Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
JAMES MILLER AGAINST J.W. WHEATLEY AND SON LTD AND ANOTHER [2023] ScotCS CSOH_84 (28 November 2023)
URL: http://www.bailii.org/scot/cases/ScotCS/2023/2023_CSOH_84.html
Cite as:
[2023] ScotCS CSOH_84,
[2023] CSOH 84
[
New search]
[
Printable PDF version]
[
Help]
OUTER HOUSE, COURT OF SESSION
[2023] CSOH 84
PD515/22
OPINION OF LORD MALCOLM
In the cause
JAMES MILLER
Pursuer
against
J.W. WHEATLEY AND SON LTD AND ANOTHER
Defenders
Pursuer: B Fitzpatrick; Digby Brown LLP
Defenders: J Gardiner; Kennedys Scotland
28 November 2023
Introduction
[1]
James Miller raised an action for the payment of damages arising out of a workplace
accident against three parties. The action was abandoned against the first defender, namely
Algo Blairgowrie Ltd (Algo). Subsequently and after a proof decree was sought against only
the third defender, a partnership named JW Wheatley and Son (Wheatley). (The other
defender is JW Wheatley and Son Ltd.) Much of the relevant background is not in dispute.
2
The background circumstances
[2]
Algo was constructing a building for the greenkeeper's maintenance equipment and
associated facilities at Dunbarnie Golf Links, Upper Largo, Fife. It sub-contracted the
electrical works to Wheatley which in turn sub-contracted part of those works, namely the
installation of solar panels on the roof, to MMS Building Services Ltd (MMS). Mr Miller is a
solar panel engineer and the sole director of MMS. He was directly responsible for the
sub-contract and for fitting the panels. He submitted a risk assessment and method
statement in respect of their installation to Algo. It identified adverse weather as a hazard.
[3]
On 21
February 2020 Mr Miller attended at the site with an employee, namely
Mr Owen Cook, to fit panels to the roof. No-one from Wheatley was present. Access to the
roof was gained using equipment belonging to Algo. Because of adverse weather the metal
roof was wet. As a result Mr Miller slipped and fell. He sustained a fracture to the left
femur and required surgery. (The parties have agreed the amount of damages to be paid if
Wheatley is found solely liable for the accident at £38,500.)
The written pleadings
[4]
In the written pleadings for Mr Miller it is claimed that one of the Wheatley partners,
namely David Wheatley, pressured him to complete the work as soon as possible. Wheatley
failed to carry out a risk assessment into the solar panel work. If it had, the obvious risk of
slipping when the roof was wet and appropriate mitigation measures, such as stopping
work, would have been identified. Reference is made to various workplace and health and
safety regulations relating to risk assessment, management, working at height, and safe
place of work. Wheatley is said to have failed in its duty of reasonable care toward
3
Mr Miller. On the hypothesis that Algo instructed Wheatley that the site was to be closed,
there was fault and negligence in that this instruction was not followed.
[5]
Wheatley aver that MMS was a specialist sub-contractor not under Wheatley's
control. There was no deadline for the work. The risk of working on the wet roof would
have been obvious to Mr Miller. It was identified as a hazard in the risk assessment
provided by him to Algo. He was solely responsible for the accident. Wheatley denies
liability, failing which there was substantial contributory negligence.
James Miller's evidence
[6]
Mr Miller confirmed that MMS were asked by David Wheatley to carry out the solar
panel work. It had been made clear that the site was on a tight timescale and that
Mr Wheatley wanted to get the work finished. Mr Miller felt under pressure to make
progress. Some preparatory work was done on the roof on 20
February 2020. Early in the
morning of the 21
st
, which was a Friday, Mr Miller telephoned David Wheatley from the site
and told him there was light drizzle. David Wheatley did not dissuade him from going on
the roof to fix the panels. He said that they needed to get the job finished. Mr Miller
appreciated that to go onto the metal roof was hazardous. It was slippy and felt unsafe.
However he decided to do the job. When asked why, Mr Miller said that it was because
Mr Wheatley wanted it finished. Having fixed some panels, in order to obtain something
from the van he went down the sloping roof at an angle. He slipped and fell. He takes it
that the slip was caused by the wetness. While he did not fall off the roof, he had broken his
hip.
[7]
When completing the risk assessment Mr Miller used a template. In hindsight he
recognises that he should have reviewed its terms. Rather than "low", the risk of working
4
on the roof should have been categorised as "medium", perhaps increasing to "high" when
there was rain.
