|
||
Neutral citation [2009] CAT 26
IN THE COMPETITION
Case Number: 1099/1/2/08
APPEAL TRIBUNAL |
||
|
||
Victoria House
Bloomsbury Place
29 April 2009
London WC1A 2EB
Before:
VIVIEN ROSE
(Chairman)
PROFESSOR PAUL
STONEMAN
DAVID SUMMERS |
||
|
||
Sitting as a Tribunal in England and
Wales |
||
|
||
BETWEEN:
NATIONAL GRID PLC
Appellant
- v -
GAS AND ELECTRICITY MARKETS
AUTHORITY
Respondent
supported by
SIEMENS PLC
CAPITAL METERS LIMITED
METER FIT (NORTH WEST)
LIMITED
METER FIT (NORTH EAST)
LIMITED
Interveners |
||
|
||
Heard at Victoria House on 15 to 28 January
2009 |
||
|
||
JUDGMENT (Non-Confidential
Version) |
||
|
||
|
||
Note: Excisions in this judgment
marked “[…][C]” relate to passages excluded having regard to
Schedule 4, paragraph 1 to the Enterprise Act 2002 |
||
|
||
APPEARANCES |
||
|
||
Mr Jon Turner QC, Mr
Josh Holmes, Mr Meredith Pickford and Ms Laura Elizabeth
John (instructed by Pinsent Masons LLP) appeared on behalf of the
Appellant.
Ms Monica Carss-Frisk QC,
Mr Brian Kennelly and Mr Tristan Jones (instructed by the
Gas and Electricity Markets Authority) appeared on behalf of the
Respondent.
Mr Christopher Vajda QC
and Ms Kassie Smith (instructed by Hill Hofstetter LLP) appeared on
behalf of Siemens plc.
Mr Christopher Vajda QC
and Mr Ben Rayment (instructed by Slaughter and May) appeared on
behalf of Capital Meters Limited.
Mr Fergus Randolph and
Ms Sarah Abram (instructed by United Utilities Group plc) appeared
on behalf of Meter Fit (North West) Limited and Meter Fit (North East)
Limited. |
||
|
||
i |
||
|
||
|
||
TABLE OF CONTENTS |
||
|
||
I.
BACKGROUND…………………………………………………….. 1
(a)
The development of competition in metering………………………….
1
(b)
The genesis of the National Grid MSA contracts……………………...
4
(c)
British Gas’s response to the possibility of metering competition…….
5
II. THE MSA
CONTRACTS…………………………………………... 6
(a) The Legacy
MSA……………………………………………………… 8
(b)
The New and Replacement MSA……………………………………… 10
III. THE
APPEAL……………………………………………………….. 11
IV.
MARKET DEFINITION…………………………………………… 12
V.
DOMINANCE……………………………………………………….. 17
(a)
Market shares………………………………………………………….
18
(b)
Barriers to entry and expansion………………………………………. 19
(c)
Countervailing buyer power…………………………………………..
21
(d)
The relevance of the P&M terms……………………………………... 29
(e)
Conclusions on dominance……………………………………………
30
VI.
ABUSE……………………………………………………………….. 30
(a)
What is “normal competition” in this market?
...................................... 32
(b)
The economic effect of the Legacy MSAs……………………… ...........
34
(d)
The level of charges incurred by an accelerated replacement
programme……………………………………………………………. 36
(e)
The use of counterfactuals………………………………………….. 42
(f)
Maintenance bundling………………………………………………… 57
(g)
The effects of the Legacy MSAs (i) Did the Legacy MSAs result in
British Gas reducing the level
of replacement undertaken by the
CMOs? ................................. 60
(ii) Did the Legacy MSAs deprive
consumers of the benefits of
competition?
...............................................................................
69
(iii) Did the Legacy MSAs hinder
product innovation and risk
impeding the roll out of smart
meters? ...................................... 71
VII.
CONCLUSION ON ABUSE………………………………………... 74
VIII. PENALTY AND
DIRECTIONS……………………………………. 75
IX.
CONCLUSION………………………………………………………. 85 |
||
|
||
ii |
||
|
||
|
||
I. BACKGROUND
1. This appeal
is brought by the appellant, National Grid plc (“National Grid”), under
section 46 of the Competition Act 1998 (“the 1998 Act”). National Grid
challenges a decision published by the Gas and Electricity Markets
Authority (“the Authority”) on 21 February 2008. In that decision (“the
Decision”) the Authority found that National Grid had abused its dominant
position in the market in Great Britain for the provision of
domestic-sized gas meters, contrary to section 18 of the 1998 Act and
Article 82 of the EC Treaty. The Decision imposed a fine of £41.6 million
on National Grid and ordered National Grid to put an end to the
infringement.1
2. The main
hearing of this appeal took place in January 2009. Before that hearing,
the parties submitted a large number of witness statements relating to
many different aspects of the appeal. Some of the witnesses were cross
examined during the hearing in January 2009. There is considerable
movement of personnel among the companies operating in this market so that
some witnesses now working for one of the parties gave evidence about what
happened at a time when they were working for another company. In Annex 1
to this judgment we set out a dramatis personae explaining the
witnesses’ employment position at the time they signed their statements
and their employment position at the time about which they gave their
evidence.
(a) The development of competition in
metering
3. The
provision of natural gas to end consumers involves a number of distinct
steps. The gas is extracted by gas producers and then sold to shippers.
The shippers contract with gas transporters which own and operate the
pipelines to carry the gas throughout Great Britain. Gas suppliers then
purchase gas from the shippers and sell it to domestic and commercial end
consumers.
4. Under the
Gas Act 1986, every domestic customer is obliged to receive their supply
of gas through a gas meter. Meter operators, such as National Grid,
typically buy the
1 Under s. 36A(3) of
the Gas Act 1986, the Authority is entitled to exercise functions under
Part 1 of the 1998 Act in respect of conduct relating to activities
falling within the Authority’s remit. The Authority is also designated as
a national competition authority for enforcing the competition provisions
of the EC Treaty: see regulation 3 of the Competition Act 1998 and Other
Enactments (Amendment) Regulations 2004 (S.I. 2004/1261) and section
54(1)(b) of the 1998 Act. |
||
|
||
1 |
||
|
||
|
||
meters from manufacturers and
retain ownership of the gas meter throughout its life. The meter operator
provides the meter to the gas supplier so that the gas supplier can sell
gas to a particular household. Installation costs are significant in
comparison with the value of an individual meter. National Grid’s average
installation costs, in addition to the cost of buying the meter, are
currently over £50 per meter. National Grid has traditionally sought to
recover the costs of providing the meter, including any on-going
maintenance, through the annual rental charges it sets for each meter. A
similar business model has been adopted by competing meter operators
(“CMOs”) which have recently entered the market. This means that in
general2 there is no transaction charge for the initial
installation of the meter at the premises – the meter is simply installed
by the meter operator and the gas supplier starts paying the monthly
rentals. If a householder decides to change gas supplier there is normally
no need for the meter to be removed or adjusted. The meter operators and
gas suppliers make arrangements whereby the rental payments for the meter
are thereafter made to the meter operator by the gas supplier to which the
customer has switched his or her supply.
5. As at the date of the Decision
there were approximately 22 million domestic gas meters installed in Great
Britain. Of these, around 90 per cent are domestic credit meters (“DCMs”)
and the remaining 10 per cent are prepayment meters (“PPMs”). Both types
of meter measure the consumption of gas, but a PPM requires the consumer
to pay in advance for gas for example by using a prepayment card.
Consumers using DCMs are billed periodically either following a meter
reading or based on an estimate of gas used over the preceding period.
According to the Decision (paragraphs 2.14 and 2.16), a new DCM costs
around £20 and typically lasts 20 years whereas a new PPM costs around
£120 and typically lasts 10 years. In practice, the time for which both
PPMs and DCMs remain installed at a property can be considerably longer
than these periods. Because PPMs are much more expensive, it can often be
economic to refurbish a PPM and install it at another property if it is
removed before the end of its useful life. DCMs are generally installed
only once and discarded if removed from a property even if they are still
functioning properly. |
||
|
||
2 Under their
contracts with British Gas the CMOs charge a transaction fee for carrying
out a functionality exchange. The significance of this is discussed
further below. National Grid has charged upfront costs for the
installation of new “Category 2” meters (that is a meter installed in a
premises which did not previously have a gas meter) since October 2000. By
January 2004, there were 700,000 installed meters for which an
installation charge had been levied. |
||
|
||
2 |
||
|
||
|
||
6.
Historically, National Grid’s predecessor (Transco plc) had a monopoly
both of gas transportation and of the supply of gas meters and ancillary
services. National Grid’s meter related costs were recovered from the
charges set by the regulator for National Grid’s overall transportation
business. Following the introduction of competition into the domestic
supply of gas in 1998 the then regulator, Ofgas, began consulting the
industry on how to enable other companies to compete with National Grid in
supplying gas meters. In order for such competition to be possible, it was
important to separate out the charges that National Grid set for its
metering services from its charges for gas transportation. Ofgas therefore
brought about the separation of National Grid’s existing regulated
transportation price control into three separate components:
transportation, gas metering and gas meter reading. A new five year price
control was put in place in April 2002. For the first time this set an
identifiable price cap for National Grid’s metering rental
charges.
7. In 2002
the Authority also launched an industry wide review, referred to as the
Review of Gas Metering Arrangements (“RGMA”), designed to encourage
competition in gas meter provision. According to the Decision (paragraph
2.61), RGMA was aimed at “setting up standard, industry-wide processes and
data flows to support all companies in the metering market and the
competitive retail market”. Paragraph 2.63 of the Decision explains
further:
“Central to the strategy for
securing effective competition was the ‘supplier hub’ principle. This
principle places the responsibility on gas suppliers to appoint meter
operators to provide and install meters at their customers’ premises and
to provide ancillary services (such as meter maintenance) in respect of
those meters. The meter operator could be a gas transporter such as
[National Grid], the in-house metering business of a gas supplier, or a
third party. Suppliers were seen as being best placed to respond to
customer demand for better service standards and more sophisticated
meters, and, under the supplier hub approach, are able to select meter
operators through competitive tenders.” (footnote references
omitted)
8. Moving to
the ‘supplier hub’ principle required meter operators and gas suppliers to
enter into new contracts. The new contracts entered into between National
Grid and gas suppliers were known as Provision and Maintenance (“P&M”)
contracts. The terms of these contracts had been developed multilaterally
by the industry as part of the RGMA process. Under the P&M contracts
there are no upfront charges for the installation of a meter. National
Grid is remunerated by monthly rental payments from the time of
installation until the meter is removed. Suppliers are able to
replace |
||
|
||
3 |
||
|
||
|
||
National Grid’s meters at 48
hours’ notice without incurring any additional charges. The rental prices
contained in the P&M contracts are in line with the cap set by Ofgem
in the April 2002 price control.
(b) The genesis of the National Grid MSA
contracts
9. Over the
years prior to the setting of the price control in 2002, the prices
charged for gas meters by the meter manufacturers had fallen
substantially. The Authority estimated that there was a fall in prices of
about 46 per cent between 1995 and 2000. At some point, National Grid
realised that new CMOs entering the industry following the RGMA would be
able to undercut the rental rates in the P&M contract terms. If CMOs
were able to replace National Grid’s meters with those of a CMO offering
lower rentals, without having to pay a penalty, this would deprive
National Grid of the rental income stream from which it had expected,
prior to the introduction of competition, to be able to recoup its costs
of installation. Given that most meters have little reuse value once
removed, this would lead to an outcome that National Grid referred to as
the “stranding” of its assets. National Grid initially explored with the
Authority whether some adjustment could be made to the price control to
compensate it for the risk of asset stranding following the introduction
of competition. But in the light of a negative response from the
Authority, National Grid instead began negotiations with each of the gas
suppliers for a new contract covering the continued rental of the meters
that were already installed in customers’ premises. These installed meters
are generally referred to as the “legacy” meter stock.
10. The evidence
before the Tribunal about the negotiations of these new contracts focussed
mainly on National Grid’s negotiations with British Gas plc (“British
Gas”). British Gas at that time had a share of around 65 per cent of the
market for the supply of domestic gas. The negotiations between National
Grid and British Gas are an important element in these proceedings (see
further, paragraphs [61] onwards, below). For now it is sufficient to note
that a Letter of Intent was signed by British Gas and National Grid in
December 2002 setting out the principal matters which the parties agreed
would form the basis of the more detailed contract in due
course.
11. Two meter services agreements (“MSAs”) were
eventually devised: |
||
|
||
4 |
||
|
||
|
||
(a) a contract covering the
existing base of installed meters owned by National Grid as at 1 January
2004 pursuant to which British Gas would rent a declining minimum number
of meters per year with early replacement charges payable by British Gas
if the number of meters rented fell below that minimum (“the Legacy MSA”);
and
(b) a contract covering any
meters installed by National Grid on or after 1 January 2004 (the “New and
Replacement MSA” or “N/R MSA”).
12. The Legacy and
N/R MSAs were signed by National Grid and British Gas in January 2004.
Between January and August 2004 National Grid entered into equivalent
contracts with RWE npower plc, Powergen Ltd (which subsequently became
part of the E.ON group), Scottish Power plc, Scottish and Southern Energy
plc and several smaller gas suppliers. Electricité de France (“EdF”) chose
to keep its legacy meters on the existing P&M contract
terms.
(c) British Gas’s response to the possibility of
metering competition
13. As a result of
the RGMA, British Gas decided to take advantage of the opening up of the
market to competition by awarding some of its metering work to CMOs.
Evidence on the tender process was provided to the Tribunal by Mr Steven
Lewis who, from November 2000 to July 2006, worked for British Gas first
as a member of what they called the Unbundling Team and then as part of
the National Metering Team. In June 2001 British Gas published a notice in
the Official Journal of the European Communities inviting
expressions of interest in tendering to supply British Gas with gas and
electricity metering services. In August 2001 an Invitation to Tender
(“ITT”) was issued to those who had expressed an interest and a short list
of eight potential bidders was drawn up. The ITT divided Great Britain
into seven regions so that British Gas could appoint a number of different
CMOs, each with exclusive rights to supply meters in the area or areas
allocated to it.
14. Tenders were
submitted by a number of potential CMOs including the Interveners in these
proceedings: Capital Meters Limited (“CML”) which is partly owned by
Siemens plc (“Siemens”) and Meter Fit (North West) Limited and Meter Fit
(North East) Limited (together, “Meter Fit”). Meter Fit is a special
purpose vehicle created by |
||
|
||
5 |
||
|
||
|
||
United Utilities plc. British Gas
also started negotiations with Utility Metering Services Ltd (“UMS”) which
is a subsidiary of National Grid but is not regulated by any licence
obligations under the Gas Act 1986. UMS trades as OnStream.
15. In May 2002
British Gas announced the appointment of Meter Fit as its meter services
provider in North Wales and North West and North East England. In December
2002 it appointed UMS as its meter provider in Scotland, the Midlands, the
South East and South West of England and South Wales. Finally, in December
2003, it appointed CML to provide meters in East Anglia and most of
London. The contracts entered into between British Gas and the CMOs
generally lasted for 20 years. That 20 years was divided into two periods.
In the initial period, usually 5 years, the CMO had the exclusive right to
install meters for British Gas in the relevant region of the country
(subject to certain exceptions where the choice of installer was
effectively outside British Gas’s control). After the expiry of the
initial period that exclusivity no longer applied but the contract
remained in place to govern the continued rental of the meters which had
been installed by the CMO during the initial period.
16. There was some
evidence before us as to why gas suppliers other than British Gas did not
take advantage of the opening of the market by placing some of their
metering business with CMOs. The Interveners suggested that gas suppliers
were inhibited from doing so by the Legacy MSA contract they had signed
with National Grid or by the Authority’s investigation into the Legacy MSA
terms. National Grid refuted that suggestion by citing a number of other
possible reasons. We have not found it necessary to make any finding on
this point. We understand that shortly before the hearing in this appeal,
some of the other gas suppliers did appoint CMOs to undertake some of
their meter work.
II. THE MSA CONTRACTS
17. Before
describing the main provisions of the Legacy MSA and N/R MSA in more
detail, there are a number of additional terms which are widely used in
this industry that need to be explained. |
||
|
||
6 |
||
|
||
|
||
Discretionary and non-discretionary
replacements
18. Under the Gas
Act 1986, National Grid is responsible for ensuring the accuracy and
safety of its meters. Batches of meters which are shown, following the
testing of a sample by National Grid, to fall outside a fixed accuracy
threshold are entered on a replacement schedule. At the relevant time,
that threshold was set at a level where 30 per cent of a particular
population is or is likely to become in the near term +/– 2 per cent
inaccurate. Under the terms of the Legacy MSA, National Grid specifies a
number of meters from the replacement schedule which the gas supplier must
replace in a given year. These replacements are referred to as “policy
replacements” and are considered “non-discretionary” because the gas
supplier is required, by National Grid, to ensure they are carried out. At
least once a year, National Grid issues the list of meters that have been
identified for policy replacement and will specify the minimum number of
non-urgent meters that must be replaced in the year in question. The full
list of non-urgent meters for replacement must contain at least 1.3 times
the number that National Grid has specified should be replaced. This gives
the gas supplier a degree of flexibility over precisely which meters it
replaces. The gas supplier does not have to use National Grid to replace
these policy meters but can elect instead to use a CMO to replace
them.
19. Meter
replacement can also occur following a request from a gas supplier to
exchange a DCM for a PPM or vice versa. The request may originate either
with the gas supplier in order to mitigate, for example, a perceived
credit risk or with the end consumer making a request for an exchange.
These are called “customer requested exchanges” (“CREs”) or “functionality
exchanges”. The Authority (at paragraph 4.38 of the Decision) includes
such replacements in its category of “non-discretionary exchanges” in
addition to replacements that occur when a meter is faulty (for example,
when a meter is replaced on a maintenance visit) or to meet policy
replacement requirements. These can be contrasted with “discretionary
exchanges” which are replacements which the gas supplier decides to carry
out on its own initiative.
“Smart” and “dumb” meters
20. The gas meters
making up the legacy stock are referred to as ‘dumb’ meters because the
volume of gas consumed by the customer can be ascertained only by someone
visiting |
||
|
||
7 |
||
|
||
|
||
the premises in order to record
the gas meter reading. Trials have been carried out in relation to more
advanced or ‘smart’ meters which would allow for automated meter readings
and two-way electronic communication between the gas supplier and the
meter, as well as other services, such as remote disconnections and
switching between credit and prepayment modes. The move to smart metering
is considered further in paragraphs [196] onwards, below.
(a) The Legacy MSA
21. The Legacy MSA
terms apply to all domestic meters rented as at 1 January 2004 by National
Grid to the gas suppliers who signed a Legacy MSA contract. The aim of the
contract is to ensure that however quickly the gas supplier decides to
replace National Grid’s meters with those of the CMOs, National Grid’s
on-going income from that gas supplier is to some extent protected. The
contract first identifies the number of meters that the gas supplier is
renting from National Grid at the start date. The gas supplier commits
either to rent from National Grid in each month a defined proportion of
that initial population or to make additional payments to National Grid if
it does not rent that defined proportion. The period covered by the
commitment is 18 years in respect of DCMs and 7 years in respect of PPMs.
The number of meters that the gas supplier must pay for declines by an
equal number each month over the given period (subject to the adjustments
referred to below). The number of DCMs that the supplier is committed to
paying for thus diminishes by 1/216th each month (i.e. 18
years’ worth of 12 monthly periods). The initial population of PPMs is
allowed to reduce by 1/84th each month (i.e. 7 years’ worth of
12 monthly payments). This contractual monthly reduction in the commitment
is described by the parties as “the glidepath”.
22. Before 2004,
DCMs had been replaced at an average annual rate of 5 per cent. The Legacy
MSA allows for replacement at a level of about 5.5 per cent per year. The
effect of the glidepath, so far as DCMs are concerned, is that gas
suppliers can replace, free of penalty, a number of meters slightly in
excess of the historic rate at which National Grid had replaced them
before the RGMA. The Legacy MSA therefore shielded National Grid to some
extent from the possibility that the opening of the market to competition
would spur gas suppliers to replace its meters at a much faster rate than
they had done when National Grid was the monopoly
supplier. |
||
|
||
8 |
||
|
||
|
||
23. The allowed
number of charge-free meter removals is adjusted each year to take account
of the fact that end-customers are lost and gained by one gas supplier to
another over the period. So if a customer decides to change his gas
supplier, the meter at that premises will move from being covered by the
old supplier’s Legacy MSA to being covered by the new supplier’s Legacy
MSA (assuming the new supplier has signed a Legacy MSA). The glidepath is
reset at the start of each month with any necessary adjustments to reflect
changes in market share during the course of the previous month being made
to the following month’s rental commitment.
24. In any month
where the number of meters rented is in fact lower than the number that
the glidepath indicates should have been rented in that month, the
supplier incurs certain charges. If the remaining legacy stock in fact
rented is between 90 per cent and 100 per cent of the glidepath
commitment, the supplier continues to pay the full rental due for the
number of meters that it was supposed to be renting at that point. In this
judgment we refer to this 10 per cent tolerance band as the “Take or Pay
zone” and to the charges set for removed meters falling in the Take or Pay
zone as “Below Line Rentals” or “BLRs”.
25. If the remaining
stock actually rented that month is below 90 per cent of the glidepath
commitment, the supplier must pay National Grid the BLRs for the meters in
the Take or Pay zone and in addition pays a one-off fee per meter for any
meter beyond the 10 per cent Take or Pay zone. This fee is referred to in
the Legacy MSA as a “Premature Replacement Charge” or “PRC”. If a supplier
removes meters beyond the Take or Pay zone and pays PRCs for those meters,
the on-going commitment under the Legacy MSA is reduced by the number of
meters for which a PRC has been paid. The glidepath is adjusted to reduce
the overall number of meters rented but also to reduce the monthly
diminution in the rental commitment. This means that the gas supplier has
to rent fewer meters as a result of paying PRCs but the number of meters
he can remove each month is also reduced so that his commitment to rent at
least some meters under the Legacy MSA still lasts for 18 and 7 years in
the case of DCMs and PPMs, respectively.
