Summary: The complainant requested the projected spending figures for funding for the Nuclear Warhead Capability Sustainment Programme up to and including the financial year 2024/2025 as submitted to HM Treasury as part of the Comprehensive Spending Review process. The Information Commissioner-™s decision is that the MOD were incorrect to determine that the public interest favoured the withholding of the information in respect of section 35(1)(a) and that it was also incorrect to rely on section 43(2), which the Information Commissioner found was not engaged. Information Tribunal appeal number EA/2012/0048 withdrawn.
Section of Act/EIR & Finding: FOI 35 - Complaint Upheld, FOI 43 - Complaint Upheld