EXTRA DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lord EassieLord ClarkeLord Kingarth
|
[2011] CSIH 35CA13/09
OPINION OF THE COURT
delivered by LORD EASSIE
in the cause
by
SCOTTISH WIDOWS SERVICES LTD
Pursuers and Respondents;
against
(1) KERSHAW MECHANICAL SERVICES LTD
First Defenders and Reclaimers;
And
(2) BUILDING DESIGN PARTNERSHIP
Second Defenders and Reclaimers:
_______
|
First Defenders and Reclaimers: Jones, Solicitor-Advocate; Brechin Tindal Oatts
Second Defenders and Reclaimers: Lake, Q.C.; Simpson & Marwick
20th May 2011
[1] In this reclaiming motion the second
defenders and reclaimers - to whom we shall refer simply as the second
defenders - bring under review the interlocutor of the Lord Ordinary of
23 March 2010 in which the Lord Ordinary, rejecting the motion
made by the second defenders that the action so far as directed against them
should be dismissed as irrelevant, allowed to parties a proof before answer of
their respective averments. The first defenders also reclaimed that
interlocutor but when the case called for hearing on the summar roll the
solicitor advocate acting for the first defenders invited the court to refuse
their reclaiming motion, it now being accepted by the first defenders that the
action, so far as directed against them, should proceed to inquiry, with all
pleas reserved and including the averments which they had invited the Lord
Ordinary to exclude from probation. The court accordingly refused the
reclaiming motion which had been enrolled by the first defenders and reclaimers
and their representatives thereafter played no part in the hearing of the
reclaiming motion by the second defenders.
[2] The action arises out of the construction
of a new corporate head office for the Scottish Widows Fund and Life Assurance Society
on ground at Port Hamilton in Edinburgh. It is concerned with defects which the
pursuers and respondents - to whom we shall refer simply as the pursuers - aver
to have existed in the standing seam roof of the building. The action was
debated before the Lord Ordinary along with another action - "the Harmon
action" - relating principally to a different category of defects said to have
been present in the glazing and cladding of the building. The Lord Ordinary
likewise allowed a proof before answer in that action. He issued a single
opinion dealing with both actions - http://www.scotcourts.gov.uk/opinions/2010CSOH42.html.
Reclaiming motions by the defending parties in the Harmon action were also
enrolled but the parties to those reclaiming motions (which included the second
defenders in this action) were agreed that, in light of certain discussions
which had taken place between parties to that action, the summar roll hearing
in the reclaiming motions in that action should be discharged. That joint
motion for discharge was granted.
[3] The contractual arrangements for the
realisation of the construction project are somewhat complicated and are
narrated more fully by the Lord Ordinary in his opinion. In summary, it
appears that on 28 March 1994 Scottish Widows' Property Management Limited granted a lease
of the relevant land to a company named Edinburgh Development Group Limited.
Sometime later, on 15 May 1996, another company, Edinburgh Construction Services Limited -
"ECSL" - engaged Laing Management Services Limited as a management contractor
on their behalf to manage the procurement of the construction project. As
prospective managers, Laing Management Services Limited had earlier, in
March 1996, entered prospectively into a "works package" contract with the
first defenders for the design and construction of the roof works in question.
At a point in 1996 - the precise date is not evident from the copy letter of
appointment, but is, in the event, not material - ECSL appointed the second
defenders to act as architects in the project.
[4] Accordingly, so far as the second defenders
were concerned, their engagement as architects in the project proceeded upon an
engagement of their services by ECSL, who might be described as the developer.
As is to be expected in a major project of this nature, the letter of
appointment of the second defenders as architects is lengthy and detailed. For
the moment, it is sufficient to note that, as architects, the second defenders
agreed to grant a number of undertakings to parties other than their employer,
ECSL, which are described in the letter of appointment as "collateral
warranties" or "collateral agreements".
