Michaelmas
Term
[2017] UKSC 66
On appeal from: [2016] CSIH 28
JUDGMENT
Aberdeen City and Shire Strategic Development Planning
Authority (Appellant) v Elsick Development Company Limited (Respondent)
(Scotland)
before
Lord Neuberger
Lady Hale
Lord Mance
Lord Reed
Lord Hodge
JUDGMENT GIVEN ON
25 October 2017
Heard on 13 June 2017
Appellant
Martin Kingston QC
Alasdair Sutherland
(Instructed by
Morton Fraser LLP)
|
|
Respondent
Roy Martin QC
Alasdair Burnet
(Instructed by
Burness Paull LLP)
|
LORD HODGE: (with whom Lord
Neuberger, Lady Hale, Lord Mance and Lord Reed agree)
1.
This appeal raises an important question of planning law. A planning
authority foresees and plans for significant growth in its area. Major
investment in transport infrastructure is required to accommodate the aggregate
of the planned development. The planning authority seeks to achieve this
investment by adopting a policy in its development plan which in substance
requires developers to enter into planning obligations with it to make
financial contributions to the pooled fund to be spent on the infrastructure,
including interventions at places where a particular development has only a
trivial impact. Is such a policy within the existing powers of the planning
authority under current planning legislation?
Factual background
2.
The Aberdeen City and Shire Strategic Development Planning Authority
(“the Authority”) has the responsibility for preparing a strategic development
plan for its area. The Authority foresaw the need for significant new and
improved infrastructure to accommodate the cumulative impact of new development
for which it planned. There were already proposals for transport infrastructure
which involved major public sector investment, including the Aberdeen Western
Peripheral Route (“AWPR”), new bridges, park and ride sites, making the A96
into a dual carriageway road and the creation of twin tracks on significant
parts of the Aberdeen-Inverness railway line, all of which was to be paid for
out of public funds. In 2010 the North-East of Scotland Transport Partnership
(“Nestrans”) commissioned a cumulative transport appraisal for the area (“the
CTA”), in which it estimated that £86.6m was required on top of already
committed public sector investment in order to fund a package of infrastructure
developments, which it identified, to address the cumulative impact of the
proposed new development in the area.
3.
In December 2011 the Authority approved non-statutory supplementary
planning guidance which proposed the establishment of a Strategic Transport
Fund (“the Fund”). In February 2013 the Authority published its proposed
strategic development plan. In that plan the Authority stated that it intended
to prepare supplementary guidance in support of the plan. This guidance would
allow for the Fund to deliver the transport projects which were needed to deal
with the combined effect of new development in four identified strategic growth
areas within the Aberdeen Housing Market Area. The Authority stated that it
would need to secure a higher percentage of the increase in land values, which
resulted from the grant of planning permission, than it had in the past in
order to be able to create sustainable mixed communities.
4.
Elsick Development Ltd (“Elsick”) proposes to develop approximately
4,000 houses together with commercial, retail and community facilities at
Elsick, near Stonehaven. Elsick’s site is located within the southerly of the
four strategic growth areas. In November 2011 Elsick objected to the draft
supplementary planning guidance while it was subject to consultation.
5.
Elsick also objected to the proposed strategic development plan and
sought to have the reference to the Fund removed from that plan on the ground
that it was contrary to the guidance of the Scottish Ministers on planning
obligations which is set out in circular 3/2012, “Planning Obligations and Good
Neighbour Agreements” (“the Circular”). The Circular advised planning
authorities to seek to have developers enter into planning obligations only if
the obligations met specified tests. These tests were that the obligations (i)
were necessary to make the proposed development acceptable in planning terms
(para 15), (ii) served a planning purpose (para 16), (iii) related to the
proposed development either as a direct consequence of the development or
arising from the cumulative impact of development in the area (paras 17-19),
(iv) fairly and reasonably related in scale and kind to the proposed development
(paras 20-23), and (v) were reasonable in all other respects. Elsick’s
principal concern was with (iv); Elsick asserted that the contribution to the
Fund which the proposed plan envisaged was out of all proportion to the demands
which its development would make on the infrastructure which expenditure from
the Fund was to improve.
6.
In the meantime, on 30 September 2013 Elsick entered into a planning
obligation under section 75 of the Town and Country Planning (Scotland) Act
1997 (as amended) (“the 1997 Act”) with Aberdeenshire Council (“the Council”)
to contribute to the Fund in terms of the draft non-statutory supplementary
planning guidance or any revision or replacement of it in the proposed
strategic development plan, but the agreement also provided that no
contributions to the Fund needed to be paid if the supplementary planning
guidance were found to be invalid. On 2 October 2013 the Council granted
outline planning permission for the development and detailed planning
permission for a first phase of 802 houses and other facilities.
7.
The proposed strategic development plan was examined by a reporter
appointed by the Scottish Ministers. In his report dated 21 January 2014 the
reporter stated that it was right that the principle of the Fund should be
established in the development plan and concluded that the CTA had demonstrated
that the overall traffic growth, which the development promoted in the plan
would create, would have harmful effects unless there were mitigation measures.
He expressed concern that the mechanism for raising contributions to the Fund
did not comply with national policy in the Circular because there was not a
sufficiently clear and direct relationship between the development supplying
the contribution and the infrastructure to be delivered. He advised that para
5.9 of the proposed plan be amended “to establish that the Fund will only be
used to gather contributions towards infrastructure improvements that are
related to the developments concerned and strictly necessary in order to make
any individual development acceptable in planning terms”.
