OUTER HOUSE, COURT OF SESSION
|
|
|
|
CA55/14
|
OPINION OF LORD MALCOLM
in the cause
MILLER CONSTRUCTION (UK) LIMITED
Pursuers;
against
BUILDING DESIGN PARTNERSHIP LIMITED
Defenders:
________________
|
Pursuers: Richardson; Burness Paull LLP
Defenders: Balfour; Simpson & Marwick
2 May 2014
[1] In this
action Miller Construction (UK) Ltd (the pursuers) ask the court to enforce an
adjudicator's award by granting summary decree ordaining Building Design
Partnership Ltd (the defenders) to pay them £224,044.96, all as part recompense
in respect of the costs arising from the replacement of a defective ventilation
system.
Submissions for the defenders
[2] For the
defenders Mr Balfour explained that the action is resisted on the basis
that the adjudicator's reasoning was inadequate and incoherent. In Diamond
& Others v PJW Enterprises Limited 2004 SC 430, the then
Lord Justice-Clerk, Lord Gill, said that a reasonable reader must be able
to make sense of an adjudicator's decision (paragraph 31). The losing
party is entitled to know why he lost. Counsel also submitted that there had
been a breach of natural justice, in that, without notice, the adjudicator
determined the dispute on a basis which had not been raised by either party. The
pursuer's case before the adjudicator was presented solely on the basis of
alleged professional negligence on the part of the defenders. The adjudicator
held that it had not been proven that the defenders were professionally
negligent. According to Mr Balfour it followed that he was bound to find
in the defender's favour. Counsel observed that the adjudicator held against
the defenders "on some notion of responsibility regarding the installation of
the ventilation system". This was "a frolic of his own". The finding at
paragraph 10.3.2 of the decision, namely that there was no evidence that
it was the defenders who selected the particular type of ventilation unit used
in the system, should have been fatal to the pursuer's case. It was submitted
that the defenders had no obligations in connection with the installation of
the ventilation system. "The issue was never one of responsibility for the
installation." Given the adjudicator's findings, his ultimate decision makes
no sense. In these circumstances summary decree should be refused and the case
put out by order for discussion as to appropriate further procedure.
Submissions for the pursuers
[3] For the pursuers
Mr Richardson contended that the failure of the ventilation system, for
which the defenders had a design responsibility, was, in itself, a breach of
contract on their part. Although there was no finding that the defenders
selected the particular type of ventilation unit used in the system, thereafter
they were involved in design decisions. The phrase "installation of the
ventilation system" might be unfortunate, but a reasonable reading of the
decision as a whole leaves no doubt as to the reasons for the award, and that
it flowed from the case presented to the adjudicator by the pursuers. In
particular the defenders were involved in a collaborative process concerning
the design of a ventilation system which failed to meet the required standard
of performance. The use of the term "installation" should be understood in
this sense. Because the adjudicator held that responsibility for the failure
was shared equally between the parties, he awarded the pursuers only 50% of the
replacement costs. The court was cautioned as to the risk of allowing the
defenders a re-run of their arguments before the adjudicator, and of being
tempted into an examination of the merits of his decision. According to
Mr Richardson it is clear that there is no defence to the action, thus
summary decree should be pronounced.
Discussion
[4] If an
adjudicator's decision is so muddled or confused as to perplex the reasonable
reader, it will not be enforced. However there is no question of muddled or
confused reasoning in respect of this award. On the contrary, the decision and
the reasons leading to it are clear, coherent and readily understandable. In
my view the real issue in the case is whether the adjudicator was entitled to
decide the dispute on the basis which he did.
[5] The
pursuers were appointed as the design and build contractors for a new facility
and associated infrastructure at Motherwell College. The defenders were the
lead consultants. They were the architects for the project, and their services
included acoustic and building services engineering. Following completion,
complaints were made about stuffy classrooms. It was discovered that the
ventilation system did not comply with the contractual requirement of a fresh
air flow rate of 8 litres per person per second. A new system was
installed at a cost of £448,089.33, exclusive of VAT. The pursuers sought to
recover this sum from the defenders, who denied liability, and the adjudication
ensued. Amongst other things the adjudicator was asked to determine that (a)
the defenders undertook responsibility for the design of the development,
including the ventilation system; (b) the defenders did not meet the required
minimum fresh air flow rate in the design of the ventilation system; and (c)
they failed to exercise the standard of skill and care expected of an
ordinarily competent mechanical and electrical engineer/lead consultant.
[6] Amongst
other things, the defenders sought a finding from the adjudicator that the
pursuers had failed to prove a breach of contract on their part. They averred
that, in order to save money, the pursuers decided to change the type of
ventilation unit to be used in the system from "Passivent" to "Renson" units.