[5] The requirement to provide such collateral
warranties or agreements is contained in clause 1.21 of the letter of
appointment. Clause 1.21.1 sets out a number of parties to such collateral
agreements, described in the headnote to that sub clause as "Scottish Widows
Collateral Agreements". They include, among others;
"Owner" defined earlier in the letter of appointment as meaning "Scottish Widows Property Management Limited or any successor or assignee thereof as owner of the Site for the Project and the buildings and others constructed as part of the Project";
"Society" defined as meaning "Scottish Widows Fund and Life Assurance Society ..... and any successors thereof";
"Purchaser" which is defined as meaning "Scottish Widows (Port Hamilton) Limited and any successors thereof or assignee thereof as Purchaser of the interest of The Edinburgh Development Group PLC's interest (sic) in the Project";
and
"Fund" which is defined as meaning "any person providing finance in respect of the carrying out and completion of the Project including but not limited to Scottish Widows (Port Hamilton) Limited ...."
[6] In addition to agreeing to provide the
"Scottish Widows Collateral Agreements", the second defenders agreed under
clause 1.21.2 to provide on request by Scottish Widows (defined as being any or
all of Purchaser, Fund, Society or Owner) collateral warranties to inter
alia tenants in a form set out in an annex to the letter of appointment. The
Lord Ordinary narrates in paragraph [24] of his opinion that those "Tenant
Warranties" were intended to cater for those parts of the development which might
be let to entities unconnected with Scottish Widows.
[7] It is accepted that in 1996, the precise date
again not being material, the second defenders granted a collateral warranty or
agreement in favour of the Society. Its full terms are contained in
production 6/10 and are set out at page 765 and following of the
Appendix to the reclaiming print. The relevant provisions are set out, and
also discussed, by the Lord Ordinary in his opinion at paragraph [20] and
subsequent paragraphs.
[8] Put shortly, the principal provisions of
the collateral warranty (in which ECSL are referred to as "the Client" and the
second defenders are referred to as "the Consultant") pertinent to this
reclaiming motion are as follows. The purpose of, or reasons for, the
collateral agreement are set out in the recitals, which are in these terms:
"WHEREAS
A. The Consultant has entered into the Appointment (hereinafter defined) with the Client in terms of which the Consultant has undertaken to carry out the Services (hereinafter defined) in connection with the Project (hereinafter defined).
B. The Society intends to occupy the development constituted by the Project and will have financial responsibilities, liabilities and/or costs in relation to the Site (hereinafter defined) and the Project and occupation and use of the Site and the Project including as a consequence of failures in respect of design and construction by indemnity or otherwise".
The main substantive provision is found in clause 3. In this clause, as in the preamble, the "Appointment" means the professional appointment entered into between ECSL and the second defenders and the "Services" means the services provided by the second defenders to ECSL for the Project pursuant to the Appointment. The clause provides:
"3.1 The Consultant undertakes and warrants to the Society that the Consultant:-
3.1.1 has carried out and shall carry out and complete the Services in conformity with the Appointment;
3.1.2 has observed, performed and complied with and shall observe, perform and comply with all the provisions and obligations on the part of the Consultant to be observed, performed and complied with all as contained in the Appointment.
3.2 The Consultant undertakes and warrants to the Society and it has been employed by the Client as Consultant in respect of the Project, the Services and the Management Contract works and that it has exercised and will continue to exercise the duties of skill, care, expertise and diligence of the type and standard specified in the Appointment for the Project;"
Clause 3.2 then contains a proviso in the following terms:
"PROVIDED ALWAYS that the Consultant's liability to the Society shall be limited to that proportion of such costs, including but not limited to related professional fees, which it would be just and equitable to require the Consultant to pay having regard to the extent of the Consultant's responsibility for the same and the quantity surveyors, civil and structural engineers, building services consulting engineers and works package contractors in respect of the Project shall be deemed to have given contractual undertakings to the Society in respect of the services which at least impose a liability on them for such costs and shall be deemed to have paid to the Society such proportion which it would be just and equitable for them to pay having regard to the extent of their responsibility".
Clause 5 of the collateral warranty in favour of the Society is headed "Continuing Effect". It provides that the provisions of the collateral warranty shall continue to have effect as between the Society and the second defenders even if the employment of the second defenders or the provision of the Services is suspended or terminated. Clause 7 of the warranty provides for assignation. It states that the Society may assign its rights under the warranty in whole or in part, but only as specified in the clause. Assignation may be made to a range of persons, in some cases with a requirement of consent on the second defenders' part. The relevant prospective category of assignee for present purposes is the fourth:
"a company which is a subsidiary of the Society (or a subsidiary of a holding company which is a subsidiary of the Society) without consent of the Consultant provided that the primary purpose of such assignation is not to transfer or assign the Society's rights in respect of this Agreement and then transfer or dispose of the assignee so it is no longer a subsidiary as aforesaid".
