Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
TILBURY DOUGLAS CONSTRUCTION LTD AGAINST OVE ARUP & PARNTERS SCOTLAND LTD [2023] ScotCS CSOH_53 (16 August 2023)
URL: http://www.bailii.org/scot/cases/ScotCS/2023/2023_CSOH_53.html
Cite as:
[2023] ScotCS CSOH_53,
2023 SLT 1047,
2023 GWD 33-274,
[2023] CSOH 53
[
New search]
[
Printable PDF version]
[
Help]
OUTER HOUSE, COURT OF SESSION
[2023] CSOH 53
CA117/21
OPINION OF LORD HARROWER
In the cause
TILBURY DOUGLAS CONSTRUCTION LIMITED
Pursuer
against
OVE ARUP & PARNTERS SCOTLAND LIMITED
Defender
Pursuer: MacColl KC, McKinlay; Brodies LLP
Defender: Dean of Faculty, Steel; Clyde & Co (Scotland) LLP
16 August 2023
The issue
[1]
This action concerns the development of a former railway yard located to the east of
Edinburgh's Haymarket station, and in close proximity to two railway tunnels running
between Haymarket and Waverley. Before the development could begin, the ground level
of the development site required to be lowered, by removing up to 6m of soil. This required
certain enabling works to be carried out, to ensure that the material could be safely
unloaded without compromising the integrity of the tunnels and in order that piling could
take place in their vicinity. In addition, the design of the enabling works required to ensure
2
that any movement of the tunnels would be predictable, and within a tolerance that
Network Rail would accept.
[2]
In November 2013, the purser was employed to carry out the enabling works. The
defender was appointed to provide related engineering services, including the preparation
of the Network Rail approved design. In this action, the pursuer complains that the
defender, in preparing the design for the enabling works for the north tunnel, was in breach
of its contractual and delictual obligations to exercise the relevant standard of care and skill.
It alleges that the defender's design adopted erroneous assumptions for the strength and
stiffness of tunnel brickwork, failed to take account of the likely presence of voids within
and behind the lining of the north tunnel, and failed to make allowance for the need for
annular and interstitial grouting to address those matters. As a result, the pursuer
complains, the defender's design required to be resubmitted with revised brickwork
characteristics and amended to include annular and full interstitial grouting of the north
tunnel, all at considerable additional expense to the pursuer.
[3]
The case called before me at a preliminary proof before answer restricted to the
question of prescription. It was conceded, on behalf of the pursuer, that it had suffered loss
and damage, for the purposes of section 11(1) of the Prescription and Limitation (Scotland)
Act 1973 ("the 1973 Act"), as at 27 November 2013, when the pursuer entered into the
enabling works contract in reliance on the defender's design. As at that date, the pursuer
argued, unbeknownst to it, materially more work was required in order to deliver the
enabling works, the cost of which it would be unable to recover from its employer. As a
matter of objective fact, therefore, and with the benefit of hindsight, the pursuer's contract
was, already on that date, worth less to it than it would have been but for the defender's
alleged breaches of duty.
3
[4]
The summons not having been served on the defender until 30 July 2019, by which
time the pursuer's rights would ordinarily have prescribed under the usual five-year
prescriptive period, the sole issue for proof was whether the start of that period should be
postponed on either of the following grounds. According to the pursuer, it should be
postponed until November 2014, at the earliest, since that was the date when it first became
aware, and could with reasonable diligence have become aware, that it had suffered loss
(section 11(3) of the 1973 Act). Alternatively, the pursuer argued, the whole of the period
between November 2013 and November 2014 should not be reckoned as part of the
prescriptive period, since it was throughout induced to refrain from making a claim by
reason of error, induced by words or conduct of the defender, which the pursuer could not
itself have discovered by exercising reasonable diligence (section 6(4) of the 1973 Act).
Preliminary matters
[5]
I heard evidence from four witnesses to fact. The pursuer lead Mr Tim Shepherd
(the pursuer's project director), Mr Robert Brindley (the pursuer's construction manager),
and Mr Michael Pratt (the pursuer's senior project manager). The defender led Dr Jeremy
Grant (an associate director of the defender, and the principal engineer involved in
providing engineering services to the pursuer). I also heard expert evidence from Mr Guy
Lance and Mr Alex Warrender. Unless specifically noted elsewhere in this opinion, I had no
concerns regarding the credibility and reliability of any of the witnesses, all of whom were
doing their best to assist the court.
[6]
The defender urged caution in relation to Mr Lance's evidence, based on alleged
selective reporting in his CV of his involvement in a previous case and his having already
been instructed by the pursuer to provide a report in relation to the enabling works (written
4
submissions, para 51.1). However, I was not informed of the circumstances of Mr Lance's
alleged earlier instruction, or the content of any report. As for the previous case referred to
in Mr Lance's CV, this related to a prosecution brought by the Health and Safety Executive
following the tunnel collapses in the Heathrow Express line. Mr Lance's alleged selective
reporting of his involvement in that case had been the subject of comment by Wilcox, HHJ,
when discussing Mr Lance's expert evidence in a later case (Thames Water Utilities Ltd v
concerning Mr Lance's CV should be seen as collateral to the court's reservations regarding
the substantive merits of Mr Lance's evidence (at least in part (para 139); other parts it
accepted without difficulty (paras 141, 142)). By contrast, I had no concerns regarding the
substance of Mr Lance's evidence, at least insofar as it was relevant to the present
proceedings.
Notes of objections to evidence
[7]
As is usual in commercial actions, written statements lodged in advance of the
commencement of the proof were to be taken as representing witnesses' evidence in chief.
Each party lodged notes of objections to certain passages in the witness statements lodged
by the other. Parties invited me to admit all of the evidence subject to relevance and
competency.
[8]
The defender's note of objections, extending to some 50 paragraphs, objected to the
admissibility of certain passages of evidence to be found in the statements of
Messrs Shepherd, Brindley and Pratt. In each case the objections proceeded on the basis that
the witness was offering opinion rather than factual evidence, or opinion evidence on
technical matters beyond his area of competence. In the case of Mr Shepherd, his evidence
5
was objected to on the additional basis that it related to matters that largely pre-dated his
involvement in the project.
[9]
Dealing with the last objection first, Mr Shepherd's direct involvement in the
enabling works did not begin until December 2014. However, from April 2014 he began to
acquire an awareness of the issues that had been encountered during the enabling works,
based on his discussions on site with both Mr Pratt and the site manager. These discussions
continued throughout the remainder of 2014. To the extent that Mr Shepherd's evidence
was based on such indirectly acquired, second-hand, knowledge, I regarded the defender's
objection as going to weight rather than admissibility. However, in some passages
Mr Shepherd appeared to be offering a running commentary on, for example, what "would"
have been the pursuer's awareness of states of affairs at various points in time. This seemed
to be based more on Mr Shepherd's no doubt considerable expertise in civil engineering, and
his review of the documentation, rather than any knowledge he had acquired either directly
or indirectly on site at the relevant time. To that extent, I would sustain the defender's
objection, since Mr Shepherd was not being offered as a skilled witness, but as a witness to
fact. Quoad ultra I would repel the defender's objections. As regards Mr Brindley and
Mr Pratt, in particular, they tended towards the exegetical, and ignored the fact that the
evidence of these witnesses was based on their direct, contemporaneous involvement in the
enabling works. If there were anything of substance in these objections, it went to weight
rather than admissibility.
[10]
For its part, the pursuer's note objected to the relevancy of certain passages in
Dr Grant's witness statements where he maintained that the defender was not in breach of
any duty, and that any alleged breach did not cause the losses in respect of which the
pursuer sought to recover damages. This being a preliminary proof on prescription, the
6
pursuer's averments regarding breach of duty and causation, which I have summarised
above, all required to be taken pro veritate (Huntaven Properties Ltd v Hunter Construction
(Aberdeen) Ltd [2017] CSOH 57). Since the defender accepted this restriction on the scope of
the proof (written submissions, paragraph 8), I will sustain the objection, insofar as it may be
necessary to do so.
