Privy
Council Appeal No. 37 of 1997
Electrotec
Services Limited Appellant
v.
Issa
Nicholas (Grenada) Limited Respondent
FROM
THE
COURT OF APPEAL OF GRENADA AND THE
WEST
INDIES ASSOCIATED STATES
---------------
JUDGMENT OF THE LORDS
OF THE JUDICIAL
COMMITTEE OF THE PRIVY
COUNCIL,
Delivered the 16th
February 1998
------------------
Present at the hearing:-
Lord Browne-Wilkinson
Lord
Lloyd of Berwick
Lord
Nolan
Lord
Hoffmann
Mr.
Justice Gault
·[Delivered by Lord Browne-Wilkinson]
-------------------------
1. In
this action the plaintiff, Electrotec Services Limited ("Electrotec")
claims against the defendant, Issa Nicholas (Grenada) Limited ("Nicholas
Limited"), the sum of EC$325,921.00 plus interest at 6% for work done by
Electrotec in 1985 and 1986 at the Ramada Renaissance Hotel of which Nicholas
Limited is the owner. There is no
dispute that the work was done by Electrotec Limited. The question is whether Nicholas Limited, as building owner, is
liable under a direct contract with Electrotec that Electrotec should do the
work or whether the work was done by Electrotec as a sub-contractor of Project
Control Associates ("PCA") under a main contract made between
Nicholas Limited and PCA.
2. The
detailed history of the matter is extremely confused. In outline it is as follows.
On 7th August 1985 Nicholas Limited
entered into a
written contract with PCA as
main contractor for the renovation of certain rooms at the hotel
("contract 1"). This contract
was subsequently extended to cover further works at the hotel ("contract
2"). The written contract between
Nicholas Limited and PCA incorporated common form general conditions which
provided for nominated sub-contractors whom Nicholas Limited, as employer,
could in certain circumstances pay direct.
There is no doubt that in relation to the works covered by contracts 1
and 2 Electrotec carried out works as sub-contractor under contracts with PCA
as main contractor.
3. Late
in 1985, Electrotec undertook further works on the site. These further works are referred to in the
documentation as contracts 3 and 4.
There is no formal written document relating to these later contracts. Some of the work under contracts 3 and 4
consisted of additions and alterations to works done under contracts 1 and 2:
the rest was new work. It appears that
some of the work under contracts 3 and 4 had been done before 5th November
1985.
4. On 5th
November 1985 a meeting took place between Mr. Gay, of Electrotec, and Mr.
Nicholas, the moving light behind Nicholas Limited. According to Mr. Gay's evidence, at that meeting he was
instructed directly by Mr. Nicholas to do the work comprised in contract
3. In a letter of 6th November 1985
from Mr. Gay to Mr. Hosein of PCA the work comprised in contract 3 is referred
to as being the subject matter of quotations given directly by Electrotec to
Mr. Nicholas. A copy of that letter was
sent to Mr. Nicholas. Mr. Gay's
evidence was that he was later instructed directly by Mr. Nicholas to do the
work comprised in contract 4. In a
letter dated 2nd December 1985 from Mr. Hosein of PCA to Mr. Nicholas, Mr.
Hosein refers to a valuation of the contract work and states, inter alia,
that the figures include contract 4 and "incorporate the contracts agreed
to by you with Electrotec for the Sewer Treatment Plant and for the External
Drainage works". According to Mr.
Gay's evidence, Mr. Nicholas promised to pay Electrotec directly for the work
comprised in contracts 3 and 4. This is
to an extent confirmed by a letter dated 4th December 1985 from Mr. Gay to PCA
in which amounts totalling over $157,000 are described as "amounts
promised to be paid by I.N. Limited".
5. The
work comprised in contracts 3 and 4 were carried out by Electrotec.
On 14th November 1985 Electrotec put in a request for payment to PCA on
a form which described PCA as "main contractor" and the request for
payment covered, in addition to work included in contracts 1 and 2 works
included in contracts 3 and 4. In the
period from 30th November 1985 to 22nd May 1986, Electrotec continued to apply
to PCA for payment for the works included in contracts 3 and 4 but, apparently,
without success. Having failed to
extract the money from PCA, Mr. Gay sought payment direct from Mr.
Nicholas. There was a meeting between
Mr. Gay and Mr. Nicholas in June 1986 at which Mr. Gay sought direct payment. Mr. Nicholas requested that Electrotec
should separate the work done by Electrotec into two categories viz., first,
the category for which Mr. Nicholas was primarily liable to PCA as the main
contractor in relation to which Electrotec's claim was against PCA; second, the
work for which Nicholas Limited was directly liable to Electrotec. According to Mr. Gay, Mr. Nicholas again
promised to pay Electrotec the amount due under the second category.
