OUTER HOUSE, COURT OF SESSION
[2010] CSOH 76
|
|
CA115/00
|
OPINION OF LORD MENZIES
in the cause
TOR CORPORATE A.S
Pursuer;
Against
SINOPEC GROUP STAR PETROLEUM COMPANY LIMITED
Defender;
________________
|
Pursuer: Johnston QC et M Ross; Tods Murray LLP
Defender: Dean of Faculty QC et McBrearty; Simpson & Marwick, WS
22 June 2010
Introduction
[1] The defender is the owner of the semi submersible drilling rig
Kan Tan IV. On 14 June 1999 the defender entered into a Management Agreement
with the pursuer whereby the pursuer undertook to act as the exclusive manager
of the rig and the defender undertook to pay to the pursuer certain sums of
money. On 30 March 2000 the defender repudiated the agreement, and
on 24 May 2000 the pursuer accepted that repudiation, and
on or about the same day the pursuer raised these proceedings, in which it
seeks payment of a sum claimed to be due in terms of the contract, and various
sums by way of damages for breach of contract. In due course these proceedings
were sisted for arbitration, in terms of Clause 9(a) of the Management
Agreement. After a proof lasting some ten weeks the panel of arbiters found
that the defender repudiated and breached its contract with the pursuer, and
that the contract came to an end when the repudiation was accepted no later
than 24 May 2000. In terms of Clause 9(d) of the
Management Agreement that decision was stated to be final and binding upon the
parties.
[2] The matter came before me for debate on the defender's first
plea-in-law, in standard terms directed to the relevancy and specification of
the pursuer's pleadings. In the Note of Arguments lodged for the defender, it
appeared that the defender sought to have certain of the pursuer's averments
excluded from probation. However, in the course of the debate it was agreed on
behalf of both parties that the case should be put out By Order for discussion
shortly after the issuing of this opinion. Each party helpfully lodged a Note
of Arguments (No 35 and 37 of process) which I do not repeat here at length,
but which (taken together with the submissions made at the bar) I have taken
into account when reaching my decision.
The relevant terms of the Management Agreement
[3] Clause 1 of the Management Agreement provided inter alia
as follows:
"The term of this Agreement shall continue and shall not be terminated except as follows...
(D) If the Manager or the Owner commits a material breach of this Agreement and has not so remedied such breach within three months of receipt of written notice by the Owner or the Manager, as the case may be, requiring the breaching party to remedy the same;
(E) If the Owner is not satisfied with his co-operation with the Manager and/or the manner in which the Manager is executing his duties and obligations as stipulated by this Agreement and has advised the Manager of his dissatisfaction in writing and the Manager has not taken the necessary steps to rectify the situation within one month, then the Owner may terminate this Agreement by providing three months written notice...
For the avoidance of doubt the Agreement cannot be terminated solely with the intent to award the management of the Vessel to another contractor."
Clause 2 provided inter alia:
"The Owner hereby appoints, and the Manager hereby accepts such appointment, as exclusive Manager of the Vessel for worldwide operations under the terms and conditions set forth in this Agreement. The Manager shall on behalf of the Owner and at the Owner's risk and expense manage, maintain and repair the Vessel in accordance with sound drilling rig management and general operation practice, efficiently and economically, to the best of its professional ability in regard to performance, safety, shipshape appearance, and will arrange technical supervision, classification etc in order to keep the Vessel in a seaworthy and fully operational condition and with valid certificates. The Manager shall keep the Owner fully advised of any significant issues concerning the Vessel and its operation..."
Clause 3.4(b) provided as follows:
"The Manager shall provide for technical supervision, repairs, classification, customary maintenance, upgrade and conversion and in all other respects use its best endeavour so that, at all times, the Vessel is kept duly operational and seaworthy, and maintains its certificates, regulatory compliance as applicable and permissions for maritime and drilling operations."
Submissions for the defender
[4] The Dean of Faculty began by drawing my attention to what he
described as the most material findings in the arbitration, which he emphasised
were binding on the parties and could not be reopened. These were as follows:-
(1) The defender's sole purpose in and after November 1999 was to change the manager of the rig and to remove the pursuer from that role, albeit that this was contrary to the provisions of clause 1 of the Management Agreement, and that the mechanism which it selected was not effective (finding 41 in paragraph 2.1.1).
