OUTER HOUSE, COURT OF SESSION
|
|
|
|
CA132/11
|
OPINION OF LORD WOOLMAN
in the cause
DONAL ALPHONSUS NOLAN
Pursuer;
against
ADVANCE CONSTRUCTION (SCOTLAND) LIMITED
Defender:
________________
|
Pursuer: JD Campbell QC, Murray; Drummond Miller LLP
Defender: Dunlop QC, Walker; Balfour + Manson LLP
17 January 2014
Introduction
[1] Donal
Nolan owns an area of ground at Branchal Road, Cambusnethan, Wishaw ('the site').
On the morning of 19 November 2010, he observed several lorries depositing
waste material at the site. He had not given permission for any tipping to
take place. He took steps to terminate the operation. He contacted the police,
as well as the Scottish Environment Protection Agency ('SEPA') and the local
authority.
[2] Advance
Construction (Scotland) Ltd ('Advance') was the contractor responsible for
depositing the spoil. It had instructed hauliers to carry out the operation. Subsequent
investigations revealed that the spoil contained small concentrations of
asbestos. Although there have been lengthy negotiations to attempt to resolve
matters, the spoil still remains on the site.
[3] Mr Nolan
raised the present action against Advance in September 2011. At that stage he
sought: (a) declarator of encroachment; (b) orders requiring Advance to
remove the spoil, to reinstate the land and to procure a bond as security
against further losses; and (c) which failing such orders, an award of
£6.8 million by way of damages. That figure represented the cost of
removing the spoil, the lost development value of the land, together with
investigative and ancillary costs, and the cost of obtaining a bond.
The Issues
[4] In
the course of the proceedings, Mr Nolan has greatly narrowed his claim. In
June 2012, he deleted his conclusion for specific implement. At the close of
the proof, he abandoned his claim for lost development value, which he had
originally valued at £4 million. He also accepted that some elements of the
claim for investigative costs are properly classified as litigation expenses.
[5] Advance
accepts that its actions were unlawful. It maintains, however, that Mr Nolan
is not entitled to recover damages. Its principal line of defence relates to
mitigation of loss. Advance submits that Mr Nolan acted unreasonably in
refusing to accept its many repeated offers to remediate the land. In
consequence, he is disentitled from recovering compensation.
[6] There
are several other lines of defence. Advance argues that the sum sought is
excessive. In particular, it contends that the pre-existing soil itself
contained asbestos, which means that the land in any event requires remediation.
It also maintains that Mr Nolan has failed to prove his claim for investigative
and ancillary costs. Finally, it submits that decree
of declarator is unnecessary, because encroachment is admitted.
Material Facts
The pursuer
[7] Mr Nolan
is a racehorse trainer, now aged 64. He retired as a jockey ten years ago. In
2001 he acquired the site, which extends to 4.2 hectares. It has a level
stretch of ground of about nine furlongs, on which he used to gallop his
horses. A coal mine was formerly located at the site. It was closed in the
mid-20th century. Signs of the old workings are still evident, including a
coal bing.
[8] Mr Nolan
stays at a farmhouse about three miles away from the site. He lives there with
his partner, Miss Melanie Collins. The couple have been in a relationship for
over 20 years. Despite Mr Nolan having title to the site and being the
sole director of various companies, Miss Collins is in charge of the
couple's business affairs. She carries out all the administration for the
horse-racing business. In addition, she has been involved in property
development since the 1970s.
[9] Miss Collins
summed up their respective business roles as follows: "Donal has no experience
and leaves decisions up to me". Any reference to "the pursuer" in the course
of this opinion should therefore be understood in that context. Miss Collins
is the controlling mind. She took all the decisions relating to the site and
to the conduct of this litigation. Another individual, Mr Connolly, was
also said to be involved as a partner in the pursuer's business dealings. His
role was not fully explored in the evidence, however, and it is not relevant to
the issues in the case.
Residential Development at the Site
[10] The
pursuer wished to develop the site for residential housing. He discussed the
construction of 99 houses with North Lanarkshire Council ('NLC'). The planning
officers recommended that the development should take place in three phases. In
consequence, he applied to develop phase 1, consisting of twenty-eight houses. NLC
granted outline permission in 2003 to Upton Park Developments Ltd and full
permission in 2008 to Oscarpark Developments Ltd. Mr Nolan controlled
both these companies. By autumn 2010, the development was still under
consideration. The pursuer had engaged an architect and a chartered quantity
surveyor to provide advice on design and costs. No finance had, however, been
put in place.
The deposit of the spoil
[11] The
waste material that Advance deposited on the site came from Coltness Primary School.
NLC entered into a design and build contract with Graham Construction Ltd to
construct a new school building. It was agreed that part of the waste material
from the demolition of the old building should be re-used in the construction
of the new school. The remainder was to be removed. Some was scheduled to go
to a licensed landfill site near Polmont. Advance was responsible for removing
the other part, which consisted mainly of subsoil. It engaged two haulage
companies, Ryan Plant Ltd and Doonin Plant Ltd, to transport it to the site.