6. On
18th June 1986 Mr. Gay wrote to PCA (with a copy to Mr. Nicholas). It reads as follows:-
"As per Mr. I.
Nicholas request, we have separated the items of work which were directly
requested by him from that for which you are responsible."
7. The
letter then specified a sum of $82,842 odd as being the sum due from PCA. On the following day, 19th June 1986, Mr.
Gay wrote to Mr. Nicholas (with a copy to PCA). The letter reads as follows:-
"Further to our
discussions, we have detailed the works requested by you on the attached
sheets.
Contract 4 - Additional
works ... 54,459.00
Amount outstanding .... $367,071.00
10. We
look forward to your payment as promised, as these moneys are now outstanding
for over four (4) months and is causing us some serious embarrassment with our
Bankers and Suppliers."
11. Enclosed
with the letter were two schedules setting out the detailed items: these
schedules referred to PCA as being the "main contractor".
12. There
was a further meeting between Mr. Gay and Mr. Nicholas on 11th July 1986. According to Mr. Gay's evidence, he and Mr.
Nicholas then agreed that certain items in the schedules sent on 19th June were
due but Mr. Nicholas queried certain other items. Mr. Nicholas said that he would pay the amounts which PCA
certified as due. Mr. Gay's account of
that meeting is confirmed by two letters dated 21st August 1986. The first was a letter from Mr. Gay to Mr.
Nicholas which reads as follows:-
"As requested by
you, we have requested Messrs. Project Control Associates to certify our final
account on the above mentioned contract.
13. We
have received the approval from PCA in the sum of $325,931.00. We wish to confirm that we would accept this
sum ... as full settlement for works performed on this contract.
15. On the
same day, 21st August 1986, Mr. Hosein of PCA and a Mr. Karamath wrote to Mr.
Nicholas a letter headed "Grenada Beach Hotel Final Account - Electrotec
Services Limited" which read as follows:-
"Electrotec
Services Limited have requested us to review their final statement of account
prior to submission to you.
16. Attached
is a copy of their statement with adjustments made by us to the figures
submitted.
Contracts
3 and 4 (original) $159,721.00
agreed with you)$166,200.00
$325,921.00"
19. Sent
with that letter was a schedule referring to "Work Under Query"
which, according to Mr. Gay, refers to the work which Mr. Nicholas required to have certified by PCA: that schedule
contained certain amendments to the original figures and was signed by Mr.
Hosein on 21st July 1986.
20. There
was no response to any of these letters by Mr. Nicholas or his company. Electrotec did not receive payment. Mr. Gay telephoned Mr. Nicholas in October
1986 asking for settlement. Mr.
Nicholas declined to pay saying that certain of the items had not been
approved. That prompted the only
document in the case emanating from Nicholas Limited being a letter which is
undated but received on 29th October 1986.
For the first time that letter alleged that Nicholas Limited were not
liable and that Mr. Nicholas assumed that PCA had sub-contracted the work to
Electrotec.
21. In
these confused circumstances, Electrotec brought these proceedings. In the amended statement of claim Electrotec
alleged that "between the months of November 1985 and July 1986, the
Defendant contracted with the Plaintiff for the Plaintiff to effect certain
electrical and plumbing works at the Defendant's said premises". It then alleged that PCA had been engaged to
certify the work to be done by the plaintiff, that PCA had certified the sum of
$325,921.00, the certificate for which had been sent to the defendant, and
claimed the sum of $325,921.00. The
defence denied that there was any contract between Electrotec and Nicholas
Limited.
22. The
case came on for trial before St. Paul J.
It is a singular feature of this case that, despite the documentary
confusion and the lack of any communications from Nicholas Limited in the
correspondence, no evidence was called on behalf of Nicholas Limited at the
trial. The only oral evidence was that
of Mr. Gay of Electrotec and Mr. Hosein of PCA. They gave evidence to the effect summarised above. In addition Mr. Hosein gave evidence which
is of critical importance. He said:-
"There were works
relating to external works which started before the end of 1985. We supervised their works. That was requested by Mr. Nicholas
verbally. This was separate from the
original works. We were not the
contractor for any of that work."
23. In
re-examination he said that he received no order under the contract for
additional works and that he did not recall signing a contract for
the central facilities of the hotel (contract 3). The judge apparently accepted the evidence
of Mr. Gay and Mr. Hosein and held the evidence of a direct agreement by Mr.
Nicholas with Electrotec to do the works comprised in contracts 3 and 4 to be
consistent with the conduct of the parties and the correspondence. He expressed his conclusion as follows:-
"I conclude that
the defendant did contract with the plaintiff for the plaintiff to effect
certain electrical and plumbing works at the defendant's premises and the
defendant engaged [PCA] to act on its behalf with regard to the said works and
the defendant promised to make payment to the plaintiff provided [PCA]
certified the said works. The works
were certified by [PCA]. I therefore
give judgment for the plaintiff ..."