26. The amount of
the PRC payable declines annually over the term of the glidepath. The list
of PRCs for DCMs shows 18 separate PRC fees, one for each year of
commitment, |
||
|
||
9 |
||
|
||
|
||
declining from £58.44 in year 1
to £1.19 in year 18. The list for PPMs shows 7 separate PRC amounts, one
for each year of commitment, declining from £37.95 in year 1 to £1.74 in
year 7.
27. According to
National Grid, the PRCs are calculated on the basis of the net present
value of the rental revenue foregone in the future from the early
replacement of the meter before the expiry of the 18 year obligation (or 7
year obligation in the case of PPMs), less the costs National Grid no
longer incurs as a result of having one less meter installed. PRCs are
adjusted annually on 1 April each year in accordance with the Retail
Prices Index (“RPI”). An alternative higher set of PRCs is payable where
National Grid is of the reasonable opinion that a gas supplier has removed
a disproportionate number of younger meters. This extra charge, according
to National Grid, is designed to compensate it for the reduced likelihood
of the remaining stock of assets lasting until the end of the glidepath,
something that would in turn lead to a reduction in rental
income.
28. It is only the
commitment to pay for a certain number of meters that has an 18 year or 7
year duration. The Legacy MSA itself is indefinite in duration. If the gas
supplier does not in fact choose to replace all its National Grid legacy
meters with new meters it must, of course, still pay rental to National
Grid under the Legacy MSA for all the meters it in fact rents. At the end
of the 18 year commitment period, the gas supplier will no longer have to
pay BLRs or PRCs if it then decides to replace legacy meters with new
National Grid or CMO meters. The rental set by the Legacy MSA is adjusted
over the period of the contract in line with inflation.
(b) The New and Replacement MSA
29. The N/R MSA
covers meters installed by National Grid on or after 1 January 2004. The
contract also includes PRCs but there is no Take or Pay zone and hence no
BLRs. PRCs are not calculated on the basis of a scheduled glidepath which
reduces annually but on the number of years that have elapsed since the
individual meter was installed. The PRC therefore declines over the
assumed life of the meters, which is taken to be 10 years for PPMs and 20
years for DCMs. The PRCs in the N/R MSA are, according to National Grid,
designed to compensate it for the present value of lost revenues
that |
||
|
||
10 |
||
|
||
|
||
National Grid would have received
had the meters remained in place for their assumed life, net of the
present value of costs saved as a consequence of early
replacement.
III. THE APPEAL
30. The main findings of the Authority as set out
in the Decision are as follows:
(a) The relevant product
market for the purposes of the Decision is the market for the provision of
installed domestic-sized gas meters including the ancillary service of
meter maintenance in Great Britain.
(b) National Grid is dominant in that
market.
(c) National Grid has
abused that dominant position by entering into long term contracts which
restrict the rate at which gas suppliers can replace National Grid’s
meters with meters offered by CMOs. The operative part of the Decision
identified the abuse as “including in the long-term meter supply
arrangements (the MSAs) the Take or Pay charges and the Premature
Replacement Charges”.
(d) That abuse had been
committed negligently for the purposes of section 36(3) of the 1998
Act.
31. As well as
imposing a fine of £41.6 million, the Authority directed National Grid to
put an end to the infringement and to refrain from engaging in conduct
having the same or equivalent exclusionary effect. The implementation of
the Authority’s directions ordering National Grid to put an end to the
infringement was suspended by order of the President, pending the
determination of the appeal. Following the lodging of the Notice of
Appeal, CML, Siemens and Meter Fit were granted permission to
intervene.
32. The Notice of
Appeal is an extensive document which, including annexes, runs to over 300
pages. National Grid challenges many aspects of the Decision and the
grounds of challenge are wide ranging. Further points have been developed
by the parties in their extensive written submissions in the run up to and
during the hearing. Both sides have argued that some of these further
points are inadmissible either, as regards National |
||
|
||
11 |
||
|
||
|
||
Grid’s case, because they have
not been prefigured in the pleadings or, as regards the Authority’s case,
because they depart from the reasoning set out in the
Decision.
33. The Tribunal has
all along been concerned to keep the scope of these proceedings within
manageable bounds: see our ruling in this appeal of 8 October 2008 ([2008]
CAT 26, paragraph [3]). However, we bear in mind that this case is not
simply about an alleged abuse occurring in the past: the glidepath
provided for in the Legacy MSA still has 14 years to run in respect of DCM
meters and its provisions are likely, if they remain in place as a result
of this appeal, to have an important impact on the development of
competition in the relevant market. This is an appeal on the merits, not a
judicial review of the Authority’s decision: see paragraph 3(1) of
Schedule 8 to the 1998 Act. It is appropriate in the public interest for
the Tribunal to consider all relevant arguments raised in the appeal
provided that the parties have had sufficient opportunity to make
submissions on them.
IV. MARKET DEFINITION
34. The test for
determining the relevant market under Article 82 EC and the Chapter II
prohibition in the 1998 Act is well established in the jurisprudence both
of the European Courts and of this Tribunal. By the time of the hearing in
this appeal, it was only the definition of the relevant product market,
not of the geographic market that was in dispute. The position is
summarised by the European Commission in its Notice on the definition
of the relevant market for the purposes of Community competition law
(OJ C372 9.12.1997) as follows:
“a
relevant product market comprises all those products and/or services which
are regarded as interchangeable or
substitutable by the customer, by reason of the products’
characteristics, their prices and their intended use” (paragraph
7).
35. In Aberdeen
Journals Ltd (No 1) v Director General of Fair Trading [2002] CAT 4
the Tribunal stressed that each case depends on its own facts and
that:
“… it is
necessary to examine the particular circumstances in order to answer what,
at the end of the day, are relatively straightforward questions: do the
products concerned sufficiently
compete with each other to be sensibly regarded as being in the same
market? Are there other products which should be regarded as
competing in the same market? The
key idea is that of a competitive constraint: do the other products
alleged to form part of the same market act as a competitive
constraint on the conduct of the
allegedly dominant firm?” (paragraph [97]). |
||
|
||
12 |
||
|
||
|
||
36. The market
definition arrived at by the Authority was “the market for the provision
of installed domestic-sized gas meters including the ancillary service of
meter maintenance in Great Britain” (paragraph 3.51 of the Decision). In
coming to this conclusion the Authority found that:
(a) new or replacement meters are good substitutes for
installed, legacy meters;
(b) DCMs and PPMs are
effective substitutes for each other because they both measure gas
consumption in domestic homes;
(c) larger capacity gas
meters are not effective substitutes for domestic-sized gas meters and
neither are electricity meters;
(d) there is no separate
market for meter maintenance so that maintenance should be treated as an
ancillary service to the provision of the installed gas
meter;
(e) there is insufficient
supply-side substitutability from electricity metering to justify
including it in the relevant market.
37. In the
Tribunal’s judgment, the Authority’s analysis of the relevant market was
entirely correct. It is critical to recognise that the product under
consideration is not the gas meter itself. The product was found in the
Decision to be the installed gas meter and this was not challenged
by National Grid. This means that the product is in fact a service – the
service of providing an installed meter to measure the amount of gas
consumed by the retail customer in the domestic premises. This service
comprises a number of elements: the initial purchase of the meter from the
manufacturer, the installation of the meter, its maintenance and various
data services. The importance of the data services element in the overall
product was illustrated by the problems that arose for the CMOs when
starting up under their contracts, as discussed later. When gas suppliers
are deciding from whom to acquire metering services they compare the
service on offer from the company which is currently providing the service
with the service on offer from a company which could replace the existing
provider’s meters with its own. The comparison will be based in large part
on price but may also take |
||
|
||
13 |
||
|
||
|
||
into account other elements of
service such as speed of response to calls. As far as the gas supplier is
concerned, the on-going metering services offered by the operator who owns
the existing installed meter competes with those offered by a different
meter operator who would install a new meter in order to provide the
services. The evidence we saw about British Gas’s reaction to the
potential supply from CMOs shows the company making just such a
comparison.
38. Expert evidence
on market definition was given for National Grid by Dr Mark Williams, an
economist working for the consultancy firm NERA Economic Consulting. He
provided two expert reports and gave evidence at the hearing. His first
argument was that the issue is not whether the physical characteristics of
the meters are the same but whether the economic characteristics are.
Because most of the costs of legacy meters are sunk whereas those of new
or replacement (“n/r”) meters are not, the incremental costs of supplying
a n/r meter are substantially higher than the incremental costs of
supplying a legacy meter. The economics of supply of the two meters are
therefore subject to real and objective differences.
39. It may well be
true that from the supplier’s perspective there are important differences
in the economics of supplying the metering service through a legacy as
compared with a n/r meter. But that has nothing to do with the test that
we must apply. The case law which binds us is clear that the product
market is defined primarily by assessing demand-side substitutability,
that is, by looking at what the customer (i.e. the gas supplier) regards
as the available alternatives to the putative dominant company’s offering
(see, for example, paragraph 13 of the EC Commission’s Notice on the
definition of the relevant market). There are many instances where the
processes involved for suppliers in creating two products are very
different. That does not prevent the final products from being in the same
relevant market if they are good substitutes from the customer’s point of
view.
40. Dr Williams’
evidence on this point confuses the physical meter with the service
provided in part through that meter. That service can be provided equally
well, so far as the customer is concerned, by the operator who owns the
existing installed meter and by the operator who would provide the same
service after installing a new meter at the premises. The need for the
service on the part of the gas suppliers generates a
demand |
||
|
||
14 |
||
|
||
|
||
for gas meters which is satisfied
partly by the stock of gas meters which are already installed and
providing the service in situ and partly by a flow demand for new
gas meters which can then be supplied and which will then provide the same
service in situ. The stock and flow aspect of the provision of gas
meters does not create two separate markets. |
||
|
||
41. Dr Williams’
second argument was that it was not correct to regard n/r meters as
competing in the same market as installed meters because the apparent
competitiveness of the CMOs’ offering only arises because of a distortion
in the market. That distortion was the fact that the legacy meters had
been installed without an upfront installation charge and were, in 2002,
rented under the P&M contracts which allowed them to be replaced
without incurring any additional charge. Dr Williams explained this in his
first report as follows:
“The normal commercial approach
to supplying a Meter is to have a term contract supported by payment
completion arrangements, up-front outright sale of the Meter to the
customer, or an up-front payment to cover the initial sunk costs combined
with some arrangement for the provision of ancillary services. In all of
these cases the “economic price” of continuing to consume the services of
an already-installed Meter (where “economic price” refers to the payments
a gas supplier can avoid by ceasing to use the installed Meter) will
reflect the incremental costs of continuing to provide the Meter after
its installation costs have been incurred. In most instances this
price will be well below that of replacing the installed Meter with a new
Meter, and the two will not be economic substitutes at any economically
relevant margin of choice. …. The reason why gas suppliers considered an
accelerated replacement of Legacy Meters with N/R Meters after
deregulation was that normal commercial (and competitive) payment
completion arrangements did not exist for National Grid’s Legacy Base. …
[F]or precisely this reason the competitive constraints operating on
National Grid’s Legacy Meter base were fundamentally different from those
operating on N/R Meters.” (paragraph 19, emphasis in the
original).
42. In his oral
evidence he developed this argument (after prompting by the Tribunal) by
reference to the “cellophane fallacy”.3 The cellophane fallacy
posits that if a monopolist has raised the price of its product
sufficiently above the competitive level, a further increase in price may
push customers to turn to products which would not have been regarded as
substitutes if the monopolist’s product had been priced competitively. It
would be a mistake in such a case to treat those other products as being
in the same relevant market as the dominant company’s product. By analogy,
Dr Williams argues, distortions present in the metering market (namely the
fact that no up-front installation |
||
|
||
3 Named after the U.S Supreme Court decision
in United States v Du Pont de Nemours & Co. 351 US 377, 76 S Ct
994 (1956): see OFT’s Guideline on Market Definition (OFT 403) paragraph
5.5. |
||
|
||
15 |
||
|
||
|
||
charge had been paid but the
P&M terms still allowed penalty-free replacement of meters)
artificially made n/r meters competitive with legacy meters when they
would not be in an undistorted market where payment completion had been
assured.
43. We do not accept
that this point is valid. If all the legacy meters had been installed over
the decades under competitive conditions it is certainly not inevitable
that every meter would be subject to payment completion arrangements of
the kinds that Dr Williams mentions. Users of the meters would have had
different attitudes to risk and it is likely that a variety of
arrangements would have grown up to accommodate this, as we see in the
supply of other long-lived assets. The cellophane fallacy deals with a
particular problem where the allegedly abusive behaviour itself might
create a distortion in the price elasticity of products inside and outside
the relevant market. It is not a general proposition that the Tribunal
must try to strip out of its analysis aspects of the market which are not
operating in a “normal” competitive way. It will only rarely be useful to
base market analysis on an imaginary market which is fundamentally
different from the market which in fact exists. In this case, such an
exercise is unlikely to lead to a useful result in terms of going on to
assess National Grid’s market power at the time of the conclusion of the
MSA contracts.
44. Finally on
market definition, National Grid raised an issue of supply-side
substitutability on the part of electricity metering companies. On
analysis, this point was simply that it is easier for companies who are
already providing electricity metering services to enter the market for
gas metering services. National Grid did not seem to be suggesting that it
makes sense to include the value of electricity metering services
in the market. It is true, as National Grid argued, that the barriers to
entry into the gas metering market are lower for a company which is
already providing electricity metering services. But as we discuss further
below, the experience of the CMOs shows that even for an undertaking with
an established electricity metering business, the move into gas metering
can be problematic.
45. We therefore
reject National Grid’s contention in its Notice of Appeal that there are
separate relevant markets for legacy meters and for n/r
meters. |
||
|
||
16 |
||
|
||
|
||
46. Several other
points were raised by the parties in relation to National Grid’s case on
market definition. The Authority argued that there was an inconsistency,
which Dr Williams denied, between National Grid’s case on countervailing
buyer power, discussed below, and its case on market definition. The
Authority also argued that Dr Williams’ acceptance that the logic of his
argument meant that each gas meter installed in a house is in its own
separate product market showed that his analysis led to absurd and
unhelpful results – a conclusion which Dr Williams also denied. Various
other points were raised concerning actual and potential in-house supply
and whether there are other examples of separate relevant product markets
being found in relation to physically identical products. The Tribunal
also queried with Mr Turner QC how it helped National Grid’s case to
establish the existence of two relevant markets when the conduct
complained of took place either in the legacy meter “market” (of which
they, as the former monopoly supplier, had a 100 per cent share) or in a
closely neighbouring market. We have considered all these points but none
of them changes our conclusion set out above.
V. DOMINANCE
47. Dominance has
been defined by the European Court of Justice (“ECJ”) in Case 322/81
Michelin v Commission [1983] ECR 3461 as:
“a position of economic strength
enjoyed by an undertaking which enables it to hinder the maintenance of
effective competition on the relevant market by allowing it to behave to
an appreciable extent independently of its competitors and customers and
ultimately of consumers.” (paragraph 30).
48. The Decision
relied on three elements to establish National Grid’s dominance: its high
market share, the existence of barriers to entry and expansion and the
absence of sufficient countervailing buyer power (“CBP”) to negate market
power.
49. In their
skeleton argument the Authority submitted that National Grid only puts
dominance in issue if we accept National Grid’s case that there are
separate relevant markets for legacy and n/r meters. National Grid denied
that their challenge was limited in this way. In our judgment National
Grid’s case was, putting it broadly, that because of the particular
characteristics of this market, its high market share was not a reliable
indicator of the existence of market power. We therefore consider that
the |
||
|
||
17 |
||
|
||
|
||
arguments on dominance must be
resolved even though we have upheld the Authority’s definition of the
relevant market.
(a) Market shares
50. The Decision
sets out at paragraph 3.63 a table showing market shares for the provision
of installed domestic-sized gas meters in Great Britain. The table shows
National Grid as having a 98 per cent share of installed meters in January
2002 falling to an 89 per cent share in January 2007. This table conflates
the share of installed meters owned by the meter operators with those
operators’ shares in the market for the provision of metering services.
But it is not suggested that a table showing percentage shares of, say,
the value of rentals paid in the relevant years would reveal a materially
different picture. National Grid’s market shares in the table include
meters provided by both National Grid and by UMS (its subsidiary which
successfully tendered for some of British Gas’s new work). Again it is not
suggested that removing UMS’s share would make a significant difference to
the market shares shown in the table in the Decision.
51. The Authority
and the Interveners relied on the well known statements of the ECJ, for
example in Case 85/76 Hoffmann-La Roche v Commission [1979] ECR 461, to the effect that large market shares are in themselves evidence of
a dominant position – the Authority accepted that these market shares were
not determinative of dominance but asserted that they were highly
indicative and important. The Authority also relies on the disparity
between National Grid’s market share and the shares of the CMOs. In our
judgment, however, in the years immediately after a statutory monopoly has
been lifted, one should approach market share figures with caution. Even
vigorous and unconstrained market entry is unlikely to result in an
instantaneous and substantial reduction of the incumbent’s market share
from 100 per cent. But such market entry may well mean that the incumbent
has little effective market power and is destined to lose market share
rapidly in future. We are therefore prepared in the particular
circumstances of this case to treat market share as one indicator of
market power but as not raising any particular presumption of the
existence of dominance. It is an important indicator but it is also
important to consider other factors that may cast a different light on the
market dynamics. |
||
|
||
18 |
||
|
||
|
||
(b) Barriers to entry and expansion
52. The Decision
concluded that the market has characteristics which make entry and
expansion on a significant scale very difficult in a short space of time.
Possible barriers include National Grid’s installed base and position in
the market, the expected length of the asset life, the fact that the costs
of installing the legacy meters were sunk by the time the Legacy MSA was
negotiated, the practical logistics of purchasing and then installing
large numbers of meters in domestic customers’ premises quickly as well as
the need to achieve economies of scale and density to be able to compete
effectively.
53. In our judgment
the evidence is overwhelming that there are significant barriers to entry
and expansion in this market. This is demonstrated most clearly by the
difficulties that the CMOs in fact encountered in trying to perform their
contracts with British Gas. Those difficulties were described by Mr Neil
Avery who gave evidence on behalf of National Grid. He was employed at
British Gas from 1985 to 2002 as Head of Metering and Transportation
Services and from 2002 to 2005 as their Head of Operational Services. He
describes the logistical problems that affected the CMOs in starting up
under the contracts awarded to them following the British Gas tender
exercise. For example, the start date for Meter Fit was delayed due to
data systems problems. Meter Fit was unable to gain access to the meters
which it was expected to target for replacement. Mr Avery states that CML
also “found going live very challenging” and that OnStream faced
operational difficulties to start with. In each case it is clear from his
evidence that if British Gas had insisted on holding the CMOs strictly to
their contractual obligations, the CMOs may well have been forced to exit
the market. Their ability to continue as market entrants depended on
British Gas adopting a supportive attitude towards them, in some cases
allowing a post-contract increase in the level of the rentals and in one
case making a payment of a substantial one-off sum. These problems arose
for the CMOs even though, as we discuss further below, the volumes of
meter replacement which the CMOs were obliged to undertake were
comparatively modest and they were already providing electricity metering
services.
54. National Grid’s
answer to this was that they faced the same barriers as the CMOs in that
it is just as difficult for National Grid to gain entry to premises to
replace the meter as it is for the CMOs. Indeed, it is clear that
UMS/OnStream, National Grid’s |
||
|
||
19 |
||
|
||
|
||
subsidiary, also had difficulty
in fulfilling its contractual obligations at the start. But that is not,
in our judgment, an answer to the point because in default of the meter
being replaced, the gas supplier continues to pay National Grid for meter
services at that customer’s premises using the existing meter. Unless or
until a CMO can actually replace the physical meter in the premises,
National Grid retains the market share represented by the rentals on that
meter.
55. National Grid
accepted that economies of scale and of density are important in this
market. How this works was described in the witness statement of Mr David
Lee on behalf of Siemens. He is responsible for the commercial management
of all of Siemens’ metering operations across both the electricity and gas
markets. He explained how the volume and mix of work available to the
meter operator has an impact on operator efficiency, that is on the volume
of jobs per day each engineer in the workforce can complete. The costs of
employing and managing the workforce represent a large proportion of
Siemens’ cost base. He says further that subcontractors typically need
eight completed jobs a day to be profitable if they are to price on a per
job basis. National Grid put forward the evidence of Mr Andrew Spence,
Operations Delivery Manager at UMS/OnStream. He described how problems
about low density of work can be overcome by improving access rates for
policy replacement work through better contact with the end consumer to
ensure that someone is in the house to keep the engineer’s appointment: in
his view “[a] CMO’s success lies in ensuring that the customer contact and
appointment making process is properly designed and continuously reviewed
and improved so as to increase access prospects”. Nonetheless in our
judgment density of work is an important factor in allowing CMOs to
establish and grow viable businesses in this market.
56. National Grid
again argued that the existence of the legacy meter base does not give it
any particular advantage in acquiring density in its meter fitting
operations. This may be so, but the requirement of economies of scale and
density are still important barriers to entry from the point of view of
the CMOs.
57. Mr Lewis (a
former employee of British Gas giving evidence on behalf of CML) described
the factors that British Gas looked for when short-listing candidates from
the ITT. One important factor he mentions is the bidder’s reputation,
proven capability and |
||
|
||
20 |
||
|
||
|
||
credentials including its ability
to service a contract of the relevant scale. This too is a barrier to
entry, albeit one which he was satisfied that the three selected bidders
(Meter Fit, OnStream and CML) were able to overcome.