(2) The defender did send a letter purporting to be a notice of determination under clause 1(E) of the Management Agreement, but this was not valid as it was not preceded by a valid notice of dissatisfaction (findings 44, 48 and 49 of paragraph 2.1.1).
(3) The defender's actions amounted to a repudiation of the contract. This was an anticipatory breach in which the defender announced its intention not to perform its obligations.
(4) The pursuer accepted that repudiation on 24 May 2000 (finding (768)).
(5) The rig was never 'fully operational and ready for contract assignment' during the pursuer's period of management. Indeed, the pursuer was in breach of many of its contractual obligations (findings 15 to 21 of paragraph 3.3.1). The defender therefore sought to terminate the agreement on the wrong ground not knowing that it had good grounds to do so because of the pursuer's material breach of the agreement. The defender could not have known that the pursuer was in material breach before 30 October 2000, because the pursuer was in breach of its obligation to '... keep the owner fully advised of any significant issues concerning the Vessels and its operation.' (findings 19 - 22 of paragraph 3.3.1).
[5] It was submitted that the pursuer had failed to establish on
the balance of probabilities that they could have avoided termination of the
contract by reason of their material breaches by curing those breaches within
three months. Once it was established that the pursuer was in material breach,
and that the defender had evinced a desire to remove the pursuer as manager of
the rig, the onus was on the pursuer to establish that it could have avoided
the consequence of its own material breach by remedying it within three
months. This was a matter which was explored in evidence in the course of the
arbitration; the pursuer maintained that they could have remedied within three
months, and the defender maintained that they could not have done so. The
arbiters' determination of this issue was to be found in finding 23 of
paragraph 3.3.1, namely:
"The Tribunal makes no finding as to whether or not Tor could have cured its breach within three months in the absence of sufficient evidence on the point".
The defender's position was that this was a finding, and it could not competently be revisited. The pursuer offered to prove before the tribunal that it could have remedied any material breaches within three months. It failed to do so, and it could not competently reopen this issue in the present proceedings.
[6] The pursuer's averment at the last sentence of Article 5 of
condescendence, to the effect that the pursuer does not accept the arbiters'
findings as to material breach of Clauses 2 and 3.4, was clearly irrelevant,
because the arbiters' findings were final and binding on the parties. The
arbiters made clear findings that the pursuer was in material breach (1) of its
repairing and maintenance obligation and (2) of its reporting obligation. Were
it not for the latter of these breaches, the defender would have known about
the former breach and would have founded on it by giving written notice in
terms of Clause 1(D). Whether the pursuer could have prevented termination by
remedying the repair and maintenance breaches within three months was an issue
of fact for the arbiters. By their finding 23 (quoted above) the arbiters
found that there was an absence of sufficient evidence on this point. The
pursuer had led evidence on this point before the arbiters, but failed to prove
that it could have remedied its own material breach within three months. The
onus of proving this rested with the pursuer. The arbiters found that the
pursuer was in material breach of its repair and maintenance obligation; in
order to avoid the result of that breach, namely termination under Clause 1(D),
the onus rested on the pursuer to prove the positive case that it could remedy
this breach within three months. It was properly open to the arbiters to reach
the conclusion that they could not be satisfied one way or the other on this
point - Rhesa Shipping v Edmunds [1985] 1 WLR 948 (particularly
at 951 A/F and 955 D). The arbiters in this case had taken the third
alternative identified by Lord Brandon of Oakbrook, namely that the pursuer had
failed to discharge the burden of proof which lay on it. Once the pursuer was
found to be in material breach, the onus was on it to show, on the balance of
probabilities, that this breach could be remedied within three months.
Moreover, the question of whether the pursuer was or was not able to remedy
within three months was peculiarly a matter within its own knowledge - the pursuer
was the manager of the rig at the time and was responsible for its maintenance
and repair. The burden of proving this positive must rest with the pursuer; to
place the burden of proof on the defender would be to give the defender a
formidable obstacle in proving a negative, in circumstances in which it was not
the manager of the rig and was not responsible for its repair and maintenance.
