OUTER HOUSE, COURT OF SESSION
|
|
|
|
CA91/11
|
OPINION OF LORD HODGE
in the cause
BAM BUCHANAN LIMITED
Pursuer;
against
ARCADIA GROUP LIMITED
Defender:
________________
|
Pursuer: R. Dunlop QC; Dundas & Wilson LLP
Defender: M. Richardson; DWF Biggart Baillie
5 July 2013
[1] The
pursuer ("the landlord") is the heritable proprietor of a building at 20/26 Buchanan
Street, Glasgow comprising seven floors and a basement ("the building"). The
defender was the tenant of parts of the basement, ground floor and first floor
of the building ("the premises") under a lease which had a date of entry of 18 September
1984 and expired on 27 January 2009. The upper floors of the building
were not occupied during most of the period of the lease, including at its
termination.
[2] The
landlord and the tenant are in dispute about sums which the landlord claims as
a service charge under the lease and also in relation to dilapidations. In
order to limit the expense of resolving their differences, the parties, after
raising this action, agreed a remit to William Morrison, a chartered
building surveyor and a director of Capita Symonds Limited, ("the reporter").
He was instructed to address the questions which they posed in relation to the
tenant's liability for the service charge and the dilapidations. By
interlocutor dated 17 August 2012 I ordered a remit to the reporter to
investigate and report on the facts and circumstances in terms of the parties'
remit.
[3] The
parties in the remit directed the reporter to produce a draft report. Clause 11
of the remit provided that, if a party objected to the draft report on an issue
of law, the reporter was to apply to the court for directions. I have heard
counsel in a debate on the landlord's note of objections to the draft report
and the tenant's answers thereto. I am invited to give directions to the
reporter.
Scope
of the court's jurisdiction
[4] There is
no dispute as to the scope of the court's jurisdiction. As the parties had
agreed to give Mr Morrison the remit of determining their factual
disputes, they have excluded probation of the matters which his report
covered. They have confined their right to challenge his report to issues of
law. This is consistent with the general approach of the court which Lord Eassie
set out in Allied Dunbar Assurance plc v Superglass Sections Ltd (unreported)
20 August 2004 at paras 23 and 24: where the parties have agreed a
remit to a skilled person to determine a question and he has performed that
remit, the court will not allow another mode of proof. See also Dixon v
Monkland Canal Company (1825) 1 W & S 636, Lord Gifford
at 655; and Lord Blantyre v Glasgow, Paisley and Greenock Railway
Company (1851) 13 D 570, Lord President Boyle at
573. Absent a reservation in the remit of the right to have a further proof,
which would defeat the cost-saving purpose, the reporter's decision governs
questions of fact.
[5] The legal
challenges available are familiar. As the reporter has received a contractual
remit, any failure to implement the directions of his remit, including a
failure to exhaust the remit, would ground a legal challenge. If the reporter
misconstrued a legal document, such as the lease, in a material way, that would
be an error of law which would invalidate his determination to the extent that
the error affected his decision. So also would be a material misunderstanding
of a non-legal document, although the court allows the decision-maker greater
discretion in interpreting such documents and will not treat a tenable
interpretation as an error of law (Findlay, Petitioner [2006] CSOH 188,
at paras 31-33). Where there required to be a factual basis for a
decision, the absence of such a basis would support a legal challenge to the
decision. Taking into account an irrelevant matter or failing to take into
account a relevant matter are familiar grounds of challenge (Wordie Property
Co Ltd v Secretary of State for Scotland 1984 SLT 345,
Lord President Emslie at 347). Another way of analysing those
grounds is to say that the decision maker has acted on the basis of a mistaken
view as to the facts. Mr Dunlop referred me to that formulation in The
Learning Trust v MP and the Special Educational Needs and Disability
Tribunal [2007] ELR 658, [2007] EWHC 1624 (Admin), Andrew Nicol QC
sitting as a deputy judge of the High Court at para 29. Wednesbury unreasonableness
is another ground of legal challenge (Wordie (above)). So also is the
failure to give an adequate statement of reasons for a decision so that the
informed reader and the court are left in no substantial doubt as to the
reasons for the decision (Safeway Stores plc v National Appeal Panel 1996 SC 37,
Lord Justice Clerk Ross at 40-41).
