COURT OF APPEAL (CIVIL DIVISION)
ON APPEAL FROM THE QUEEN'S BENCH DIVISION
TECHNOLOGY AND CONSTRUCTION COURT
MR JUSTICE JACKSON
HT-04-314
Strand, London, WC2A 2LL |
||
B e f o r e :
LORD JUSTICE MAY
and
LADY JUSTICE SMITH DBE
____________________
MULTIPLEX CONSTRUCTIONS (UK) LIMITED |
Appellant |
|
- and - |
||
(1) CLEVELAND BRIDGE UK LIMITED (2) CLEVELAND BRIDGE DORMAN LONG ENGINEERING LIMITED |
Respondents |
____________________
Adrian Williamson QC and Lucy Garrett (instructed by Reid Minty LLP) for the Respondents
Hearing dates : 13th December 2007
____________________
Crown Copyright ©
Lord Justice May:
Introduction
The Sub-Contract and the Heads of Agreement
"Future Fabrication is to be outsourced by MPX as per schedules handed by B Rogan (BR) to A Muldoon (AM) on 11/02/04 with any changes to be agreed by them."
The judge found in paragraph 151 of his judgment that the schedules referred to in this clause of the Heads of Agreement, and in clauses 6 and 7, were what he and the parties had referred to as the top half schedule, the category 1 schedule, the category 2 schedule and schedules showing permanent steelwork to be fabricated by Multiplex and Cleveland Bridge respectively.
"… design and fabrication drawings, Bought Out Materials and Subcontracts according to schedule handed by BR to AM (11/02/04) with any changes to be agreed by them."
Clause 7 of the Heads of Agreement provided for Cleveland Bridge's new fixed price of £12m. for their future retained work (other than work for which they were to be reimbursed at cost under clause 8). The judge found (paragraph 151) that the effect of clause 7 was that buyouts and subcontracts listed in the category 1 schedule were included in the £12m. lump sum, but that buyouts and subcontracts listed in the category 2 schedule were not. This superficially cryptic conclusion was (I believe) because the amount of £2.421m. in column 8 line 5 of the top half schedule (which is part of the £12.045m. from which the £12m fixed price was derived) is the product of deducting the amount in column 6 from the amount in column 7 – and the amount in column 7 derives from the sum of the 5th column (headed "Forecast against Supplemental Agreement") in the category 1 schedule alone. I note in passing that the top half schedule has in lines 1 and 2 amounts for Design and Drawings, which in column 8 make significant contributions to the £12.045m.
The Supplemental Agreement
Clause 3.1 | "The Sub-Contract Works shall be varied post 15 February 2004 only by the omission of the fabrication and supply to the Site of the items specified in Schedule 3, Part A." |
Clause 3.2 | "Notwithstanding Clause 3.1, the Sub-Contractor shall retain responsibility under the Sub-Contract for all design and fabrication drawings. In addition, the Sub-Contractor shall retain responsibility under the Sub-Contract for bought out materials and sub-contracts remaining in its scope after execution of this Agreement." |
Clause 4 | "Save as may be subsequently adjusted in accordance with the terms of the Sub-Contract …, it is agreed that (taking account of all matters referred to in Clauses 2.1, 3.1 and 3.2) the adjusted Sub-Contracts Sum (exclusive of Valued Added Tax) shall be as specified in Schedule 1." |
Clauses 6.1 and 6.2 | provided for the payment of two lump sum amounts. |
Clause 8 | "In the event that the parties fail to reach such agreement in accordance with Clause 7 on or before 29th June 2004 …, the Contractor shall be entitled to give 28 days written notice … to the Sub-Contractor further varying the Sub-Contract works to remove from the Sub-Contract the unperformed reimbursable cost items referred to in Schedule 1, paragraph (c)." |
Clause 9 | "In the event that the unperformed reimbursable cost items (referred to in Schedule 1, paragraph (c)) are removed from the Sub-Contract Work in accordance with Clause 8, it is agreed that: |
.... | |
Clause 9.2 | "there shall be no adjustment to the Sub-Contract Sum or other payment to the Sub-Contractor arising for such Variations other than the additional payment referred to in Clause 9.3." |
Clause 9.3 | gave Multiplex an option to use for a consideration "all temporary buildings, plant, tools, equipment and temporary works necessary for the carrying out and completion of the unperformed reimbursable cost items". |
Clause 10 | "The Sub-Contract shall be amended in accordance with the provisions of Schedule 2 and, save as amended by this Agreement, the Sub-Contract shall continue in full force and effect." |
One of the amendments in Schedule 2 made the Supplemental Agreement itself the prime sub-contract document after the Articles of Agreement.
