Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
RECLAIMING MOTIONS BY NETWORK RAIL INFRASTRUCTURE LTD AGAINST FERN TRUSTEE 1 LTD AND OTHERS AND THE SCOTTISH MINISTERS AGAINST McLAUGHLIN & HARVEY LTD AND OTHERS [2022] ScotCS CSIH_32 (08 July 2022)
URL: http://www.bailii.org/scot/cases/ScotCS/2022/2022_CSIH_32.html
Cite as:
2022 SLT 997,
2022 GWD 23-318,
[2022] CSIH 32,
[2022] ScotCS CSIH_32
[
New search]
[
Printable PDF version]
[
Help]
FIRST DIVISION, INNER HOUSE, COURT OF SESSION
[2022] CSIH 32
CA23/21 and CA56/21
Lord President
Lord Malcolm
Lord Woolman
OPINION OF THE COURT
delivered by LORD CARLOWAY, THE LORD PRESIDENT
in the reclaiming motions by
NETWORK RAIL INFRASTRUCTURE LIMITED
Pursuers and Reclaimers
against
(FIRST) FERN TRUSTEE 1 LIMITED, (SECOND) FERN TRUSTEE 2 LIMITED and
(THIRD) McLAUGHLIN & HARVEY LIMITED
Defenders and Respondents
and
THE SCOTTISH MINISTERS
Pursuers and Reclaimers
against
(FIRST) McLAUGHLIN & HARVEY LIMITED, (SECOND) FERN TRUSTEE 1 LIMITED, and
(THIRD) FERN TRUSTEE 2 LIMITED
Defenders and Respondents
Pursuers (Network Rail): DM Thomson QC, Steel; Dentons UK and Middle East LLP
Pursuers (Scottish Ministers): Massaro; Morton Fraser LLP
Defenders (Fern): Barne QC; MacRoberts LLP
Defenders (McLaughlin & Harvey): GJ Walker QC; Balfour and Manson LLP
2
8 July 2022
Introduction
[1]
This litigation concerns remedial works which contractors (McLaughlin & Harvey)
agreed to carry out on an office block in Glasgow in terms of what has become known as the
Remedial Works Agreement between them, the owners (Fern) and the tenants (the Scottish
Ministers and Network Rail). The tenants argue that the RWA: (i) gave them the right to
have their views, on whether the remedial works had been completed, conveyed by the
owners to the contractors, and (ii) obliged the owners not to agree that Completion had been
achieved until the tenants were content that it had been. The commercial judge rejected
these arguments ([2021] CSOH 107). By interlocutors dated 21 October 2021 he dismissed
the tenants' actions against the owners and the contractors. The issues in these reclaiming
motions (appeals) against those interlocutor centre on the correct construction of the RWA,
which set out the mechanism for determining whether and when Completion was achieved.
The original works and the RWA
[2]
Between 2002 and 2004, the contractors carried out works on the office block in terms
of a building contract which they had entered into with the previous owners. The current
owners bought the block in 2006. The contractors granted collateral warranties to the new
owners and the tenants.
[3]
Defects in the original works became apparent in 2008. The owners and the tenants
raised actions against the contractors. Those actions were settled. Separate settlement
agreements were entered into by the contractors on the one hand and the owners and the
tenants on the other. The agreements provided that the contractors were to carry out
remedial works in terms of the RWA and to pay sums by way of damages. Network Rail
3
were also entitled to liquidate damages of £52,500 per week if Completion had not occurred
by 30 September 2018, or a later agreed date. The Scottish Ministers were to be paid a
monthly sum until Completion. Their agreement contained an express provision whereby,
for the avoidance of doubt, they were entitled to claim damages in the event of a breach of
the RWA.
[4]
Completion was "the date on which satisfactory completion of the Remedial Works
shall be deemed to have taken place in accordance with clause 3.30 of this Agreement"
(cl 1.1.8).
[5]
The RWA set out the process to be followed:
"3.26 Within 7 days of completion of the Remedial Works, the [contractors] shall
notify [the owners and tenants] ... that it considers that the Remedial Works have
been completed ... (`the Defender's Completion Notice').