[8]
In cross-examination Mr Miller accepted that if he thought it unsafe he should not
have done the work, however they wanted it completed. He was aware of pressure from
both Algo and Wheatley. He stressed that during the telephone call that morning
David Wheatley did not tell him to stop the job. He accepted that he could have decided not
to go on the roof and that it was his decision to do so. He denied that the rain was more
severe than drizzle. The conditions were not windy otherwise he would have stopped
work. There were Algo workers but no Wheatley employees on the site that day.
[9]
In re-examination Mr Miller stated that if he had been told that Algo had closed the
site he would not have gone onto the roof.
Barbara Miller's evidence
[10]
Mrs Miller assists with administration for MMS such as drafting invoices and
certificates for completed works. Her husband deals with contract documents. She had
spoken to David Wheatley on the phone and there were emails concerning the golf links
work. For several days before the accident Mr Miller was stressed and feeling under
pressure. Mr Wheatley kept asking him to get the work finished.
The evidence of Owen Cook
[11]
Mr Cook is a retired HGV driver. He was employed as a labourer by MMS for the
solar panel work. On the Friday the weather was "dampish". They were later in arriving
and, having been to see the site agent, Mr Miller said they would wait in the van till the
weather cleared and it was safe to go on the roof. There were two people working in the
5
building who were nothing to do with them, and there were others on golf course duties.
He heard but did not see the fall. He knew that Mr Miller had slipped. It had been chilly
the night before but it was a fine day. When asked about precipitation Mr Cook said that
one has to wait till the roof was totally dry - one cannot take any chances. It was drying out.
[12]
The "boss man" wanted the job finished and asked Mr Cook whether he could attend
the following day. If it was fine with Mr Miller it was fine with him. There would be two
electricians and two workers. The following day, which was a Friday, the boss man,
Mr Cook and the others had the job finished. Mr Cook was surprised when told that the
accident occurred on a Friday. Mr Cook would not normally work on a Saturday unless he
had to. The person on the roof was a Mr Wheatley. He was the "boss man".
[13]
In cross-examination Mr Cook stated that the night before the accident and in the
early morning there had been heavy rain. When asked if there were strong winds, he
replied - yes, normal winds.
The evidence of James Latto
[14]
Mr Latto is a construction site manager employed by Algo. That February he was
responsible for the Dunbarnie Links site and one other. On the Thursday the weather was
becoming stormy. Adverse weather was coming. He decided that no one should go on the
roof on the Friday. Over the telephone he told David Wheatley not to instruct people to
work that Friday. He told Algo employees that there was to be only internal work. He
expected other workers to be told this. On the Friday he was in Perth. The weather was
bad. He was shocked that someone had gone on the roof. Along with others
David Wheatley finished the solar panel installation the following week. He could not see
why there would be time pressure to finish it.
6
[15]
In cross-examination Mr Latto confirmed that before the accident Mr Miller gave him
the MMS risk assessment for the solar panel work. As site manager it was his, not
David Wheatley's job to ensure the site was closed. During re-examination in a couple of
leading questions Mr Latto was asked if he expected David Wheatley to comply with the no
external working instruction and communicate it to workers who might be on the roof. He
replied in the affirmative.
David Wheatley's evidence
[16]
David Wheatley was the only witness led for the defence. He was the partner
running the business from day to day. It lacked accreditation to fit solar panels. Wheatley
sub-contracted that work to MMS. He saw the MMS risk assessment before the accident. It
was up to MMS to decide how the work would be done and carry out its own risk
assessment. There was no fixed date for the installation of the panels. The job was not time
sensitive. He did not put any pressure on Mr Miller to finish the work.
[17]
Mr Wheatley did not recall a phone call from Mr Latto concerning the anticipated
adverse weather on the Friday. He did not tell Mr Miller that no work was to be done that
day. Mr Wheatley was in his office in Alyth. No Wheatley employees were on site. He had
no idea as to the weather at the golf links until he attended after the accident. When asked
about a phone call early in the morning from Mr Miller, Mr Wheatley said that he did not
recall it. He did not hear from Mr Miller and did not know where he was until told of the
accident. It was Mr Miller's choice to install the panels on the Friday. It was his decision.
[18]
In cross-examination Mr Wheatley said that some time later Mr Latto got in touch
and told him that he did speak to him on the Thursday about closing the site on the Friday.