It is not disputed that the pursuers are such a subsidiary company of the Society. Finally, clause 8.1.1 of the collateral warranty, headed "Tenant Warranties", provides as follows:
"Within twenty one days of written request from time to time, the Consultant shall execute and deliver to the Society a Tenant Warranty Agreement in terms of the draft Tenant Warranty Agreement set out in the Schedule hereto in the name of the first occupational tenant or tenants of the Project or any part or parts thereof. Ten Tenant Warranties in aggregate with any BPF Warranty Agreements which are provided or are to be provided pursuant to the Appointment will be provided free of charge but payment of £1,500 for each BPF Warranty above ten will be made".
[9] On 21 August 1997 Edinburgh
Development Group Limited, who held the tenant's interest under the lease
granted to them by Scottish Widows Property Management Limited, granted a partial
assignation of their rights under that lease to a company named Scottish Widows
(Port Hamilton) Limited. On 13 May 1998, Edinburgh Development Group Limited
granted a further partial assignation of their right as tenants under the lease
to Scottish Widows (Port Hamilton) Limited. By those two partial assignations Scottish
Widows (Port Hamilton) Limited thus came to hold all of the tenant's interest
in the lease granted to Edinburgh Development Group Limited by Scottish Widows
Property Management Limited (or, at least, all of the parts of the subjects of
that lease of consequence for this litigation).
[10] It is perhaps useful to interpose at this
point in the transactional chronology, mention of the history of the
achievement of the project and the defects with which the action is concerned.
Practical completion of the Project was achieved on 23 March 1998. It is averred (Article
Vof Condescendence) that prior to that date, during the winter of 1997/1998,
the roofs of two blocks of the buildings suffered storm damage. Further damage
occurred in the succeeding winter. It is then averred that in early 2001 the
bullnose assembly on those blocks became detached in high winds; and that on
the night of 27 to 28 January 2002 the bullnose became detached in high
winds at several locations distributed over the four blocks of the buildings.
There then follow averments of the technical nature of the claimed defects of
design and construction, but those details are not material for the purposes of
the debate and the reclaiming motion, it being taken that the pursuers have
averred attribution of the presence of those defects to negligence on the part
of the second defenders in terms sufficient to justify inquiry. The
contentious matter related essentially to whether the present pursuers had
relevantly averred their having suffered - put broadly - a "loss" which
entitles them to recover the costs of rectification of the averred defects.
[11] Reverting to history of the transactions,
the next stage is that on 8 July 1999 Scottish Widows (Port Hamilton)
Limited granted a sub-lease in favour of the Society and immediately
contemporaneously therewith, the Society assigned that sub-tenant's interest to
the pursuers. Some four years later, on 10 July 2003, the Society assigned
to the pursuers the full benefit of its interests and rights under the
collateral undertaking previously granted by the second defenders in favour of
the Society, together with all rights to sue or take action in respect of any
breach of that collateral agreement. The pursuers thus pursue the present
action being assignees of both the Society's interest under the sub-lease and
the Society's rights under the collateral undertaking granted in 1996, the
relevant terms of which are set out in paragraph [8] above.
[12] Clause 9 of the sub-lease by Scottish
Widows (Port Hamilton) Limited in favour of the Society imposed certain
repairing obligations on the Society as the sub-tenant. In his submissions to
the Lord Ordinary, and also to us, counsel for the second defenders submitted,
on a review of the authorities, that the terms of that clause were not apt to
impose on the Society any contractual obligation to carry out the particular
remedial works in question in this litigation. The Lord Ordinary deals with
this matter in paragraph [32] and subsequent paragraphs of his opinion.
