SHERIFFDOM OF GRAMPIAN HIGHLAND AND
A2457/05
|
|
JUDGEMENT
of |
|
|
in the cause |
|
|
ANNE CAMPBELL
|
|
|
Pursuer |
|
|
against |
|
|
|
|
|
Defenders |
The court having reconsidered the
cause, finds the following facts proved.
1. The pursuer is Miss Anne Campbell who
resides at and has resided at for the last 15 years
2. The defenders are a local authority
and as such are proprietors and landlords of
"In this agreement the
word repair and repairs includes any work necessary to put the house into a
state which is wind and water-tight, habitable and in all other respects
reasonably fit for human habitation."
Clause 5.3 reads as
follows.
"During the course of
your tenancy we will carry out repairs or other work necessary to keep the
house in a condition which is habitable, wind and water- tight and in all other
respects reasonably fit for human habitation ... all repairs will be done to the
standard of a reasonably competent contractor using appropriate material".
Clause 5.2 of said
agreement reads as follows.
"If we cause damage to
the house or your property in connection with inspections, repairs or
improvements ... we may reinstate the damage or compensate you for your losses".
4. Between February and October 2003, the
defenders embarked on a major repair and protect programme on the high-rise
blocks erected in the Seaton area of
5. The work involved repairing spalled
concrete from the "bison" panels which make up the external cladding of and
outside face of the high-rise block and thereafter coating the outside face and
exposed edges of said panels with an impermeable membrane.
6. The system of construction using bison
concrete panels provides for panels to be placed one on top of the other with
an overlap on the horizontal joints.
There is no overlap on the vertical joints and the bison panels are laid
side by side. In the vertical joints
there is provision to stop the penetration of air and water by means of an air
baffle and a neoprene strip between the vertical edges of the panels and on the
internal face of said panel joints light duty cement pack is applied by hand and
dry.
7. Said neoprene strip is not
everlasting. Said dry cement pack has no
structural strength.
8. Prior to treating the slabs the
defenders were advised that cleaning by way of high pressure water jetting was
required.
9. The defenders instructed an independent
contractor to carry out high pressure washing of the whole building. There was no detailed evidence of the PSI
applied to the external face of the panels during this cleaning process. The work of high pressure jet washing was
commenced in about March 2003. The
system of access to the high points of the building used by the contractors was
a platform hoist system. In order to
secure the platform hoist system it was necessary to
drill holes in the panels to hold restraining bolts which would be in place
only for the duration of the work being carried out.
10. Two holes were bored in the panel forming
the external south wall of the pursuer's flat.
In about early March high pressure jet washing took place on the
external walls of the pursuer's flat.
The following day the pursuer found pools of black water on the parquet
floors of her living room and the backs of two sofas which had been touching
the internal south wall were also found to be damp.
11. The pursuer formed the view that water
had penetrated her flat as a result of the remedial works being carried out and
in particular she suspected that the holes drilled in the wall on the outside
to facilitate the use of a hoist system had allowed the water to come in.
12. The
holes drilled did not allow the water to penetrate into the pursuer's flat.
13. The high pressure jetting of, or in close
proximity to, the vertical corner joint between the south and west external
walls of flat did create an ingress of water to the
pursuer's flat.
14. The
pursuer was not immediately aware of the extent of the ingress of water.
15. Some weeks later the pursuer became aware
of mould patches forming on the internal walls and on the back of the sofa
covers.
16. The saturation of the plaster behind the
pursuer's wallpaper on the south and west walls of the living room did not show
through that wallpaper.
17. Some two months later part of the paper
was stripped off and revealed large wet patches of plaster and also some "tide
marking" where previously saturated plaster had dried back to the still wet
southwest corner. It can be reasonably inferred that the plaster on the south
and west internal walls became saturated for the full height of the room
spreading from the southwest corner.
18. Mould spores are to be found in normal
atmosphere. Mould spores develop in damp
conditions.
19. Damp conditions can arise in a room or
portion of a room where there is little circulation of dry air. Air which is carrying moisture will deposit
that moisture on cold surfaces when the temperature of the surface in contact
with the air is below the dew point of that air. That cold surface will thus become damp or
damper.
20. The degree of moisture borne in the air
in any room will depend on the amount of moisture available to be absorbed by
air and the temperature of the air.
21. Mould did form on some of the surfaces of
the pursuer's living room which were less exposed to air movement. In these areas condensation occurred unknown
to the pursuer as the air in her living room had become much more moist as the
result of evaporation from the wet plaster of the south and west walls. During
the first half of 2003, the general lifestyle of the pursuer had not
changed. She had no problem with mould
prior to March 2003. She has had no
problem with mould since the plaster dried out.
22. The condensation on her walls and the
subsequent mould damage was not caused by the pursuer's failure to adopt an
appropriate standard of house maintenance.
The mould arising from the condensation was a direct result of plaster
having become saturated.
23. Saturation of the plaster was caused by
water from the high pressure jetting hoses entering the vertical joints,
penetrating the vertical neoprene strip and dry cement pack between the slabs forming
the southwest corner of the pursuer's flat.
It was reasonably foreseeable that a high pressure water jet directed
into the vertical seams between the slabs would penetrate the neoprene strip
and dry cement pack.