[7] It was submitted that the pursuer's averments beginning with
the words "explained and averred" in line 14 of page 14 of the Adjusted Record
(41 of process) and ending with the word "achieved" in line 3 of page 15 were
irrelevant, as these issues were the subject of evidence in the arbitration
(see paragraph 3.3.2.5.3, (319 et seq)). It had been never been argued by the
pursuer that the arbiters had exceeded their jurisdiction in considering this
issue. No such argument had been advanced in the arbitration itself, nor in
the judicial review proceedings which followed. The pursuer is now trying to
revisit an issue which was before the arbiters.
[8] On the question of where the burden of proof lies, I was
referred to Dickson The Law of Evidence (third edition) paragraph 26; Walker
and Walker, The Law of Evidence in Scotland (third edition) paragraphs
2.2.2 - 2.2.4; and Joseph Constantine Steamship Line Ltd v Imperial Smelting
Corporation Limited [1942] AC 154 (particularly at 174/5, 177 and
194). It was submitted that the defender in the present case did not fall
within any of the exceptions to the general rule that the burden of proof rests
on the party who alleges the affirmative. Moreover, where a chain of causation
has begun, the burden of showing that it has been broken lies on the party
alleging this - SS "Baron Vernon" v SS "Metagama"
1928 SC (HL) 21. In the present case there is a material breach of contract by
the pursuer which has as its natural consequence the right of the defender to
terminate the contract. In order to breach this chain of causation, the
pursuer must discharge the burden of proving that the breach could be remedied
within the specified timetable. The Dean of Faculty accepted that no clear and
concise rule could be stated as to where the onus of proof lies in every case,
but in the present case it was relevant to consider whether, if the defender
had given notice to the pursuer of the pursuer's material breach, and there was
no evidence at all that anything had happened thereafter, could the contract be
properly terminated after three months? The general law provides that a
material breach of contract by one party entitles the other party to determine
the contract. It is open to parties to contract for an exception to that
remedy, but the party seeking to rely on that exception must plead it and prove
it. The Minute of Agreement in the present case provided for one exception,
namely remediation within three months, and the burden of proving that this
would have been achieved rests with the pursuer. Another contract might
contain fifty exceptions; it would be quite unreasonable to place the burden of
negativing each of these on the party relying on the general rule.
[9] It follows from the above that the pursuer had the onus of
proving, in the circumstances found by the arbiters, that it would have
continued to enjoy the benefit of the contract notwithstanding its material
breach of it. The defender's purpose was to remove the pursuer as manager; the
pursuer was in material breach, which would have enabled the defender to
achieve this purpose; the defender did not rely on the material breach because
it was unaware that it had occurred; this lack of knowledge arose because of a
separate material breach by the pursuer, namely breach of the obligation to
report. In these circumstances the pursuer cannot rely on the defender's failure
to give a notice of intention to terminate under Clause 1(D), because that
failure arose as a result of the pursuer's own breach. It is a principle of
law that no one can take advantage of the existence of a state of things which
he himself produced; a man shall not be permitted to take advantage of his own
wrong - New Zealand Shipping Company Limited v Société des Ateliers
et Chantiers de France [1919]AC 1; McBryde on Contract (second
edition) 20-21.
[10] The pursuer has not chosen to plead its case on the basis of a
lost chance. The sum sought in the second conclusion relates to a bonus
payment which would only have arisen in September 2002, and the sum sought in
the fourth conclusion relates to sums allegedly payable in terms of the
contract between September 2002 and December 2011. The averments in support of
these conclusions are to be found in Article 5 of Condescendence, from which it
is clear that the pursuer is not relying on the loss of a prospect or a chance
- rather the pursuer offers to prove that the vessel would have remained under
the pursuer's management, drilling contracts for the rig would have been
entered into, and that the pursuer would have earned the sum fourth concluded
for in the period between September 2002 and December 2011. These averments
cannot be relevant standing the pursuer's inability to prove to the arbiters
that it could have remedied its own material breach and thereby avoided
termination. In support of this proposition I was referred to the Mihalis
Angelos [1971] 1 QB 164 (particularly the opinions of Lord Denning MR at
196/7 and Edmund Davies LJ at 201/3) and Golden Strait Corporation
v Nippon Yusen Kubishika Kaisha ("the Golden Victory")
[2007] UKHL 12, [2007] 2 AC 353. Applying the principles for
calculation of damages consequent upon a repudiatory breach stated in these
cases to the circumstances of the present case, it is clear that the defender
would have availed itself of any opportunity to terminate the contract, and if
it had known that the pursuer was in material breach it would have relied on
that material breach. It was therefore clearly predictable at the date of
termination that there would be a supervening event cutting off damages. The
benefit which the pursuer lost as a result of the termination of the contract
was only the benefit under a contract of which they were in material breach.
