Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
COAL PENSION PROPERTIES LTD against TECHNIP UK LTD [2021] ScotCS CSOH_39 (14 April 2021)
URL: http://www.bailii.org/scot/cases/ScotCS/2021/2021_CSOH_39.html
Cite as:
[2021] CSOH 39,
2021 GWD 15-226,
2021 SLT 1224,
[2021] ScotCS CSOH_39
[
New search]
[
Printable PDF version]
[
Help]
OUTER HOUSE, COURT OF SESSION
[2021] CSOH 39
CA91/20
OPINION OF LORD TYRE
In the cause
COAL PENSION PROPERTIES LIMITED
Pursuer
against
TECHNIP UK LIMITED
Defender
Pursuer: Barne QC; DLA Piper Scotland LLP
Defender: P O'Brien QC; Eversheds Sutherland (International) LLP
14 April 2021
Introduction
[1]
The pursuer is the landlord, and the defender is the former tenant, of business
premises ("the property") at Westhill, Aberdeenshire. The term of the lease to the defender
expired on 15 July 2018. This action is concerned with the defender's liability to the pursuer,
at the end of the term, for the cost of work required to put the property in the state of repair
and condition required by the lease. The principal issue raised is one of interpretation of the
relevant provisions of the lease and, in particular, of the proper construction of the tenant's
obligation to "pay to the landlord the reasonable sum certified by the landlord's surveyor as
being equal to the cost of carrying out such work".
2
The terms of the lease
[2]
In terms of clause 6.1.1, the defender was obliged to keep the property in good and
substantial repair and condition throughout the term of the lease. The defender was not,
however obliged to put the property into any better repair and condition than that shown in
a Schedule of Condition prepared in 2011 at about the time of the commencement of the
lease, except in relation to specific obligations to re-carpet and redecorate the property
immediately prior to the expiry of the lease.
[3]
Clause 17.1 (entitled "To Remove") provided, so far as material, as follows:
"17.1.1 At the end of the Term the Tenant must return the Property to the
Landlord in the state of repair and condition required by this Lease. The Tenant
shall be obliged to re-carpet the Property immediately prior to the expiry of the
Lease using carpet approved by the Landlord whose approval shall not be
unreasonably withheld or delayed. The Landlord and Tenant agree that this
obligation to re-carpet, and also the obligation to decorate in terms of Clause 7.1,
shall be complied with notwithstanding the Schedule of Condition....
17.1.2 If at the end of the Term the Property is not in the state of repair and
condition required by this Lease then at the option of the Landlord eith er:
(a)
the Tenant must carry out at its own cost the works necessary to put
the Property into such repair and condition; or
(b)
the Tenant must pay to the Landlord the reasonable sum certified by
the Landlord's surveyor as being equal to the cost of carrying out such
work and if the Tenant pays to the Landlord the sum as certified together
with the surveyor's reasonable fees in connection with such certificate
within twenty Working Days of written demand the Landlord will accept
that in full satisfaction of the Tenant's liability under this Clause 17 (To
Remove).
...
17.1.5 If the Tenant does not comply with its obligations in this Clause 17 (To
Remove), then, without prejudice to any other right or remedy of the Landlord,
the Tenant must pay the Landlord an amount reasonably equivalent to the Annual
Rent at the rate payable immediately before the end of the Term apportioned pro rata
for the period that it would reasonably take to put the Property into the condition it
3
would have been in had the Tenant performed its obligations under this Clause 17
(To Remove). This amount will be a debt due by the Tenant to the Landlord on
demand.
17.1.6 This Clause 17 (To Remove) will continue to be binding on the parties even
after the end of the Term until the terms of this Clause 17 (To Remove) have been
complied with."
The landlord's demand for payment
[4]
After the lease came to an end, the pursuer served a terminal schedule of
dilapidations on the defender, and intimated that it was electing to claim payment under
clause 17.1.2(b), as opposed to requiring the defender to carry out the works under
clause 17.1.2(a). The pursuer also demanded payment of sums in terms of clause 17.1.5.