He reached a conclusion which essentially upheld the second defenders'
contention on the interpretation of the sub-lease, namely that the sub-lease
did not require the Society, or their assignees - ie the pursuers - as the
sub-tenants, to carry out remedial works of the kind in question. But the Lord
Ordinary went on to hold that his conclusion on that issue did not matter. In
the course of paragraph [34] of his opinion he says:-
"At the start of the [sub]-lease it had become apparent that the building was not wind and watertight because of defects in the glazing and shortly after the start of the lease it became apparent that the roof was defective; that caused the building not to be wind and watertight. Normally a landlord would have an obligation to repair such a defect, but such an obligation was excluded by the opening words of clause 9.1. The result was that the subtenants, the Society, were left with a building in a manifestly unacceptable condition with no right of recourse against their landlords, Port Hamilton, or against the owner of the building. In such a situation the only remedy available to the subtenants was to perform the necessary remedial works themselves. On the pursuers' averments the works were in fact paid for by the pursuers, who were assignees of both the Society and Port Hamilton. Port Hamilton had no obligation to the Society to carry out repairs, but obviously they too would have an interest to ensure that the defects were made good as they were the tenants under the head lease of the building. I am accordingly of opinion that it is immaterial where the obligation to make [good] the defects lies as between Port Hamilton and the Society; the defects had to be made good, for practical reasons, and it is the expense of making them good that gives rise to a claim under each of the [second defenders' and Harmon's] collateral warranties. Ultimately the repairing obligations in the lease and sublease are of negative significance: if there is no obligation to carry out repairs, the subtenant or tenant is compelled to do so simply to have a building fit for occupation. It is the fact that necessary repairs have been carried out at the expense of the grantees of the collateral warranties or their assignee that gives rise to a claim."
The pursuers did not lodge any cross grounds of appeal respecting the Lord Ordinary's conclusions on the interpretation of clause 9 of the sub-lease to the Society and in his submissions to us the Dean of Faculty made clear that the pursuers did not challenge that construction of the sub-lease. The pursuers' case did not depend upon the Society, or the pursuers as the Society's assignees, having a contractual liability under the sub-lease to effect the remedial works; their case proceeded upon the practical need, as occupiers or subtenants, to carry out the works and the terms of the collateral agreement or warranty granted by the second defenders in favour of the Society, the benefit of which had been fully assigned to the pursuers.
[14] In these circumstances we do not consider it
necessary to visit the terms of clause 9 of the sub-lease, or the
authorities relevant to the interpretation of that clause, both of which are
fully dealt with by the Lord Ordinary in his opinion.
[15] That said, much of the argument deployed by
counsel for the second defenders had, at its base, the view that the pursuers'
case depended upon the pursuers and their cedents having had a contractual
responsibility in terms of the sub-lease to rectify the averred defects. Thus
the principal argument for the second defenders began with the proposition that
any breach of duty on the part of the second defenders preceded the date of
practical completion on 23 March 1998. At that point the only party
who could claim to have suffered loss by reason of such a breach was the owner
of the building. Reference was made in particular to GUS Property
Management v Littlewoods Mail Order 1982 SC (HL) 157 and McLaren
Murdoch & Hamilton v The Abercrombie Motor Group 2003 SCLR 323.
Accordingly, as at the date of practical completion, the Society had no
possible claim because they had not, and could not have, suffered any possible
loss. The Society was not the owner, or the tenant of the building at the time
of practical completion. So what, asked counsel, had changed? To that
rhetorical question counsel offered the answer that the Society briefly got a
tenant's interest in a sub-lease with a limited liability for repairs, which the
Society instantly assigned and so had suffered no loss. Assuming, contrary to
what the Lord Ordinary had found on the construction of the relevant provisions
of the sub-lease, the pursuers or their cedents were contractually required to
expend money on the relevant repairs by virtue of that sub-lease, they incurred
that contractual requirement by a voluntary decision to enter upon that
contractual, locational relationship. They themselves had suffered no loss;
the loss represented by the averred defects in the building resided elsewhere,
namely with the building owner.
[16] It was recognised, said counsel, that the
building owner, who had suffered the economic loss represented by the defects
in the building, might assign its claim against the second defenders for its
loss in respect of those defects. But any claims assigned to the pursuers were
assigned by the Society as sub-tenants of Scottish Widows (Port Hamilton)
Limited or as grantees under the collateral warranty or agreement. The Society
was thus the wrong cedent; for they were not the building owner. It was,
counsel further submitted, for that reason that the pursuers now sought to side-step
that difficulty by basing their claim on either a contractual, or even a merely
practical, requirement to carry out the repairs.