[12] Prior
to the deposit taking place, Advance took a number of preparatory steps. It put
up security fencing around the boundary of the site, made up a haul road, sent
a bulldozer to level the waste material and installed a portakabin. It also carried
out a survey to establish the ground levels. It intended to carry out a second
survey once the tipping operation had ceased. The aim of the two surveys was
to enable Advance to calculate the precise amount of spoil deposited at the site.
That was designed to avoid any dispute with the landfill operator over tipping
charges.
[13] Advance
also applied to SEPA for an exemption to allow 5,000 tonnes of waste material
to be deposited at the site. The application was made under para 19 of
schedule 3 of the Waste Management Licensing Regulations 1994 (now
repealed and replaced by the Waste Management Licensing (Scotland) Regulations
2011). The application form erroneously stated that the operation would begin on
29 November 2010. SEPA replied on 15 November seeking further
information. Before matters were finalised, Advance realised that it did not
have permission to tip the spoil at the site. Accordingly, no exemption was
granted.
[14] The
lorries containing the spoil began arriving at the site on 15 November
2010. The dumping took place on an area that broadly coincided with phase 1 of
the proposed development. Mr Nolan and Miss Collins learned about
the operation on the morning of Friday 19 November 2010. They immediately
went to the site where they found several tipper lorries waiting in a queue. At
least one of them was in the process of dumping spoil when they arrived. They
noticed that the lorries bore the livery of either 'Ryan Plant' or 'Doonin
Plant' and that Advance's logo featured on the portakabin and the bulldozer.
[15] Miss Collins
exhibited Mr Nolan's title deeds to the police to vouch his ownership. On
learning that it did not have permission to carry out the tipping operation,
Advance immediately instructed the hauliers to cease any further transfer or
deposit. Its position from the outset has been that it was the subject of
deception.
[16] Advance's
technical manager, Lance Gordon, explained matters at the proof. Two
individuals, William Edward and Jim Aitken, approached him and represented that
they acted for the owner of the site. They stated that it was a landfill
facility with the correct licences in place. Mr Gordon asked to see the
licences, which they undertook to forward to him. He was not overly concerned
about the absence of paperwork, because it is common within the industry for
documentation to arrive late. He saw no reason to doubt the representations
made to him. Mr Edward had formerly worked for Advance and his daughter
is one of its employees.
After the incident
[16] Shortly
after the incident, Mr Nolan and Miss Collins met Seamus Shields, the
managing director of Advance. The pursuer's solicitor described the meeting as
a "fruitful" one. Mr Shields acknowledged that the deposit was
wrongful. In the course of discussions, he raised the question of Advance
purchasing the site, or entering into a joint venture with the pursuer. The
pursuer accepted Advance's explanation of the circumstances leading up to the
deposit of the spoil. It paid him a sum of £5,000 as a contribution toward
compensation. No one was then aware that the spoil contained asbestos.
[17] The
degree of accord between the parties is illustrated by a letter dated 25 January
2011 sent by the pursuer's solicitors to Advance's solicitors. It enclosed a handwritten
letter, signed by Mr Nolan and addressed to Advance, which stated:
"I hereby provide you with my consent as follows: -
(1) For permission (retrospectively) to deposit all soils upon said site pursuant to any contractual agreement(s) which you may have entered into with 3rd parties for the deposit of said soils."
[18] Potentially
that letter could have been of great significance to the present litigation. Mr Dunlop
informed me, however, that he had instructions not to found upon it as
relieving Advance from liability.
[19] From
about March 2011, the pursuer's attitude toward Advance began to change. He
queried whether it had been deceived into depositing the spoil. Suspicion
turned into belief. He became convinced that Advance had engaged in
fly-tipping in order to avoid incurring the expense of removing the spoil to a
landfill site. He was concerned about his own duty as the landowner to deal
properly with the waste materials: Environmental Protection Act 1990; Van
de Walle v Texaco Belgium SA [2005] Env LR 24 Mountpace Ltd v
Haringey LBC [2012] Env LR 32.
[19] The
pursuer's misgivings grew in the light of the information he received from the
experts whom he instructed to investigate matters. They advised him that there
might be as much as 16,000 tonnes of spoil and that it would be very expensive
to remove, given the very high rate of landfill tax applicable to asbestos. It
was against that background that he raised the present action in Hamilton
Sheriff Court.
Offers to Remediate
[20] Advance
has made repeated offers to remediate the site. Because of their significance
in relation to mitigation, it is necessary to consider them in some detail. For
the sake of convenience, I shall generally narrate the communications as if
they passed between parties. In fact they mainly took place between their
respective solicitors. The pursuer did not accept any of the offers. Miss Collins
explained that she distrusted Advance, as it had "proved
beyond a shadow of doubt that it was unreliable". She enlisted the aid of Mr
Alex Neil MSP and he became involved in several meetings and email
correspondence about the dispute.