The adjusted Sub-Contract Sum shall comprise:-
(a) …
(b) "A fixed, lump sum of £12,000,000 for the completion of all remaining works, services and other obligations under the Sub-Contract (save for those reimbursable cost items referred to in paragraphs (c) and (f) below and those lump sum items referred to in paragraphs (d) and (e) below …
(c) All costs reasonably and properly incurred by the Sub-Contractor from 15th February 2004, in connection with the erection and site works (being site staff, direct labour, cranes and other site related costs), plus a fixed amount for off site administration and overheads at a rate of £80,000 per month from 15th February 2004, subject to the deduction of Retention and other deductions permitted under the Sub-Contract."
"The Contractor will carry out the following Sub-Contract Works:"(i) Attached A4 Schedule (2 pages) entitled "Schedule 3 MPX Fabrication responsibility including MPX sublet, China steel returned unmade and 667T CBUK sublets;(ii) Attached A4 Schedule entitled "Schedule 3 varied Sub-Contract Works Part A – Document 2"".
The 2 page schedule referred to in (i) is a schedule consisting of a significant part of the remaining permanent steelworks. The schedule referred in (ii) is a reproduction of the first column of the February 2004 category 2 schedule – compare the relevant part of paragraph 74 of the judge's first judgment with the identical material in paragraph 23 of the judge's second judgment.
Steelwork erection
"132. Temporary works design is not intrinsically linked to permanent works design. There are a number of ways of constructing steelwork to a given design. There is considerable scope for the ingenuity of different teams over how such erection will be achieved. In relation to temporary supports, different teams will have their own preferences, partly dependent on the equipment available to them.
133 Therefore temporary works are generally inseparable from permanent works. This was especially so on the Wembley project, where the temporary works required were extraordinarily complicated."
Multiplex' claim
Issue 11 judge's decision
"In the period post 15 February 2004, did
(i) the design and drafting, and(ii) the fabrication
of some or all temporary works relating to the bowl, the arch and/or the roof fall within:
(a) 'all remaining works' (in paragraph (b) of Schedule 1 to the Supplemental Agreement); and/or(b) 'erection and site works' (in paragraph (c) of Schedule 1 to the Supplemental Agreement); and/or(c) 'temp works – roof props' (in Schedule 3 Part A to the Supplemental Agreement)?"
The appeal
Clauses 3.1 and 3.2
"158. The effect of clause 3.1 is that the fabrication referred to in that clause is not excluded altogether from the subcontract works. On the contrary, that fabrication work is to remain part of the subcontract works, but is to be paid for on a cost plus basis until such time as a new contract is agreed between the parties or, alternatively, Multiplex serves notice under clause 8.
159 Let me turn now to clause 3.2. If the phrase "all design and fabrication drawings" includes design and fabrication drawings for temporary works, then the clause makes perfectly good sense. CB retains responsibility for all designs and fabrication drawings, even though certain of those drawings are to be paid for on a cost plus basis. Alternatively, the phrase "all design and fabrication drawings" may be a somewhat clumsy reference to all design and fabrication drawings for the permanent works. However clause 3.2 is interpreted, it is not inconsistent with the conclusion that the design of roof temporary works falls outside the scope of the lump sum works."
Lady Justice Smith:
Lord Justice Pill: