Scottish Court of Session Decisions
You are here:
BAILII >>
Databases >>
Scottish Court of Session Decisions >>
ENERGIEKONTOR UK LTD FOR JUDICIAL REVIEW [2020] ScotCS CSOH_107 (23 December 2020)
URL: http://www.bailii.org/scot/cases/ScotCS/2020/2020_CSOH_107.html
Cite as:
2021 GWD 1-2,
2021 SLT 101,
[2020] ScotCS CSOH_107,
[2020] CSOH 107
[
New search]
[
Printable PDF version]
[
Help]
Page 1 ⇓
OUTER HOUSE, COURT OF SESSION
[2020] CSOH 107
P1176/19
OPINION OF LORD TYRE
in the petition of
ENERGIEKONTOR UK LIMITED
Petitioner
for
Judicial Review of (i) the policy of the Ministry of Defence in connection with safeguarding
the Eskdalemuir Seismic Array, and (ii) the noise budget allocation table prepared and
applied by the Ministry of Defence in that regard
Petitioner: Mure QC; Wright Johnston & Mackenzie LLP
First Respondent (Advocate General for Scotland): Crawford QC; Morton FraserLLP
Third Respondent (CWL Energy Limited): Van der Westhuizen; CMS
23 December 2020
Introduction
[1] The petitioner is a developer of commercial wind farms. The first respondent is the
Advocate General for Scotland, representing the Ministry of Defence (“MOD”). The third
respondent (“CWL”) is another developer of commercial wind farms who has entered the
petition process as an interested party. The petitioner has applied for planning permission
for a wind farm development within the consultation zone surrounding the Eskdalemuir
Seismic Array (“the Array”). That application has been objected to by the MOD in
accordance with a policy intended to prevent wind farm development from interfering with
Page 2 ⇓
2
the operational capabilities of the Array. In this petition for judicial review, the petitioner
challenges the lawfulness of the manner in which the MOD’s policy is currently operated.
[2] The petition initially came before me for a hearing, in terms of section 27B of the
Court of Session Act 1988, as to whether it was equitable to extend the 3 month time limit in
section 27A(1)(a) and grant permission for the application to proceed. That hearing took
place prior to CWL’s entry into process. My opinion dated 17 April 2020 granting
permission to proceed is at [2020] CSOH 37. I have used my summary of the material facts
in that opinion as the basis for the narrative below.
[3] The petition was set down for a substantive hearing which, due to Covid restrictions,
was held remotely. Affidavit evidence was presented on behalf of all par ties. I accept the
evidence as credible and reliable.
The planning background
[4] The Array comprises an array of seismometers capable of detecting vibrations caused
by nuclear tests. It is part of the verification regime provided for in the Comprehensive
Nuclear Test Ban Treaty and operated under the surveillance of the Preparatory
Commission for the Comprehensive Nuclear Test Ban Treaty Organisation. There is an
agreement dated 12 November 1999 (Cm 4675) between the UK and the Preparatory
Commission on the conduct of activities relating to the International Monitoring Facilities
for the Treaty. The Treaty presently has no force in UK domestic law. However, based
upon its obligations under the Treaty and under the Vienna Convention on the Law of
Treaties, it is the UK Government’s policy to protect the Array for the purposes of the
Treaty. The MOD takes the lead through its Safeguarding Department within the Defence
Page 3 ⇓
3
Infrastructure Organisation. That protection includes protection from seismic vibrations
from other sources that could interfere with the Array’s detection capabilities.
[5] The forces acting on wind turbines cause vibrations in their structure, some of which
are transferred to the ground and can travel for many kilometres. A report commissioned
in 2005 (the Styles Report) made recommendations regarding the siting of wind farms in the
vicinity of the Array. The authors of the report recommended an aggregate seismic ground
vibration threshold for all wind farms of 0.335 nanometres (nm) of ground displacement.
This is known as the noise budget. In the light of the Styles Report, the MOD established
two zones around the Array: (i) an exclusion zone of 10km within which the MOD would
object to any wind farm development, and (ii) a consultation zone of 50km within which the
MOD would require to be notified of relevant applications. Paragraph 3 of the Ministry of
Defence (Eskdalemuir Seismic Recording Station) Technical Site Direction 2005 requires a
planning authority to consult the MOD before granting any application for wind farm
development within the 50km zone.
[6] The Eskdalemuir Working Group (“EWG”) was established in 2004 to consider the
potential impact of wind farms in the vicinity of the Array. It is funded by inter alia the
MOD and Renewable UK (formerly the British Wind Energy Association) and is convened
by the Scottish Ministers. Its members include a number of commercial wind farm operators
including the petitioner and CWL. The EWG was responsible for commissioning the Styles
Report and, in 2014, it commissioned a further report (the Xi Report) to re-examine the
Styles methodology. The Xi Report concluded that the 2005 methodology should be
replaced by a physics-based algorithm and that, if this was done, there was “headroom” for
additional wind farm developments within the 0.335 nm noise budget threshold.
Page 4 ⇓
4
[7] MOD policy is to allocate noise budget on a first come first served basis. The basis
upon which the MOD decides whether or not to object to a wind farm development
application is whether the granting of the application would or would not cause the noise
budget threshold to be exceeded. In order to assess whether this would be so, the MOD uses
an Excel spreadsheet called the Noise Budget Tool. This spreadsheet lists all existing and
proposed wind farm developments within the consultation zone, together with inter alia
their capacity, mean distance from the Array, and calculated amplitude (in nm). The effect
of a wind farm development on the noise budget will depend primarily upon the number of
turbines and their proximity to the Array. When a proposed new wind farm development is
added to the spreadsheet, the Noise Budget Tool re-calculates the cumulative amplitude of
the new development together with all of those already appearing in the spreadsheet. By
this means the MOD assesses whether the amplitude of a further proposed development
would cause the cumulative total to exceed the noise budget; if so, an objection will be
lodged. It is very unlikely that a development objected to by the MOD on this ground
would receive planning permission without the MOD having subsequently given its
approval.
[8] The spreadsheet can be used to produce a table, in electronic or print form,
containing details of all existing and proposed windfarm develo pments within the
consultation zone, as at the date when the information is requested. A version of the table
produced for the purposes of the present proceedings has had added to it a further column
entitled “status” (eg “constructed” or “granted”). Proposed developments intimated after
the noise budget has been exceeded are not entered in such a table, but are instead placed by
the MOD, on the same first come first served basis, on a “waiting list” entitled “Eskdalemuir
Applications Since Budget Breached”.
Page 5 ⇓
5
[9] The statutory procedure for obtaining planning permission for a wind farm
development differs according to whether or not the capacity of the proposed development
exceeds 50 megawatts (MW). For a development exceeding that capacity, consent must be
given by the Scottish Ministers under section 36 of the Electricity Act 1989 (an application
requiring such consent is referred to as a section 36 application). The local planning
authority is a statutory consultee. In terms of the Electricity Works (Environmental Impact
Assessment) (Scotland) Regulations 2017, certain (but not all) section 36 applications must be
accompanied by an environmental impact assessment (EIA) report. In terms of
regulation 12(1) of the 2017 Regulations, a developer may (but is not obliged to) ask the
Scottish Ministers to adopt a scoping opinion, which advises on what should be included in
any EIA report accompanying a section 36 application. Where a scoping opinion is
requested, the Scottish Ministers consult the MOD on the proposal.
[10] For a development with a capacity not exceeding 50MW, there is no requirement for
a section 36 consent, and the application for planning permission is made to the local
planning authority under the Town and Country Planning (Scotland) Act 1997. Again,
certain applications must be accompanied by an EIA report, and the developer may (but
need not) ask the planning authority to adopt a scoping opinion which advises on what
should be included in such a report. If a scoping opinion is requested, the MOD will be
consulted.
[11] The issue in the present petition arises out of a distinction drawn in the policy of the
MOD, as regards the allocation of noise budget, between the treatment of applications for
developments with capacity greater than 50MW and of those with capacity not
exceeding 50MW. In relation to a proposed development whose capacity does not
exceed 50MW, noise budget is allocated to the development when the MOD is notified by
Page 6 ⇓
6
the local planning authority of the developer’s planning application. However, in relation
to a proposed development whose capacity exceeds 50MW, noise budget is allocated to the
development when the MOD is notified by the Scottish Ministers of a scoping request by the
developer in relation to an EIA report. The petitioner’s contention in these proceedings is
that this difference in treatment creates a preference in favour of larger (capacity > 50MW)
proposed developments, which will be allocated noise budget at an earlier stage of the
planning process than smaller proposed developments.
The petitioner’s planning application
[12] From about 2015 the petitioner became interested in carrying out wind farm
developments with capacities of less than 50MW at locations within the consultation zone.
In September 2017, the petitioner applied to the local planning authority (Dumfries and
Galloway Council) for a scoping opinion in relation to a proposed windfarm of 14 turbines
at Little Hartfell, near Langholm. The planning authority consulted the MOD who advised
that the noise budget would be “allocated to planning application” [sic] on a first come first
served basis, and that if the budget had been fully allocated at the time of submission of the
application, it was possible that the MOD might object. On 9 February 2018, the petitioner
applied for planning permission for a wind farm at Little Hartfell. The application was
intimated to the MOD. On 26 February 2018 the MOD added the application to its waiting
list. On 13 April 2018, the MOD submitted an objection to the application “due t o the
potential unacceptable impact of the wind farm on the [Array]”, on the ground that the limit
of the noise budget had already been reached. That had occurred by virtue of the Faw Side
application having been allocated noise budget, as narrated below.
Page 7 ⇓
7
[13] On 9 June 2020, Dumfries and Galloway Council granted planning permission for the
Little Hartfell wind farm development. The grant of permission is subject inter alia to a
condition that
“…no part of any turbine shall be erected unless and until a Mitigation Scheme to
address the impact of the development upon the Eskdalemuir Seismic Array has
been submitted to and approved in writing by the Council as planning authority (in
consultation with MoD)”.
CWL’s planning application
[14] On 4 December 2017, CWL submitted a request for a scoping opinion to the Scottish
Ministers’ Energy Consents Unit (ECU) in relation to a proposed wind farm development
consisting of 49 turbines with a maximum generating capacity of 315MW situated at Faw
Side, approximately 11km from the Array. The request was submitted to the MOD by the
ECU on 18 January 2018. On that date, in accordance with the policy narrated above, the
MOD allocated noise budget to the proposed Faw Side development. However, as a
consequence of its location and capacity, the amplitude of the proposed development
(0.674nm) caused the noise budget to be exceeded. By letter dated 6 February 2018, the
MOD informed the ECU that it would object to the development. The ECU issued its
scoping opinion to CWL on 5 April 2018. On 22 May 2019, CWL submitted an application to
the Scottish Ministers for a section 36 consent. By letter dated 26 June 2019, the MOD
objected to the application, on the ground that the reserved noise budget had been reached.
The MOD have since confirmed that the budget would be breached if more than two
turbines were to be built at Faw Side. The application for section 36 consent has not yet been
determined.
Page 8 ⇓
8
Remedies sought by the petitioner
[15] In these proceedings for judicial review, the petitioner seeks:
(i) declarator that the MOD’s policy in respect of the allocation of noise budget to
proposed wind farm developments within the consultation zone is unreasonable,
ultra vires and unlawful; and
(ii) reduction of the MOD’s decision in respect of allocation of noise budget to CWL’s
proposed Faw Side windfarm development, and of the “waiting list” produced as a
consequence of that decision.
The petitioner initially sought reduction of the current table containing the details of noise
budget allocation. However, following clarification in an affidavit lodged by the MOD of
the status of the table as, in effect, no more than an expression of the operation of the Noise
Budget Tool at any given time, and consideration of the MOD’s note of argument prepared
in the light of that clarification, the petitioner refined its submission to seek reduction of the
allocation decision and its immediate consequence for the petitioner’s application.
[16] The MOD does not object to the granting of the declarator sought by the petitioner.
It concedes that its current approach to the allocation of noise budget is unlawful because
(a) it does not have a record of the reasons therefor, and (b) the chronological order of
allocations was not known by developers until about 2018. It makes no concession that its
approach is unlawful for any other reason. Senior counsel for the MOD assured the court
that its intention was to consult in early course on a new approach. The MOD does,
however, oppose the granting of any decree of reduction. For its part, CWL opposes the
granting of both declarator and reduction.
Page 9 ⇓
9
Argument for the petitioner
[17] On behalf of the petitioner it was submitted that the MOD’s policy to list section 36
proposals by reference to the date the MOD is consulted in respect of a scoping request, but
to list 1997 Act applications by reference to the date when the planning authority consulted
the MOD in accordance with the Direction was unreasonable, ultra vires and unlawful.
Distinctions between different groups had to be drawn on a rational basis. The MOD’s
policy discriminated without any rational basis between (a) proposals where the developer
requested a scoping opinion for a proposed development requiring section 36 consent from
the Scottish Ministers and (b) proposals where the developer requested a scoping opinion
for a proposed development requiring planning permission from a local planning authority.
At the same time, it discriminated without any rational basis between (a) applications made
to the Scottish Ministers under section 36 and (b) applications for planning permission made
to planning authorities. In contrast, the policy failed to discriminate (as it ought to do)
between requests for a scoping opinion and applications for planning permission. A
scoping request might or might not lead to a later application for section 36 consent or
planning permission. Years might pass between the scoping request and any eventual
planning application. There was no obligation on developers to request a scoping opinion;
but every developer had to lodge an application for section 36 consent or planning
permission. Protection of the Array did not require the policy currently being operated. The
policy and its effects were also irrational because the MOD’s role was purely to pr otect the
Array and not to promote particular wind farm proposals. The effect of the policy was to
hamper proper planning within the consultation zone in a way that was not necessary for
the Array’s protection.
Page 10 ⇓
10
[18] The MOD did not seek to defend its current policy and offered no justification or
explanation for it. The justifications proposed by CWL were irrelevant. They mostly
consisted of planning considerations which were of no concern to the MOD. The example of
Faw Side itself, a large windfarm close to the exclusion zone in respect of which no
application for consent had been made at the time when it was allocated noise budget, was a
clear demonstration of the irrational nature and consequences of the policy. The
development was obviously not presently deliverable and was preventing the construction
of smaller developments further from the Array. In all of these circumstances the declarator
sought should be granted.
[19] The court should also exercise its discretion to grant decree of reduction in the
revised terms sought; there were no special circumstances to justify withholding it. The
MOD’s policy had always been unlawful and fell to be treated as null from the start. The
MOD had the power to take fresh decisions in respect of noise budget allocation. In order to
prepare the ground for that process, and in any event to ensure that the petitioner had the
opportunity of being treated equally with other developers, the court should reduce the
unlawful decision. Reference was made to the observations of Lord Glennie in Council of the
Law Society of Scotland v Scottish Legal Complaints Commission 2017 SC 718 at paragraph 82.
[20] In the circumstances of the present case, reduction was appropriate. It made clear to
the MOD that it was within its power to re-determine past allocations of noise budget that
had been made pursuant to the unlawful policy, and provided clarity for the anticipated
consultation process. It provided an appropriate remedy for the petitioner and an
opportunity for the MOD to treat the Little Hartfell and Faw Side proposals equally. It
ensured that future planning decisions would not be affected by decisions made under an
unlawful policy. It did not dictate what the MOD’s future policy should be. It did not
Page 11 ⇓
11
disturb allocations of the current noise budget made by the MOD in the past in respect of
any party not represented in these proceedings. It did not affect the MOD’s power to object
to any wind farm proposal that might prejudice the Array, or interfere with any existing
letter of objection. It did not seek to prejudge any issues that might arise as a result of any
re-determination by the MOD of prior allocations. On the contrary, if reduction were not
granted, the court would be stepping in to preserve the consequences of an unlawful
decision. Granting reduction accorded with good public administration. If CWL had a
legitimate expectation in respect of any new policy, that was a matter between the MOD and
CWL and was not an issue for these proceedings.
Argument for the MOD
[21] On behalf of the MOD it was confirmed that there was no opposition to the granting
of the declarator sought by the petitioner, but it was submitted that it was unnecessary and
inappropriate for the court to grant reduction as sought by the petitioner. It would be
academic and serve no useful purpose. The MOD’s objections to the various outstanding
planning applications would remain in place unless and until withdrawn. The condition
attached to the petitioner’s planning permission would not change. The “logjam” of
planning applications objected to by the MOD would not be removed.
[22] The petitioner’s concern that without reduction the declarator would have little
practical effect was unfounded. The issues arising in relation to the MOD’s policy were best
resolved by the imminent consultation process, against a background in which the court’s
declarator (if granted) had cleared the ground. Lord Glennie’s observations in the Council of
the Law Society of Scotland case explained that an ultra vires act can be remedied by the person
responsible. The MOD intended to do so after consultation with interested parties. It was
Page 12 ⇓
12
not for the court to express a view on what the outcome of that consultation should be. In
Salvesen v Riddell 2013 SC (UKSC) 235, the Supreme Court had allowed an opportunity for
an unlawful Act of the Scottish Parliament to be put right; the same approach should be
followed here. Reduction would add nothing to the process of reconsideration of the policy.
A refusal of reduction would not restrict the scope of the reconsideration, whereas the order
sought might have the effect of prejudging the outcome. It was not the MOD’s position that
consultation would only take place if reduction was granted.
Argument for CWL
[23] On behalf of CWL it was submitted that the orders sought by the petitioner should
be refused. It was obvious that the real target of the petition was the MOD’s allocation of
noise budget to Faw Side in preference to the petitioner’s proposed developments at Little
Hartfell and two other sites. CWL was also developing a windfarm at Scoop Hill which
would have a maximum generating capacity of over 500MW and which, like Faw Side, had
been allocated a place in the MOD’s noise budget queue in accordance with the current
policy. The Scottish Government’s renewable energy policies were not about the number of
wind farms but about the amount of renewable energy that could be generated. It was in
the public interest that wind farms contributed to the ambitious renewable energy targets
and that renewable energy capacity was maximised. To date £1,495,839 had been spent in
developing Faw Side and a further £1,546,652 in developing Scoop Hill. In addition,
£1.5 million had been spent on research analysing the MOD’s current noise budget
allocation algorithm with a view to demonstrating to the MOD that there was greater
capacity available. That research would be shared with the MOD and the EWG in due
Page 13 ⇓
13
course. CWL was optimistic that this would enable Faw Side and Scoop Hill to be
developed fully.
[24] UK domestic law did not recognise equal treatment as a distinct principle of
administrative law. Inequality had to be irrational before it was justiciable. The greater the
policy content of a decision the more hesitant the Court ought to be in holding the decision
to be irrational. The Court’s discretion in deciding whether or not to grant or withhold relief
in judicial review proceedings was broad and could take into account many considerations
including the needs of good public administration, the delay in bringing a challenge, the
effect on third parties and the utility of granting the relief sought.
[25] Given that the MOD’s current policy had been operated since 2005, the absence of
any explanation for why it was introduced did not mean that it was irrational. The size of
the allocation of noise budget to Faw Side was a consequence of its size and proximity to the
Array, and not a consequence of the policy under challenge. The petitioner had known since
at least 2015 that there was a risk that the noise budget could be exceeded at any time. The
MOD’s policy was not irrational. Retaining it was one of the options considered in an
options paper prepared by the Scottish Government for the EWG in 2019. The two
categories covered different sizes of wind farms which were already distinguished in terms
of planning consent procedure. Proposals for larger developments were generally more
time consuming and costly, and it was preferable for developers to have certainty with
regard to noise budget allocation before incurring those costs. The majority of smaller
(capacity ≤ 50MW) developments that had already been allocated noise budget had only one
or two turbines and relatively low capacity. It was reasonable to assume that most of the
wind farm development proposals notified to the MOD by local authorities were unlikely to
involve a scoping opinion application, whereas the majority of those notified by the ECU
Page 14 ⇓
14
were likely to have one. In these circumstances, the MOD’s approach in distinguishing
between the two categories in relation to the timing of the allocation of noise budget could
not be said to be so irrational as to violate the common law principle of equality.
