) When deciding whether to make an order granting development consent for EIA development the Secretary of State must—
(a) examine the environmental information;
(b) reach a reasoned conclusion on the significant effects of the proposed development on the environment, taking into account the examination referred to in sub-paragraph (a) and, where appropriate, any supplementary examination considered necessary;
(c) integrate that conclusion into the decision as to whether an order is to be granted; and
(d) if an order is to be made, consider whether it is appropriate to impose monitoring measures."
"environmental information" means the environmental statement (or in the case of a subsequent application, the updated environmental statement), including any further information and any other information, any representations made by any body required by these Regulations to be invited to make representations and any representations duly made by any other person about the environmental effects of the development and of any associated development".
"'further information' means additional information which, in the view of the Examining authority, the Secretary of State or the relevant authority, is directly relevant to reaching a reasoned conclusion on the significant effects of the development on the environment and which it is necessary to include in an environmental statement or updated environmental statement in order for it to satisfy the requirements of regulation 14(2)"
and
"'any other information' means any other substantive information provided by the applicant in relation to the environmental statement or updated environmental statement"
THE FACTUAL BACKGROUND
The Projects
"15. The applications for development consent comprised an offshore element and an onshore element. The offshore element is for the construction and operation of up to 67 (in the case of EA1N) and 75 (in the case of EA2) wind turbine generators ("WTGs"); together with up to four offshore electrical platforms; an offshore construction, operation and maintenance platform; a meteorological mast; inert-array cables linking the WTGs to each other and to the offshore electrical platforms; platform link cables; and up to two export cables to take the electricity generated by the WTGs from the offshore electrical platforms to landfall. The proposed generating capacity was up to 800MW for EA1N and up to 900MW for EA2."
16. The onshore works in respect of both applications include landfall connection works north of Thorpeness in Suffolk, with underground cables running to a new onshore substation located next to Friston, Suffolk. The onshore works also include the realignment of existing overhead power lines and the construction of a new National Grid substation at Friston. The proposal is therefore that the Friston site will accommodate a substation for each of EA1N and EA2, and a new National Grid NSIP comprising a substation and cable sealing ends connected to the realigned overhead lines. The site at Friston extends to 46.28 hectares."
The Applications
"124. The Environment Agency's Long Term Flood Risk Information map (Environment Agency undated) (Figure 20.3.3) shows the onshore development area is primarily in an area at primarily low risk of surface water flooding i.e. outside the extent of the 1 in 1,000 year surface water flooding event.
125. However, the National grid Substation National Grid CCS cable sealing end compounds and permanent access road are located in an area with varying risk of surface water flooding. The northern and western boundary around the National Grid substation, including the cable sealing and compounds, and part of the footprint of the National Grid substation, includes areas at both high risk of surface water flooding i.e. during the 1 in 30 year event and medium risk of surface water flooding i.e. there is a risk of flooding during the 1 in 100 year vent. This flood risk is associated with the drainage of surface water from the north in proximity to Little Moor Farm.
126. The onshore substation and onshore substation CCS are located in areas primarily at low risk of surface water flooding i.e. outside the extent of the 1 in 1,00-year surface water flooding event.
127. As part of the onshore substation and National Grid infrastructure a permanent access road will be built up to the north-east of Moor Farm, connecting to both the onshore substation and National Grid substation. In addition, permanent access tracks to the cable sealing end compounds will be built to the north of the National Grid substation. Parts of the access roads are likely to cross areas at both high risk of surface water flooding i.e. during the 1 in 30-year event and medium risk of surface water flooding i.e. there is a risk of flooding during the 1 in 100-year event (Figure 20.3.3).
128. The surface water flood risk extends downstream to Friston, where they have been several reports of historical flooding, as providing by local residents. Flood incident records as recorded by the LLFA are reported as having a low priority, and are generally located along the B1121 Saxmundham Road (Suffolk County Council 2018a and b).