Pursuer's failure to call key witnesses
[11]
This is a convenient place to note the defender's complaint that the pursuer failed to
call Mr David Ewing and Mr Brian Reid, each of whom had appeared on the pursuer's
original list of witnesses. The former was to speak to "pre-contract discussions and the
requirement for tactile surveys", while the latter was to speak to "pre-tender stage and
progress of the project during part of 2014". In addition, the defender complained that the
pursuer failed to call its senior quantity surveyor, Mr Craig Adams, whose evidence might
have been relevant to whether the pursuer was aware of having sustained a loss, for the
purposes of section 11(3) of the 1973 Act, and also to whether the pursuer was in error or
induced to refrain from making a claim (section 6(4) of the 1973 Act). The defender
submitted that where these witnesses might reasonably have been expected to provide
relevant evidence on a central point over which the court was in some doubt, then the court
would be entitled to draw inferences favourable to the defender (written submissions,
paras 55-7, under reference to O'Donnell v Murdoch McKenzie 1967 SC (HL) 63. at pp71, 73,
and Royal Bank of Scotland v Carlyle 2010 CSOH 3, para 36). As a generality I have no
difficulty in accepting that proposition, but, except where otherwise noted in what follows,
my decision did not turn on any doubts I may have had arising from the evidence.
7
Background
[12]
The development had a long gestation period. As far back as 2007, a company called
Tiger Developments Limited appointed the defender to provide civil and structural
engineering services in relation to the development, and by 2008, the defender had already
prepared a design for the enabling works. However, in 2009 the development was put on
hold due to the global financial crisis. Between 2009 and 2012 both tunnels were electrified
by Network Rail, which involved the installation of overhead line equipment and the
lowering of the tracks. During the course of the electrification project in the north tunnel,
Carillion was employed to carry out remedial works to the brickwork including large areas
of render repairs. Eventually, the original developer entered into a joint venture with a
development company from within the Interserve group of companies, as a result of which
Edinburgh Haymarket Developments Limited ("EHDL") was formed. By agreements dated
26 and 27 November 2013, EHDL employed the pursuer (then registered under the name of
Interserve Construction Limited) to carry out the enabling works, and appointed the
defender to provide related engineering services, including the preparation of a Network
Rail approved design. At the same time the defender's appointment was novated to the
pursuer.
[13]
One of the problems faced by the designer was the limited information available at
the time the design was being prepared. No agreement had yet been entered into with
Network Rail that would have allowed a contemporary inspection or intrusive investigation
of the condition of the lining. Of course, the defender did have a certain amount of
information, for example, regarding the manner of construction of the tunnels. In particular,
while each tunnel was just over 900m in length, had an arch profile, and was lined with
bricks and masonry, they had been constructed at different times using quite different
8
methods. The south tunnel was constructed in around 1890 and was mostly bored. The
north tunnel was constructed in around 1849 using predominately "cut and cover"
techniques. In addition, such intrusive works as had been carried out at the design stage
had not identified any significant voiding behind the brick lining of the north tunnel. As a
result, the defender's design, issued in terms of Network Rail's standard form, assumed that
there would be no need for so-called "annular" grouting of the north tunnel, that is grouting
between the extrados of the tunnel lining and the surrounding bedrock (Form B,
para 7.1.1.1). By contrast, the defender specified annular grouting for the south tunnel.
[14]
A second feature of the north tunnel construction was that one to two courses of
"blue" engineering bricks had been added at some point between around 1920 and 1945.
Such investigations as had been carried out in the north tunnel were undertaken "with the
aim of identifying brickwork separations [sic] issues between the old and new brickwork".
Only a "limited area of separation was interpreted to be present", behind the second brick
ring between chainages 41 and 42, though several other "minor delaminations" were also
noted (Form B, para 3.3.3.1). No significant deeper voiding within the tunnel lining had
been identified at the design stage.
[15]
While the parties are in dispute over whether the defender made sufficient use of the
information available to it, certainly the design intention was to predict the behaviour of the
tunnel lining once unloaded, on the basis of certain assumptions or parameters, for example,
for brickwork strength and stiffness. The defender calculated that, while the maximum
stress reductions would be in the haunches and the crown, nevertheless the tunnel lining
would remain in compression throughout its whole profile during each stage of the
overburden removal (Form B, para 7.1.1.2). Moreover, while generally the unloading of the
tunnel would lead to a stress reduction, the crown was predicted to experience an increase
9
in compressive stress at the intrados. Therefore, to prevent damage to rolling stock in what
it described as the "unlikely event" of bricks being dislodged there, the defender proposed a
safety net (a "geogrid fall arrest system") to the tunnel crown (Form B, para 7.1.2). Since the
largest reductions in stress were predicted to occur at the intrados of the upper sidewalls
and haunches, the uncertain bonding of the inner brickwork to the original tunnel
construction created a risk of brickwork failure in these locations. To that end,
reinforcement was to be provided, principally by the technique of "stitch grouting" or stitch
pinning of certain known critical areas (the mechanical bonding of brickwork rings by
inserting pins, and the grouting of the stitch pins to keep them in place).
[16]
While, therefore, on the basis of its model, the defender was able to stipulate in
advance certain defined works, it was always acknowledged that additional works might
also ultimately prove necessary. These additional works would include stitch grouting, re-
pointing, brick replacement and the repairing of previously carried out failed render repairs
where these were necessary to allow stitch grouting to take place. The final scope of these
additional works was inherently uncertain, being dependent on what was identified once
access had been gained to the north tunnel, and following a "tactile survey" to be
undertaken as the works progressed (Form B, para 7.6.1).
[17]
The tactile survey was intended to include a physical inspection of each and every
area of the brickwork at close proximity in order to establish spalling or delamination. It
included carrying out a "hammer test" to identify areas of delamination between the first
and second rings of brickwork. When struck with a geological hammer, areas that
`sound[ed] "drummy"' were to be identified (Form B, Appendix A, para 2.1). The hammer
test was not suited to establishing deeper voids located within the lining or between the
lining and the bedrock (Dr Grant's email dated 17 September 2014). In addition, the purpose
10
of the tactile survey was to identify water seepage, insufficient mortar to joints,
misalignment of brickwork and loose brickwork. The tactile survey required full access to all
parts of the tunnel lining and would take several weeks to complete.
[18]
The information available to the defender at the design preparation stage included
the results from tests previously carried out on brickwork cores. 18 results, deemed
sufficiently representative of composite brickwork, were available from the south tunnel,
but only 5 from the north tunnel. Due to the small sample size taken from the north tunnel,
the defender proposed to test further brickwork cores from the north tunnel to ensure the
design values for unconfined compressive strength were representative (Form B, para 4.1).
Timeline
[19]
Designs relating to infrastructure managed by Network Rail required to be issued in
Network Rail's standard form. Form A set out the design concept, on which approval in
principle would be sought from Network Rail. Form B contained the detailed design. The
defender's design for the enabling works was contained in Form A, Issue 6, July 2013 and
Form B, Issue 4b, dated 19 August 2013. It was approved by Donaldsons Associates Limited
("Donaldsons"), appointed to represent Network Rail in relation to engineering aspects of
the enabling works, and Mott MacDonald Limited (Mott MacDonald), appointed as
"Category III" checker. Network Rail's approval of Form B was qualified by certain
comments contained in "Part 4: Acceptance on behalf of Network Rail". The completed
Forms A and B were part of the employer's requirements under the enabling works contract.
[20]
On 2 September 2013, in relation to the design parameter for unconfined compressive
strength of 8.0 MPa, Dr Grant advised Mr Ewing by email that, since the removal of the
overburden actually reduced the brickwork stresses, then the maximum stress condition
11
would be for the tunnel in its then current condition, ie with the overburden still in place.