58. National Grid
argued that the scale of recent market entry shows that there are no real
barriers to this market. In its Notice of Appeal (paragraph 263) National
Grid set out a table showing the number of meters fitted in 2005, 2006 and
2007 by each of the meter operators. This shows that (counting UMS as a
new entrant and not as part of National Grid’s market share) the CMOs have
fitted more than half of all new meters in 2005 and 2007 and almost half
in 2006. In our judgment, these figures must be treated with caution.
First, there is a dispute between the parties as to whether it is right to
treat UMS as being a new entrant for this purpose or whether its
installation numbers should be combined with those of National Grid.
Secondly, there are various factors present in the market which might
distort the scale of new entry, for example the existence of the Legacy
MSAs themselves (since they affect the overall volume of meter replacement
work) and the desire of British Gas to sponsor new entry. This latter
factor may have disguised the extent of barriers to entry and distorted
the shares of business. We do not consider it is right to interpret these
estimates of the shares of meters fitted as showing that market entry has
been healthy or unimpeded.
59. There was
considerable debate between the economist expert witnesses about whether
the existence of sunk costs constituted a barrier to entry. We consider
this issue further in the context of countervailing buyer power. Even
without this factor, there is plenty of evidence that barriers to entry
and expansion exist and have had a significant impact on the initial
opening up of this market to competition.
(c) Countervailing buyer power
60. In Hutchison
3G UK Limited v Office of Communications [2005] CAT 39, the Tribunal
described the proper approach to the assessment of countervailing buyer
power (“CBP”):
“[T]he right question is not the
binary one of whether CBP exists or not. In other words, it is not enough
to ask whether there is CBP, and if so to hold that there cannot be
[dominance]. CBP is the power of counterparties to offset the powers of
the party whose allegedly superior powers are under consideration, and the
important question is what degree of CBP is there, and (bearing in mind
all the circumstances) does it |
||
|
||
21 |
||
|
||
|
||
operate to a sufficient extent so
as to mean that there is no [dominance]? CBP is not an absolute concept in
terms of its strength. It is a concept which embodies a possible range of
strengths. In any case where it is relevant, the relevant question is
likely to be not whether there is CBP or not, but whether there is any
CBP, and if so how much and what effect does it have.” (paragraph
[110(c)]).
The question to be addressed in
this context is thus not just the presence or absence of CBP on the part
of British Gas, but the degree of such CBP and the extent to which
it operated as a constraint on National Grid’s ability to exert market
power. National Grid put its case on CBP in two ways. The first argument
analysed what happened during the negotiations with British Gas between
2002 and 2004 leading up to the signing of the Legacy MSA. The second
argument was a more theoretical argument about the effect of sunk costs on
the bargaining power of the parties.
(i) Negotiations with British Gas
61. The case put
forward by National Grid focussed on the negotiations between it and
British Gas. As British Gas is by far the biggest gas supplier in Great
Britain, if they do not have sufficient CBP to negate National Grid’s
dominance then none of the other gas suppliers will have. We were taken
through a large number of contemporaneous documents including internal
minutes of both British Gas and National Grid, correspondence between the
two companies and notes of meetings. We also had written and oral evidence
from Mr Avery who was involved in the negotiations on behalf of British
Gas and Mr Colin Shoesmith who was a key participant in those negotiations
on behalf of National Grid.
62. The case
presented by National Grid was that the company realised by February 2002
that it faced a serious risk of losing about £600 million of its £1.4
billion investment in meters as a result of the introduction of
competition. That figure of £1.4 billion represents the Regulatory Asset
Value (“RAV”) on which returns on assets were calculated for the purpose
of setting the regulated price cap. Mr Shoesmith says that he attended
meetings with British Gas executives in 2002 where the threat was made
that “British Gas would simply rip out all of our installed meters as
quickly as it could and replace them with cheaper ones”. He says that at a
meeting in July 2002 he was “personally threatened” with a five year
replacement programme by British Gas. He records that when he went into
the negotiations with British Gas over the MSAs, he |
||
|
||
22 |
||
|
||
|
||
thought that British Gas “had the
upper hand… British Gas could rip out all of our meters and there was
nothing we could do about it”. Mr Avery’s evidence from the British Gas
side of the negotiations supported that of Mr Shoesmith, saying that
British Gas felt that it was in a strong negotiating position because of
the possibility of stranding National Grid’s meter assets.
[…][C]
63. Other people
within National Grid seem to have been a little more sanguine than is
suggested by Mr Shoesmith in his evidence. In an internal National Grid
Board minute of 24 April 2002 the author noted that British Gas can save a
substantial amount each year on meter rental because the market entrants’
rental is substantially cheaper than the regulated price of £12.90. But he
went on: “practical logistics limit the pace with which these reductions
can be achieved across their […][C] customers”. With considerable
prescience, the author of the minute notes that if British Gas act
rationally:
“they should be willing to trade
off their ability to secure a large … discount on an initially small
though growing population of meters, for the ability to secure a smaller,
though still sizeable discount on all the meters they need for their
customers”.
This is precisely what happened.
64. We have seen a
note of the 1 July 2002 meeting. This indeed records, as Mr Shoesmith
says, that British Gas said at the outset of the meeting that they
expected to be able to replace all meters in five years using CMOs. But it
also records National Grid’s response which was that, based on their own
estimate of comparative rental levels and of how fast meters could be
replaced, National Grid “would take the risk that [British Gas] could not
replace meters as fast as they say.” It is apparent from the note that,
after that opening rattling of sabres on each side, the parties settled
down to negotiate terms, British Gas indicating that it wanted to
negotiate rental prices on the basis of a commitment of 13 years for DCMs
and 5 years for PPMs.
65. An internal
National Grid slide presentation on 3 July 2002 does not mention the 5
year threat. One slide notes that the rate at which meters are replaced
prematurely is affected by price differentials, meter supply capacity and
management and labour resources, apparently concluding that there is
“significant uncertainty” about this. This accords with Mr Avery’s
evidence that no one knew how fast replacement could
take |
||
|
||
23 |
||
|
||
|
||
place because at that time no one
had tried to implement a rapid replacement of large numbers of
meters.
66. We find that the
evidence we have seen and heard falls far short of demonstrating that
British Gas had sufficient CBP to negate National Grid’s market power to a
significant extent. We have been concerned to interpret the
contemporaneous documents in the context of what we understand to be the
commercial position of the two companies. This approach is more fruitful
than simply picking out comments made in internal emails between
executives. Overall, the internal National Grid and British Gas documents
show that both companies engaged in a careful assessment of their
respective options and were able to make a shrewd assessment of the
factors and calculations of net present value and costs that were likely
to be influencing the other party’s stance. This is entirely what we would
expect to find between these two substantial and seasoned companies
operating in a sector where they have been principal players for many
years.
67. It is true that
the outcome of the negotiations was an agreement with which British Gas
was, and still is, content. It is also true that important concessions
were made by National Grid: Mr Avery records in his statement that the
British Gas Managing Director regarded the negotiation of the MSAs as a
real success. When British Gas walked away from the negotiations when they
reached a stalemate in the Autumn of 2002, it was National Grid which came
back to British Gas with an improved offer of lower legacy rentals,
leading to the conclusion of the Letter of Intent in December 2002. But
British Gas did not get their own way on all points: for example National
Grid refused to unbundle maintenance even though British Gas appears to
have based its ITT proposals on the assumption that the CMOs would be able
to maintain National Grid meters. Also, British Gas had initially asked
for the glidepath commitment to be limited to 13 years for
DCMs.
68. We also accept
that National Grid did not succeed in setting rental and PRC levels which
resulted in it recovering the totality of its RAV. National Grid argued
that this RAV was a good proxy for its sunk costs. Under the Legacy MSAs
ultimately signed, even if the gas suppliers had replaced meters at
precisely the rate set by the glidepath, the total revenues earned over
the 18 years would have fallen short of National
Grid’s |
||
|
||
24 |
||
|
||
|
||
sunk costs by many millions of
pounds. National Grid pressed the fact that they had had to agree a
substantial drop in the legacy meter rental in order to achieve a deal
with British Gas. But Mr Shoesmith accepted in cross examination that
because National Grid were able to offer a price reduction across the
board for legacy stock, they expected to be able to agree a rental that
was above the level being offered by the CMOs. Further, we agree that this
price differential is significant because, as the Authority argued, the
correct comparison when assessing the scope of the price reduction is a
comparison between National Grid’s prices and the CMOs’ prices and not a
comparison between the Legacy MSA prices and the P&M
prices.
69. A key factor in
considering the extent of CBP is what options were open to British Gas if
the negotiations reached a stalemate. It was not open to British Gas to
choose not to rent any meters from National Grid. Each party was a “must
deal” partner of the other. The default option for British Gas was to
remain on the P&M terms and try to switch out meters as fast as
possible with the CMOs. Both parties were well aware of the uncertainties
that surrounded such a policy in terms of the logistical challenges that
we discussed in the context of barriers to entry.
70. There was an
additional factor at play here, namely an understanding on the part of
both parties that the Authority would be opposed to the gas suppliers
adopting a policy of taking out large numbers of functioning meters in
order to take advantage of the CMOs’ lower rentals. The Authority’s
evidence was that this understanding was not in fact a correct reading of
their position -- their concern was only with the public reaction if a
very rapid and wide scale replacement of fully functioning meters took
place. But wherever the idea came from, the contemporaneous documents show
that British Gas, like other players in the market, believed it was
constrained in how rapidly it could switch out National Grid meters by a
perception that the Authority considered that an accelerated programme
would raise serious customer disruption issues. National Grid were aware
of this factor and were prepared to use it both in its negotiations with
the Authority and with British Gas. In a June 2002 internal document
setting out National Grid’s strategy for negotiating with the Authority,
the author stresses that it is expected that both National Grid and the
Authority will wish to discourage inefficient replacement of existing
meters before the end of their useful lives and reduce potential
disruption for consumers that may result from accelerated replacement
programmes. |
||
|
||
25 |
||
|
||
|
||
National Grid’s 9 October 2002
slide presentation to British Gas lists as one of the risks to British Gas
of not doing a deal that British Gas “will be the only major player
prematurely replacing meters”.
71. The third
important factor is that the evidence shows that British Gas was not a
particularly price sensitive customer going into the negotiations with
National Grid. First, Mr Avery says in his statement that the business
case for British Gas awarding CMO contracts did not anticipate that there
would be any reduction in rentals for legacy meters. It was based
entirely on there being a substantial difference between the P&M price
and the CMOs’ rental prices and a gradual cost saving by replacement of
National Grid meters with cheaper CMO meters. The ITT that was issued by
British Gas in 2001 sought tenders for installation of only about one
third of the number of existing meters – and that included new
installations as well as replacement of legacy meters. In other words,
even though British Gas expected at that point (a) to continue to pay the
regulated P&M rental on all legacy meters and (b) that CMO rentals
would be cheaper, it still sought tenders on the basis that it would
spread replacement of its legacy meters over 13 to 15 years. On this basis
any reduction that British Gas negotiated from National Grid in
respect of legacy meter rentals was a bonus rather than an essential
element of the viability of their business plan. National Grid must have
recognised that British Gas’s ITT signalled that British Gas contemplated
paying the P&M rental on large numbers of meters for a considerable
period. Any improvement that National Grid was prepared to offer on this
position was likely to be welcomed by British Gas.
72. Further, Mr
Avery explains that British Gas realised that there were in fact
disadvantages to the company if the National Grid rentals came down too
low. The disadvantages were twofold. First, a very low National Grid price
would make it difficult for CMOs to enter the market. As Mr Avery says,
British Gas saw “benefits in keeping three players in the market” and so
wanted to retain a margin within which the CMOs could operate viable
businesses. Secondly, British Gas understood that National Grid, because
of its regulatory non-discrimination obligations, would have to offer
whatever level of legacy rental it agreed with British Gas to all other
gas suppliers. By contrast a low price negotiated with the CMOs would not
have to be offered to other gas suppliers. There was no competitive
advantage in the retail market for British Gas in pushing the National
Grid legacy rental price down. As Mr Avery put it: |
||
|
||
26 |
||
|
||
|
||
“The price agreed …. was not as
low as we would expect to get under the CMO contracts but that suited us.
Having decided that we were going to purchase our meter provision on a
competitive basis we would not have wanted to abandon the competitive
process. Any price that National Grid offered us for its meters would also
be offered to other gas suppliers which would have eroded some of the
competitive advantage to us in the low CMO prices that we had negotiated.
Some differential between the CMO price and the National Grid price was
therefore good. It would have been very difficult for us contractually if
National Grid had gone down as low as the CMO level…” (paragraph 33 of Mr
Avery’s witness statement).
73. These factors
indicate that the fact that British Gas was and may still be content with
the terms of the Legacy MSA does not establish that those terms are not
anti-competitive. British Gas’s interests do not necessarily coincide with
those of the CMOs, or with those of the end consumer, or with those of the
Authority.
(ii) The relevance of sunk costs
74. National Grid’s
second argument was that the competitive conditions affecting the
bargaining position of a supplier of a gas meter differ profoundly
depending on whether negotiations take place before or after the sinking
of cost. Dr Williams on behalf of National Grid argued that the existence
of sunk costs put National Grid in a weak bargaining position if its aim
was to recover as much of its sunk costs as possible. It was the victim of
what economists refer to as the “hold up” problem (in the sense of a
robber “holding up” a bank) because the party which has sunk its costs is
at the mercy of the other party if it is to get any revenue to offset the
unrecovered cost of its investment. The position was very different with
regard to new or replacement meters where the negotiation over rental
terms took place before the costs had been sunk, that is before the meter
had been installed. Although it is the case that as soon as a new meter is
installed, its costs of installation are sunk, this does not matter
because the terms on which that meter is rented are still the terms that
were negotiated at the point when the costs of installing it were not yet
sunk.
75. Professor Paul
Grout on behalf of the Authority saw the matter differently. Professor
Grout is the Professor of Political Economy and Head of the Department of
Economics at Bristol University. He explained that a company which has
incurred customer specific sunk costs will be incentivised (in response to
a competitive threat) to reduce its prices to the level of its marginal
costs in order to ensure that it earns at least some on-going revenue.
Some money is, after all, better than none. Because competitors
and |
||
|
||
27 |
||
|
||
|
||
potential market entrants realise
this, they will be deterred from competing if they have not already sunk
their own costs. Thus, in a market such as this where marginal costs are
very low, market entry may be deterred because potential entrants see that
there is a risk of aggressive post-entry pricing by the incumbent seeking
to protect its revenue stream. Thus the existence of sunk costs and their
deterrent effect on new entrants may have the effect of increasing the
de facto bargaining power of the incumbent supplier.
76. We do not
consider that either of these models really explains what was likely to
happen in this market. This was not a “hold up” problem because British
Gas (the “holder up” in this scenario) had to have some arrangement
with National Grid to pay for the legacy meters. It could not simply stop
using the meters without also exiting the retail market. It did not have
the option of moving instantly to the CMOs because of the factors we have
considered earlier.
77. Conversely, the
CMOs were able to protect themselves from possible post-entry aggressive
pricing by concluding five year exclusive contracts for their particular
geographic region, with British Gas promising a minimum volume of work. As
we have mentioned earlier, Mr Avery’s evidence is that British Gas’s
policy was to sponsor market entry by the CMOs since it saw this as being
in its long term interests. Mr Paul King, giving evidence on behalf of
Meter Fit, describes how the Meter Fit contract contained a volume floor
of […][C] per cent such that should British Gas not be able to
provide sufficient volumes to meet Meter Fit’s requirements, Meter Fit
would be “kept whole” by British Gas making a volume shortfall payment to
Meter Fit. As Mr King put it: “[t]his floor limited Meter Fit’s exposure
to factors affecting provision and installation of volumes outside its
control”. When the CMOs got into difficulties in the start up period of
their contracts, British Gas renegotiated their terms with the result that
they were able to continue in business.
78. The existence of
sunk costs may have influenced the nature of the contracts between the
CMOs and British Gas. But the principal relevant features of those
contracts were set out in the ITT issued by British Gas before the
negotiations over the legacy meters started. We have not seen evidence to
suggest that the theoretical possibility that post-entry aggressive
pricing may have a deterrent effect on market entry actually played any
part in the negotiations of the Legacy MSAs. |
||
|
||
28 |
||
|
||
|
||
(d) The relevance of the P&M terms as a default
option for the gas suppliers
79. National Grid
argued that the regulated terms and conditions under the P&M contract
acted as a backstop or default position which was always available to the
gas suppliers when they were negotiating arrangements for the legacy
meters with National Grid. Since those terms and conditions, including the
rental, were set by the regulator in 2002, it can be assumed that they are
not abusive. National Grid was therefore unable to impose abusive terms
and conditions (whether exploitative or exclusionary) on the gas suppliers
because they could simply choose, as EdF did, to stick to the existing
P&M terms. This, Mr Turner submitted on behalf of National Grid,
“neutralised, drew the sting from the ability to extract disadvantageous
terms”.
80. We do not
consider that the existence of the price cap in this case negates the
existence of market power. We agree with the Authority that it is not
necessary in all cases of alleged abuse for the regulator to establish
that the putative dominant firm has the ability to maintain prices
appreciably above the competitive level – indeed National Grid accepted
that this was true. The Office of Fair Trading’s Guidelines on the
Assessment of Market Power (OFT 415, December 2004) state that market
power can exist even where there is economic regulation because even price
capping “may still allow for the undertaking profitably ... to engage in
exclusionary behaviour of various kinds” (paragraph 6.7). In the present
case, which does concern an alleged exclusionary rather than exploitative
abuse, the Authority certainly does not need to establish that National
Grid can raise prices above the competitive level. In addition, caution
must be exercised when considering whether a regulatory constraint can be
relied on as negating market power: see Hutchison 3G UK Limited v
Office of Communications [2005] CAT 39 and Hutchison 3G UK Limited
v Office of Communications [2008] CAT 11 which both concerned alleged
significant market power in the market for mobile call termination. In the
present case therefore, the P&M terms cannot be relied on to negate
any dominance that National Grid has in this market.
81. In the light of
this finding in relation to the relevance of the price cap, it is not
necessary for the Tribunal to resolve the various other issues explored by
a number of witnesses about whether the RAV used by the Authority in
setting the 2002 price cap is |
||
|
||
29 |
||
|
||
|
||
or is not a useful proxy for the
value of National Grid’s sunk costs (a point that cropped up in a number
of other contexts). Neither is it necessary to consider whether the 2002
price cap is a better indicator than the CMO prices of what is an
“efficient” price or a “competitive” price at any given time nor whether
gas suppliers were influenced by a concern that the price cap reflected in
the P&M terms might be lifted during the currency of the Legacy
MSA.
(e) Conclusions on dominance
82. We therefore
conclude that National Grid was dominant in the relevant market, as
defined by the Authority, at the time it negotiated and entered into the
MSA contracts.
VI. ABUSE
83. The classic
description of an abuse contrary to Article 82 EC is found in the
Hoffmann-La Roche case cited earlier (paragraph [51]):
“The concept of an abuse is an
objective concept relating to the behaviour of an undertaking in a
dominant position which is such as to influence the structure of a market
where, as a result of the very presence of the undertaking in question,
the degree of competition is weakened and which, through recourse to
methods different from those which condition normal competition in
products or services on the basis of the transactions of commercial
operators, has the effect of hindering the maintenance of the degree of
competition still existing in the market or the growth of that
competition” (paragraph 91).
84. The Authority
and the Interveners emphasised the case law of the ECJ referring to the
“special responsibility” of a dominant firm not to engage in conduct which
damages competition in the market which is already affected by its
dominance: see for example paragraph 57 of the ECJ’s judgment in
Michelin cited earlier (paragraph [47]).
85. In the Decision the Authority concluded
that:
(a) The MSAs impose significant
switching costs on gas suppliers who wish to replace a larger number of
meters than is allowed without penalty under the glidepath. The early
replacement charges in the Legacy MSAs are triggered by modest levels of
meter replacement; |
||
|
||
30 |
||
|
||
|
||
(b) The BLRs paid for meters
that have been removed take no account of avoidable costs and the
suppliers’ ability to leave the Take or Pay zone is constrained by future
non-discretionary replacement requirements (that is policy replacements
and CREs);
(c) The level of the
PRC in the first year of the Legacy MSA, £57 per meter for DCMs, is high
relative to the commercial benefits that gas suppliers would expect to
obtain by switching to a cheaper CMO and will reduce their incentive to
switch;
(d) The bundling of meter
maintenance by National Grid exacerbates the effect of the Legacy MSA
provisions because meters replaced on a maintenance visit are replaced by
National Grid rather than the CMO and count against the “free” allowance
under the glidepath. But in the absence of other restrictive factors of
the MSAs, the requirement to take maintenance from National Grid would not
of itself appreciably restrict competition and so is not a separate
abuse;
(e) The Legacy MSAs have
had an actual foreclosing effect on competing CMOs;
(f) The Legacy MSAs have
deprived customers of the benefits of competition in terms of lower prices
and reducing or removing the incentives on suppliers to improve technology
and introduce smart meters.
86. The Authority
therefore concluded that the MSAs have the actual and likely effect of
foreclosing competition within the relevant market. They are long term
contracts that limit significantly the commercial benefits that gas
suppliers and customers could obtain if there was more effective
competition in the market and suppliers could switch to CMOs without
incurring artificially high switching costs.
87. Critically, the
Authority recognised that the use of early replacement charges may be
necessary and proportionate to allow for the recovery of customer specific
sunk costs such as the cost of the installation of the meter. But the
Authority’s conclusion was that |
||
|
||
31 |
||
|
||
|
||
the Legacy MSAs were not a
necessary or proportionate means of recovering those costs. First, the
Authority found that the rentals payable in the Take or Pay zone do not
reflect a reasonable estimate of National Grid’s avoided costs (given that
the company is no longer required to maintain or provide other services in
relation to the meter). Secondly, the Authority found that a different
contract structure linking charges payable on early replacement to the age
of the meter would have protected National Grid’s position but would have
been cheaper for the gas suppliers. This latter point relates to extensive
expert evidence and argument over whether the age-related counterfactual
should have been “revenue neutral”: see paragraphs [135] onwards,
below.