24. Nicholas
Limited appealed to the Court of Appeal (Sir Vincent Floissac C.J. and Byron
and Singh JJ.A.) who unanimously allowed the appeal. On the appeal, counsel contended that the Court of Appeal should
not disturb the findings of fact made by the trial judge in accordance with the
ordinary principles. However in the
judgment of the court given by Byron J.A. he said:-
"This proposition,
however, is not applicable to this appeal as no evidence was adduced on behalf
of the appellant and the findings of the learned trial Judge did not turn on
his evaluation of the credibility of any witness. His decision was based on the inferences he drew from
uncontradicted oral and documentary evidence."
25. He
then considered the legal principles which he considered applicable. He set out the well known principle that,
since there is no privity of contract between building owner and
sub-contractor, in the ordinary case the building owner cannot be directly
liable to the sub-contractor. He said
that an employer might become directly liable to a sub-contractor on an
"express" promise to pay the sub-contractor where he gives him a
direct order to carry out work. In
support of that proposition he relied upon Keating on Building Contracts
5th Edn. page 285. Given the fact that
in relation to contracts 1 and 2 Electrotec was undoubtedly a sub-contractor,
he held that the evidence given by Mr. Hosein that his role changed at the end
of 1985, after which Nicholas Limited paid Electrotec and other sub-contractors
directly, was not sufficient
to show a
direct obligation owed by Nicholas Limited to Electrotec. He further held that, in relation to the two
occasions on which Mr. Nicholas entered into direct dealings with Mr. Gay
leading to Electrotec doing the work, this was not sufficient to give rise to a
separate contract because there was no "express" promise to pay the
sub-contractor. He held that the
conduct of the parties up to the end of May 1986 was consistent only with the
existence of the sub-contract between Electrotec and PCA. As to the promises to pay, made by Mr.
Nicholas in June, July and August 1986, the Court of Appeal did not treat them
as creating a contractually binding promise changing the status of the parties.
26. Their
Lordships are unable to agree with the approach taken by the Court of Appeal to
the judge's findings of fact. True it
is that there was no conflict of evidence since no evidence was called on
behalf of Nicholas Limited. The learned
judge accepted the evidence that Mr. Nicholas instructed Electrotec separately
to do the works comprised in contracts 3 and 4 and did in June, July and August
1986 promise to pay Electrotec directly for such work provided that it was
certified by PCA. The question is not
what inference should be drawn from this evidence but whether it should be accepted
at all given the undoubted position in relation to contracts 1 and 2 that
Electrotec was a sub-contractor, PCA being the main contractor.
27. In
their Lordships' view the critical question in this case is whether the works
comprised in contracts 3 and 4 were ever the subject of any contract between
Nicholas Limited and PCA as main contractor.
If there ever was such a contract, then the work under contracts 3 and 4
must have been done by Electrotec as sub-contractors. That being so, Electrotec would have no claim to direct payment
from Nicholas Limited in the absence of a separate contract by Nicholas Limited
to pay Electrotec direct even though Electrotec was a sub-contractor. Like the Court of Appeal their Lordships
would have had considerable doubts whether such a separate agreement to pay
Electrotec, as sub-contractor, directly could be spelt out of the evidence.
28. But in
their Lordships' view that was not the question confronting the judge. Although the point is not noticed by the
Court of Appeal, Mr. Hosein of PCA was quite clear in his evidence (which was
not challenged in cross-examination) that
Nicholas Limited never
entered into any contract with PCA to do the works comprised in
contracts 3 and 4. In those
circumstances, this was not a case in which an undoubted sub-contractor was
seeking to prove a separate obligation on the employer requiring him to pay the
sub-contractor. The only question in
this case was whether there was in fact a contract between Nicholas Limited and
Electrotec there being no evidence of any contract between Nicholas Limited and
PCA relating to the works comprised in contracts 3 and 4. Given that Electrotec did the work and that
in 1986 Mr. Nicholas treated himself as liable to pay Electrotec for such work
there was ample ground on which the judge could make his finding of fact that
there was a direct contract between Nicholas Limited and Electrotec (there
being no contract between Nicholas Limited and PCA) to do the work comprised in
contracts 3 and 4 and therefore to pay for it.
29. In
their Lordships' view, therefore, the Court of Appeal were not justified in
upsetting the factual findings of the learned judge which were consistent with
the evidence before him. Their
Lordships will humbly advise Her Majesty that the appeal should be allowed, the
judgment of the Court of Appeal set aside and the judgment of St. Paul J.
restored. The respondent must pay the
appellant's costs in the Court of Appeal and before their Lordships' Board.
© CROWN COPYRIGHT as at the date of
judgment.