There is no foundation for any claim for damages for the period between
September 2002 and December 2011, because it was clearly predictable at the
date of termination that the defender would have terminated the contract in
reliance on the pursuer's material breach. For the pursuer to make relevant
averments of loss attributable to the period from 1 September 2002 to 31
December 2011 against the
background of the arbiters' findings, it must offer to prove that it would have
been manager of the rig during that period. It is not enough for it to make
the bald averment in the third sentence of Article 5 of Condescendence that "but
for the defender's said breach of contract the vessel would have remained under
the pursuer's management"; this is inconsistent with the arbiters' findings. Nothing
would be gained by granting a proof before answer, because at any such proof
the court would be left with the arbiters' findings of fact. The Dean of
Faculty moved me to sustain the defender's first plea-in-law in the principal
action and to refuse to admit the pursuer's second and fourth conclusions to
probation, but suggested that the matter should be put out By Order following a
determination of the issues raised.
Submissions for the pursuer
[11] Senior counsel for the pursuer submitted that the onus of proof
rested with the defender. It is the defender which seeks to rely on Clause
1(D), and to do so it must bring itself within that clause. As it is the
defender which puts forward the proposition, it is for the defender to
establish it. The general principle that the person who asserts the
affirmative must prove it is not in dispute, but the question arises as to what
the affirmative is in the present case. The authorities referred to for the
defender dealt with quite different issues. The Joseph Constantine case
concerned frustration of a contract consequent on an explosion on a ship, and the
observations of the court in that case fell to be read in that context. In the
present circumstances, Clause 1 of the Minute of Agreement sets out a number of
specified grounds on which the contract might be terminated; if a party wishes
to rely on one of these grounds, it is for that party to prove that the grounds
exist. As stated in paragraph 12 of the Note of Argument for the pursuer, three
facts need to be established if the argument for the defender is to succeed -
(1) there must have been a material breach by the pursuer, (2) if the
defender had known about the condition of the vessel it would have served a
valid notice, and (3) if such a notice had been served, the pursuer would not
have been able to remedy the defect timeously. Each of these elements arises from
Clause 1(D), and if the defender seeks to limit damages consequent on its
repudiation of the contract it must establish each of these elements. To take
the example of a contract with fifty exceptions to a general rule, the defender
in such a case would require to negate each exception. The notice specifying a
breach of contract in terms of Clause 1(D) must specify the particular
elements of the breach which required to be remedied. This sets the parameters
for a later assessment as to whether a remedy has been effected within three
months or not. In the arbitration proceedings, both parties led a lot of evidence
about non-operational or defective equipment, so placing the onus on the
defender is not an intolerable burden; all that is required is for the defender
to establish that there was some material or significant aspect of the state of
the rig which could not have been remedied within the three month period. Clause 1(D)
is a single express term of the contract, and it would be extraordinary if the
burden of proving any element of it rested on anyone other than the party
relying on it to terminate the contract.
[12] Turning to the arbiters' finding 23, the defender's position is
that the pursuer had the chance before the arbiters to prove that it could have
remedied the breach within three months, but it failed to prove this, and the
defender relies on finding 23
in this regard and maintains
that the onus was on the pursuer to prove this in the arbitration or not at
all. This argument should be rejected, (a) because the onus does not, and did
not, rest on the pursuer, and (b) because finding 23 is not a finding that the
pursuer has failed to prove anything. It was necessary to bear in mind the
context; before the arbiters the defender was not seeking an order that it was entitled
to terminate under Clause 1(D), but was rather seeking a finding that the
pursuer was in material breach. This is clear from paragraph (230) on page 60
of the arbiters' Note of Reasons. This is why order No. 20 was framed as it
was - the arbiters found in respect of the counterclaim that the claimant was
in material breach of contract. The defender made various claims before the
arbiters about failures on the part of the pursuer; failures in maintenance
were found to be established in part, failures in marketing were rejected, and failures
in regular accounting were rejected or found not to be material. However, the
issue of Clause 1(D) was not canvassed before the arbiters. It was clear from
findings 18 and 20 at page 62 of the Note of Reasons that the arbiters
understood that there was a difference between establishing material breach on
the part of the pursuer and being entitled to terminate in terms of
Clause 1(D); however, this difference was not material for the arbiters'
purposes, because they were only being asked to decide whether there had been a
material breach. The question whether the defender could invoke Clause 1(D)
was not referred to the arbiters.
