Statutory Instruments
Infrastructure Planning
Made
12th March 2015
Coming into force
17th March 2015
The Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014(1) contains correctable errors, as defined in paragraph (1)3 of Schedule 4 to the Planning Act 2008(2).
Before the end of the relevant period(3), the Secretary of State received a written request from Thames Water Utilities Limited to correct the correctable errors.
In accordance with paragraph 1(7) of Schedule 4 to the Act(4), the Secretary of State has informed the relevant local planning authorities(5) that the request has been received.
The Secretary of State makes this Order in exercise of the power conferred by paragraph 1(4) of Schedule 4 to the Planning Act 2008(6).
1. This Order may be cited as the Thames Water Utilities Limited (Thames Tideway Tunnel) (Correction) Order 2015 and comes into force on 17th March 2015.
2. In relation to each of the provisions of the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 specified in the first column of each of the tables in the Schedule, the erroneous text or omission identified in the second column of each table is corrected in accordance with instructions in the third column.
Signed by authority of the Secretary of State
Sarah Fairbrother
Team Leader, Thames Tunnel DCO Decision Team
Department for Environment, Food and Rural Affairs
12th March 2015
Lindsay Speed
Decision Officer, Planning Casework Team
Department for Communities and Local Government
12th March 2015
Article 2
Provision | Erroneous text | Correction |
---|---|---|
Wherever the erroneous text appears in the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 | "Environmental Statement" | Substitute "environmental statement". |
Provision | Erroneous text/omission | Correction |
---|---|---|
Article 2(1) - definition of "environmental statement" | "6.1 and" | Insert before "6.2". |
Article 2(1) - definition of "environmental statement" | "environment statement" | Substitute "environmental statement". |
Article 10(1) and (2) | "other than in respect of specified works subject to the LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works," | Omit. |
Article 10 | "(4A) The provisions of sections 32 to 39 of the Traffic Management Act 2004 apply to any street works carried out under paragraph (1) or (2) to the extent that those works constitute "specified works" as defined in section 32(3) of that Act and which would, notwithstanding the provisions of this article, be subject to LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works." | Insert after paragraph (4). |
Article 11(1) and (2) | "other than in respect of specified works subject to the LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works," | Omit. |
Article 11 | "(5A) The provisions of sections 32 to 39 of the Traffic Management Act 2004 apply to any street works carried out under paragraph (1) or (2) to the extent that those works constitute "specified works" as defined in section 32(3) of that Act and which would, notwithstanding the provisions of this article, be subject to LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works." | Insert after paragraph (5). |
Article 16(1) | ", other than in respect of specified works subject to the LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works" | Omit. |
Article 16 | "(2A) The provisions of sections 32 to 39 of the Traffic Management Act 2004 apply to any street works carried out under paragraph (1) to the extent that those works constitute "specified works" as defined in section 32(3) of that Act and which would, notwithstanding the provisions of this article, be subject to LoPS as applied by the highway authority in whose area the undertaker seeks to carry out such works." | Insert after paragraph (2) |
Article 42(5) | "paragraph (1)" | Substitute "paragraph (4)". |
Article 60 | "Unilateral undertaking" | Substitute "unilateral undertaking". |
Provision | Erroneous text/omission | Correction |
---|---|---|
Table in paragraph 2, Excavated material and waste, Ref PW12 – third column | "(document reference 6.3)" | Insert after "Habitats Regulations Assessment No Significant Effects Report". |
Table in paragraph 3, Contaminated land, Ref ACTST3 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 4, Contaminated land, Ref HAMPS2 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 5, Contaminated land, Ref BAREL3 – third column, sub-paragraph (1) | (1) "the results of the site investigation" | (1) Insert on a new line after "a remediation strategy which includes-". |
(2) sub-headings (i)-(iv) in b. | (2) Omit. | |
Table in paragraph 6, Contaminated land, Ref PUTEF10 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 7, Contaminated land, Ref CARRR3 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 8, Contaminated land, Ref DRMST3 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 9, Contaminated land, Ref KNGGP3 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 10, Contaminated land, Ref FALPS2 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
(3) "the results of the site investigation" | (3) Insert on a new line after "a remediation strategy which includes-". | |
Table in paragraph 11, Contaminated land, Ref CREWD6 – third column, sub-paragraph (1) | (1) "a." | (1) Insert before "a preliminary risk assessment". |
(2) "b." | (2) Insert before "a remediation strategy". | |
Table in paragraph 13, Contaminated land, Ref KRTST2 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 14, Contaminated land, Ref HEAPS5 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 15, Contaminated land, Ref ALBEF11 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 16, Contaminated land, Ref VCTEF13 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 17, Contaminated land, Ref BLABF16 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 18, Contaminated land, Ref SHTPS3 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 19, Contaminated land, Ref CHAWF6 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 20, Contaminated land, Ref EARPS3 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 21, Contaminated land, Ref DEPCS 5 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 22, Contaminated land, Ref GREPS7 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 23, Contaminated land, Ref KEMPF9 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 24, Contaminated land, Ref BEKST3 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 25, Contaminated land, Ref ABMPS3 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Table in paragraph 26, Contaminated land, Ref BESTW2 – third column, sub-paragraph (1) | "the results of the site investigation" | Insert on a new line after "a remediation strategy which includes-". |
Provision | Erroneous omission | Correction |
---|---|---|
Paragraph 3 – definition of "scour and accretion monitoring and mitigation strategy" | "in accordance with the principles set out in the four-way legal agreement between Thames Water Utilities Limited, the Port of London Authority, the Environment Agency and the Marine Management Organisation dated 3rd March 2014 (as amended 7th August 2014) (APP183)" | Insert after the words "submitted to the Authority". |
Provision | Erroneous text | Correction |
---|---|---|
Paragraph 2(1) – definition of "designated works" | "Part 5 (for the protection of major highways structures)" | Substitute "Section 3 of Part 4 (protection for highways structures)". |
Paragraph 2(4) | Existing wording | Omit. |
(This note is not part of the Order)
This Order corrects errors and omissions in the Thames Water Utilities Limited (Thames Tideway Tunnel) Order 2014 (S.I. 2014/2384), a development consent order made under the Planning Act 2008 (c. 29), following a request made under paragraph 1(5)(a) of Schedule 4 to that Act.
The relevant period is the period specified in section 118(1)(b) of the Act, in accordance with paragraph 1(6)(a) of Schedule 4. Under paragraph 1(5)(a) of Schedule 4, it is a condition for the exercise of the power to make this Order that the Secretary of State receives a written request to correct the correctable errors from any person.
Paragraph 1(7) of Schedule 4 was amended by the Localism Act 2011 (c. 20), Schedule 13, Part 1, paragraph 70(3).
A relevant local planning authority means a local planning authority for all or any part of the area in which the land to which the decision relates is situated, under paragraph 4 of Schedule 4 to the Act.
Paragraph 1(4) of Schedule 4 was amended by the Localism Act 2011, Schedule 13, Part 1, paragraph 70(3).