Having received a letter from Algo's solicitor Mr Wheatley replied by letter dated
7
11 February 2022 stating that Mr Latto did communicate with him and Mr Miller saying that
the site would be closed due to the expected poor weather. He wrote this in haste thinking it
was the right thing to do. However he does not recall the conversation. He was referred to
the admission in Wheatley's pleadings. It was the main contractor's job to control what
happens on the site.
[19]
When pressed as to the call from Mr Miller early on the Friday and shown a record
of his mobile calls at the time which appeared to confirm it, Mr Wheatley was not saying
that it did not happen, just that he does not recall it. He had not checked his mobile phone.
He had removed Mr Miller from it. He denied that the work was completed on the
Saturday. Having looked at photographs on his phone, he could say that the panel work
was completed on 27
February. He worked on it alongside Mr Cook.
The submissions for James Miller
[20]
There was no dispute as to the immediate circumstances of the accident.
David Wheatley as Mr Miller's superior in the chain should have passed on the site agent's
instruction not to work on the roof on the Friday. The main submission was that the
relationship between Wheatley and Mr Miller was akin to employer/employee. MMS was
not an independent contractor. Mr Miller could be categorised as a "worker" for Wheatley.
Not all workers will be employees. Recent case law has blurred the distinction between
employees and independent contractors. While there was no pay slip it was necessary to
look at the underlying situation. Mr Miller was there to get the solar panel aspect of the
Wheatley work completed. Reference was made to Uber BV v Aslam [2021] ICR 657,
Makepeace v Evans Brothers (Reading) [2001] ICR 241, Pimlico Plumbers Ltd v Smith [2018]
8
[21]
On the issue of Wheatley's alleged control over Mr Miller's operations reliance was
placed on the following factors. Mr Miller did not supply equipment allowing access to the
roof. It did not matter that it was provided by Algo. While Mr Miller picked Mr Cook as his
labourer, after the accident he remained involved working with David Wheatley. The work
was done on the Saturday outside Mr Cook's normal working hours, something which was
an extraordinary instruction showing control over someone not your employee. Mr Cook
called him the boss man. Mr Cook wrongly thought the accident happened on the
Thursday. He said that the work was completed the day after the accident, which must
have been the Saturday.
[22]
Much of the submission focussed on various passages in the judgment In Uber,
particularly at paragraphs 91/92, 98, and 126. Counsel clarified that it was not asserted that
liability flowed from the various regulations cited; however, the policy underpinning the
decision in Uber was to ensure that vulnerable groups were protected. Common law
protection equivalent to the contents of the regulations should be afforded to both
employees and statutory "workers", see section 230(3) of the Employment Rights Act 1996.
The common law and statutory duties were coterminous, Kennedy v Cordia
paragraphs 110/111. Reference was made to section 69 of the Enterprise and Regulatory
Reform Act 2013, the Management Regulations 1999, Allison v London Underground
[2008] ICR 719 at paragraphs 57/58, Makepeace at paragraphs 12/13, and to various passages in
Victoria Rose.
[23]
On a realistic view of matters the relationship was of the employer/employee type,
triggering a duty of reasonable care. This included telling Mr Miller not to go on sloping
metal roofs in wet weather. An employer owes a duty to protect his employees from their
own stupidity. Both Mr Wheatley and Mr Latto said there was no urgency to complete the
9
work. Simply on the neighbourhood principle Mr Wheatley should have told Mr Miller that
the site agent had decided there should be no external work that day. Had he done so,
Mr Miller said he would not have gone on the roof. Wheatley should have carried out a risk
assessment of the solar panel installation operation. There had been no engagement with
the Work at Height Regulations 2005. The roof was clearly an unsafe place of work unless
suitable precautions were taken.
[24]
It was accepted that there was also a duty on Mr Miller to take care for his own
safety, but it was not a matter of 100% liability upon him. There was nothing special about
independent contractors such that others did not owe them a duty of care, especially in the
context of a construction site. The drive is towards co-operation and improved standards of
health and safety. It appeared that Mr Wheatley took the view that he need not tell
Mr Miller anything and that it was up to him to look after himself. He was more
blameworthy than Mr Miller for the severe injury caused by the accident.
