Made | 26th February 2007 | ||
Coming into force | 19th March 2007 |
1. | Citation and commencement |
2. | Interpretation |
3. | Power to construct works and survey |
4. | Power to deviate |
5. | Power to execute street works |
6. | Stopping up of streets and extinguishment of rights |
7. | Temporary stopping up of streets |
8. | Application of the 1991 Act |
9. | Power to dredge etc. |
10. | Cables, pipes or wires under or over tidal water or tidal lands |
11. | Ouseburn not to be a reservoir |
12. | Agreements with owners of land and others for construction of works |
13. | Temporary closing of Ouseburn in connection with works |
14. | Diversion of flow of water |
15. | Power to take, pump, impound and discharge water |
16. | Deposits in Ouseburn |
17. | Tidal works not to be executed without approval of Secretary of State |
18. | Lights on tidal works during construction |
19. | Provisions against danger to navigation |
20. | Abatement of works abandoned or decayed |
21. | Survey of tidal works |
22. | Permanent lights on tidal works |
23. | Power to acquire land |
24. | Application of Part 1 of Compulsory Purchase Act 1965 |
25. | Vesting declarations |
26. | Power to acquire new rights |
27. | Power to acquire subsoil only |
28. | Temporary use of land for maintenance of works |
29. | Disregard of certain interests and improvements |
30. | Acquisition of part of certain properties |
31. | Extinction or suspension of private rights of way etc. over land |
32. | Time limit for exercise of powers of acquisition |
33. | Power to operate scheduled works |
34. | Misuse of scheduled works, etc. |
35. | Extinguishment of navigation rights etc. in upstream Ouseburn |
36. | Navigation etc. in vicinity of scheduled works |
37. | Removal of vessels |
38. | Arbitration in respect of removal of vessels |
39. | Removal of obstructions other than vessels |
40. | Arbitration in respect of removal of obstructions other than vessels |
41. | Removal of projections |
42. | Arbitration against notices under article 41 |
43. | Emergency powers and consents |
44. | Byelaws |
45. | Protection of certain persons |
46. | Saving for Trinity House |
47. | Crown rights |
48. | Minerals |
49. | Access to scheduled works |
50. | Power to transfer undertaking |
51. | Obstructing execution of Order |
52. | Defence of due diligence |
53. | Certification of plans etc. |
54. | Arbitration |
55. | No double recovery |
56. | Service of notices |
Schedule 1 | — Description of the scheduled works |
Schedule 2 | — Streets subject to street works and to be temporarily stopped up |
Schedule 3 | — Streets to be stopped up for which no substitute is to be provided |
Schedule 4 | — Modification of compensation and compulsory purchase enactments for creation of new rights |
Schedule 5 | — Provisions relating to statutory undertakers etc. |
Schedule 6 | — Protection of certain persons |
Part 1 | Provisions for the protection of the Port Authority |
Part 2 | Provisions for the protection of the Environment Agency |
Part 3 | Provisions for the protection of Northumbrian Water |
Part 4 | Provisions for the protection of the Port Health Authority |
Part 5 | Provisions for the protection of those with an interest in navigation in the Ouseburn or the environment and amenities of the Ouseburn |
(2) References in this Order to reference points shall be construed as references to Ordnance Survey National Grid Reference points.
(3) With the exception of the level of the crest of the weir as provided in article 4(2)(d), all directions, distances and reference points stated in any description of works, powers or lands shall be construed as if the words "or thereabouts" were inserted after such direction, distance and reference point.
(4) References in this Order to rights over land include references to rights to do, or to place and maintain, anything in, on or under land or in the air-space over its surface and references to the subsoil of any land include references to any cellar, basement, vault, arch or other construction forming part of any such land.
(5) Without prejudice to the generality of paragraph (4), within the limits of deviation or on any land to be acquired or used by the Council for the purposes of this Order the Council may, for the purposes of, and for purposes ancillary to, the construction or maintenance of the authorised works—
(6) Section 9 of the Salmon and Freshwater Fisheries Act 1975[12] shall not apply to the construction of the authorised works or to the alteration thereof.
(7) On the completion of any part of the works authorised by this article the Council shall remove all temporary works placed by it in exercise of the powers conferred by this article.
Power to deviate
4.
—(1) Subject to paragraph (3), in constructing or maintaining any of the scheduled works the Council may deviate laterally from the lines or situations shown on the works plans to any extent within the limits of deviation and may deviate vertically from the levels shown on the sections to any extent upwards or downwards.
(2) The scheduled works shall be so constructed that—
(3) Nothing in paragraph (4) or paragraph (5) of article 3 (power to construct works and survey) shall authorise the Council to execute any works in contravention of the restrictions imposed by paragraph (2) of this article.
(2) In this article, "apparatus" has the same meaning as in Part 3 of the 1991 Act.
Stopping up of streets and extinguishment of rights
6.
—(1) Subject to the provisions of this article, the Council may, in connection with the construction of the authorised works, stop up the street specified in columns (1) and (2) of Schedule 3 (street to be stopped up) to the extent specified, by reference to the letters and numbers shown on the works plans, in column (3) of that Schedule.
(2) Where a street has been stopped up under this article, all rights of way over or along the street so stopped up shall be extinguished.
(3) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the Land Compensation Act 1961[13].
(4) This article is subject to paragraph 2 of Schedule 5 (provisions relating to statutory undertakers etc.).
Temporary stopping up of streets
7.
—(1) The Council may, during and for the purpose of carrying out the authorised works, temporarily stop up, alter or divert any street specified in columns (1) and (2) of Schedule 2 (streets subject to street works and to be temporarily stopped up) to the extent specified, by reference to the letters and numbers shown on the works plans, in column (3) of that Schedule and may for any reasonable time—
(2) The Council shall provide reasonable access for pedestrians going to or from premises abutting on a street affected by the exercise of the power conferred by this article if there would otherwise be no such access.
(3) The Council shall not exercise the powers conferred by this article in relation to any street specified as mentioned in paragraph (1) without first consulting the street authority.
(4) Any person who suffers loss by the suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the Land Compensation Act 1961.
(5) This article is subject to paragraph 2 of Schedule 5 (provisions relating to statutory undertakers etc.).
Application of the 1991 Act
8.
—(1) The provisions of the 1991 Act mentioned in paragraph (2) and any regulations made, or code of practice issued or approved under, those provisions shall apply (with the necessary modifications) in relation to the stopping up, alteration or diversion of a street by the Council under the powers conferred by this Order where no street works are executed in that street as they would apply if the stopping up, alteration or diversion were occasioned by street works executed in that street by the Council.