8.
The Strategic Development Plan was amended to take account of the
reporter’s comments. As so amended the relevant paragraphs of the Plan stated:
“5.8 Developers will have to
accept the need for contributions towards necessary infrastructure, services
and facilities within their own site. However, in cases where development has
wider effects, we will have to secure contributions to deal with these as well,
although the public sector will also need to make an important contribution.
5.9 We will prepare
supplementary guidance in support of this plan. This will allow (through a
‘Strategic Transport Fund’) transport projects which are needed as a result of
the combined effect of new development to be funded and delivered. … We will
look for contributions from housing, business, industrial, retail and
commercial leisure developments in the strategic growth areas within the
Aberdeen Housing Market Area, (detailed criteria will be set out in the supplementary
guidance). We will only use contributions to support projects that are related
to the developments concerned and that are necessary to make those developments
acceptable in planning terms.”
9.
The Authority then resolved to convert the non-statutory supplementary
planning guidance into statutory guidance. On 12 December 2014 the Authority
issued a consultation draft of the proposed statutory guidance. In a report to
the meeting of the Authority which approved the consultation draft it was
explained that the consultants who had prepared the CTA had re-presented table
7.2 of the study, which I discuss in more detail in para 16 below, to show a
clear and direct link between the development providing a contribution to the
Fund and the infrastructure improvement to be delivered. The report also stated
that the supplementary guidance was
“based on a strategic level
evidence base and uses this to derive appropriate contribution levels for
individual developments. The main driving force behind the preparation of the
existing non-statutory guidance was the need to facilitate development rather
than leave it to individual developers to try to satisfy Transport Scotland and
the two councils that they had adequately mitigated all their cumulative
impacts on the transport network.”
10.
Elsick and others objected to the consultation draft on several grounds,
including that it failed to comply with the Circular. The Authority responded
to Elsick’s representations by stating that all but one of the transport
interventions were within a three-mile radius of Aberdeen City centre and had
strong inter-relationships and that the modelling of the CTA had demonstrated
that there was a cumulative impact from all development areas to all of the
interventions. The Authority approved the draft supplementary guidance on 24
April 2015 and sent it to the Scottish Ministers for ratification.
11.
The Scottish Ministers advised that the Authority could adopt the draft
supplementary guidance if they added a statement that the use of any planning obligation
shall follow the guidance in the Circular. The Authority made that amendment
and adopted the supplementary guidance (“SG”) on 25 June 2015. As I explain
below when I discuss the legislative background, the SG forms part of the
development plan for the purpose of determining planning applications.
The Supplementary Guidance
12.
After setting out the purpose of and background to the SG and who would
be expected to contribute, the SG explained that the purpose of the Fund was to
mitigate the cumulative impact of developments at specific “hotspots” in the
network which the CTA had identified. It continued (in para 4.8): “[t]here will
still be a requirement to mitigate impacts specific to the development (defined
as local impacts) whether they are on the local or strategic network”. In
section 5 the SG set out the contributions which were required to deliver the
proposed interventions at an estimated cost of £86.6m. In Table 1 in that
section the SG set out contribution levels which for residential developments
were fixed by reference to unit size, ranging from £1,350 per unit for a one
bedroom unit to £3,148 per unit for a unit of five bedrooms or more. The table
also provided for contributions from non-residential developments.
13.
Because the Authority has argued that contribution to the Fund was
voluntary (para 20 below), I set out para 5.4 so far as relevant. It provided:
“Developers can elect to assess
and mitigate their cumulative impact outwith the [Fund], although this
will require a considerably more comprehensive Transport Assessment and the
design and delivery of the mitigation measures shown to be necessary. This will
definitely be more time-consuming and almost certainly more expensive, if it
can be achieved at all.” (emphasis added)
14.
Section 6 of the SG addressed how and when contributions would be
payable. Para 6.1 stated that a planning obligation or other legal agreement
would normally be used to secure contributions. In accordance with the advice
of the Scottish Ministers, the paragraph also stated that the use of any
planning obligation shall follow the guidance in the Circular.
15.
Section 7 of the SG explained that the contributions would be used only
to fund the transport interventions which it listed. Para 7.3 stated:
“No contributions from development
sites will be used to support projects where the development in question is
predicted to gain no mitigation benefit from the infrastructure being provided
and therefore is un-related to the development making the contribution. The CTA
has shown that the delivery of each of the projects identified above is
necessary to make all developments acceptable in planning terms (see
appendix 2).” (emphasis added)
16.
Appendix 2 summarised the CTA and listed the cumulative infrastructure
requirements which it had identified. It reproduced as Table 3 the revised
table 7.2 of the CTA, which had been prepared in response to the reporter’s
criticism (para 7 above) that it had not been demonstrated that there was a
clear and direct relationship between the development contributing to the Fund
and the infrastructure which would be delivered. But that table showed the
traffic generated by each development which would use the infrastructure at the
identified “hotspots” as a percentage of the total traffic generated by that development.
For example, the table showed the following in relation to the Elsick site:
Development Zone
|
Persley Bridge
|
A947
|
A96 East of AWPR
|
Kingswells North
|
A944
|
New Bridge of Dee
|
Elsick
|
3.45%
|
0.10%
|
0.76%
|
1.46%
|
0.79%
|
8.39%
|
Thus, taking the columns on the left, the table showed
that 3.45% of the traffic which the Elsick development would generate would use
Persley Bridge and 0.10% of that traffic would use the A947.