[26] Even if, as the petitioner contended, the MOD’s approach protected larger proposals
that had not reached and might never reach the stage of an application for planning
permission to the detriment of smaller proposals that had reached the stage of an
application for planning permission, that would not mean that the MOD’s approach was
irrational. A proposal (large or small) in respect of which noise budget had been allocated,
and which had received section 36 consent or planning permission, was not guaranteed to
be developed. That would similarly be to the disadvantage of other proposals and would
not be a consequence of the MOD’s policy. In any event, a smaller (capacity ≤ 50MW)
development could use more of the noise budget than a larger (capacity > 50MW)
development if it was closer to the edge of the Array. The petitioner’s criticism accordingly
related to how and when, once a development had been allocated a place in the noise budget
queue, it could be removed from the queue, and did not relate to the timing of allocations.
The petitioner had failed to demonstrate that the MOD’s approach was counter to the need
for consistency in public administration or that it gave rise to unintended consequences and
losses.
[27] As regards the granting of an order for reduction, the petitioner’s late change of
position demonstrated that the Faw Side allocation (which the petitioner was now too late to
challenge) had been the real target all along, and the petition ought to have been intimated
to CWL at the outset. If it had been, permission to proceed might not have been granted.
There had been no indication at that time that the MOD might conduct a further
consultation. Reduction of the Faw Side allocation and the waiting list would cause
Page 15 ⇓
15
prejudice not only to CWL but also to other developers whose proposed developments were
on the waiting list. Because of the first come first served priority that it conferred, a place on
the waiting list was almost as important as an allocation of noise budget, and those
developers were not parties to these proceedings. CWL should not be penalised for having
entered the process.
[28] In any event the court should exercise its discretion to refuse reduction. Even if the
MOD were to re-allocate the noise budget, Faw Side would remain as a large development
requiring noise budget allocation, and would be listed in the Table and/or in the waiting list.
In this regard, Faw Side would continue to absorb a large slice of existing or future budget,
which was contrary to the petitioner’s suggestion that the MOD’s current approach
discouraged smaller schemes and undermined renewable energy targets, and the
implication that this would be ameliorated by reduction. The petitioner had made an
application to vary a condition of its Little Hartfell permission, which would require a new
planning application and would put it back behind Faw Side in the noise budget queue. The
petitioner’s delay in bringing proceedings should be taken into account by t he court as an
adverse factor.
[29] Any decree with retrospective effect would cause serious prejudice to CWL. The
development of Faw Side first began in 2016 when the Eskdalemuir area was identified as a
target for development. Scoping applications were submitted as early as possible for both
Faw Side and Scoop Hill inter alia because obtaining an allocation of noise budget from the
MOD was a critical factor in the projects. Following the EWG consultation in 2019, it was
assumed that the issue regarding the MOD’s approach to the allocation of noise budget had
been settled. CWL had reasonably assumed that if the Faw Side allocation had not been
Page 16 ⇓
16
challenged within 3 months, it could be relied upon. Since scoping, costs of £918,467 had
been incurred.
Decision
[30] As Lord Hoffmann observed when delivering the judgment of the Privy Council in
Matadeen v Pointu [1999] AC 98 at page 109, the fact that equality of treatment is a general
principle of rational behaviour does not entail that it should necessarily be a justiciable
principle. It is now settled that the principle of equality, in so far as justiciable, simply
means that distinctions between different groups mu st be drawn on a rational basis, and is
therefore no more than an example of the application of Wednesbury rationality: see R(G) v
Nottinghamshire Healthcare NHS Trust [2010] PTSR 674 (CA) at paragraph 90; R (Gallaher
Group Ltd) v Competition and Markets Authority [2019} AC 96, Lord Carnwath at
paragraphs 24-28. It follows that when expressions such as unlawful and ultra vires are used
in this context they should be taken to mean irrational. That is the test that must be applied
in relation to the policy under challenge in these proceedings.
[31] In my opinion the test of irrationality - or Wednesbury unreasonableness - is met by
the MOD policy in so far as it allocates noise budget to larger (> 50MW capacity) wind farm
developments by reference to the date of a scoping request, but allocates noise budget to
smaller (≤ 50MW capacity) by reference to the date of the planning application. It is
common ground that the planning merits of wind farm applications are of no interest to the
MOD. Whether a proposed development is above or below the 50MW threshold is similarly
a matter of indifference to the MOD. It plays no part in the furtherance of the renewable
energy policies of the Scottish Government and has no view on whether or not those policies
are better promoted by larger windfarm developments. The MOD’s only concern is
Page 17 ⇓
17
protection of the operating capacity of the Array, which it does by intervening in the
planning process when a proposed development would cause the noise budget to be
exceeded. In this regard it must be borne in mind that the maximum generating capacity of
a proposed development is not the only factor in the noise budget calculation; proximity to
the Array is also critical. A large development remote from the Array might require to be
allocated less noise budget than a smaller development close to the Array.