(2) The provisions of the 1991 Act referred to in paragraph (1) are—
(3) Sections 54 and 55 of the 1991 Act as applied by paragraph (2) shall have effect as if references in section 57 of that Act to emergency works were a reference to a stopping up, alteration or diversion (as the case may be) required in a case of emergency.
(2) The powers conferred by this article shall only be exercisable with the prior written consent of the Port Authority, such consent not to be unreasonably withheld.
(3) The Council shall pay compensation to all persons for any damage sustained by them by reason of the exercise by the Council of its powers under paragraph (1)(a) and the amount of the compensation to be paid, where not agreed, shall be determined by the tribunal.
(4) The Council may use, appropriate or sell or otherwise dispose of anything (other than wreck within the meaning of Part 9 of the Merchant Shipping Act 1995[14]) removed in exercise of the power conferred in paragraph (1).
Cables, pipes or wires under or over tidal water or tidal lands
10.
Notwithstanding anything in this Order, any cables, pipes or wires to be laid or placed by the Council pursuant to this Order (other than those laid or placed within or attached to the structure of the scheduled works) under or over any tidal waters or tidal lands below the level of high water shall be laid or placed at such depth under, or such height over, tidal waters or tidal lands as the Port Authority and the Environment Agency may require.
Ouseburn not to be a reservoir
11.
Notwithstanding the provisions of subsection (2) of section 1 of the Reservoirs Act 1975[15], no part of the Ouseburn as is impounded by the scheduled works shall, by virtue of the retention of water by means of the scheduled works, be taken to be a reservoir for the purposes of that Act.
Agreements with owners of land and others for construction of works
12.
—(1) The Council may enter into and carry into effect agreements or arrangements with the Port Authority, the Environment Agency and the owners of, or other persons interested in, any land in or through which any of the authorised works are or may be constructed, or the drainage of which may be affected by the construction of any of the authorised works, for or with respect to the doing of anything which may be necessary in order to carry out, or in consequence of, the authorised works.
(2) Without prejudice to the generality of paragraph (1), any such agreement may provide for—
Temporary closing of Ouseburn in connection with works
13.
—(1) Notwithstanding anything in any other enactment or in any rule of law, the Council may temporarily close the Ouseburn between the Low Level Bridge and the Ouseburn Culvert, or any part thereof, to navigation during or for the purposes of executing any works or doing anything authorised by or under this Order.
(2) The Council shall not exercise the powers conferred by paragraph (1) without the consent of the Port Authority (such consent not to be unreasonably withheld) and, in the exercise of those powers—
(3) Neither the Council nor the Port Authority shall be liable for any costs, damages or expenses whatsoever incurred by any person (save as provided in Part 1 of Schedule 6 (provisions for the protection of the Port Authority)) as a result, directly or indirectly, of any closure of the Ouseburn under paragraph (1).
(4) In the case of an emergency, the Council's powers under paragraph (1) may be exercised by the Council without the consent of the Port Authority provided that the Port Authority are informed of the action as soon as possible.
Diversion of flow of water
14.
The Council may by means of the authorised works divert, intercept, stop up or otherwise interfere with the waters of, or the flow of water in, the Ouseburn.
Power to take, pump, impound and discharge water
15.
—(1) The Council may take, impound and use water from, and discharge water into, the Ouseburn, and may pump any water required by it from or into the Ouseburn or pump any water found by it into the Ouseburn or into any watercourse, public sewer, or drain in connection with the construction or maintenance of the authorised works and for those purposes may lay down, take up and alter conduits, pipes and other works and conveniences and may, on any land within the limits of deviation, make openings into, and connections with, the Ouseburn, or any watercourse, public sewer or drain.
(2) Any dispute arising from the exercise of the powers in paragraph (1) to connect to or use a public sewer or drain shall be determined as if it were a dispute under section 106 of the Water Industry Act 1991[16].
(3) The Council shall not, in exercise of the powers conferred by this article—
(4) This article does not authorise the entry into controlled waters of any matter whose entry or discharge into controlled waters is prohibited by section 85(1), (2) or (3) of the Water Resources Act 1991[17].
(5) The Council shall take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain in exercise of the powers conferred by this article is as free as may be practicable from gravel, soil or other solid substance or oil or matter in suspension.
(6) In the exercise of its powers conferred by this Order the Council shall not except with the consent of Northumbrian Water (which may be given subject to such terms and conditions as Northumbrian Water may reasonably impose) move, alter or break into any public sewer, lateral drain or disposal main which is at that time vested in Northumbrian Water and shown on the sewer map maintained by Northumbrian Water in accordance with section 199 of the Water Industry Act 1991.
(7) In this article—
Deposits in Ouseburn
16.
Except so far as may be unavoidable in the construction of the authorised works, or in the exercise of the powers conferred by article 9 (power to dredge etc.) or article 15(1) (power to take, pump, impound and discharge water), the Council shall not, without the consent of the Environment Agency and Port Authority (which shall not be unreasonably withheld), deposit in or allow to fall or be washed into the Ouseburn any gravel, soil or other materials in the carrying out of the authorised works.
and any expenditure incurred by the Secretary of State in so doing shall be recoverable from the Council.
Lights on tidal works during construction
18.
—(1) The Council shall at or near a tidal work during the whole time of the construction, alteration or replacement thereof, exhibit every night from sunset to sunrise such lights, if any, and take such other steps for the prevention of danger to navigation as the Secretary of State shall from time to time direct.
(2) If the Council fails to comply with any requirement of a direction reasonably given under paragraph (1), it shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Provisions against danger to navigation
19.
—(1) In the case of injury to, or destruction or decay of, a tidal work or any part thereof the Council shall as soon as reasonably practicable notify Trinity House and shall lay down such buoys, exhibit such lights and take such other steps for preventing danger to navigation as Trinity House may from time to time direct.
(2) If the Council fails to notify Trinity House as required by paragraph (1) or to comply with any requirement of a direction under it, the Council shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Abatement of works abandoned or decayed
20.
—(1) Where a tidal work is abandoned, or suffered to fall into decay, the Secretary of State may by notice in writing require the Council at its own expense either to repair and restore the work or any part thereof, or to remove the work and restore the site thereof to its former condition, to such an extent and within such limits as the Secretary of State thinks fit.
(2) Where—
the Secretary of State may include that part of the work, or any portion thereof, in any notice under paragraph (1).
(3) If, on the expiration of a period of 30 days from the date on which a notice under this article is served, the Council has failed to comply with the requirements of the notice, the Secretary of State may execute the work specified in the notice and any expenditure incurred by him in so doing shall be recoverable from the Council.
