OUTER HOUSE, COURT OF SESSION
|
|
|
OPINION OF LORD WOOLMAN
in the Commercial Action
GREATER GLASGOW & CLYDE HEALTH BOARD
Pursuers;
against
GHI CONTRACTS LIMITED
Defenders:
________________
|
Pursuers: Richardson; Pinsent Masons LLP
Defenders: Mure QC; Maclay Murray & Spens LLP
14 November 2012
Introduction
[1] In
2007, Greater Glasgow Health Board ("GGHB") sought tenders for works to be
carried out at the Royal Alexandria Hospital, Paisley ("RAH"). The works involved the refurbishment of the maternity unit. GHI
Contracts Limited ("GHI") tendered £3,846,710.64 for the works. On 4
December 2007, GGHB accepted the tender
and appointed GHI as the main contractor. There was the usual extensive
documentation for a contract of this nature and scope. It was based upon the
Standard Building Contract With Quantities for use in Scotland, 2005 edition
(Revised May 2006) and appendices I - IV, together with amendment 1:
April 2007 ("the Contract").
[2] The
labour ward, theatres and high dependency unit are located on the first floor
level. Most of the works were to be carried out there. But they were also
necessary in other parts of the building, including decant facilities on the
third floor level. GGHB wished to ensure the continuity of obstetric services. The sequencing of
the works was therefore important. There were a high
number of variations during the course of the works. The contract period was
43 weeks, but practical completion only took
place much later, in August 2009.
[3] At
the conclusion of the works, GHI lodged two applications for payment.
Application No. 19 sought payment
of £5,968,232.70 for the period ending 28 July 2009. On 27 October 2009 GGHB issued an
interim certificate for £4,572,701.66. GHI
did not accept the certified sum and referred
the claim for adjudication. Mr L C H Bunton of Bunton Consulting
Partnership acted as the adjudicator. In December 2009, he decided that
GHI was not entitled to any further sums in respect
of application No. 19.
[4] Application No. 21 related to the period ending 5 March 2010. GHI sought payment of £6,220,777.46.
On 26 April 2010 GGHB issued an interim
certificate for £4,746,134.01. Again GHI referred the matter for
adjudication. In his Award dated 10 September 2010, Mr Bunton determined that GGHB should pay GHI £544,943.64 plus
VAT, together with interest of £37,821.92 ("the Award"). Subsequently GGHB
satisfied the Award by paying those sums to GHI.
[5] Neither
party agrees with the Award. GGHB argues that it is an overvaluation, while GHI maintains that it is an undervaluation. Hence this action.
GGHB seeks to recover most of the sum it has already paid to GHI. The summons
proceeds on the ground of unjust enrichment. For present purposes, the
arithmetic is not important and it is sufficient to notice that GGHB concludes
for payment of £776,723.61. In its counterclaim for £277,312.53, GHI seeks payment
of higher sums than those awarded by Mr Bunton. It also seeks payment for (a) re-measurement of sanitary ware, and
(b) overtime worked to mitigate delay. Neither
of these items was included in application 21.
[6] The
respective valuations of the heads of claim are as follows:
Head of Claim |
Award |
GGHB |
GHI
|
Soil Vent Pipes, Building, M & E
|
£200,800.60 |
£91,355.77 |
£207,077.49 |
M & E Coordinator
|
£15,500.00 |
£0 |
£46,125.00 |
Mark-up on M & E variations
|
£110,146.03 |
£40,521.96 |
£110,146.03 |
Isolation Works
|
£43,747.26 |
£0.00 |
£32,263.86 |
Stainless Steel Works/Piping
|
£57,101.00 |
£18,857.64 |
£66,797.62 |
Extension of Time |
42 wks |
31 wks |
43 wks 1 day
|
Additional Preliminaries
|
£138,222.00 |
£0.00 |
£153.509.88 |
M & E Extension of Time
|
£146,319.85 |
£0.00 |
£190,069.49 |
Additional Staff
|
£99,940.00 |
£0.00 |
£120,850.19 |
Re-measurement of Sanitary Ware
|
- |
- |
£52,154.11 |
Overtime to mitigate Delay
|
- |
- |
£87,914.75 |
There are four short points to make at this point. First, both in the table and throughout this opinion, I use "M & E" as shorthand for "mechanical and electrical". Secondly, all items in the table are listed exclusive of VAT. Thirdly, the extension of time period is included as it is the basis for certain heads of claim. Fourthly, during the hearing I granted Mr Mure's unopposed motion to amend the figure for additional preliminaries from £159,392.88 to £153,509.88.