[32] For these reasons it is, in my view, clear that there is no rational justification for the
current policy in that in allocating noise budget it adopts different dates in the planning
process for larger and smaller developments respectively. In so doing it fails to treat like
cases alike and unlike cases differently. The effect of the policy is to afford developers of
larger developments an opportunity to obtain an allocation of noise budget at an earlier
stage of the process than developers of smaller wind farm developments, simply by making
an application to the Scottish Government to adopt a scoping opinion. In circumstances
where, for the reasons discussed, the maximum generating capacity of a development is not
determinative of the matter with which the MOD is concerned, namely whether there is any
headroom within the noise budget, this distinction is irrational, and the breach of the
principle of equality is therefore justiciable. The irrationality goes beyond the two features
accepted by the MOD, namely that the reasoning behind it cannot now be traced and that it
was insufficiently publicised. The MOD has not submitted any rationale at all for allocating
noise budget according to the date of application for a scoping opinion in one category of
case and not in the other.
[33] I am not convinced that any of the explanations suggested by CWL supplies a
rational basis for the policy. In my opinion the petitioner is correct to describe t hem as
mainly consisting of planning considerations that are of no interest to the MOD. Even if it
Page 18 ⇓
18
were the case, as CWL suggested, that applications for scoping opinions are more likely to
be made in relation to larger applications, that would provide no rational justification for
selecting them as the priority date for larger but not for smaller applications. It goes beyond
the ambit of this court’s function to express a view on whether the use of an optional step in
the planning process (application for a scoping opinion) would be an appropriate criterion
for allocating noise budget if applied to all applications; no doubt that is a matter that can
be considered in the forthcoming consultation. But to use such an optional step in relation
to one category of applications and not the other, thereby conferring an advantage on the
former, has not, in my view, been demonstrated to be capable of rational justification.
[34] On the other hand, I am not entirely persuaded by the petitioner’s submission that
the circumstances of the present case demonstrate that the MOD’s current policy has an
adverse effect on the planning of wind farms generally because it can result, as here, in the
allocation of a very large amount of noise budget to a wind farm proposal that has not
reached the stage of a planning application and may not do so for some time to come. That
might be regarded as an adverse effect of allocating noise budget by reference to the date of
a scoping request, but that is not of itself the inequality that I find amounts to irrationality.
The same effect could occur if, for example, the inequality were removed by allocating noise
budget as soon as a scoping request was intimated, regardless of the size of the
development. The circumstances of the present case afford a somewhat extreme example
because the Faw Side development is both large and very close to the exclusion zone, but
such a development would be likely to create a log-jam effect regardless of the priority date
used by the MOD, until such time as either (a) it was removed, for whatever reason, from
the table and the waiting list or (b) the noise budget was increased, for whatever reason, to a
level that would more than accommodate it. It has been correctly emphasised by all parties
Page 19 ⇓
19
that it is not for this court to direct the MOD as to the policy that it should adopt, or to
prejudge the consultation process, beyond making a finding that the policy currently being
operated is unlawful in the sense of being irrational or Wednesbury unreasonable. The latter
is achieved by granting declarator in the terms sought by the petitioner.
[35] I am also satisfied that the petitioner is entitled to more than a bare declarator. In
circumstances where a court holds that administrative action has been unlawful, it is u sual
to grant a practical remedy and not merely to make a declaration of the unlawfulness. In
Council of the Law Society of Scotland v Scottish Legal Complaints Commission, Lord Glennie
(with whom Lord Turnbull agreed) affirmed the existence of the power of a decision-maker
to revisit and to correct a decision that has been shown to be wrong in law, without the need
for court action to set aside the original decision. In particular, Lord Glennie observed (at
paragraph 82), having reviewed the authorities, that
“…it is right and consistent with good public administration that in such
circumstances the decision maker should not only apply the correct interpretation
of the law in the future but should consider whether and to what extent to apply it
retrospectively without everyone affected by the mistaken decisions having to bring
proceedings to correct them.”
