OUTER HOUSE, COURT OF SESSION
|
|
|
|
CA197/13
|
OPINION OF LORD MALCOLM
in the cause
BRITISH TELECOMMUNICATIONS plc
Pursuer;
against
COMMON SERVICES AGENCY
Defender:
________________
|
Pursuer: Crawford QC, J MacGregor; CMS Cameron McKenna (Scotland) LLP
Defender: Dunlop QC, Duthie; Dundas & Wilson LLP
7 February 2014
[1] In this
action the pursuer, British Telecommunications plc (BT) seeks an order under
regulation 48 of the Public Contracts (Scotland) Regulations 2012 ("the
regulations") setting aside the defender's decision to appoint Capita plc as
the preferred bidder in relation to the procurement exercise concerning the
Scottish Wide Area Network (SWAN), failing which for payment of damages of
£20m. The pursuer describes SWAN as the creation of a single, holistic
telecommunications service available for the use of any, and potentially, all
public service organisations in Scotland. The defender is the Common Services
Agency (also known as NHS National Services Scotland). Bearing in mind the
need for expedition, an early diet of debate was fixed. After that hearing,
and having taken a few days to allow reflection and consideration of the
papers, I delivered the following ruling in open court.
The ruling after the debate
[2] The
pursuer asks the court to set aside the defender's decision to appoint Capita
as the preferred bidder and to order a new SWAN procurement exercise, failing
which an award of damages. Capita has not entered the process. The raising of
the action has prevented the completion of the contract. An expedited hearing
took place on 16 and 17 January. On behalf of the defender,
Mr Dunlop Q.C. moved the court to dismiss the action, founding on
pleas of time bar, competency, and relevancy. For the pursuer Ms Crawford
Q.C. sought a proof before answer. Mr Dunlop did not move for an interim
order, not even as a fall-back position. (An interim order under regulation 47(9)(b)
would lift the prohibition on the completion of the contract with Capita - as
would dismissal of the action.) Both counsel invited the court to put the case
out by order so that the parties could reflect on the implications of its
ruling on the issues debated at the hearing, and decide on the appropriate
further procedure, including whether an interim order might be sought.
[3] Mr Dunlop
described the pursuer's complaint about non-disclosure of a particular aspect
of the scoring of the bids as "the nub of the case". I agree with him on
this. Although Ms Crawford sought no more than a proof, Mr Dunlop urged
the court to rule on this matter now, citing the Second Division's recent
emphasis on an objective approach based upon how a reasonable tenderer would
read and understand the documents (Healthcare at Home Ltd v Common
Services Agency 2013 SC 411). He submitted that there was no need for
evidence on this point. If there is a problem with the procurement process,
the defender would prefer to know about it sooner than later. Whilst stressing
that there is no allegation of illegitimate conduct, Mr Dunlop noted that
the pursuer is the incumbent provider, the inference being that it may be less
concerned about a delay in the resolution of the case. I now turn to what has
been described as the nub of the case.
[4] A large
number of the challenges narrated in the summons have a common theme. As
elaborated upon in the course of the hearing, it can be described as follows. An
output based specification (OBS) set out the specific requirements for the SWAN
services. The final version, upon which tenderers were to form their bid, was
dated 13 September 2013 and is 6/4 of process. Section 3 of
production 6/2 sets out the evaluation criteria and scoring methodology to be
used to assess the tenders and identify the most economically advantageous
bid. The OBS contains percentage weightings for the various aspects of the
bids. By the final stage of the process, 35% was allocated to technical
issues, 30% to commercial/legal, and 35% to affordability/price.
[5] These
three headings were described as level 1 sub-criteria. They were each
divided into level 2 sub-criteria, and so on, down to level 4
sub-criteria in respect of the initial sub-portfolio of services in the
technical section. Each level 2 sub-criterion was allocated a certain amount
of the overall percentage; for example, the initial portfolio of services
level 2 sub-criterion carried 12%, meaning that it bore more than a third of
the total percentage attributed to the technical section. That 12% was spread
over four level 3 sub-criteria in varying proportions; for example one
carried 4%, with that 4% split between two level four sub-criteria, with
3% to one and 1% to the other. All of this is shown diagrammatically at
pages 10 and 11 of production 6/2.