[21] Advance
sent its first written offer on 19 May 2011, some four months before the
litigation was raised. Its solicitors wrote:
"... to reiterate the offer that our clients have repeatedly made that they will remove from site the material which they deposited and only that material and remove it to a safe site which has already been identified. They will then reinstate the area to the way in which it was prior to them commencing the tipping or alternatively they would be prepared to consider otherwise reinstating the ground in a different manner if this could provide settlement. In that regard we would need fairly detailed proposals."
[22] The
pursuer replied to the effect that he wished to ascertain the nature and amount
of the spoil and whether SEPA had approved a method statement for its removal
and the reinstatement of the site. In July 2011 the Finance Director of
Advance visited Mr Neil at his constituency surgery. Mr Neil subsequently
reported to the pursuer that Advance was "keen to try to find a way
forward which is mutually agreeable". It was willing either to have direct
discussions, or to refer the matter to mediation.
[23] On
9 and again on 19 September 2011, Advance again offered to remove the
material. It undertook to return "this site to the condition and ground
levels that existed prior to any dumping taking place". The following
day, the pursuer raised the present action and arrested on the dependence. That
motion was granted on the basis of the initial writ, which contained the
following averment:
"The pursuer has sought the removal of said contaminated waste materials by the defenders, but as at the commencement of these proceedings the defenders have refused or delayed to do so."
[24] In
October 2011 Advance lodged defences and successfully moved to remit the case
to this court. At an early stage in the proceedings (it is not clear when) the
parties had another meeting. One of the pursuer's experts, Alexander Boyd,
arranged and chaired the meeting, which took place in a hotel on the M8. He told
the representatives of Advance that it should (a) remove the material from the site,
(b) provide a bond, and (c) compensate the pursuer for the upheaval caused by
its conduct. When the meeting finished, he departed thinking that matters
would resolve on that basis. Shortly afterwards, however, he was
surprised to learn that the pursuer was only prepared to settle the action in
return for a payment of £3 million.
[25] A
few months later Miss Collins consulted with Miss Joughin, advocate. Counsel
advised her to accept Advance's offer. She added that there would have to be a
good reason to reject it. This evidence was adduced from Mr Boyd, who was
present at the consultation. It is very unusual to hear such testimony in the
course of a proof. Normally it would be protected by privilege. Mr Campbell
expressly indicated, however, that he did not object to this line of
questioning.
Further offers of remediation
[26] Another
meeting took place in about April 2012 between Miss Collins and Mr Shields.
During the course of their discussion, he offered to remove the waste material
to a location in Baillieston. Miss Collins visited the proposed site and
found it to be a residential development under construction by Bellway Homes. She
said that the location was clearly unsuitable and that his suggestion deepened
her mistrust of Advance. However, she only appears to have made the visit a
year after the proposal was made.
[27] Advance
made further written offers to remediate throughout 2012.
a. On 20 July (shortly after the pursuer abandoned his claim for specific implement) it stated that the work would be carried out by an independent contractor.
b. On 23 October, it stated:
"Either the material will be entirely removed, at our clients' sole expense, thus rectifying the entire problem at the site; or the removal exercise will not cure the problems, in which case your client's claim for damages is not only left intact, it is far easier to prove."
c. On 7 November, it stated that the work would be overseen by David Murray and Associates, engineers, who themselves would use specialist contractors (REC Asbestos Removal).
d. On 21 December, it proposed that the removal contractor should be Yuill & Dodds Ltd, whom Miss Collins had previously approved.
[28] None
of these offers was accepted. On 30 May and again on 7 November 2012,
the pursuer indicated that he would arrange for the removal of the waste
material himself. No such steps were in fact taken.
[29] In
the course of 2013, Advance made further efforts to reach an extra-judicial
settlement. It wrote to the pursuer on 7 May and stated:
"standing the proximity to the Proof, it is appropriate that we make one final attempt to try and resolve matters to parties' mutual satisfaction with a view to minimising court time and expenditure."
[30] The
letter set out a detailed proposal for the removal and disposal of the waste
material, which was to be carried out either by Advance or by a third party
contractor. It added that the offer was "without prejudice to any damages
claim your client may have."
[31] On
9 May the pursuer made a counter-proposal. He required Advance (a) to
remove the waste material in terms of an agreed method statement; (b) to pay
£5 million in damages, together with legal costs and landfill tax; and (c) to
grant a formal indemnity in his favour. On 24 May Advance rejected the
counter-proposal on the basis that the financial claim was "unrealistic". Instead
it proposed that one of two named contractors would remove the waste material
in compliance with regulatory requirements. Advance and its parent company
would provide an indemnity to the pursuer in respect of any claim or liability
arising from (a) the dumping of the waste material; and (b) the removal
operation. The letter concluded by stating that damages should remain a
discrete matter.