The Scope of the Dispute
The Pleadings
[7] The matter
came before me on the procedure roll at the instance of GGHB. Its note of
argument contended that GHI's pleadings were irrelevant, inspecific, or both.
At the outset of the hearing, Mr Mure moved to amend GHI's pleadings in
terms of a minute of amendment that he lodged at the bar. It referred to
several documents that (he said) demonstrated how GHI calculated several of the
disputed heads of counterclaim. They had been lodged as tabs 10, 12, 13, 14 and
15 of the joint bundle of documents. Mr Richardson did not oppose the
motion to amend, but invited me to reserve both GGHB's right to revise its own
pleadings in response and the question of expenses. I allowed the amendment on
that basis.
GHI's Position
[8] GHI adopts
a straightforward position. It seeks a proof before answer. Mr Mure
submitted that the claims require to be placed in context. At this stage the
court does not have full information. It is being asked to proceed on the basis
of the abbreviated pleadings suitable for a commercial action. Further, the
joint bundle contains only a fraction of the relevant documents. If the matter
is remitted to proof, the court will have the benefit of fuller material,
including detailed witness statements and oral testimony. Mr Mure argued that
it is important for the court to know what the professionals involved were
thinking, doing and communicating at any given point during the course of the
Contract. Absent that evidence, there is a limit to what the court can
understand about the project.
GGHB's Position
[9] Mr Richardson
accepted that the late minute of amendment cured certain points of
specification. He indicated that GGHB might not have sought a debate if it had
been lodged at an earlier stage. He also accepted
that a proof would be required on a number of heads of claim.
He insisted, however, that GHI's
pleadings were deficient in a number of material respects.
The Effect of Adjudication
[10] Journalism
is said to be the first rough draft of history. In my view, adjudication can
be viewed in a similar light. It is only a provisional assessment. An
adjudicator's award only binds the parties until the
dispute is finally determined. That can occur through litigation, arbitration
or agreement between the parties: Scheme for
Construction Contracts (Scotland) Regulations 1998, Schedule Pt.1 para. 23(2).
In this case, the adjudication was an important event for the parties. But it
has no bearing on the issues in this litigation, other than to provide the
basis for the arithmetic in calculating the various sums alleged to be due.
[11] I accept
that the court should be careful about dealing with matters as a "desk top"
exercise. But relevancy depends solely on the pleadings. Most of the disputed
claims made by GHI relate to claims for loss and expense or variations. In some
instances, they are pleaded in the alternative. The main thrust of Mr
Richardson's submissions was that GHI's averments did not support its first
plea-in-law, which states that the counterclaim is brought "under and in terms
of the
contract". He maintained that, as framed, the disputed elements did not comply
with the terms of the Contract. The pleadings in respect of these items were
therefore irrelevant and should not be remitted to probation.
[12] At proof the
question of onus is not affected by the adjudicator's decision: City Inn Ltd
v Shepherd Construction Ltd 2002 SLT 781, 794L per Lord Macfadyen. At
debate GHI's pleadings must of course be taken pro veritate. But
thinking about the burden of proof is not a wholly superfluous exercise. It
assists in concentrating on the central question of relevancy: if GHI
establishes all the matters it offers to prove, would it be entitled to succeed
in the counterclaim?