"In other words, a reduced brickwork strength is going to highlight an existing problem for
the tunnel rather than alter our approach". In relation to the proposed additional cores to be
taken from the north tunnel, he added, "Testing involves taking further cores (say 13no [sic]
to bring number in line with the South Tunnel) and lab testing of these".
[21]
On 15 November 2013, EHDL entered into an asset protection agreement with
Network Rail, the purpose of which was to ensure the protection of Network Rail's
infrastructure, and to establish a procedure according to which the design was to be
submitted, and if necessary resubmitted, to Network Rail for approval. The events
triggering an obligation on EHDL to resubmit the design included the event that either
party, acting reasonably, believed the design, or the information upon which it was based,
was incorrect or insufficient.
[22]
On 5 December 2013, the pursuer subcontracted the carrying out of certain of the
enabling works to BAM Nuttall Limited ("BAM").
[23]
Around 6 January 2014, preliminary work began on site. Dr Grant issued a full
method statement for the tactile survey on 16 January 2014, and shortly thereafter, the tactile
survey commenced.
[24]
In late January 2014, BAM workers carrying out drilling in preparation for the stitch
grouting of the tunnel lining began to report concerns about the condition of the brickwork
in the north tunnel. The minutes of the weekly progress meeting on 30 January 2014
recorded that "some of the tunnel walls appear to be softer than others/thin bricks, therefore
there must be a review of the model", and that "[the defender] will expect a core from the
soft bricks and thin walls". In a request for further information dated 3 February 2014, BAM
noted that drilling had "potentially identified" brickwork of variable thickness and
12
condition "throughout the tunnel", and asked for confirmation that cores would be
required, and if they were, their location and specification.
[25]
The tactile survey carried out in January/February 2014 identified a "substantial
amount of defects (hollows in the crown)" (see the minutes of the site meeting on 13
February 2014) and the need for additional brick repair works. These included repairs to the
defectively undertaken Carillion render repairs that were wider in scope than had been
anticipated (compare Dr Grant's email of 30 September 2013 ("we did [following a visual
inspection of the tunnel linings in December 2012] identify some [Carillion] repairs which
had not been properly undertaken") with that of 25 February 2014 ("the tactile survey now
undertaken identifies that large areas of the render repairs are defective (hollow)").
[26]
On 19 February 2014, Dr Grant issued a plan showing proposed locations for cores to
be taken from the north tunnel lining, and on 24 February 2014, a technical note, increasing
the number of proposed cores to 21 (HM-TN-03).
[27]
On 28 February 2014 the defender issued drawings illustrating the works required as
a result of the tactile survey findings.
[28]
On 8 March, the pursuer instructed BAM to carry out investigative coring of the
north tunnel. Investigative coring of the north tunnel was carried out in March 2014. On
24 March 2014, BAM submitted an application for payment which included the sum of
£12,455.20 for north tunnel coring.
[29]
On 19 March 2014 Dr Grant issued further drawings showing proposed brickwork
repair techniques 1-4 for the north tunnel masonry repairs. Repair technique 4 showed a
form of stitch grouting similar to that set out in Form B. Though differing in matters of
detail, the primary purpose of the grouting was to hold the stitch pins in place. A secondary
purpose was to fill any voids in the immediate vicinity.
13
[30]
In its report dated 17 March 2014, while noting various defects that had been
identified following the tactile survey, the defender reported that the "tunnel lining was
observed to be performing adequately throughout the length inspected". There was "no
bulging or deformation of the tunnel lining that gave cause for structural concern". The
report noted possible soft brickwork, possible areas where the lining was less than 500mm
thick, and possible voids within the brickwork and between the lining and the rockhead/soil
behind. It noted that coring had been instructed, and that subject to the results of that
exercise, there was nothing arising from coring to date that would cause it to alter its
"analysis assumptions". In particular, the coring exercise to date had found that, with the
exception of "HM136 where a small void was identified above the crown", the brickwork
was found to be "tightly constructed to the bedrock/superficial materials throughout". It
further stated that compressive strength was not an issue, and that "with the current lining
not showing any signs of movement or distress the unloading of this brickwork will often be
beneficial to these areas of the lining".
[31]
By March 2014 at the latest, the pursuer expressed concern over the "serious
commercial implications" arising from the additional brick repair works (email from the
pursuer's Craig Adams dated 26 March 2014). Emails exchanged between Mr Adams and
Dr Grant highlighted an anticipated £300,000 increased payment to BAM for carrying out
brickwork repairs to the north tunnel.
[32]
On 1 April 2014, Dr Grant reported by email that, although the coring investigation
was ongoing, the defender was "generally encouraged by the findings ... although
Donaldsons were not so positive". Donaldsons were insisting on stiffness testing of the
cores in addition to strength testing. The defender warned that "in the worst-case scenario
14
this could lead to the analysis needing to be revisited if the testing [gave] poor results", and
that further coring/testing might also be required.
[33]
At the site meeting on 8 May 2014, Donaldsons requested that "the void at
[Chainage] 120 be the first area of cross pinning and grout repair".
[34]
On 23 May 2014, following a progress review meeting on 20 May 2014, the defender
reported the results of the investigative coring in the north tunnel to the pursuer. It
confirmed that soft brick had been found in the cores. The defender presented their re-
analysis of their model using revised parameters for brickwork strength and lining
thickness. This showed "no significant change to predicted movement". The defender's
report did however confirm that the soft brick that had been found in the cores, had made
Network Rail more "nervous" than at the Form B stage, resulting in their providing slower
approvals.
[35]
On 27 May 2014, BAM sought payment of £924,820.99 in respect of "additional
brickwork and other repairs" (BAM's application for payment number 5).
[36]
By June 2014, following a second tactile survey, Network Rail required brickwork
repairs to be undertaken to the lower sidewall (from cess level to 1.2m in height) of the north
tunnel. This had not been anticipated in the Form B design which, as noted above,
envisaged maximum stress reductions only at the crown and haunches.
[37]
By 5 June 2014, the defender was reporting a delay of 6 weeks to the enabling works.
[38]
On 24 June 2014, BAM sought a payment to account from the pursuer of £100,000 in
respect of work carried out to implement brickwork repair techniques 1, 3 and 4 (BAM's
application for payment number 6).
[39]
In August 2014, BAM experienced larger than anticipated volumes of grout being
taken up while carrying out repair technique 4 (as described by BAM in their email of 22
15
August 2014). In an email dated 26 August 2014, Donaldsons raised the possibility of the
need for grouting throughout the north tunnel in order to produce the desired continuum
("ie no gaps, voids or cracks in the model which is being used to managed the risk to the
railway"). While "minor deviations" from the analysis could be monitored and mitigated,
the reported excessive uptake in grout was stated to represent "20% voiding".
[40]
On 29 August 2014, Dr Grant emailed Mr Pratt, mentioning high grout uptake at
Chainage HM137. Dr Grant proposed further investigative coring at that location (Dr
Grant's email of 1 September 2014).
[41]
On 17 September 2014 the defender updated its report on brickwork repairs, an
earlier version of which had been issued on 17 March 2014. It recommended that the
unconfined compressive strength parameter be reduced from 8.0 N/mm
2
to 3.5N/m
2.
and that
the parameter for lining thickness be reduced from 500mm to 400mm in the area of the
lower sidewalls.
[42]
On 25 November 2014, Mr Pratt reported internally within the pursuer that "the
whole tunnel lining" might now require to be grouted.
[43]
On 28 November 2014, Mott MacDonald raised concerns over the design
assumptions or parameters, and whether they adequately represented the "apparent
variability" of the tunnel lining. On the same day, following high grout uptakes that
morning, Dr Grant advised the pursuer by email that full grouting of the north tunnel was
now required.
[44]
On 10 December 2014, the pursuer informed the defender that it might hold it liable
for the costs associated with the defender's substantial alterations to its design.
[45]
On 15 December 2014, the defender issued a preliminary issue drawing for grouting
the north tunnel.