[32] In
his response of 4 June, the pursuer: (i) queried the suitability of one
of the contractors, (ii) stipulated that the works should be authorised and
supervised by SEPA, (iii) asked to see a draft method statement and indemnity,
and (iv) undertook to provide vouchers for all the costs he had incurred. He
also made a new proposal:
"Instead of removing the material we apply to [NLC] for planning permission to cap the site. When it is received our clients will carry out the work at your client's expense, subject to SEPA's advice and supervision. Budgets will be obtained in advance."
[33] This
was the first time that the pursuer had mentioned capping as a solution. On
6 June Advance purported to accept that counter-proposal, leaving over the
question of damages. Following a debate, however, I held that this sequence of
letters did not constitute a concluded agreement.
Credibility and reliability
Mr Nolan
[34] Mr Nolan
struck me as a remarkable witness. In a commercial action in which at one
stage he sought a sum in excess of £6 million, he professed to know virtually
nothing about the circumstances. His witness statement is less than half a
page long. It states that Miss Collins was in charge of all issues
involving development at the site on his behalf. When giving evidence, his
stock answers were "I don't know", "probably", and "you should ask Melanie". In
reply to a question about one of the offers made by Advance he responded:
"I don't know about this. I'm not up to all this paperwork. I'm not going to contradict you. I do not want to tell lies. I wouldn't read this letter anyway. I would pass it to my partner."
[35] Even
allowing for Miss Collins' role within their relationship, Mr Nolan's
lack of knowledge was extraordinary. He stated that he did not give
instructions to raise these proceedings - "Melanie would have done that". He
was unaware of:
i. whether he was a director of various companies;
ii. the extent of the site ("I haven't a clue");
iii. the identity of the solicitors instructed on his behalf (he had changed firms several times);
iv. whether he had been informed of the defender's offers to remediate;
v. whether he had told his solicitors that he was going to remove the material;
[36] As
a result I found Mr Nolan's evidence to be of
little value. He was wholly unreliable and he contributed
little to my understanding of the case.
Miss Collins
[37] In
matters of dispute I do not accept Miss Collins as a reliable witness for the
following reasons:
i. She was unable to formulate a clear rationale for rejecting Advance's offers to remove the spoil.
ii. She was inclined to be evasive when difficult questions were put to her.
iii. She was quick to impute dishonesty to other witnesses.
iv. She was dismissive of expert evidence that contradicted her own opinion.
v. She did not appear to be willing to achieve a practical solution.
[38] I
was particularly concerned about two key questions arising out of the
proceedings in the sheriff court. First, why did the initial writ contain a
crave for specific implement, if the pursuer did not wish Advance to remove the
waste material? Second, who gave instructions for the averment that Advance
had refused the pursuer's requests to remove the material, standing the
pre-litigation offers that had been made? Those questions cry out for an
explanation. Yet Miss Collins was unable to provide one. She stated that its
wording had nothing to do with her. I regard that answer as being
disingenuous.
[39] I
concluded that Miss Collins' aim was to maximise the financial sum that she
could recover from Advance. That was why she adopted the unshakeable belief
that any offer made by Advance was tainted. At best, she failed to evaluate
them in an objective manner. Her perspective was a distorted one.
Mr Alexander Boyd
[40] Alexander
Boyd of NPL Environmental Ltd is a geotechnical engineer. He had been providing
advice to Miss Collins in 2010 about another planning matter. When she
mentioned the problem at the site, he suggested digging four trial trenches. He
undertook the work at the end of March 2011 and was the first to uncover
evidence of asbestos. On 5 April he sent an email to Miss Collins, which
stated:
"Just a quick note on the sampling from the Branchal Road Site.
The visual examination of the long trenches revealed a little asbestos, solvents, what looks like grease oil, wood and organic materials.
...
The asbestos is probably from a roof tile though there are other coloured specimens that show either boarding or fabric."
[41] Mr Boyd
also informed her that a sizeable quantity of spoil had been deposited, and that
the cost of removal would be substantial. Following laboratory testing of soil,
he informed SEPA in May 2011 that he had found small quantities of asbestos at
the site. In his July 2011 report, he stated:
"The site has been covered with approximately 5000 m3 of waste materials containing asbestos, building rubble, old oil containers, plastic, steel sheets, old electrical wiring mixed through a clay matrix."
[42] Subsequently,
Mr Boyd and Miss Collins fell out and he ceased carrying out any work
on her behalf. He believes that she misrepresented his findings in three key
respects. First, she exaggerated matters at meetings with SEPA by referring to
the spoil as "toxic waste" or "hazardous waste". He did
not regard those terms as warranted. Second, he thought that she over-stated
the amount of the spoil. As he put it in his affidavit:
"My estimate of the deposited waste was five thousand tonnes. I have since heard a figure quoted by Melanie Collins of fifteen thousand tonnes and I dismissed that as being ridiculously excessive."