[13] Senior counsel accepted that the arbiters referred to Clause
1(D) (and he accepted that the reference to Clause 2(d) in part 1 of finding
(768) was an error and should be read as referring to Clause 1(D)), and he did
not challenge their entitlement to make such reference; however, finding 23 at
page 62 was not made in the context of a consideration as to whether Clause
1(D) was made out or not, because they had no need to carry out such an exercise.
References by the arbiters to Clause 1(D) are in the context of their
considering whether the pursuer was in material breach. Senior counsel
submitted that there was no determination by the arbiters as to whether the
pursuer could have remedied any material breach within three months, and there
was no need for such a determination because this was not an issue was
addressed to them for a decision. Claim 3 in the counterclaim was just that the pursuer was in
material breach; it did not extend to the argument that the pursuer could not
have remedied that breach within three months.
[14] Senior counsel drew attention to what he regarded as an illogicality
in the defender's Note of Argument; in paragraph 3.3 it is stated that it is
inevitable that the defender would have served a notice under Clause 1(D)
by 14 March 2000, yet in paragraph 3.7 they assert that if 14 March 2000 is not
to be regarded as the correct date, such a notice would have been served by 30
October 2000. Whichever date is chosen, the material which the defender has
produced is inadequate to show that the contract would have been terminated
three months after either date.
[15] Neither the Mihalis Angelos nor the Golden Victory
was directly in point, and each was concerned with very different circumstances
from the present case. In the former, it was an established fact that the
vessel was not going to be ready to load; there was therefore an element of
inevitability or "predestination" which could not be said to apply in the
present case. There is no finding by the arbiters in the present case of an
event which would bring the matter to an end. There are accordingly two areas
of dispute between the parties: (1) whether the onus of proof rested with
the pursuer or the defender, and (2) even with a finding that the defender
wished to remove the pursuer as manager of the rig and a finding that the pursuer
was in material breach, the question remained whether Clause 1(D) could be
invoked to terminate the contract. The question is whether on the facts found
by the arbiters, the contingency that Clause 1(D) could be invoked and the
contract terminated by the defender is sufficiently realistic that it has to be
taken into account when valuing the pursuer's contractual rights. In the context
of the discussion in the Golden Victory (and in particular the spectrum
between inevitability and mere possibility considered by Lord Walker of Gestingthorpe
at paragraph 46 of that case) senior counsel submitted that such a contingency
in the present case fell to be categorised as a mere possibility carrying
little or no weight in commercial terms. There is no finding as to whether (or
when) the defender could have terminated the contract under Clause 1(D),
and there is not the same inevitability about such a contingency as there is
about war or the failure of a ship to arrive, because of the mechanism of the
three month period for remedying a breach.
[16] The New Zealand Shipping case was so far removed from present
circumstances as to be irrelevant. The pursuer was not seeking to terminate
the contract by its own wrong, nor was it trying to obtain an advantage by its
own wrong, but was merely responding to the defender's new case in relation to
Clause 1(D). The pursuer's argument amounted to no more than that if the defender
wished to establish the date of termination under Clause 1(D) they must
bring themselves within it.
[17] In conclusion, senior counsel observed that these proceedings
are about quantifying damages for a breach of contract. The position of the
defender is that the contract would have been definitely terminated under
Clause 1(D) by one date or another. That assertion is not supported by
the evidence, so damages ought to be assessed without regard to any
restriction, and should not be cut off at May 2000. Senior counsel accepted
that it was appropriate for the court to issue a decision on the question of principle
and thereafter put the case out By Order to enable amendment to be made if
required.