Survey of tidal works
21.
If he deems it expedient, the Secretary of State may at any time order a survey and examination of a tidal work or of the site upon which it is proposed to construct the tidal work, and any expenditure reasonably incurred by him in relation to any such survey and examination shall be recoverable from the Council.
Permanent lights on tidal works
22.
—(1) After the completion of a tidal work the Council shall at the outer extremity thereof exhibit every night from sunset to sunrise such lights, if any, and take such other steps, if any, for the prevention of danger to navigation as Trinity House may from time to time direct.
(2) If the Council fails to comply in any respect with a direction reasonably given under this article, it shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.
(2) Part 1 of the 1965 Act, as so applied, shall have effect as if—
Vesting declarations
25.
—(1) The Compulsory Purchase (Vesting Declarations) Act 1981[19] shall apply as if this Order were a compulsory purchase order.
(2) The Compulsory Purchase (Vesting Declarations) Act 1981, as so applied by paragraph (1), shall have effect with the following modifications.
(3) In section 3 (preliminary notices), for subsection (1) there shall be substituted—
(4) In that section, in subsection (2), for "(1)(b)" there shall be substituted "(1)" and after "given" there shall be inserted "and published".
(5) In that section, for subsections (5) and (6) there shall be substituted—
(6) In section 5 (earliest date for execution of declaration)—
(7) In section 7 (constructive notice to treat), in subsection (1)(a), the words "(as modified by section 4 of the Acquisition of Land Act 1981)" shall be omitted.
(8) References to the 1965 Act shall be construed as references to that Act as applied to the acquisition of land under article 23 (power to acquire land).
Power to acquire new rights
26.
—(1) The Council may compulsorily acquire such easements or other rights over any land referred to in article 23 (power to acquire land) as may be required for any purpose for which that land may be acquired under that article, by creating them as well as by acquiring easements or other rights already in existence.
(2) Subject to section 8 of the 1965 Act (as substituted by paragraph 5 of Schedule 4 (modification of compensation and compulsory purchase enactments for creation of new rights)), where the Council acquires a right over land under paragraph (1) the Council shall not be required to acquire a greater interest in that land.
(3) Schedule 4 (modification of compensation and compulsory purchase enactments for creation of new rights) shall have effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right.
Power to acquire subsoil only
27.
—(1) The Council may compulsorily acquire so much of the subsoil of the land referred to in article 23 (power to acquire land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
(2) Where the Council acquires any part of the subsoil of land under paragraph (1) it shall not be required to acquire an interest in any other part of the land.
(3) Paragraph (2) shall not prevent article 30 (acquisition of part of certain properties) from applying where the Council acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.
(2) Paragraph (1) shall not authorise the Council to take temporary possession of—
(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the Council shall serve notice of the intended entry on the owners and occupiers of the land.
(4) The Council may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance works for which possession of the land was taken.
(5) Before giving up possession of land of which temporary possession has been taken under this article, the Council shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
(6) The Council shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
(7) Any dispute as to a person's entitlement to compensation under paragraph (6), or as to the amount of the compensation, shall be determined by the tribunal under Part 1 of the Land Compensation Act 1961.
(8) Without prejudice to article 55 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6) of this article.
(9) Where the Council takes possession of land under this article, it shall not be required to acquire the land or any interest in it.
(10) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 24(1) (application of Part 1 of the Compulsory Purchase Act 1965).
(11) In this article, "the maintenance period", in relation to a scheduled work, means the period of 5 years beginning with the date on which the work is opened for use.
if the tribunal is satisfied that the creation of the interest, the erection of the building, the execution of the works or the making of the improvement or alteration was not reasonably necessary and was undertaken with the intention of obtaining compensation or increased compensation.
(2) In paragraph (1), "relevant land" means the land acquired from the person concerned or any other land with which that person is, or was at the time when the building was erected, the works executed or the improvement or alteration made, directly or indirectly concerned.
(2) In such a case, the owner may, within the period of 21 days beginning with the day on which the notice was served, serve on the Council a counter-notice objecting to the sale of the land subject to the notice to treat and stating that he is willing and able to sell the whole ("the land subject to the counter-notice").
(3) If no such counter-notice is served within that period, the owner shall be required to sell the land subject to the notice to treat.
(4) If such a counter-notice is served within that period, the question whether the owner shall be required to sell only the land subject to the notice to treat shall, unless the Council agrees to take the land subject to the counter-notice, be referred to the tribunal.
(5) If on such a reference the tribunal determine that the land subject to the notice to treat can be taken—
the owner shall be required to sell the land subject to the notice to treat.
(6) If on such a reference the tribunal determine that only part of the land subject to the notice to treat can be taken—
the notice to treat shall be deemed to be a notice to treat for that part.
(7) If on such a reference the tribunal determine that—
the notice to treat shall be deemed to be a notice to treat for the land to which the material detriment is confined in addition to the land already subject to the notice, whether or not the additional land is land which the Council is authorised to acquire compulsorily under this Order.
(8) If the Council agrees to take the land subject to the counter-notice, or if the tribunal determine that—
the notice to treat shall be deemed to be a notice to treat for the land subject to the counter-notice whether or not the whole of that land is land which the Council is authorised to acquire compulsorily under this Order.
(9) In any case where by virtue of a determination by the tribunal under this article a notice to treat is deemed to be a notice to treat for less land or more land than specified in the notice, the Council may, within the period of 6 weeks beginning with the day on which the determination is made, withdraw the notice to treat; and if it does so shall pay the owner compensation for any loss or expense occasioned to him by the giving and withdrawal of the notice, to be determined in case of dispute by the tribunal.
(10) Where the owner is required under this article to sell only part of a house, building or manufactory or of land consisting of a house with a park or garden, the Council shall pay him compensation for any loss sustained by him due to the severance of that part in addition to the value of the interest acquired.
Extinction or suspension of private rights of way etc. over land
31.
—(1) All private rights of way over land subject to compulsory acquisition under this Order shall be extinguished—
(2) All private rights of way over land owned by the Council which, being within the limits of land to be acquired or used shown on the land plan, are required for the purposes of this Order shall be extinguished on the appropriation of the land for any of those purposes by the Council.
(3) All private rights over land of which the Council takes temporary possession under this Order shall be suspended and unenforceable for as long as the Council remains in lawful possession of the land.
(4) Any person who suffers loss by the extinguishment or suspension of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part 1 of the Land Compensation Act 1961.