24. The defenders failed to keep the property
wind and water-tight during the cleansing operation being carried out on their
instructions in March 2003.
25. Accordingly, the defenders are in breach
of Condition 5.3 of the contract of lease.
The defenders failed to keep the house wind and water-tight (c.f.
5.7). The defenders failed to keep the
property wind and water-tight particularly during the cleaning operation being
carried out on the instructions of the defenders in March 2003.
26. Accordingly, the defenders are in breach
of their obligations in terms of said agreement. As a result of said breach the pursuer has
suffered loss.
27. The loss sustained by the pursuer has
been agreed between the parties to be reasonably stated at the sum of
£2,900.
28.
Accordingly,
finds it established that the pursuer has sustained loss as a result of the
defenders' breach of contract and is entitled to be compensated for that
loss. Therefore upholds the pursuer's
pleas-in-law 1 and 2; repels the defenders' pleas-in-law 1, 3, and 4, upholds
the defender's plea-in-law 2. grants decree for
payment to the pursuer by the defenders of the sum of £2,900 and appoints
parties to be heard on the question of interest and expenses on
NOTE
The evidence on this matter came
essentially from four witnesses, the pursuer herself and Keith Moir, a
buildings surveyor, Mike MacIntosh who is the building consultant employed by
the defenders, Alan McPherson an Energy Assessor employed by the defenders.
I had no difficulty in finding all
the witnesses credible but I was more persuaded by the conclusions of Keith
Moir. Mr Moir is a qualified buildings
surveyor experienced in tracing causes of damp in buildings. The defenders' witness who viewed the
property after complaints by the pursuer were probably quite right to conclude
that the damage complained of was caused by condensation. The real issue is why there should be condensation
in this particular flat.
I have no doubt that both Mr
McPherson and Mr McIntosh in their experience of looking after Council
properties have often come across properties where lack of ventilation has
allowed a build up of humidity in internal air and subsequent condensation and
mould damage. When they examined the
pursuer's flat they were seeing some signs they associated with bad
housekeeping. There was also indication
of good housekeeping but the attention was focussed on the former. In addition the pursuer had made her own
diagnosis and attributed the extra water in her house to the holes drilled in
the wall to allow the fixing of bolts to restrain the cables of the hoist
system which was being used by the contractors involved in high pressure jetting
of the building.
There was no evidence from any of the
experienced or qualified witnesses to support that diagnosis and the defenders'
employees were correct to dismiss it as a probable cause of the ingress of
water moisture to the pursuer's flat.
They then reached a conclusion based
on rejection of the pursuer's theory and their own experience of complaints of
mould in other properties. Mr McIntosh
was of the view that there was no correlation between the works being carried
out and the damage. He examined the horizontal
joints and the window frames and eliminated them from suspicion as being a
source of ingress of water. Intriguingly
while Mr McIntosh was aware of the detail of the construction method he did not
appear to consider the extent to which the weather proofing of the vertical
joints which had no concrete overlap might have been affected by the high
pressure hosing. Mr McPherson did not
have the technical building experience to be able to comment in detail. In my view the defenders' witnesses'
explanation is based on insufficient information and their conclusion is
therefore flawed.
I accepted the pursuer's explanation
that she had never had a condensation problem in any of the fourteen years of
prior occupancy of the flat nor in the years since the
walls had been stripped of paper and allowed to dry out.
The examination by Mr Moir revealed
information that the plaster of west and south internal walls had been
saturated. The tide-marking observable
after the paper had been stripped off showed that the walls had dried back
towards the south western corner. At the
time of this examination the walls were still damp at that corner.
The construction of the external
walls was such that the vertical faces of the cladding panels known as bison
slabs abutted one to another leaving a small gap. That gap was filled by the insertion of
neoprene baffle to prevent wind and rain penetrating. Neoprene is not everlasting and deteriorates
with age. The internal face of the
neoprene packed gap was dressed with dry pack cement. Dry pack cement has no structural strength.
The balance of probability favours
the conclusion that at some point in the jetting process the high pressure jet
had been directed into vertical joint and not been repelled by the neoprene
baffle or the dry pack and water from the jetting process had penetrated from
the outside to the inside of the slabs and then been absorbed by the internal
plaster walls.
The paper decorating the walls of the
living room - the south west room of the flat - disguised the fact that the
plaster beneath it had become saturated.
The saturation caused the moisture content of air in the room to rise
and created conditions in which mould spores could develop. The dampness in the sofa coverings was
probably caused by natural capacity of cloth to absorb and a "wicking" effect
when the sofas were touching the walls.
Parties were agreed on what
compensation should be paid to the pursuer if the pursuer were to succeed in
establishing a liability in the defenders.
The defenders plainly failed to keep the pursuer's flat "wind and
water-tight" and the pursuer has succeeded in proving liability for damage.
I accordingly have decerned for the
agreed damages at £2,900 and continued the hearing to allow parties to address
me on interest and expenses.
The issue of negligence was barely
touched upon in submissions which reflects the absence
of any attempt to establish negligent behaviour at the proof and I have simply
upheld the defenders' second plea to recognise that element of the pursuer's case
on record as not proven.