The Contract
Loss and Expense
[13] Claims
for loss and expense are governed by clause 4.23 of the Contract:
"If in the execution of this Contract the Contractor incurs or is likely to incur direct loss and/or expense for which he would not be reimbursed by a payment under any other provision in these Conditions due to a deferment of giving possession of the site or relevant part of it under clause 2.5 or because the regular progress of the Works or of any part of them has been or is likely to be materially affected by any of the Relevant Matters, the Contractor may make written application to the ... Contract Administrator. If the Contractor makes such application, ... then, if and as soon as the ... Contract Administrator is of the opinion that the regular progress has been or is likely to be materially affected as stated in the application or that direct loss and/or expense has been or is likely to be incurred due to such deferment, the ... Contract Administrator shall from time to time thereafter ascertain, or instruct the Quantity Surveyor to ascertain, the amount of the loss and/or expense which has been or is being incurred; provided always that the Contractor shall:
.1 make his application as soon as it has become, or should reasonably have become, apparent to him that the regular progress has been or is likely to be affected;
.2 in support of his application submit to the ... Contract Administrator upon request such information as should reasonably enable the ... Contract Administrator to form an opinion; and
.3 upon request submit to the ... Contract Administrator or to the Quantity Surveyor such details of the loss and/or expense as are reasonably necessary for such ascertainment."
[14] Clauses of
this type have been a familiar feature of the JCT family of contracts for many
years. At their heart is the requirement that the contractor makes an
application. It is a condition precedent to a claim: London Borough of
Merton v Stanley Leach (1985) 32 BLR 51, 95-6 per Vinelott J.
He continued:
"The contractor must act reasonably: his application must be framed with sufficient particularity to enable the architect to do what is required to do. He must make his application within a reasonable time: it must not be made so late that, for instance, the architect can no longer form a competent opinion on the matter on which he is required to form an opinion or satisfy himself that the contractor has suffered the loss or expense claimed. But in considering whether the contractor has acted reasonably and with reasonable expedition it must be borne in mind that the architect is not a stranger to the work and may in some cases have a very detailed knowledge of the progress of the work and other contractor's planning. Moreover, it is always open to the architect to call for further information either before or in the course of investigating a claim. It is possible to imagine circumstances where the briefest and most uninformative notification of a claim would suffice: a case, for instance, where the architect was well aware of the contractor's plans and of a delay in progress caused by a requirement that works be opened up for inspection the mirror dispute whether the contractor had suffered direct loss or expense in consequence of the delay had already emerged. In such case the contractor might give a purely formal notice solely in order to ensure that the issue would in due course be determined by an arbitrator when the discretion would be exercised by the arbitrator in the place of the architect." (at pp 97-8)
Akenhead J followed that approach in WW Gear Construction Ltd v McGee Group Ltd (2010) 131 Con LR 63, at p73.
Variations
[15] Clause 5
is a lengthy provision containing ten sub-clauses. I shall narrate the ones
that are relevant for the purposes of this case.
Clause 5.2.1:
"the value of
.1 all Variations required by an Instruction of the ... Contract Administrator or subsequently sanctioned by him in writing ... shall be such amount as it is agreed by the Employer and the Contractor or, where not agreed, shall ... be valued by the quantity surveyor ... in accordance with clauses 5.6 to 5.10 ('the Valuation Rules')."
Clause 5.6 (Measurable Work):
".1 To the extent that a Valuation relates to the execution of additional of substituted work which can properly be valued by measurement ... such work shall be measured and shall be valued in accordance with the following rules:
.1 where the additional of substituted work is of similar character to, is executed under similar conditions as, and does not significantly change the quantity of, work set out in the Contract Bills, the rates and prices for the work so set out shall determine the valuation;
.2 where the additional of substituted work is of similar character to work set out in the Contract Bills, but is not executed under similar conditions thereto and/or significantly changes its quantity, the rates and prices for the work so set out shall be the basis for determining the valuation and the Valuation shall include a fair allowance for such differences in conditions and/or quantity;
.3 In any valuation of work under Clauses 5.6.1 and 5.6.2
measurement shall be in accordance with the same principles as those governing the preparations of the Contract Bills ...
.3 allowance, where appropriate, shall be made for any addition to or reduction of preliminary items of the type referred to in the Standard Method of Measurement, provided that no such allowance shall be made in respect of compliance with an Architect/Contract Administrator's instruction for the expenditure of a Provisional Sum for defined work."