Third, Mr Boyd believed that Miss Collins had inflated the figure of financial compensation to which the pursuer was entitled.
[43] Miss Collins
disputed his contentions. She feels a sense of betrayal, because Mr Boyd
gave evidence on behalf of Advance and supported its position in a number of
respects.
[44] I
found that Mr Boyd gave his testimony in a straightforward and level
fashion. His evidence largely corresponded with that of the documents and the
other experts. I could discern no reason for him to lie about matters. I
accepted his denial that he was motivated by commercial considerations. In
those circumstances, I found him to be a reliable witness.
Mr Gordon
[45] Senior
counsel for the pursuer made a sustained attack on the credibility of Mr Gordon,
the technical manager for Advance. He submitted that Mr Gordon's account
of how Advance had come to deposit the spoil on the site "does not bear close
examination, and is false; in any event, it is unsupported by any credible
evidence." When I pressed him on the basis for this statement, Mr Campbell
pointed out that Mr Edward had not been brought to court and that it did
not square with the application for an exemption made to SEPA on 12 November
2010.
[46] Mr Campbell
also submitted (a) that Mr Gordon had misled SEPA by stating that the work
was going to commence on 29 November, rather than 15 November; and
(b) that it was unlikely that Advance would have carried out a topographical
survey if it believed that it was lawfully depositing waste material at a
licenced landfill site.
[47] I
was troubled by the date given in the application to SEPA, but in general
Mr Gordon struck me as a frank and open witness who had come to court to
tell the truth. One moment during his re-examination made a particular
impression upon me. Mr Dunlop asked him whether he understood that
Mr Campbell had challenged his veracity. Mr Gordon paused for a long
time before replying, as if to indicate that he found it difficult to take that
suggestion on board. I regarded that as a genuine response. It fitted with my
overall impression of him as an honest person. In my view it is inappropriate
to speculate on why Mr Edwards was not brought to court or on what his
evidence might have been.
[48] Accordingly,
I accept Mr Gordon's evidence (a) that Advance is a very sizeable company with
600 employees which operates for a number of major house-building contractors
and has never previously been prosecuted; (b) that he continually asked to see
the licences, but without success and that it is common in the industry for
paperwork such as licenses to be shown after the contract had commenced; (c)
that there were many landfill sites to which the spoil could have been taken; and
(d) that it was his standard practice to undertake a survey whenever Advance
starts a site for record-keeping purposes.
How Much Spoil was Deposited?
[49] In
my view the correct estimate of the amount of spoil is 2,807m3.
Using a conversion factor of +2 (the industry standard) that converts to 5,600
cubic tonnes. I accept the evidence in this regard from Andrew Parsons, the
expert geologist called on behalf of Advance. He has 22 years' experience,
is a director of IKM Consulting Limited, sits on the Contaminated Land Advisory
Group of the Scottish Government and is a representative of the Environmental
Industries Commission.
[50] Mr Parsons
used robotic laser equipment to survey the site and calculate the amount of the
spoil. It is the most up-to-date technology for carrying out this exercise and
I detected no flaw in the methodology he employed. Further, Advance also used
a robotic instrument to undertake its pre and post deposit surveys. Those
results were then fed into a computer software program, which calculated that
there was 2,796 m³ of spoil. Accordingly, these two methods yielded an almost
identical result.
[51] In
my view, the other methods of calculation do not engender the same degree of
confidence. Mr Farleigh carried out a physical site survey, but he based
his estimate of 16,000 tonnes on two questionable foundations. First, he used
an area measurement of 6,175 m2, whereas the robotic surveys
measured the area at 5,055 m2. Second, he used one trench
measurement to derive an average depth of only 1.3 m for the waste material. He
stated that Mr Boyd provided him with details of the ground levels at the
site. But Mr Boyd denied ever meeting Mr Farleigh and did not agree
that the average depth was 1.3 m. Likewise the logs of the trial pits dug by
Mr Parsons and Mr Jamieson did not square with that figure.
[52] The
waste
transfer notes should have provided
the best evidence of the amount of the spoil. Unhappily, however, they were
incomplete and could not be relied upon. An NLC official,
Julie Heron, examined the available notes relating to all the waste material
removed from Coltness primary school. She concluded that it involved a total
of 18,000 m³, of which 15,000 m³ had gone to other sites. That implies that
about 3,000 m³ went to the site.
[53] Avondale
Environmental Ltd, which operates the asbestos landfill facility near Polmont,
issued an advice note dated 29 September 2010 stating that it received a
total of 13.36 tonnes of waste material from the school. It is difficult to
know what weight to attach to that note. According to Miss Collins, when
she sought to check it in November 2011, Avondale indicated that it had never
received an enquiry from a contractor in relation to Coltness primary school.
[54] Miss Collins's
own method of measurement involved counting the lorry loads that came to the site.