17.
The previous table 7.2 in the CTA was more informative about the impact
of the proposed developments on the infrastructure. It showed the percentage of
the total traffic using the new infrastructure at the identified “hotspots”
which the traffic generated by each proposed development was estimated to
create. For example, in relation to the Elsick development, it had shown that
the percentage of the total traffic predicted to use the same infrastructure as
the following:
Development Zone
|
Persley Bridge
|
A947
|
A96 East of AWPR
|
Kingswells North
|
A944
|
New Bridge of Dee
|
Elsick
|
1%
|
0%
|
1%
|
2%
|
1%
|
7%
|
It also showed that 2% of the traffic on the Loirston Link
would be generated by the Elsick development and 79% of the traffic on the
Elsick Fastlink. In relation to a separate development at Blackdog the original
table 7.2 of the CTA showed that 1% of the traffic on the A947 would be
attributable to that site and 0% of the traffic on all of the other listed
infrastructure.
18.
Paragraph 7.4 explained that the contributions would be used to deliver
the specified transport interventions. It stated:
“Nestrans as the Regional
Transport Partnership will hold and administer contributions in a strategic
transport fund. As contributions are received they will be placed into a
ring-fenced account. The monies in this account will only be available for
delivering the strategic transport projects listed above, including detailed
assessment, development and design work.”
The challenge
19.
Elsick appealed against the adoption of the SG to the Inner House of the
Court of Session under section 238 of the 1997 Act. On 29 April 2016 the First
Division of the Inner House (The Lord President (Lord Carloway), Lord Menzies
and Lord Drummond Young) allowed the appeal and quashed the SG: [2016] CSIH 28.
The First Division upheld three of the four grounds of appeal which Elsick
advanced. First, the court upheld the submission that the Authority had failed
to comply with national policy on the use of planning obligations, holding that
it was a fundamental principle of planning law, which was reflected in the
Circular, that a condition attached to the grant of a planning permission,
whether contained in a planning obligation or otherwise, must fairly and
reasonably relate to the permitted development. The First Division accepted the
distinction, which the reporter had drawn, between the sharing of costs among
developments which had cumulatively required a particular investment in
transport infrastructure on the one hand and the funding of a basket of
measures, not all of which were relevant to every development. The court
referred (in para 35 of its opinion) to the original Table 7.2 and held that
many of the planned developments had no impact at all on several of the
proposed infrastructure interventions. It added: “[t]his applies to both Elsick
and Blackdog relative to a number of the interventions. In respect of others
the impact is de minimis”. The result was that the additional sentence
in the SG about complying with the guidance in the Circular, which was added at
the request of the Scottish Ministers (para 11 above), could not prevent the obligation
to contribute to the Fund, in which contributions were pooled, from breaching
the Circular. The First Division also upheld Elsick’s submission that there was
no rational basis for relying on Table 3 of Appendix 2 of the SG (ie the
revised table 7.2 of the CTA) to support the contention that a particular
intervention was made necessary by reason of either a particular development or
the cumulative effect of it along with other developments.
20.
The Authority applied for and was given permission to appeal to this
court arguing that the policy tests in the Circular were not part of the legal
tests for the validity of a planning obligation, that the Inner House had taken
an unduly restrictive approach to policy, and that the Authority had
substantially complied with the Circular when the SG afforded the opportunity
to a developer to make mitigation contributions to infrastructure wholly
outside the Fund (para 5.4 of the SG, which is set out in para 13 above). This
court refused to allow the Authority to argue that the Inner House had erred in
law and fact in finding that many of the planned developments, such as Elsick
and Blackdog, have no impact on some of the proposed interventions and, in the
case of Elsick and Blackdog, the impact on some other interventions is de
minimis, because that was a finding of fact, based on the original table 7.2 of
the CTA, the contents of which were not disputed.
Discussion
21.
The central issue in this appeal is the lawfulness of the planning
obligation which Elsick has entered into in conformity with the requirements of
the SG. The Authority challenges the First Division’s conclusion that the tests
applicable to a planning condition are properly to be applied to a planning
obligation. To address this challenge I examine (i) the correct legal test as
to the lawfulness of a planning condition, (ii) the correct legal test as to
the lawfulness of a planning obligation, (iii) the role of a planning
obligation in the decision to grant or refuse planning permission, and (iv) the
boundary between questions of legality and questions of policy.
22.
I set out the legislative background before turning to each of the four
questions. Finally, I will apply the answers to those questions to the facts in
this appeal.
The legislative background
23.
The 1997 Act was amended extensively by the Planning etc (Scotland) Act
2006 to provide in Part 2 for strategic development planning: see section 2 of
the 2006 Act. Section 4 of the amended 1997 Act empowers the Scottish Ministers
to designate a group of planning authorities as authorities which are jointly
to prepare a strategic development plan for the area which the Scottish
Ministers determine (section 5(3)). Section 7 provides that a strategic
development plan is to include a vision statement, which is to be a broad
statement setting out the strategic development planning authority’s views on
how development could and should occur in its area and the matters, including
infrastructure, which might affect that development. The 1997 Act provides for
the preparation and publication of a proposed strategic development plan
(section 10), the appointment by the Scottish Ministers of a reporter to
examine the proposed plan (section 12), the approval or rejection of the
proposed plan by the Scottish Ministers (section 13), and, on such approval,
the publication of the constituted strategic development plan.
24.