129. Flood risk from surface water to the onshore substation and National Grid infrastructure and off-site as a result of the proposed East Anglia one North project will be addressed through the development of a detailed drainage design, the beginnings of which are provided in the Outline Landscape and Ecological Management Strategy (OLEMS), as secured under the requirements of the draft DCO, and submitted with this DCO application. Existing land drains will need to be reinstated and/or connected into the formal drainage network following construction.
130. A local specialised drainage contractor will undertake surveys, locate drains, create drawings pre- and post-construction, and ensure appropriate reinstatement. The Surface Water and Drainage Management Plan will include provisions to minimise flood risk within the working area and ensure ongoing drainage of surrounding land.
131. The Surface Water and Drainage Management Plan, as secured under the requirements of the draft DCO, will include Sustainable Drainage System (SuDS) measures. Further detail is provided in the OCoCP submitted with this DCO application.
132. Further details related to management of surface water flood risk and drainage for the onshore substation and National Grid infrastructure is considered within section 20.7."
"From the outset the Applicants have committed to mitigating and managing surface water within the Order limits so as not to exacerbate flood risks to downstream receptors and the evidence supports that this is possible. In higher return period events, the Applicants anticipate the operational SuDS will provide a betterment to the existing surface water regime within the Order limits, in turn providing for both the Projects and the residents of Friston by containing excess surface water and ensuring it is discharged as a controlled rate.
The Applicants have provided plans showing the locations of the indicative designs together with the calculations that support the sizing".
The Examining Authority Report
"28.4.4. In the ExA's judgement, the benefits of the Proposed Development at the national scale, providing highly significant additional renewable energy generation capacity in scalar terms and in a timely manner to meet need, are sufficient to outweigh the negative impacts that that have been identified in relation to the construction and operation of the Proposed Development at the local scale. The local harm that the ExA has identified is substantial and should not be underestimated in effect. Its mitigation has in certain key respects been found to be only just sufficient on balance. However, the benefits of the Proposed Development principally in terms of addressing the need for renewable energy development identified in NPS EN-1 outweigh those effects. In terms of PA 2008 section 104(7) the ExA specifically finds that the benefits of the Proposed Development do on balance outweigh its adverse impacts.
28.4.5. In reaching this conclusion, the ExA has had regard to the effect of the Proposed Development cumulatively with the other East Anglia development and with such other relevant policies and proposals as might affect its development, operation or decommissioning and in respect of which there is information in the public domain. In that regard, the ExA observes that effects of the cumulative delivery of the Proposed Development with the other East Anglia development on the transmission connection site near Friston are so substantially adverse that utmost care will be required in the consideration of any amendments or additions to those elements of the Proposed Development in this location. This ExA does not seek to fetter the discretion of future decision-makers about additional development proposals at this location. However, it can and does set out a strong view that the most substantial and innovative attention to siting, scale, appearance and the mitigation of adverse effects within design processes would be required if anything but immaterial additional development were to be proposed in this location.
28.4.6. In relation to this conclusion, the ExA observes that particular regard needs to be had at this location to flood and drainage effects (where additional impermeable surfaces within the existing development site have the potential to affect the proposed flood management solution), to landscape and visual impacts and to impacts on the historic built environment, should these arise from additional development proposals in the future.
28.4.7. The ExA concludes overall that, for the reasons set out in the preceding chapters and summarised above, the SoS should decide to grant development consent.
28.4.8. The ExA acknowledges that this is a conclusion that may well meet with considerable dismay amongst many local residents and businesses who became IPs and contributed positively and passionately to the Examination across a broad range of matters and issues. To them the ExA observes that their concerns are real and that the planning system provided a table to which they could be brought. However, highly weighty global and national considerations about the need for large and timely additional renewable energy generating capacity to meet need and to materially assist in the mitigation of adverse climate effects due to carbon emissions have to be accorded their due place in the planning balance. In the judgment of the ExA, these matters must tip a finely balanced equation in favour of the decision to grant development consent for the Proposed Development."