Over the following months, the parties discussed the pursuer's claim. The defender did not
accept that the sum claimed by the pursuer was a reasonable one. In particular, the
defender considered that the pursuer's claim did not sufficiently account for the condition of
the property as evidenced by the Schedule of Condition, and did not reflect a correct
understanding of the extent of the works that the defender was liable to carry out in terms of
the lease. Following negotiations, carried out under reference to a Scott Schedule, the
difference between the parties' surveyors' estimates of costs for the remedial works
narrowed but remained significant.
[5]
By letter dated 11 March 2020, the pursuer's solicitors gave a further notice to the
defender, reiterating that the pursuer had elected for payment under clause 17.1.2(b) of the
lease. The letter enclosed a revised Scott Schedule which now included, at its foot, a
certificate dated 10 March 2020 by the pursuer's surveyor. The certificate was in the
following terms:
"I certify that this Scott Schedule and the costs totalling £380,207.27 is an accurate
statement of the costs being equal to the cost of carrying out such repair and
4
remedial works in accordance with the Tenant's repairing obligations together with
the sum of £214,219.70 being the reasonable sum in connection with loss of rent costs
arising from the carrying out of such repair and remedial works and the surveyor's
reasonable fees in connection with the certification of same, all in accordance with
the obligations contained in the Lease between HXRUK 3 (2010) Scotland Limited
and Technip UK Limited dated 27 June and 26 August and registered in the Books of
Council and Session on 4 October, all 2011 as amended, varied and assigned."
[6]
The letter itself referred to the lease, to the notices previously served, and to the
surveyor's certificate, and then stated:
"In accordance with clause 17.1.5, you require to make payment of the certified
sums within 20 Working Days (as such expression is defined in the Lease) of this
said written demand. Payment of the demanded amount totalling £594,426.97
should be made by way of bank transfer to the undernoted account..."
The defender replied, disputing its liability to make payment of the demanded amount.
[7]
In this action, the pursuer concludes for payment of the sums of £380,207.27
and £214,219.70, with interest thereon at the contractual rate from 11 March 2020. In the
alternative, the pursuer concludes for damages consisting of (i) the sum of £380,207.27;
(ii), the sum of £178,194.80, being the pursuer's alleged loss of rent; (iii) the sum
of £36,024.90, being the surveyor's fees for preparation of the schedule; and (iv) the sum
of £4,860.00, being other costs incurred by the pursuer in preparing and serving the notices
and schedules of dilapidations on the defender; all with interest.
Argument for the defender
[8]
The defender's argument was presented as four propositions. Firstly, it was
submitted that no valid demand for payment had been made, because the certificate was
defective. Both the certificate and the accompanying letter proceeded on the basis that the
surveyor had certified a figure of £594,426.97. The certificate purported to certify not merely
the cost of required works under clause 17.1.2(b), but also the lost rent claim potentially
5
arising under clause 17.1.5. The clause 17.1.5 claim was not properly included within the
certificate, and indeed was not payable at all if the tenant paid a reasonable demand within
the specified period. Nor could it be argued that the reference to the clause 17.1.5 claim was
severable. The contractual scheme was that the landlord demanded a certified sum for
repair works; then, if the tenant paid that sum within 20 days of demand, it obtained a
discharge of any obligation under clause 17.1.5 to pay a sum in respect of lost rent. The
commercial purpose was to encourage prompt payment and discourage disputes, and did
not allow the possibility of a partially valid certificate. The pursuer's approach would
undermine this purpose.
[9]
Secondly, it was submitted that on a proper construction of clause 17.1, the
surveyor's certificate was not conclusive as to the tenant's liability under clause 17.1.2(b).