The submissions for Wheatley
[25]
Mr Miller worked for and was the face of MMS, who were classic independent
contractors hired to carry out a discrete piece of specialist work. The factors relied on to
support the proposition that the relationship between Wheatley and Mr Miller was akin to
employer/employee were unconvincing. Mr Cook only helped to complete the work
because Mr Miller allowed it. It was of no significance whether this happened on the
Saturday or later the following week, however Mr Cook insisted it was not done on the
Saturday. MMS brought the solar panels to the site. It mattered not that it used Algo
equipment to gain access to the roof. Even if Mr Miller's evidence of the work being on a
tight timescale and needing to get finished is accepted, it is not evidence of control of MMS
10
by Wheatley. If Wheatley did control MMS, David Wheatley could have ordered Mr Miller
to go on the roof that day. The most Mr Miller said was that he did not dissuade him.
[26]
None of the authorities relied on assist Mr Miller. The transportation service
provided by Uber drivers was "very tightly defined and controlled by Uber",
paragraph 101. Their remuneration was fixed by Uber, paragraph 94. The present case was
wholly different. Furthermore Mr Miller need not rely on section 230(3) of the 1996 Act for
his employment rights - he can look to MMS.
[27]
Makepeace was not authority for the proposition that even if Mr Miller was an
independent contractor, Wheatley might still owe duties to him under the neighbourhood
principle. It turned on the particular combination of factors set out at paragraph 14 of
Holman J's judgment. Here there are no circumstances pointing to a duty of care for the
safety of Mr Miller. Mr Wheatley did not direct Mr Miller to work on the roof.
[28]
There is no factual or legal basis for a duty on Wheatley to risk assess the solar panel
operation. MMS was responsible for how the work was done and for managing the risks.
On any view there was no obligation on Wheatley to carry out another risk assessment. The
accident was not caused by any gap in the risk assessment. It stated that adverse weather
conditions should be taken into account when working at height. The safety risk that
morning was apparent and had been identified by Mr Miller yet he chose to begin the work.
On his own evidence he decided against the obvious mitigation, namely delaying until it
was safe to install the panels.
[29]
As to the case based on the site closure, Algo were in charge of the site. Any
criticism should be directed to them. In the absence of record for it, the court should not
entertain the argument that Mr Wheatley should have passed on the detail of a telephone
call from Mr Latto. In any event Wheatley was not in control of when MMS did the work.
11
MMS in the shape of Mr Miller was responsible for managing the work and the risks. He
was an experienced solar panel installer. He had risk assessed the work. Mr Wheatley did
not disobey Mr Latto by instructing roof work that day. Mr Miller was on site and had all
the information he needed to make his own decision. The problem was that he ignored his
own risk assessment and, on his own admission knowing it was unsafe to do so, began the
work.
[30]
If liability is established, contributory negligence should be at the top of the range.
Analysis
[31]
In certain circumstances it can be difficult to decide whether a claimant was an
employee to whom a duty of care was owed or an independent contractor. This is not such
a case. MMS were specialist independent contractors hired by Wheatley under a contract for
services to perform the solar panel aspect of the electrical work they had agreed to provide
for Algo, the main contractors in the construction project. Mr Miller was employed by
MMS, not Wheatley. It was MMS, not Mr Miller, that supplied services to Wheatley.
Nonetheless it was submitted that there were particular factors in play which supported the
proposition that he was Wheatley's "worker" in terms of section 230(3)(b) of the 1996 Act.
Just as each Uber driver worked for Uber under a worker's contract and so could look to
Uber to satisfy certain employment rights, it was contended that Mr Miller was entitled to
expect that Wheatley would comply with the provisions of certain regulations and exercise
reasonable care for his safety when he was installing the panels.
[32]
The difficulty with the submission is that there is no comparison between the
circumstances of the present case and the position of Uber and the Uber drivers. There are
three parts to the definition of a worker's contract under section 230(3)(b). First there must
12
be a contract whereby an individual undertakes to perform work or services for the other
party; secondly an undertaking to do this personally; and finally a requirement that the
other party is not a client or customer of any profession or business undertaking carried on
by the individual. Mr Miller did not undertake "to do or perform personally any work or
services for" Wheatley. MMS agreed to install the panels. Mr Miller was working for
MMS - not for himself, and not for Wheatley. It was apparent that each Uber driver was
personally providing services as part of Uber's business undertaking, and hence could claim
the benefits under the Act. It cannot be said that Mr Miller was providing his services as
part of Wheatley's business. And even if Mr Miller had been self-employed, the argument
would fall foul of the statutory requirement that Wheatley was not a client or customer of a
business undertaking carried on by Mr Miller.