3.27 Within 7 days of receipt of the Defender's Completion Notice, the Owner shall
confirm ... whether or not it accepts that the Remedial Works have been satisfactorily
completed (`the Owner's Completion Notice'). The Owner shall liaise with the
Tenants regarding acceptance of whether or not the Remedial Works have been
satisfactorily completed and shall add any elements of the Remedial Works it
considers have not been completed satisfactorily to the Owner's Completion Notice.
3.28 If the Owner does not accept that the Remedial Works have been satisfactorily
completed:
3.28.1 the Owner shall specify in the Owner's Completion Notice what
elements of the Remedial Works it considers have not been completed
satisfactorily and why;
3.28.2 the [contractors] shall within 7 days of receipt of the Owner's
Completion Notice notify the Owner in writing whether it agrees or disagrees
with any of the matters raised by the Owner;
3.28.3 if the [contractors] agrees with any of the matters raised by the Owner
it shall carry out and complete such works that are reasonable to address the
matters raised by the Owner and then issue a fresh Defender's Completion
Notice ...;
3.28.4 if the [contractors] does not agree with any or all of the matters raised
in the Owner's Completion Notice then the [contractor] may refer the
question of satisfactory completion of the Remedial Works to adjudication ...
3.29 The Parties agree that the existence of snagging items, minor defects or
omissions, or minor incomplete works which ... do not interfere with the occupation
4
and use of the Property ... shall not ... cause the Remedial Works to be incomplete ...
All such Snagging shall be specified in a list to be completed by the contractors for
the Owner's approval and issued along with the Defender's Completion Notice. The
[contractors] shall complete and make good all Snagging within 10 Working Days of
the date on which satisfactory completion the Remedial Works [sic] is deemed to
have taken place.
3.30 The date on which satisfactory completion of the Remedial Works shall be
deemed to have taken place shall be:
3.30.1 the date of the relevant Defender's Completion Notice, when accepted
by the Owner; or
3.30.2 a date determined by the Adjudicator...".
[6]
Clause 3.31 provided that the effect of Completion was that the owners assumed
responsibility for the insurance and ongoing care of the works. The defects period of one
year commenced. Any defects which appeared during this period, and were caused by the
contractors, were to be specified by the owners in a schedule to be delivered to the
contractors no later than 14 days after the expiry of the period (cl 3.34). The owners were: to
liaise with the tenants regarding the identification of defects (cl 3.36); to add into the
schedule any defects so identified (cl 3.36.1); and to issue any instructions to make good the
defects, if requested to do so by the tenants (cl 3.36.2).
The Remedial Works
[7]
Remedial works were carried out. On 17 December 2019, the contractors issued a
Defender's Completion Notice. The tenants wrote to the owners stating that various works
were defective or incomplete. On 23 December 2019, the owners issued an Owner's
Completion Notice, setting out that they did not accept that satisfactory completion had
been achieved. They appended the correspondence from the tenants.
5
[8]
The contractors disagreed with the OCN. They commenced negotiations with the
owners. Some matters were agreed, but others remained contested. In September 2020, the
owners told the tenants that they were inclined to agree that Completion had been achieved
on 29 May 2020. The tenants replied that Completion had not occurred. On 1 February
2021, the contractors referred the question of whether, and when, Completion had occurred
to adjudication. The tenants were not convened as parties to that process. The adjudicator
held that Completion had occurred on 17 December 2019 (the date identified by the
contractors).
[9]
The tenants raised the present actions. They seek declarator that Completion has not
occurred and has not been deemed to occur in terms of the RWA. The Scottish Ministers
seek an additional declarator that the contractors "are yet to discharge" their obligation,
under both the RWA and their settlement agreement, to complete the works. They aver that
the owners were not entitled, without their consent, to reach a compromise on the matters in
the OCN which had not in fact been remedied. No new OCN was issued. There was
therefore, according to the tenants, a live dispute on whether Completion had occurred.