The pursuer's interpretation was highly literal and did not accord with commercial common
sense. The tenant would be unable to argue that an item of work was overpriced, or that it
ought not to have been included at all. He might not even have the opportunity to identify
that an error had been made, since the clause did not require the surveyor to give reasons
for the figure he certified. This could result in a tenant becoming liable for a certified sum
significantly larger than its underlying repair obligations would justify, without the right
to a hearing before a court or the opinion of an independent expert. A non-literal
interpretation that accorded with commercial common sense and with the parties'
fundamental purposes was to be preferred to one that did not. Parties were unlikely to have
intended the disproportionate burden, arbitrariness and potential windfall that could flow
from the pursuer's interpretation: cf Ashtead Plant Hire Co Ltd v Granton Central Developments
Ltd 2020 SC 244. The word "certificate" was not decisive: Beaufort Developments (NI) Ltd v
Gilbert Ash NI Ltd [1999] AC 266, Lord Hoffmann at page 275, especially where, as here, the
6
certificate could have been given on the basis of incomplete information, and was given by
an agent of one of the parties. For these reasons, on a proper construction of the clause,
ascertainment of the amount payable by the defender in respect of repair costs remained at
large for the court.
[10]
Thirdly, in any event, even if the correct amount payable in respect of repair costs
was not at large for the court, the scope for challenge of the certificate was broader than
simply bad faith and subjective unreasonableness. The tenant at least had to be entitled to
challenge the sum certified on the basis that it was not objectively reasonable, having regard
to the true facts and the true underlying legal obligations. This followed from the reference
in clause 17.1.2(b) to "the reasonable sum certified by the Landlord's surveyor..." The
demanded sum had to be both certified and reasonable. The natural meaning of the words
was that the sum had to be reasonable, and not merely the procedure by which it was
calculated. Moreover, the question entrusted to the surveyor was limited to the cost of the
works, and did not extend to any dispute about what the underlying repair obligations
actually were, or what works were required. This reflected the language of the provision:
the words "such work" referred back to clause 17.1.2(a), which in turn referred to the
opening words of clause 17.1.2: "the state of repair and condition required by this Lease".
The contract thus provided for the surveyor to place a figure on the cost of "such works",
which did not imply authority to decide antecedent questions, such as what works were
required.
[11]
Fourthly, the action was premature. No claim could be made for payment under
clause 17.1.5 until there had been a valid demand for payment under clause 17.1.2(b) and the
tenant had had the opportunity to meet the demand within 20 days and discharge its
remaining liability under the clause. Nor could the landlord avoid the clause 17.1 procedure
7
by framing its claim as one for common law damages instead. Properly construed, where
the landlord opted for payment under clause 17.1.2(b), that clause set out an exhaustive
procedure for claiming damages for repair costs and lost rent. The parties cannot have
intended that a parallel claim at common law in respect of the same costs would survive the
discharge provided for by clause 17.1.2(b). That would defeat the purpose of the discharge.
A contract could be construed as excluding common law remedies where it would be
incoherent for them to exist alongside the terms that the parties agreed: cf Scottish Power UK
Argument for the pursuer
[12]
On behalf of the pursuer it was submitted that a valid demand had been made. The
lease did not require any particular formality for the surveyor's certificate or for the
demand. Service of the Scott Schedule, including the certificate, made it clear to the
defender that the pursuer was opting for clause 17.1.2(b). The letter and the certificate itself
made clear that the sum demanded in respect of repair costs was £380,207.27. In order to
avoid liability for lost rent under clause 17.1.5, the defender also had to make payment of
"the surveyor's reasonable fees in connection with such certificate". Accordingly, the level
of those fees required to be intimated to the tenant. It was accepted that the lease did not
provide for certification of the lost rent, but the wording of the certificate, properly
construed, both certified the remedial works in terms of clause 17.1.2(b) and provided the
defender with other requisite information. If necessary, the part of the letter demanding
payment of lost rent was severable.