"As a result the ventilation system was inadequate to meet the contractual
requirements". There was no requirement on the defenders to examine the design
of proprietary products supplied by the contractors. It was claimed that the
defenders were not liable. It was averred that the defenders advised the
pursuers that Passivent units were the only suitable solution of which they
were aware. In short, the defenders blamed the deficiencies on the pursuers'
decision to use Renson units rather than those specified by the defenders.
But for that, all would have been well.
[7] In his
decision the adjudicator noted that the dispute concerned factual and
contractual differences of importance. He had regard to evidence led on behalf
of the pursuers to the effect that it was the design team which concluded that
the initial Passivent design was unsuitable. The design development process
continued for some months. It was said that it was only after confirmation
from the defenders and the sub-consultants for building services (Aecom) that
the pursuers instructed purchase of the Renson units. One witness accepted
that there was a cost saving, but claimed that this was not the reason for the
change. There was evidence that the defenders and Aecom communicated directly
with Renson throughout the design period.
[8] The
adjudicator's decision includes reference to the expert reports submitted by
the parties. Mr Williamson's stated that the defenders and Aecom had a
duty to coordinate the alternative Renson proposal into the overall design.
Another, Mr Morris, said that it was for the designers of the building and
the ventilation system to determine and assess whether the pressure differences
required to provide the necessary air flow would be present at all times. Had
this been done, it would have been evident that the 8 litres per person
per second requirement would not be met if the Renson units were used.
[9] The
adjudicator noted that there were significant factual disputes between the
parties, and differences as to "which party carries responsibility for the
installation of a Renson system which failed to meet the employers'
requirements, and which should bear the costs of replacing the Renson system
with an acceptable Passivent system" (paragraph 9.1). Counsel for the
defenders takes exception to this formulation, but in my view it is an entirely
reasonable description of the issues put before the adjudicator by both
parties. The adjudicator observed that the pursuers blame the design team for
the change to the Renson units, thus it is said that the defenders, as lead
consultants, should take full responsibility for the subsequent failures. On
the other hand, the defenders blame the pursuers for instructing a purely cost
saving measure, and claim that they were not in breach of any of their duties
(paragraphs 9.2/3).
[10] In chapter 10
of the decision, the adjudicator set out his findings on the relevant issues.
He thought it probable that the change to Renson units was made by the pursuers
as a cost saving measure. He found no evidence that the defenders were involved
in the selection of the Renson units. The Renson system failed because in
certain circumstances the Renson units could not match their stated performance
data. Both parties were involved in the process of managing the installation
of the units. There was a design failure in that, as an overall concept, it failed
to meet the contractual performance requirements. The adjudicator noted that
the pursuers relied upon a term of the contract that the contractors would have
no liability in respect of any defect, insufficiency or fault in the
consultant's design; and that the defenders referred to another provision
which stated that the consultants need not examine the design of proprietary
products supplied by the contractors. At paragraph 10.8 the adjudicator
concluded that neither party could place all of the responsibility for the
selection and installation of the inadequate Renson system on the other party.
The defenders did not design the Renson system, however they "did have
obligations and responsibilities in respect of the installation of the
system". By this I understand the adjudicator to mean that the defenders did
not choose to use Renson units, but this did not discharge them of all
contractual responsibilities for the effectiveness of the system as a whole.
[11] The
adjudicator was not persuaded that the defenders fell below the standard of
skill and care expected from reasonably competent lead consultants. He
explained that there was a substantial element of unpredictability in the
assessment of air flows in the new buildings. "Both parties took risks in
assuming that the Renson system would meet the contractual requirements. I
find that the parties share responsibility" (paragraph 10.9). The
adjudicator decided that the parties should be liable for the replacement costs
on a 50-50 basis, hence the award of just over £224,000.
[12] This
reasoning was carried forward into the adjudicator's decisions on the redress
sought by the parties. They included that the defenders undertook
responsibility for the design of the development, including the ventilation
system, under exception of products manufactured or supplied by contractors or
sub-contractors. In other words, while the defenders had no involvement in the
choice of the Renson units, as lead consultants they retained a degree of
accountability for the performance of the ventilation system as a whole. They
could not simply wash their hands of the subsequent failure to meet the
contractual requirements as to air flow. The adjudicator made it clear that he
was not deciding the case on the basis of the allegation of a failure to
demonstrate the care and skill expected of lead consultants, but rather on the
defenders' obligation to design a system which complied with the contract
specifications.
[13] One can
understand why the defenders are disappointed with the decision. They
succeeded in putting the blame for the choice of the Renson units on the
pursuers' desire to save costs. Without that change, in all probability the
system as originally designed would have worked well. Furthermore the pursuers
failed to prove that the defenders were professionally negligent. However the
court's task is not to assess the merits of the decision, nor to discuss the
substance of the dispute referred to the adjudication. The question is whether
the adjudicator was entitled to reach the decision summarised above.