(a) What is “normal competition” in this
market?
88. As we have
mentioned, the Authority accepted that in a market where long lived assets
are installed in customers’ premises and where those assets have minimal
re-use value if removed, it is legitimate for meter providers to protect
itself against the stranding of those sunk costs if the customer decides
to replace the asset with that of a competitor. In its Defence the
Authority said that it remains its case that in normal competition a meter
operator might adopt various methods to achieve this including upfront
payment, cancellation charges, or adjusting the rental
prices.
89. National Grid
argued that the Authority had to establish that the Legacy MSAs
constituted “recourse to methods different from those which condition
normal competition” before it could establish that they were abusive. In
this market, the Authority had accepted that it was “normal”, given the
nature of the assets, for operators to put some form of premature
replacement protection in place in their contracts. No deviation from
“normal competition” had been established by the Authority and hence there
was no abuse within the meaning of Hoffmann-La Roche.
90. We do not accept
that this is the correct way to interpret what the ECJ said in
Hoffmann-La Roche. “Normal competition” there means the parameters
which affect a customer’s choice in a situation where the customer is free
to choose from amongst the products which make up the relevant market. In
conditions of normal competition, a buyer will base his purchasing
decisions on his assessment of who offers the best price and the best
quality product or service. He might, on the basis of these criteria,
choose the dominant firm’s product and thereby maintain or increase the
dominant firm’s |
||
|
||
32 |
||
|
||
|
||
market share. That does not
involve an abuse because the dominant firm has won that business because
its product is the better overall offer from the customer’s point of view.
If the customer subsequently discovers that another company offers a
better, cheaper product he will switch his custom to the new supplier – he
may switch back again if the dominant undertaking then improves its
offer.
91. Any form of
contract which ties the buyer to continuing to trade with a particular
undertaking, even if a competitor appears on the market offering a better,
cheaper product or service, inhibits the competitive process to some
extent. There may be entirely proper justifications for such contracts and
they do not always have anti-competitive effects. But they are still
capable of being abusive if entered into by a dominant firm because that
firm has a special responsibility not to impede whatever competition takes
place on the market.
92. All
Hoffmann-La Roche indicates is that a dominant firm is free to
compete vigorously on price and quality and similar parameters. As DG
Competition put it in the 2005 Discussion paper on the application of
Article 82 of the Treaty to exclusionary abuses:
“the purpose of Article 82 is not
to protect competitors from dominant firms’ genuine competition based on
factors such as higher quality, novel products, opportune innovation or
otherwise better performance, but to ensure that these competitors are
also able to expand in or enter the market and compete therein on the
merits without facing competition conditions which are distorted or
impaired by the dominant firm”. (paragraph 54)
93. We therefore do
not accept that the Authority’s recognition that some form of premature
replacement charge would feature in this market under conditions of normal
competition rules out a finding that this contract is an abuse. The issue
in this case is not whether any payment protection arrangements
could be justified where a long-lived rented asset is installed without an
upfront transaction charge. It is accepted on all sides that such
arrangements are legitimate or normal. The question in this case is
whether the Legacy MSA goes too far in protecting National Grid from the
consequences of competition and whether the agreement’s foreclosing effect
is too severe to be justified by National Grid’s desire to protect the
revenue stream generated by its meters.
(b) The economic effect of the Legacy
MSAs |
||
|
||
33 |
||
|
||
|
||
94. There was some
debate, in particular between CML/Siemens and National Grid about whether
arguments about the advantages and disadvantages of the Legacy MSAs should
be considered in the context of assessing whether there was
anti-competitive foreclosure or in the context of considering whether any
such foreclosure was objectively justified. Both National Grid and the
Authority appeared content to deal with them under the former heading and
neither of them submitted that anything turned on this. We therefore
consider the points in the manner presented by the Appellant and
Respondent.
95. Before delving
into the detail of the parties’ arguments it is important to analyse the
nature of the Legacy MSAs and the effect they are likely to have on
competition. The European jurisprudence on Article 82 has for many years
stressed that an abuse can be committed where a dominant undertaking
engages in any behaviour which forces or encourages customers to buy a
certain proportion of their requirements from it. Thus in Hoffmann-La
Roche the Court of Justice stated that where a dominant undertaking
ties purchasers, even at their request, to obtain all or most of their
requirements from that undertaking, that will be an abuse. The same
applies if the dominant undertaking adopts a system of fidelity rebates
which have the same effect, again, even if the loyalty obligations are
imposed at the buyer’s request. The leading case of Michelin (cited
at paragraph [47] above) explains that the mischief of the loyalty rebate
scheme condemned in that case arose because the scheme was:
“calculated to prevent the
dealers from being able to select freely at any time in the light of the
market situation the most favourable offers made by the various
competitors and to change supplier without suffering any appreciable
economic disadvantage. It thus limits the dealers’ choice of supplier and
makes access to the market more difficult for competitors. Neither the
wish to sell more nor the wish to spread production more evenly can
justify such a restriction of the customer’s freedom of choice and
independence” (paragraph 85).
96. In Case C-95/04
P British Airways v Commission [2007] ECR I-2331 the ECJ considered
whether the bonus arrangements offered by British Airways could produce an
exclusionary effect “that is to say whether they are capable, first, of
making market entry very difficult or impossible for competitors of the
undertaking in a dominant position and, secondly, of making it more
difficult or impossible for its co-contractors to choose between various
sources of supply or commercial partners.” (paragraph 68). Having
concluded that the bonus arrangements were capable of having such an
effect, |
||
|
||
34 |
||
|
||
|
||
the Court said that one then
needs to examine whether there is an objective justification for the bonus
scheme - thereby acknowledging that even a scheme which does “produce an
exclusionary effect” may avoid being characterised as abusive in certain
circumstances (paragraph 69).
97. The Legacy MSA
operates in the same way as a contract which obliges the customer to take
a certain percentage of its requirements from the dominant undertaking.
Indeed, Mr Turner confirmed that National Grid fully accepted that the
Legacy MSAs discourage gas suppliers from replacing the legacy meters with
new meters rented from a CMO or under the N/R MSA at levels higher than
those allowed free of penalty (Transcript, Day 2 pp. 8 – 9). As he put it
in his opening submissions at the hearing, National Grid’s aim was “to
bargain to keep its installed meters in place while they functioned
perfectly well, [and] to try to get back as much of its sunk costs as it
can” (Transcript, Day 1, p.16). The Legacy MSAs therefore have the same
kind of economic effects as the ECJ described in the Michelin
case.
98. It is also
important to recognise that the Legacy MSAs are not a cost recovery
arrangement but a revenue protection arrangement. In other words, the
amount of the early replacement charge payable under the Legacy MSA is not
related to the difference between the initial cost of installing that
meter and the amount of rental that has already been paid for that meter.
Rather, because of the way that the PRCs are calculated, it relates to the
difference between the amount of rental that would have been paid if the
customer had continued to rent the number of meters set by the glidepath
and the amount of rental that will actually be paid given the number of
meters removed. In other words the payment that is “completed” is the
payment of future rentals, not the payment of past installation costs.
National Grid’s case is that, nonetheless, the contracts are legitimate
because the revenue guaranteed by the Legacy MSA falls far short of the
RAV which it regards as a good proxy for its unrecovered sunk costs
aggregated over the whole of the legacy meter installed base. The key
question for the Tribunal is whether the Authority was right to conclude
that the foreclosure effect arising from the Legacy MSA was too severe to
be justified by National Grid’s admittedly legitimate interest in ensuring
that it was able to recoup some of the costs that it had incurred in
installing the legacy meters. |
||
|
||
35 |
||
|
||
|
||
(c) A comparison of the PRC
with the annual rental for DCMs and PPMs
99. The Decision
measured the foreclosing effect of the Legacy MSAs in different ways. The
first was simply to compare the size of the PRC with the benefit that the
gas supplier would expect to obtain from switching to a cheaper CMO. The
PRC for a DCM was taken by the Authority to be £57 per meter in the first
year of the Legacy MSAs. This is high relative to the annual saving that a
gas supplier could expect to make on the rental payable for the meter if
it incurred that PRC and installed a CMO’s meter, given that annual
rentals for DCMs were about £11 in 2003. We agree that this comparison
supports the Authority’s conclusions on abuse because the cost incurred if
the gas supplier has to pay a PRC on a meter is so high that it is likely
to be more than the savings the gas supplier can expect from renting a
cheaper CMO meter.
100. So far as PPMs were
concerned, the Authority did not compare the first year’s PRC (which the
Authority took to be £37) with the annual rental for a PPM but with the
average cost of purchasing and installing a new or refurbished meter. The
Authority appears to have accepted that at the £37 level, it is not the
case that the PRC is likely to exceed the present value of the savings
available from swapping to a CMO meter. But the Authority referred to the
fact that National Grid had announced that it intended “re-balance” its
DCM and PPM charges resulting in an increase of the PRC for PPMs to £78
for the year 2005/06. National Grid argued that it was no longer in fact
intending to re-balance the PRCs and that it has not done so. We accept
that it would not be fair to rely on this proposal to “re-balance” when
making this comparison. We do not read the Decision therefore as drawing
any conclusion on foreclosure effect from a simple comparison of the first
year PPM PRC with either PPM rentals or cost of installation.
(d) The level of charges
incurred by an accelerated replacement programme
101. The second way in
which the Authority measured the costs that the Legacy MSA provisions
imposes on gas suppliers was to work out how much a gas supplier would
have to pay National Grid if it exceeded the glidepath. We had evidence on
this from one of the Authority’s expert witnesses, Mr Tim Keyworth, an
economic consultant specialising in the assessment of regulatory and
competition policy. He was instructed by the Authority during its
investigation and was involved in the analysis of abuse that was presented
in the Decision. |
||
|
||
36 |
||
|
||
|
||
102. Mr Keyworth’s
calculations are based on figures arrived at by aggregating the total
number of meters that are covered by all the Legacy MSAs entered into with
the gas suppliers who signed them. In total the population of DCMs covered
(or treated as covered) by Legacy MSAs as at 1 January 2004 was 17.56
million and the opening population of PPMs was 1.9 million. This means
that the penalty-free allowance under the glidepath across all gas
suppliers who had signed a Legacy MSA is about 980,000 DCMs per year
(1/18th of the opening total) or 81,000 per month. For PPMs the
penalty-free allowance under the glidepath was about 279,000 per year or
approximately 23,000 per month.
103. As regards DCMs, the
Decision posited a situation where a gas supplier decides to replace more
meters than are allowed for free under the glidepath. In the first
scenario the gas supplier decides, in each of the first three years of the
contract, to replace 50 per cent more DCMs than the glidepath allows. That
would result in it replacing about 1.5 million additional DCMs (about half
a million each year) and would take the gas supplier into the Take or Pay
zone but would not incur any PRCs. In the second scenario the gas supplier
decides to replace 65 per cent more DCMs than the glidepath allows for in
each of the first three years of the contract. This would result in
replacing about 2 million extra meters and would take the gas supplier
beyond the Take or Pay zone into the payment of PRCs.
104. When calculating the
total cost to the gas supplier under both these scenarios one must bear in
mind that a BLR may be payable in years beyond the year in which the meter
is actually removed. This will depend on whether the gas supplier returns
to a position at or above the glidepath commitment in subsequent years. In
order to calculate the likely cost of removing 50 or 65 per cent more
meters over the first three years, some assumptions have to be made about
levels of replacement after the three years to see how quickly the gas
supplier would return to the glidepath and cease to be liable to pay BLRs.
The assumption made by Mr Keyworth was that after the three years, the gas
supplier would only replace meters which were non-discretionary meters.
Further, it was assumed that there would be 850,000 of these
non-discretionary DCM replacements each year. Finally, the rental and PRC
levels used in the calculation were taken from the Legacy
MSA. |
||
|
||
37 |
||
|
||
|
||
105. Applying the Legacy
MSA terms to the two scenarios and making those assumptions about the
speed of return to the glidepath after the first three years’ excess
replacement, the Authority concluded that the total cost of replacing 50
per cent more DCMs would be £87 million. This makes the average charge for
each of the 1.5 million meters replaced about £60. Under the second
scenario the total cost would be £124 million amounting to about £65 per
DCM.
106. Mr Keyworth also
calculated the marginal cost of replacing a meter, making the same
assumptions about the number of non-discretionary DCM replacements after
the first year in which the glidepath is exceeded. He calculated that the
marginal cost of replacing an additional meter in year 1, after 520,000
additional meters in excess of the glidepath allowance had been replaced
in that year, would be about £50 per meter (taking the annual rental to be
£10).
107. Mr Keyworth concluded
that the average and marginal cost calculations provided “compelling
evidence” that the costs of replacing more meters than allowed by the
Legacy MSA glidepath could, at the start of the contract, have been
expected to give rise to early replacement charges that increased very
rapidly. These charges were very high relative to the overall cost of DCM
provision (about £11 per year) and were incurred in response to only
relatively modest additional levels of replacement.
108. The same exercise was
carried out for PPMs although this was limited to the first scenario – the
replacement of an additional 50 per cent more than the free PPM
replacement provided for by the glidepath in the first three years. On the
basis of the PRC levels set in the Legacy MSA the Authority calculated
that the cost in the first scenario amounted to over £19 million. This was
equivalent to an average cost per additional PPM replacement of around
£46. In Annex 4 to the Decision where the Authority set out its
calculation for PPMs it acknowledged that PPM replacement is not likely to
result in a long period in the Take or Pay zone because the gas supplier’s
ability to return to the glidepath is not impeded by having to undertake
policy replacements. The Authority concluded from this in paragraph 4.80
of the Decision that the impact of the provisions on the costs to a
supplier of replacing more PPMs than scheduled by the glidepath “is likely
to be less pronounced than is the case for the DCMs”. National Grid
invited us to hold that there was no finding of foreclosure
in |
||
|
||
38 |
||
|
||
|
||
relation to PPMs. We disagree.
The finding was that there was still foreclosure but that it was not as
severe than was the case for DCMs. In other places where the Authority
concludes that there is no finding of abuse (for example in relation to a
separate abuse of maintenance bundling) the Decision states this
expressly. We do not read paragraph 4.80, or the Decision as a whole, as
deciding that foreclosure was limited to DCMs.
109. National Grid
criticised a number of aspects of this calculation of average and marginal
costs of exceeding the glidepath. First they attacked the realism of the
50 per cent and 65 per cent excess scenarios. They referred to quotations
from the internal contemporaneous documents of the gas suppliers which
indicated that they thought that the Legacy MSA glidepath allowed them to
carry out a replacement programme as rapidly as they had intended. It was
unrealistic, National Grid argued, to posit that in the absence of the
Legacy MSAs the gas suppliers would have wanted to replace substantially
more meters than they were allowed to do, penalty free, under the
glidepath.
110. There was some debate
before us as to where the 50 per cent and 65 per cent figures had come
from. The Decision states (paragraph 4.73) that the 50 and 65 per cent
scenarios are reasonable in relation to the actual levels of replacement
that British Gas had contracted for ahead of signing the Legacy MSAs.
National Grid argued that this was not true and that these levels of
replacement were based on inaccurate estimates made by the Authority. In
its supplementary submissions, the Authority accepted that some of these
criticisms were justified. Using more recent data and the more detailed
approach that National Grid had advocated, the Authority recalculated its
“best view” of the initial CMO volumes as a percentage of the glidepath
allowance in 2004 to 2007 and came to figures which were broadly the same
as those included in paragraph 4.73 of the Decision.
111. National Grid also
argue that, if the scenarios were based on the figures in British Gas’
ITT, this was not a fair comparison because those figures were proposed by
British Gas before negotiations on the Legacy MSAs started. Those figures
were therefore what British Gas thought it would replace if it remained on
the P&M terms with no payment completion terms. They were not a
fair indication of the level of replacement that British Gas would want to
undertake if it were subject to lawful payment
completion |
||
|
||
39 |
||
|
||
|
||
terms different from those
alleged to be abusive. The proper comparison was as between the
replacement levels under the Legacy MSA and the replacement levels under a
hypothesised alternative lawful payment completion
arrangement.
112. Our conclusion on this
point is as follows. It is essential when assessing the effect of the
early replacement charges in the Legacy MSA to work out how expensive it
is for a gas supplier to replace more than the glidepath allowance.
Because of the existence of the BLRs this exercise has to be more
complicated than simply comparing the PRC with the cost of the meter
(though the Authority also relied on that comparison in relation to DCMs).
That is why the Authority used the 50 per cent scenario (which only incurs
BLRs) as well as the 65 per cent scenario (which incurs both BLRs and
PRCs).
113. We do not accept the
argument that the Authority ought to have worked out what would be the
likely increase in replacement volumes comparing the Legacy MSAs with a
lawful payment completion arrangement. That was not the purpose of this
exercise. The cost comparison between the Legacy MSA and an alternative
payment completion arrangement was carried out using the age-related
counterfactual and is discussed below. We do not consider that the 50 per
cent and 65 per cent scenarios are unrealistic or that the Authority
should have assumed that the gas suppliers would not have replaced more
than the glidepath amounts if they had been free to do so. National Grid
was certainly not prepared to take the risk that gas suppliers would
replace only a very limited numbers of meters. The main driver behind the
design of the Legacy MSAs was National Grid’s anxiety that British Gas
might well replace more meters than the glidepath – even possibly
replacing all their legacy stock over five years.
114. National Grid referred
to the fact that in the years leading up to the introduction of the MSAs,
National Grid replaced around 900,000 DCMs a year on average and about
200,000 PPMs. National Grid described this rate of replacement as the
“organic natural pattern of replacement”, arguing that it was unlikely
that gas suppliers would want to replace so many more meters in the first
years of the contract (Transcript, Day 1). Any faster replacement would be
“the inefficient and wasteful replacement of good working meters” as Dr
Williams put it (paragraph 116 of his second witness statement). But in
our judgment it is not right to assume that gas suppliers would or should
have remained |
||
|
||
40 |
||
|
||
|
||
content to limit replacement to
those levels once competitors entered the market offering substantially
cheaper rentals. Neither is it right to characterise such replacement as
wasteful or inefficient. That would be to assume that the introduction of
competition would or should have no effect on the scale of National Grid’s
business. In our judgment there was nothing improper or unrealistic about
the 50 per cent and 65 per cent scenarios that the Authority used in this
part of its analysis.
115. National Grid’s second
complaint was the reasonableness of the assumption that there would be
850,000 DCM non-discretionary replacement meters each year. This
assumption increases the cost incurred by the excess replacement in the
first three years because it delays the point at which the gas supplier
returns to the glidepath and ceases to be liable to pay BLRs. Mr Keyworth
explained where the assumption came from. He analysed the volume of
non-discretionary replacements (that is, policy replacements maintenance
replacements and functionality changes) in fact undertaken for DCMs in the
first three years of the Legacy MSA and found that it was about 850,000
per year. For PPMs there were generally no policy replacements so the
number of non-discretionary replacements was much smaller (limited to CREs
and maintenance replacement). The average cost calculations for PPMs
therefore did not take into account non-discretionary PPM
replacements.
116. Mr Keyworth’s
assumptions appear to us to be entirely justified and indeed favour
National Grid in assuming that the only replacements that the gas supplier
makes after the first three years are the 850,000 non-discretionary DCM
replacements. We reject National Grid’s argument that the Authority should
have taken into account that the company had changed its policy
replacement criteria as from April 2008 resulting in a steep fall in the
number of policy replacements and hence an increase in the number of free
discretionary replacements available to the gas suppliers. The important
question is what cost calculations would gas suppliers have made when
planning their replacement strategy in the first three years. At that time
there was nothing to suggest that the number of policy replacements was
going to fall.
117. National Grid’s third
criticism was that it was wrong to focus on the first three years in
assessing the foreclosure effect of the Legacy MSAs. The Authority
recognised that (see the Decision paragraph 4.166) it could be argued that
the Legacy MSAs envisaged |
||
|
||
41 |
||
|
||
|
||
that all DCMs legacy stock could
be replaced by CMOs over an 18 year period without incurring charges and
the age-related counterfactual envisaged that all stock could be replaced
without charge over a 20 year period. National Grid also argued that the
CMOs had, in fact, been able to establish viable businesses in the first
three years of the Legacy MSA. But the Authority rejected the idea that
this meant that the Legacy MSA was no more foreclosing than the
age-related counterfactual. We agree with the Authority that it does
matter that the Legacy MSA pushes more replacement into later years than
would be the case under the age-related counterfactual because by that
time competition may have been stifled through earlier market foreclosure.
An agreement which restricts the introduction and expansion of competition
immediately after the lifting of a statutory monopoly has a serious
foreclosing effect even if competition might be less restricted in future
years.
118. In our judgment, the
exercise carried out by the Authority to calculate the marginal and
average cost of exceeding the glidepath was a legitimate one and was
carried out fairly. We find that it supports the conclusions that the
Authority drew from it.
(e) The use of counterfactuals
119. The third method
relied on by the Authority to assess the effect of the Legacy MSA
provisions was to compare the costs of carrying out a given replacement
programme under the Legacy MSA with the cost of carrying out the same
programme under one or more counterfactuals. The main counterfactual used
in the Decision was an age-related one; that is a contract in which the
size of the early replacement charge was smaller for older meters than for
younger. National Grid accepted the validity of using counterfactuals to
assess the foreclosure effect of the Legacy MSA. Indeed it was their case
that a relevant counterfactual was an essential element in establishing
the existence of an abuse under Article 82. But they objected to the
counterfactual used by the Authority.
(i) The age-related counterfactual in the
Decision
120. The Authority noted in
the Decision that the provisions of the Legacy MSA differ markedly from
the provisions regarding early replacement of meters found in the CMO
contracts and in National Grid’s own N/R MSAs. Importantly, the Decision
says, |
||
|
||
42 |
||
|
||
|
||
under the CMO contracts and the
N/R MSAs, the early replacement charges payable will depend on the
characteristics of each specific meter that is replaced, notably the age
of that meter. Under the CMO contracts and under the N/R MSA, the level of
early replacement charges a gas supplier pays depends on the period of
time that has elapsed since the relevant meter was installed, with, under
each contract, the early replacement charge that is payable declining to
zero over 20 years for DCMs and over 10 years for PPMs.