16
[46]
At a meeting on 18 December 2014, attended by the parties, Donaldsons, Network
Rail, Mott MacDonald and EHDL, the need for annular grouting was agreed. Minutes for
the meeting prepared by the defender referred to "the recent evidence of voiding being
present within and behind the brickwork lining and the resulting concerns that a brickwork
continuum [did] not exist as per the analysis assumption". The grouting would not involve
any further stitch pinning. The aim was to "remove voiding and produce a more
homogeneous mass not to improve the properties of the brickwork". Further coring and
testing would also be carried out.
[47]
The defender produced updated drawings for grouting the north tunnel in
February, March and again in June 2015, showing a two-stage process. The first stage was
"to encourage flow paths to interstitial voids towards the rear of the lining and to also
permeate annular voids behind the lining". The second stage was to target interstitial voids
within the front 350mm depth of lining. The strength of the grout was weaker than that
used for stitch grouting (11N/mm
2
compared to 40N/mm
2
).
[48]
Annular and, what the defender's drawing referred to as, "interstitial" grouting was
carried out between June and October 2015.
Pleadings
[49]
As already noted, the pursuer's pleaded case of fault and causation requires to be
taken pro veritate for the purposes of a preliminary proof on prescription.
[50]
Having plead the defender's breach of a general duty of care, in article 7 of
condescendence, the pursuer set out to particularise in articles 7.1 to 7.7 the various specific
ways in which it alleged that the defender was in breach of that duty. These can be
summarised as follows: a failure to carry out a sufficient number of test samples to derive a
17
meaningful characteristic strength and stiffness for the tunnel brickwork (7.1); a failure to
note that such limited surveys as were available at the design stage indicated defects that
were indicative of potential gaps and voids, including voids at the tunnel/lining interface
(7.2); a failure to adopt a more conservative design methodology that would have reflected
the unreliability of available data and be more representative of the variable condition of the
tunnel lining (7.3); erroneously basing its design on a model that provided for full contact
between the lining and the bedrock behind it (7.4); a failure to make provision for full tunnel
grouting, including "back grouting" (ie annular grouting) and "interstitial grouting"
(ie grouting that was not merely ancillary to stitch grouting); erroneously relying on data
from the south tunnel when deriving parameters for strength and stiffness for the north
tunnel (7.6); and a failure to take into account the data that was available to the defender in
relation to the north tunnel brickwork and the gaps in that data (7.7).
[51]
In article 10, the pursuer avers, "As a direct and natural result of the defenders'
breach of their obligations under the Contract, the pursuer has suffered loss and damage".
It then avers, "Extensive re-design of the enabling works was required, which resulted in a
significant increase to the nature, time and cost of the enabling works".
Submissions
[52]
Both parties lodged lengthy, detailed written submissions, supplemented by brief
oral submissions.
[53]
So far as section 11(1) of the 1973 Act was concerned, as previously noted, the
pursuer accepted that loss occurred as soon as its defective design had been submitted.
Already at that stage, unbeknownst to it, the pursuer's contract with EHDL was worth less
18
to it than it would have been but for the defender's breach of duty (written submissions,
paras 2, 61).
[54]
However, so far as section 11(3) of the 1973 Act was concerned, the pursuer
submitted that it was not aware until November 2014 that the design for the enabling works
was negligent and therefore that its contract with EHDL was less valuable that it had
thought. It conceded that the need for additional brickwork repairs brick replacement,
repointing, render repairs and stitch grouting - going beyond what had been anticipated in
the Form B design, had been identified between January and April 2014, and that the
pursuer incurred associated additional costs that would not be recoverable from EHDL.
However, the need for these works to be carried out, together with their associated costs,
was not caused or otherwise related to the defender's breach of duty. The pursuer's claim
related to the design for the fixed rather than the ad hoc aspects of the enabling works.
Similar arguments could be made in relation to the additional works required to the lower
side walls. So far as the additional coring tests were concerned, these would have been
required even if the defender had specified a materially lower figure for brick strength in its
Form B. Nor was there any evidential basis for concluding that the project would not have
been in delay by May 2014, even had there been no breach of contract on the part of the
defender. In any event, the cost of the additional coring no more than about £12,500 was
de minimis in the context of the project as a whole.
[55]
So far as section 6(4) of the 1973 Act was concerned, the pursuer was induced to
refrain from making a claim as a result of its erroneous belief, induced by the words and
conduct of the defender, that it had produced a competent design, and that there was no
need for grouting, other than stitch grouting, in the north tunnel. The pursuer relied on the
defender's presentation of its design and its claiming payment therefor, as well as its
19
ongoing assurances from August 2013 until around September 2014. It was only in late
November 2014 that the defender advised that full grouting would be required. The
pursuer could not, exercising reasonable diligence, have discovered its errors any sooner.
[56]
On that basis, the pursuer moved the court to repel the defender's third plea in law,
and allow a proof before answer on the parties' "remaining" averments, which I understood
as meaning all the averments on record with the exception of those relating to prescription.
[57]
In its written submissions, the defender proceeded upon the basis that loss did not
occur until March/April 2014, when the pursuer incurred costs and/or delays on the project
(written submissions, paras 66, 81-83). Accordingly, and leaving section 6(4) to one side,
where the pursuer's submissions focussed on actual and constructive awareness of loss,
under section 11(3), the defender's written submissions were restricted to section 11(1) and
failed to address section 11(3) at all. This deficit was remedied to some extent by the Dean
of Faculty in his oral submissions, which noted that the pursuer had accepted that prima facie
prescription started to run in August 2013, when the pursuer relied on the defender's
design. The only question therefore was whether the start of prescription should be
postponed beyond 30 July 2014, on the basis of either section 11(3) or section 6(4).
[58]
Firstly, the defender submitted that it was only on 2 September 2021, by way of
adjustment of its pleadings, that the pursuer first made averments regarding the defender
having made over-optimistic assumptions of lining stiffness. Prior to that its complaint had
been about brickwork strength. Since the pursuer itself treated prescription as having
started to run in December 2014, it followed that any claim relating to lining stiffness must
have been extinguished in December 2019. Since the whole of the sum sued for related to
the additional works "prompted by the stiffness issues", the pursuer's entire case collapsed.
20
[59]
Secondly, the pursuer's case, properly analysed, rested upon a single allegation of
fault, namely, the provision of a defective design. It was therefore sufficient to ask when the
pursuer had suffered any loss, or had actual or constructive knowledge of any loss arising
from breach of that obligation. The pursuer had actual knowledge of costs and/or delays
in March/April 2014. The summons having been served only on 30 July 2019, more than five
years later, the pursuer's right of action in respect of all such losses had prescribed. There
could be no distinction between "additional brick repair works to the tunnel lining" and
"extensive re-design of the enabling works".
[60]
Thirdly, and in any event, the additional works that actually took place in
March/April 2014 were not restricted to brick repair work to the tunnel lining. These
included additional coring, render repairs, the stitch grouting of voids, and repairs to the
lower side walls. The pursuer's position, that it was always aware that there were going to
be unquantifiable works the cost of which would remain with the pursuer, was
commercially unrealistic.
[61]
Fourthly, the pursuer incurred costs and delays associated with these additional
works from March/April 2014. The proposed additional repair works required to be
checked by Mott MacDonald, and approved by Network Rail. Mr Pratt and Mr Brindley
had expressed concerns over the potential for resulting delay in March and April 2014. On
24 March 2014, BAM issued its application for payment number 3, which sought payment of
£12,455.20 in respect of variation 39A, north tunnel coring. On 27 May 2014, BAM issued its
application for payment number 5, which sought payment of £924,820.99 in respect of
variation 37, additional brickwork and other repairs. On 24 June 2014, BAM issued its
application for payment number 6, which sought a payment to account of £100,000 in
respect of variation 49, "brickwork repair techniques 1. 3 & 4". The pursuer was aware of
21
these applications at or around the time they were made. These were costs and delays
"connected" to what the pursuer referred to as "extensive re-design".