[13]
The key issue was whether certification under clause 17.1.2(b) was binding on the
parties. That was a question of contractual interpretation. On a proper construction of this
8
clause, the certification was binding. Certification by the surveyor was both a condition
precedent of the tenant's obligation to pay and a definition of the debt. Without it, the
obligation to make payment did not arise because the tenant's liability was what the
landlord's surveyor said it was. That was the ordinary and natural meaning of the words
used, and made commercial sense. It provided an expedited method by which the tenant's
terminal liability could be assessed by an expert. It was unclear on the defender's approach
what role the court could play on review. There was no room for the court to redefine a
liability that, by contractual agreement, was to be defined by the surveyor : cf Beaufort
Developments (NI) Ltd v Gilbert Ash NI Ltd (above), Lord Hoffman at page 273. On the
defender's argument, the certificate served no purpose at all.
[14]
The position under the lease could be contrasted with certain certificates encountered
in construction contracts where the presence or absence of a certificate did not prevent a
party from arguing before an adjudicator, arbitrator or court that a liability existed under the
contract. It could also be contrasted with those leases where the tenant's obligation to pay a
service charge was calculated on a particular basis under reference to the landlord's actual
costs as certified by the landlord In both of these types of case, the liability existed
independently of the certification procedure. Nor was it an objection to the pursuer's
approach that the expert in question was the landlord's surveyor. This did not
automatically constitute a conflict of interest. The surveyor would be expected to carry out
his duty with professionalism. Bad faith would be a ground of challenge.
[15]
Properly construed, the jurisdiction conferred upon the surveyor extended to both
identifying and valuing the requisite remedial works. The defender's alternative
construction was unworkable: if the certificate was not conclusive as to the works required,
the 20 day period would not begin to run until after the parties had been to court to obtain a
9
decision in relation to the scope of the works required, and/or the valuation thereof. That
would be an absurd interpretation and contrary to commercial common sense.
[16]
The defender's averment that the amount certified was grossly excessive was not a
valid objection in the absence of any suggestion of bad faith, fraud or failure to follow
instructions. There was nothing in the pleadings or in the Scott Schedule to suggest that
differences between the pursuer's and defender's surveyors' valuations were anything more
than disagreements in the exercise of professional judgement. There was no basis for the
suggestion that the certificate had to be "objectively reasonable". The word "reasonable"
was an instruction to the surveyor; it did not provide a ground of challenge. It would not
accord with commercial common sense for the court to be able to scrutinise every element of
the Scott Schedule in order to pronounce on whether the amount certified was reasonable.
[17]
As regards the alternative claim for damages, there was a presumption that parties
did not intend to give up rights or claims given to them by the general law: Gilbert-Ash
(Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689. Clear words were required
to exclude or limit that right. In the present case, it was clear that clause 17 did not provide
a complete code since clause 17.1.5 began by stating: "If the Tenant does not comply with its
obligations in this Clause 17 (To Remove), then, without prejudice to any other right or
remedy of the Landlord..." Clause 17 did not merely replicate common law rights; for
example, clause 17.1.2(a) had no common law counterpart. The alternative claim for
damages was made on the basis that there was no valid certificate and therefore no
entitlement under clause 17. There would have been nothing to prevent the pursuer from
ignoring clause 17 and simply claiming damages.
10
[18]
If the pursuer's argument that the certificate was binding was accepted, the pursuer
was at least entitled to interim decree for the lower of the surveyors' respective valuations of
the lost rent, which amounted to £123,961.60.
Decision
(i)
Has there been a valid demand for payment?
[19]
It is unfortunate that the pursuer's solicitors' letter of demand dated 11 March 2020
was not drafted with more careful attention to the terms of clause 17.1. The demand was
clearly disconform to the pursuer's entitlement under that clause, in that it failed to allow for
the defender's right under clause 17.1.5 to discharge its entire liability under the clause by
making payment within 20 days of the amount certified by the landlord's surveyor as being
equal to the cost of the repair works, plus the surveyor's reasonable fees in connection with
the certificate. On any view, a total sum of £594,426.97 was not due on the date when the
letter was sent. As a subsidiary point, the letter also failed to specify the sum demanded by
way of the surveyor's reasonable fees.