[6] During the
hearing counsel discussed the point at issue by reference to the customer
engagement section of the technical chapter in the OBS, though this could
equally have been done by reference to other aspects wherever a sub- criterion
contains a number of individual requirements. The customer engagement section
is at chapter 5 of the OBS and includes various sub-chapters, for example
account management, customer satisfaction, and training. Over the whole
chapter there are eight individual requirements, each with a unique
identification reference. For example, CEN001 calls for a description of an
account management structure, and CEN007 asks for suggestions as to SWAN
related training courses.
[7] Of the 35%
allocated to the technical section of the OBS, 1% was allocated to the customer
engagement section. Section 3.2 of production 6/2 sets out the technical
evaluation and scoring methodology. Before turning to it, it is important to explain
how the defenders scored the bids, all as described by Mr Dunlop at the
hearing. This was illustrated by reference to the customer engagement
section. Counsel explained that on the marking range of 0-5, a cumulo
decision was made on the responses to all eight individual requirements in the
section. The possible scores were 0, 1, 3 or 5. In order to obtain a 3 or a
5, a bidder would need to meet all the requirements in each section, by which I
understood Mr Dunlop to mean the basic or minimum response needed for each
requirement. There were no pre-ordained relative weightings as between the
individual requirements, but if one requirement was not met, and no matter how
meritorious the bid was in respect of the others, the maximum possible score was
then 1 out of 5. A failure to meet the basics of one requirement necessarily
limited the maximum overall score to 1 out of 5. By contrast, if all the
requirements were just met, a bid could score a 3. If all the requirements
were satisfied it would be open to the scorers to award a 5, if overall the
responses so merited. The pursuer's complaint is that, until a post decision
de-briefing on 15 November 2013, it was unaware that a failure to satisfy
the basics on one requirement would so limit the maximum possible score. The
defender submits that this would have been clear to any reasonable bidder
reading production 6/2 and its predecessor documents. Thus the complaint
of non-disclosure of this element of the evaluation criteria and scoring
methodology should be rejected.
[8] Ms Crawford
submitted that knowledge of the consequences of missing out on one requirement
would have had an impact on the preparation and the content of the pursuer's
tender. It was understood that the requirements would be assessed
cumulatively, and an overall score of up to 5 awarded accordingly, with
regard being had to all the responses. Thus, for example, a near miss on one
requirement could be compensated by good responses in the others.
Mr Dunlop observed that the specific complaints made in the summons tend
to relate to those aspects of the bid where the pursuers scored a 1, suggesting
that this issue is at the heart of the dispute between the parties. Both Ms
Crawford and Mr Dunlop proceeded upon the basis that the question turns on how
a reasonably diligent, competent and informed tenderer would have understood
section 3.2 of production 6/2. I therefore turn to consider that section.
[9] At the
outset I notice what, to my mind at any rate, is an uncertainty as to the meaning
of the term "referenced statement". If one simply reads the narrative without
reference to the glossary of terms in schedule 1, "referenced statement"
relates to the sub-criteria described in the immediately preceding part of the
document. This comes across strongly in the second paragraph of
section 3.2. The fifth paragraph makes it clear that each sub-criterion
will be given a score out of 5. The narrative does not recognise or
address the issue of a sub-criterion with a number of individual requirements
within it, for example the eight requirements in the customer engagement
level 2 sub-criterion. The narrative in section 3.2 indicates that
the eight responses to the individual requirements will be given a score on a
cumulative basis, for example a 3, which would then mean 0.6% being added to
the overall score of the bid (0.6% being 3/5ths of 1%). Doubts may
creep in if one looks at the definition of "referenced statement" in the
glossary of terms at schedule 1, and to the terms of table 2 in
section 3.2. Table 2 appears to recognise only one requirement being
scored out of 5, and the definition equiperates "referenced statement"
with the individual requirements identified by a unique reference code. This
suggests that one should attempt to read section 3.2 on the basis that
each of the requirements in the customer engagement is a separate referenced
statement. This is not an easy task. All would be well if each sub-criterion
contained only one requirement, but this is not always the case. It may be
that the drafter overlooked the apparent conflict between the terms of the
narrative in section 3.2 and the definition of referenced statement in
schedule 1.