It quickly became apparent that her approach was flawed, because she assumed
(i) that the tipping had started on 8 November, rather than 15 November,
and (ii) that each lorry load was completely full. I therefore place no
reliance on her estimate of 15,000 tonnes.
What is the concentration of asbestos within the spoil?
[55] The
experts agreed that the levels of asbestos are very low, the concentration
being in the range 0.001% to 0.007%.
Mr Boyd stressed that "the deposited material was inert and did not
contain any significant hazardous or toxic material. According to Kenneth
Boag, SEPA's
head
of operations in south-west Scotland, the spoil is not
classified as hazardous waste. Mr Jamieson took
a more cautious view. Although the asbestos concentrations are within the limit for Special Waste
(ie hazardous waste), he
believed that the material is a risk to human health because it exceeds 0.001%.
Was the soil at the site already contaminated?
[56] Because
of its fire retardant properties, asbestos was commonly used at collieries. After
mines are closed and the buildings demolished, it is often found in the soil. The
experts all accepted that there might be asbestos in the pre-existing
soil
at the site. Mr Parsons explained that he was "very
confident" of making such a finding, based upon his experience as a member of
the team that carried out due diligence on similar sites when British Coal was
sold. In the event, his tests showed that the pre-existing soil did contain
low levels of asbestos.
[57] Mr Jamieson
accepted that finding of asbestos in the soil at a former colliery
is well-recognised.
Mr Boyd
said that he "would not be surprised" for asbestos
to be present in the soil at the site.
[58] Asbestos
does not leach downwards. Accordingly any finding would not result from new
spoil being deposited above. I conclude that there is asbestos in the
pre-existing soil. That means that the site could not have been used for
housing without some form of remediation.
Removal or Capping?
[59] The
problem of dealing with the asbestos in the spoil can be addressed by either
removal or capping. Both solutions are possible. Mr Parsons
took the view that capping is the appropriate option. Mr Jamieson agreed
that capping can be used for brownfield sites, even where they are to be
developed for residential housing. His reservations related to the attitude of
SEPA and whether it would require removal.
[60] SEPA
has a primary role in ensuring the safe production, transport, handling and
disposal of waste in terms of the Environmental Protection Act 1990, the Waste
Framework Directive 2008 (2008/98/EC) and other legislation. It investigated
the incident at the site, but did not initiate a prosecution. Instead it wrote
an advisory letter to NLC in relation to its responsibilities as the originator
of the waste. It also issued warnings (a) to Ryan Plant Hire regarding the
quality of the waste transfer notes, and (b) to Advance regarding the disposal
of the waste without a paragraph 19 exemption.
[61] Mr Boag
explained that, as the spoil is not classified as hazardous waste, it does not require
to be sent to a designated asbestos landfill site, such as the one operated by
Avondale. However, the spoil
could not be used for open or garden spaces in residential developments.
[62] Mr Boag
indicated that SEPA's general policy was to require removal of waste material
as soon as possible. But he emphasised that each case must be considered on
its own merits. In this instance, SEPA has decided not
to use its powers to require removal of the material. Further,
it had not been asked to comment on a capping solution, as this is a local
authority matter.
The measure of loss
Which Option?
[63] Mr Parsons
also stated that if the question of asbestos in the soil was not being
addressed, the ground levels at the site could be re-profiled at a modest cost.
[64] Mr Campbell
provided a range of calculations based upon the figures contained in Mr Farleigh's
report dated 26 September 2012, which estimated that the total cost of
removal might amount to £1.7 million. In my view, the much more compelling
evidence came from the quotations from contractors obtained by Mr Parsons.
a. Removal The estimates from four contractors for removal of the spoil ranged from £181,600 (excl VAT) to £335,487 (excl VAT).
b. Capping The estimates from two contractors varied from £97,140 to £140,520 (inclusive of VAT).
[65] As
removal is more expensive, the pursuer is confined to recover the cost of capping:
Pomphrey v James A. Cuthbertson Limited 1951 SC 147. Further in this
case I conclude that the pursuer would not use any sum to remove the spoil. I
do not accept Miss Collins's evidence to the contrary. It defies common
sense. Removal of the spoil would not of itself allow residential development
to take place. Further remediation by way of capping
would still be required. The clear economic advantage lies
in simply retaining the sum. An award of compensation should
not be made if the person does not intend to apply it for the purpose in
respect of which it is granted: Ruxley Electronics v Forsyth
[1996] 1 AC 344.
The further problem
[66] Any
award based on the cost of capping throws up a further question. The
pre-existing soil requires remediation. Can the pursuer recover damages in
respect of an expense which he would in any event have had to incur? In Performance
Cars v Abraham [1962] 1 QB 33, the defendant negligently collided
his car with the plaintiff's Rolls Royce. The plaintiff sought the cost of
re-spraying his car. In fact it had been involved in an earlier collision and
he had been awarded damages against another defendant for the cost of a re-spray,
which had not been paid.
