ON APPEAL FROM Queen's Bench Division, Technology & Construction Court
Mr Justice Edwards-Stuart
HT-2016-000089 & HT-2016-000096
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE LINDBLOM
and
LADY JUSTICE THIRLWALL
____________________
Adam Architecture Limited |
Claimant / Appellant |
|
- and - |
||
Halsbury Homes Limited |
Defendant / Respondent |
____________________
David Sears QC (instructed by Myers Fletcher & Gordon Solicitors) for the Respondent
Hearing date: Wednesday 11th October 2017
____________________
Crown Copyright ©
Lord Justice Jackson :
Part 1 Introduction |
Paragraphs 2 - 13 |
Part 2 The facts |
Paragraphs 14 26 |
Part 3 The present proceedings |
Paragraphs 27 33 |
Part 4 The appeal to the Court of Appeal |
Paragraphs 34 41 |
Part 5 Ground 1: The effect of Section 111 of the 1996 Act |
Paragraphs 42 65 |
Part 6 Ground 2: Repudiation |
Paragraphs 66 74 |
Part 7 Conclusion |
Paragraphs 75 76 |
"109.- Entitlement to stage payments.
(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless
(a) it is specified in the contract that the duration of the work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
(4) References in the following sections to a payment include a payment by virtue of this section.
110.- Dates for payment.
(1) Every construction contract shall
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
(b) provide for a final date for payment in relation to any sum which becomes due.
The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
(1A) The requirement in subsection (1)(a) to provide an adequate mechanism for determining what payments become due under the contract, or when, is not satisfied where a construction contract makes payment conditional on
(a) the performance of obligations under another contract, or
(b) a decision by any person as to whether obligations under another contract have been performed.
(1B) In subsection (1A)(a) and (b) the references to obligations do not include obligations to make payments (but see section 113).
(1C) Subsection (1A) does not apply where
(a) the construction contract is an agreement between the parties for the carrying out of construction operations by another person, whether under sub-contract or otherwise, and
(b) the obligations referred to in that subsection are obligations on that other person to carry out those operations.
(1D) The requirement in subsection (1)(a) to provide an adequate mechanism for determining when payments become due under the contract is not satisfied where a construction contract provides for the date on which a payment becomes due to be determined by reference to the giving to the person to whom the payment is due of a notice which relates to what payments are due under the contract.
(2)
(3) If or to the extent that a contract does not contain such provision as is mentioned in subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.
110A Payment notices: contractual requirements
(1) A construction contract shall, in relation to every payment provided for by the contract-
(a) require the payer or a specified person to give a notice complying with subsection (2) to the payee not later than five days after the payment due date, or
(b) require the payee to give a notice complying with subsection (3) to the payer or a specified person not later than five days after the payment due date.
(2) A notice complies with this subsection if it specifies-
(a) in a case where the notice is given by the payer-
(i) the sum that the payer considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated;
(b) in a case where the notice is given by a specified person-
(i) the sum that the payer or the specified person considers to be or to have been due at the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated.
(3) A notice complies with this subsection if it specifies-
(a) the sum that the payee considers to be or to have been due at the payment due date in respect of the payment, and
(b) the basis on which that sum is calculated.
(4) For the purposes of this section, it is immaterial that the sum referred to in subsection (2)(a) or (b) or (3)(a) may be zero.
(5) If or to the extent that a contract does not comply with subsection (1), the relevant provisions of the Scheme for Construction Contracts apply.
(6) In this and the following sections, in relation any payment provided for by a construction contract-
"payee means the person to whom the payment is due;
"payer" means the person from whom the payment is due;
"payment due date" means the date provided for by the contract as the date on which the payment is due;
"specified person" means a person specified in or determined in accordance with the provisions of the contract.
110B Payments notices: payee's notice in default of payer's notice
(1) This section applies in a case where, in relation to any payment provided for by a construction contract-
(a) the contract requires the payer or a specified person to give the payee a notice complying with section 110A(2) not later than five days after the payment due date, but
(b) notice is not given as so required.
(2) Subject to subsection (4), the payee may give to the payer a notice complying with section 110A(3) at any time after the date on which the notice referred to in subsection (1)(a) was required by the contract to be given.
(3) Where pursuant to subsection (2) the payee gives a notice complying with section 110A(3), the final date for payment of the sum specified in the notice shall for all purposes be regarded as postponed by the same number of days as the number of days after the date referred to in subsection (2) that the notice was given.