[10] Having said
all that, the key question is, did the document disclose the scoring
methodology which was employed, including that to miss the basics in one of a
number of requirements would limit the maximum possible mark to 1 out of 5? No
matter how one might attempt to reconcile the ambiguity which I have discussed,
in my opinion the answer to this question is no. If an individual score was
reached for each requirement, on the basis of the text in section 3.2 the
bidder would expect, and in my view would be entitled to expect, that at the
end of the exercise there would be a cumulative assessment for the
sub-criterion as a whole, with at least the potential for a score of 3 or
above, even if one requirement achieved only a zero or a 1. If, on the other
hand, there were no individual scores for each requirement, but simply one
overall score awarded with regard to the responses as a whole, again the bidder
would not have been told that the maximum mark is a 1 if there is a failure to
meet the minimum in respect of one of the requirements.
[11] All of this
is disclosed most clearly from the terms of the second paragraph in section
3.2, but is also implicit in the rest of the section. In any event, one
searches in vain for any express explanation of the consequences for the
overall mark if one requirement is missed. In my opinion the reasonable
tenderer would not understand that in such circumstances the maximum possible
score is 1 out of 5. It follows that the scoring methodology involved a
departure from that set out in the relevant documents. I uphold the pursuer's
submission as to the proper understanding of the terms of section 3.2 and equivalent
passages in production 6/2. I reject Mr Dunlop's submission that the
practice adopted by the scorers should have been anticipated by the reasonable
reader of section 3.2. As a result the pursuer is also justified in saying
that there was no reason to suspect that anything was amiss in this regard
until the meeting in mid-November. As Mr Dunlop recognised, this has
implications for the time bar plea.
[12] My
understanding is that both counsel proceeded upon the basis that such a ruling
would mean that, having regard to the legal propositions set out in
paragraph 122 of Mr Justice Ramsey's judgment in the case of Mears
Limited v Leeds City Council [2011] EWHC 1031 (TCC), there
was a breach of the transparency requirement in regulation 4(3). If I am
wrong on that, the issue can be explored at the by order hearing. In any event
the question arises as to any remedy to which the pursuer may be entitled.
Again I expect parties' position on the implications of this ruling to be
clarified at the next hearing.
[13] The above
decision relates directly to the grounds of challenge in articles 16-30 of
the condescendence of the summons. However the same complaint does, to varying
degrees, have relevance to at least some of the other complaints in the
summons. So far as these alternative grounds of challenge are concerned, for
example, manifest error and failure to seek clarifications, I prefer the
submissions for the defender, and this largely for the reasons given in its
note of argument as elaborated upon by Mr Dunlop at the hearing last
week. However, I will make further brief comments by way of explanation.
[14] Insofar as
the averments in article 31 criticise the scores awarded, and also matters
of marking judgment distinct from the section 3.2 issue, in my view they are
not relevant to a proper challenge under the regulations. The authorities are
clear that the court should not become embroiled in a review of the merits of
the assessment process itself. Similar remarks apply to the averments in
articles 32, 33 and 34.
[15] With regard
to the averments in articles 35 and 36, in my opinion, even if proved,
they are insufficient to demonstrate manifest error. Again I consider that the
pursuer is simply seeking to open up an investigation into the facts and the
substance of the decision-making process itself. Similar comments apply in
respect of article 37. The defender proceeded on the basis of the terms
of the pursuer's bid. The section 3.2 issue may be relevant to these
complaints, in that in this chapter BT was given a 1, and Capita a 5.