[62]
Fifthly, the enabling works contract was for a guaranteed maximum price. There
was no contractual mechanism by which the costs associated with the additional works
could be passed on to the employer. It followed that the cost to the pursuer of the variations
identified above were loss, injury and damage for the purposes of the 1973 Act. This was
true whether the works to which such costs related were classified as "brick repair work to
the tunnel lining" or "extensive redesign".
[63]
Sixthly, there was concurrence of iniuria and damnum no later than 24 June 2014,
when BAM submitted its application for payment number 6. On the pursuer's hypothesis,
iniuria was the deficient design, and damnum was the significant increase to the nature, time
and cost of the enabling works. Prescription had operated by the time the summons was
served on 30 July 2019.
[64]
Finally, the pursuer could not be rescued by the application of section 6(4). The
notion that any words or conduct of the defender might have induced error on the part of
the pursuer overlooked the fact that it was Network Rail that had the "casting vote" in
relation to design. The defender's design was always liable to change as a result of
additional demands that Network Rail was entitled to make by virtue of the asset protection
agreement. In any event, any error could have been discovered by the pursuer by the
application of reasonable diligence. The pursuer could not be relieved of the obligation to
exercise reasonable diligence merely by virtue of the fact that defender continued to endorse
the validity of its own design. It was sufficient that the pursuer was, or ought to have been,
aware of the circumstances which disclosed deficiencies in the design: Glasgow City Council
and West Dunbartonshire Council v VFS Financial Services Limited [2022] CSIH 1, para 55. The
22
pursuer was aware of Network Rail's concerns from an early stage of the works. It was
aware by April 2014 that additional expense had been incurred. By June 2014, these were
greater than £1million. That was more than enough to trigger investigation, and the running
of time against the pursuer.
[65]
For all of these reasons, the defender moved the court to sustain its third plea in law
and grant decree of absolvitor.
Decision
Section 11(1) of the 1973 Act
[66]
Time starts to run on an obligation to make reparation for loss, injury and damage
when the obligation becomes enforceable (section 6(3), Sch 1, 1973 Act). In terms of
section 11(1) of the 1973 Act, any such obligation becomes enforceable when the loss, injury
or damage occurred. The pursuer sues in respect of the need for extensive redesign of the
enabling works, and the resulting delay and costs. I agree with the pursuer that the primary
component of that loss, the need for the enabling works, occurred as soon as the pursuer
relied upon the defender's design, that is, in August 2013. Already, as at that date albeit,
the pursuer says, unbeknownst to it - extensive redesign of the enabling works would have
been required, with consequential costs to the pursuer. For the purposes of section 11(1),
therefore, this is when time started to run.
Section 11(3) of the 1973 Act
[67]
For the purposes of section 11(3), time is postponed until the pursuer first became
aware or could with reasonable diligence have become aware, of the occurrence of loss
caused by the breach or breaches of which it complains. In order for time to start running,
23
the pursuer does not also require to be aware that the loss was caused by the breach or
breaches of duty of which it complains (David T Morrison & Co Ltd v ICL Plastics Ltd 2014 SC
(UKSC) 222; Gordon's Trustees v Campbell Riddell Breeze Paterson LLP 2017 SLT 1287). The
pursuer correctly stated the position when it said that, for the purposes of section 11(3) the
prescriptive period will commence when the creditor is aware of "the objective facts which
constitute his loss" (written submissions, para 47). I have therefore disregarded those parts
of its submissions where it pleads its own lack of awareness of the defender's negligence
(written submissions, para 62).
[68]
Obviously, the loss, the occurrence of which the pursuer must actually or
constructively be aware, will still require to be one that is connected to the cause of action,
even if the pursuer need not also be aware that it is so connected (Gordon's Trustees, para 17;
Midlothian Council v Raeburn Drilling and Geotechnical Ltd 2019 SLT 1327, para 25; WPH
Developments Ltd v Young and Gault LLP (in liquidation) [2021] CSIH 39, para 36). Depending
on the circumstances of the individual case, therefore, much is likely to turn on the proper
characterisation of the pursuer's cause of action. Generally speaking, the more broadly it is
conceived, the more likely it will be that particular costs and delays that have been incurred
will be said to be attributable to the pursuer's complaint. Conversely, the more narrowly it
is defined, the less likely it is that the pursuer's awareness of particular costs and delays will
start time running against his claim.
[69]
In this action, the defender complains that the pursuer has drawn an artificial
distinction between "additional brick repair works" and "extensive redesign". "[A]t its
heart", it says, the pursuer's complaint is about "Form B fail[ing] ... to reflect the actual
condition of the tunnel", or the "scope of works envisaged by Form B [being] ... insufficient
to enable unloading of the tunnel in a manner which satisfied the requirements of Network
24
Rail" (written submissions, para 65.7). Properly understood, it asserted, there is a "single
fault" alleged against the defender, namely, "the provision of the deficient design", from
which all the losses suffered by the pursuer "must flow" (written submissions, para 65.7).
Whether it be additional brick repair works or repairs required by Network Rail to the lower
side walls, since none of these were anticipated in the Form B design, they must all be losses
caused by the allegedly defective design. Furthermore, since costs and delays associated
with these failures had been identified between January and April 2014, they were losses of
which the pursuer was aware more than 5 years before the action was raised.
[70]
The problem with this approach is that it conflates the pursuer's several complaints
into one single ground of fault. I prefer the approach of Lord Eassie, in Musselburgh and
Fisherrow Co-operative Society Ltd v Mowlem Scotland Ltd 2004 SCLR 412, where he stated that,
"although a contractual relationship will often contain general provisions such as a general
duty of care or a general duty to construct in a workmanlike manner, for the purposes of the
running of the five-year prescription it is necessary to identify the particular respect in
which the general duty is breached and which leads to the causing of the particular defect in
question" (para 50). Citing Sinclair v MacDougall Estates Ltd 1994 SLT 76, and Cole v Lonie
2001 SLT 608, Lord Eassie went on to make it clear that it matters not that the defect be one
of design or construction, or that the defect may not be of great magnitude, albeit he
acknowledged that difficulties may arise in practice when determining whether defects are
truly distinct and discrete (para 50, p430C-D).
[71]
Thus, while in this case, it may be true to say that the defender was under a general
duty of care in respect of the provision of engineering services, for the purposes of the
running of the five-year prescription it is necessary to identify the particular respects in
which the general duty is said to have been breached. Although there may be a degree of
25
overlap between and among the several breaches plead by the pursuer in article 7.1 to 7.7 of
condescendence, in my opinion, the pursuer's pleaded case of fault should at least have
represented the starting point for the defender's analysis.
[72]
What the pursuer may not do, of course, as the pursuer itself conceded (written
submissions, para 60), is artificially restrict the loss claimed. As I have already noted, the
pursuer limits the loss for which it claims reparation to the need for an extensive redesign of
the enabling works together with the resulting delay and costs. However, should any of the
breaches of which it complains have given rise to an earlier material loss, of which it was or
ought to have been aware more than 5 years before the action was raised, then its cause of
action in respect of that particular breach will not be saved by section 11(3). This is so even
if the pursuer can establish that it was unaware of the need for an extensive redesign caused
by that alleged breach until much later. Against that background, I now turn to what the
defender identified as earlier established losses of which the pursuer had actual or
constructive knowledge.