(4) If
(a) the contract permits or requires the payee, before the date on which the notice referred to in subsection (1)(a) is required by the contract to be given, to notify the payer of a specified person of
(i) the sum that the payee considers will become due on the payment due date in respect of the payment, and
(ii) the basis on which that sum is calculated, and
(b) the payee gives such notification in accordance with the contract,
that notification is to be regarded as a notice complying with section 110A(3) given pursuant to subsection (2) (and the payee may not give another such notice pursuant to that subsection).
111 Requirement to pay notified sum
(1) Subject as follows, where a payment is provided for by a construction contract, the payer must pay the notified sum (to the extent not already paid) on or before the final date for payment.
(2) For the purposes of this section, the "notified sum" in relation to any payment provided for by a construction contract means
(a) in a case where a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(b) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with a requirement of the contract, the amount specified in that notice;
(c) in a case where a notice complying with section 110A(3) has been given pursuant to and in accordance with section 110B(2), the amount specified in that notice.
(3) The payer of a specified person may in accordance with this section give to the payee a notice of the payer's intention to pay less than the notified sum.
(4) A notice under subsection (3) must specify-
(a) the sum that the payer considers to be due on the date the notice is served, and
(b) the basis on which that sum is calculated.
It is immaterial for the purposes of this subsection that the sum referred to in paragraph (a) or (b) may be zero.
(5) A notice under subsection (3)-
(a) must be given not later than the prescribed period before the final date for payment, and
(b) in a case referred to in subsection (2)(b) or (c), may not be given before the notice by reference to which the notified sum is determined.
(6) Where a notice is given under subsection (3), subsection (1) applies only in respect of the sum specified pursuant to subsection (4)(a).
(7) In subsection (5), "prescribed period" means-
(a) such period as the parties may agree, or
(b) in the absence of such agreement, the period provided by the Scheme for Construction Contracts.
(8) Subsection (9) applied where in respect of a payment-
(a) a notice complying with section 110A(2) has been given pursuant to and in accordance with a requirement of the contract (and no notice under subsection (£) is given), or
(b) a notice under subsection (3) is given in accordance with this section.
but on the matter being referred to adjudication the adjudicator decides that more than the sum specified in the notice should be paid.
(9) In a case where this subsection applies, the decision of the adjudicator referred to in subsection (8) shall be construed as requiring payment of the additional amount not later than-
(a) seven days from the date of the decision, or
(b) the date which apart from the notice would have been the final date for payment,
whichever is the later.
(10) Subsection (1) does not apply in relation to a payment provided for by a construction contract where-
(a) the contract provides that, if the payee becomes insolvent the payer need not pay any sum due in respect of the payment, and
(b) the payee has become insolvent after the prescribed period referred to in subsection (5)(a).
(11) Subsections (2) to (5) of section 113 apply for the purposes of subsection (10) of this section as they apply for the purposes of that section."
"109 Entitlement to stage payments.
(1) A party to a construction contract is entitled to payment by instalments, stage payments or other periodic payments for any work under the contract unless-
(a) it is specified in the contract that the duration of the work is to be less than 45 days, or
(b) it is agreed between the parties that the duration of the work is estimated to be less than 45 days.
(2) The parties are free to agree the amounts of the payments and the intervals at which, or circumstances in which, they become due.
(3) In the absence of such agreement, the relevant provisions of the Scheme for Construction Contracts apply.
(4) References in the following sections to a payment under the contract include a payment by virtue of this section.
110 Dates for payment.
(1) Every construction contract shall
(a) provide an adequate mechanism for determining what payments become due under the contract, and when, and
(b) provide for a final date for payment in relation to any sum which becomes due.
The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment.
(2) Every construction contract shall provide for the giving of notice by a party not later than five days after the date on which a payment becomes due from him under the contract, or would have become due if-
(a) the other party had carried out his obligations under the contract, and
(b) no set-off or abatement was permitted by reference to any sum claimed to be due under one or more other contracts,
specifying the amount (if any) of the payment made or proposed to be made, and the basis on which that amount was calculated.
(3) If or to the extent that a contract does not contact such provision as is mentioned in subsection (1) or (2), the relevant provisions of the Scheme for Construction Contracts apply.
111 Notice of intention to withhold payment.
(1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment.
The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section.
(2) To be effective such a notice must specify-
(a) the amount proposed to be withheld and the ground for withholding the payment, or
(b) if there is more than one ground, each ground and the amount attributable to it, and must be given not later than the prescribed period before the final date for payment.
(3) The parties are free to agree what that prescribed period is to be.
In the absence of such agreement, the period shall be that provided by the Scheme for Construction Contracts.
(4) Where an effective notice of intention to withhold payment is given, but on the matter being referred to adjudication it is decided that the whole or part of the amount should be paid, the decision shall be construed as requiring payment not later than-
(a) seven days from the date of the decision, or
(b) the date which apart from the notice would have been the final date for payment,
whichever is the later."