[16] Articles 38
to 42 aver a failure to seek various clarifications of the pursuer's bid. In
my view there is no real prospect of the pursuer proving that the defender was
required to make any of the suggested requests. At most, these were
discretionary matters for it to weigh up and decide. Articles 43-45 set
out a challenge based on an alleged failure to provide adequate reasons for the
decision on the bids. I agree with Mr Dunlop's proposition that the
averments are lacking in specification, and with his submission that the
reasons and explanations proffered to the pursuer were sufficient to comply
with the requirements of the relevant regulation.
[17] As
mentioned at the outset, the defender has a plea of time bar. This was based
on its understanding of the pursuer's case in articles 16-30 of the
pleadings, which refer to a failure to disclose the relative weightings of the
requirements within a sub-criterion. It was said that, if there is merit in
this complaint, it could have been taken at a much earlier stage when the
relevant documents were issued. However, by the close of the discussion last
week, the exact nature of the main complaint was clarified in such a way that
Mr Dunlop acknowledged, in my view rightly, that the pursuer could not
have been aware of it before the meeting on 15 November 2013. It
follows that it is not caught by the time bar provisions in the regulations.
[18] This leaves
only the plea to the competency of the action, which was based on a complaint
that the pursuer's agents' letter, 6/18 of process, failed to meet the
requirements of regulation 47(6), in that there was insufficient notice of the
grounds of complaint. (The timing point was not pursued.) It was said that
the letter is generic, and should have been more specific as to the particular
allegations of breach of duty. While it is true that the pursuer cannot open
up new fronts in the action, I am not persuaded that anything of that nature
has occurred, nor that there was any fundamental deficiency in the terms of the
letter as would prevent all or any of the challenges in the summons. I see no
merit in the competency plea.
[19] A few days
later a further hearing took place. Both parties presented submissions on
further procedure in the light of the above decision. Thereafter I advised
parties as follows, again in open court.
The ruling after the second hearing
[20] Having decided
that there has been a breach of the regulations, I now require to deal with an
application by the pursuer for an order setting aside the decision to award the
SWAN contract to Capita, and with the defender's request for an order in terms
of regulation 47(9)(b) which would allow the contract to be concluded,
thus limiting the pursuer's remedy to damages. Mr Dunlop withdrew a
motion for dismissal after Ms Crawford tendered a minute of amendment
elaborating upon how the pursuer intends to demonstrate that the breach of the
regulations had an impact on the terms of the pursuer's bid.
[21] I deal
firstly with the pursuer's motion for a set aside order. Both counsel accepted
that, in terms of regulation 48(1)(b), the court enjoys a broad discretion
to select the most appropriate remedy for a breach of the regulations. The
pursuer argues for an order which would result in a re-run of the process, at
least from the invitation to submit a final tender stage. The defender
contends that the court should allow the contract to proceed, meantime
preserving the pursuer's right to seek damages for any loss caused by the
irregularity.
[22] I now
summarise the submissions tendered by Ms Crawford on behalf of the
pursuer. Ms Crawford emphasised that, because of the non-disclosure of
part of the scoring methodology, BT was prevented from putting forward its best
bid, or, in other words, the one most likely to win the competition. It is
this which gives BT a cause of action and the right to seek reduction of the
decision. Evidence is not required to allow this to be resolved in BT's
favour. Full knowledge of the scoring methodology would have had an impact on
the whole bid, not just on the two sections in the technical chapter where a
score of one was achieved. The primary remedy should be one which corrects the
flaw in the procedure, and thereby allows a re-run avoiding the illegality
which has tainted the bidding and scoring process so far. There has been a
breach of the regulations, and to sanction the contract would award Capita what
were described as "poisoned fruits". Ms Crawford submitted that, for
actionability in terms of regulation 47(5), it is enough for the pursuer
to demonstrate a risk of harm, thereby opening up the possibility of reduction
of the decision. It is not necessary to prove that on full disclosure the
pursuer would have won the competition. Such issues arise only in the context
of a damages claim. According to Ms Crawford the defenders should not be
allowed to breach the regulations, as she put it, with impunity. Substantial
weight should be given to the public interest in a lawful and transparent
procurement exercise, especially in a matter of considerable public importance.