Clause 5.9:
"If as a result of:
.1 compliance with any instruction requiring a variation;
.2 compliance with any instruction as to the expenditure of a Provisional Sum for undefined work;
.3 compliance with any instruction as to the expenditure of a Provisional Sum for defined work, to the extent that the instruction for the work differs from the description given for such work in the Contract Bills; or
.4 the execution of work for which an approximate quantity is included in the Contract Bills, to the extent that the quantity is more or less than the quantity described to that work in the Contract Bills,
there is a substantial change in the conditions under which any other work is executed (including CDP Works), then such work shall be treated as if it had been the subject of an instruction requiring a Variation and shall be valued in accordance with the provisions of this section 5."
[16] It is also important to notice
Clause 5.10.2. It prevents claims for loss and expense from being treated
as variations:
"No allowance shall be made under the Valuation Rules for any effect upon the regular progress of the Works or of any part of them or for any other direct loss and/or expense for which the Contractor would be reimbursed by payment under any other provision in these Conditions."
The Disputed Elements
[17] Mr
Richardson challenged six elements of GHI's counterclaim: (a) the appointment
of an M & E coordinator, (b) the isolation works, (c) additional
preliminaries, (d) M & E extension of time, (e) additional staff, and
(f) overtime worked to mitigate delay. He grouped (c) (d) and (e) together, on
the basis that the same considerations applied to each of them.
(a) M & E Coordinator
[18] In this
connection GHI avers:
"No provision was made in the tender documents for the defender to provide such a coordinator. As a result of the variations instructed on behalf of the pursuers the amount of M & E supervision required in relation to the works as a whole was far greater than provided for in the Bill of Quantities. The variations founded upon by the defender are listed in the schedule at Joint Bundle tab 12. As a result, it was necessary for the defenders to engage an M & E coordinator in respect of both the work contained in the variations and the work forming part of tender documents. The defenders are entitled to payment in respect of the engagement of the M & E coordinator. The valuation of the work required in this regard under and by virtue of the said variations, is valued under cl. 5.6.1.3 in the calculation at Joint Bundle 13 in the sum of £46,125. It is not possible to allocate this required work between the many individual variations listed in the Schedule at Joint bundle Tab 12. Reference is made to clauses 5.1.1.1, 5.6 and 5.9 of the Contract."
[19] The
document at tab 12 is headed "M & E Variations demonstrating the
increase in M & E coordination". It is sixteen pages long and
consists of a table of the variations founded upon. The document at tab 13 is
an invoice for £46,125, which is said to represent the cost of the
M & E Coordinator working half time from 6 April 2008 to 16 February 2009. It shows his basic wage, bonus, car allowance and national insurance. Mr
Mure submitted that there was a clear connection between the two documents.
Taken together, they give GGHB fair notice of what is sought by GHI. To require
GHI to recreate the valuation exercise in respect of each item would not assist
the court and should not be required in terms of the contract provisions.
[20] Mr
Richardson argued that it was illegitimate for GHI to approach the matter in
this way. He suggested that it had only done so because it had failed to make an
appropriate application for loss and expense. But clause 5.10.2 precluded a
claim being dressed up as a variation. He referred to Emden, Building
Contracts, which explains the reason for such clauses as follows:
"To guard against fair valuations compensating a contractor beyond the loss caused by a variation, standard forms commonly incorporate a provision that valuation of variations should not include losses reimbursable under any other contract provisions such as rights to claim for loss and expense ..." [para. 455]
[22] From the
provisions that I have quoted above, it is clear that there is a comprehensive
contractual regime that relates to variations. Clause 5.6 itself is headed "The
Valuation Rules". No doubt its aim is to facilitate the resolution of any
dispute that may arise. That is why it stipulates how claims for variations are
to be valued. A significant degree of precision is involved. In consequence
each party should be readily able to assess a variation claim by testing it
against the contract provisions. In my view, GHI required to identify each
variation and specify what extra work that individual variation necessitated.
It has failed to do so. The documents at tabs 12 and 13 adopt an approach that
does not square with the Contract. GHI acknowledge that to be the case by
stating: "It is not possible to allocate this required work between the many
individual variations ..." In my opinion that concession is fatal. It
demonstrates that GHI has departed from the provisions of clause 5.6. In my
view, GHI is not entitled to rely on clause 5.9, as there is no specification
of the content of the other work undertaken. In my view this head of claim is
irrelevant
[23] In light of
my decision, it is strictly unnecessary for me to consider further the question
of the M & E coordinator. But in case I am wrong on this point, I believe
that I should provide my opinion on another argument mounted by Mr Richardson.