Discussion
[18] There are several issues raised in the Notes of Argument and
submissions for the parties. I propose to consider first where the burden of
proof lies, second what the effect of finding 23 in paragraph (231) of the arbiters' Note of Reasons is,
and finally certain factors relating to the assessment of damages.
[19] Both senior counsel accepted that there is no easily formulated
rule as to the burden of proof which may be said to apply to all cases. There
are different principles which may apply, more or less forcefully, to different
circumstances. As is observed in Dickson on Evidence (at paragraph 26) "the
leading rule is that the burden of proof lies upon the party who alleges the
affirmative. Ei qui affirmat, non ei qui negat, incumbit probatio. This
was not disputed by senior counsel for the pursuer, but, as he observed, the
difficulty frequently lies in deciding which party is truly alleging the
affirmative. He submitted that if the defender is to rely on Clause 1(D),
it must bring itself within it. While recognising that the arbiters made a
finding that the pursuer was in breach of its repair and maintenance
obligation, no finding was made that had the defender known about the condition
of the vessel it would have served a valid notice, nor that the pursuer would
not have been able to remedy the defect timeously.
[20] Although attractive, I am not persuaded that this argument is
sound. The remedy which the law generally provides for material breach of
contract is to entitle the other party to terminate the contract. This
entitlement may be modified or restricted by agreement. In the present case
there is the restrictive mechanism provided by Clause 1(D), which requires
written notice and a three month period within which remedial steps may be
taken. The burden of proving that the contractual exception applies and that
it would have had the effect of averting the normal remedy of entitlement to
terminate must rest on the party asserting this - i.e. the pursuer. The arbiters
have found that the pursuer was in material breach of its repair and
maintenance obligation, and that the defender had as its underlying purpose at
the material time the removal of the pursuer from the role of manager of the rig.
Against this established factual background I consider that it is incumbent on
the pursuer to prove that it could have taken the necessary steps to remedy the
breach within the required timescale and so avoid termination. Such a
conclusion is consistent with the principles enunciated by the House of Lords in
the Joseph Constantine Steamship Line case, and is also
consistent with the "breach of chain of causation" reasoning adopted by Viscount
Haldane in the "Baron Vernon".
[21] I am fortified in this conclusion by the consideration that the
facts relating to this issue are peculiarly within the pursuer's knowledge.
The pursuer was the manager of the rig at the material time, and was charged
with its repair and maintenance. It was in a much better position to lead
evidence as to what was necessary to place the rig in a proper seaworthy
condition, and within what timescale this could have been achieved. By
contrast, the defender was unaware of the actual condition of the rig. It had
not inspected it, and it had been provided with reports from the pursuer which
gave a misleading picture of its condition.
[22] Senior counsel for the pursuer drew my attention to paragraph (230)
of the Note of Reasons, where the order sought by the defender was "Tor was in
material breach on contract", and suggested that it was important to note that
the defender was not seeking an order that it was entitled to terminate under
Clause 1(D), which was not an issue canvassed before the arbiters.
However, it is clear that the arbiters did consider whether a remedy under
Clause 1(D) was open to the defender, what the requisites were for such a
remedy, and whether there was sufficient evidence as to whether or not the
pursuer could have cured its breach within three months. This is apparent
from, for example, the discussion at paragraph (326), the first finding in
paragraph (768), and the recital of the evidence of some of the witnesses.
[23] In light of all the circumstances of this case, I am satisfied
that the burden of proving that the pursuer could have remedied its breach of
the obligation to repair and maintain within a three month period rested with
the pursuer.
[24] I now turn to the effect of finding 23 in paragraph (231) of the arbiters' Note of Reasons.
The defender categorises this as a finding in fact, at least to the extent that
the arbiters found that there was an absence of sufficient evidence such that
they could make no finding as to whether or not the pursuer could have cured
its breach within three months. As the burden of proving this point rested
with the pursuer, and as the arbiters' award was agreed to be final and binding
upon the parties, the pursuer had failed to avail itself of the opportunity to
discharge the burden of proof, and the matter was now closed and could not be
revisited. As discussed above, the pursuer submitted that the burden of proof
did not rest on it, and in any event finding 23 was not a finding that the
pursuer had failed to prove anything.