[67] Lord
Evershed MR said that "the necessity for respraying was not the result of the
defendant's wrongdoing because that necessity already existed." Donovan
LJ said:
"the question, as I see it, is this: what extra burden in the matter of respraying was put upon the plaintiff company by the second collision? To my mind the answer must be: None, for the earlier collision had already imposed the burden of re-spraying upon them."
The Court of Appeal has subsequently approved that approach: Steel v Joy [2004] 1 WLR 3002.
[68] This
poses a significant difficulty for the pursuer.
Mitigation
[69] A
person must take "all reasonable steps to mitigate the loss consequent on
the breach, and [is debarred] from claiming any part of the damage which is due
to his neglect to take such steps": British Westinghouse v Underground
Electric Railways [1912] AC 673, 689 per Viscount Haldane LC. Determining
whether a pursuer has discharged that duty is a question of fact.
[70] In
my view, the pursuer did not take all reasonable steps in this case. The
offers of remediation were plainly reasonable. It is difficult to see what
more Advance could have done. It proposed (a) that third party contractors
would undertake the work; (b) that it would be supervised by independent
engineers to the satisfaction of SEPA; and (c) that any remaining damages after
remediation would be reserved. The offers were therefore framed in textbook
fashion. They were simple and straightforward. Shortly before the proof,
Advance unilaterally granted an indemnity relieving the pursuer of liability in
respect of the removal.
[71] Was
it reasonable for the pursuer to reject these offers? Looked at objectively,
there is only a slender basis for Miss Collins' mistrust of Advance. Her
belief that it engaged in fly-tipping is hard to reconcile with the steps it
took in relation to the site, including its prior notice to SEPA and the
display of its logo. These are not the hallmarks of a clandestine operation. A
reasonable person might have posed two questions. First, why would a
substantial enterprise like Advance imperil its commercial reputation on one
relatively small operation? Second, why would it compromise itself further by
carrying out the remediation in an unlawful manner?
[72] There
is also the pursuer's failure to follow counsel's advice. In Donnelly v Baird & Co Ltd 1908 SC 536 a man
had become incapacitated in consequence of an injury to his hand. His
employers applied to terminate or reduce the payments it was making to him
under the Workmen's Compensation Act 1897. They did so because he had refused
to follow the recommendation of three doctors that one of his fingers be
amputated. By a 5:2 majority, the court held that the man's conduct precluded
him from receiving further payments. His conduct was
unreasonable. Lord McLaren stated (at
page 541):
"a prudent and reasonable man will be guided by medical opinion rather than by his own fears; and, without saying that the case is absolutely clear, my view is that by refusing to submit to the operation the party has disentitled himself to further payments. Any difficulty I have felt in considering the case is almost entirely removed by the consideration that nothing but good can come to this young man from the operation."
[73] In
my view, the inference is as strong or stronger when a pursuer declines to
accept the advice of counsel, particularly when Miss Joughin stated that
there had to be a good reason to reject the offer made by Advance.
[74] In
a commercial contract, it is generally appropriate to accept an offer from the
party in default: Payzu Ltd v Saunders [1919] 2 KB 581, 589 per
Scrutton LJ. It will depend on the whole context. In
two recent cases involving vehicle collisions, the court
has held that a claimant may reasonably refuse the defendant's offer of a
replacement car: Copley v Lawn [2010] Bus LR 83 and Sayce v
TNT (UK) Ltd [2012] 1 WLR 1261.
[75] Finally,
it is difficult to square the pursuer's alleged mistrust of Advance with the
terms of the pre-litigation correspondence, which do not mention it. It is
also impossible to reconcile with the terms of the initial writ. Why did he
seek an order for specific implement requiring Advance to remove the spoil, if
that was the precise opposite of what he wished?
[76] In
the present case, Advance should have been given the opportunity to cure the
problem it caused. The circumstances ineluctably point toward the conclusion that
the pursuer has failed to mitigate his loss.
What is the effect of mitigation?
[77] The effect of a failure will depend on the circumstances
of the particular case. The general principle is that damages should be
assessed on the basis of what the pursuer would have received, if he had been
acting reasonably: McAuley v London Transport [1957] 2 Lloyd's
Rep 500, 505 per Jenkins LJ. But the position is not entirely
straightforward. In Sayce, Moore-Bick LJ commented on the difficulty of
reconciling the various cases on mitigation (at paragraphs 29 and 30). He made
that remark in the context of an obiter remark by Longmore LJ in Copley
that a claimant might still be entitled to damages, even if he had acted
unreasonably.
[78] Moore-Bick
LJ had previously analysed the consequences of mitigation in Uzinterimpex
JSC v Standard Bank plc [2008] Bus LR 1762. That case involved a
claim for conversion against a bank in respect of a quantity of cotton held in
a warehouse. In order to avoid further storage costs and depreciation, the
bank offered to sell the cotton and hold the proceeds in an account to await
the outcome of the dispute. The plaintiff's attitude toward the bank "was
coloured by a lack of faith and confidence" and it rejected the bank's
proposal. The Court of Appeal held that damages could only be recovered for
losses incurred prior to the date of that offer.