He invited me to exclude from probation a document dated 10 September 2007 and issued by Buro Happold, the M & E engineer ("BS003 Rev T2"). It states that "the
main contractor shall allow for the employment of an engineering services
coordinator to provide a full-time service on site for the duration of the
contract."
[24] GHI founds
upon it as evidence disclosing that it was always envisaged that an
M & E coordinator was required. GHI only became aware of this document
when it was produced in the course of the second adjudication. It accepts that
BS003 Rev T2 does not form part of the Contract.
[25] Mr Richardson
queried how a document that predated the Contract by three months could predict
the need for an M & E coordinator. He said that would be "an
astonishing act of prophecy". Accordingly it should be excluded from probation.
[26] In my view,
however, if there had been an enquiry into the question of whether GHI was
entitled to appoint an M & E coordinator, BS003 Rev T2 would have been
an adminicle of evidence. Its weight (if any) could only be properly assessed
in the context of a proof.
(b) Isolation Works
[27] Despite its
heading, GHI avers that "this part of the claim does not relate to carrying out
isolation works." Instead it concerns "work done in tracing of existing
services within the hospital building which the contract required be isolated
constituted variation to the scope of the Works for which the defenders are
entitled to be paid."
[28] GHI accepts
that the Contract imposed certain obligations upon it in this connection. Prior
to tender, it was required to make a site visit to "ascertain the nature of the
site, access to all local conditions and restrictions likely to affect the
execution of the Works": Contract Bill A-preliminaries page A/4,
Clause A12, item D 250. GHI contends, however, that it had (a)
no design liability for the existing services; (b) no liability for identifying
redundant services which were to be removed; and (c) no obligations in relation
to services which were not underground.
[29] GHI also
states that although its employees did make the appropriate site visit, problems
subsequently developed for two reasons. First, the labelling of existing
switches and cables was non-existent, inadequate, or incorrect. Secondly, the "as
built" drawings and design information did not adequately show how the various
cables related to services. Further, during the course of the works, GHI avers
that it received oral instructions to identify the isolation works, to which GGHB
did not object to the vouching that GHI presented in respect of the sums
claimed during the period of the Contract.
[29] GGHB submits
that the isolation works formed part of the Contract Works. It follows that no
further payment is due to GHI. GGHB points out that GHI was obliged prior to
tender and undertaking the works: (i) to ascertain the nature of the site and
all local conditions and restrictions that were likely to affect the execution
of the works; (ii) to examine all available drawings of the site and site
services; and (iii) to carry out an examination and full (and if appropriate
intrusive) survey of the site, buildings, structure and services affected by
the works. GHI was then required to ensure that any existing utility services
were identified and only redundant services removed. As well as Contract Bill
A, GGHB relies on A510: "Identification: Before starting work, check and mark
positions of names/services. Where positions are not shown on drawings
obtaining relevant details from service authorities, statutory undertakers or
other owners."
[30] In my view,
this is a matter to be properly determined after evidence has been led. GHI's
averments raise mixed questions of fact and law which make it unsuitable to
determine at this stage. It will be necessary to hear evidence to determine the
scope of the work that GHI had to carry out to determine the local conditions and
restrictions likely to affect the execution of the works.
(c)
(d) and (e) Additional Preliminaries, M & E Extension of Time, and
Additional Staff
[31] Under these
three heads, GHI claims payment to reflect time-related preliminaries, supervision,
additional staff and for the extra costs incurred by its M & E
sub-contractor (from whom it has already received a loss and expense claim). GHI
state that these matters arise of out 700 variations instructed by GGHB, which
increased the scope of the works by thirty per cent. GHI also relies upon the
extra period taken for the contract works.
[32] In each of
these three cases, GHI presents the claim as a variation under clause 5.6.3.3,
which provides that "allowances where appropriate shall be made for any addition
to or reduction of preliminary items ..." In the alternative, it makes a claim
for loss and expense. GHI contends that its method of calculation is in
accordance with the contractual provisions and that it was followed without
difficulty during the course of the works. It relies on three documents to
provide adequate specification for the claim.