The First Respondent's Decision
"8. The onshore substation and National Grid infrastructure locations were also reviewed against the Environment Agency's surface water flood risk mapping and identified as being located in an area predominantly at very low risk of surface water flooding Furthermore, the National Grid substation location was selected in full cognisance of the presence of a shallow surface water flow route (comprising approximately 4cm of water depth during a 1 in a 100 year storm event), noting that such features can be diverted and their continued conveyance ensured using well established and proven techniques. A commitment to this is made within the Outline Operational Drainage Management Plan (OODMP) … along with a commitment to offset any reduction volume relating to other existing surface water features affected at the substation locations."
"22. The revised focus of the wording in the NPPF and accompanying Planning Practice Guidance acknowledges the need to consider all sources of flooding; however, it does not provide any criteria for their assessment on their suitability in terms of location (similar to that provided for the flood zones and vulnerability of a development) which can be used to determine whether a development is appropriate or not.
23. While the Applicants have considered all sources of flooding, in the absence of any criteria as to how this should be implemented, they have sought to address the potential risk from surface water flooding by locating the onshore substations and National Grid infrastructure in an area at low risk of surface water flooding, and by adopting appropriate mitigation measures within the design to address any remaining surface water flood risk concerns."
"First, the decision letter deals with the responses to the change in the wording of the Framework in paragraph 4.27 and noted the following:"
"4.27 The Secretary of State consulted on the issue of updates to the NPPF on 2 November 2021 and 20 December 2021, the key responses are summarised below:
• SCC (the Lead Local Flood Authority)—the changes to the NPPF would require the Applicant to undertake a Sequential Test, and if necessary, an Exception Test. However, SCC acknowledge that as the PPG has not been updated, it is not clear how the Sequential and Exception Tests would be applied.
• ESC—states that the reference in the updated NPPF has the potential to have important implications for the East Anglia ONE North and East Anglia TWO projects. However, they also acknowledge that as the PPG has not been updated, it is not clear how the Sequential and Exception Tests would be applied.
• SASES—consider that it is clear from the Applicant's submissions that surface water and ground water were not taken into account during the site selection process and, consequently, the Sequential test was not properly applied. Additionally, SASES consider that the updates to the NPPF do not impose any new policy requirement but rather reinforce the existing requirements. SASES also reiterated that they considered the infiltration testing conducted by the Applicant was insufficient and had concerns about the Applicant's approach to applying the Sequential Test. Overall, SASES considered that because of the defects of the Applicant's approach, that policy requirements had not been met.
• The Applicant—acknowledges that the updated NPPF is more explicit in the use of the term 'any source' of flooding but note that the criteria for the assessment and application of the Sequential Test remains unchanged, and that the PPG does not provide any criteria for the assessment of suitability of a location to determine whether a development is appropriate or not. The Applicant also highlighted:
(i) they have considered all sources of flooding in the design of the Proposed Development;
(ii) the substation site and National Grid infrastructure have been located in an area at low risk of surface water flooding;
(iii) appropriate mitigation measures have been adopted to address any remaining surface water flood risk concerns;
(iv) SCC had already given surface water flooding equal weighting when reviewing the Proposed Development's assessment of flood risk throughout the examination;
(v) that the emphasis in the updated NPPF to move away from hard engineered flood solutions is not considered by the Applicant to be a fundamental change that would alter their proposed drainage strategy or adoption of SuDS measures;
(vi) that the extensive landscape planting proposed would reduce the speed of surface water runoff compared to that currently experienced, as well as soil erosion and silt levels in runoff;
(vii) modelling undertaken for the Friston Surface Water Flood Study15 confirms that surface water flooding within Friston primarily results from surface water flow from a number of locations unrelated to the substation site; and
(viii) by attenuating surface water and ensuring a controlled discharge rate from the site there is no increase in flood risk to the surrounding area, specifically Friston."