[33]
Wheatley enjoyed none of the elements of control or direction in respect of
Mr Miller's work which might create something akin to employment or common law duties
of care. In agreement with the submissions for Wheatley I consider that none of the factors
relied on by Mr Miller's counsel for a common law case are persuasive. Standing the
evidence on the point from Mr Latto and Mr Wheatley, and the absence of any explanation
as to why there was a tight deadline, I consider that Mr Miller exaggerated any pressure he
might have felt under to complete the work. In any event a customer's desire for progress is
not the same as the exercise of control and direction. Likewise it is of no moment that
Mr Miller used Algo equipment to gain access to the roof. And it matters not that Mr Cook,
an MMS employee was allowed to assist with completion of the work, even if that happened
on a Saturday outside his normal working hours. That said the weight of the evidence was
against it being done on the Saturday, a proposition which depended entirely on Mr Cook's
13
mistaken recollection that the accident happened on a Thursday. No-one spoke to the work
being done on a Saturday.
[34]
As to the events on the day of the accident I accept the evidence that there was an
early morning call from Mr Miller to Mr Wheatley. As with the telephone call from
Mr Latto, ultimately Mr Wheatley did not deny that this happened. However Mr Wheatley
did not attempt to exercise control over Mr Miller. The most that Mr Miller said was that
Mr Wheatley did not dissuade him nor tell him not to go on the roof. That is not surprising.
He was not employing Mr Miller and was not in charge of the site. It was not Mr Wheatley's
place to issue instructions to Mr Miller. If he had Mr Miller would have been entitled to
say - I am my own boss. I am on the site and no one there is trying to stop me. I can assess
the weather conditions and the state of the roof. I can decide whether I do or do not want to
carry out the work. If Mr Cook is to be believed, and I see no reason not to, they waited in
the van for some time for the weather to clear until the person in charge, namely Mr Miller,
decided that it was alright to set foot on the roof. In short, and as Mr Miller accepted, it was
his decision to work on the roof.
[35]
I accept that the previous evening there was a telephone conversation between
Mr Latto and Mr Wheatley in which the latter was told of the anticipated bad weather and
the intention to close the site at least regarding external working. However, and no matter
what Mr Latto's expectations might have been, Mr Wheatley breached no legal duty by not
mentioning that to Mr Miller. Nor was he under a duty to issue a similar instruction to
Mr Miller. He had no right or power to do so. He was not in charge of either the site or
Mr Miller. Unlike Mr Miller he was unaware of the actual conditions at the site. If Mr Miller
found the site open it was up to him what he did.
14
[36]
In submissions Mr Miller's counsel made nothing of the suggested pressure to finish
the job. On the contrary mention was made of the evidence from both Mr Latto and
Mr Wheatley that there was no timescale. This conflict in the evidence is not critical. Even if
Mr Wheatley was keen that the work was progressed quickly and made that apparent to
Mr Miller, it remained for Mr Miller to decide whether to work that day. Just as
Mr Wheatley had no power to issue orders, Mr Miller was his own free agent as to whether
he did or did not succumb to any pressure, real or perceived.
[37]
Mr Miller was aware that to walk on the sloping metal roof when it was wet was
hazardous, yet of his own volition he chose to do so. That was not because of any element of
direction or control by Wheatley sufficient to create the legal relationship on which the case
is based. None of the duties imposed by a contract of employment, nor anything akin to
such, lay on Mr Wheatley. No circumstances imposed a neighbourhood principle duty on
Mr Wheatley to take care for an independent contractor.
[38]
Taking Mr Miller's case at its highest on the evidence, it fails. Throughout he was an
employee of MMS who were classic independent contractors. There was no underlying
reality or particular features which created a responsibility resting on Wheatley for
Mr Miller's safety nor a liability for the accident. Mr Miller was not a subordinate and
vulnerable person requiring the statutory protection of section 230(3)(b) of the 1996 Act to
obtain rights against Wheatley. Having regard to the whole circumstances, in my view he
was solely responsible for the accident.
[39]
If this is wrong and Wheatley were in breach of a duty owed to Mr Miller, I consider
that the lion's share of the blame for the accident lies with his own decision to work on the
roof despite his view that it was unsafe to do so. On this hypothesis I would assess
Mr Miller's contributory negligence at 75%. However the overall result is that the action
15
fails and Wheatley and the other remaining defender are absolved of any liability in
damages.