"Payment notices
5.14 The Architect shall issue payment notices at the intervals specified in the schedule of Fees and expenses.
Each notice shall comprise the Architect's account setting out the sum that the Architect considers to be due at the payment due date including all accrued instalments of the fee and other amounts due, less any amounts previously paid and stating the basis on which that sum is calculated, which shall be "the notified sum". The payment due date shall be the date of the Architect's payment notice. Instalments of fees shall be calculated on the Architect's reasonable estimate of the percentage of completion of the Services or stages or other services or any other specified method.
The Client shall pay the notified sum within 14 days of the date of issue of the relevant notice (which shall be the "final date for payment") unless:
(a) The Architect has become insolvent (as defined in the Construction Acts at any time between the last date on which the Client could have issued the Notice under 5.15 and the final date for payment);
(b) The Client issues a notice under 5.15.
Otherwise the amount due and payable shall be the notified sum. The Client shall not delay payment of any undisputed part of the notified sum,
The Architect shall submit the final account for fees and any other amounts due when the Architect reasonably considers the Services have been completed.
Notice of intention to pay less
5.15 If the Client intends to pay less than the notified sum the Client shall give a written notice to the Architect not later than five days before the final date for payment specifying the amount that the Client considers to be due on the date the notice is served, the basis on which that sum is calculated and, if any sum is intended to be withheld, the ground for doing so or, if there is more than one ground, each ground and the amount attributable to it. The Client shall on or before the final date for payment make payment to the Architect of the amount if any specified in the written notice.
If no such notice is given the amount due and payable shall be the notified sum stated as due in the Architect's account. The Client shall not delay payment of any undisputed part of the account. If the Client issues such a notice and the matter is referred to an adjudicator who decides that an additional sum greater than the amount stated in the notice of intention to pay less is due, the Client shall pay that sum within seven days of the date of the decision or the date which apart from the notice would have been the final date for payment.
Payment on suspension or termination
5.17 If the Architect or the Client suspends performance of any or all of the Services or terminates performance of the Services and/or other obligations the Architect shall issue an account or accounts as soon as reasonably practicable and the Architect shall be entitled to:
5.17.1 payment of any part of the fee and other amounts properly due to the date of the last instalment and a fair and reasonable amount up to the date of termination or suspension; and
5.17.2 payment of any licence fee due under clause 6; and
5.17.3 reimbursement of any loss and/or damages caused to the Architect by reason of the suspension of the termination, save where the Client gives notice of suspension or termination by reason of the material or persistent breach of the Agreement by the Architect.
Termination
8.2 The provisions for termination are:
8.2.1 The Client or the Architect may by giving reasonable notice to the other terminate performance of the Services and/or other obligations, stating the reasons for doing so and the Services and obligations affected."
Stage 1: Site analysis and feasibility | £12,750 |
Stage 2: Develop layout | £23,125 |
Stage 3: Design development | £66,650 |
Stage 4: Reserved matters planning application | £53,750 |
Total | £156,275 |
Adam stated that its appointment would be subject to the RIBA Conditions.
"As discussed with yourself and Jonathan approx 3 weeks ago we are utilising both Robert Adam Architects and Vince Douglas who is a local Architect for this scheme.
I have now agreed that we will be using his Layout for this scheme and incorporating the various House styles that have been drawn for this development.
We are not totally against including a dutch gable but both Phillip and I do not like the version you have included on the 3 Bed Detached house type, it does not appear to follow the style of that used on the Trowse development.
We want to work with you on this Development and to include the House styles you have drawn but will utilise ASD as the Architect who will prepare the application and with the benefit of their in house Engineering practice will have the ability to coordinate all of the Road and Sewer designs, Roundabout, realignment of George Lane, Play area and other associated technical matters."
"Thank you for the note. This is not quite how I understood the relationship between ASD and ourselves was to develop. We had discussed engineering input from ASD but the layout design to come from us. As I have noted before, we design places, we do not assemble house types and the design of the layout is an essential part of that. If we have no input on the layout then there is really no place for us in this project."
Ten minutes after that Mr Jonathan Fox of Adam sent an email to Halsbury stating that he had been instructed to stop work. All work duly stopped.
"Following David Bryant's notification to us on 2nd December 2015 that we are no longer to be responsible for the masterplan at Loddon, our original scope of work is void. Our fee proposal of 7th October 2015 provided for a full service, from Site Analysis and Feasibility work through to preparation of material for the Reserved Matters Planning Application. Work was initiated under this proposal in October including the preparation of a draft layout for discussion at the Design Team Meeting held on 29th October 2015.