"4.28 The Secretary of State notes that all sources of flooding have been considered by the Applicant in the design of the Proposed Development, he also notes the surface water mitigation measures which the Applicant has proposed to address flood risk concerns. Furthermore, the Secretary of State has considered all the consultation responses relevant to the NPPF updates and, noting that the guidance on how the Sequential Test should be applied in respect of all sources of flooding has not been updated, is satisfied that the Applicant has (as it is currently defined) applied the Sequential Test as part of site selection. As such, the Secretary of State considers that the FRA is appropriate for the Application."
"5.12 In response to significant concerns from a number of parties (including the Councils') about future projects, the Applicant submitted an Extension of National Grid Substation Appraisal. This Appraisal assessed the potential effects of extending the National Grid substation to accommodate future projects, including: Nautilus interconnector, EuroLink interconnector, North Falls and Five Estuaries offshore wind farms. However, the Appraisal states "it has been confirmed by both the proposed North Falls and Five Estuaries projects that they will not connect near Leiston.
5.13 The Secretary of State notes that the future projects considered are in the following stages of development:
• Nautilus interconnector—National Grid Ventures requested a section 35 direction under the Planning Act 2008 on 4 March 2019, the Secretary of State received further information from National Grid Ventures on 4 April 2019 and a direction was made by the Secretary of State on 29 April 2019. The application is expected to be submitted to the Planning Inspectorate Q2 2023.
• EuroLink interconnector—is a proposal by National Grid Ventures to build a HVDC transmission cable between the UK and the Netherlands. The capacity of the link will be 1.4 GW and the project is still in the very early stages of development. No information on this project has currently been submitted to the Planning Inspectorate or the Secretary of State.
"5.14 Currently, the only documentation available on the Planning Inspectorate's website for the Nautilus interconnector project is the Section 35 Direction made by the Secretary of State for the proposed development to be treated as development for which development consent is required under the 2008 Act. The Eurolink interconnector project is earlier in the development consent process than Nautilus, and no documentation has been submitted to the Planning Inspectorate. Consequently, there is very limited environmental information available which would allow the Applicant to conduct a cumulative assessment. The Applicant's decision not to include these proposed projects in its cumulative effects assessment is also supported by the Planning Inspectorate's Advice Note Seventeen: Cumulative effects assessment relevant to nationally significant infrastructure projects. Paragraph 3.3.1 of the Advice Note lists the information required to conduct stage 4 of a cumulative effects assessment:
• proposed design and location information;
• proposed programme of construction, operation and decommissioning; and
• environmental assessments that set out baseline data and effects arising from the 'other existing development and/or approved development'.
"5.15 As none of the above information was available prior to the close of the East Anglia ONE North and East Anglia TWO examination period for either the Nautilus or Eurolink projects, the Secretary of State is content that it was not necessary for the Applicant to include these proposed projects in its cumulative effects assessment. Further details of the Secretary of State's position on the inclusion of these projects in the Applicant's cumulative assessment can be found in paragraph 12.14 of this document.
"5.16 The ExA concludes that: 'The extension of National Grid Substation Appraisal demonstrates a significant worsening of potential adverse effects for relevant VPs [Viewpoints] and for landscape character. The extension of the NG substation would intensify and worsen the effects of the Proposed Development on both the local landscape and on visual receptors. Such an effect would be added to in an unknown way by the provision of required surface water drainage."
"5.22 In reaching the above conclusions the ExA has not considered the Extension of National Grid Substation Appraisal, noting that the Applicant acknowledges that the Appraisal is 'environmental information' and is not intended to comprise a Cumulative Impact Assessment.
"5.23 The Secretary of State agrees with the ExA's conclusions on Landscape and Visual Amenity."