The service charge
[6] Clause 8(2) of the lease provides that any part of the service
charge shall be payable to the landlord by the tenant on demand as and when the
item of expenditure is incurred or the landlord becomes liable to pay it. The
service charge is defined in clause 8(1) as follows:
"To pay to the Landlord in the manner mentioned in Sub-clause (2)of this Clause 8 a fair proportion of the expense incurred by the Landlord in supplying any services facilities or amenities whatsoever to the Premises or the Building and in cleaning, decorating, painting, plenishing, lighting, repairing, maintaining, renewing or rebuilding any part of the Common Parts...
...and of any expenses incurred by the Landlord in complying with any requirements of a competent authority relating to the Premises or the Building or any part thereof or any obligation thereanent under any superior lease and to provide for periodic items including repairs and redecoration (and that regardless of the age or state of repair or dilapidation of the Building and irrespective of the cause of the damage causing such repair, maintenance, renewal, rebuilding or others, and including any which may be rendered necessary by any defects, latent or patent, which may exist or subsequently become manifest in the Building) together with any outgoings and Value Added Tax which the Landlord may be liable to pay in respect of such services and matters or in respect of the Building..."
Clause 8(3) defines "fair proportion" for the purposes of clause 8(1) in relation to different parts of the building.
[7] Mr Dunlop
submitted that the range of work covered by the service charge in clause 8(1)
of the lease was very broad. It covered works which at common law would be
classified as extraordinary repairs (House of Fraser plc v Prudential
Assurance Co Ltd 1994 SLT 416, Lord Cullen 419D-J) and
extended to rebuilding. He emphasised that the disregards in parentheses in
clause 8(1) had the effect that the history or the cause of a state of
fact was not relevant and he referred to Lowe v Quayle Munro Ltd 1997 SC 346,
Lord Penrose at 350G-351A. Mr Richardson did not seriously challenge
this analysis but submitted that it fell to be implied into the lease that the
costs must be reasonably incurred. I consider that that is correct (Gordon
District Council v Wimpey Home Holdings Ltd (No 2) 1989 SLT 142).
Mr Dunlop did not suggest otherwise. Further, I observe that the parties
have acted on that understanding by including in the remit a question in
relation to each of the disputed items whether the costs incurred were
reasonable. Similarly, the parties, recognising that the service charge did
not cover the redevelopment of the upper floors, included in the remit a
question whether each of the disputed works related to the (phase 3)
redevelopment of the building.
[8] Between
2008 and 2010 BAM Construction Limited, a company associated with the landlord,
carried out works on the premises and the building in three phases under the
supervision of Gardiner & Theobald, quantity surveyors. The first phase
comprised works on the front façade, envelope repairs and roof works. The
phase 2 works involved repairs to the rear façade of buildings in Morrison
Court, later known as buildings A and B, of which only building A was within
the tenant's demise. Phase 3 related to retail and office development
which amounted to a re-development of the building, including the refurbishment
of the upper floors to bring them back into use. The landlord makes no claim
for a service charge in relation to that phase. But the tenant has suggested
that certain works in the earlier phases related to the redevelopment of the
building and involved betterment. The tenant has also challenged certain works
as unnecessary and certain charges as excessive.
[9] The
reporter produced a draft report dated 21 December 2012. Thereafter, the
landlord lodged a note of objections, which the tenant answered. In this
opinion I deal in turn with each of the landlord's objections.
(a) Phase 1 Works (pp.1-9 of the reporter's schedule)
[10] The
landlord challenged the reporter's reduction of the claim in application for
payment no. 5 by Stirling Stone Limited dated 28 October 2008. The
reporter considered that the rates which the sub-contractor charged in respect
of certain items were excessive. Mr Dunlop submitted that the reporter
had no jurisdiction to look behind the invoice which the sub-contractor
submitted and the landlord had paid. Further he had failed to give
comprehensible reasons for holding those rates to be excessive.
[11] I am
satisfied that the reporter has not erred in law in this regard. Two of the
questions on which he was asked to report in relation to the service charge
were:
"(e) In so far as evidenced, are the costs incurred reasonable?
(f) In the event that it is considered that costs in respect of particular items that are not yet agreed between the parties in terms of the Response have been evidenced but were not reasonable, what costs would have been reasonable for such items?"
It is clear from this remit that the reporter was empowered to look behind the rates contained in an invoice submitted by the main contractor or a sub-contractor and to take a view on what was a reasonable charge for the work in question. The reporter accepted the rates which the sub-contractor had charged for certain items of work and modified others. Where the reporter reduced the rate for an item, he recorded that the rate claimed was excessive for "the scope of the work" or for "the nature and scope of the work" and stated what he considered to be a reasonable rate.
[12] Mr Dunlop
accepted that it would have been sufficient reasoning if he had stated that the
rate was excessive by reference to the market rates that were current when the
works were carried out. In my view that was implicit in what the reporter has
stated. In para 5.1.6 of his report Mr Morrison listed the main
variables that determined the cost of the works. They included "fluctuations
in labour and material costs" and "prevailing market forces". He explained
that he had based his assessment of reasonable costs on:
"a combination of the following:
· The costs which have been evidenced by the Pursuer
· The costs detailed in the Defenders' response
· Reference to the BCIS Building Maintenance Price Book ?Edition [sic] for guidance on labour and material rates
· My professional opinion.
On a number of occasions I have not accepted the contractor's rate where in my opinion the specified rate or cost in the bill item is not appropriate."
I consider this to be adequate reasoning in the circumstances of his remit.
(b) Phase 1 Works: biocidal wash (p.8 of reporter's schedule)
[13] On page 8
of his schedule the reporter considered a claim for £11,584.75 which related to
the biocidal wash of the glazed brick section of the building. The tenant
contested that charge and suggested a cost of £6,750. The reporter decided
that the area and rate claimed were excessive and referred to an email dated 12 November
2008 in support of the conclusion that the cleaned area was only 146 sq metres.
Applying a rate of £8.00 per square metre, he valued the claim at £1,168.
[14] Mr Dunlop
submitted that the reporter had fallen into error by misunderstanding the
evidence before him. In particular, he suggested that the reporter had
misconstrued the email of 12 November 2008 from Stirling Stone Ltd to the
landlord. In that email Mr Bill Smith of Stirling Stone Ltd stated:
"Further to our discussions regarding the Final Account we would confirm the following reductions should be made to the proposed final account:
1.
|
Holes on glazed bricks |
49 nr @ £500 |
= £2450.00 |
2.
|
Cleaning |
146 sq m @ £19.18 |
= £2800.28 |
3.
|
Out of hours |
Tender does not require this therefore variation remains. ..." |
Stirling Stone Ltd initially claimed £14,385 for 750 sq m of biocidal wash at a rate of £19.18 per sq. m. in its application for payment no. 5. The landlord deducted £2,800.25 from that sum and claimed £11,584.75 (604 sq m x £19.18) from the tenant. The email intimated agreed reductions from the sub-contractor's claim in its final account and one had to look at that account and apply the reductions to understand what Stirling Stone Ltd had claimed from the landlord and what properly was the landlord's claim.
[15] I am
persuaded that the reporter has misread the email which bears the
meaning that Mr Dunlop suggested. In short, the reporter has treated the
proffered reduction as the result or product of a reduction. Mr Richardson
pointed out that the reporter had found that both the area and the rate were
excessive. While that is so, it appears that the reporter has relied on the
email of 12 November 2008 as vouching that the area which was cleaned was
146 square metres. As, in the absence of evidence of the factual matrix
which supports a contrary construction, I consider that to be a misinterpretation
of the email, I think that the reporter has erred. I will therefore direct him
to reconsider this claim together with any further submissions which he allows
the parties to make in relation to the interpretation of the email.
(c) Further coats of biocidal wash at fire damaged area (p. 8 of reporter's schedule)
[16] The
reporter disallowed the claim for £750 in respect of two further coats of
biocidal wash which the landlord claimed was required at a fire damaged area.
He found that the work would improve the appearance of the building but that
the two coats were "in excess of the cleaning of the common parts as detailed
in clause 8(1) of the sub under lease". He suggested that the work
related to phase 3 works.
[17] Mr Dunlop
submitted that this was an error as Stirling Stone Ltd carried out and charged
for the biocidal works well before phase 3 started in February 2009.