Section 22 empowers a strategic development planning authority to adopt
and issue supplementary guidance in connection with a strategic development
plan, which guidance has to be submitted to the Scottish Ministers who can by
notice require the authority to modify it. The Town and Country Planning
(Development Planning) (Scotland) Regulations 2008 (SSI 2008/426) provide (in
regulation 27(2)) that such supplementary guidance may only deal with the
provision of “further information or detail in respect of the policies or
proposals set out in [the] plan and then only provided that those are matters
which are expressly identified in a statement contained in the plan as matters
which are to be dealt with in supplementary guidance”.
25.
Section 24 defines the development plan, which is an important concept
in relation to decisions taken under the planning Acts, as including the
provisions of the approved strategic development plan for the time being in
force for the area and also the supplementary guidance issued in connection
with that plan. The central importance of the development plan to planning
decisions can be seen in two provisions of the 1997 Act. First, section 25(1)
provides:
“Where, in making any
determination under the planning Acts, regard is to be had to the development
plan, the determination is, unless material considerations indicate otherwise -
(a) to be made in accordance with that plan …”
Secondly, section 37(2) provides:
“In dealing with [an application
for planning permission] the authority shall have regard to the provisions of
the development plan, so far as material to the application, and to any other
material considerations.”
Sections 25(1) and 37(2) in combination set up what has
been called “a presumption that the development plan is to govern the decision
on an application for planning permission”: City of Edinburgh Council v
Secretary of State for Scotland 1998 SC (HL) 33, 43G; [1997] 1 WLR 1447,
1458 per Lord Clyde. I will return to these two provisions when I consider
question (ii) below.
26.
In order to address question (i) (the lawfulness of a planning
condition) I refer to section 37(1) which provides:
“Where an application is made to a
planning authority for planning permission - (a) … they may grant planning
permission, either unconditionally or subject to such conditions as they think
fit”,
and section 41(1) which provides so far as relevant:
“Without prejudice to the
generality of section 37(1) to (3), conditions may be imposed on the grant of
planning permission under that section -
a) for regulating the
development or use of any land under the control of the applicant (whether or
not it is land in respect of which the application was made) or requiring the
carrying out of works on any such land, so far as appears to the planning
authority to be expedient for the purposes of or in connection with the
development authorised by the permission;
b) for requiring the
removal of any buildings or works authorised by the permission, or the
discontinuance of any use of land so authorised, at the end of a specified
period, and the carrying out of any works required for the reinstatement of
land at the end of that period. …”
27.
Of direct relevance to question (ii) (the lawfulness of a planning
obligation) is section 75 (as substituted by section 23 of the 2006 Act) which,
so far as relevant, provides:
“(1) A person may, in respect
of land in the district of a planning authority -
(a) by agreement with that
authority, or
(b) unilaterally,
enter into an obligation (referred
to in this section and in sections 75A to 75C as a ‘planning obligation’)
restricting or regulating the development or use of the land, either
permanently or during such period as may be specified in the instrument by
which the obligation is entered into (referred to in this section and in those
sections as the ‘relevant instrument’)
(2) Without prejudice to the
generality of subsection (1), the reference in that subsection to restricting
or regulating the development or use of land includes - (a) requiring
operations or activities specified in the relevant instrument to be carried out
in, on, under or over the land, or (b) requiring the land to be used in a way
so specified.
(3) A planning obligation
may - …
(b) require the payment -
(i) of a specified amount
or an amount determined in accordance with the relevant instrument. …”
Section 75(5) provides that a
relevant instrument, to which the owner of the land is a party, may be recorded
in the Register of Sasines or registered in the Land Register of Scotland so
that the planning authority may enforce certain obligations in the instrument
against both the owner and his successors in title. Sections 75A and 75B
provide for the modification and discharge of planning obligations by agreement
with the planning authority or by the determination of the Scottish Ministers
on an appeal.
Question (i): the lawfulness of a planning condition
28.
A planning condition is a statutory creation. Section 37(1) of the 1997
Act (para 26 above) and similar legislative provisions in England and Wales
(section 70(1) of the Town and Country Planning Act 1990 (“the 1990 Act”))
authorise a planning authority to impose planning conditions when it grants a
planning permission. The apparently unlimited power (“subject to such
conditions as they think fit”) has long been interpreted restrictively by the
courts to prevent its abuse. The courts have formulated three principal
constraints. First, the conditions must be imposed for a planning purpose and
not solely to achieve some ulterior object, however desirable in the public
interest that object may be. Secondly, the conditions must “fairly and
reasonably relate to the permitted development”. Thirdly, the conditions must
not be unreasonable in the Wednesbury sense (Associated Provincial
Picture Houses Ltd v Wednesbury Corpn [1948] 1 KB 223, 233-234).
29.
The first constraint arises from the statutory origin of the power of a
planning authority to impose conditions: administrative law provides that it
must be exercised for the purposes of the 1997 Act, namely planning purposes.
The second constraint was first articulated by Lord Denning in Pyx Granite
Co Ltd v Ministry of Housing and Local Government [1958] 1 QB 554, 575. His
statement has been endorsed on several occasions by the House of Lords in Fawcett
Properties Ltd v Buckingham County Council [1961] AC 636, Mixnam’s
Properties Ltd v Chertsey Urban District Council [1965] AC 735, and Newbury
District Council v Secretary of State for the Environment [1981] AC 578. It
arises from the statutory context of the power in section 37: a planning
authority is tasked with determining an application for planning permission on
its merits having regard to the development plan so far as relevant and other
material considerations; the power to attach conditions to the permission is an
inherent part of the power to grant permission for the development of land;
therefore the conditions imposed on the grant of that permission must relate to
the development for which permission is given. The third constraint is a
feature of our administrative law.
