[2013] UKPC 30
Privy Council Appeal No 0073 of 2011
JUDGMENT
General Construction Limited (Appellant) v Chue Wing & Co Ltd and another (Respondents)
From the Supreme Court of Mauritius
before
Lord Neuberger
Lord Mance
Lord Clarke
Lord Carnwath
Lord Toulson
JUDGMENT DELIVERED BY
Lord Mance
ON
15 October 2013
Heard on 12 June 2013
Appellant Gavin Kealey QC Julia Dias QC Eric Ribot SC (Instructed by De Comarmond & Koenig) |
LORD MANCE:
Introduction
Background facts
Code civil and force majeure
"1382 Tout fait quelconque de l'homme, qui cause à autrui un dommage, oblige celui par la faute duquel il est arrivé, à le réparer.
1383 Chacun est responsable du dommage qu'il a causé non seulement par son fait, mais encore par sa négligence ou par son imprudence.
1384 On est responsable non seulement du dommage que l'on cause par son propre fait, mais encore de celui qui est causé par le fait des personnes dont on doit répondre, ou des choses que l'on a sous sa garde.
…..
La responsabilité ci-dessus a lieu, à moins que …. le gardien de la chose ne prouve que le dommage a été causé par l'effet d'une force majeure ou de la faute exclusive de la victime. …."
Judgment of Court of Civil Appeal
"89 In other words, while l'irrésistibilité of the event is the crucial element, the predictability of same becomes important to find whether precautions could have been taken to avoid the disastrous consequences.
90 In sum, what is force majeure with respect to cyclone Firinga was decided by the French Courts on the basis of its résistibilité. The fact that it was résistible was decided by the fact that it was prévisible. In other words, the prévisibilité of the cyclone rendered it possible for people to mitigate the disaster it would have caused."
"105 When the Assemblée Plénière speaks of the double need of prévisibilité [sic] and irrésistibilité, one may need to follow what is the nature of the cumulative character of these two elements. If it is unpredictable and irresistible, there is no doubt, it is a force majeure. But there may occur an event which is prévisible yet when it strikes, it is irresistible. In that case, it would qualify as a force majeure:
"Quand le danger prévisible était irresistible, il y a bien force majeure"
para 714, Philippe Le Tourneau, La responsabilité civile, 3ème ed. p.241.
106 Thus, where an event is predictable but irresistible, it amounts to a force majeure where it can be shown that all measures taken to make the event resistible were of no avail. What the courts are looking for is whether all reasonable measures have been taken to render the predictable resistible. ….
"… exigeant des juges du fond qu'ils recherchent si, en l'espèce, toutes les mesures requises pour empêcher l'événement avaient été prises: ...."
"there is a very real difference between absence of faute or negligence and a standard of conduct referable to reasonable and practical possibility. The mere fact that a defendant has not been negligent or at fault does not of itself prove that he took all measures that were reasonably possible in the sense of being reasonably and practically available to him. In other words, a concept of irresistibilité which incorporates a standard of reasonable and practical possibility still requires a defendant to do much more than prove that he was not negligent. On the contrary, he must go further and show that once the event was foreseeable he did everything which was reasonably possible and practicable, not only that which it might have been reasonable for him to do."
"Q: En fin de compte, concernant la grue, le technicien voit si c'est bien monté, la grue lorsque c'est installée d'après les données du dessin ?
A: Nous faisons strictement ce qui est demandé dans le livre. Nous faisons tous les tests, tous les réglages de sécurité ; ensuite un ingénieur qui vient vérifier, fait des tests et émet un certificat.
Q: En temps normal ?
A: Oui, quand la machine est montée.
Q: Pas en temps cyclonique?
A: Quoi?
Q: D'après le livre, la grue peut tenir à quelle vitesse de vent?
A : Dans le livre, c'est pas vraiment mentionné aucune part, mais je pense ça devrait tenir à peu près à des vents supérieurs à 200 km selon les spécifications données comme je vous ai dis, nous travaillons selon ce livre, nous faisons ce que ce livre nous recommande – on a toujours fait ca [sic] dans le passé, on n'avait jamais eu de problèmes.