[18] I am
satisfied that there is nothing in this challenge. The landlord did not focus
on this challenge in its note of objections and it is therefore not properly
before me. In any event, I construe the reporter's decision as meaning that
the two further coats were in excess of the scope of the service charge in the
lease. That was the gravamen of his decision and the comment about phase 3
was not essential to his reasoning. I construe the reference to phase 3 as
shorthand for the works to redevelop the building. In relation to the
objection in the note of objections, I consider that it was for the reporter to
judge both whether the work that was carried out fell within the concept of
"cleaning" in clause 8(1) and whether it was reasonable to incur the
claimed costs. He has treated the work as entailing cleaning but has concluded
that the works went beyond what clause 8(1) of the lease envisaged. That
is a matter for his judgement. I detect no legal error on his part.
(d) Repairing holes (reduced) (p. 9 of reporter's schedule)
[19] The
landlord claimed £1,450 for the repair of holes as part of the restoration
works on the building. The tenant suggested that the appropriate charge was
£600. The reporter found that the rate charged by Stirling Stone Ltd was
excessive and allowed for the filling of 19 holes at £25 per hole. He
stated in response to the question as to what costs would have been reasonable
"allow 19 No (49 - 30) @ £25.00 = £475)".
[20] Mr Dunlop
submitted that the reporter had erred in misconstruing the email dated 12 November
2008 which Stirling Stone Ltd sent to the landlord (para [14] above).
Stirling Stone Ltd's application for payment no. 5 included a claim for
the repair of 78 holes at the rate of £50 per hole. The email intimated a
reduction of 49 holes, leaving a balance of 29 holes.
[21] In my
opinion the reporter has misconstrued the email as discussed in para [15]
above. He treated the reduction of 49 holes as the product of the
reduction, namely that the total number of holes filled under items 5.5.f and
5.5.g of the Scott schedule was 49. Of that figure he allocated 30 to the
repairs under 5.5.f and the balance of 19 to 5.5.g.
[22] As the
error affects his treatment of items 5.5f and 5.5.g, I will direct the reporter
to reconsider both of those items in the light of this guidance and any further
submission which he allows the parties to make on this issue.
(e) Disallowance of claims because nature of work was unclear (p. 10 of reporter's schedule)
[23] The
landlord claimed £200 for cleaning off mortar from previous builderwork and
£1,500 for "stripping down butt at top floor (glazed brick)". The tenant
suggested that no sums were due under either entry. Both entries were included
in Stirling Stone Ltd's application for payment no. 5 dated 28 October
2008. The reporter found that the landlord had become liable to pay for those
items before the termination of the lease on 27 January 2009 but decided
that the costs were not reasonable because the nature of the works was unclear.
[24] Mr Dunlop
submitted that the reporter's conclusion was irrational because, like other
items, the claims were supported by the evidence of Stirling Stone's
application for payment and the landlord had paid for the work. Alternatively,
the error could be seen as a lack of adequate reasoning or as a failure to
fulfil his remit by asking parties for further information about the claim.
[25] Mr Richardson
submitted that the reporter's approach was not irrational. When he found that
the nature of the work was unclear, he was responding to a question "in so far
as evidenced, are the costs incurred reasonable?" The reporter was entitled to
disallow a claim if, having considered the detailed reports which each party
provided him, he was unclear as to the nature of the work. He submitted that the
reporter's powers to obtain further information under clause 7 of his
remit were discretionary.
[26] I do not
think that the reporter was irrational. He had a power under clause 7 of
his remit to interview any individual to obtain further information or to ask
the parties to produce further evidence so that he had sufficient information
to reach an opinion. But, as Mr Richardson contended, he had a discretion
whether to exercise that power. In my opinion when he was dealing with
comparatively low value items, the reporter was entitled to decide whether a
cost was reasonable in the light of the information which the parties placed
before him. I detect no legal error in this regard.
(f) Scaffolding (p.11 of the reporter's schedule)
[27] Mr Dunlop
also attacked the reporter's decision to reduce the landlord's claim for
scaffolding from £74,312.27 to £42,600 on the basis that part of the
scaffolding costs related to the phase 3 redevelopment works. He observed
that the charge for scaffolding works was vouched by an invoice from TTAG
Scaffolding Ltd which the landlord had paid well before the phase 3 works
commenced. The reporter had been provided with documentary evidence of the
charge and its payment. Further, in assessing what costs were reasonable, the
reporter had omitted to allow anything for ties for signage and for adaptations
which formed part of TTAG Scaffolding Ltd's claim. By so failing, the reporter
had not completed his remit.