The commercial judge
[10]
The commercial judge applied well-established principles of contractual
interpretation as derived from Arnold v Britton [2015] AC 1619 (at paras 14 23) and Ashstead
Plant Hire Co v Granton Central Developments 2020 SC 244 (at paras [9] [17]). The use of
commercial common sense was appropriate where a phrase was capable of bearing more
than one meaning. Clause 3.27 was not capable of bearing more than one meaning. Its
terms were unambiguous. The owners' obligation was to liaise, ie to consult, with the
tenants before intimating to the contractors whether or not they accepted that the works had
6
been satisfactorily completed. The decision on whether to add any elements to the OCN
was one for the owners alone. This form of phraseology was continued in clause 3.28, with
the reference to what should happen if "the Owner" did not accept that the works had been
completed. There was no reference to the tenants in clauses 3.28 to 3.31.
[11]
Clause 3.36, in contrast to 3.27, gave the tenants a right not only of liaison but also to
have any additional elements added to the schedule of defects. It made commercial sense to
treat the two clauses as affording different rights. It made sense to place the decision on
whether to accept that the works had been completed in the hands of the owners, given their
responsibility for the ongoing care of the works, the commencement of the defects period
and that the incidence of insurance fell on them.
[12]
The various settlement agreements formed part of the context against which the
RWA fell to be construed. Nothing in them, including the fact that the tenants' differing
rights to liquidate damages were effectively terminated by the occurrence of Completion,
pointed towards the tenants' interpretation of clause 3.27 being correct. They had no
contractual entitlement to challenge the owners' decision to accept that the works had been
completed on 29 May 2020, to enter into an adjudication with the contractors on that basis,
and to accept the adjudicator's determination that Completion had occurred on 17 December
2019.
[13]
The Scottish Ministers had not pled a separate case in support of their argument that
their settlement agreement conferred a stand-alone right to make a claim against the
contractors for a breach of the RWA.
7
Submissions
Network Rail
[14]
The RWA had to be read in a manner which ensured that the tenants' reasonable and
well-founded views on Completion were included in the Owners' Completion Notice.
There could be no departure from the OCN until satisfactory completion of the matters
raised by the tenants had been achieved. The works had not, as a matter of fact, been
completed because the building was not wind and watertight. The tenants had made
relevant averments to that effect. An inquiry was required. Clause 3.27 had to be read in
the context of the RWA and the settlement agreements between the tenants and the
contractors. The obligation to carry out the works was established by the settlement
agreement, whilst the scope of those works was defined by the RWA.
[15]
The commercial judge erred in concluding that clause 3.27 had only one meaning
and that therefore commercial common sense was not relevant. The literal meaning of the
clause was recognised, but the clause was ambiguous. Commercial common sense
supported the tenants' construction. Completion affected the tenants' rights. A reasonable
person would not attribute a meaning to the clause which undermined these rights.
[16]
The commercial judge's construction violated several principles of contractual
interpretation (Arnold v Britton; Wood v Capita Insurance Services [2017] AC 1173). The parties
to a contract must act reasonably. An obligation to liaise must be intended to have
meaningful content (Apcoa Parking (UK) v Crosslands Properties [2016] CSOH 63 at para [20]).
One party should not be able to determine the parties' rights and liabilities (Van Oord UK v
Dragados UK 2021 SLT 1317 at para [20](iii); R E Brown v GIO Insurance [1998] CLC 650 at
659). Clear words were required to signal a party's intention to give up valuable rights.
Contractual powers must be exercised in good faith, and not capriciously (Braganza v BP
8
Shipping [2015] 1 WLR 1661, at paras [23], [27],[42] and [52]-[53]; Socimer International Bank v
tenants to insist on the inclusion of their complaints in the OCN, the owners were obliged to
serve the notice in good faith, and not to depart from its terms until the matters raised in it
were satisfactorily completed.