(5) This article does not apply in relation to any right of way to which section 271 or 272 of the planning Act (extinguishment of rights of statutory undertakers etc.) or paragraph 2 of Schedule 5 (provisions relating to statutory undertakers etc.) applies.
Time limit for exercise of powers of acquisition
32.
After the end of the period of 5 years beginning with the day on which this Order comes into force—
(2) The power contained in paragraph (1) shall be exercised so as to safeguard and improve the environment and amenities of the Ouseburn.
(3) Paragraph (2) shall not prevent the exercise of the power contained in paragraph (1) in order—
(4) When operating the scheduled works the Council shall have regard to—
(5) The Council shall operate the scheduled works in accordance with—
(b) any reasonable requirement of the Port Authority as to the general programme for the operation of the scheduled works in order to secure satisfactory navigation in the Ouseburn.
(6) Subject to paragraph (7), notice of a request under paragraph (5)(a)—
(7)
(8) The Council shall consult Natural England to seek their view as to ways in which the scheduled works may be operated so as to develop and conserve flora and fauna in the upstream Ouseburn.
(9) The Council shall give to the Environment Agency and the Port Authority as much notice as is reasonably practicable in the circumstances of its intention to operate both lock gates simultaneously for the following purposes—
(10) The Port Authority shall have regard to any notice given under paragraph (9) in exercising its powers to regulate the movement of vessels on the Ouseburn.
(11) Subject as otherwise expressly provided in this Order, no liability shall arise in respect of any costs, damages, losses or expenses incurred by any person as a direct or indirect result of—
occasioned by the operation of the scheduled works unless the costs, damages, losses or expenses are incurred by reason of negligence in its operation.
Misuse of scheduled works, etc.
34.
Any person who without lawful authority or reasonable excuse—
shall be guilty of an offence and shall for every such offence be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Navigation etc. in vicinity of scheduled works
36.
—(1) In this article, "in the vicinity of the scheduled works" means on or in the area of water between—
(2) Any person who, other than in an emergency or with some other reasonable cause—
shall be guilty of an offence and shall be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Removal of vessels
37.
—(1) Whenever any vessel is sunk, stranded or abandoned in the Ouseburn lying within the limits of deviation, or without lawful authority left or moored in that part of the Ouseburn, the Council may, after giving (except in an emergency) not less than 21 days' written notice to the owner of the vessel, unless it is not practicable after reasonable inquiry to ascertain the name and address of the owner, raise, remove, store or otherwise dispose of the vessel.
(2) Subject to article 43 (emergency powers and consents), the power in paragraph (1) shall not be exercisable by the Council if—
(3) Where a vessel is left or moored adjoining riparian property the Council shall give not less than one month's notice to the owner or occupier of that property and such owner or occupier may make representations to the Council as to the proposed raising, removal, storage, or disposal of the vessel.
(4) Any notice given by the Council under paragraph (1) shall—
(5) The Council may recover from the owner of any such vessel all expenses reasonably incurred by the Council in respect of the raising, removal, storage or disposal of the vessel or in raising, removing, storing or disposing of any furniture, tackle and apparel of the vessel or any goods, chattels and effects raised or removed from the vessel.
(6) In any proceedings by the Council against a person served with a notice under paragraph (1) for the recovery of any expenses which the Council is entitled to recover from that person under paragraph (5), it shall not be open to that person to raise any question which could have been raised on a referral to arbitration under article 38.
(7) Subject to paragraph (8), if any vessel to which paragraph (1) applies is not within 6 weeks of its removal by the Council, proved to the Council's satisfaction to belong to any claimant, the vessel (together with any such furniture, tackle and apparel) shall vest in the Council.
(8) If within 12 months of its removal a claim is made to the vessel by a person who subsequently proves to the satisfaction of the Council that he was the owner of the vessel, or has become the owner since the vessel was sunk, stranded, abandoned, left or moored as mentioned in paragraph (1), then the Council shall—
(9) In this article—
Arbitration in respect of removal of vessels
38.
—(1) Any person served with a notice by the Council under article 37(1) (removal of vessels) may, within 21 days of service of the notice, serve a counter-notice on the Council disputing the notice and stating that—
and any dispute under this article shall be determined in accordance with article 54 (arbitration).
(2) If and in so far as a dispute under this article is based on the ground of some informality, defect or error in, or in connection with, the notice, the arbitrator shall dismiss the dispute if he is satisfied that the informality, defect or error was not a material one.
(3) On the hearing of the dispute the arbitrator may confirm or set aside the notice.
Removal of obstructions other than vessels
39.
—(1) This article applies to anything, other than a vessel, causing an obstruction or impediment to the navigation or use of the Ouseburn lying within the limits of deviation (in this article and article 40 referred to as an "obstruction") and which the owner of the obstruction, or the owner or occupier of the land, as the case may be, caused or knowingly permitted to become or remain an obstruction.
(2) Subject to paragraph (3), the Council may by written notice require the owner of an obstruction or, if he is not known, the owner or occupier of any land on which the obstruction is situated to mark, modify or remove the obstruction.
(3) Subject to article 43 (emergency powers and consents), the power in paragraph (2) shall not be exercisable—
(4) If the owner of the obstruction, or the owner or occupier of the land, fails to take any action specified by the Council in a notice pursuant to paragraph (2), the Council may take that action and recover the reasonable costs of doing so from that person.
(5) In any proceedings by the Council against any person required to modify, remove or mark an obstruction under paragraph (2) for the recovery of costs which the Council is entitled to recover under paragraph (4), it shall not be open to that person to raise any question which could have been raised on a referral to arbitration under article 40 (arbitration in respect of removal of obstructions other than vessels).
(6) Subject to paragraph (13), the Council may—
in such circumstances as it considers fit.
(7) Before exercising its powers under paragraph (6), the Council shall, if it is reasonably practicable to do so, give not less than 21 days' written notice of its intention to the owner or occupier of any land on which the obstruction is situated.
(8) If an obstruction removed by the Council under this article is so marked as to be readily identifiable as the property of any person, the Council shall within one month of its coming into the Council's custody give written notice, in accordance with paragraph (12), to that person and, if possession of the thing is not retaken within the period specified in, and in accordance with the terms of, the notice, it shall vest in the Council at the end of that period.
(9) If an obstruction removed by the Council under this article, which is not marked as described in paragraph (8), is not within 3 months of its coming into the custody of the Council proved to the Council's reasonable satisfaction to belong to any person, it shall vest in the Council.