[23] With
reference to Ms Sue Edwards' affidavit, the view is that the delay need be
for no more than 6 to 8 weeks. It would not be necessary to rewind to the
start of the whole process. Any immediate problems for Education Scotland and
the Pathfinder (South) Councils (Scottish Borders and Dumfries and Galloway
Councils) can be resolved in the longer term. As for the information disclosed
to parties after the decision, this was simply a consequence of an application
of the regulations. Acknowledging that there are few reported decisions where
the court has set aside a decision, the norm being the grant of an interim
order, particular reliance was placed upon two Northern Irish judgments, to
which I will return. It was submitted that an award of damages would mean that
BT were deprived of "a fair crack of the whip", and that a damages claim would
be unlikely to address reputational damage to the company from losing out on
the SWAN project. To quash the decision would respect the core purpose of the
regulations, minimise injustice, and provide an effective review of the
procurement exercise.
[24] Turning to
Mr Dunlop's submissions on behalf of the defender, he recognised that they
are relevant to both of the applications before the court. He suggested that
the pursuer will struggle to prove that the non-disclosure of part of the
scoring methodology made a difference to the outcome of the competition.
Production 6/12 reveals the amount of ground which BT need to make up.
For example, it would not be enough to substitute marks of five for the scores
of one in the technical section. He noted that, in terms of the minute of
amendment, the pursuer offers to prove only that it is possible that BT would
have won the contract. Notwithstanding the irregularity in the process, this
remains a weak case on the merits. The court should not order a re-run just
because BT might have won. Without a stronger case on the operative effect of
the problem, a damages claim is a sufficient and appropriate remedy. Reliance
was placed upon Ramsey J's judgment in the case of Mears (cited earlier).
This was an example of the court restricting the claim for a proven breach to
one of damages. There is no presumption in favour of reduction as a primary
remedy. Everything depends upon the particular circumstances of the particular
case.
[25] Counsel
suggested that Ms Crawford had no satisfactory answer to the question:
what is wrong with an award of damages for any loss caused by the breach? Such
a claim would be relatively straightforward, involving identification of the
contract value, BT's profit margin, and an assessment of the lost chance. On
the other hand, if the decision to award the contract to Capita were to be set
aside, this would cause a large number of problems and considerable harm to the
public interest benefits underpinning the implementation of the SWAN project,
which itself was prompted by the McClelland report recommendations. The
factors relied upon by Mr Dunlop in this regard can be summarised as
follows. Reduction would cause delay, uncertainty, and yet more
non-compensable losses to public bodies and to Capita. In all probability
Education Scotland and the Pathfinder (South) Councils would lose the benefits
of their early involvement in the SWAN project. In the meantime BT would
continue to be paid as the incumbent provider, while Capita and others would
have no remedy for wasted costs and lost savings. The considerable benefits
flowing from the improved public services inherent in the McClelland
recommendations would be, at best, delayed for an uncertain period. Vulnerable
groups in society would be harmed.
[26] Mr Dunlop
indicated that there are real questions as to whether there could be a fair
re-run of the process given the recent disclosure to the parties of details as
to the bids, and of other confidential and sensitive information. The worst
outcome would be a fresh challenge to a new decision. Those with
responsibility for the procurement exercise question the practicality of a
re-start at the advanced stage suggested by the pursuer, especially in a
process governed by the competitive dialogue procedure. In any event it is
unlikely that Education Scotland and the Pathfinder (South) Councils would be
involved in any new competition, given that they will require to renew their
current contracts this year. So any new specification and bids are likely to
be materially different. It was submitted that all of this outweighs the
arguments for a re-run, especially given BT's continuing right to seek
compensation for any proven losses. Furthermore, as the wholesaler, BT will
still receive financial benefit, even with Capita as the chosen contractor.