[36] That case, however, followed on from a previous decision of the court (Anderson
Strathern LLP v Scottish Legal Complaints Commission 2017 SC 120) in which it had been held
that a particular categorisation of complaints by the Commission was ultra vires, and the
question in the Council of the Law Society of Scotland case was whether the Commission had
power to re-categorise complaints that had been unlawfully categorised without the need
for court proceedings. In the present case the MOD has made clear its intention to revisit its
policy on noise budget allocation, and to take account of the decision of the court in the
present case in so doing. In my opinion, however, the petitioner is entitled to more than a
reconsideration. This application is already before the court, and it seems to me that the
Page 20 ⇓
20
proper comparison is with the Anderson Strathern case itself, in which the issue of the
lawfulness of the categorisation was decided. The court did not simply declare the
categorisation to be unlawful; it quashed the categorisation quoad the case before it. In the
same way it appears to me that the appropriate course of action here is to grant decree of
reduction of the practical manifestation, quoad the petitioner, of the application of the policy
that I have held to be unlawful. After some reconsideration, the petitioner has fixed upon
the MOD’s decision to allocate noise budget to Faw Side, and of the “w aiting list” produced
as a consequence of that decision, as constituting such practical manifestation. I am content
that that is correct and that I should grant decree of reduction in the terms now sought.
[37] On behalf of the MOD it was contended that the ground was more appropriately
cleared for the forthcoming consultation process by the granting of declarator alone, and
that the granting of decree of reduction could prejudice that process. I am not persuaded
that this is correct. It is true that the effect of my decision is to take one option (the status
quo) off the table for the consultation, but that is a necessary and obvious consequence of it
having been held to be irrational, and does not depend upon the granting of reduction. If
anything, it seems to me that the granting of reduction may be helpful to the MOD in
putting beyond doubt that there is no need to include that option in the consultation
process. As senior counsel for the MOD observed during the hearing, the MOD is in a sense
caught up in an argument between rival developers, albeit that it is the author of its own
misfortune by operating an irrational policy. By granting decree of reduction, the ground is
cleared for consultation and, in due course formulation and application of a lawful policy
which will allocate whatever noise budget was available at the time when it was, as I have
held, unlawfully allocated to Faw Side on the basis of its scoping request.
Page 21 ⇓
21
[38] In exercising my discretion to grant reduction, I take account of the fact that such an
order will have no adverse practical consequence as regards any wind farm development
which has either been constructed or in respect of which planning permission has been
granted. Regardless of whether reduction is granted, my decision clearly has an adverse
consequence for CWL in that it loses (at least for the time being, pending implementation of
a new MOD policy) the noise budget allocated to Faw Side on 18 January 2018, and arguably
a further adverse consequence in that Scoop Hill’s position in the waiting list may be
affected. On the other hand, reduction will have no immediate practical consequences. At
the time of the hearing, section 36 consent for the Faw Side development had not been
granted. No construction work has taken place. Moreover, having regard to the fact that the
amplitude of the proposed Faw Side development (0.674nm) is more than double the entire
noise budget of the Array (0.335nm), it must have been apparent to CWL throughout the
period since submission of the scoping application that the MOD would object to the
development and that it would not be likely to proceed unless the calculation of the noise
budget were to be subject to significant change. In that regard, CWL’s optimism that it will
be possible to show that there is greater capacity to allow wind farm development in the
consultation zone and to develop Faw Side in full must, for the time being, be regarded as
speculative. As regards the argument that CWL has proceeded on the basis that the current
policy remained in place following the 2019 review, an affidavit by CWL’s associate director,
Mr Dafydd Rhys Thomson, confirmed that CWL was aware that the petitioner was
continuing to contemplate court action notwithstanding that the 3 month time limit for
commencing judicial review proceedings had elapsed. In my opinion, none of CWL’s
arguments, individually or collectively, outweighs the interests of good public
Page 22 ⇓
22
administration in rectifying the practical consequences of the operation of an irrational
policy.
Disposal
[39] For these reasons I shall grant the orders for declarator and reduction sought by the
petitioner. Questions of expenses are reserved.