(10) The Council may at such time and in such manner as it thinks fit dispose of anything referred to in paragraph (9) which is of a perishable nature or the custody of which involves unreasonable expense or inconvenience notwithstanding that at the time it has not vested in the Council under this article, and if it is sold the proceeds of sale shall be applied by the Council in payment of the expenses incurred by it under this article in relation to the thing, and any balance shall—
(11) If an obstruction removed by the Council under this article—
the Council may recover the deficiency or the whole of the expenses, as the case may be, from the person who was the owner at the time when the thing removed came into the custody of the Council or who was the owner at the time of its abandonment or loss, if that person caused or knowingly permitted the obstruction to be there.
(12) A notice given under paragraph (8) shall specify the thing removed and state that, upon proof of ownership to the reasonable satisfaction of the Council and payment of the reasonable costs of the raising, removal and storage of the thing, possession may be retaken at the place named in the notice within the time specified in the notice, being not less than 14 days after the date when the notice is served.
(13) The Council shall not under the powers of this article remove, or require the removal of, or modify, or require the modification of, any obstruction specifically authorised by any enactment or by a works licence granted by the Port Authority under section 5 of the 1990 Act.
(14) In paragraph (1), reference to anything causing an obstruction or impediment to the navigation or use of the part of the Ouseburn lying within the limits of deviation is a reference to anything causing an obstruction or impediment to a vessel of a size customarily navigated or used on that part of the Ouseburn.
Arbitration in respect of removal of obstructions other than vessels
40.
—(1) Any person required by the Council to modify, remove or mark an obstruction under article 39(2) (removal of obstructions other then vessels) may within 21 days of being so required serve a counter-notice on the Council disputing the notice on any of the following grounds which are justified by the circumstances of the particular case—
and any dispute under this article shall be determined in accordance with article 54 (arbitration).
(2) Any person served with a notice under article 39(7) may within 21 days of service of the notice serve a counter-notice on the Council disputing the notice on any of the following grounds which are appropriate in the circumstances of the particular case—
and any dispute under this article shall be determined in accordance with article 54 (arbitration).
(3) On the hearing of a dispute under this article the arbitrator may confirm, vary or set aside the requirement or the notice, as the case may be.
Removal of projections
41.
—(1) Without prejudice to article 39 (removal of obstructions other than vessels), the Council may by written notice require the owner or occupier of a projection which in the opinion of the Council is, or is likely to become, by reason of its insecure condition or want of repair—
to remedy its condition to the satisfaction of the Council within a period of time (being not less than one month) specified in the notice.
(2) Any notice served by the Council under this article shall—
(3) In serving a notice under this article the Council may impose such terms and conditions as it thinks fit as to how the works or other operations shall be carried out.
(4) If a person required by any notice served by the Council under paragraph (1) to execute works fails to execute the works required within the time specified in the notice, the Council may itself execute the works and recover the expenses reasonably incurred by it in so doing from that person.
(5) In proceedings by the Council against the person served with the notice for the recovery of any expenses which the Council is entitled to recover from that person under paragraph (4), it shall not be open to that person to raise any question which could have been raised on a referral to arbitration under article 42.
(6) In this article, "projection" means anything which projects over the Ouseburn lying within the limits of deviation and includes any tree, bush or other plant but does not include any such things authorised by or under statute or by a works licence under section 5 of the 1990 Act to be placed or constructed.
Arbitration against notices under article 41
42.
—(1) The following provisions of this article shall apply in relation to any notice served by the Council under article 41 (removal of projections).
(2) A person served with such a notice may, within 21 days of service of the notice, serve a counter-notice on the Council disputing the notice on any of the following grounds which are appropriate in the circumstances of the particular case—
and any dispute under this article shall be determined in accordance with article 54 (arbitration).
(3) If and in so far as a dispute under this article is based on the ground of some informality, defect or error in, or in connection with, the notice, the arbitrator shall dismiss the dispute if it is satisfied that the informality, defect or error was not a material one.
(4) Where the grounds upon which a dispute under this article is brought include a ground specified in paragraph (2)(e) or (f), the appellant shall serve a copy of the counter-notice on each other person referred to, and in the case of any dispute may serve a copy of the counter-notice on any other person having an estate or interest in the structure or embankment in question.
(5) On the hearing of the dispute the arbitrator may confirm or set aside the notice and may make such award as he thinks fit with respect to the person by whom any work is to be executed and the contribution to be made by any other person towards the cost of the work, or as to the proportions in which any expenses which may become recoverable by the Council are to be borne by the appellant and such other person.
(6) In exercising its powers under paragraph (5), the arbitrator shall have regard—
Emergency powers and consents
43.
The Council's powers under articles 37 (removal of vessels), 39 (removal of obstructions other than vessels) and 41 (removal of projections) may be exercised by the Council in an emergency without prior notice to the Port Authority provided that the Port Authority are informed of the action as soon as possible thereafter.
(3) The Council shall not make any byelaws under this article without the consent of the Environment Agency, the Port Authority and the Port Health Authority.
(4) The Environment Agency and the Port Health Authority shall not withhold their consent to the making of any byelaw except on the ground that it conflicts with or duplicates a byelaw of that authority; and any unresolved question whether there is any such conflict or duplication shall be determined in accordance with article 54 (arbitration).
(5) Nothing in any byelaw made under this article shall apply to anything done by the Port Authority in the exercise of any of their statutory functions and the byelaws of the Port Authority shall be unaffected by any byelaw made under this article.
(6) In making any byelaws under this article the Council shall take into account matters relating to public safety and any reasonable requirements of the Environment Agency, the Port Authority and the Port Health Authority.
(7) Byelaws under this article may provide for it to be an offence for a person to contravene, or to fail to comply with, a provision of the byelaws and for such a person to be liable on summary conviction to a fine not exceeding level 3 on the standard scale.
(8) The provisions of sections 236(3) to (8) and (11) and 238 of the Local Government Act 1972[20] (which relates to the procedure for making, and evidence of, byelaws) shall apply to any byelaws made by the Council under this article.
(9) In its application to byelaws made under this article by the Council, section 236 of the Local Government Act 1972 shall have effect as if in subsection (7), after the word "confirm" where it first occurs, the words "with or without modification" were inserted.
(10) The confirming authority for the purposes of section 236 of the Local Government Act 1972 in its application to byelaws made under this article shall be the Secretary of State.
(11) The Secretary of State may charge the Council a reasonable fee for the purpose of defraying any administrative expenses incurred by him in respect of byelaws made under this article which are submitted to him for confirmation.