30.
The second legal requirement - that a condition must fairly and
reasonably relate to the development - requires there to be a reasonably close
relationship between the development and the condition which governs it. In British
Airports Authority v Secretary of State for Scotland 1979 SC 200 the Inner
House looked for a “clear relationship” between the condition and the permitted
development (218 per the Lord President (Emslie)) or “a recognised and real
relationship … that is fair and reasonable” (220 per Lord Cameron).
31.
Such a relationship between a condition and the permitted development
existed where a planning authority imposed a negative suspensive condition,
that development of a site should not commence until an event had occurred which
the developer alone did not have power to bring about. In Grampian Regional
Council v Secretary of State for Scotland and City of Aberdeen District Council
1984 SC (HL) 58 the House of Lords upheld the validity of such a condition
which overcame an objection to a proposed industrial development on the ground
of road traffic safety. The condition was that the development of the site
could not commence until the road on the western boundary of the site had been
closed by a road closure order which the Secretary of State would have to
confirm. In the leading speech, Lord Keith of Kinkel (pp 66-67) accepted the
three tests which I have stated in para 28 above and which have come to be
associated with the Newbury case and held that the condition met the
third test because it was not unreasonable to impose such a condition which was
in the public interest and where there were reasonable prospects that a road
closure order would be confirmed.
32.
The three-fold legal test for validity, having been repeatedly approved
by judges at the highest level, is an established part of planning law. Other
rules of administrative law, such as the requirement to take account of all
relevant considerations and not to take account of irrelevant considerations in
decision-making, apply to a decision to impose a particular condition.
Question (ii): the lawfulness of a planning obligation
33.
A planning obligation also is a statutory creation. As with a particular
planning condition, the lawfulness of a particular obligation depends upon (i)
the wording of the statute, and (ii) the rules of our administrative law.
34.
Section 75 of the 1997 Act, like its predecessor legislation (section 50
of the Town and Country Planning (Scotland) Act 1972), requires that the
obligation restricts or regulates the development or use of the land to which
it relates. As section 75(3)(b) shows, the planning obligation can include the
payment of money.
35.
Prima facie the planning authority is given a wide discretion as to the
circumstances in which it can seek a planning obligation and the nature of that
obligation. While it is not uncommon for planning authorities to duplicate some
planning conditions in a section 75 agreement and thereby obtain an alternative
means of enforcement, planning obligations also enable a planning authority to
control matters which it might otherwise have no power to control by the
imposition of planning conditions. Planning obligations are most commonly
required in the context of an application for planning permission, but they are
not confined to such circumstances and are available as a means of keeping land
free from any development. It is not surprising therefore that there is no
general legal requirement that there be a relationship to a permitted
development.
36.
In Good v Epping Forest District Council [1994] 1 WLR 376, in
which Ralph Gibson LJ delivered the leading judgment, the Court of Appeal
addressed the question whether a planning authority could validly achieve by
agreement any purpose which it could not validly achieve by planning condition
or whether the test for validity was the same in each case. In substance, the
Court held that the powers of a planning authority to bring about a planning
obligation were not controlled by the nature and extent of its statutory powers
to grant planning permission subject to conditions (p 387C). A planning
obligation did not have to relate to a permitted development.
37.
In Tesco Stores Ltd v Secretary of State for the Environment
[1995] 1 WLR 759, which I discuss more fully when addressing question (iii)
below, both Lord Keith of Kinkel (769B-C) and Lord Hoffmann (779C-D) referred
with approval to the judgment of the Court of Appeal in Good v Epping Forest
District Council (above). Lord Hoffmann (779D) summarised the case thus:
“the only tests for the validity of a planning obligation outside the express
terms of section 106 [of the 1990 Act] are that it must be for a planning
purpose and not Wednesbury unreasonable”. Thus beyond the restrictions
implicit in the words of the section there are only the constraints of
administrative law, which requires the planning authority to exercise its power
to seek a planning obligation for a planning purpose: its exercise solely for a
purpose unrelated to land use planning would be an abuse of power. Similarly,
if a local planning authority acts unreasonably in the Wednesbury sense
in requiring the undertaking of a planning obligation, the obligation may be reduced
(nullified). Other rules of administrative law, such as the requirement to take
into account all relevant considerations, also apply.
38.
The express words of section 75 require a relationship between the
planning obligation and the land to be burdened by the obligation because the
obligation must in some way restrict or regulate the development or the use of
that land. But those restrictions or regulation do not necessarily relate to a
particular permitted development on the burdened land. A planning obligation
may prohibit the development of the land in a particular way or the use of the
land for particular purposes. A planning obligation may keep the burdened land
free from any development and may be entered into in circumstances which are
not connected with any planning application.
39.
Restrictions may validly be imposed in the context of the development of
another site. Thus, to take an example discussed in Good v Epping Forest
District Council, the owner of two farms, A and B, within the area of a
planning authority might apply for planning permission to develop and operate
an intensive breeding establishment on farm A. The owner of the farms might
offer, or the planning authority might require, a section 75 planning
obligation preventing the use of farm B for that purpose. The restriction would
relate to farm B and would be justified for the planning purpose of preventing
an undesirable number of such establishments in the same area.
40.