[28] I am
satisfied that Mr Morrison has not erred in law in this regard. First,
his reference to phase 3 works is shorthand for the redevelopment works
which do not fall within the service charge. Thus the fact that an invoice was
paid before the phase 3 works were started does not indicate any error of
law. Secondly, in relation to the alleged failure to include charges for ties
for signage and adaptations, Mr Richardson pointed out that the landlord's
expert report by Mr Francis Fitzpatrick, which formed the basis of
its claim before the reporter, did not separate out those items in its claim
for £74,312.27 (Appendix p.6). I agree with Mr Richardson that there
is nothing to suggest that the reporter failed to perform his remit. He had
before him the claim for £74,312.27 from the Fitzpatrick report and he
identified in answer to the parties' questions the costs which he considered to
be reasonable.
(g) Supply and fit Gypliner; beam encasure works; dry lining the roof light; and cut and remove water damaged flooring and joist caused by leaking roof (pp. 17, 19, 20 and 21 of reporter's schedule)
[29] The
reporter disallowed each of these items in answering the question whether the
costs were reasonable. In each case he expressed the view that the costs
related to the phase 3 works and were not reasonable "in the context of
the service charge". Mr Dunlop's challenge to this treatment of each of
the items was that the reporter had misconstrued the scope of the service
charge in the lease. Clause 8(1) entitled the landlord to recover through
the service charge the costs of repair and rebuilding regardless of the state
of the disrepair. All of the works were carried out under phase 1 and
predated the phase 3 redevelopment.
[30] I am
satisfied that the reporter has not erred in law in excluding these items. The
third question in the remit relating to the service charge (question (c)) was:
"Do the items claimed by the pursuer in the Phase 1 Scott Schedule Final Report and the Phase 2 Scott Schedule Final Report as produced in the "Fitzpatrick Report" that are not yet agreed between the parties in terms of the Response relate to the Phase 3 Works ...?"
This question clearly recognised that one issue in the dispute was about whether works done in phases 1 and 2 were in substance redevelopment works which were not properly within the service charge. Further, question (e), which I set out in para [11] above, asked whether the costs incurred were reasonable. In the context of the parties' agreed position that the costs claimed under the service charge must have been reasonably incurred (see para [7] above), the reporter had the remit of reaching a view on whether items in phases 1 and 2 were outside the service charge because they related to the redevelopment of the building. If they were, he was entitled to hold that the costs of those items were not reasonable as part of the service charge. Each of the items related to works on the upper floors which, before the works, were vacant and semi-derelict. The reporter found that the first three altered the pre-existing nature or quality of the building and improved the condition of the upper floors. The reporter took the view that they were properly categorised as redevelopment work. I detect no error of law in his approach to the questions he was asked to address.
(h) Strip out glass in two roof lights and install patent glazing bars and Georgian wired obscure glazing (p. 22 of reporter's schedule)
[31] Mr Dunlop
submitted that the reporter had erred in disallowing this item because there
was no evidence that there was water penetration. That, he suggested, involved
a misconstruction of the scope of the service charge.
[32] I am
satisfied that there is no substance on this challenge. As Mr Richardson
submitted, it takes a statement in his response to question (e) ("Insofar
as evidenced, are the costs reasonable?") out of context. When one considers
the entirety of the reporter's answers to the questions on this item, it is
clear that he considered that the item involved improvement and related to the
redevelopment of the building. Accordingly, it did not fall within the service
charge. That was a matter for the reporter to decide.
(i) All gutter bearers, raggling, pointing etc. necessary to completely renew all associated leadwork; strip out existing lead gutter to front and sides of dome and renew etc.; and overlay wallhead to front and sides of dome (pp. 24-25 of reporter's schedule)
[33] This
challenge concerned to three items of work in relation to the dome of the
building. The reporter allowed only 20% of the overall cost as part of the
service charge in relation to the first and last items but 80% in relation to
the second item (stripping out and replacing the lead gutter). Mr Dunlop
submitted that he had failed to explain why he had awarded different
proportions of the costs in respect of the different items. The findings were prima
facie inconsistent. He had failed to give adequate reasons for his
decision. Further, in relation to the first and second items the reporter had
observed in his response to question (e) ("Insofar as evidenced, are the
costs reasonable?") that the replacement leadwork had a 25 year guarantee,
which amounted to betterment. Mr Dunlop submitted that as the landlord
had excluded the cost of that guarantee from his claim, the reporter had taken
an irrelevant consideration into account.