(12) Where in relation to any byelaws submitted to him for confirmation the Secretary of State proposes to make a modification which appears to him to be substantial he shall inform the Council and require it to take any steps he considers necessary for informing persons likely to be concerned with the modification and shall not confirm the byelaws until such period has elapsed as he thinks reasonable for consideration of, and comment upon, the proposed modification by the Council and by other persons who have been informed of it.
(2) Where an agreement has been made by virtue of paragraph (1) references in this Order to the Council shall include references to the transferee or the lessee.
(3) The exercise of the powers conferred by any enactment by any person in pursuance of any transfer or grant under paragraph (1) shall be subject to the same restrictions, liabilities and obligations as would apply under this Order if those powers were exercised by the Council.
(4) Subject to paragraph (5), the Council shall not under this article transfer or lease any rights conferred by Part 5—
(5) The Council shall not under this article transfer or lease any rights conferred by article 44 (byelaws).
Obstructing execution of Order
51.
Any person who, without reasonable excuse, obstructs any person acting under the authority of the Council in setting out the lines of the scheduled works, or in constructing any authorised work or who interferes with, moves or removes any apparatus belonging to any such person shall be guilty of an offence and liable on summary conviction to a fine not exceeding level 3 on the standard scale.
Defence of due diligence
52.
—(1) In proceedings for an offence under Part 3, it shall be a defence for the Council to prove that it took all reasonable precautions and exercised all due diligence to avoid the commission of the offence.
(2) If in any case the defence provided under paragraph (1) involves the allegation that the commission of the offence was due to the act or default of another person, the Council shall not, without leave of the court, be entitled to rely on that defence unless, not less than 7 clear days before the hearing, it has served on the prosecutor a notice in writing giving such information as was then in its possession, identifying or assisting in the identification of, that other person.
Certification of plans etc.
53.
The Council shall, as soon as practicable after the making of this Order, submit copies of the book of reference, the sections, the land plan and the works plans to the Secretary of State for certification that they are true copies of, respectively, the book of reference, sections and plans referred to in this Order; and a document so certified shall be admissible in any proceedings as evidence of the contents of the document of which it is a copy.
Arbitration
54.
Unless otherwise provided in this Order, any difference under any provision of this Order shall be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the President of the Institution of Civil Engineers.
No double recovery
55.
Compensation shall not be payable in respect of the same matter both under this Order and any other enactment, any contract or any rule of law.
Service of notices
56.
—(1) A notice or other document required or authorised to be served for the purposes of this Order may be served—
(2) Where the person on whom a notice or other document to be served for the purposes of this Order is a body corporate, the notice or document is duly served if it is served on the secretary or clerk of that body.
(3) For the purposes of section 7 of the Interpretation Act 1978[22] as it applies for the purposes of this article, the proper address of any person in relation to the service on him of a notice or document under paragraph (1) is, if he has given an address for service, that address, and otherwise—
(4) Where for the purposes of this Order a notice or other document is required or authorised to be served on a person as having any interest in, or as the occupier of, land and his name or address cannot be ascertained after reasonable enquiry, the notice may be served by—
(5) Where a notice or other document required to be served or sent for the purposes of this Order is served or sent by electronic transmission the requirement shall be taken to be fulfilled where the recipient of the notice or other document has given his consent to the use of electronic transmission either in writing or by electronic transmission.
(6) Where the recipient of a notice or other document served or sent by electronic transmission notifies the sender within 7 days of receipt that he requires a paper copy of all or any part of that notice or other document the sender shall provide such a copy as soon as reasonably practicable.
(7) A person may revoke his consent to the use of electronic transmission in accordance with paragraph (8).
(8) Where a person is no longer willing to accept the use of electronic transmission for any of the purposes of this Order he shall—
(9) This article shall not be taken to exclude the employment of any method of service not expressly provided for by it.
(10) In this article, "electronic transmission" means a communication transmitted—
Signed by authority of the Secretary of State
Ellis Harvey
Head of the Transport and Works Act Orders Unit, Department for Transport
26th February 2007
(1) | (2) | (3) |
Area | Street subject to street works and to be temporarily stopped up | Extent of temporary stopping up |
City of Newcastle upon Tyne | Unnamed area of footpath situated to the west of Maling Street and adjacent to the east of the eastern bank of the Ouseburn (excluding the highway carried over Glasshouse Bridge). | Between points ST1 and ST2 |
City of Newcastle upon Tyne | Part of Maling Street (excluding its eastern footway and the highway carried over Glasshouse Bridge). | Between points ST3 and ST4 |
City of Newcastle upon Tyne | Part of the highway carried over Glasshouse Bridge (excluding any highway below the Glasshouse Bridge). | Between points ST5 and ST6 |
City of Newcastle upon Tyne | Part of the highway carried across the Low Level Bridge. | Between points ST7 and ST8 |
(1) | (2) | (3) |
Area | Street to be stopped up | Extent of stopping up |
City of Newcastle upon Tyne | Unnamed area of footpath situated to west of Maling Street and to the east of the eastern bank of the Ouseburn (excluding the highway carried over Glasshouse Bridge). | Between points NSF1 and NSF2 |
(3) In section 58(1) (determination of material detriment where part of house etc. proposed for compulsory acquisition), as it applies to determinations under section 8 of the 1965 Act as substituted by paragraph 5—
3.
—(1) The 1965 Act shall have effect with the modifications necessary to make it apply to the compulsory acquisition under this Order of a right by the creation of a new right as it applies to the compulsory acquisition under this Order of land, so that, in appropriate contexts, references in that Act to land are to be read (according to the requirements of the particular context) as referring to, or as including references to—
(2) Without prejudice to the generality of sub-paragraph (1), Part 1 of the 1965 Act shall apply in relation to the compulsory acquisition under this Order of a right by the creation of a new right with the modifications specified in the following provisions of this Schedule.
4.
For section 7 of the 1965 Act (measure of compensation), there shall be substituted the following section—
5.
For section 8 of the 1965 Act (provisions as to divided land), there shall be substituted the following—
the Ouseburn Barrage Order 2007[24] ("the Order") shall, in relation to that person, cease to authorise the purchase of the right and be deemed to authorise the purchase of that person's interest in the whole of the relevant land including, where the land consists of such a park or garden, the house to which it belongs, and the notice shall be deemed to have been served in respect of that interest on such date as the tribunal directs.
(2) Any question as to the extent of the land in which the Order is deemed to authorise the purchase of an interest by virtue of subsection (1) of this section shall be determined by the tribunal.
(3) Where in consequence of a determination of the tribunal that it is satisfied as mentioned in subsection (1) of this section the Order is deemed by virtue of that subsection to authorise the purchase of an interest in land, the acquiring authority may, at any time within the period of 6 weeks beginning with the date of the determination, withdraw the notice to treat in consequence of which the determination was made; but nothing in this subsection prejudices any other power of the authority to withdraw the notice.".