The Scottish Ministers
[17]
The Scottish Ministers adopted Network Rail's submissions. The RWA should be
construed as giving the tenants rights: (a) to insist that the contractors carried out the works;
and (b) to seek to establish that the works had not been carried out. The commercial judge's
construction of clause 3.27 made no sense. It gave the tenants no means by which to
challenge the owners' decision that the works had been satisfactorily completed. The
contractors had given collateral warranties to each of the parties whereby they would carry
out the works in compliance with the RWA. The judge's construction made a nonsense of
those warranties. It placed the tenants at the mercy of the owners. The Scottish Ministers
had been granted a collateral warranty in respect of the original refurbishment when they
took up their tenancy in 2006. The judge's construction gave the Ministers no right of
recourse against the contractors. That would mean that the Ministers had surrendered
valuable rights. The overall scheme of the agreements had to be considered, rather than the
natural meaning of the words in the clause (Re Sigma Finance Corp [2010] BCC 40 at para 12).
[18]
Network Rail were correct in their alternative argument that, even if the tenants had
no entitlement to secure inclusion of matters in the OCN, the owners had an obligation to
serve, and insist upon, the notice in good faith. They had failed to do so.
9
[19]
If Completion was only a construct of the RWA, the warranties and other contractual
undertakings given to the Scottish Ministers by the contractors under the settlement
agreement must still be capable of enforcement. There was a separate relevant case pled in
support of the Ministers' second conclusion.
Owners
[20]
The commercial judge's construction of the RWA was correct. The essential features
of contractual interpretation were set out in Wood v Capita Insurance Services (at paras 13-15).
Business common sense only applied where there were "rival meanings". There was only
one possible meaning of clause 3.27. Care was taken throughout the RWA to differentiate
between the parties in order to ensure that specific rights and obligations were directed
towards particular parties. There was no term which supported the proposition that the
owners could not depart from the terms of their OCN without the agreement of the tenants.
Clauses 3.26 3.28 made it clear that the determination of the date on which Completion
occurred was a matter between the owners and the contractors. This was in contrast to the
tenants' rights under clause 3.36 relative to the schedule of defects. Having multiple parties
arguing over the content of the OCN would be unworkable.
[21]
In any event, commercial common sense did not assist the tenants. Completion in
the overall scheme of the RWA signalled the owners' responsibility for insurance. It was
without prejudice to the contractors' other obligations under the RWA, including those
during the defects period. Completion had important consequences. It made no sense for
the owners to be obliged to determine an issue which was raised by the tenants but with
which they did not agree. Unlike the tenants, the owners did not have an interest in
delaying Completion in order to secure liquidate damages or other similar benefits.
10
[22]
A duty to act not only in good faith but also without being arbitrary or unreasonable
arose only in limited situations; typically where one party was acting as a decision maker on
a matter that affected both parties. Such a duty was likely to be found where there was a
significant imbalance of power. It was less likely where both parties were sophisticated and
had legal advice. The tenants had not advanced a case based on such an implied duty or
how that duty had been breached. A duty on a contracting party to act reasonably was a
novel concept.
Contractors
[23]
The contractors adopted the owners' submissions. The commercial judge interpreted
clause 3.27 correctly. The owners had the sole entitlement to determine whether or not the
works had been satisfactorily completed. Clauses 3.26 3.28 treated the owners differently
from the tenants and gave different rights to each. The contents of the OCN were under the
control of the owners, in contrast with the rights given to the tenants in relation to the
schedule of defects.
[24]
There was no ambiguity in the wording of clause 3.27 and it was not appropriate to
rely upon commercial common sense. The words chosen were the most obvious source for
ascertaining the intention of the parties (Arnold v Britton, at para 17).
[25]
The consequences of Completion, whereby the owners assumed liability for the
insurance and care of the works, were consistent with them having the right to determine
whether it had occurred. By serving an OCN, the owners did not avoid their liabilities as
landlords. The tenants' positions were not prejudiced. One party was not at the mercy of
the another. The tenants' settlement agreements could not be an aid to interpretation of the
RWA as their terms were confidential.
11
[26]
The tenants did not plead a case of implied duty. They did not aver facts from which
it could be inferred that the OCN was not both drafted and served reasonably and in good
faith. If such a duty did exist, it was not incumbent upon the contractors. At best the
tenants would have a right of action against the owners for breach of that duty.