[33] The first is
a letter dated 1 March 2010 sent by GHI to the project consultants acting on
behalf of GGHB. In the letter GHI sought an extension of 43 weeks and 1 day,
together with "reimbursement of associated loss and expense under 4.24.1 and
4.24.5" (tab 10). The second document is a short table headed "variations which
led to delay and extension of time" (tab 14). The third document comprises
valuation spreadsheets (tab 15). Mr Mure submitted that, taken together, they provide
fair notice to GGHB of how GHI value these elements. GHI challenges the
quantity surveyor's decision to value the 'allowance' element in clause 5.6.3
at nil. Mr Mure reiterated two points: (i) that the matter could only properly
be understood at proof, when the commercial context of both sides' positions
could be fully understood; and (ii) that in the context of such a high number
of variations, it should not be necessary to itemise the work for each one.
[34] Mr
Richardson submitted that these three heads were irrelevant, whether presented
as a claim for variations, or a claim for loss and expense. So far as it was a
claim in relation to variations, he took the same point - GHI had not complied
with the valuation rules. In particular, contrary to clause 5.2 and 5.6, it did
not offer to prove the value of the work which the variations are said to have
necessitated. As he put it, the assessment "appears to be time-driven, rather
than work-driven". In other words, the sums are based on the delays caused by
the work, not on the work itself. So far as the case is based upon loss and
expense, Mr Richardson argued that GHI had failed to notify GGHB of the relevant
matters upon which it now relies.
[35] For the
reasons given above in relation to the M & E Coordinator, I hold that the
claims so far as being ones based on variations are irrelevant. The decision
on the alternative argument centres on five letters that GHI sent to the
Contract Administrator between January and November 2008.
1. On 29 January GHI wrote in the following terms: "we would advise that to try to limit further delay and disruption to the works that we accelerate the works by working to 6:30 pm Monday to Thursday and Sunday all day, for which we would look to recover costs. We will advise separately of the costs to cover same."
2. On 6 April GHI stated that it aimed to recover "our associated extension costs".
3. On 12 May, under reference to changes to the contract, GHI stated "These items should then be dealt with as an out of Phase works package and valued separately."
4. Finally on 11 November GHI sent two letters, one of which stated: "we await your award of a prolongation with costs to the overall Contract as well as the sectional dates."
[36] In my view,
these letters are capable of being read as complying with the terms of clause
4.23. It will be a matter for proof to determine whether in the whole
circumstances GHI gave adequate notice to the contract administrator of the relevant
matters at the appropriate time.
(f) Overtime
[37] This head
of claim is based on the following averment:
"The defender submitted notices under clause 2.27 of the contract seeking extensions of time. The Contract Administrator has failed to respond to these. ... in the absence of response from the Contract Administrator, as he was required to do within 12 weeks of receipt under and in terms of clause 2.28 of the contract, the defender elected to mitigate their (sic) exposure to additional preliminaries by introducing substantial overtime working."
[38] Clause 2.28
requires GHI to "constantly use his best endeavours to prevent delay in
the progress of the works or any section, however caused, and prevent the
completion of the works or section being delayed or further delayed beyond the
relevant completion date". Mr Mure submitted that GHI is entitled to recover
in respect of the costs of non-productive overtime, on the basis that it had acted
responsibly in terms of that provision. It had sought to mitigate any loss.
[39] GGHB argued
that this head of claim is irrelevant, because the Contract states that out of
hours working requires to be "specifically requested": Bill No. B - PC &
Provisional Sums page B/6. The bill of quantities is to similar effect. GHI
must "prior to overtime being worked, submit details of times, types and
locations of work to be done": clause E 530. By failing to aver that it
complied with these provisions, the claim is irrelevant. The alternative claim
is fundamentally lacking in specification as to be irrelevant.
[40] In my
view, there is sufficient specification to allow this head of claim to proceed
so far as it is founded upon clause 2.28. But there is no fair notice of what
is meant by "...the overtime costs are claimed by the defender as part of the
cost of variations." Accordingly, that averment falls to be deleted.
Conclusion
[41] For
the reasons I have given, I shall delete the averments I have identified. Both
counsel agreed that I should put the case out by order to determine further
procedure in the light of this opinion.