6.
The following provisions of the 1965 Act (which state the effect of a deed poll executed in various circumstances where there is no conveyance by persons with interests in the land), that is to say—
shall be so modified as to secure that, as against persons with interests in the land which are expressed to be overridden by the deed, the right which is to be compulsorily acquired is vested absolutely in the acquiring authority.
7.
Section 11 of the 1965 Act (powers of entry) shall be so modified as to secure that, as from the date on which the acquiring authority has served notice to treat in respect of any right, it has power, exercisable in the like circumstances and subject to the like conditions, to enter for the purpose of exercising that right (which shall be deemed for this purpose to have been created on the date of service of the notice); and sections 12 (penalty for unauthorised entry) and 13 (entry on warrant in the event of obstruction) of the 1965 Act shall be modified correspondingly.
8.
Section 20 of the 1965 Act (protection for interests of tenants at will etc.) shall apply with the modifications necessary to secure that persons with such interests in land as are mentioned in that section are compensated in a manner corresponding to that in which they would be compensated on a compulsory acquisition under this Order of that land, but taking into account only the extent (if any) of such interference with such an interest as is actually caused, or likely to be caused, by the exercise of the right in question.
9.
Section 22 of the 1965 Act (protection of acquiring authority's possession where by inadvertence an estate, right or interest has not been got in) shall be so modified as to enable the acquiring authority, in circumstances corresponding to those referred to in that section, to continue to be entitled to exercise the right acquired, subject to compliance with that section as respects compensation.
shall be entitled to recover from the Council compensation in respect of expenditure reasonably incurred by him, in consequence of the removal, for the purpose of making his drain or sewer communicate with any other public sewer or with a private sewage disposal plant.
(5) The provisions of the planning Act mentioned in sub-paragraph (1), as applied by that sub-paragraph, shall not have effect in relation to apparatus as respects which Part 3 of the 1991 Act applies.
(6) In this paragraph—
(3) Subject to the following provisions of this paragraph, the Council shall pay to any statutory utility an amount equal to the cost reasonably incurred by the statutory utility in or in connection with—
(4) If in the course of the execution of relocation works under sub-paragraph (2)—
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the Council, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which apart from this paragraph would be payable to the statutory utility by virtue of sub-paragraph (3) shall be reduced by the amount of that excess.
(5) For the purposes of sub-paragraph (4)—
(6) An amount which apart from this sub-paragraph would be payable to a statutory utility in respect of works by virtue of sub-paragraph (3) (and having regard, where relevant, to sub-paragraph (4)) shall, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
(7) In this paragraph —
(3) With the exception of any duty owed by the Port Authority to the Council which is expressly provided for in this Part, nothing in this Order shall be construed as imposing upon the Port Authority either directly or indirectly, any duty or liability to which the Port Authority would not otherwise be subject and which is enforceable by proceedings before any court.
(4) Except as otherwise expressly provided in this Order and except so far as may be necessary to enable the objects of this Order to be effected, nothing in this Order shall prejudice or derogate from the estates, rights, interests, privileges, liberties or franchises of the Port Authority or harbour master or alter or diminish any power, authority or jurisdiction vested in the Port Authority on the date that this Order comes into force.
the Council shall submit to the Port Authority plans thereof and such further particulars as may be available to the Council and as the Port Authority may reasonably require and in carrying out such works or in exercising such powers, the Council shall comply with all reasonable modifications and conditions (not involving alteration to the basic design of any tidal works) required by the Port Authority, including protective works.
(2) Any modifications or conditions referred to in sub-paragraph (1) shall be notified by the Port Authority to the Council within 28 days of the receipt by the Port Authority of the plans or particulars to which such modifications or conditions relate.
the Council, if so requested by the Port Authority before, or within the period of 10 years after, the relevant date, shall remedy such accumulation or erosion in the manner specified in sub-paragraph (3) and, if it refuses or fails so to do, the Port Authority may themselves cause the work to be done and may recover the reasonable cost thereof from the Council.
(2) Should any accumulation or erosion in consequence of such construction arise within the period of 10 years mentioned in sub-paragraph (1) and be remedied in accordance with sub-paragraph (3), any recurrence of such accumulation or erosion shall from time to time be so remedied by the Council during that period of 10 years and at any time thereafter, save that the Council's obligation under this paragraph shall cease in the event that following the remedying of any accumulation or erosion a period of 10 years elapses from the completion of that remedying, without any further accumulation or erosion being caused or created in consequence of such construction.
(3) For the purpose of sub-paragraph (1)—
(4) In the event that surveys, inspections, tests and sampling carried out pursuant to sub-paragraph 8(1)(a) or (b) establish that any accumulation or erosion mentioned in sub-paragraph (1) or (2) would have been caused in any event by factors other than the construction of the tidal work, the Council shall be liable to remedy such accumulation or erosion only to the extent that the same is attributable to such construction as aforesaid.
(5) For the purposes of sub-paragraph (1), "the relevant date" means, in relation to the scheduled works and any other tidal work executed in connection therewith or incidental thereto, the date on which it is certified by the Engineer of the Council that the scheduled works are substantially complete and the lock gates are capable of being closed.
(6) The Council and the Port Authority shall consult the Environment Agency in relation to any action taken under this paragraph with a view to co-ordinating or reconciling any such action with any action taken under paragraph 13.
(c) the construction of any of the tidal works or the failure of any of the tidal works or the undertaking by the Port Authority of works or measures to prevent or remedy danger or impediment to navigation or damage to any property arising from such construction or failure; and
(d) any act or omission of the Council or its servants or agents whilst engaged in the construction or operation of any of the tidal works.
(2) Without prejudice to the generality of sub-paragraph (1), the Council shall indemnify the Port Authority from and against all claims and demands arising out of, or in connection with, such construction, failure or act or omission as is mentioned in that sub-paragraph.
(3) Nothing in this paragraph shall impose any liability on the Council to the extent that any losses, costs, charges, damages, expenses, claims or demands referred to in sub-paragraphs (1) and (2) are attributable to negligence on the part of the Port Authority or of any person in their employ or of their contractors or agents.
(4) The Port Authority shall give to the Council notice of any claim or demand in relation to which the Council may be liable under this Part and no settlement or compromise of any such claim or demand shall be made without the consent in writing of the Council.
12.