[27] Turning to my
decision on the applications before the court, I consider that much can be
gained from a consideration of three cases, each of which involved a proven
breach of the regulations. I will begin with the two decisions from Northern
Ireland relied upon by Ms Crawford. The first of these is McLaughlin
and Harvey Limited v The Department of Finance and Personnel (No.3) [2008] NIQB 122. The plaintiff participated in a competition to identify five
economic operators who would join a framework agreement allowing them to bid
for some £800 million worth of public building works over four years. The
plaintiff came a narrow sixth, less than 1% behind those marked fourth and
fifth. The judge noted that even a modest improvement in its marking could
have materially affected the outcome. The plaintiff offered the fourth lowest
price, so was well placed to benefit from any slight improvement in the quality
assessment of its tender. It was held that some 39 elements taken into
account by the evaluation panel had not been disclosed to the plaintiff, nor
had the weightings applied to them. The court having rejected a request to add
the plaintiff to the list of approved operators, the issue came to be between
setting aside the decision complained of, or limiting the claim to damages.
The judge asked: which is the most appropriate remedy to grant to the
plaintiff, it having succeeded in proving a breach of duty? He noted the
difficulties which, in the particular circumstances of the case, the plaintiff
would face in seeking to prove and qualify damages. To set aside the framework
agreement would cause a delay of months, not years. In the meantime the
department could enter into specific contracts for any projects ready to
proceed. Reduction would cause little, if any, real inconvenience, and would
avoid the waste of paying both the contract price for works and damages to the
plaintiff. This could be contrasted with a difficult and lengthy damages
assessment process. The conclusion was that damages would be a manifestly
inferior remedy. Setting aside the framework agreement was a much better
alternative.
[28] The second
Northern Irish case is Resource (NI) v The Northern Ireland Courts
and Tribunals Service [2011] NIQB 121. An evaluation panel failed to
disregard an impermissible enhancement to a bid by G4S. The judge was, to put
it mildly, unimpressed with the quality of the evidence led in support of the
decision. He found that there were manifest and serious breaches of the rules
which were contrary to the substance, spirit and ethos of the relevant
guidance, and which infringed the principle of equality of treatment. Only G4S
benefited from preferential treatment in a case where "the margins could not
have been tighter". In the critical section of the bid, G4S received a mark of
five out of five. Had it been below a four, the plaintiff's bid would have
won. The judge regarded the impermissible factor as "plainly influential".
The error was serious and of obvious gravity, the panel having given credit for
a factor which was "alien to the contract being pursued".
[29] While it
was noted that each of the remedies listed in the regulations is discretionary
in nature, no one had suggested that damages would be an appropriate remedy.
The contest was between a re-run before a different evaluation panel, or the
judge simply awarding the contract to the plaintiff. The former option was
chosen. In all the circumstances it is wholly understandable that the court
was not asked to preserve the decision by limiting the claim to damages.
Plainly this was a case at the very serious end of the spectrum, with the
unfair advantage given to one bidder being just enough to see it over the line
narrowly ahead of the plaintiff.
[30] The third
case is that of Mears (cited earlier). It was established that the
authority had failed to notify the tenderers of the applicable scoring guidance
and consequent weightings, all in breach of the transparency provision in
regulation 4(3) and the terms of regulation 30(3). As to the test of
actionability, the judge concluded that, in the context of a case where he was
considering the detail of the loss, he required to decide whether, had the
relevant disclosure taken place, there was a real or significant, as opposed to
a fanciful chance, that the plaintiff's bid would have been selected. He
referred to earlier case law to the effect that, while the damages test is
proof of loss, a cause of action under the regulations does not depend upon
proof that but for the breach of duty the plaintiff's tender would have won.
Mr Justice Ramsey was satisfied that, because of the infringement, Mears
lost a significant chance of obtaining the contract. The judge observed that
the court has a discretion as to the appropriate remedy. The court required to
balance the public interest in the contract proceeding and the private
interests of the plaintiff. There is no presumption in favour of any one form
of remedy. Everything depends upon the particular circumstances. The remedy
requires to be proportionate. At one end of the scale there might be a breach
so serious that it can only be met by quashing the decision at issue. There
will be other cases where the impact is less serious or obvious, and in which
damages will deal adequately with the breach.
[31] In the
circumstances of the case before him Ramsey J concluded that the overall
balance favoured allowing Mears the remedy of damages alone. The plaintiff's
loss, or risk of loss, could be adequately compensated by financial
compensation, which provided a proportionate remedy.