121. The Decision then said this about the use of the
counterfactual:
“As they are the contractual form
used by CMOs, UMS and [National Grid] in the N/R MSAs, age-related PRC
arrangements are a useful counterfactual against which to compare the
effects of the Legacy MSAs on the development of competition. The
Authority notes that contracts containing age-related PRCs are not the
only alternative to the Legacy MSAs. It remains open to [National Grid] to
seek to recover their customer specific sunk costs without
long term contracts through, for example, competitive rental charges so
that suppliers do not have an incentive to switch to CMOs and replace
[National Grid] meters before the end of their useful life. … [National
Grid’s] dominance in this market makes it difficult to identify an example
of “normal” competition and the Authority does not consider that the CMO
contracts necessarily represent the benchmark for normal competition in
the domestic gas metering market.” (paragraph 4.89, emphasis in original,
footnote references omitted).
122. The counterfactual
used in the Decision compared the effect of an age-related scheme with the
Legacy MSA as regards the replacement of DCMs. It did not cover PPMs. The
Authority first compared the treatment of non-discretionary
replacements of DCM meters less than 20 years old under both the
Legacy MSAs and the CMO contracts. They found that under the Legacy MSAs,
the supplier would be able to make all non-discretionary replacements
without incurring charges because the glidepath allowance was high enough
to cover this. Under the CMO agreements, policy replacements and other
replacements of faulty meters were also free from penalty, regardless of
the age of the meter. But under the CMO contracts and the N/R MSAs a
transaction charge is payable for functionality exchanges. Under the CMO
contracts this charge is generally fixed for the initial period of the
contract (5 to 7 years) and then declines on an age-related scale. Under
the N/R MSA it is a fixed amount irrespective of the age of the meter. The
Decision records that the Authority calculated that if gas suppliers had
had to pay age-related PRCs for CREs, the total PRC payment over 3 years
would be £21.1 million. National Grid’s calculation of the same sum came
to £37 million. |
||
|
||
43 |
||
|
||
|
||
123. Turning to a
comparison of the costs of discretionary replacement of DCMs under
the age-related approach, the Decision sets out as at 2004, how many
legacy DCM meters fell into one year age bands showing that, for example,
821,000 legacy DCMs were more than 20 years old, 424,000 were 19 – 20
years old, 493,000 were 18 – 19 years old etc. They also set out the
age-related PRC which would have been payable in 2004 for any meter
removed in each age band. These age-related PRCs were derived from
National Grid’s calculations of the averaged PRC level for 2004 with some
adjustment to take account of a higher level of avoidable costs than
National Grid had included. The same information about the age profile of
the DCM legacy stock was set out in a histogram as Figure 1 in the
Decision. This showed that the numbers of meters which would reach the age
of 20 or more years during the first three years of the contract was not
particularly high compared with the numbers of meters in the other age
bands.
124. The Authority then
went back to consider the first scenario it had posited when working out
the cost of exceeding the glidepath, namely a gas supplier who replaces 50
per cent more meters than is allowed on the glidepath. This scenario is
equivalent to the gas supplier replacing about 4.4 million meters over
three years (that is three years of glidepath allowance of 980,000 meters
plus three years of an additional 500,000 meters per year). About 2
million of this 4.4 million would be accounted for by non-discretionary
exchanges4 leaving 2.4 million discretionary replacements over
the three years, or 0.8 million DCMs per year. The Authority concluded
that the age structure of the DCM meter population is such that even if
suppliers decided to replace all the 2.4 million meters in the first
year rather than over three years, the highest early replacement
charge that they would incur for any meter would be about £26 and the
charges averaged over all the meters replaced would be about £13 for each
additional DCM. This compares with the average charge of £60 under the 50
per cent scenario applying the Legacy MSA provisions as described
earlier.
125. Mr Keyworth
acknowledged that no account was taken of access and density issues in
this comparison, that is to say, as to whether it would be feasible for a
gas supplier actually to expect his meter operator to take out meters
strictly in order of their age |
||
|
||
4 This figure was
arrived at taking the earlier assumption of 850,000 non discretionary
replacements each year and adjusting it to remove those DCMs which could
have been expected (absent replacement) to be less than 20 years old at
the end of the third year of the Legacy MSAs. |
||
|
||
44 |
||
|
||
|
||
profile in order to take
advantage of the age-related PRC structure. The calculation assumed that
the gas suppliers would be able to replace about 80 per cent of all the 16
to 17 years and older meters if they were targeted. If this were not
possible, higher PRCs would have to be incurred on some replacements of
younger meters. This is potentially significant because, according to
National Grid, the older meters are evenly spread throughout the country
rather than clustered in particular locations. This appears to be borne
out by the experience of Meter Fit when it entered the market. Meter Fit’s
contract required it to focus on replacing meters that were over 20 years
old but Meter Fit found that there was insufficient density of such meters
to enable it to carry out its business efficiently. The age constraint had
gradually to be relaxed to allow them to replace 12 year old meters in
order for their business to remain viable.
126. However, Mr Keyworth
concludes that even if the gas suppliers were unable to target all the
oldest meters, the average cost of the additional replacements would not
be a great deal higher than the £13 figure. In other words, the gap
between the average cost under the age-related counterfactual and the
Legacy MSA is so great that even if quite a few younger meters had to be
replaced in order to give an adequate density of operations to the CMO,
the age-related counterfactual would still be significantly cheaper for
the gas supplier than the Legacy MSA.
127. Mr Keyworth reiterates
that the exercise the Authority carried out favours the Legacy MSAs
because it calculates the cost to the gas supplier under the age related
counterfactual of replacing all the 2.4 million additional discretionary
meters in the first year not spread over three years as was done in
calculating the average cost under the Legacy MSA. The counterfactual also
included 660,000 non-discretionary replacements of meters less than 20
years old, that is one year’s worth of non-discretionary replacements. In
total, therefore, the exercise assessed the costs of making over 3 million
replacements that is, more than three times the level of replacements
allowed without charge under the glidepath.
(ii) National Grid’s challenges to the age-related
counterfactual
128. National Grid
contended that the age-related counterfactual used in the Decision was
invalid and showed nothing useful about the reasonableness of the early
replacement charges in the Legacy MSA. |
||
|
||
45 |
||
|
||
|
||
The parties would not have been able or willing to conclude
such a contract in 2004
129. National Grid’s first
point was that the counterfactual was unrealistic because it would not
have been feasible for the parties to enter into such a contract at the
time the Legacy MSA was negotiated. The information about the age profile
of the legacy meter stock that the Authority used to compare costs was
produced, we were told, after a huge amount of internal work by National
Grid involving drawing together and analysing many hundreds of difference
data sets. At the time that the Legacy MSAs were negotiated there was a
very large number of meters installed where the company had no reliable
information about date of installation. National Grid also referred us to
contemporaneous documents which make clear that neither National Grid nor
British Gas thought it was either feasible or desirable to have an early
replacement scheme which relied on the characteristics of specific meters.
For various practical reasons, both parties preferred a scheme which
involved a flat rate charge because this minimised transaction costs and
maximised the flexibility that the gas suppliers had in deciding which of
their portfolio of meters they replaced at any given time.
130. In our judgment this
criticism is based on a misapprehension of the function of the
counterfactual in the economic analysis required in a case such as this.
The Authority does not have to establish that the parties would have
preferred to enter into a contract along the lines posited in the
age-related counterfactual. The age-related counterfactual is based on
features of other contracts operating in the market, namely the CMO
contracts and National Grid’s N/R MSA. The question the Authority is
asking is “what would have been the position if the parties had operated a
system in relation to the legacy meters similar to the system that now
operates in relation to new meters?”. We regard that as a useful avenue of
inquiry even if there would have been logistical or financial difficulties
in setting up such a system. As Ms Carss-Frisk QC argued in her closing
submissions, the Authority is not setting out to prove that the
counterfactual is what would or should have happened or that it would have
been preferred by the parties. It is simply asking what would be the
result if they had.
No correlation between age and condition of the
meter
131. National Grid’s second
attack on the age-related counterfactual was that it was based on an
assumption that older meters are less valuable than new meters and that a
lower PRC |
||
|
||
46 |
||
|
||
|
||
should therefore be payable for
the replacement of an old meter than for a new meter. National Grid
submitted that this was not the case and that in fact the correlation
between age and condition was very weak. On this point, Mr Mark Way gave
evidence for National Grid. Mr Way is currently employed by National Grid
Metering Limited as Asset and Planning Manager. He is responsible
primarily for operational metering and asset management activities. His
witness statement was not quite directed at the right point because he did
not distinguish between meters which were the subject of a policy
replacement requirement and those which were not. Since policy replacement
meters are not part of the age-related PRC scheme under the counterfactual
(because all policy meters can be replaced without incurring an early
replacement charge) the relevant question was whether there was a
correlation between the age and accuracy of a meter, leaving aside the
policy meter population. But in his oral evidence Mr Way still did not
agree that, leaving aside policy replacement meters, older meters are
necessarily or even generally less valuable or more prone to failure than
younger meters. National Grid also referred to the fact that since 1997,
the industry regulator had refused to include a capital expenditure
allowance in the price control based on National Grid replacing all 20
year old meters on the grounds that a policy of replacing meters just
because they had crossed that age threshold would be incompatible with
efficient capital expenditure in the interests of consumers.
132. We accept that there is no
perfect correlation between the age of a meter and its accuracy. As with
any mechanical item, whether it is a car, a washing machine or a gas
meter, different models will have a reputation for being more or less
reliable throughout their life. But that does not detract from the fact
that, overall, older mechanical items are more prone to failure than new
and therefore are regarded as less valuable. In his statement Mr Way
included a graph showing the accuracy performance against installation
date of the brand of meter which currently accounts for some 60 per cent
of National Grid’s domestic meter population. He said that this showed
that the meters continue to perform well, with very few meters anywhere
near the criteria for designating them for policy replacement over a 20
year life. But we accept the Authority’s reading of this graph that it
shows in fact that there is a correlation between age and reliability
albeit that the graph does not demonstrate a linear relationship. The
graph shows that if one looks at the line indicating reliability of meters
installed between 1981 and 1985 and separately at the line relating to
meters installed between |
||
|
||
47 |
||
|
||
|
||
1996 and 2006, neither line shows
reductions in reliability with age. However the older meters show lower
reliability than the more recently installed meters. It may be that after
ten years in service something happens to the meter which makes it less
reliable. Or the post-1996 versions of this brand of meter may have
incorporated some technical improvement which means that they will
maintain that level of accuracy for the rest of their lives. For our
purposes it does not matter – the graph shows that for the model of meter
which makes up 60 per cent of National Grid’s stock there is a material
difference in accuracy between the older and newer meters. No graph was
produced by National Grid to show a different profile for any other brand
of meter.
133. We also accept,
as Mr Way stressed, that even in the later years, this brand of meter is
still performing well within the accuracy tolerance designed to identify
the policy meters. But that is not the point we are discussing here. We
agree with the evidence of Professor Grout that the fact that an older
meter is not so inaccurate as to merit designation by National Grid as a
policy replacement, does not mean that from the gas supplier’s point of
view the older, less accurate meter is just as good as a newer, more
accurate meter. The question we are addressing here is, when a gas
supplier is deciding which meters to replace out of the pool of meters
which are not policy replacement meters, does it make sense to replace the
oldest meters first? In our judgment on the evidence before us, the answer
to that question is clearly “yes”.
134. In any event, we are
not convinced that National Grid is right to say that there is an
assumption underlying the age-related counterfactual that older meters are
less accurate than newer. The counterfactual is based on the provisions of
the CMO contracts and National Grid’s N/R MSA. Those contracts, for
whatever reason, apply early replacement charges that decrease with the
age of the meter. As we discuss below, it is legitimate for the Authority
therefore to use an age-related counterfactual to assess the Legacy MSAs
because that is how meter operators in a competitive scenario have chosen
to structure their arrangements.
The counterfactual is not revenue or value
neutral
135. National Grid’s third
challenge to the usefulness of the age-related counterfactual was that it
was neither revenue neutral nor benefit neutral, that is to say, although
the counterfactual used the National Grid rental rates, it is not set up
so that National Grid |
||
|
||
48 |
||
|
||
|
||
receives the same money under the
age-related counterfactual as it is guaranteed to receive under the Legacy
MSAs. Further, the gas suppliers do not receive the same benefits under
the age-related counterfactual as they do under the Legacy MSA. This
arises, in part at least, because under the age-related counterfactual the
gas supplier is allowed many more penalty-free replacements because of the
age profile of the legacy meter stock and the number of policy meters
which are replaced during those three years. National Grid calculated that
under the age-related counterfactual devised by the Authority there were
1.18 million penalty-free replacements over the first three years whereas
under the Legacy MSA there were only about 380,000 discretionary
replacements (that is 980,000 glidepath allowance less 850,000 policy
replacements per year in each of three years).
136. Although the Authority
initially asserted in the Decision that the age-related counterfactual was
revenue neutral, they acknowledged during the course of the hearing, that
this was not so: the age-related counterfactual used in the Decision in
fact generates a lower revenue for National Grid. National Grid argued
that this lack of revenue neutrality fatally undermined the validity of
the counterfactual. They argued that the results of the counterfactual are
highly sensitive to the numbers that are included in the scenario. If the
counterfactual is set up to give the gas supplier more free replacements
and lower charges, then of course the end result will be that the
counterfactual is cheaper for the gas supplier. They also argued that the
lack of revenue neutrality undermines the purpose of the counterfactual
which is to identify whether the structure of the Legacy MSA
provisions was anti-competitive, not whether the amount of revenue earned
by National Grid was reasonable. As National Grid submitted, the Authority
had been prepared to assume that the level of the charges imposed in the
Legacy MSA was not unduly onerous in the sense of being far greater than
the actual customer-specific sunk costs. Given therefore that the abuse
derived from the structure of the Legacy MSA provisions rather than
from the amount of revenue they would generate, it is essential
that the counterfactual also focus on the structure of the charges and not
on their amount. National Grid argued that it is “a matter of basic
scientific method” (Transcript, Day 9) to set up a ‘control’ which
isolates the effect of the elements in the Legacy MSA to which objection
is taken. National Grid put forward the evidence of a further expert
witness, Mr David Matthew, who made a detailed critique of what Mr
Keyworth had done. Mr Matthew devised an age-related |
||
|
||
49 |
||
|
||
|
||
counterfactual which was revenue
neutral. This showed, he argued, that gas suppliers would be no worse off
under that counterfactual than they were under the Legacy
MSA.
137. In our judgment this
criticism of the age-related counterfactual and Mr Matthew’s evidence is
misguided. There would be much force in National Grid’s argument if the
Authority had simply picked the various inputs in the counterfactual at
random. If it had simply used lower PRCs or higher numbers of free
replacements in an arbitrary manner, the fact that they resulted in lower
overall costs would not have told us anything useful. But the point about
the counterfactual was, as Mr Keyworth repeatedly stressed, that it was
“rooted in market reality” (Transcript, Day 9). The length of the contract
(20 years), the provisions about free replacements and the level of the
age-related PRCs were not simply chosen at random by the Authority. Mr
Keyworth acknowledged that the metering business involves customer
specific sunk costs and that this may provide a justification for the use
of early replacement charging arrangements. In an important paragraph in
his statement he says this:
“The Decision… takes account of
the fact that commitments to future rental payments (and associated
provisions for early replacement charges) are a feature that is observed
in other contracts in the relevant market (specifically the CMO contracts
and the N/R MSA). These contracts were examined in order to identify the
specific means by which – through rental payment commitments and
associated early replacement charging provisions – these contracts sought
to address the fact that meter provision gives rise to customer specific
sunk costs. The age-related counterfactual in the Decision was defined
so as to include early replacement charging provisions that were in a
form that these contracts indicated to be sufficient to address this fact
(with both the CMOs and [National Grid] having undertaken replacement
activity on the basis of early replacement charging provisions that are
similar in form to those examined in the age-related counterfactual).”
(paragraph 79, emphasis added).
138. The counterfactual is
therefore looking at what bargains have in fact been struck in the sector
of the market where meter operators are subject to competitive pressures.
Those meter operators are incurring the same kinds of customer
specific sunk costs as National Grid has incurred, albeit not necessarily
the same level of costs. It is relevant to ask to what extent those
meter operators have been able in their negotiations with British Gas to
protect their revenue streams from the risk of early meter replacement. To
put it another way, it is relevant to look at what kinds of arrangements
other meter operators regard as giving them adequate revenue assurance
such that they are prepared to conclude contracts, enter the market and
carry out meter replacement on the basis of those arrangements. Having
identified those terms, the counterfactual then
assesses |
||
|
||
50 |
||
|
||
|
||
what would have happened if those
kinds of provisions had been applied to the legacy meter stock – would gas
suppliers have been better off? That is a perfectly valid question to ask
and constructing the counterfactual as Mr Keyworth has done is a good way
to find out the answer to that question. It does not matter whether the
age-related counterfactual is value or revenue neutral. What matters is
that it is based on the contractual terms under which competing CMOs have
been prepared to enter the market. If the counterfactual shows that gas
suppliers would be better off under the counterfactual than they
are under the Legacy MSA, that points to a conclusion that the Legacy MSAs
go further than they should or need to go in order to protect National
Grid’s revenue in a competitive market.
139. We agree with Mr
Keyworth that it would only be necessary to ensure that the age-related
counterfactual was revenue neutral compared with the Legacy MSA if the
Authority accepted that National Grid was entitled to receive from
the gas suppliers the level of revenue that is generated for it by the
Legacy MSAs (that is some part of the RAV). The Authority is very far from
accepting that and they are clearly right to reject any such suggestion.
National Grid argues that because the Authority (a) accepts that payment
completion arrangements are a legitimate way in which a meter operator can
recoup its sunk costs and (b) assumes that the level of the PRCs is not
unduly onerous (in the sense of being far greater than actual
customer-specific sunk costs), that means that the Authority must be
attacking only the structure of the Legacy MSA charges and not their
amount. National Grid moves from this assumption to an assertion that the
counterfactual must be revenue neutral in order to be valuable. We
disagree with that line of argument. Even though the Authority has not
treated this as an excessive pricing case, it is still entitled to find
that the level and structure of the early replacement charges in the
Legacy MSA create a disproportionate disincentive for gas suppliers to
move their business to new entrants. The Authority was therefore entitled
to find (see paragraph [87] above) that the charges provide a level of
protection for the dominant firm which is far greater than the new
entrants were able to achieve in their negotiations with the same
customer.
140. As a further point
National Grid argued that in basing the age-related counterfactual on the
CMOs’ contracts the Authority has “cherry picked” those elements in the
contracts which favour its case. Mr Matthew, on behalf of National Grid,
illustrated how |
||
|
||
51 |
||
|
||
|
||
sensitive the outcome of the
counterfactual is to a change in the input parameters. He calculated what
would be the cost of the replacement programme posited in the Decision if
the age-related counterfactual had been based on 25 years and found that
the average costs of the 50 per cent accelerated replacement programme
would rise (on his calculations) from less than £18 to around £40 to £53.
Since many meters last well in excess of 20 years there is, National Grid
argues, no reason why the parties could not have used a notional life for
meters in the contract of greater than 20 years.
141. Again, we agree with
the Authority that although there may be “no reason” why the 20 year cut
off is used, the important fact for our purposes is that 20 years is
the cut off used in the CMO and National Grid’s N/R MSA agreements. As
Mr Keyworth put it, 20 years was a clearly understood benchmark as being
sufficient protection to underpin new investment by the market entrants.
National Grid pointed to the UMS contract which provides, in certain
circumstances, for a 25 year rather than a 20 year scale of PRCs for DCMs.
But that applies only in very limited circumstances, […][C]. This
does not, in our judgment, detract from the fact that the industry
“standard” outside the Legacy MSA is to treat DCMs as likely to be in
place for 20 years.
142. National Grid
complained that the counterfactual also ignores the fact that the CMOs
have a five year exclusivity period at the start of their contracts and
(though there was some dispute about this) that after that exclusivity has
expired, British Gas can only replace the CMOs’ meters in limited
circumstances. But we consider that the Authority was right to conclude
that it would not make sense to replicate all the terms of the CMOs’
contracts into the counterfactual. Those contracts are entered into by
firms which are not only non-dominant but also new entrants into the
market. As Mr Keyworth pointed out, at least one of the contracts – the
UMS contract – does allow replacement in the secondary period by another
party of any of the CMO’s installed meters and in all three of the
contracts, the PRC payable where the meter can be taken out in that
period is clearly based on an age-related structure. We do not agree with
National Grid that there was unfair “cherry picking” of those aspects of
the CMOs’ contracts which served the Authority’s purpose in devising the
counterfactual.
143. We therefore reject
National Grid’s criticisms of the age-related counterfactual. In our
judgment this was a useful exercise properly carried out by the Authority.
It supports |
||
|
||
52 |
||
|
||
|
||
the Authority’s conclusions that
an age-related approach would have provided CMOs with significantly
greater opportunities to engage in meter replacement programmes, whilst
gas suppliers would face early replacement charges that would be
substantially lower than those likely to be payable under the Legacy MSAs.
This in turn supports the Authority’s conclusion that the Legacy MSAs went
too far in protecting National Grid’s revenue stream and were therefore
not justified.
144. As to the complaint
that the age-related counterfactual is not “value neutral”, National Grid
focused on the fact that under the CMO contracts, gas suppliers had to pay
a transaction charge for CREs whereas the glidepath allowance under the
Legacy MSA was designed to be high enough to allow all expected CREs to be
undertaken without incurring early replacement charges. This point was,
however, dealt with in paragraphs 4.94 and 4.95 of the Decision. The
Authority calculates the amount that gas suppliers would have to pay CMOs
for CREs over the first 3 years of the contract as £13.4 million for DCMs
and sets out the way it has arrived at these figures in Annex 5. The
Authority concluded that this did not affect the use of the age-related
counterfactual because it was likely that the imposition of this
transaction cost would be offset by a reduction in the overall rentals.