—(1) Without prejudice to the generality of sub-paragraph 11(4), the requirements which the Environment Agency may impose under that sub-paragraph include—
(2) Any specified work, and all protective works required by the Environment Agency under sub-paragraph (1)(b)(ii), shall be constructed—
and the Environment Agency shall be entitled by its officer to watch and inspect the construction of such works.
(3) The Council shall give to the Environment Agency not less than 14 days' notice in writing of its intention to commence construction of any specified work and notice in writing of its completion not later than 7 days after the date on which it is brought into use.
(4) If any part of the works comprising a structure in, over or under a watercourse is constructed otherwise than in accordance with the requirements of this Part, the Environment Agency may by notice in writing require the Council, at the Council's own expense, to comply with the requirements of this Part or (if the Council so elects and the Environment Agency in writing consents, such consent not to be unreasonably withheld) to remove, alter or pull down the work and, where removal is required, to restore the site to its former condition to such extent as the Environment Agency reasonably requires.
(5) Subject to sub-paragraph (6), if within a reasonable period, being not less than 28 days from the date when a notice under sub-paragraph (4) is served upon the Council, it has failed to begin taking steps to comply with the requirements of the notice and has not thereafter completed them within such reasonable period as may be specified in the notice, the Environment Agency may execute the works specified in the notice and any expenditure incurred by it in so doing shall be recoverable from the Council.
(6) In the event of any dispute as to whether sub-paragraph (4) is properly applicable to any work in respect of which a notice has been served under that sub-paragraph, or as to the reasonableness of any requirement of such a notice, the Environment Agency shall not except in emergency exercise the powers conferred by sub-paragraph (5) until the dispute has been finally determined.
(4) To the extent that the Council establishes by surveys, inspections, tests or sampling that such accumulation or erosion or effect of alteration of tidal flow would have been caused in any event by factors other than the construction, maintenance or operation of a specified work the Council shall not be liable to remedy such accumulation or erosion or effect of alteration of tidal flow.
(5) In carrying out any surveys, inspections, tests or sampling under sub-paragraph (4) the Council shall not unreasonably delay the execution of any remedial action required under sub-paragraphs (1) or (2).
(6) The impoundment or release of water by means of the scheduled works shall not of themselves be an effect of alteration of tidal flow for the purposes of this paragraph.
(7) The Council and the Environment Agency shall consult the Port Authority in relation to any action taken under this paragraph with a view to co-ordinating or reconciling any such action with any action taken under paragraph 7.
damage is caused to the fishery, or the Environment Agency has reason to expect that such damage may be caused, the Environment Agency may serve notice on the Council requiring it to take such steps as may be reasonably practicable to make good the damage, or, as the case may be, to protect the fishery against such damage.
(3) If, within such time as may be reasonably practicable for that purpose after the receipt of written notice from the Environment Agency of any damage or expected damage to the fishery, the Council fails to take such steps as are described in sub-paragraph (2), the Environment Agency may take those steps and may recover from the Council any expenditure reasonably incurred by it in so doing.
(4) In any case where immediate action by the Environment Agency is reasonably required in order to secure that the risk of damage to the fishery is avoided or reduced, the Environment Agency may take such steps as are reasonable for the purpose, and may recover from the Council the reasonable cost of so doing provided that a notice specifying those steps is served on the Council as soon as is reasonably practicable after the Environment Agency has taken, or commenced to take, the steps specified in the notice.
(2) Without prejudice to the other provisions of this Part, the Council shall indemnify the Environment Agency from all claims, demands, proceedings, costs, damages, expenses or loss which may be made or taken against, or recovered from or incurred by, the Environment Agency by reason of—
which is caused by the construction of any of the specified works or any act or omission of the Council, its contractors, agents, workmen or servants whilst engaged upon any such work.
(3) The Environment Agency shall give to the Council reasonable notice of any such claim or demand and no compromise or settlement thereof shall be made without the agreement of the Council which agreement shall not be unreasonably withheld.
(4) Prior to incurring any expense which it may seek to recover under this paragraph, the Environment Agency shall, except in a case of urgency, serve notice on the Council informing it of the Environment Agency's intentions and requiring it within such time as the Environment Agency may reasonably specify to take such steps as may be reasonably practicable to avoid the need for the Environment Agency to incur such costs.
(5) Nothing in this part of this schedule shall impose any liability on the Council in respect of any damage to the extent that it is attributable to the negligent act or omission of the Environment Agency, its officers, servants or, if not the Council, its contractors or agents.
(2) Prior to the commencement of the scheduled works, the Council shall ask Northumbrian Water to identify relevant outfalls which, following reasonable agreement by the Council, shall be made subject to an outfall survey by the Council.
(3) The Council shall consult Northumbrian Water as to the method and timing of any outfall survey and the Council shall provide a copy of the survey results to Northumbrian Water within 28 days of the survey being completed.
(4)
(5) Should any relevant outfall or the bed of the Ouseburn in the vicinity of such outfall be subject to siltation to a significantly greater depth than identified in any outfall survey undertaken in accordance with sub-paragraph (2), to the extent that the performance of the outfall is significantly prejudiced and provided that the siltation is largely or completely due to the construction or operation of the scheduled works, then Northumbrian Water may either require the Council to clear the area concerned or undertake the work itself.
(6) The cost of any work done in accordance with sub-paragraph (5) shall be borne by the Council to the extent that the siltation requiring clearance has been caused by the construction or operation of the scheduled works but otherwise the said cost shall be borne by Northumbrian Water and should the said work be required partly on account of the scheduled works and partly by other causes the costs of such work shall be apportioned between the Council and Northumbrian Water.
the Council shall submit to the Port Health Authority plans thereof and such further particulars as may be available to the Council and as the Port Health Authority may reasonably require in respect of carrying out such works or in exercising such powers.
31.
The Council shall provide reasonable accommodation for the meetings of the consultative body on not less than 6 occasions in any 12 month period during its first 5 years and subsequently on not less than 4 occasions in any 12 month period if so required by the consultative body and shall provide reasonable secretarial services for the consultative body.
32.
The consultative body may determine its own quorum and procedure and shall appoint a chairman.
33.
An individual member of the consultative body may, on giving notice in writing to the chairman of that body, send a substitute to any meeting of the consultative body.
34.
A member of the consultative body shall hold office for the period of 3 years from the date of his appointment and at the end of his period shall be eligible for reappointment.
35.
A member of the consultative body may resign his office at any time by notice in writing given to the chairman of the body who shall send a copy of the notice to the Council.
36.
This Part shall cease to have effect in the event that the scheduled works are removed from the Ouseburn.
[4] S.I. 1992/3230 as amended by S.I. 1997/2906.back