"Additional" cores
[73]
In article 7.1, the pursuer avers that the defender failed to carry out a sufficient
number of test samples in order to determine the characteristic strength and stiffness of
brickwork in the north tunnel. At the design stage, only 5 brickwork test results were
available in respect of the north tunnel, with 18 being available from the south tunnel. With
that in mind, the defender stated in its Form B that, "Due to the small sample size taken
from the North Tunnel it is proposed to test further brickwork cores from this tunnel to
ensure [the design values for unconfined compressive strength were] representative". The
Form B was never specific as to how many further cores would be required. Certainly, in his
26
2 September 2013 email to David Ewing, Dr Grant proposed to take a further 13 cores to
bring the number of test results into line with those available for the south tunnel. But in my
judgment this did not alter the fundamental design proposal, which was to take sufficient
further cores, however many might be required, to ensure the strength values were
representative. Apart from anything, there was always a risk, particularly with smaller
diameter cores, that they would fail to extract a sufficient cross-section of brickwork (the
Form B recorded at paragraph 4.1 that, of the 34 cores taken in 2002, only 23 contained a
combination of bricks and mortar). But more fundamentally, it had always been known that
the north tunnel brickwork was "variable" in condition (Form B, paragraph 3.3.3.3). If,
therefore, following the reports of soft bricks in January 2014, it was decided to increase the
number of cores to be taken, this was done in implement of the Form B design rather than as
a modification of or variation to the design. I would therefore reject the defender's
submission that the cost of coring of £12,455.20 itself constituted a loss to the pursuer
(written submissions, para 75). Rather it was no more than a cost, which had always been
anticipated as part of the enabling works, even if its precise amount was uncertain at the
time the design was proposed.
[74]
I note in passing that BAM's application for payment number 3, dated 24 March
2014, seeking payment of £12,455.20 in respect of variation 39A, did so in implement of the
pursuer's instruction number 16 which itself related to all 21 cores proposed by Dr Grant in
his technical note, HM-TN-03, dated 24 February 2014, rather than just the 7 smaller 50mm
cores identified as being required in response to the drillers' reports. Further, the technical
note increased to 14 the number of further cores suggested in September 2013 for reasons
that appear to have had nothing to do with the drillers' reports.
27
Additional brickwork repairs
[75]
Similar comments can be made about the additional brick repair works. I take these
to include the identification, following the tactile survey, of the need to carry out greater
quantities of masonry repairs over greater areas than had been anticipated at the Form B
stage, and of the need to repair defective Carillion repairs, the scope of which was greater
than had been anticipated at the Form B stage. The additional brick repair works also
included the need to repair the lower sidewalls of the tunnel, in order to comply with the
request from Network Rail.
[76]
The defender argued that the additional brick repair works were not something to be
regarded as separate from the enabling works. When, therefore, the pursuer claims in
respect of the "extensive redesign" of the enabling works, it should be understood as
including the need to carry out these significant additional brick repair works. But just
because the additional brick repair works might conceivably be understood, in one sense, as
an "extensive redesign" of the enabling works, it doesn't follow that they are that part of the
extensive redesign in respect of which the present claim is framed. The defender appeared
to make something of the fact that they were included in the pursuer's claim as originally
framed, but this in itself is obviously irrelevant to the resolution of what is now in issue.
[77]
The defender further objected that the pursuer did not offer to prove that it "always
knew" that the scope of works might expand to include the lower sidewalls (written
submissions, para 70). It then generalised this objection, arguing that there was no evidence
that the pursuer was aware that "additional brick repair works m[ight] be required to the
tunnel lining" (written submissions, para 71). Rather, it pointed to email correspondence,
such as the email from the pursuer's Craig Adams dated 26 March 2014, addressing the
potential for the additional brick repair works to raise "serious commercial implications".
28
As I understood the defender's argument, it was that the pursuer must have become aware
of having suffered a degree of commercial exposure, and therefore of having incurred a loss,
starting the prescription clock running by March 2014 at the latest.
[78]
However, if it is a loss, it is not obviously one arising from any of the grounds of
fault plead by the pursuer. For example, the pursuer does not specifically plead negligence
on the part of the defender in leaving any part of the enabling works undefined until such
time as the tactile survey had been carried out. Nor does it plead negligence on the part of
the defender in allowing Network Rail to determine the ultimate scope of the works.
Assuming for the purposes of argument that such averments might have been relevantly
plead, then conceivably the expansion in the scope of the additional works beyond what had
been anticipated at the design stage might be capable of being described as a loss. However,
if so, it would not obviously be one arising from the present cause of action.
[79]
The pursuer may very well have become concerned about the degree to which it had
become commercially exposed to its subcontractor for the cost of these additional works,
whether arising as a result of the tactile survey or the need to gain Network Rail's approval.
However, I do not necessarily interpret that concern as evidence of a belief that these were
costs, for which the defender must be liable, or that they were somehow inseparable from
the cost of the extensive redesign for which the pursuer now claims. If they were evidence
of such a belief, then it was an erroneous belief. In my judgment, the additional works
should be seen as within the risk of the contractual arrangements the pursuer entered into,
rather than being a consequence of any breach of duty by the defender. In Midlothian
Council v Raeburn Drilling and Geotechnical Ltd 2019 SLT 1327, at para 25, Lord Doherty drew
what I would regard as an analogous distinction between the consideration paid for
services, and loss caused as a result of breach in the performance of these services. I take it
29
that the UK Supreme Court has not obliterated the distinction between cost and loss, and it
is still necessary to ask oneself whether the costs and delays which the pursuer must have
been aware that it had incurred in March/April 2014 were losses caused as a result of the
breaches of obligation of which the pursuer complains.
Voids
[80]
The pursuer's case, as developed in its written submissions, is that the defender
failed to make allowance for the need for annular and full interstitial grouting. Article 7.2 of
condescendence alleges that the defender failed to carry out sufficient investigations at the
design stage in relation to "voids and potential voids". However, there was no dispute that
the defender's design acknowledged a "known issue regarding possible separation between
the original brickwork and layer(s) of blue engineering bricks" (pursuer's written
submission, para 15). Rather, the pursuer's complaint was that the design assumed that
there was little or no significant evidence of deeper voiding, whether within the lining itself
(Form B, para 3.3.3.1) or between the lining and the rockhead/soil behind (Form B,
paras 3.3.2 and 7.1.1.1).
[81]
The defender's argument, summarised in particular at paragraph 69.3 of its written
submissions, and spoken to at length by Dr Grant throughout his evidence, was that there
was no material difference, certainly none in an engineering sense, between voids,
delaminations, hollows or gaps of any kind within the tunnel lining or even between the
lining and the rockbed. It followed that, as soon as voids of any kind were discovered, and
repairs carried out, at a cost to the pursuer, then it had suffered loss.
[82]
I am not persuaded by this argument. It was not the purpose of the tactile survey to
identify the presence of these deeper voids. Tactile surveys involve a full inspection of the
30
intrados, and the use of a geological hammer to detect hollowness. I have noted what
Dr Grant said in his supplementary witness statement, at paragraph 23, where he discussed
the relevant Network Rail standard in accordance with which the tactile survey was
undertaken (NR/L3/CIV/006/4C). The standard instructed the use of two defect codes for
types of hollowness: HS for "hollow with no evidence of lining distortion caused by
incipient spalling" and HN for "hollow with no evidence of lining distortion cause not
determinate". Dr Grant observed that, on its tactile survey drawing dated 28 February 2014,
the defender had used the code HS for spalling brickwork between chainage HM130 and
HM143. However, he also noted that, according to the standard, the defect denoted by the
code HN was more serious, "as it implie[d] ring separation or voiding behind the lining"
(the standard actually uses the word "element", but it is clear from the overall context that in
doing so, it is referring to the tunnel lining). Dr Grant concluded that, "According to
Network Rail's own handbook therefore, one potential defect which might be identified in a
tactile survey is the existence of voids". However, the key word here is "potential": it is only
a potential defect, rather than a defect, and it is only a potential defect in the sense that the
tactile survey cannot exclude it. Dr Grant's own view, clearly expressed in his email to
Michael Purkis of Donaldsons sent on 17 September 2014, was that, "Hammer tapping is
done to try and establish a possible ring separation between the first and second brickwork
ring only. It cannot be used to establish any deeper defect" (emphasis supplied). In my
judgment, therefore, it was not the purpose of the tactile survey to establish the presence of
deeper voids.