They noted that there was evidence that this had in fact happened in the
negotiations between CML and British Gas. We agree with the Authority’s
submissions on this issue.
(iii) The no-PRC counterfactual
145. The Authority also
relied in the alternative on a counterfactual which included no PRCs but
simply assumed either that National Grid maintained the P&M terms with
higher rentals and no early replacement charges or that it had sought to
retain customers by simply competing on price without any early
replacement charges. The Authority argued that this counterfactual had
been prefigured in the Decision and was a proper response to National
Grid’s assertion that gas suppliers were at all times free to decline to
enter into the Legacy MSA and remain on the P&M terms instead. Since
the Tribunal has rejected National Grid’s criticisms of the calculation of
the cost of exceeding the glidepath and of the age-related counterfactual,
it is not necessary for us to resolve the issues surrounding the no-PRC
counterfactual. |
||
|
||
53 |
||
|
||
|
||
(iv) National Grid’s counterfactual – the same incentives
as a sale
146. National Grid argued
that the correct counterfactual was the sale of the meter by the meter
operator to the gas supplier. A sale arrangement was quite clearly not
foreclosing and hence not abusive. A sale sets up economically efficient
incentives for gas suppliers to decide what meter replacement programme to
undertake. The Legacy MSA, National Grid argued, replicated these
incentives. Hence it could not be regarded as anti-competitively
foreclosing.
147. To make the point that
the Legacy MSA contract reproduced the replacement incentives of ownership
it was assumed that a meter has a physical life of 20 years whether owned
or rented. The discount rate was assumed to be zero. Whoever owns the
meter has incurred costs in buying and installing the meter at time zero
and those costs are sunk and not recoverable.
148. In a scenario where
meters are sold rather than rented the position is as follows. In year τ
the owner of a meter may consider replacing the existing meter with a new
model which he considers offers a better service. The annual value of that
improvement can be expressed as D. The new meter is assumed, in National
Grid’s example, to have a life of (20 – τ) years. This means that
installing the new meter brings a net present value of benefits to the gas
supplier who is buying the meter equal to D(20 – τ). To install the new
meter will cost the gas supplier P(τ) and thus the incentive for a gas
supplier to replace the meter in year τ can be expressed as D(20 – τ) –
P(τ).
149. In a scenario where
the meters are rented, the rental contract hypothesised by National Grid
provides for an annual rental (“r”) per year for 20 years starting from
time zero. If the contract is terminated before the end of year 20 a
penalty equal to the remaining rental must be paid. Thus if the contract
is terminated in year τ a penalty of r(20 – τ) is due. Under the
hypothesised rental contract, in year τ the gas supplier would upon
replacement also benefit to the extent of D(20 – τ) at an acquisition cost
(in rentals or one off cost) of P(τ). But he would also pay a penalty of
r(20 – τ). However, future rentals on the old meter, also equal to r(20 –
τ), are saved and the penalty and saved rentals thus cancel out. The
implication is that in net terms renters and owners have the same
incentives to update the meter stock at any time τ that is D(20 – τ) –
P(τ). |
||
|
||
54 |
||
|
||
|
||
150. This result requires
however that the rental contract terminates at the date that the meter
becomes physically obsolescent. If that is not so then the net benefit to
replacement under ownership differs from the incentive under the rental
agreement. For example, the commitment to pay an early replacement charge
under the contract may terminate (as with the Legacy MSA) after 18 years
rather than 20 but if the meter continues to be rented then rental is
still due for the last two years. The renter may avoid these later rental
charges by replacing the meter without penalty. However, the gas supplier
who owns its meters has sunk all the cost of purchasing the meter (at a
price presumably based on its expected physical life) and thus does not
have such savings to make. Quite correctly, therefore, National Grid made
the point that if the commitment to pay an early replacement charge under
the contract terminates prior to the physical obsolescence of the
meter then the net gain from replacement at any time for a gas supplier
who owns the meter is less than under the rental agreement.
However, this particular result is only partial for it does not take into
account what is known as the intertemporal arbitrage condition. This
refers to the fact that although it may be profitable for the gas supplier
to replace the meter at a point in time it might be even more profitable
to wait before replacement. With this condition in place the ranking of
incentives to owners and renters may be different from those suggested by
National Grid in a scenario where the penalty period ends prior to the end
of the physical life of the meter.
151. But more to the point
is the fact that the hypothesised rental contract does not reproduce the
character or terms of the Legacy MSA contract. Under that contract one of
three penalties is payable if a meter is removed; zero if the number of
meters rented remains above the number set by the glidepath, the BLR if in
the Take or Pay zone, and the unrecovered future rentals represented by
the PRC for replacements which take the number of meters rented below the
Take or Pay zone. It is true that the amount of the PRC the gas
supplier pays if he pays a PRC declines over the years of the
Legacy MSA contract. But the question whether the gas supplier has
to pay a PRC is not related to the age of the meter or how many years of
rental are outstanding on that meter. Rather, the PRC depends entirely
upon the number of meters already removed from the stock in that year or
in previous years. Further, whether penalties are incurred under
the Legacy MSA is dependent not just on how many meters the gas supplier
decides to replace but on how many meters National Grid determines it
should replace in the form of the |
||
|
||
55 |
||
|
||
|
||
policy requirement. In the
hypothesised rental agreement the early replacement penalty is equal to
future rental payments yet to be paid dependent upon the number of years
the meter has been installed and is unrelated to the number of other
meters removed. In that sense, it is an age-related scheme because
whenever the customer decides to remove it, the amount of the PRC payable
(including whether it is zero or not) depends on how long the meter has
already been in place and hence for how many years rental has already been
paid.
152. National Grid may
therefore have succeeded in showing that an age-related early replacement
scheme provides the same incentives for replacement as the sale of the
meter (putting on one side the differences that exist between what the
buyer acquires when he rents rather than buys a product). But the Legacy
MSA cannot be described as an age-related scheme just because the PRC
declines over the years. The amount of PRC payable, including whether it
is zero or not, is not dependent on how many years that meter has been in
place or how much rental has been paid in respect of that meter. Looking
at the operation of the Take or Pay zone, the number of years’ rental
(BLRs) that the customer pays when he removes a particular gas meter does
not depend at all on how many years he has already paid rent on that
meter. It is determined purely by the number of meters removed over past
years and how many meters the customer removes in later
years.
153. In comparing the
incentives for replacement operating on a gas supplier under two different
kinds of arrangements, one cannot leave out of account the provisions
which determine whether a penalty is paid and focus instead on the amount
of the penalty paid. The contractual conditions which determine whether
a penalty is payable do not simply influence which meters the
renter will choose to replace but when they will be replaced and
how many will be replaced. It is not right therefore to see the
Legacy MSA as some form of scaled up or aggregated version of an
individual meter, age-related scheme.
154. We do not find,
therefore, that the comparison carried out by National Grid is useful. It
focuses entirely on the fact that the PRCs are calculated using the net
present value of future rentals. It ignores the elements of the contract
that would, in practice, influence the decisions of the gas suppliers as
to the number of meters to replace, namely the |
||
|
||
56 |
||
|
||
|
||
provisions which determine when
early replacement charges (whether BLRs or PRCs) actually become
payable.
155. A more useful analysis
of the incentives likely to influence the decisions of the gas suppliers
as to the rate at which to remove meters under the Legacy MSAs was
provided, at the Tribunal’s request, during the course of the hearing.
Instead of spreading the amount of the early replacement charges over the
population of meters removed (as Mr Keyworth did in calculating the
average costs of replacement) this exercise spread that amount over the
population of meters remaining. In other words the cost of removing
a given number of meters was expressed as an additional rental due on the
remaining meters. The resulting table (attached to this judgment as Annex
2) shows how much higher the rental per meter would be if, instead of
pursuing an 18 year replacement strategy for DCMs as envisaged by the
glidepath, the gas supplier implemented a programme of replacing all its
meters over 17 years, or over 16 years and so on. The table shows that the
rental per meter rises fairly rapidly as the supplier removes meters
faster than allowed under the glidepath such that if he decides to remove
all his National Grid legacy meters over 14 rather than 18 years, his
rental rate is the same as the rental he would have been paying if he
stayed on the P&M terms – a level of rental which was at the time of
the conclusion of the Legacy MSAs above the rental on offer from the
CMOs.
156. In conclusion, we
reject National Grid’s criticisms of the counterfactual used in the
Decision and we also find that the effect of the Legacy MSA early
replacement charges does not generate the same replacement incentives as
the sale of meters would generate. The counterfactual exercise used in the
Decision was properly carried out by the Authority and fully supports the
conclusions drawn from it.
(f) Maintenance bundling
157. Another aspect of the
Legacy MSAs that the Authority criticised was the effect that maintenance
bundling had on the amount of replacement activity that the gas supplier
could make available to a CMO. The Authority did not find that maintenance
bundling was itself an abuse. But meters are sometimes replaced by
National Grid on a maintenance visit. This affects the CMOs’ business in
two ways. First, it means that the new meter will not be a legacy meter
which the gas supplier is likely to want the |
||
|
||
57 |
||
|
||
|
||
CMO to replace (see Decision
paragraph 4.82). In addition because a replacement carried out on a
maintenance visit counts against the free allowance under the glidepath,
the effect was to reduce the number of discretionary replacements that a
CMO could expect to be asked to replace without the gas supplier incurring
an early replacement charge: see paragraph 2.96 of the
Decision.
158. So far as DCMs are
concerned, the evidence before us indicates that there is really no
maintenance service required for these meters, even though an element
supposedly covering the cost of maintenance is included in the National
Grid rental price. According to Mr Avery, British Gas decided that it
would operate a “first visit fit” principle whereby any opportunity for a
CMO to gain access to a domestic premises was regarded as an opportunity
to replace the meter, whether it was capable of being repaired or not.
Even with the maintenance bundling obligation in place, British Gas
regarded itself as entitled to direct what started out as a maintenance
call to a CMO so that the CMO could replace the meter, rather than call
National Grid to repair or replace it. It is true that this meter then
counts against the glidepath just as it would if National Grid had
replaced it. But for DCMs it appears that the bundling of maintenance had
no foreclosing effect additional to that of the operation of the Legacy
MSA glidepath.
159. The position regarding
PPMs is different. CML and Siemens in particular stressed in their
submissions that real maintenance work is carried out on these meters
because they are much more expensive to replace. The meters have batteries
that need to be replaced periodically and they are more technically
complicated than DCMs. The gas supplier is therefore likely, given that
maintenance is bundled, to ask National Grid to attend on a maintenance
call out to a PPM meter rather than direct the CMO to replace it with a
new PPM.
160. Mr David James and Mr
Avery for National Grid made the point that National Grid’s PPM charges
are lower than the PPM charges set by the CMOs so that, if the meter does
need to be replaced, gas suppliers are likely anyway to want National Grid
to replace their PPM meters rather than a CMO. As Mr Avery put it
(paragraph 105 of his witness statement) “due to the cross subsidy a
National Grid PPM is always cheaper than a CMO PPM and it makes no
economic sense to switch out a National Grid PPM unnecessarily, except to
meet the volume commitments under the CMO
contracts”. |
||
|
||
58 |
||
|
||
|
||
However, Mr Avery’s evidence (and
that of Mr Duncan Southgate on behalf of Siemens) was that at the time of
the ITT, British Gas had intended to negotiate an unbundling of
maintenance with National Grid and use the CMOs for PPM maintenance work,
even though if the meter had been replaced rather than repaired, they
would have, as Mr Avery put it, “to take that hit of prepayment meters
being slightly more expensive through CMOs than they were through National
Grid” (Transcript, Day 4, p.33). This accorded with Mr James’ evidence in
cross examination when he confirmed that at the time of the ITT, British
Gas intended that the “first visit fit” principle would apply to both PPMs
and DCMs.
161. We were told that in
2005 around 600,000 unplanned maintenance visits to PPMs were undertaken
by National Grid. When it is called out to repair a PPM meter, National
Grid may indeed simply repair it. In such a case the visit has no effect
on the Legacy MSA. But if the meter is replaced on that maintenance visit
then the new PPM will go onto the N/R MSA. This has the double effect
found by the Authority, namely that the CMO does not have an opportunity
to replace that meter with its own meter and there is one less
penalty-free meter available under the glidepath. Of the 600,000 visits
undertaken in 2005, about 15 per cent resulted in meter replacement (about
85,000). This represents about 5 per cent of National Grid’s total number
of PPMs. Although these numbers are small in terms of volume, they have a
value out of proportion to their number. Siemens and CML showed us that in
their initial bid against the British Gas ITT, although the proposed
number of PPMs was less than a third of the number of DCMs, the expected
annual revenue was substantially more for PPMs than for DCMs. Mr David
Lee’s evidence on behalf of Siemens was that in Area 5 which was allocated
to CML, the number of PPMs replaced by National Grid on maintenance visits
would have translated into approximately 8,000 PPM replacements in the
first year of the MSA contracts - a significant proportion of their total
contracted gas meter installation volumes.
162. Further, it is
difficult for a gas supplier to ensure that only those PPMs which really
need to be replaced are replaced by National Grid when it makes a
maintenance visit. Mr Avery confirmed that British Gas’s preferred outcome
would be that National Grid actually repaired the meter rather than
replacing it if possible. There was some suggestion in the papers before
us that British Gas suspected that National Grid was |
||
|
||
59 |
||
|
||
|
||
replacing PPMs on maintenance
visits rather than carrying out routine maintenance. Certainly, the way
the Legacy MSA works gives National Grid an incentive to replace meters
rather than repair them because it reduces the number of free
discretionary replacements available to the gas operator (which could be
used to install a CMO meter).
163. We therefore conclude
that even though maintenance bundling has not been found to be abusive, it
does aggravate the effect of the Legacy MSAs in the two ways that the
Authority found.
(g) The effects of the Legacy MSAs
(i) Did the Legacy MSAs result
in British Gas reducing the level of replacement undertaken by the
CMOs?
164. The Authority found
that the Legacy MSAs had had an actual foreclosure effect on the relevant
market. In relation to each of the CMOs, the Authority found that once the
Legacy MSA terms had been concluded, they resulted in British Gas
tightening the terms of its contracts with the CMOs in order to minimise
its exposure to the early replacement charges. The Tribunal was provided
with a great deal of evidence from National Grid and the Interveners on
this issue, seeking to explain what had happened in the negotiations
between British Gas and the CMOs and what had been British Gas’s
motivation. Although British Gas did not intervene in these appeals, we
had not only the evidence of the witnesses who had been employed by
British Gas at the relevant time but also large numbers of internal
British Gas documents which formed part of the Authority’s case file. We
consider each of the CMOs in turn to consider whether the findings made by
the Authority are supported by that evidence.
Meter Fit
165. Meter Fit was the
first CMO to enter into a contract with British Gas in 2002. Its first
installation was in November 2002. The findings in the Decision regarding
the effect of the Legacy MSA on Meter Fit’s business were limited. Ms
Carss-Frisk for the Authority confirmed that there was no finding in the
Decision that there had been a reduction in Meter Fit’s volumes of meter
replacement and the Authority was not asserting that there had been such a
reduction as part of its case in this appeal. The |
||
|
||
60 |
||
|
||
|
||
Authority focused instead on the
renegotiation of the contract which began at the end of 2003 and was
concluded in June 2004. As a result of that renegotiation, the fixed
volume caps which prevented Meter Fit from replacing more than a certain
percentage above contract volumes were “tightened”. This means that if the
volume of meters in one year is in excess of a low percentage above the
cap, that is treated in the renegotiated contract as a material breach.
The Authority appears to have accepted Meter Fit’s view that the
introduction of this cap was a result of British Gas becoming nervous
about the replacement volumes in the Meter Fit contract.
166. Before the Tribunal,
Meter Fit put the case on actual foreclosure rather differently from the
stance taken by the Authority. Evidence about the renegotiation was given
in the witness statement of Mr King. It was accepted on all sides that
there had been substantial “teething problems” when Meter Fit’s contract
with British Gas first came into operation in early 2003. It was also
common ground that these problems were caused by fault on both sides. Mr
King attributes the problems to IT systems issues at both the British Gas
and Meter Fit ends. The data problems on British Gas’s part created
difficulties for Meter Fit’s subcontractors. The renegotiation of the
contract started in Autumn 2003 and was concluded in June 2004, setting
new contract volumes and extending the initial period of exclusivity in
the contract for a further year. There was also an upward revision of the
meter rentals.
167. Meter Fit sought to
show that the volumes of meters that British Gas contracted for in this
renegotiation were lower overall than the original volumes and that this
reduction in business was the result of the conclusion of the Legacy MSAs
in May 2004. They produced a table showing the original contract volumes
as compared with the renegotiated contract volumes, Year 1 being November
2002 – November 2003: |
||
|
||
61 |
||
|
||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
Volumes under Meter Fit / British Gas
Contract |
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
168. Meter Fit argued from
this table that the renegotiation resulted in an overall reduction in
volume ([…][C]) of about 7 per cent. We do not agree that that is a
sensible reading of the table. The total volumes over all the years (and
hence the average annual volume) are lower than was contracted for because
of the substantial underperformance in the first year of the contract –
some […][C] meters fewer than originally contracted for. Mr King
says that “at no point during the negotiations did [British Gas] raise the
issue of reducing volumes due to non-performance”. But this can only have
been because it was obvious to both sides without British Gas raising it
that, since Meter Fit only managed to replace about half of the first
year’s commitment, this was what was prompting the renegotiation. This
underperformance had nothing to do with the introduction of the Legacy
MSA. Mr Avery’s evidence was that the original contract did not allow
Meter Fit to carry forward volumes that it had not replaced in one year to
the next year. The effect of the renegotiation was in fact to allow Meter
Fit to make up for its underperformance in the first year by making
slightly more replacements in subsequent years.
169. Mr King was not called
for cross-examination by National Grid. We have read his written statement
carefully and conclude as follows. Although Mr King says (in paragraph
18(e) of his witness statement) that “it would appear” that the
renegotiation was affected by the Legacy MSAs, he does not say what
happened at the time of the renegotiation which made that apparent. Meter
Fit has not shown that the overall reduction in replacement volumes
averaged over the life of the contract was the
result |
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
62 |
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||
of the Legacy MSA. Further, we
had the unchallenged evidence of Mr Lewis and Mr Neil Williams who were
negotiating for British Gas with the CMOs that no overall reductions in
the volume commitment were agreed with Meter Fit.
170. So far as the
tightening of the maximum cap is concerned, Mr Avery explained that the
cap was set because the contract moved from one where British Gas
specified exactly which meters should be replaced (and could control the
actual volumes replaced in that way) to one where they specified a pool of
meters from which Meter Fit was free to choose the ones it would replace.
The cap was included in the renegotiated contract so that British Gas
could maintain its control over the total number of meters replaced by
Meter Fit from that pool. This accords with the contemporaneous internal
British Gas documents in particular an email from Mr Avery to a colleague
in May 2004 in which he describes the reasons for the renegotiation with
Meter Fit and the resulting agreement. There is also an internal British
Gas paper dated May 2004 which explains:
“Car Park Volumes – Under
the Agreements as originally conceived British Gas had near total control
over the volume of work passed to [Meter Fit]. Under the Amendment
Agreement British Gas will maintain a “car park” of available gas meter
work from which [Meter Fit] can draw work. … Control over a significant
portion of volumes is thereby passed to [Meter Fit].”
Neither the email nor the paper
mentions the Legacy MSAs as a reason for amending volumes in the Meter Fit
contract.
171. It is not right
therefore to say, as Mr King does, that this was introducing a restriction
that did not exist in the earlier contract. It is also not right to assume
that the maximum cap operated to reduce the number of meters in fact
replaced by Meter Fit. It could be regarded as simply re-establishing a
mechanism for maintaining a degree of control over the volumes replaced.
We do not accept therefore that the Authority was justified in drawing any
conclusion from the renegotiation of the maximum cap.
172. Mr Avery was very
clear why it mattered to British Gas that Meter Fit should not be able to
replace all the meters in the pool in one year – this was in order not to
go into the early replacement charges. It may be that British Gas would
have asked Meter Fit to replace more meters over the life of the contract
in the absence of the Legacy MSA rather than sticking to the contract
minima. But the Decision made no such finding and the Authority did not
make any such assertion at the hearing. Mr Avery in fact
denied |
||
|
||
63 |
||
|
||
|
||
that this had occurred. His
evidence was supported to some extent by the July 2004 email which we
discuss further below which says as regards Meter Fit that given their
commercial difficulties, “a commitment to allow them to operate at 100%
volume was given during the recent contract renegotiations”.
173. In so far as the
Authority relied on the changes in the contractual terms when the Meter
Fit contract was renegotiated to establish an actual foreclosure effect
from the Legacy MSA, we find that such a conclusion is not adequately
supported by the evidence before us.
CML
174. The position of CML
was different from Meter Fit in that CML and British Gas were still
negotiating the terms of their contract at the point when the Letter of
Intent concerning legacy meters between National Grid and British Gas was
signed in late 2002. The Decision found that there were two aspects of
British Gas’s relationship with CML which pointed to an actual foreclosure
effect. First, in the pre-contract negotiations in March 2003, British Gas
informed CML that it wanted to rent around 15 per cent fewer DCMs from CML
than it had previously expected to rent. Thus, the Authority found, the
volumes included in the contract were lowered in order to reduce British
Gas’s exposure under the Legacy MSAs. Subsequently in May 2006, after the
contract had been concluded and gone live, British Gas informed CML that
it was reducing the volumes that it would ask CML to replace so that
British Gas kept to the minimum number that it was obliged to ask CML to
replace. The Authority found that although British Gas was entitled under
the contract to reduce the volume by this amount, CML had expected to
supply 100 per cent of the contractual volumes.