[20]
In my opinion, however, it does not follow that no valid demand for payment was
made. The letter was sent under specific reference to the Scott Schedule, which contained
the surveyor's certificate. Although the terms of the certificate are also open to criticism in
that it bears to certify not only the amount of the repair costs but also a further sum
consisting of lost rent and reasonable fees, for which additional certification no provision
was made in the lease, the first two lines (ie to the words "in accordance with the Tenant's
repairing obligations") contain a clear and unequivocal certification in the terms required by
clause 17.1.2(b). It was also clear from the Scott Schedule how the amount of £214,219.70
divided as between lost rent and surveyor's fees; the latter amounted to £36,024.90. The
11
defender was, of course, well aware that there had been a process of negotiation between the
parties' respective surveyors. At the time of receipt of the demand, the defender can h ave
been in no doubt that it was being made under clause 17.1.2(b), that the pursuer's surveyor
had certified the cost of repair works as £380,207.27, and that a further £36,024.90 was being
demanded in respect of surveyor's fees. Although the demand was (incorrectly) made for a
single sum of £594,426.97, that did not in my view mean that the defender's only options
were to pay the whole of that sum or to refuse to pay anything at all. If the defender had
been minded, despite being of the view that either or both of those sums was excessive, to
obtain the benefit of the discharge from liability in clause 17.1.5, it could have done so by
paying those two sums and resisting any further (ill-founded) claim by the pursuer for the
balance. For these reasons, I reject the argument that no valid demand for payment was
made.
(ii)
What was the contractual scope of the certification?
[21]
I find it logical next to address this issue, which falls within the defender's third
proposition. The question is whether the certification authority given by clause 17.1.2(b)
covers only valuation of required repair works, or whether it extends to determination of
what repair works are required. The matter is of importance because it is clear from the
terms of the Scott Schedule that a significant part of the surveyors' disagreement was in
relation to what works were required in order to meet the defender's obligation under
clause 17.1.1 to return the property to the pursuer in the state of repair and condition
required by the lease, as opposed to the cost of works required.
[22]
It was common ground that when construing the provisions of the lease, I should
apply the principles enunciated by Lord Drummond Young, delivering the opinion of the
12
court in Ashtead Plant Hire Co Ltd v Granton Central Developments Ltd (above) at
paragraphs 9-17. I need not set these out at length, but for the purposes of the present case it
is worth emphasising the following points that emerge from that analysis:
1.
A contract must be construed contextually.
2.
The exercise of construction is objective: the meaning of any particular provision
is what a reasonable person in the position of the parties would have understood
it to be.
3.
The court should adopt a purposive approach, ie it should have regard to the
fundamental objectives that reasonable persons in the parties' position would
have had in mind.
4.
The court may have regard to what is generally referred to as commercial (or
business) common sense. In any case where a contractual provision is capable of
bearing more than one meaning, the court should adopt the construction that
best accords with commercial common sense.
5.
In relation to commercial common sense, three features of general business
conduct will frequently be relevant: (i) the notion of quid pro quo, ie that the
obligations of one party are broadly equivalent to the obligations of the other;
(ii) the principle pacta sunt servanda, which implies that parties will normally
avoid the risk of unreasonable or disproportionate burdens; and (iii) the
importance of predictability, which is achieved by the use of a contextual and
purposive construction of the words used, with the application where
appropriate of commercial common sense.