[27]
There were no averments in support of the Scottish Ministers' submission that they
had a stand-alone case of a breach of the obligation to carry out the works.
Decision
[28]
In construing clause 3.27, the court must strive to ascertain the intention of the
parties by determining what a reasonable person, having the background knowledge of the
parties, would have understood from the language selected by them (Midlothian Council v
Bracewell Stirling Architects 2018 SCLR 606 LP (Carloway), delivering the opinion of the
court, at 615, following Arnold v Britton [2015] AC 1619, Lord Neuberger at para 15, cited in
Scanmudring v James Fisher MFE 2019 SLT 295, LP (Carloway) at para [47]). The meaning of
the words must be assessed having regard to the other relevant parts of the contract. If there
are two possible constructions, the court is entitled to prefer one which is consistent with
business common sense (Arnold v Britton, Lord Hodge at para 76; Wood v Capita Insurance
Services [2017] AC 1173, Lord Hodge at para 11). The exercise involves balancing, on the one
hand, the language with the factual background and the consequences of any alternative
meanings on the other. "Textualism and contextualism are not conflicting paradigms" (ibid
at para 13).
[29]
Clause 3.27, when read in the context of the Remedial Works Agreement as a whole,
is only capable of one meaning. It is for the owners, and the owners alone, to decide
whether the works have been satisfactorily completed for the purposes of issuing an
12
Owner's Completion Notice. The owners require to liaise with the tenants; that is to say,
they need to consult with them. They may add on matters raised by the tenants, but they
are not obliged to do so. This is made clear by the words "the Owner shall confirm ...
whether or not it accepts" (emphasis added) that the works have been satisfactorily
completed. That interpretation is in turn strengthened by clause 3.28 which refers to what is
to happen if "the Owner does not accept" (emphasis added) that the works have been
completed. Looking more broadly, this meaning is confirmed by the contrasting provision,
in what was a complex contract negotiated and prepared by professionals, in clause 3.36.
This states that the owner must include elements identified by the tenants.
[30]
Commercial common sense does not assist the tenants. Completion is an important
stage in the progress of the contract. Although, in broad terms, the tenants have an interest
in the works being carried out in terms of their own settlement agreements, the primary
interest in Completion is that of the owners and the contractors. It would not make sense to
have the date of Completion fought over by what might be competing views raised by one
or other of the tenants and the owners. Rather, the limited interest of the tenants in this
aspect of the RWA is deemed sufficiently covered by the obligation to liaise. That is no
doubt on the basis that, if there were any substantial matters raised by the tenants, the
owners would take them on board and include them in the OCN. Since the owners are in
control of what goes into the OCN, it follows that they can reach a compromise with the
contractors on its content or refer the issue to an adjudicator. Put another way, the tenants
cannot insist in their concerns being taken to adjudication.
[31]
The purpose of Completion is to commence the defects liability period and to impose
responsibility for insurance and the ongoing care of the works on the owners. It is
important that the owners are able, perhaps in negotiation with the contractors, to fix a
13
Completion date to enable these matters to progress without undue delay or dispute. The
tenants continue to be protected by the provisions in the RWA in relation to defects.
Commercial common sense favours an interpretation of the contract which accords with the
natural meaning of the words used, in their context. The court thus agrees with the
commercial judge (Opinion para [37]) that the tenants have no right to challenge the owners'
decision to accept that the works were satisfactorily completed and to enter into an
adjudication with the contractors about the date when that occurred.
[32]
The court also agrees with the commercial judge that there is no separate case based
upon the contractors' failure to complete the works in terms of clause 2.1 of their settlement
agreement. The Scottish Ministers' second conclusion is not one for damages, based upon
averments of breach of contract. It is for a bare declarator that the contractors have "yet to
discharge" their obligations under the RWA and the settlement agreement. If the Scottish
Ministers wish to found upon the clauses which require the contractors to complete the
works, they should do so by way of an action for specific implement or damages for breach.
[33]
The court will refuse the reclaiming motions and adhere to the commercial judge's
interlocutors of 21 October 2021.