Summary: On 29 June 2008 the complainant made a request to Homes for Islington for information linking a section 20 notice and a contractor-™s itemised list of work and costs. At the internal review stage the public authority provided further information pertaining to the request. The complainant contacted the Commissioner to complain about the public authority-™s delay in dealing with the request; the format and content of the disclosed information; the validity of the refusal notice and the public authority-™s complaints procedure. The Commissioner finds the public authority complied with section 11 of the Act and regulation 6 of the EIR but did not comply with section 10 and regulation 5. He requires no remedial steps from the public authority. Information Tribunal appeal number EA/2011/0058 dismissed.
Section of Act/EIR & Finding: FOI 10 - Complaint Upheld, FOI 11 - Complaint Not upheld, EIR 5 - Complaint Upheld, EIR 6 - Complaint Not upheld