[25] Applying the normal meaning of the language used in finding 23,
and looking to the Note of Reasons as a whole, I consider that the arbiters
have applied their minds to the question whether the pursuer could have cured
its breach timeously. They were unable to answer that question because there
was not sufficient evidence on the point. I have already decided that the
burden of leading evidence on that point rested with the pursuer. It appears
that the arbiters heard evidence on this point, and submissions about it.
Having done so, they opted for what Lord Brandon of Oakbrook described in Rhesa
Shipping (at page 955D) as the "third alternative". They were entitled to
reach this view, and no challenge has been mounted to their jurisdiction or
power to do so. I do not consider that it is now open to the pursuer to seek
to lead evidence before this court in an attempt to prove that it could have
remedied the breach within three months.
[26] I now turn to consider parties' submissions about a variety of
factors which may affect the assessment of damages. In doing so, the principle
that a man shall not be permitted to take advantage of his own wrong (referred
to in the New Zealand Shipping Company case and in McBryde on
Contract) needs to be borne in mind. Senior counsel for the pursuer was
correct in observing that the facts of the New Zealand Shipping Company
case were far removed from the present circumstances but it does not follow
that the principle is irrelevant in this case. In its fourth conclusion the
pursuer seeks payment of more than $61,000,000 by way of damages for the period
September 2002 to December 2011. However, on the basis of the arbiters'
findings, it appears that the defender only purported to invoke the
Clause 1(E) procedure because it was unaware that the Clause 1(D)
procedure was open to it; this state of affairs arose because of the pursuer's
breach of its repair and maintenance obligation, and its further breach of its
obligation to provide the defender with accurate reports of the vessel's
condition. It would be a surprising result if the pursuer was able to recover
damages for the period 2002 to 2011 because, by its breach of its reporting
obligation, the defender was unaware of its material breach of its repair and
maintenance obligation.
[27] Once the arbiters had found (a) that it was the defender's
underlying purpose to remove the pursuer from its role as manager of the rig,
and (b) that the pursuer was in material breach of its repair and maintenance
obligation, it may perhaps be thought to be likely that the defender would rely
on such material breach as soon as it became aware of it, using the mechanism
of Clause 1(D) in order to seek termination of the contract. I say no
more about this at this stage, because the defender makes averments in this
regard which are denied by the pursuer. It may therefore be necessary for
evidence to be led in this respect. This evidence may have an effect on the
proper assessment of the valuation of the damages to which the pursuer may be
entitled. It is not appropriate for me to express any concluded views on these
matters at this stage. However, in deference to the arguments which were
advanced before me about the various dicta in the Mihalis Angelos and
Golden Victory cases, it may assist if I give some indication of how the
court might approach evidence to the effect that the defender would indeed have
initiated the Clause 1(D) procedure in reliance on the pursuer's material
breach as soon as it became aware of that breach. Lord Walker of Gestingthorpe
at paragraph 46 of the Golden Victory case suggested a spectrum of later
events ranging from inevitable (in the sense of being predictable with
confidence equal, or closely approximating, to 100%), and a mere possibility
carrying little or no weight in commercial terms. While I accept that the
defender's successful invoking of the Clause 1(D) provisions to achieve
termination of the contract may fall short of what Megaw LJ described as a "predestined
event" in the Mihalis Angelos and so perhaps falls short of Lord Walker
of Gestingthorpe's categorisation of inevitability, it appears to me to be towards
that end of the spectrum, and far more than "a mere possibility".
[28] As observed by the Dean of Faculty, the pursuer has chosen to
plead its case on a "but for" basis, not on the basis of the loss of an
opportunity or chance. For the reasons which I have given above, I consider
that many of the averments relating to loss of profits between September 2002
and December 2011, which provide the basis for the fourth conclusion, are
irrelevant. Were it not for the agreement between the parties that the case
should be put out By Order shortly after the issuing of this opinion, I should
have been minded to sustain the defender's first plea-in-law in the principal
action, to refuse the fourth conclusion, and to exclude from probation certain
averments in Article 5 of Condescendence. However, in light of parties'
agreement, the case will be put out By Order in early course, once parties have
had the opportunity to consider this Opinion.