A planning obligation may also regulate the development or use of the
burdened site. An example, in the context of a planning application, is where a
planning obligation requires the developer to provide affordable housing as a
component of a development on its site or to create specified infrastructure on
its land to meet the needs of that development.
41.
Similarly, a planning authority may contract for the payment of
financial contributions towards, for example, educational facilities,
healthcare facilities, sewerage or waste and re-cycling: requiring a
development to contribute to, or meet, its own external costs in terms of
infrastructure involves regulating the development of the land which is
burdened by the obligation. The financial contribution can be applied towards
infrastructure necessitated by the cumulative effects of various developments,
so long as the land which is subject to the planning obligation contributes to
that cumulative effect and thereby creates a sufficient relationship between
the obligation in question and the land so that one can fairly speak of the
obligation as regulating the development of the land.
42.
In each of the examples in paras 38-41 above the restriction or
regulation serves a purpose in relation to the development or use of the
burdened site. In this appeal a question of principle arises: can a restriction
or regulation of a site be imposed in the form of a negative suspensive
planning obligation, analogous to the negative suspensive planning condition in
the Grampian Regional Council case, for a purpose which does not relate
to the development or use of the site? In particular, is it lawful by planning
obligation to restrict the commencement of the development of a site until the
developer undertakes to make a financial contribution towards infrastructure
which is unconnected to the development of the site? Alternatively, is it
lawful to require contributions towards such infrastructure in a planning
obligation which does not restrict the development of the site by means of a
negative suspensive obligation?
43.
The answer to each question is no. Dealing first with the latter
question, a planning obligation which required a developer to contribute to
infrastructure unconnected with its development but did not make the payment of
the contribution a pre-condition of development of the site would not fall
within section 75 as it would neither restrict nor regulate the development or
use of the site. In Tesco Stores Ltd v Secretary of State for the
Environment (1994) 68 P & CR 219, Beldam LJ (pp 234-235) stated:
“In section 106(1) [of the 1990
Act] the obligations referred to in subsections (a), (b) and (c) clearly relate
to the land in which the person entering into the obligation is interested. The
obligation entered into by a person interested in land under subsection (d) to
pay money to the authority is not expressed to be restricted to the payment of
money for any particular purpose or object. But all the planning obligations
are, by section 106(3), enforceable not only against the person entering into
the obligation but also against his successors in title to the land. Against
the background that it is a fundamental principle that planning permission
cannot be bought or sold, it does not seem unreasonable to interpret subsection
(1)(d) so that a planning obligation requiring a sum or sums to be paid to the
planning authority should be for a planning purpose or objective which should
be in some way connected with or relate to the land in which the person
entering into the obligation is interested.”
In my view, this analysis is equally applicable to section
75 of the 1997 Act which, in so far as is relevant, is in substantially similar
terms as section 106 of the 1990 Act (as substituted by section 12(1) of the
Planning and Compensation Act 1991) as the obligations in section 106(1)(a) - (d)
are reflected in section 75(1)(2) and (3)(b).
44.
A planning obligation, which required as a pre-condition for commencing
development that a developer pay a financial contribution for a purpose which
did not relate to the burdened land, could be said to restrict the development
of the site, but it would also be unlawful. Were such a restriction lawful, a
planning authority could use a planning obligation in the context of an
application for planning permission to extract from a developer benefits for
the community which were wholly unconnected with the proposed development,
thereby undermining the obligation on the planning authority to determine the
application on its merits. Similarly, a developer could seek to obtain a
planning permission by unilaterally undertaking a planning obligation not to
develop its site until it had funded extraneous infrastructure or other
community facilities unconnected with its development. This could amount to the
buying and selling of a planning permission. Section 75, when interpreted in
its statutory context, contains an implicit limitation on the purposes of a
negative suspensive planning obligation, namely that the restriction must serve
a purpose in relation to the development or use of the burdened site. An
ulterior purpose, even if it could be categorised as a planning purpose in a broad
sense, will not suffice. It is that implicit restriction which makes it both
ultra vires and also unreasonable in the Wednesbury sense for a planning
authority to use planning obligations for such an ulterior purpose.
45.
It is, perhaps, surprising that the legal boundaries of a planning
obligation have not been the subject of more extensive judicial comment, beyond
the cases discussed in Good v Epping Forest District Council, the
comment by Beldam LJ in the Court of Appeal in Tesco (para 43 above),
and the opinion of Lord MacLean in McIntosh v Aberdeenshire Council 1999
SLT 93 (which upheld the validity of a planning obligation to build an estate
road to serve the owner’s development of his land and also to facilitate the
development of neighbouring land in third party ownership) when the risk of
misuse of planning obligations has long been recognised as a matter of
policy. There were concerns that some planning authorities were tempted to make
exorbitant demands for what has been called “planning gain”, to confer benefits
on the community which were not part of the developer’s original proposal. A
developer in order to obtain a planning permission might be forced to incur
disproportionate costs in providing such gains which were unrelated or
insufficiently related to its development or otherwise suffer the delay and
expense of an appeal to the Scottish Ministers. This practice risked bringing
the planning system into disrepute. In 1981, in a report to the Secretary of
State for the Environment called “Planning Gain”, the Property Advisory Group
advised that planning obligations be used only to overcome legitimate planning
objections to an application for planning permission and that the practice of
bargaining with developers for planning gain was unacceptable. The report, which
was criticised for taking too narrow an approach to the planning process,
advocated that the Secretary of State should issue guidance. The Department of
the Environment and the Welsh Office produced such guidance in 1983 in circular
22/83, which sought to control rather than exclude the pursuit of planning
gain. In Scotland, the Scottish Development Department issued a circular in
1984, entitled “Section 50 Agreements” (SDD circular 22/1984). Current guidance
on the use of planning obligations in Scotland is contained in the Circular
(para 5 above). As I explain when addressing question (iv) below, this
guidance, while an important statement of national policy, does not have the
force of law.