[34] I am not
persuaded that there is any substance in the first part of this challenge. The
items are three separate items which the reporter had to consider
individually. Further, on considering the reporter's answers to all of the
questions in relation to these items, it is clear that, in the cases in which
he allowed only 20% of the claim, he was not persuaded that there needed to be
renewal to the extent claimed. Thus he attributed most of the cost to
redevelopment rather than the service charge.
[35] I am
satisfied that the reporter proceeded under a mistaken understanding of the
evidence when he founded on the existence of the guarantee as the Fitzpatrick
report in schedule 2 (item 21) had stated that the landlord had not
claimed on the basis of the tender which included that guarantee but on a lower
tender which did not. I will therefore direct the reporter to reconsider this
aspect of his decision with the assistance of such further submissions from the
parties on those items as he may order.
(j) Entries from scope of work H 71 (Lead sheet coverings/flashings) where reporter allowed no cost (pp.23-28 of the reporter's schedule)
[36] Mr Dunlop
submitted that the reporter had erred in excluding altogether claims for
certain items in scope of work H 71 on the ground that they were not
essential. In relation to several items he had answered question (e) by
saying that the costs were not reasonable in the context of the service charge
and by referring to a survey report of March 2006 which recorded that the
bituminous felt was serviceable and that re-covering was not considered to be
essential. This, he submitted, demonstrated a misunderstanding of clause 8(1)
of the lease which did not confine the works for which the landlord could claim
under the service charge to items which were essential.
[37] Mr Richardson
objected to the argument that there was an error in requiring items to be
essential. This was not foreshadowed in the note of objections which wrongly
asserted (in para 13) that the reporter had allowed nothing for items
under scope of work H 71. In my view there is substance in that objection. In
order to ensure timely resolution of disputes, it is incumbent on parties to
identify their objections in the manner which the remit provided in clause 5.
In any event, I construe the reporter's answers to the earlier questions as
expressing the view that the works involved betterment and were to be treated
as part of the redevelopment of the building. The reference to re-covering not
being essential appears to be a summary of the survey report rather than the
ground of his decision. The reporter's answer to question (e) in my view
is the result of his answers to the earlier questions about betterment and
redevelopment rather than the application of an incorrect criterion in
answering question (e).
[38] Mr Dunlop
also submitted that the reporter had erred because the excluded works were
required by statute. While it may be correct that the landlord would have to
use a specific code leadwork on the dome in place of the felt to comply with
listed building legislation, the matter was not focused in submissions to the
reporter, including the King Sturge dilapidations report to which Mr Dunlop
referred. I am not persuaded that the reporter erred in law in this regard.
If he were aware of the listed building requirements in relation to the
building, that awareness would not necessarily alter his judgement that the
claimed items were redevelopment rather than proper charges under the service
charge.
(k) Lifts (p. 35 of the reporter's schedule)
[39] Mr Dunlop
submitted that the reporter had erred in law in treating a claim for lift
replacement as betterment on the mistaken understanding that the original lift
had been removed and a new lift installed at a new location as part of the
redevelopment of the building. The reporter had misunderstood the evidence and
so erred in law. The landlord had claimed only for the removal of the lift as
part of the service charge and not for the cost of the lift which replaced it
at the same location.
[40] Mr Richardson
explained that the reporter had not erred in his understanding of the
evidence. The relevant lift (which counsel referred to as the "Dorothy Perkins"
lift) had been a combined goods and passenger lift. It was removed and
replaced at the same location by a passenger lift which was to a higher
specification. A new goods lift was installed on the east of the building at
the location of a pre-existing goods lift, as part of the redevelopment. The
reporter had not erred in his understanding of the evidence. He referred me to
a diagram of the building (Pro 7/23) which appeared to bear out his
submission.
[41] On the
information before me I am not persuaded that the reporter erred in law in his
treatment of this item. He was entitled to treat the removal of the "Dorothy
Perkins" lift as part of the redevelopment rather than a proper item for the
service charge.