175. We had a number of
witness statements about these negotiations. Four of them came from people
who had been involved in the negotiations on the British Gas side. The two
more senior British Gas people, Mr James and Mr Avery, gave evidence on
behalf of National Grid. The two more junior members of the British Gas
National Metering Team, Mr Lewis and Mr Williams, gave evidence on behalf
of CML. There was also evidence from Mr Duncan Southgate on behalf of
Siemens and from Mr Timothy Hoskin on behalf of CML about those companies’
negotiations with British Gas at the |
||
|
||
64 |
||
|
||
|
||
relevant time. Further details
about these witnesses are set out in Annex 1 to this
judgment.
176. It was accepted on all
sides that there had been a reduction in volumes of DCM replacements
negotiated in March 2003: the chronology agreed between National Grid and
the Authority put this at 20 per cent. This accords with the evidence
about these negotiations given by Mr Southgate on behalf of Siemens. But
there was a dispute as to why this had happened. In his first
witness statement, Mr James’ evidence was that by the time CML came into
the picture in late 2003, the British Gas negotiating team understood the
Legacy MSA constraints well and these, along with other considerations,
“were factored into the CML contracts”. This accords with the evidence of
Mr Avery to the effect that “the opportunity was taken” during the
renegotiation to reduce the CML volumes to minimise the likely exposure to
penalties on early replacement of National Grid meters. In his third
witness statement Mr James, while not going back on his earlier statement,
suggests that the Legacy MSAs were only one of a number of factors – he
describes six others – which were at least as important in arriving at the
lower CML contract volumes.
177. His evidence is
contradicted by that of Mr Lewis and Mr Williams. Mr Lewis says that at
some point in early 2003, he and his colleagues became aware that a deal
was being negotiated with National Grid that would restrict the number of
National Grid meters that could be exchanged in any year. As a result,
British Gas wanted to identify the extent to which the CMO volumes were
likely to result in British Gas exceeding the level of replacement
allowed. Mr Lewis and Mr Williams carried out various hypothetical
modelling exercises and these made clear that the contract volumes agreed
or proposed to be agreed with the CMOs were in excess of the glidepath
allowance. They indicated that British Gas would be in the Take or Pay
zone for a substantial period for both DCMs and PPMs. Mr Lewis then
describes the internal British Gas discussions as to how to approach a
reduction in the CML volumes, given that the CML contract had not yet been
concluded. He states that he decided for purely commercial reasons not to
disclose to CML that the reason for British Gas seeking to reduce volumes
was the effect of the Legacy MSA. Such a reference could have been
inflammatory and unhelpful. We accept that this explains why the
correspondence between British Gas and Mr Southgate at Siemens does not
blame the volume |
||
|
||
65 |
||
|
||
|
||
reductions on the Legacy MSAs.
Nevertheless, Mr Lewis says that there was no reason to change the CML
volumes other than the impact of the Legacy MSA. His evidence was
supported by a document from January 2003 that was included in a bundle
introduced by National Grid during the course of the hearing. The document
is headed “Meter Operator Contracts Volumes and Gas Legacy Impact
Discussion Paper”. This sets out the conclusion that even if operating at
the bottom of the volume bands in the CMO contracts, there are
“significant problems” in the first two years in terms of replacement
exceeding the glidepath. In other words even if British Gas restricted the
CMOs to the minimum levels of replacement that were envisaged for them,
the number of replacements would still exceed the glidepath allowance by a
significant number of meters in the first two years. This could be dealt
with, according to the Paper, by significantly reducing meter replacement
after the expiry of the initial five year period (that is the period
during which the CMOs have guaranteed volumes); renegotiating the volume
bands with the CMOs; delaying the roll out of the CMO contracts or
incurring the penalties under the CMO or Legacy MSA
contracts.
178. Mr Lewis’ evidence is
also supported by an email from 9 July 2004 from Mr Avery to his
colleagues setting out a draft email to be sent to Mr Paul Bysouth, Mr
Avery’s director at the time (“the July 2004 email”). In this email (which
was in fact sent to Mr Bysouth on 22 July 2004) Mr Avery seeks approval to
negotiate a revised deal with OnStream “to address the legacy volume
mismatch issue”. Mr Avery explains by way of background that when the
Legacy MSA Letter of Intent was signed with National Grid (in December
2002), British Gas was aware that there would be a mismatch between the
numbers of DCM replacements under the Legacy MSA glidepath and the
contractual commitments under the CMO contracts. Mr Avery sets out the
“Actions Already Taken” to address the mismatch including reducing
Siemens’ volumes to approximately 80 per cent of the tender numbers as
well as operating the OnStream contract at 80 per cent of the contractual
commitment.
179. We accept that there
may have been a number of different reasons for the reduction in the CML
volumes, but we prefer the evidence of Mr Lewis over that of Mr James’
third witness statement. Mr Lewis’ and Mr Williams’ description of the
modelling carried out and the discussions within the British Gas National
Metering Team establishes, in our judgment, that the Legacy MSAs were an
important factor in British Gas’s decision |
||
|
||
66 |
||
|
||
|
||
to reduce the contract volumes
during the 2003 negotiations. Mr James’ and Mr Avery’s attempts in their
evidence to downplay the significance of the Legacy MSAs are, in our
judgment, unconvincing. We do not accept that the parallel, larger,
reduction in electricity PPM volumes at about the same time casts doubt on
the conclusions of the CML witnesses. Mr Avery accepted when cross
examined by Mr Vajda QC that during 2003 and into 2004, British Gas
realised that it was cheaper for them to cut the volumes available to the
CMOs than to pay the BLRs even if the reduction in volumes meant that the
CMO rentals had to rise. We find that in the 2004 renegotiations, British
Gas was trying to optimise its metering costs by cutting the volumes
contracted for with CML so as to reduce the costs of operating in the Take
or Pay zone.
180. Turning to British
Gas’s proposal in May 2006 to reduce levels to the contractual minimum, we
had evidence on this from Mr James on behalf of National Grid. For CML we
had evidence from Mr Hoskin who has been General Manager of CML since
April 2006 and whose evidence covered both his own experience and what he
had been told when he joined CML by his predecessor in the post, Duncan
Southgate.
181. We regard the
correspondence in 2006 as very telling. When the contract was concluded in
December 2003, British Gas supplied CML with a comfort letter to show to
its bankers confirming that British Gas “will use all reasonable efforts
to maintain the benchmark volumes at the 100% contracted level on an
annual basis…”. However, by 2006 the correspondence shows that British Gas
was pressing to reduce the volumes to the minimum required under the
contract, that is 85 per cent of the benchmark only. It is clear to us
from this correspondence that the tenor of these discussions was to
explore how British Gas could reduce the number of meters that CML was
replacing without rendering the CML business unviable. It is also clear
that the reason for British Gas’s insistence that it must keep replacement
volumes to an absolute minimum was because it wished to avoid penalty
payments under the Legacy MSA. We have no doubt therefore that the effect
of the Legacy MSAs was to push British Gas to a position where its primary
concern was to limit CML’s replacement volumes to the minimum commensurate
with its contractual obligations and the continued viability of CML’s
business. This is not what one would expect to see, given the evidence
that British Gas considered that CML’s DCM rentals were materially cheaper
than National Grid’s. |
||
|
||
67 |
||
|
||
|
||
182. There was some
disagreement among the witnesses as to whether CML would have been able to
undertake a higher volume of replacements than the minimum they were in
fact asked to undertake. But we accept the evidence of Mr Lee that by mid
2005 Siemens was achieving the contracted rate of installation and could
easily have accommodated significant additional volumes of
work.
183. We therefore uphold
the Authority’s finding that the Legacy MSAs had an actual foreclosure
effect on the amount of business that British Gas gave to
CML.
UMS
184. In the Decision the
Authority found that in 2004 British Gas also considered ways of
renegotiating the UMS contract to reduce the volumes contained in the
contract. Mr Lewis’ evidence was that he had been involved in the
negotiations with OnStream and their five year contract volumes were
reduced by 40 per cent. As discussed above (paragraph [178] above), the
July 2004 email sent by Mr Avery to Mr Bysouth recommended that
negotiations were progressed with OnStream to reduce volumes to 60 per
cent of the contracted volumes, provided that the increase in rental price
was not greater than a certain amount. The Authority was therefore
entitled to rely on a reduction in the volumes of replacements undertaken
by OnStream as evidence of actual market foreclosure arising from the
operation of the Legacy MSA provisions.
Conclusion on reduction in CMO replacement
levels
185. We find therefore that
the evidence as regards CML and UMS supports the Authority’s findings that
the Legacy MSAs have had an actual foreclosing effect on competing CMOs
and that this is likely to make it more difficult for the CMOs to compete
with National Grid for even the limited meter numbers that suppliers might
want to replace using a CMO.
186. Overall we also note
that despite British Gas’s efforts to limit the number of replacements
carried out by the CMOs, it has still been in the Take or Pay zone since
February 2006 and was contemplating the possibility of incurring PRCs in
the course of 2007. Whatever the reason why British Gas has replaced more
meters than allowed by the glidepath, this indicates that the glidepath
allowance was not, in fact, sufficient to |
||
|
||
68 |
||
|
||
|
||
allow British Gas to make all the
replacements it wanted without incurring charges. This is bound to affect
the numbers of replacements it makes in subsequent years.
(ii) Did the Legacy MSAs deprive consumers of the benefits
of competition?
187. In paragraphs 4.111
onwards of the Decision, the Authority found that by restricting the
volume of meters that gas suppliers are likely to contract with CMOs, the
Legacy MSAs harm customers because gas suppliers cannot pass on the lower
costs of CMO DCMs as compared with National Grid DCMs. The Authority set
out a graph which compared the Legacy MSA rental charges with a weighted
average CMO charge over the period January 2004 to January 2007. This
showed that there was an average annual saving of over £1.25 for switching
out a legacy meter. The Authority pointed out that the price differential
will increase over the duration of the Legacy MSA because the rental
charge is indexed to inflation (assuming that inflation will in fact occur
over the coming years). Further, the Authority says, even this comparison
may underestimate the harm to customers because in a competitive market
the CMO prices might be even lower.
188. National Grid submit
that the “essential flaw” in the Authority’s comparison is that it
overlooks the fact that the MSAs gave the gas suppliers instant and
substantial savings in rentals across their entire meter portfolio
“compared with the charges that would otherwise have been levied”
(National Grid Supplemental Submissions, paragraph 5). The Tribunal does
not accept that this point constitutes a flaw in the Authority’s
reasoning. The extent to which National Grid responded to competitive
pressure by reducing its Legacy MSA rental from the P&M rate was
affected by its view of the likely speed at which meters could be
replaced. It is this speed of replacement that the Legacy MSA early
replacement provisions are intended to slow down. What the Authority is
seeking to identify here is not the overall benefit to consumers of the
introduction of competition into the market but the effect on consumers of
the fact that fewer cheaper meters are being installed than would be
installed absent the Legacy MSA glidepath. National Grid, as the dominant
supplier, was able to negotiate the limitation on the numbers of
replacements as a quid pro quo for the reduction in the annual
rentals. But that does not reflect what would be likely to happen in a
competitive market. It is not therefore right to regard the P&M
charges as being “the charges that would otherwise have been levied” in
the absence of the Legacy MSA |
||
|
||
69 |
||
|
||
|
||||||||||||||||||||||||||||||||||
because in a competitive market
where there were no barriers to entry, National Grid’s prices would have
to fall to compete with the cheaper CMO product. As Siemens and CML put it
in their closing submissions: “… the effect of the MSAs was to freeze
prices for a controlled volume of meters at a level which quickly became
anti-competitive”.
189. Detailed evidence
comparing prices was submitted in the evidence of Mr Hoskin on behalf of
CML. The Tribunal restricted the comparison made to the prices of DCMs
since this was the scope of the comparison made in the Decision: see our
ruling of 8 October 2008 ([2008] CAT 26). Mr Hoskin explained the data
sources and methodologies underlying the price comparisons and set out the
comparison on various bases. Basis 3 was the most relevant as it compared
National Grid prices under the Legacy MSA against CML’s prices under the
British Gas contract modelled so that they are on a like for like basis.
[…][C] CML also showed what the figures would be if an adjustment
was made stripping out the element in National Grid’s DCM rental which
represents the cross subsidy of PPM rentals. If that adjustment is made to
remove the effect of the cross subsidy the difference in price is, of
course, smaller: […][C] Mr Hoskin also set out in a table a
comparison of CML’s service levels compared with National Grid’s.
[…][C]
190. National Grid
criticised the price comparison set out in the Decision (which was based
on a weighted average of CMO charges). Although National Grid did not
cross examine Mr Hoskin, they also set out various criticisms of his
calculations in their written Supplementary Submissions served in October
2008. CML countered those criticisms in its submissions served on 7
November 2008. In the Annex to its skeleton argument for the hearing, CML
adjusted its model to take account of the points raised by National Grid
to ascertain whether they would affect the contention that CML’s prices
were cheaper than National Grid’s. The rental comparison, on Basis 3, was
as follows: |
||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||
With cross subsidy
Without cross
subsidy |
||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||
70 |
||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||
|
||
191. We agree with CML that
the correct comparison is the comparison of prices with, rather than
without the cross subsidy. As Mr Rayment pointed out on behalf of CML, it
would be unfair to compare DCM prices without the cross subsidy without
also comparing PPM prices without the cross subsidy. National Grid
succeeded at the earlier hearing in excluding evidence put forward by CML
about PPM price comparisons so no such evidence about PPMs was before us
at the hearing. We also note that the difference in prices may increase
during the operation of the agreements because the rentals under the
Legacy MSA are adjusted each year in line with inflation whereas the
prices in the CMO contracts do not.
192. National Grid argued
that the Authority should take into account the benefits to consumers
arising from the Legacy MSAs, namely the minimisation of customer
disruption. There is a disbenefit to domestic consumers if they have to
stay at home to allow the CMO to change a meter where that meter is
working perfectly well but the gas supplier has decided to replace it to
benefit from lower CMO prices. In our judgment, this is not a point that
is available to National Grid. It is for the gas suppliers competing with
each other in the domestic gas supply market to weigh up the advantages
for their customer of having the lower gas price resulting from a pass
through of a lower meter rental against the disruption involved in having
the meter replaced. It is not for National Grid to “protect” the gas
suppliers’ customers from an accelerated replacement
programme.
(iii) Did the Legacy MSAs
hinder product innovation and risk impeding the roll out of smart
meters?
193. In assessing the
effect of the Legacy MSAs on product innovation one should not focus
solely on the introduction of smart metering. Product innovation can occur
by incremental steps improving “dumb” meters as well as by the big jump to
smart meters. For example, we had evidence from Mr Hoskin for CML that one
brand of meters which measures gas by ultrasonic means is more accurate
than other meters which rely on a diaphragm and displacement measurement.
The brand which uses ultrasonic means is also less likely to be affected
by being tilted at an angle than the meter which uses a diaphragm method.
He also referred to the fact that newer meters being installed have a
modular design which allows them to be switched between DCM and PPM modes
without needing to be replaced. Further, we were told by Mr Way on behalf
of |
||
|
||
71 |
||
|
||
|
||
National Grid that, as one would
expect, when National Grid’s on-going testing of meter accuracy identifies
a defect in a particular model of meter, that information is fed back to
the manufacturers so that the problem can be ironed out in future models.
Those later models are therefore better than the legacy stock even though
they are not “smart”.
194. In so far as the
structure of the Legacy MSAs slows down the replacement of the existing
meters with new meters (including with new National Grid meters), it can
be expected to discourage the installation of improved versions of meters.
Thus the Legacy MSAs prevent the “creative destruction” that occurs where
innovation renders earlier technology obsolete, to the disadvantage of the
companies dependent on that earlier technology. We were referred by Ms
Carss-Frisk to Albion Water v Water Services Regulation Authority
[2006] CAT 23 where the Tribunal referred to competition as “taking
the form of, and leading to, innovation in products and processes as part
of the continual pursuit of customers’ business” (paragraph
[663]).
195. However, we do not
find that the Legacy MSAs impede product innovation beyond that. It is
unlikely that the Legacy MSAs have a material effect on the level or
nature of research and development in meter improvement. This is an
international market. We have not seen any evidence to suggest that access
to the British market materially affects manufacturers’ decisions about
meter research and development.
196. So far as the proposed
introduction of smart metering is concerned, the parties disagreed as to
how likely it was that smart metering would be rolled out in the United
Kingdom in the foreseeable future. The Decision referred to documents
indicating that some of the gas suppliers (namely British Gas and EdF
Energy) were concerned that the Legacy MSAs could stifle innovation,
though National Grid put forward other documents suggesting that this was
not an accurate assessment of those companies’ views. The Authority
accepted that these concerns were not universally felt – for example
Scottish Power and Npower seem not to have been concerned. National Grid
argued that by discouraging gas suppliers from replacing ‘dumb’ legacy
meters with new ‘dumb’ CMO meters, the Legacy MSA is likely to increase
the take up of smart meters because gas suppliers would be less likely to
replace a brand new dumb CMO |
||
|
||
72 |
||
|
||
|
||
meter with a smart meter and more
likely to replace an old legacy meter with a smart meter.
197. The Authority
submitted that the prospects for smart metering were much stronger at the
time the Decision was adopted than they had been at the time the Legacy
MSAs were concluded. In his witness statement, Mr Stephen Smith who is the
Managing Director for Networks at the Authority, identified various
factors which have made the business case for smart meters more
compelling. The Authority pointed to the growing evidence of Government
interest in rolling out smart metering. The Government document
“Consultation on Policies Presented in the Energy White Paper” published
in August 2007 sought views on whether the Government should introduce a
programme to replace or upgrade all existing dumb meters with smart meters
over a ten year period. Although the consultation document post dates the
Decision, we consider that it casts light on what would have been the
expectations of the market participants at the relevant time and the
Authority accepted that it was legitimate for the Tribunal to take it into
account.
198. National Grid
countered with evidence that there were many other factors still impeding
the large scale roll out of gas meters, relating to the basic economics
of, and structural issues arising in, the competitive metering market.
National Grid pointed to evidence from the gas suppliers that the benefits
to them of rolling out smart meters are not sufficient to support a
business case for them to undertake this. British Gas, we were told,
responded to a Government consultation saying that costs would have to
more than halve or the benefits would have to double before it would make
sense for suppliers to deploy smart meters to all domestic and small
business customers. British Gas had warned therefore that the Government
cannot rely on suppliers taking the initiative to lead a roll
out.
199. In our judgment, the
decision whether to replace dumb meters with smart meters nationwide over
a ten year period is a decision likely to be taken at Government level. We
agree that, as National Grid put it, there is now a political appetite for
mandating universal smart metering. That plan if it is indeed adopted will
be based on macro-economic considerations as well as political and
environmental criteria. It will inevitably involve the Government in
detailed negotiations with the different |
||
|
||
73 |
||
|
||
|
||
participants in the industry, not
least as to who is going to pay for it. The gas suppliers’ assertions that
they cannot see the business case for undertaking this themselves must be
seen in that context. If the Government decides to go ahead with the roll
out, this will be a very substantial infrastructure project. One of many
factors which will need to be dealt with will be the existence of early
replacement charges imposed for the existing meter stock in both the
Legacy MSAs and the CMOs’ contracts. There were references in the
Government consultation document to “additional stranding costs because of
the terms of the Legacy contracts”. But we are not convinced that this is
referring specifically to the early replacement charges under the Legacy
MSAs rather than referring more generally to the problem about what to do
about the installed “dumb” meters if a ten year total replacement policy
is indeed mandated. The contracts might make it more expensive for the
Government to “buy out” the obligations. But we find that there is
insufficient evidence to establish that the terms of the Legacy MSAs are
likely currently to represent a primary constraint on the roll out of
smart meters. The Authority’s conclusion that the Legacy MSAs will have a
material impact on the roll out of smart meters is not adequately
supported by the material we have seen.
VII. CONCLUSION ON ABUSE
200. The Tribunal upholds the
Authority’s finding that the early replacement provisions of the Legacy
MSAs constitute an abuse by National Grid of its dominant position. They
clearly have a foreclosure effect in discouraging gas suppliers from
moving more of their business to the CMOs and hence are likely to delay
the reduction of National Grid’s market share. The effect of the Legacy
MSAs was demonstrated by British Gas’s actions taken to reduce the volume
of business it provided to some of the CMOs once the terms of the Legacy
MSAs had crystallised. It is true that National Grid has incurred sunk
costs in providing the installed meter to the gas supplier without an
upfront charge. But this does not justify putting in place charges which
may have the effect of maintaining volumes of replacement at little more
than the level that applied when National Grid was a monopoly supplier.
The disproportionate nature of the early replacement charges is, in our
judgment, amply demonstrated by the comparison carried out with the terms
in the CMO contracts and in National Grid’s N/R MSA. There are some minor
aspects of the Decision where we have found that the
Authority |
||
|
||
74 |
||
|
||
|
||
was not justified in coming to
the conclusions it did. But the main finding of abuse set out in the
Decision was, in our judgment, undoubtedly right.
VIII. PENALTY AND DIRECTIONS
201. Section 36(2) of the
Competition Act 1998 confers on the Authority a power to impose a fine for
conduct that infringes the Chapter II prohibition and Article 82 EC where
the dominant company has acted intentionally or negligently. By the time
of the hearing, there was no dispute that there was jurisdiction to impose
a fine in the event that we upheld the finding of abuse. The Authority
made clear in paragraph 6.56 of the Decision that, in setting the penalty,
it had regard to OFT’s Guidance as to the appropriate amount of a
penalty (December 2004, OFT 423). The Tribunal has unlimited
jurisdiction with regard to imposing, revoking or varying the amount of
the penalty imposed by the Authority (see paragraph 3(2)(b) of Schedule 8
to the 1998 Act and Napp Pharmaceutical Holdings Limited v Director
General of Fair Trading [2002] CAT 1 at paragraph [499]). The role of
the OFT’s Guidance on penalties in relation to the Tribunal’s jurisdiction
has been considered both by this Tribunal and by the Court of Appeal: see
Makers UK Limited v Office of Fair Trading [2007] CAT 11 paragraphs
[117] to [120] and the cases cited therein. Although that Guidance does
not bind the Tribunal, we recognise that we should not disregard it and
that the Authority, like the OFT, has a margin of appreciation as regards
the level of fine it considers appropriate for a particular
infringement.