46.
There was also a perceived risk that developers, who were each promoting
a different site in a competition for what might be an exclusive permission to
develop one of the sites, would offer to enter into an obligation with the
planning authority to fund infrastructure or other community facilities which
were unrelated or only marginally related to their developments. This practice
similarly threatened to bring the planning system into disrepute, by creating
the impression that they were buying planning permissions. In the heady days of
the “store wars”, major supermarket chains competed with each other before
planning authorities and in planning appeals to obtain permission to develop
rival sites up and down the United Kingdom. This competition, which often
involved offers to provide “planning gain”, led to authoritative judicial
guidance on the relevance of a planning obligation to the grant or refusal of a
planning permission, which I now consider under question (iii).
Question (iii): the role of the planning obligation in the
grant or refusal of planning permission
47.
What is the role of a planning obligation in the decision to grant or
refuse planning permission? In Scotland that decision is governed by section
37(2) of the 1997 Act which requires that the planning authority have regard to
the provisions of the development plan, so far as material to the application,
and to any other material considerations (para 25 above). In Tesco Stores
Ltd v Secretary of State for the Environment (above) the House of Lords,
when considering a legislative provision in identical terms (section 70(2) of
the 1990 Act), gave guidance on the relevance of a planning obligation to the
grant or refusal of planning permission. That guidance is not challenged in
this appeal.
48.
In the leading speech, which Lord Keith of Kinkel delivered, the House
held that for a planning obligation to be a “material consideration”, which it
interpreted as a “relevant consideration” (764G), in the decision whether to
grant planning permission, the obligation must have some connection with the
proposed development which is not de minimis (ie too trifling for the law to be
concerned with it). In what follows, I paraphrase the Latin phrase as
“trivial”. Lord Keith described the relevance of a planning obligation in these
terms (770A-B):
“An offered planning obligation
which has nothing to do with the proposed development, apart from the fact that
it is offered by the developer, will plainly not be a material consideration
and could be regarded only as an attempt to buy planning permission. If it has
some connection with the proposed development which is not de minimis, then
regard must be had to it.”
49.
In that case, developers, including Tesco and Tarmac, which was
associated with Sainsburys, competed to obtain planning permission for their
sites for a superstore outside the centre of Witney in Oxfordshire. The Witney
local plan proposed a new link road, including a new river crossing, to relieve
traffic congestion. Tesco entered into a planning obligation with the planning
authority under section 106 of the 1990 Act to fund that road. The Secretary of
State on appeal favoured the Tarmac site and refused permission to the Tesco
application, holding that the link road was not needed to enable any of the
food stores to be developed or so directly related to any of the developments
or the use of the land after completion that any of the developments should not
be permitted without it. Tesco appealed under section 288 of the 1990 Act,
arguing that the Secretary of State had erred in law in not treating the offer
to fund in the planning obligation as a material consideration. The House held
that the Secretary of State had correctly had regard to the offer but had
chosen in the exercise of his planning judgement to attach little weight to it
and so had not erred in law.
50.
No challenge was made in Tesco, in the House of Lords or in the
courts below it, to the validity of the planning obligation: the question
whether the obligation regulated the development of Tesco’s site was not put in
issue and only Beldam LJ commented on the legality of an obligation to
contribute money (para 43 above).
51.
The inclusion of a policy in the development plan, that the planning
authority will seek such a planning obligation from developers, would not make
relevant what otherwise would be irrelevant. Section 37(2) (para 25 above)
requires the planning authority to have regard to the provisions of the
development plan “so far as material to the application” and treats its
provisions as a relevant consideration only to that extent. Thus, a green belt
policy will be relevant to an application if the site of the application falls
within the specified green belt and a requirement that a certain amount of open
space is provided in a proposal for residential development will be relevant to
an application for residential development. Similarly, a requirement in the
plan that an applicant should agree to contribute to the cost of offsite
infrastructure, which is related to its development, will be relevant to the
application. But the words, which I have emphasised, mean that if a planning
obligation, which is otherwise irrelevant to the planning application, is
sought as a policy in the development plan, the policy seeking to impose such
an obligation is an irrelevant consideration when the planning authority
considers the application for planning permission.
52.
It is important to recall that the question whether a benefit conferred
by a planning obligation is a material consideration in the determination of an
application for planning permission is quite separate from the question whether
a planning obligation restricts or regulates the development or use of a
particular piece of land. Thus, to use the example of the farmer with two
farms, A and B. He wishes to develop farm A and is prepared to enter into a
planning obligation to restrict the development or use of farm B in the context
of his negotiation of a permission for farm A. The legality of the planning
obligation in relation to farm B will depend, among other things, on whether it
restricts or regulates the development or use of farm B. The relevance of the
planning obligation to the determination of the application in relation to farm
A depends upon there being a more than trivial connection between the benefit
conferred by controlling farm B and the development of farm A, as the Tesco
case decided.
Question (iv): The boundary between questions of legality
and questions of policy
53.