Essentially the defenders claim that the pursuers' case was perilled on the
allegation of professional negligence, and that there was no scope for a finding
of breach of contract upon some other basis. In the defences to the action it
is averred that the adjudicator determined matters on the basis of which party
bore "responsibility", which "was not the issue that had been remitted to him
for his determination." The defenders should have been given an opportunity to
address the approach which found favour with the adjudicator, hence there was a
substantial breach of natural justice.
Decision
[14] In my view
the defenders have taken too narrow a view as to the issues in the
adjudication, and as to the scope of the adjudicator's decision-making powers.
The broad issue remitted to him was to determine whether the defenders
undertook responsibility for the design of a ventilation system which failed to
meet the minimum fresh air flow rate requirement. It is true that there was an
offer to prove professional negligence in the Hunter v Hanley
sense, but I find nothing to support the view that the pursuer's case depended upon
that, or that it was not open to the adjudicator to conclude that the lead
consultants carried some responsibility for the deficiencies in the ventilation
system given their design obligations and ongoing involvement in the design
process once the Renson units were chosen. At paragraph 6.1.4 of the
Notice of Intention to Refer, the pursuers allege that the defenders were in
breach of contract and further in any event they failed to meet the
standard of skill and care required of a competent mechanical and electrical
engineer in providing a defective design (emphasis added). Furthermore, it
appears from the defenders' rejoinder to one of the submissions to the
adjudicator that they fully appreciated that the pursuers' case was not
dependent upon proof of negligence. At paragraph 2.1 of production 6/7,
the defenders stated:
"The referring party's case proceeds on an erroneous hypothesis, namely that by demonstrating the minimum airflow was not met, an inference arises that the respondent was in material breach of contract. The contractual test which the respondent requires to meet is not one of fitness for purpose but rather one of failing to meet the standard required of an ordinary competent professional exercising appropriate skill and care."
[15] No doubt
one possible outcome of the adjudication was that the pursuers, having
specified the Renson units in place of the apparently satisfactory Passivent
units originally chosen by the design team, should be held wholly responsible
for the unsatisfactory outcome. However there was evidence before the
adjudicator that the defenders and the sub-consultants communicated directly
with Renson throughout the design period, and there was expert evidence that
they required to coordinate the alternative Renson units into the overall
design. Another expert was of the view that there should have been an
assessment by the defenders of the suitability of the Renson units to provide
the required performance, and that, had this been done, it would have been
apparent that the required air flow rate would not be met. It seems to me that
there was scope and a basis for the view that the defender's design duties and
obligations did not end when the Renson units were specified by the pursuers.
Thereafter the decision to share liability on an equal basis was within the
discretion of the adjudicator.
[16] I agree
with Mr Richardson's submission that Mr Balfour took an overly strict
view of the adjudicator's use of the phrase "installation of the system." The
adjudicator had firmly in mind the overall design obligations undertaken by the
defenders, and, on a fair reading of his decision as a whole, it is clear that
he was not criticising the workmanship involved in the installation, but rather
the defenders' post-Renson unit ongoing involvement and collaboration in
respect of a ventilation system which proved to be inadequate for the buildings
concerned. No doubt if the defenders had done no more than provide a document
setting out a system using the Passivent units, and then, without their
knowledge or involvement, the pursuers used that design but substituting Renson
units, the outcome might have been different; but the adjudicator's findings
paint a very different picture. There may be some infelicities in the
expression of certain parts of the decision, and a lawyer might have expressed
matters differently, however none of that gives me any cause for concern.
[17] It is well
established in the authorities that an adjudicator is given considerable leeway,
and that the court should be very slow to refuse enforcement on the grounds of
breach of natural justice or that the adjudicator exceeded his jurisdiction.
For example, reference can be made to the decision in the case of Diamond (cited
earlier), and to the judgment of Chadwick LJ in Carillion Construction
Limited v Devenport Royal Dockyard Limited [2006] BLR 15 at
paragraphs 52/3 and 84/7. Amongst other things it was confirmed that an
adjudicator is not required to adopt one or other of the parties' submissions.
He can take an intermediate position without giving notice of his intention to
do so. The remedy for the disappointed party is to resort to litigation or
arbitration to establish the correct position in fact and law.
[18] I have
already held that the adjudicator's reasoning was clear and coherent. I am
also satisfied that he was entitled to proceed as he did, and that the decision
was within the scope of the dispute referred to him. He did not embark upon
the suggested "frolic of his own". There was no unfairness by not giving the
defenders an opportunity for further submissions in respect of the
adjudicator's intended approach. In my opinion there is no sound basis for
challenging this award and the defence to the action must fail. There is
nothing to be gained by further procedure. I shall grant summary decree in the
terms sought by the pursuers.