During November, we made frequent requests for input and comment on the layout. None was forthcoming. In parallel, given the deadline for submitting the planning application, you asked us to progress the House Types. We had every expectation that we would continue to work together on the layout as confirmed in our Design Team Meeting notes dated 29th October 2015. This is clearly no longer the case.
This represents a break in our anticipated design brief and, as we will not wish to work other than with our own layout, casts our continued involvement into doubt. Our agreed fee is no longer relevant and, all other matters considered, we need to draw a line under our work to date. Our invoice is enclosed which is due for payment by 24th December 2015."
i) The pay less regime did not apply to the December invoice;
ii) Halsbury was not liable to pay that invoice;
iii) The adjudicator's decision was unenforceable.
Adam issued proceedings under CPR Part 7 to enforce the adjudicator's decision.
i) Halsbury's email to Adam dated 2nd December 2015 was a repudiation of the contract of engagement.
ii) Adam accepted the repudiation by (a) its two emails of 2nd December, (b) stopping work on 2nd December, (c) its letter dated 3rd December with the invoice dated 30th November attached.
iii) Even though Halsbury did not intend to pay the invoiced sum, it was not contractually required to serve a pay less notice, for three separate reasons:
a) The contract had been discharged, so that neither party was required to perform its primary obligations under the contract.
b) The invoice sent on 3rd December was a final account within the meaning of the last sentence of clause 5.14 of the RIBA Conditions, with the consequence that the invoiced sum was not "the notified sum" as defined in the first sentence of clause 5.14.
c) The invoice sent on 3rd December was a termination account under clause 5.17 of the RIBA Conditions, with the consequence that the invoiced sum was not "the notified sum" as defined in the first sentence of clause 5.14.
iv) Accordingly Halsbury was entitled to the declaration which it sought.
v) In those circumstances, the issue upon which the adjudicator had reached his temporarily binding decision was now finally decided.
vi) Therefore the court would not enforce the adjudicator's decision, but would instead dismiss Adam's claim in the enforcement proceedings.
i) Even though the contract of engagement only required pay less notices in respect of interim applications, section 111 of the 1996 Act required pay less notices in respect of both interim applications and any final account or termination account.
ii) The judge erred in his decision on repudiation. Alternatively, he ought not to have dealt with that complex issue in Part 8 proceedings.
iii) The court has not decided the dispute which was the subject of adjudication. Therefore the court ought to have enforced the adjudicator's decision.
"AA specifically conceded at the outset of the hearing that it did not seek to argue that the payment provisions of the parties' agreement were non-compliant with the statutory payment provisions set out in the Housing Grants, Construction and Regeneration Act 1996 (as amended)."
"9. The time period during which matters can be checked before the final certificate is to be issued is much longer than that for interim certificates. That is as one would expect. In this case it is essentially three months. In practice therefore a final certificate is more likely to be accurate than an interim certificate. But nothing actually turns on this for it is common ground that section 111(1) applies to both interim and final certificates.
10. It was the debate about a final certificate which brought out the true nature of the provision. Suppose a final certificate included items not done or charged for twice and the time for serving a withholding notice has passed. An obvious concern would arise if the provision had the effect of not only requiring the client to pay for such items, but was conclusive. The section would override the contractual term specifically saying certificates are not conclusive. But the section does not say that failure to service a withholding notice creates an irrebuttable presumption that the sum is in the final analysis properly payable. It merely says the paying party "may not withhold payment of a sum due". This throws one back to the contract to find the answer to how the sum is determined and when it is due."
" In the absence of a withholding notice, section 111(1) operates to prevent the client withholding the due sum. The contractor is entitled to the money right away. The fundamental thing to understand is that section 111(1) is a provision about cash-flow. It is not a provision which seeks to make any certificate, interim or final, conclusive."
In other words the employer must pay the sum stated to be due and argue about it afterwards. After any subsequent arbitration, litigation, mediation or other dispute resolution procedure, the employer can recover any amount which it has overpaid.
i) If the contractor's employment is determined in consequence of the appointment of a receiver, then under clause 27.6.5.1 the employer has no further liability to make interim payments to the contractor.
ii) In the present case it was not possible for the employer to serve a withholding notice by the due date under section 111(1) of the 1996 Act (11th May 2003) because the employer did not know about the appointment of receivers until 22nd May 2003.
iii) The law does not compel people to do that which is impossible.
iv) Therefore "section 111(1) should be construed as not applying to a lawful ground for withholding payment of which it was in the nature of things not possible for notice to have been given within the statutory time frame".
Lord Justice Lindblom :
Lady Justice Thirlwall :