[83]
The defender conceded that the stitch drillers had identified only "potential" voiding
(written submissions, para 69.3). It went on to suggest that the tactile survey "confirmed the
position". But what it confirmed was a "substantial amount of defects (hollows in the
31
crown)". Because, as discussed, the hammer test cannot reveal deeper voids, this note could
not be referring to anything other than delamination between the first and second rings of
brickwork (or possibly between the engineering bricks and the red bricks). Further, stitch
pinning or stitch grouting was a technique adopted to deal with certain problems identified
through the tactile survey. Since the tactile survey could not establish the presence of
deeper voids, it could not have been the purpose of stitch pinning or stitch grouting to
repair or grout deeper voids. As was stated in the Form B, "the purpose of the stitch
grouting [was] to provide mechanical bonding between the brick courses where stress
reductions at the tunnel intrados are considered to be significant. This is particularly relevant
to providing a bond between the re-cased inner brick rings and the original brickwork" (emphasis
supplied). Repair technique 4 was not materially different from the form of stitch grouting
identified in the Form B. The defender's drawing C1T-ARU-S-NT(48)CD075 (issue C3)
showed in section the mischief at which repair technique 4 was directed, namely, a
delamination between the innermost brickwork ring and the brick course behind it, adding
the words, "Lining ring separation void to be grouted". A further section, showing the
arrangement of stitch pins, showed delamination between the first and second and the
second and third innermost brick courses.
[84]
I have noted what Dr Grant says at paragraph 26 of his supplementary witness
statement, that the defender had specified that repair technique 4 had "the aim of ensuring
that grout flow[ed] and permeat[ed] brickwork". Here he was referring to technical note 15
to the drawing with reference number C1T-ARU-S-NT(48)CD075 (Dr Grant in fact referred
to C1T-ARU-S-NT(48)CD074, but that drawing appears to relate only to repair techniques 1
to 3). However, note 15 has to do with the pressure at which grout was to be injected, rather
than the locations or areas to be grouted. I can see no suggestion that this repair technique
32
was to be used to permeate what I have referred to as deeper voids, or voids other than
those that might require to be filled as a by-product of stitch pinning.
[85]
I have also noted what Dr Grant says at paragraph 17 of his supplementary witness
statement that, "The only difference between [repair technique 4] and the full tunnel
grouting done after December 2014, was that the later grouting did not involve the insertion
of bars, and was much wider in scope as it involved the entire tunnel at Network Rail's
insistence". However, this is incorrect, since, in addition to the insertion of bars, the
defender specified a lower strength of grout for stitch grouting compared to that specified
for what Dr Grants calls "full tunnel grouting".
[86]
I have also noted Dr Grant's evidence that the defender never said that there would
be "absolutely no voids" in the north tunnel, and that the defender's drawing of the tunnel
in section "highlighted" the presence of voids behind the lining (supplementary witness
statement, para 19). "Depending on whether there was a direct linkage to the voiding
providing a pathway through the brickwork," Dr Grant added, "there would be some back
grouting to the rear involved in the exercise" (Ibid, para 19). However, the pursuer's case is
not premised on any absolute guarantee by the defender that there would be no voids in the
north tunnel. To suggest that the tunnel section shown in drawing C1T-ARU-S-
NT(48)CD075 "highlighted" voids behind the lining is misleading or, at best, an
exaggeration. The drawing was about stitch pinning and stitch grouting. It contained no
note drawing attention to the void behind the lining. It showed no pathway through which
injected grout might reach any deeper void, including the void behind the lining. I reject
any suggestion that this drawing would have made the pursuer aware of the significant
presence of deeper voids, including voids behind the lining, or that repair technique 4
represented any systematic design solution for the grouting of such voids.
33
[87]
I do accept that the loss of very significant quantities of grout, while carrying out
stitch grouting, might provide a basis for an awareness of deeper voids, and in particular,
voiding behind the tunnel lining. However, it seems not to have been disputed that this
only occurred for the first time in August 2014. In my judgment the pursuer has established
that he was not aware and could not with reasonable diligence have been aware of the
presence of deeper voids until this time.
Delay
[88]
In its written submissions, the pursuer noted the defender's position that the north
tunnel works were in delay by May 2014 when the programme target for the north tunnel
enabling works was not met. However they went on to state that "there [was] no evidence
from which the Court could conclude that that date would have been met but for the
breaches of contract upon which the present action is based" (para 63(d)). I would accept
that proposition so far as what I have referred to as the additional works are concerned,
since I have accepted that the need for these works did not arise from any breach of contract
on the part of the defender. However, the position regarding delay and the north tunnel
coring is more complicated.
[89]
The critical document here is the defender's minutes of progress review meeting of
20 May 2014, sent to the pursuer on 23 May 2014. The purpose of the meeting was to
"review progress on Network Rail approvals". The defender reported that, "The soft brick
found in the recent cores through the north tunnel lining has made [Network
Rail/Donaldsons] more nervous than at Form B sign off. This has resulted in slower
approvals and NR requesting an internal review from their chief UK tunnel engineer
Colin Simms. This review is not due to take place for a further two weeks". As Dr Grant
34
noted at paragraph 10 of his supplementary witness statement, while this statement was
included in a section titled, "Extent of repair work", it was perfectly clear that Network
Rail's concerns arose from the coring, and in particular, the soft brick. By 5 June 2014, the
defender was reporting a delay of 6 weeks. Some of this delay is likely to have been caused
by other factors, such as the additional works, the need for which I have accepted was not
attributable to any pleaded fault on the part of the defender. However, it is inconceivable
that at least some of this delay was not also due at least in part to the discovery, after the
enabling works had started, of soft bricks, slowing down the approval process. By this I
mean that the delay was not simply the result of the taking of additional cores, including an
increase in the number of additional cores compared to that envisaged by Dr Grant
in September 2013. Rather, Dr Grant was attributing the delay to the particular stage at
which soft brick was confirmed, that is, after the Form B had been issued and after the
enabling works had started, with the resulting "nervousness" on the part of Network Rail.
[90]
This question of the timing of test sampling was the focus of the pursuer's pleaded
case at article 7.1 of condescendence. So, by May/June 2014 at the latest, the pursuer was
aware that it had suffered loss as a result of its alleged failure "to carry out a sufficient
number of test samples to derive a meaningful characteristic strength and stiffness for the
tunnel brickwork" (article 7.1). This is obviously not changed by the fact that the pursuer
may have restricted its claim to the need for an extensive redesign of the enabling works and
the resulting delay and costs. For the purposes of section 11(3) of the 1973 Act, therefore,
time started to run against the pursuer's article 7.1 complaint as soon as it was aware of the
fact that the enabling works were in delay as a result of the impact that the results from the
cores had on Network Rail. In arriving at this conclusion, I would note that it is not enough
for the pursuer, upon whom the onus of proof lies in order to make out a section 11(3) case,
35
to point to an absence of evidence. Moreover, insofar as there may be any doubt about the
cause of delay, in the absence of Mr Adams, or any other key witness who might have been
able to give evidence for the pursuer, I consider that I am entitled to draw an inference
favourable to the defender. Even if the pursuer were not actually aware of such a delay as at
May/June 2014, then I would hold that the pursuer could with reasonable diligence have
been so aware by that stage.
[91]
For the avoidance of doubt, the delay, of which I have held the pursuer to be both
actually and constructively aware as at May/June 2014, does not obviously appear to me to
have been a consequence of any of the other breaches complained of by the pursuer. There
is a complaint in article 7.6 that the defender "failed to see to it that testing of a sufficient
sample of bricks had been undertaken". However, that complaint is essentially that the
defender adopted "erroneous assumptions" for strength and stiffness based on data from
the south tunnel, rather than one of failing to carry out sufficient test sampling at the design
stage.