(l) Costs of the structural engineer (p. 36 of the reporter's schedule)
[42] Mr Dunlop's
final challenge under the service charge was that the reporter had erred in his
conclusion that it had not been necessary to engage a structural engineer owing
to the nature of the works, the costs of which were recoverable under the
service charge. He contended that no reasonable reporter would have concluded
that a structural engineer was not needed in relation to:
(i) the works in the scope of work H 71;
(ii) the structural strengthening between level 6 and the roof;
(iii) remedial and strengthening works to the roof and 6th floor support structure;
(iv) replacing steel channels and plates between the 6th floor and the roof, including rebuilding a section of wall; and
(v) installing permanent structural support of the basement roof supporting Buchanan Street pavement.
Mr Dunlop submitted that the reporter had failed to give comprehensible reasons for his decision.
[43] The
background to the reporter's decision was the tenant's challenge to the claim
for the structural engineer's fees (appendix 1 p. 17 of the
Fitzpatrick report) which stated (so far as relevant):
"In addition, Beattie Watkinson are a firm of structural engineers and it is not clear why their input was required for works in relation to the service charge. Beattie Watkinson were appointed to design structural alterations to the property, including the redevelopment of the rear section of the property. The works are not part of the service charge."
The reporter, when he considered the claim for professional fees, answered question (e) ("Insofar as evidenced, are the costs incurred reasonable?") in the negative. He stated:
"The inclusion of fees for a structural engineer is unreasonable in my opinion given the nature of the work recoverable through the service charge for works to the common parts."
His decision flows from his assessment of the scope of the service charge. I have not detected any significant errors of law in that assessment which would impact on the role of a structural engineer. I therefore reject the challenge that the reporter was unreasonable in his refusal to allow the recovery of the fees of the structural engineer under the service charge. Further, I do not have difficulty in following his reasoning and do not consider it to be inadequate.
Dilapidations
[44] The tenant had an obligation under clause 4(6) of the lease:
"at all times throughout the term at the tenant's expense well and substantially to repair, maintain, rebuild, reinstate, decorate, cleanse, glaze, point and generally in all respects put and keep in good repair and condition the premises and every part thereof ..."
Under clause 4(7) of the lease the tenant was obliged on every fifth year of the term and also:
"in the last three months of the term to decorate the interior of the premises in a workmanlike manner to the reasonable satisfaction of the Landlord, and in the case of the last such decoration prior to termination of this lease to carry out the same in accordance with colour schemes and finishes approved by the landlord."
[45] Mr Dunlop
mounted two challenges to the reporter's determination in relation to
dilapidations. First, he submitted that the reporter erred in law in disallowing
the cost of replacing a disused goods lift to the east of the demised premises
(marked "3" in the annotated lease plan which is item c. in appendix IX
to the Fitzpatrick report). Clause 1 (12) of the lease defined the
demised premises as the subjects specified in the first schedule to the lease.
In turn, the first schedule described the premises by reference to what was
outlined in red on annexed plans
"together with (one) right of egress in emergency only by the staircase shown coloured yellow on said plans (subject to payment of 50% of the whole costs of maintenance and decoration thereof, as certified by the landlord's surveyor); (two) the goods lift shown on said plans ...".
[46] The
difficulty which has arisen is that the plans of the basement and ground floors
attached to the lease show two lifts. One, which is within the red line of the
premises at the south is marked "goods/passenger lift" and counsel referred to
it as the "Dorothy Perkins lift". The other, which lies to the east of the
premises and outside the red-lined area, is marked "goods lift".
[47] The
reporter construed the lease as referring to the "Dorothy Perkins lift" on the
south of the premises, which I discussed in paras [39] and [40] above in
relation to the claim for removal costs under the service charge. He found
that the costs of redeveloping that lift were not reasonable in the context of
a dilapidations claim but that they were reasonable costs for the redevelopment
of the building. He stated:
"From my review of the sub-under-lease, I am of the opinion that the goods lift referred to in (two) of the first schedule relates to the lift within the leased premises located at the south external wall adjacent to the stair, rather than the goods lift to the east out with the leased premises as the Tenant only had a right of egress in emergency to the common passageway giving access to the exit stair and the east goods lift.
Should my opinion subsequently be proved to be incorrect and the east goods lift did form part of the leased premises, I reserve the right to amend my opinion on the reasonable costs."
[48] Mr Dunlop
submitted that the reporter's opinion was indeed incorrect and that he had
erred in treating the "Dorothy Perkins lift" as the lift to which the first schedule
referred. He advanced two reasons for his submission. First, the lift to the
east was the only lift which the plans described as "goods lift". It was
located at the rear of the building. Secondly, the lift marked
"goods/passenger lift" (i.e. the "Dorothy Perkins lift") was clearly located
within the red lines of the premises.