[17] The focus placed by counsel for the second
defenders, particularly before the Lord Ordinary, on the pursuers' case being
centred on their having incurred a contractual responsibility to carry out the
necessary repairs in question is perhaps understandable in light of the terms
of the pursuers' third plea in law which reads:
"3. Separatim. Esto the Society has not suffered a loss, the pursuers themselves having incurred a liability as sub-tenants in respect of the remedial works, having suffered loss and damage as a result of the first and second defenders' breach of warranty to the Society, and being entitled as assignees to the benefit of the warranty granted by the first and second defenders to the Society, are entitled to reparation jointly and severally from the defenders therefor".
In paragraph [39] of his opinion, having rejected (in paragraph [34]) the proposition that the terms of the sub-lease required the pursuers to carry out the repairs but having opined thereafter that the absence of such contractual liability was not material, the Lord Ordinary says:
"In relation to the
criticism of the formulation of the pursuers' plea in law relating to the
alternative case, I agree with counsel for [the second defenders] that the
measure of loss that could be recovered is that resulting from any breach of
contract on the part of [the second defenders], and is not to be measured by
the pursuers' liabilities under the sublease in their favour. On this matter,
I refer to paragraph [34] above; the sublease explains why the pursuers
carried out the works, to enable them to occupy premises that were wind and
watertight, but the existence of a liability under the sublease to carry out
repairs or to make good defects is not in my opinion essential to recovery.
The right to recovery rather proceeds on the collateral warranty, which confers
a right to sue for the physical loss caused by defects in the building and any
recoverable economic consequences that the physical loss may have. On this
analysis the pursuers' [third]
[1]
plea in law is not particularly well framed, in that it refers to the pursuers'
incurring a liability as subtenants. Nevertheless, it seems to me that the
intention is clear enough: the pursuers are subtenants of the building; as
subtenants they required to make good the defects in the building in order to
have premises that were wind and watertight; and in doing so they incurred
liabilities. I think that the plea in law can be construed in that sense, and
accordingly I do not find this part of the pursuers' case to be irrelevant."
[18] We agree with the Lord Ordinary that the
terms of the plea in law are not happily drafted; but we also consider that
those terms can be read in the way in which the Lord Ordinary decided that they
could be read. Moreover, the note of argument lodged in the course of the
proceedings in this reclaiming motion by the pursuers proceeds
[2] on the basis of acceptance of
the Lord Ordinary's view that the terms of the repairing obligations in the
sub-lease were only of "negative" significance. Accordingly, we consider that,
bearing in mind that this is an action on the commercial roll, there is no real
prejudice to the second defenders arising from the argument pressed by the Dean
of Faculty to the effect that the claim under the collateral undertaking in
question could, and did, proceed upon a practical necessity on the occupier to
remedy the defects attributed ex hypothesi of the pleadings to failings
on the part of the second defenders. In his response to the submissions of the
Dean of Faculty, counsel for the second defenders submitted that there were no
express averments that either the Society, or the pursuers, were ever in
occupation of the building at the time at which the decision or decisions to
instruct and incur the cost of the repairs was or were taken. Adopting a very
narrow construction of the pursuers' pleadings, that may arguably be so, but in
the whole circumstances and given the existence, or the purpose of the project
and the transactional history, it is not difficult to infer from the terms of
the averred circumstances as a whole that the Society or the pursuers had occupancy.
As the Dean of Faculty stressed, the pursuers are their assignees in respect of
both the sub-lease and the benefit of the collateral warranty. In these
circumstances, particularly in a commercial action, we consider that the
absence of any express averment of occupancy is not a good ground for reversing
the Lord Ordinary's decision to allow a proof before answer.
[19] We therefore turn to what we perceive as
having become the central issue in this reclaiming motion, namely the soundness
of the submission advanced on behalf of the pursuers to the effect that,
irrespective of what might obtain in terms of delictual liability, the
collateral undertaking granted to the Society, as occupier, gave a right to
recover, in terms of that contractual undertaking, the cost of repairing
defects (ex hypothesi attributable to the fault of the second defenders)
by reason of the occupier's practical need to have a wind and water tight
building.