[79] Moore-Bick
LJ (with whom Sir Anthony Clarke MR and Laws LJ agreed) stated at paragraph 67:
"It is impossible to ignore the claimant's own conduct in relation to ... loss, since, if he has failed to take advantage of an opportunity reasonably available to him to avoid it in whole or in part, it will be difficult for him to justify requiring the defendant to pay compensation for loss that could not fairly be attributed to his wrongful act."
[80] In
my view, the same reasoning applies in this case. By failing to accept the
offer made by Advance, the pursuer is the author of his own misfortune. If he
had accepted Advance's offer to remove the spoil
in May 2011 (which I hold was a reasonable one), the spoil would have been
removed and most of the investigative costs would not have been incurred. I
conclude that the estimated cost of re-profiling the ground to address the
difference in levels caused by the spoil (£19,600 exc. VAT) represents
reasonable compensation for the pursuer in the circumstances of this case. To
award any sum in respect of capping would amount to betterment.
Claim for Costs to date
[81] The
pursuer originally claimed the sum of £300,000 in respect of the various costs that
he had incurred as a result of the deposit of the spoil. They included
investigating the extent and content of the spoil, reinstating the road,
employing a night watchman and securing the site.
[82] In
the course of the proof, Mr Nolan was not asked any questions about the
invoices vouching these costs. When Miss Collins was questioned about
them in examination in chief, Mr Dunlop made two objections. First, he
submitted that this evidence ought properly to have come from Mr Nolan. Second,
he argued that the evidence was irrelevant, because many, if not most, of the
invoices were addressed to companies that Mr Nolan controlled,
such as Oscarpark Ltd and Oscarpark Developments and Recycling Ltd.
I allowed this line of evidence, subject to competency and relevancy.
[83] I
draw attention to these objections because they demonstrate that in the course
of the proof, Advance put the pursuer on notice that it challenged these
invoices.
(a) Proof of Payment
[84] An
invoice only establishes that a debt has been incurred. It does not prove
payment. Neither Mr Nolan nor Miss Collins was asked whether the invoices
vouching these costs had actually been paid. On the evidence, I am not
satisfied that the invoices were paid. Even if it were possible to travel that
far by way of inference, it would be conjecture to determine whether they had
been paid by the pursuer, or by one of his companies.
(b) Title to Sue
[85] Miss Collins
explained that Mr Nolan had been advised to put the bills in the name of
his companies. Whatever the practical or tax advantages of taking that course,
it is not the case set out in the pleadings. The pursuer's
second plea-in-law makes it plain that he sues for losses sustained by him. Mr Campbell
submitted that it was "trivialising the matter" to say that the invoices were
not in Mr Nolan's name. He argued that both Mr Nolan
and
Miss Collins were "de facto agents of one another or their
companies". There were no averments to support that approach. It was unclear
to me how Miss Collins acted at the same time both as the agent of
Mr Nolan and of the companies to whom the invoices were addressed.
[86] It
is inappropriate to blur the lines of legal personality without the clearest
averments and proof. If an invoice was rendered to a company, it remains the
company's debt. Miss Collins ought to have been well aware of this point.
In a recent case involving one of her former companies, the court rejected a
similar argument: Upton Park Homes Ltd v
Macdonalds 2010 PNLR 12.
(c) Damages or Expenses?
[87] A
pursuer cannot recover by way of
damages an item that should properly be included in an account
of judicial expenses: McDowall v
Stewart (1871) 10 M 193. That principle has stood unchallenged for over a
century: Shanks v Gray 1977 SLT (Notes) 26. Both
Mr Nolan and Miss Collins accepted in cross-examination that the
investigative costs were incurred for the purposes of the court action. She expressly
affirmed that position in re-examination.
(d) Failure to mitigate
[88] If
the pursuer had accepted Advance's offer to remove the spoil in mid-2011, he
would not have incurred most of the
investigative costs.
Summary
[89] In
my view, each of these points presents a formidable obstacle to this head of
claim. Taken together, they are insurmountable. I hold that the pursuer has
failed to prove that he incurred and paid the invoices on which he founds.
Decree of declarator
[90] Advance
admits encroachment. There is therefore no dispute between the parties on this
point. In those circumstances, I decline to grant decree of declarator, on the
footing that it would serve no practical purpose: North British Railway Co.
v Birrell's Trustees 1918 SC (HL) 33, 47 per Lord Dunedin.
Conclusion
[91] I
propose to grant decree in favour of the pursuer in the sum of £19,600 plus
VAT. I shall put the matter out for a by order hearing to determine further
procedure. Meantime I reserve all questions of expenses.