[49] Mr Richardson
disputed that construction of the lease. He pointed out (consistently with the
reporter's construction) that in the first schedule the right to use the
building to the east of the premises was confined to the emergency egress (para [45]
above). It made no sense for the demised premises to include a goods lift to
which the tenant had no access. It made more sense to interpret the expression
"goods lift" as referring to the "Dorothy Perkins lift" which could have served
the other floors if they had been in use as well as the demised premises. That
lift would not otherwise fall within the clause 1(12) definition. There
was no reference to lifts in that definition. It extended "the premises" only
to those other parts of the building, including services, which exclusively
served the premises. The "Dorothy Perkins lift" did not serve the premises
exclusively. It made sense therefore to include the "Dorothy Perkins lift" in
the definition of the premises by the reference in "(two)" in the first
schedule. It was also a standard conveyancing practice to demise a lift
expressly.
[50] I think
that the reporter has correctly construed the lease. The use on the plans of
the expression "goods/passenger lift" to describe the "Dorothy Perkins lift"
has created some ambiguity. But I am persuaded that the lack of access to the
lift at the rear of the building makes it highly unlikely that the parties
intended that lift to be within the definition of the demised premises. I
consider the fact that the "Dorothy Perkins lift" is shown within the red line
of the premises is of no moment. I detect no error in the reporter's exclusion
of the claim for the replacement of the goods lift to the rear of the building.
[51] Mr Dunlop's
final challenge related to the reporter's exclusion of the landlord's claim for
redecoration of sales areas, staff rooms, lavatories, staircase enclosures and
stockrooms (item 19 in appendix 4 to the reporter's report). Mr Dunlop
referred to the tenant's obligation in clause 4(7) of the lease (para [44]
above) and observed that while the tenant had contested the landlord's claim
(£8,099.67) under this head, it had suggested that £7,103.46 was due. That
notwithstanding, the reporter had disallowed the claim. He explained his
decision to allow nothing under this head in answer to question (e)
("Insofar as evidenced, are the costs reasonable?"), stating:
"While it is clear that the tenant did not redecorate at the ish in accordance with the lease terms, the scope of the decoration carried out by the landlord was in connection with the redevelopment of the building and the works altered the premises superseding the requirement in my opinion."
Mr Dunlop submitted that the issue was properly one of quantification, by the exclusion of betterment, rather than disallowance in total and accordingly the reporter had erred.
[52] Mr Richardson's
riposte was succinct: the reporter was entitled to hold that the landlord had
suffered no loss because the redecoration was part of the redevelopment.
[53] I do not
think that Mr Richardson's point is a complete answer to the challenge.
As I said in a case which involved another report by Mr Morrison, namely Sane
Investments Ltd v AstraZeneca UK Ltd [2013] CSOH 81, at
para 13, the landlord is entitled to be placed in the same position in
monetary terms as it would have been if the tenant had not breached its
contract by failing to redecorate. That may raise issues of savings or of
betterment when the landlord decorates the premises in a way which differs from
the tenant's obligation. In other cases where the landlord radically alters
the layout of the premises in a redevelopment, that work would have superseded
the tenant's redecoration and would give rise to an argument that the tenant's
failure to redecorate caused no loss.
[54] There is
some ambiguity in the reporter's explanation of his decision. If he is saying
that the redevelopment works changed the layout of the areas in question to
such a degree that any redecoration by the tenant would have been wasted
expenditure, that may be unexceptionable. But if part of his reasoning is that
the redecoration was to a higher standard than that which the lease required,
that would not provide a reason for disallowing the whole claim. I propose to
direct the reporter to clarify his reasoning and, if necessary, reconsider this
item of claim.
Conclusion
[55] I have generally sustained the reporter's decisions because I have
not been persuaded that he erred in law. But in paragraphs [15], [22],
[35] and [54] above I have upheld Mr Dunlop's challenges in relation to
some of the smaller items or parts of claims. Counsel invited me to express my
views on the challenges and have the case put out by order to enable a brief
discussion of the precise terms of any directions which arose from my
decision. I will have the case put out by order for that purpose and invite
the parties to submit in advance of that hearing a draft of the directions
which they propose.