[23]
Needless to say, both parties submitted that the principles thus enunciated
supported their interpretation of clause 17.1.2(b) in relation to the scope of the surveyor's
13
certification. I have come to the conclusion that the pursuer's interpretation is to be
preferred. The defender submitted that by providing for the surveyor to place a figure on
the cost of "such works", it did not confer authority to determine the antecedent question of
what works were required. It seems to me that the clause is capable of bearing either
meaning, and that when one considers context, purpose and commercial common sense, the
opposite interpretation is preferable. The threshold requirement for clause 17.1.2 to have
any application at all is that at the end of the term the property is not in the state of repair
and condition required by the lease. The sub-clause recognises that this has two
consequences: firstly, that expenditure is required on repair works and, secondly, that the
property may not be in tenantable condition until the works have been carried out, and that
there will be a consequential loss of rent. In that context, the incentive afforded to the tenant
by clause 17.1.2(b) is important in relation to interpretation: any liability for lost rent can be
discharged by making payment of the sum certified for repair works within 20 days. This
incentive would make no commercial sense if disputes as to what works were required were
excluded from the scope of the surveyor's certification and reserved for determination by
the court. As the pursuer submitted, that would mean that the 20 day period would not
begin to run until after any such court proceedings had come to an end. The purpose of the
incentive to pay the certified sum promptly, and thereby to allow the repair works to
proceed and the rent loss to be minimised, would be defeated.
[24]
The point made in Ashtead about the notion of quid pro quo is also of relevance in the
context of the present case. Discharge of the tenant's liability for a sum equal to lost rent is a
significant financial benefit to the tenant (indeed the landlord's surveyor's valuation of lost
rent exceeded the ultimate difference between the two surveyors' valuations of the repair
works required). The quid pro quo of that benefit is that the tenant will forego any
14
entitlement to dispute either the "reasonable sum" certified by the landlord's surveyor for
repair costs or the sum claimed by way of reasonable fees. In my opinion this is the
appropriate purposive approach to interpretation of the clause, giving effect to the parties'
objective of achieving a speedy end to any argument about the tenant's liability in relation to
the condition of repair of the property at the end of the lease.
[25]
The inclusion of the word "reasonable", in relation to both the sum certified and the
surveyor's fees, is also significant. The parties to the lease have envisaged that only a
reasonable certification will start the running of the 20 day period. Assuming that the
landlord was as keen as the tenant to obtain prompt agreement to the amount payable by
way of repair costs, it would not have been in the landlord's interest to risk delaying the
running of the 20 day period by making a demand based upon certification of an
unreasonably excessive amount. As the defender submitted, the clause does not provide
that whatever sum is certified by the surveyor must be taken to be reasonable: it provides
rather that the sum must be reasonable, ie within the reasonable range of sums that might be
arrived at by a surveyor acting in good faith and exercising professional skill. It is
noteworthy that in the present case the sum eventually certified was not the sum that the
pursuer's surveyor proposed initially, but one arrived at after negotiation. Although the
clause does not oblige the landlord's surveyor to participate in a process of negotiation, it
seems to me to have been a sensible way to reduce the risk of the sum certified being
challenged as, and after litigation determined to be, unreasonable, resulting in the landlord
losing the benefit that he stood to gain from the clause 17.1.2(b) procedure.
15
(iii)
Is the sum certified binding on the parties?
[26]
Subject to what I have just said regarding the meaning and application of the word
"reasonable", I consider that, properly construed, clause 17.1.2(b) provides for a certification
that is binding on the parties. I agree with the pursuer's submission that the certificate
would otherwise, in the circumstances of this case, serve no purpose. It is the certification
that creates the landlord's entitlement to payment and the tenant's obligation to pay. This is
not a case in which the obligation subsisted independently of the certification; having opted
for clause 17.1.2(b), the pursuer's entitlement rested upon the certification by its surveyor of
a reasonable sum. The case is distinguishable from those where certification is simply part
of the process for obtaining payment, such as an architect's certificate in the course of
construction works, where it remains open for a party to claim an entitlement to payment
even though no certificate has been issued.