Section 6(4) of the 1973 Act
[92]
In order to rely on section 6(4)(a)(ii) of the 1973 Act, the pursuer must establish, in
respect of any obligation upon which it relies, that, by reason of error induced by words or
conduct of the defender it was induced to refrain from making a claim. It must establish the
period during which it was so induced, and no account shall be taken of any period during
which the pursuer could, with reasonable diligence, have discovered the error.
[93]
The errors upon which the pursuer founded were (1) that the defender had produced
a competent design, and (2) that there was no need for grouting, other than stitch grouting,
in the north tunnel. It argued that it was induced to refrain from making a claim by the
36
words and conduct of the defender, including the preparation and presentation of its design,
the defender claiming payment for its services, the absence of any warning that its design
was not competent or that any material changes would be required, and the ongoing
assurances from the defender regarding its design in the period from the issue of its Form B
in August 2013 until around September 2013. The pursuer claims it could not with
reasonable diligence have discovered its error prior to December 2014, when the defender
advised that full grouting of the north tunnel would be required.
[94]
The defender argued that the pursuer was not in error "as to the scope of [its]
remedies" (written submissions, paras 85, 86, under reference to Adams v Thorntons WS
2005 1 SC 30). I reject that submission. Although the defender advised the pursuer on
23 May 2023 that the north tunnel cores had confirmed the presence of soft brick, it
reassured the pursuer, having reviewed the impact this discovery had on its model, that its
design remained valid. On the basis of that reassurance, and others noted in the above
timeline, the pursuer had no cause to believe it had any remedy against the defender in
respect of the need for any extensive redesign or its resulting delay and costs. Had the
defender advised the pursuer at that stage that full grouting of the tunnel was necessary, I
have no doubt that the pursuer would have promptly responded to the defender, holding it
liable for the resulting costs. After all, this is precisely what happened in December 2014,
following Dr Grant's email of 28 November 2014. In that sense, the pursuer can legitimately
be said to have "refrained" from taking legal action as a result of error induced by the
defender. In reaching that conclusion, I consider it is unnecessary to identify a "conscious
and deliberate decision" on the part of the pursuer or anyone representing the pursuer
(BP Exploration Operating Company Ltd v Chevron Transport (Scotland) 2002 SC (HL),
Lord Hope, para 30; cf Lord Clyde, para 66, and Lord Millett, paras 102-109). I am not
37
persuaded, therefore, that the pursuer's case was fatally undermined, as the defender
contended it was, by its decision not to call Mr Adams.
[95]
The defender argued that the pursuer could not rely on the defender having insisted
on the validity of its design. It figured the following example, "Suppose that the roof of a
house blows off in the wind. The architect who designed the house claims that there was
nothing wrong with the design. On the pursuer's approach, ... [t]he simple act of denying
liability is apparently enough to prevent a claim ever from prescribing" (written
submissions, para 84.3). I reject that argument. The analogy is not exact. Here we are not
dealing with a designer who digs his heels in after an entirely new construction has already
been completed and an obvious problem has arisen. The present case involves an antique
Victorian tunnel, in less than perfect condition, and where the defender's assurances were
given during the course of the enabling works and at a time when the pursuer continued to
rely upon its specialist engineering services. The pursuer does not rely upon a "simple act
of denying liability", but a practical context in which it continued to rely upon the
defender's services. In these circumstances, it can properly be said to have been "induced"
to refrain from raising proceedings. No one would argue that a simple denial of liability
could operate as an inducement. In effect, the defender's reassurances operated as a
renewal and a restatement of its design, one on which the pursuer relied.
[96]
The defender argued that the pursuer was aware of the concerns being expressed by
Donaldsons and Mott MacDonald. Moreover, since Network Rail had the "casting vote" in
relation to design, it was "nonsensical to suggest that the defender's production of the
design (coupled with its receipt of payment in respect thereof) was enough to lead the
pursuer into error" (written submission, para 84.1). However, the fact that others
Donaldsons, Mott MacDonald may have been appointed to check the defender's design
38
does not necessarily undermine the pursuer's case that it was induced into error in reliance
on the defender. It would be enough that the pursuer relied on the defender to some extent,
even if it also relied on others. The pursuer does not require to argue that the words or
conduct of the defender was the sole cause of its error; it is enough that it contributed to that
error (Heather Capital v Levy & McRae 2017 SLT 376, para 63). In any event, taking the
pursuer's averments pro veritate, as I must do at this stage, I proceed on the basis that the
pursuer was entitled to rely on the defender's design and the assurances given to it by the
defender.
[97]
I have accepted, of course, that the pursuer was aware in May/June 2014 that the
discovery of soft brick had caused the enabling works to be already delayed. But I do not
accept that there is a sufficient basis for concluding that the pursuer, exercising reasonable
diligence, could have discovered the error that induced it to refrain from raising
proceedings. Of course, there is no requirement that the pursuer should have acquired,
actually or constructively, "knowledge of all the facts relevant to the matter" (Glasgow City
Council v VFS Financial Services Ltd 2022 SC 133, para 55). And, were it not for the
reassurances given by the defender, the pursuer's awareness of delay having been caused by
the discovery of soft brick might have led it, with reasonable diligence, to discover the
alleged failure to take sufficient test samples at the Form B stage. However, that is not the
relevant error under which the pursuer was labouring. Rather, its errors were in respect of
the need for an extensive redesign and the need for grouting. These were the errors that
induced it to refrain from taking legal action, and standing the words and conduct of the
defender, in particular, the reassurances given, the pursuer could not, even by exercising
reasonable diligence, have discovered them. In my judgment, therefore, the pursuer is
entitled to rely on section 6(4) in relation to all its pleaded grounds of complaint, by
39
discounting the period up until the end of November 2014 as part of the prescriptive period.
There is no conflict here with what I have already held in relation to the pursuer's
constructive awareness of delay. Reasonable diligence, for the purposes of section 11(3),
relates to the awareness of loss. Reasonable diligence, for the purposes of section 6(4),
relates to the discovery of error. They are different tests.
Strength and stiffness
[98]
I deal finally with the defender's argument that the pursuer's averments introducing
a complaint of over-optimistic assumptions of lining stiffness, adjusted into the pleadings on
2 September 2021, came too late to interrupt prescription.
[99]
The problem here for the defender is that the strength and stiffness of materials,
while analytically separate properties, are clearly related. In any event, taking the pursuer's
averments pro veritate, this is what is plead. In article 7.1 of condescendence, the pursuer
explains that "strength of brickwork was not irrelevant (as the defender now asserts). While
removal of overburden would reduce thrust loading, it would also induce movements in the
tunnel structure that would be related to the long-term stiffness of the brick. On that basis, it was
necessary for an engineer acting to the appropriate standard to check that the magnitude of
these movements, derived from a potential range of long-term moduli, fell within specified
trigger levels. It was also necessary for the compressive and tensile stresses induced by the
range of movements to be determined as the thrust compressive stress had been reduced. The
potential for a combination of high tensile stresses and low compressive stresses inducing local
brick failures also required to be considered" (emphasis supplied). And again at article 7.6,
"The defender did not properly consider the effect on long term modulus arising from a lower
compressive strength of the bricks (as it should have done)" (emphasis supplied). As the
40
pursuer explains in article 10, the modulus of elasticity is in essence a measure of the
stiffness of a material, and its earlier averments make it clear that strength and stiffness are
separate but related properties.
[100]
Properly understood, the pursuer's averments regarding over-optimistic
assumptions of lining stiffness are a development or a modification of the existing grounds
of fault, rather than the introduction of a fundamentally different ground of fault. Applying
the appropriate test (Assuranceforeningen Skuld v International Oil Pollution Compensation Fund
(No 2) 2000 SLT 1348, at 1351L), the defender's objection falls to be repelled.
Disposal
[101]
I will repel the defender's third plea in law and allow a proof before answer on all
averments on record other than those relating to prescription. I will reserve meantime any
question of expenses.