202. In determining the
level of the fine the Authority concluded that the infringement was
serious, albeit not so serious as it had thought at an earlier stage of
the investigation. The maximum starting point for the most serious
anti-competitive conduct is 10 per cent of the undertaking’s turnover in
the relevant product market (see paragraph 2.8 of the OFT’s Guidance). The
Authority concluded that the appropriate starting point in this case was 4
per cent of that turnover. National Grid’s turnover in the domestic-sized
gas meter market is about £260 million per annum, 4 per cent of which is
£10.4 million. National Grid complained that that the turnover figure used
at this point in the calculation included the turnover for UMS whereas in
other parts of the Decision, in particular in finding that there had been
actual foreclosure, the Authority had treated UMS as a new entrant. We do
not agree that there is an inconsistency here. It is
clear |
||
|
||
75 |
||
|
||
|
||
from the OFT’s Guidance that,
having regard to the evidence of Mr Shoesmith about the relationship
between National Grid and UMS, the two entities should be treated as part
of the same undertaking for this purpose. It is still legitimate to look
at the reduction in UMS’s contract volumes as evidence of the foreclosure
effect of the Legacy MSAs (see paragraph [184], above) because those
reductions would most likely have occurred regardless of whether UMS was a
subsidiary of National Grid.
203. The Authority applied
a multiplier of four to take account of the duration of the infringement
between 1 January 2004 (the date on which the Legacy MSAs are, by their
terms, deemed to apply) and the date of the Decision. This brought the
fine up to £41.6 million. The Authority decided that there was no need to
increase the fine in order to ensure it has an adequate deterrent
effect.
204. The Authority then
considered that there were “potential aggravating and potential mitigating
factors” in the case but that on balance none of them was sufficiently
serious to influence the penalty (paragraph 6.63 of the Decision). As a
potential aggravating factor, the Authority identified that National Grid
had not sought formal guidance from the Authority on the MSAs. In
potential mitigation the Authority recognised that National Grid had taken
positive steps to facilitate the introduction of competition in the
domestic gas market. The fine ultimately imposed was therefore £41.6
million.
205. Before the Tribunal,
National Grid’s main argument in mitigation of the fine was that the
Authority had been involved all along in the discussions about the
development of the Legacy MSA and had not made clear to National Grid that
it had serious concerns about the terms. This did not, National Grid
conceded, create a fully-fledged, public law legitimate expectation on the
part of National Grid that the Authority would not take action against the
MSAs. But the fact that the Authority was monitoring and discussing the
terms of the MSAs with the industry and was kept informed as the contracts
evolved should mitigate the fine.
206. The Authority refutes
this suggestion. Evidence about the discussions between National Grid and
the Authority was given by Ms Maxine Frerk who is currently Director of
Governance, Social and Consumer Affairs at the Authority. Ms Frerk was
involved in discussions with National Grid about the issues arising from
the opening up |
||
|
||
76 |
||
|
||
|
||
of metering services to
competition. In her evidence she drew a distinction between the stage in
2002 when National Grid was pushing the Authority for a regulatory
solution to asset stranding and the later stage when National Grid had
decided to deal with the issue by commercial negotiations with the gas
suppliers. At the earlier stage the Authority, she said, would have been
careful not to express either approval or disapproval of any proposal from
National Grid because that would risk prejudging the outcome of the
consultation procedure which would be needed before any such amendment to
the regulatory framework could be adopted. The Authority relies on
correspondence in October 2002 in which it made clear to National Grid
that any proposals “must provide a clear net benefit to customers, and
must not prevent the development of competition and customer benefits in
the future”.
207. As regards the later
stage, once it became clear towards the end of 2002 that National Grid was
going to deal with the legacy meters issue by private contractual
arrangements with the gas suppliers, Ms Frerk says that from her
perspective “Ofgem’s interest in the proposed revised changes ceased”. In
February 2003 when National Grid sought the view of the Authority as to
the appropriate level of charges the Authority replied (letter of 18
February 2003):
“You specifically asked us for
our view on the appropriate level of the domestic credit meter charge.
Since this development is to be pursued by commercial negotiation Ofgem
has no views on the appropriate level of the charge provided in setting
its charges, terms and conditions [National Grid] is compliant with its
obligations under licence and, more generally, competition and consumer
law.”
In an internal paper prepared for
the Authority’s Management Committee dated 5 February 2003, National
Grid’s proposals for its contracts with gas suppliers were discussed. That
paper recognised that the proposals reduce the incentive for suppliers to
replace gas meters before the end of their useful lives but recommended
that the Authority “take no action to support or oppose these
developments” which National Grid was pursuing through contractual
negotiations. The paper concluded that the Authority would continue to
monitor the situation to ensure that the best interests of customers are
served.
208. We have considered
carefully the meeting notes and correspondence between National Grid and
the Authority over the whole period. These must be seen in the context of
the fact that the Authority was the architect and main driver of the
process of opening up |
||
|
||
77 |
||
|
||
|
||
metering services to competition.
It had launched the consultation “Strategy for Metering – Report on
Progress and Next Steps” in 2002 and was in frequent contact with all the
industry players. It was pushing forward the plans for this major change
in the structure of the industry as an important initiative. It must have
been clear to the Authority that the terms of National Grid’s contracts
dealing with the legacy meters were absolutely key to the success or
failure of the RGMA project. Given the importance that the Authority has
attached to the success of the RGMA project, we are surprised that the
Authority did not consider that it was part of its role either as an
industry regulator or as a competition law enforcement agency to steer the
industry participants away from making private arrangements which risked
jeopardising the competitive process to a serious degree. The Authority
appeared content for National Grid to enter into contracts with the gas
suppliers which it now considers, according to the Decision, have had a
significant actual anti-competitive foreclosure effect and hindered the
development of the business of the CMOs.
209. Both National Grid and
British Gas are undertakings with long experience of working under
regulation and are used to conducting their business under the scrutiny of
the regulator and indeed of having major aspects of their business decided
or at least influenced by the regulator. Ms Frerk records in an email in
August 2002 that at a meeting at the end of June 2002 the Authority had
invited National Grid: “to come up with a creative solution to the problem
of premature replacement of meters” which did not involve a re-opening of
the price control and which offered benefits to customers. In response to
that invitation, National Grid wrote to the Authority in August 2002
proposing the introduction of premature replacement charges linked to a
reduction in annual rentals as “the most transparent and most effective”
way to reduce the current incentive for premature replacement. The letter
closed with the National Grid Head of Regulation saying that he would
welcome the Authority’s views on their proposals. The paper attached to
that letter sets out the proposal in more detail and again invites the
Authority’s views on the approach. There followed meetings between
National Grid and the Authority in August and September 2002 and further
correspondence where the Authority outlined several detailed concerns
about the proposals and National Grid responded to those concerns by
changing the proposals. Overall, we can well understand National Grid’s
surprise and dismay when the Authority opened its |
||
|
||
78 |
||
|
||
|
||
investigation into these
agreements under the 1998 Act and imposed such a substantial
fine.
210. There were two
particular points which the Authority put forward to show that they had
not given any comfort to National Grid in the course of the discussions.
The first was that, so far as the Authority was concerned, the issue about
the stranding of National Grid’s assets had been dealt with in the earlier
decisions which set the 2002 price control. According to Ms Frerk, this
was the view of the Ofgem Management Committee with whom she met in
October 2002. Callum McCarthy (Ofgem’s Chairman and Chief Executive) and
Eileen Marshall (the Authority’s Managing Director of Competition and
Trading Arrangements) were “very unsympathetic” to National Grid’s
concerns because National Grid had done well out of the overall deal
struck at the time of the price control and should not be allowed now to
unpick the less favourable parts of that deal. Mr McCarthy, we were told,
expressed this view to Sir John Parker (Chairman of National Grid) when
they met for lunch on 15 October 2002. We also had the evidence of Mr
Stephen Smith who was Director of Trading Arrangements at the Authority
during the 2002 price control review. He explained how National Grid had
benefited from the adoption of an “unfocused” approach to the valuation of
the transportation and metering assets. In the Decision (paragraphs 2.56
to 2.60) the Authority described this choice between the focused and
unfocused approach to asset valuation and referred to National Grid’s
valuation of the benefit to it of the “unfocused” approach ultimately
adopted as being “up to £2 billion”. The Decision states that when
National Grid tried to reopen the issue in 2002 to suggest that stranding
costs should be recovered through an increase in their allowed revenues
for the transportation business the Authority “made clear it considered
this issue settled and closed” (see paragraph 2.60).
211. National Grid
countered with evidence from another NERA consultant Mr Graham
Shuttleworth who believed that it had never been feasible for the
Authority to adopt a focused approach to asset valuation so that the
supposed £2 billion gain for National Grid was illusory. They also pointed
out that at paragraph 2.49 of the Decision the Authority appears to
acknowledge that the adjustments made to the price control were not
intended to compensate National Grid fully for any potential stranding. As
Mr Turner put it in his opening submissions: “on everybody’s
understanding, Ofgem’s and |
||
|
||
79 |
||
|
||
|
||
ours, one way or another there is
something sticking out of the duvet there that has not been covered in the
price control, which is the risk of the asset stranding” (Transcript, Day
1, p.49).
212. We were not shown
contemporaneous evidence that any particular element in the price control
methodology (such as the unfocused approach to asset valuation) was
expressly adopted as a quid pro quo for National Grid accepting the
risk of asset stranding. We do not read Mr Smith’s evidence as asserting
that the parties acknowledged this at the time of the 2002 price control
review. The Authority showed us an extract from the 2002 Price Control
consultation which they said makes clear that the Authority was genuinely
considering whether the focused approach was appropriate. We accept that
this is the case – but the document does not refer to potential asset
stranding as one of the reasons why the Authority might choose to continue
with the unfocused approach for National Grid’s benefit.
213. In our judgment,
whatever may have been the views within the upper echelons of the
Authority, the Authority did not generally conduct its discussions with
National Grid on the basis that the price control in 2002 had adequately
recompensed National Grid for potential asset stranding. On the contrary,
it appeared from those discussions that the Authority did accept that
asset stranding for legacy meters was still an issue which could
legitimately be addressed by entering into arrangements which included
payment completion terms. We were taken, for example, to the notes of a
meeting between the Authority and National Grid in April 2002 attended by
Ms Frerk among others. The notes record that Mr Shoesmith, one of the
National Grid team, pressed the point about the discrepancy between the
“legitimate recovery expectations” at the time the meters were installed
compared to “the value that could reasonably be expected to be recovered
under the present circumstances.” The notes then record: “[Ms Frerk]
accepted that the basis upon which meter investments were historically
made were different now to then. Citing examples such as ‘meter
manufacturers’ prices were higher then”. There is no suggestion here that
the Authority dismissed National Grid’s concerns on the basis that those
issues were being taken care of in the settlement of the price control
which was happening at about the same time. |
||
|
||
80 |
||
|
||
|
||
214. In the May 2002
Consultation document there is a reference (at paragraph 4.16) to the way
in which, in setting the price control, the Authority “acknowledged” that
National Grid would face stranded costs as a result of stranding through
reduced meter costs. They sought consultees’ views on (a) the likely scale
of stranding as a result both of divergence of replacement values from
RAV-values and of competition and (b) what elements of stranded meter
costs should be compensated and how. The document does not indicate that
the Authority thought that the price control settlement was the last word
on the matter. In our judgment, the correspondence and meeting notes all
point to the fact that the Authority did recognise, despite the bargain
struck in the 2002 price control, that National Grid could legitimately
impose early replacement charges in its commercial contracts in order to
recover some of its sunk costs. National Grid understood this to be the
case and acted accordingly.
215. We also accept
National Grid’s point that it believed that it had the support of the
Authority in trying to slow down the replacement of legacy meters in order
to avoid the disruption to customers caused by a programme of accelerated
meter replacement. We do not accept that the Authority’s concern was
limited to a very rapid programme of replacement or “hell for leather
replacement” as Ms Frerk put it. In her oral evidence (Transcript, Day 6,
p.15) she described the concern of the Authority in the following
terms:
“[The Director of Supply’s] focus
was very much on “What were the consumer groups going to be saying about
this, and how would it play?”. He had the team that managed consumer
complaints coming to Ofgem. So, his focus was going to be, naturally, a
short term one – if there are pictures in the Press of piles of unused
meters, or a Mrs Smith saying “I took the day off work and I had to take
it off again six months later to have an identical meter fitted”. So, his
concerns would have been about the immediate impact on
consumers”.
216. Even if some of the
Authority’s senior management believed it was beneficial to replace
working meters in the short term to push National Grid to reduce its
prices, that was not the message that came across from the Authority to
the industry participants. The industry understood from their discussions
with the Authority that the Authority’s concern about the public
perception of waste and inconvenience arising from opening up this market
was more general than that. Again, National Grid interpreted this as a
reason why the Authority would not object to National Grid and the gas
suppliers |
||
|
||
81 |
||
|
||
|
||
putting in place a contract which
spread replacement over a longer period than might otherwise
occur.
217. We reject the
criticisms levelled at National Grid in the Decision that the company did
not discuss the introduction of PRCs openly and frankly with the
Authority. We have seen documents that were supplied to the Authority over
the period clearly describing the key ingredients of the Legacy MSAs, for
example a letter of 16 December 2002. In September 2003 National Grid sent
to the Authority a six page summary of the terms of the Legacy and N/R
MSAs setting out very simply and accurately how the contracts worked. The
Authority’s assertion that these were provided to the Authority for a
different regulatory purpose and not for formal competition law clearance
is unconvincing in this case. The recipient of the summary document was in
fact someone who had been involved in the discussions at the end of 2002
and had, indeed, been the author of the note sent to the Management
Committee in February 2003 recommending that the Authority continue to
monitor the development of the proposals to ensure that the best interests
of customers are served.
218. This is not to say
that sectoral regulators are in all cases required to step in and sound
some warning bells on competition grounds if they see market developments
taking a worrying turn. Neither are we saying that if a company sends a
draft contract out of the blue to an official within the regulator it can
then claim to have tacit approval if the regulator does not take action.
But the Authority was closely involved in and concerned about the roll out
of the RGMA project from start to finish and there were internal meetings
of the Authority at which National Grid’s proposals for its contracts with
the gas suppliers were discussed in detail. In our judgment, the history
of the discussions in the particular circumstances of this case merits a
significant reduction in the fine.
219. We have considered the
other points in mitigation raised by National Grid, for example that this
case raised a novel point and that the Authority’s case against National
Grid has changed during the course of the investigation. We also bear in
mind that we have arrived at different conclusions from the Authority on a
number of minor issues in the case, for example with regard to the effect
of the Legacy MSAs on the roll out of smart |
||
|
||
82 |
||
|
||
|
||
meters. However, none of those
points affects, in our judgment, the level of the fine to be
imposed.
220. Taking all these
points into account, the Tribunal has concluded that a fine of £30 million
properly reflects the seriousness of the infringement and the mitigating
factor arising from the Authority’s involvement with the development of
the Legacy MSA.
221. So far as the
directions given by the Authority are concerned, the operative part of the
Decision (other than the penalty) reads as follows:
“…THE AUTHORITY:
1.
Finds that, contrary to Chapter II of the Competition Act 1998 and
Article 82 of the EC Treaty, NG has abused its dominant position in the
market in Great Britain for the provision of domestic-sized gas meters by
including in the long-term meter supply arrangements (the MSAs) the Take
or Pay charges and the Premature Replacement Charges;
2.
Orders that NG put an end to the infringement identified in
paragraph 1 above;
3.
Orders that NG shall refrain from engaging in conduct having the
same or equivalent exclusionary effect as the infringement identified in
paragraph 1 above;
4.
Orders that NG shall as soon as reasonably practicable, but in any
case within ninety (90) days of the date of this decision, communicate to
the Authority all the measures that it has taken under paragraphs 2 and 3
in sufficient detail to enable the Authority to assess NG's effective
compliance with this decision, including these directions;”
222. National Grid objects
to the order in paragraph 3 that the company refrain from engaging in
conduct having the same or equivalent exclusionary effect. We do not agree
that this form of wording is unacceptably vague or inappropriate. That
wording is frequently used in competition cases both in the United Kingdom
and in Europe and is designed to ensure that the infringing undertaking
cannot avoid the effect of the order by engaging in behaviour which is
slightly different in form from that condemned but the same in economic
effect.
223. However, we agree with
National Grid’s criticism of the Decision that it does not make clear
whether the infringement found extends to the N/R MSA as well as the
Legacy MSA and if so, why. In its Defence the Authority say that paragraph
1 of the operative part of the Decision is clearly a reference to the
Legacy MSAs and that, since the N/R |
||
|
||
83 |
||
|
||
|
||
MSAs do not include Take or Pay
charges, it would nonsensical to regard the sentence as including the N/R
MSAs. Yet the Authority also say that there is nothing confusing or
inaccurate about saying that National Grid has abused its dominant
position by entering into the Legacy MSAs and the N/R MSAs even though
there is nothing in the Decision to suggest that, taken alone, the
Authority consider the N/R MSAs to be abusive.
224. We find that it is
indeed confusing and inaccurate to say that National Grid has committed an
abuse by entering into both the contracts even though there is nothing in
the Decision which identifies what is wrong with the N/R MSAs. We do not
agree with the Authority that it is artificial to divorce the assessment
of the Legacy MSAs from the N/R MSAs. They are two entirely separate
contracts with different terms. The outcome of this appeal is that
National Grid will now have to renegotiate its contractual arrangements
with the gas suppliers. It is unsatisfactory for the parties to be left
uncertain as to whether the N/R MSA also needs to be renegotiated to bring
National Grid into compliance.
225. In our judgment, the
Decision does not contain any adequate reasoning to support a finding that
the terms of the N/R MSA infringe the Chapter 2 prohibition of the 1998
Act or Article 82 EC. There is nothing to suggest that the payment
completion arrangements in the N/R MSA suffer from the same defects as
those in the Legacy MSA. It is true that meters which are replaced by
National Grid in the course of a maintenance visit are then covered by the
N/R MSA but we do not consider that this link of itself means that the N/R
MSA is unlawful. We would therefore make it clear that the finding of
abuse is limited to the terms of the Legacy MSA.
226. National Grid also
objects to the time limit set by the Authority for its compliance in
paragraph 4 of the operative part of the Decision. We agree with National
Grid that the 90 day deadline is unrealistic in this case given the
complexity of unravelling the Legacy MSA contracts with several different
counterparties. But National Grid must comply with the directions as soon
as practicable and report to the Authority on their progress within 90
days. |
||
|
||
84 |
||
|
||
|
||
227. Finally, we note that
the Authority refers in paragraph 6.64 of the Decision to the possibility
that National Grid could have sought formal guidance from the Authority on
the MSAs. Whether or not such formal guidance is now sought by National
Grid we would expect the Authority to become fully engaged with the
process of changing these contracts to bring them into line with the
competition rules. It is most important that the restriction on
competition resulting from the offending provisions of the Legacy MSA is
lifted as quickly as possible.
IX. CONCLUSION
228. We mentioned at the
outset of this judgment (paragraph [32]) that the Notice of Appeal in this
case ran to some 300 pages. Paragraph 6.49 of the Tribunal’s Guide to
Proceedings (October 2005) notes that even in complex and difficult cases
“a notice of appeal above the range of 50 to 75 pages should be regarded
as exceptional”. Unfortunately the substantial length of the Notice of
Appeal seems to have set the benchmark for the amount of written material
produced subsequently by the parties including lengthy skeleton arguments
and supplementary submissions, a number of notes handed up during the
course of the 11 day hearing (which one counsel described as an
‘avalanche’) and further voluminous written closing submissions. We
recognise that limiting the hearing to 11 days meant that counsel were
expected to compress their oral argument and that some of the notes handed
up were in answer to queries raised by the Tribunal or to cover points
which there was no time to cover orally. We have referred at a number of
places in this judgment to a considerable range of points that we have not
found it necessary to resolve. This judgment would have been substantially
longer if we had described and dealt with every point raised. This case
illustrates the importance of the parties focusing on the real issues in
the appeal and limiting the exploration of peripheral issues.
229. In the light of the above reasoning, the Tribunal
unanimously:
(a) dismisses National Grid’s
appeal against the finding that the Below Line Rentals and the Premature
Replacements Charges included in the Legacy MSAs constitute an abuse by
National Grid of its dominant position, contrary to the Chapter 2
prohibition of the 1998 Act and Article 82 EC; |
||
|
||
85 |
||
|
||
|
||
(b) restricts paragraph 1 of
the operative part of the Decision to refer to the Legacy MSAs
only;
(c) decides that the
penalty imposed on National Grid should be varied and the Decision set
aside to that extent. We fix the penalty imposed on National Grid at £30
million. There will be interest on the penalty to run, subject to any
further submissions the parties wish to make, at 1 per cent above the Bank
of England base rate from the date set for the payment of the penalty in
the Decision, namely 21 May 2008, until payment or judgment under section
37(1) of the 1998 Act;
(d) sets aside and varies
paragraph 4 of the operative part of the Decision and orders National
Grid, as soon as reasonably practicable, to notify the Authority of all
the measures that it has taken to comply with the Decision and in any
event to notify the Authority within 90 days of the progress it has made
in this regard. |
||
|
||
Vivien Rose
Professor Paul Stoneman
David
Summers |
||
|
||
Charles Dhanowa
Date: 29 April 2009
Registrar |
||
|
||
86 |
||
|
||