[32] The
following general propositions are illustrated by these decisions. The
judicial task is to identify the most appropriate remedy, which should be both proportionate
and effective. The court enjoys a broad discretion which is to be exercised
with regard to all the relevant facts of the particular case. A proven
infringement of the regulations will always carry substantial weight, but not
all breaches of duty have the same impact and effect. For example, if there
was a serious breach of a fundamental principle underpinning the regulations
which related directly to the evaluation of the winning tender, and it was that
unfair advantage which caused its success, that would be a strong indicator in
favour of an order setting aside the unlawful decision. However, if a less
egregious breach was of more doubtful operative effect, and if reduction would
cause harm to public and other legitimate interests, the court may well prefer
the route of financial compensation for any loss sustained. In this regard,
something will depend on whether the proof and assessment of damages is of more
than usual complexity or difficulty. It is relevant to consider and weigh in
the balance the likely benefits and detriments of respectively a set aside
order and the alternative of limiting the claim to one of damages. If a re-run
causes little harm and inconvenience, that will support the view that a fresh competition
should be carried out free of the problem which tainted the previous
procedure.
[33] I have
taken into account all that is said in the affidavits lodged in court. I
mention the following specific points. Some of the affidavits explain how, with
disclosure of the full scoring methodology, BT would have altered its bid. It
is only realistic to acknowledge that this is being said with the benefit of
hindsight as to the scores given to the bids. There will always be an inherent
difficulty in trying to construct what BT's bid would have looked like with
full disclosure first time round, and to assess the score it would have
achieved. That said, I have no difficulty in accepting the general point that it
is likely that BT would have taken greater care and invested more in respect of
individual requirements where, within a sensible budget, there was room for
improvement. Mr Gibb notes that even within the pricing requirements, BT
had some £10m or thereby with which to enhance its bid.
[34] Mr Salvetta
explains the potential benefits and savings for public services involved in the
SWAN project. In respect of the four vanguard partners (the defender,
Education Scotland and the Pathfinder (South) Councils), the contract value is
£110m, potentially rising to £325m across the wider public sector. He comments
on the work required at Capita before the new system can go online as planned
by April 2014. Already the work is several weeks behind schedule. He notes
the imminent problem of the expiry of Education Scotland's current contract.
Continuing uncertainty will adversely affect the Pathfinder (South) Councils in
respect of the contracts with their providers, which end in October this year.
The SWAN project is described as a flagship policy designed to protect
vulnerable groups in society by facilitating the rapid exchange of
information. Mr Salvetta elaborates upon the concerns for the vanguard
partners in his supplementary affidavit. So far as NHS Scotland is concerned,
work needs to start by April 2014. More generally, on-going problems and
delays could impact on the viability and credibility of the whole project.
Other potential partners could be dissuaded from participation.
[35] The impact
of delay and uncertainty on Capita is explained in Mr Strang's affidavit.
Capita's Mr McLaughlin questions the feasibility of the pursuer's
suggestion that the process could be re-run from the invitation to submit a
final tender stage to a conclusion in just a few weeks. He states that, on any
view, the Education Scotland contract could not be completed on time, and some
technical requirements would not be achieved before the planned roll out of
Pathfinder (South) services. The NHS Scotland transition would be at risk. He
offers the view that in terms of delivering the objectives of the SWAN
programme, the point of no return is approaching. In addition, Capita have
concerns over the fairness and integrity of any new competition, given the
revelation of commercially sensitive information since the original decision.
[36] In my
opinion the nature and the impact of the breach of the regulations in the
present case are very different from those discussed in Resource (NI), which
concerned a grave irregularity directly relating to the successful bid. The evaluators
gave it an unfair and illegitimate advantage, which, given the small margins
involved, meant that it, rather than the plaintiff's bid, was successful. But
for the irregularity the plaintiff would have won the competition and been
awarded the contract. While I accept that in the present case the defender's
breach of duty impacted upon the pursuer's approach to its bid, there was no
favouritism towards nor direct discrimination in favour of the Capita tender.