Relevant ministerial guidance which sets out national planning policy is
unquestionably a material consideration for any planning authority when it
determines applications for planning permission. A failure by a planning
authority to take into consideration national guidance, such as that in the
Circular (para 5 above) on the tests which a planning authority should apply
when deciding whether to seek a planning obligation, would be unlawful.
Further, if a planning authority were to depart from national planning guidance
when refusing an application for planning permission, it might risk an appeal
by the disappointed applicant to the Scottish Ministers. But a decision by the
planning authority is not illegal if it departs from ministerial guidance in a
planning circular, provided that the authority has treated that guidance as a relevant
consideration when it reached its decision.
54.
In Tesco (above) Lord Hoffmann pointed out (780F-G) that the law
has always made “a clear distinction between the question of whether something
is a material consideration and the weight which it should be given”. The
former is a question of law; the latter is a matter for the planning judgement
of the planning authority. Accordingly, a failure by a planning authority to
have regard to relevant guidance as a material planning consideration would be
an error of law. A decision, after considering the guidance, not to follow it,
would (absent another ground of challenge in administrative law) be a matter of
planning judgement, in which the courts have no role.
The legality of Elsick’s planning obligation
55.
What is the nature of the scheme which the SG has established?
56.
First, it involves the payment by developers of financial contributions
towards the funding of specified transport infrastructure in and around
Aberdeen, principally through the mechanism of planning obligations. It
involves the pooling of the contributions and no one developer is liable for
the costs of any of the specified interventions (paras 1.5 and 3.3 and Appendix
2). Secondly, the obligation to contribute to the Fund is in addition to the
requirement that a developer mitigate impacts specific to its development (para
4.8). Thirdly, the contributions from residential developers are fixed at a sum
per unit (Table 1 summarised in para 12 above). Fourthly, those payments are
not tied to the impact of a particular development on the transport network.
The original table 7.2 in the CTA suggested that there was no connection
between traffic generated by certain developments and the need to intervene at
particular hotspots. The revised table 7.2 which is referred to in para 7.3 of
the SG and reproduced in Appendix 2 shows that some vehicles from each of the
developments will use the proposed infrastructure but in many cases such use is
at a very low level.
57.
Fifthly, the opt-out which para 5.4 of the SG offers (para 13 above)
does not make the scheme voluntary in any real sense. The developer is still
expected to provide a contribution towards the cumulative impact of the
developments on infrastructure over and above the impact of its individual
development and the paragraph understandably expresses doubt whether a
developer could create the needed assessment, design and provide for the
necessary mitigation measures. Unless a developer were able to perform this
daunting task and persuade the planning authority that it was robust, it is
clear that the scheme envisages that it would not obtain planning permission
for its development.
58.
Sixthly, the statement in para 6.1 that the use of any planning
obligation shall follow the guidance in the Circular is inconsistent with the
nature of the scheme. This is because the pooling of fixed per unit
contributions towards the funding of infrastructure interventions, which
include many on which a particular development’s impact is minimal, does not
meet the criterion in the Circular that the obligation is fairly and reasonably
related in scale and kind to the proposed development. The statement which the
Scottish Ministers inserted into the SG therefore is no safeguard.
59.
As the Lord President has observed, there appears to be much that can be
said in favour of such a scheme. It enables a planning authority to facilitate
development within its area. Inclusion of such a scheme in a development plan
allows a public debate during the statutory process of the approval of the plan.
The scheme allows developers in the area to assess the viability of their
proposed developments knowing the extent of their liability to the Fund before
they spend large sums pursuing their applications. In England and Wales Part 11
of the Planning Act 2008, which provided for a community infrastructure levy,
was enacted to achieve similar ends.
60.
But the 1997 Act does not allow for such a scheme. The Inner House has
found that the connection between certain developments, including the
development at Elsick, and some of the interventions which the pooled Fund is
intended to finance is at best trivial. The illegality of the scheme is not
because it does not comply with the Circular. The guidance in the Circular is
simply a material consideration which the planning authority must take into
account when deciding whether to grant planning permission. The weight which
the planning authority attaches to such guidance is a matter of planning
judgement. The scheme of the SG and the planning obligations which it promotes
are unlawful for two separate reasons.
61.
First, the requirement imposed on a developer to contribute to the
pooled Fund, which is to finance the transport infrastructure needed to make
acceptable all of the developments which the development plan promotes, entails
the use of a developer’s contribution on infrastructure with which its
development has no more than a trivial connection and thus is not imposed for a
purpose in relation to the development and use of the burdened site as section
75 requires.
62.
Further, the Council did not include any provision in the planning
obligation restricting the development of the Elsick site until a contribution
was made. Instead it resolved to grant planning permission for the development
but to issue that permission only once Elsick had entered into the obligation. The
planning obligation was therefore neither restricting nor regulating the
development of the Elsick site and so was outside the ambit of section 75.
63.
Secondly, Tesco (above) establishes that for a planning
obligation, which is to contribute funding, to be a material consideration in
the decision to grant planning permission, there must be more than a trivial
connection between the development and the intervention or interventions which the
proposed contribution will fund. The planning obligation which Elsick entered
into could not be a relevant consideration in the grant of the planning
permission. In my view, it was not within the power of the planning authority
to require a developer to enter into such an obligation which would be
irrelevant to its application for permission as a precondition of the grant of
that permission.
64.
If planning authorities in Scotland wish to establish a local
development land levy in order to facilitate development, legislation is needed
to empower them to do so.
Conclusion
65.
I would dismiss the appeal.