THE JUDGMENT BELOW
"58. I agree with the submission made by the defendant and the applicants that, whilst NPS EN-1 refers to all sources of flooding, the specific guidance on the application of the sequential test only refers to the location of projects in different flood zones. Whilst flood zones are plainly relevant, they are designated on the basis of the risk of fluvial flooding, not surface water or other sources of flooding, and so they are not a sufficient means of assessing surface water flood risks. Therefore, it is a matter of judgment for an applicant, and ultimately the decision-maker, as to how to apply the sequential test to flood risks from other sources, such as surface water."
"64. It is apparent that the Framework and the PPG require surface water flooding to be taken into account when considering location of development, as part of the sequential approach, but, beyond that, there is no further direction as to exactly how surface water flooding is to be factored into the sequential approach. Policy and guidance is not prescriptive in this regard. Therefore it will be a matter of judgment for the applicant and the decision-maker (as envisaged in para 7.034 of the PPG) as to how to give effect to the policy appropriately, in the particular circumstances of the case."
65. I accept the submission of the defendant and applicants that neither the policies nor the guidance support the claimant's submission that the application of the sequential test means that, where there is some surface water flood risk, it must be positively demonstrated that there are no sites reasonably available for the development with lower surface water flood risk."
"79. At DL 4.27, the defendant noted the applicants' position that all sources of flooding had been assessed with regard to the onshore substations, and that the wider area, including the village of Friston, would not be adversely affected. The substation and infrastructure were located in an area at low risk of surface water flooding, and appropriate mitigation measures had been adopted to address any remaining surface water flood risk concerns, by attenuating surface water and ensuring a controlled discharge rate from the site. There was no increase in flood risk to the surrounding area, specifically Friston."
"197. I accept the submissions made by the defendant and the applicants that the approach taken by the defendant did not constitute a breach of the EIA Regulations 2017. The developments in question were not "existing and/or approved projects" in respect of which a cumulative assessment would be required by reference to paragraph 5 of Schedule 4 to the EIA Regulations 2017".
198. The Extension Appraisal did not constitute a cumulative impact assessment for the reasons set out in that document at 1.1. The two projects were at such an early stage that there was not sufficient reliable information to undertake a satisfactory cumulative assessment. That approach was in accordance with the guidance in Advice Note Seventeen.
199. The ExA and the defendant were entitled to regard the Extension Appraisal as "environmental information" but not "further information", as defined in regulation 3 of the EIA Regulations 2017 , as it was not "additional information which, in the view of the Examining authority, the Secretary of State or the relevant authority, is directly relevant to reaching a reasoned conclusion on the significant effects of the development on the environment and which it is necessary to include in an environmental statement … in order for it to satisfy the requirements of regulation 14(2)".
200. Like all other representations made by the applicants about the environmental effects of the development (ie "environmental information" as defined in regulation 3), the Extension Appraisal was carefully examined by the ExA, and fully taken into account by the defendant when making his decision. The issues of flooding and transport were considered in the screening assessment with the Extension Appraisal, but were not taken forward for further assessment.
201. The defendant was entitled, as the decision-maker, to disagree with the ExA's statement that satisfactory assumptions could have been made to allow the future projects to be included in the cumulative impact assessment, for the reasons he gave at DL 12.14–12.19. Furthermore, although the claimant relied upon the ExA's description of the decision as "finely balanced", the defendant took a different view and concluded that the applicants had a strong case (DL 27.7).
202. In my judgment, the defendant's approach cannot be characterised as irrational. He was entitled to agree, in the exercise of his judgment, with the applicants' case that the uncertainties about the future projects were such that it was not possible to undertake a reliable assessment of cumulative effects for the purposes of regulation 21(1)(b) of the EIA Regulations 2017.
203. Finally, I consider that the reasons given for the decision were clear and sufficient, and met the legal standard."
THE FIRST GROUND OF APPEAL – FLOOD RISK FROM SURFACE
WATER
Submissions
Discussion
THE SECOND GROUND – ASSESSMENT OF CUMULATIVE IMPACTS
Submissions
Discussion
CONCLUSION
LORD JUSTICE WILLIAM DAVIS
LORD JUSTICE COULSON