In my view, the infringement is of a less serious nature, consisting of a
deficiency in the description of the scoring methodology. The successful Capita
bid is not directly tainted in the manner of the G4S tender. Furthermore, in Resource
(NI) there was no real doubt that, but for the irregularity, the
plaintiff's bid would have won. That is not true in the present case. On the
contrary, in the whole circumstances, and given the scores as set out in
production 6/12, my impression is that it would be difficult for the
pursuer to demonstrate that, absent the non-disclosure, it would have won the
competition. To be fair the pursuer does not offer to prove that. It pleads
that, for the reasons elaborated upon in the minute of amendment, had it known the
full facts it might have presented the successful tender. In damages terms
this translates to a loss of a chance. In my view there is force in
Mr Dunlop's submission that, in the absence of a clear demonstration that
the flaw in the process altered the result, and given the adverse consequences
of a re-run, it would not be proportionate to set the decision aside.
[37] Unlike the
position in the other Northern Irish case of McLaughlin and Harvey Limited,
to order a re-run in the present case will cause significant harm, particularly
in respect of the Education Scotland and Pathfinder (South) contracts, which
are due for renewal this year. At least one, and possibly both of these vanguard
partners would, in all likelihood, drop out of the project meantime, and there
would be uncertainties over the NHS contract. In my view, even if the process
returned only to the invitation to tender stage, the prediction of a delay of
no more than two months is likely to be optimistic, given the scale of the task
and the need to mobilise other parties. In any event, it is far from clear
that it would be practicable or sensible to rewind only to that point,
especially given the use of the competitive dialogue procedure. There is the
potential for a challenge to the outcome of any new competition, given the possible
compromise of its integrity and fairness arising from the recent disclosure of
sensitive information concerning the parties and their previous bids. The
worst outcome would be if a new competition became mired in a fresh legal
challenge.
[38] I recognise
the strong public interest in a fair and transparent procedure best placed to
identify the most economically advantageous bid. Failing a re-run, no doubt BT
will harbour an understandable sense of grievance and of hurt which no damages
claim will assuage or compensate. However, it will be entitled to pursue a
damages claim which, in comparison with some, will not be unduly complicated or
difficult. The case law teaches that I require to balance the public interest
in allowing the contract to proceed and the private harm to the pursuer in
being deprived of notice of the full details of the scoring methodology to be
deployed. In my view, and having regard to all the circumstances, damages is
an adequate, proportionate, and effective remedial route, and one which is
preferable to the alternative of setting the defender's decision aside. I
shall therefore refuse Ms Crawford's motion.
[39] Turning to
the defender's application for an order under regulation 47(9)(b) ending
the prohibition on the completion of the contract with Capita, as counsel
recognised, much the same considerations arise as have been discussed in the
context of the proposed set aside order. In considering the strength of the
pursuer's case, full weight needs to be given to the fact that a breach of the
regulations has been established, and also to the uncertainties as to the
extent to which it affected the bids, their scores, and the ultimate outcome.
For the reasons given earlier, the issues of balance of convenience and the public
interest favour the defender. I have already held that a claim in damages is
an adequate and proportionate remedy. It would not be impeded by an order
lifting the standstill period. The overall balance points to allowing the
contract with Capita to proceed without further delay. I shall therefore grant
the defender's application.
[40] The pursuer
sought leave to appeal, against these decisions, but subsequently that motion
was withdrawn. The overall result is that the court has allowed the defender
to complete the contract with Capita, and the pursuer's remedy is limited to a
claim in damages for any loss which it can prove was caused by the breach of
regulation 4(3).
[41] The court
has attempted to follow the recent guidance of the Inner House, which is to the
effect that the court should be mindful of the need for questions as to the
validity of public procurement decisions to be resolved as quickly as
reasonably practicable. As a result, and notwithstanding the complexities of
the case, this stage has been reached two months after service of the summons.
I wish to acknowledge the willing cooperation of parties, agents, and counsel
in this task, and to thank all involved.