[20] In approaching that issue, we begin by
noting that the terms of the tenant's collateral agreement which the second
defenders undertook to provide, if requested, pursuant to clause 1.21.2 of
the letter of appointment, envisage that the second defenders might become
contractually bound to the occupational tenant, who is the grantee of such a
collateral warranty to meet the costs of repairing defects, albeit that the tenant
to whom the collateral undertaking is granted is not the building owner and has
not suffered the primary loss. Clause 1 of the pro-forma tenant's
warranty
[3]
is in these terms:
"1. The Firm [the second defenders] warrants that it has exercised and will continue to exercise reasonable skill, care and diligence in the performance of its services to the Client under the Appointment. In the event of any breach of this Warranty:
(a). subject to paragraphs (b) and (c) of this clause, the Firm shall be liable for the reasonable costs of repair renewal and/or reinstatement of any part or parts of the Development and for the reasonable costs of all professional services associated with such repair, renewal and/or reinstatement to the extent that the Tenant is liable either directly or by way of financial contribution for the same but the Firm shall not be liable for other losses incurred by the Tenant;
....."
Paragraph (b) is a net contribution clause and paragraph (c) essentially enables the grantor of the warranty to plead any defence which it would have had against the client were the client to have brought the claim. In our view, the terms of the pro-forma tenant's warranty are thus inconsistent with the notion, which appeared to underlie the principal submission for the second defenders, to the effect that any liability of the second defenders to pay for the rectification of the defects in the building was owed only to the building owner (or its assignees of a claim qua building owner) and could not be transferred elsewhere by a collateral warranty or undertaking.
[21] With that observation we turn to the
collateral undertaking granted to the Society upon which the pursuers sue as
assignees of the benefit of that warranty. Subject to the net contribution
clause to be found in the proviso to clause 3.2, the liability of the
second defenders ("Consultant") for breach of the warranty to the Society is
not given, in that clause, any specific parameters. Consistent with the
essential premise underlying his submissions, namely that liability in damages
for repairing the defects in the buildings was owed only to the building owner,
counsel for the second defenders contended that the proper scope for recovery
under this warranty must therefore be restricted to liabilities incurred by the
Society, as occupier, to other third parties - such as employees or visitors
who might suffer injury consequent upon a failing in the building; or in
respect of claims for damage to the Society's moveable property within the building
caused by the defect in issue; but its scope did not extend to the economic
loss represented by any practical need faced by the occupier to rectify the
actual deficiencies in the quality of the building itself.
[22] Apart from the difficulty which that
argument faces in that it appears to proceed upon the notion of some legal
obstacle to an architect's agreeing contractually to meet the repair costs
incurred by a party other than the building owner, we consider that the terms
of the preamble to the Society collateral warranty are also hostile to the second
defenders' contention. For convenience, we reiterate recital B:-
"The Society intends to occupy the development constituted by the Project and will have financial responsibilities, liabilities and/or costs in relation to the Site (hereinafter defined) and the Project and occupation and use of the Site and the Project including as a consequence of failures in respect of design and construction by indemnity or otherwise."
Counsel for the second defenders understandably did not suggest that in a contractual document such as this there was any difficulty in having regard to the recitals in the preamble as having force in its overall interpretation and in our view there is nothing in the terms of the recital which would support the limited scope of the undertaking which counsel for the second defenders contended.
[23] As was stressed by the Dean of Faculty, the
collateral agreement or undertaking granted to the Society envisaged the
Society's having the status of a simple occupier and as such occupier incurring
financial costs in the event of breach of the warranty granted by the second
defenders. There is, in our view, nothing inherently impossible, or even
difficult, in the notion of an architect, or other member of the professional
team - or indeed the contractor or sub-contractor - granting indemnity to a
named prospective occupier, or that occupier's assignees, for the costs of
rectifying defects, impinging on the occupiers enjoyment, for which defects the
granter is responsible by reason of breach of professional or other contractual
duty. As the Lord Ordinary puts it at paragraph [56] of his opinion, while the
primary physical loss may be sustained by the owner or tenant of the building
at the time when the defective work was performed, that physical loss has
economic consequences, and any party who suffers those economic consequences,
such as a subsequent owner or tenant, may sue for that loss provided that a
contractual relationship exists between the party responsible for the defective
condition of the building and the person who suffers the economic
consequences. In the present case, such a contractual relationship is not
disputed and it is plainly averred that the pursuers, whether directly or as assignees,
have incurred the costs for which recovery is sought. In these circumstances
we consider that their case cannot be dismissed at this stage on the basis that
it is irrelevant.
[24] In consonance with the reasoning of the Lord
Ordinary we also consider that the proper course was the allowance of a proof
before answer. We therefore refuse the reclaiming motion and remit to the Lord
Ordinary to proceed as accords.