[27]
I accept that treating the certificate as conclusive creates the possibility that the
tenant's liability could be conclusively determined to be for an amount that is factually
incorrect (one way or the other) because it contains a latent error or because it was arrived at
on the basis of incomplete information. But, as Lord Denning MR observed in Campbell v
Edwards [1976] 1 WLR 403, the parties are nevertheless bound by the certification because
they have agreed to be bound by it. They must be taken to have accepted the risk of such
error in return for the benefit (to both parties) of obtaining an expeditious determination of
the amounts payable by the tenant in respect of repair costs and fees. It is important to
emphasise once again that the "reasonableness" qualification operates as a control: if the
effect of an error were to render the sum certified unreasonable, there would be no valid
certification and the 20 day period would not begin to run. The same control, in my opinion,
provides an answer to the defender's point that the certificate is being provided by the
16
landlord's agent. Despite being appointed by only one of the parties, the surveyor's
obligation is to certify a reasonable sum. Even if, hypothetically, the surveyor were to certify
a sum towards the upper end of the range of reasonable figures, that could still be regarded
as part of the quid pro quo for the tenant's discharge from liability for lost rent, and accords
with the purpose of the clause and with commercial common sense.
[28]
It is also worth emphasising that in clause 17.1.2(b) the words "sum" and "cost"
appear in the singular. This seems to me to confirm that the parties did not envisage that the
sum certified would be open to dissection with a view to identifying components with
which one or other party disagreed. Again that would defeat the contractual purpose of
speedy resolution to the benefit of both parties. On a proper construction, the parties have
agreed that the figure that is binding upon them, and which must be reasonable, is the total
amount certified by the surveyor.
(iv)
Is the pursuer's alternative claim for common law damages relevant?
[29]
In my opinion, clause 17.1 provided an exhaustive remedy for the pursuer in the
event of the property not being in the state of repair and condition required by the lease at
the end of the term. It provides remedies that are not the same as the landlord's remedies
at common law, and in my view it would make no commercial sense to interpret the lease
as conferring upon the landlord an option eith er to exercise its contractual remedies or to
ignore them and sue for damages at common law instead. In Scottish Power UK plc v BP
Exploration Operating Co Ltd (above), Christopher Clarke LJ, delivering a judgment with
which the other members of the court concurred, referred to the presumption that parties
do not intend to give up rights that the general law gives them, but continued (at
paragraph 30):
17
"[The judge] concluded that the contract only made coherent sense if Article 16.6
provided the sole remedy for under deliveries because Article 16 represented a
contractually agreed mechanism, and because it was inherently improbable in the
light of the scheme and the language of Article 16.5 that, in the case of a breach of
Article 7.1, there should be a different right to compensation. Further the strength of
the presumption is reduced in proportion to the degree of derogation from the
common law position. Article 16.6 is not a pure exclusion clause. It is a clause which
replaces common law rights with a different contractual remedy, which may, in
certain circumstances, be more valuable than the right to damages."
In my opinion, a similar approach is apposite here. In particular, the opportunity afforded
to the tenant to obtain a discharge of any liability for lost rent is a key element of the parties'
bargain, materially departing from the common law, and it cannot have been intended by
the parties that the landlord could deprive the tenant of that opportunity simply by
choosing to make a claim for common law damages. Nor, in my view, are the words
"without prejudice to any other right or remedy of the Landlord" which appear in
clause 17.1.5 of assistance to the pursuer's argument; they relate solely to the claim for lost
rent and do not indicate that any right has been reserved to bypass the remainder of
clause 17.1.
[30]
Senior counsel for the pursuer argued that he was not trying to have his cake and
eat it, but merely to obtain some cake in the eventuality that the landlord's claim under
clause 17.1.2(b) was unsuccessful. The point is academic because I have effectively held in
favour of the landlord on the previous three issues. If, however, hypothetically, the landlord
were to fail in a claim under clause 17.1, there would have to be some reason for that, and it
does not seem to me to accord with the parties' agreement that a common law claim should
simply be allowed to proceed by way of substitution.
18
Disposal
[31]
For these reasons, it would appear that the pursuer is entitled to decree for payment
of the sum certified by the surveyor in respect of repair costs, and also to payment of sums
in respect of (a) the surveyor's fees and (b) lost rent. There may however be further issues to
determine in relation to the latter sums. I shall, as requested, put the case out by order
before pronouncing any interlocutor. Questions of expenses are reserved.