Q: Le livre vous recommande jusqu' à quelle vitesse de vent ?
A: C'est pas dit.
Q: D'après vous c'est plus de 200 ou de 300 km?
A : Je ne sais pas, je ne suis pas apte à entrer dans les détails techniques.
Q : Est-ce que vous attendiez que la grue allait tomber pendant le cyclone?
A : Non.
Q : C'est tout
.....................
.....................
Court : He was asked his opinion about what would be the maximum speed of wind that this crane would be able to resist and he expressed the opinion that it may be more than 200 km. Am I right, Sir Marc?
Sir Marc David: Perfectly right, Your Lordship.
XXX 1/332-33 or 2/552-3
"The evidence of this expert witness is to the effect that they went by the books, and to the letter at that, following the Potain Manual. The evidence shows also that they have the temps normal in mind when they raise the crane. The clearance certificate is issued with that in mind, once the crane has been erected for operation. That leaves a lot to be desired: Poain Manual is silent on how this artificial structure of over 16 sections tall by 5,750 metres with an overhanging arm of 36 metres long having been imported in a cyclone-prone country would behave in such an environment, more particularly, in cyclonic conditions. And what is more. [sic] General Construction have never seriously bothered about it."
"[118] From the above, it is clear that the cyclone itself did not have any of the characteristics of a force majeure and the crane was put up with little thought given to its capacity to resist a cyclone by no means exceptional in intensity or otherwise.
[119] It is our view that where a construction company has put up a man-made structure of such an inverse-L type, of such a height, with an arm of such a length which overhangs people and property, it is not at the time of Class 1 warning that it should start bothering about the potential and inherent mischief that such a structure would constitute to life and property, especially in time of a cyclone. The gardien of such a chose should have done his homework better. He should have carried an up-front assessment of the manner in which his abnormal structure poses risks to the safety and security of life and property well ahead of Class I warning; indeed, well before, from the moment of the very conception of such a structure if it was meant to be imported and used in climates other than cyclone-free France.
[120] As it is, General Construction had never bothered to find out how such a structure made in France in 1973 and imported to be used in Mauritius and bought by itself as a second-hand platform behaves in a cyclonic environment, all the more so when it knows that it cannot be dismantled so easily from the announcement of Class 1 Warning and that such a structure necessarily suffers from metal fatigue in view of its age. No one in his right mind in Mauritius waits for Class 1 warning to start bothering about the capacity of the superstructure he has put up to resist an impending cyclone. What he has to do he has to do well ahead of Class 1. Any failure is at his risk and peril."
"entirely ignored the evidence that Potain manufactured cranes for use worldwide and that the crane in question had been used by the Appellant in Mauritius for 12 years without any problem."
"MR Y ABOO BAKER SC: And, we have in Mauritius we had cyclones with much more wind strength. Therefore, it was prévisible.
COURT: The other thing is I haven't seen it. What is the capacity of the crane? What is the wind that it can resist?
MR Y ABOO BAKER QC: I will have a word on that, my Lords because I believe the onus was on the respondent [sic] to bring that to you. Mr Curé comes and says, I believe it must be above 200 kms, 201, 202, 203, we do not know. The onus vested [sic] squarely in view of Article 1384 on the respondent [sic] to bring to your attention".
Interest in favour of second respondent
"Clerical Mistakes
Clerical mistakes in pleadings, orders or judgments owing to any accidental slip or omission, may at any time be corrected by the Court or by the Master on a motion made to that effect in presence of all parties".
Reliance on this provision could on the face of it have been, but was not, placed by the second respondent before the trial judge. The omission of any award to the second respondent of the interest it had claimed must have been a mistake – an important one in the context of litigation which has been so regrettably drawn out as this has been in the Mauritian courts. The post-judgment Addendum issued by the Court of Appeal could, at least if it had been made on a motion by the first respondent, also be regarded as made under this slip rule, in view of the Court's failure to reiterate the judge's award of interest in its favour.
Conclusions