SECOND DIVISION, INNER HOUSE, COURT OF SESSION
|
|
Lord Justice ClerkLord OsborneLord Emslie
|
[2010] CSIH 99CA151/04
OPINION OF THE COURT
delivered by LORD OSBORNE
in appeal by
by
WYMAN-GORDON LIMITED
Pursuers and Reclaimers;
against
PROCLAD INTERNATIONAL LIMITED
Defenders and Respondents:
_______
|
Alt: Robertson, Advocate; Brodies LLP
21 December 2010
The background circumstances
[1] The
pursuers and reclaimers in this action are specialists in, among other areas,
the extrusion of pipes. The defenders and respondents are engaged in the
design, manufacture and supply of pipeline components, including pipes. They
have developed a patented process for the manufacture of clad co-extruded
pipes, known as the Proclad Wex pipe, weld extruded pipes. The exterior part
of Wex pipe is manufactured from carbon steel, as in the case of an ordinary
extruded pipe, but, bonded to the inside surface of the carbon steel is a
cladding material, itself metallic, known as Inconel. The purpose of the
cladding on the inside surface of the pipe is to protect it against the
corrosion which would otherwise occur in a pipe used for the transmission of
oil or gas. The reclaimers also manufacture ordinary extruded pipe, which is
generally known as Ex pipe, which is manufactured from carbon steel and
possesses no cladding on the interior surface.
[2] In early February 2002, the respondents
approached the reclaimers in connection with an order that they had obtained
from an American company, known as FMC for the supply of pipes for an oil
installation in the Gulf of Mexico. The project for the supply of these pipes was known as
Project Thunderhorse. The respondents' intention was to supply FMC with both
Wex and Ex pipes of various diameters.
[3] The procedure followed in the manufacture
of Wex pipes was, in summary, as follows. The reclaimers ordered round steel
bars, known as "blockers", from an outside supplier. Each blocker was
compressed into the appropriate shape by the reclaimers and then pierced in
readiness for the process whereby the blocker was extruded into a pipe. The
pierced blocker was machined by the reclaimers and then supplied to the respondents,
who applied a cladding process using Inconel to the inside surface of the
blocker to be extruded. The blocker was then returned to the reclaimers, who
fed it through their extrusion press, thus producing the clad pipe. The clad
pipe was then subjected to a number of further treatments before the sections
of pipe were ready for use, at which point they were supplied to FMC. The
processes of manufacture were the subject of elaborate manufacturing procedure
specifications for each category of pipe. Pipes were produced only after
lengthy correspondence and meetings between the parties, at which
representatives of FMC attended, since the pipes had ultimately to satisfy
their requirements. Much of the discussion related to the acceptable
tolerances for the pipe, since the extrusion process placed limits on the
number of different tolerances that could be achieved. Agreement on the
tolerances required by FMC was concluded on 30 September 2002 and the tolerances were
set out in a fax message sent by the reclaimers to the respondents on that
date.
[4] The reclaimers' initial quotation for the
supply of certain sizes of Wex pipe was dated 6 February 2002. During the ensuing
months, a number of other quotations for various sizes of Wex and Ex pipe
followed. Those quotations were accepted by purchase orders from the
respondents, which were for specific quantities of each category of pipe. The
initial purchase orders were for small quantities for qualification testing, to
ensure that the pipe was capable of meeting the requirements of FMC and the
ultimate customer for the installation, BP. Later purchase orders were for
quantities of pipe for use in the installation. Following supply of the pipe,
invoices were rendered by the reclaimers; the respondents paid a substantial
number of those invoices.
[5] As the project proceeded, it became
apparent that significant numbers of the Wex pipes were failing to meet the
tolerances agreed on 30 September 2002. It also became apparent that the
cross-section of the pipe, on occasions, developed eccentricities, or
deviations from a rounded shape, in either the base material or the cladding.
In addition, channels or grooves became apparent on the inside surfaces of the
pipes. The most significant of the problems encountered in the manufacture of
Wex pipes was a variation in the thickness of the cladding on the inside of the
pipes along their length. It had become possible to identify that because
improved methods came into use to measure clad thickness. At an earlier stage
clad thickness could be measured only at the ends of a Wex pipe. As a result
of the improved methods of measurement, it became possible to measure its
thickness at different points along the length of the pipe. These difficulties
were the subject of discussion at a meeting between representatives of the
parties held on 28 October 2003, at which the respondents indicated that they considered
that certain pipes had failed in a number of respects, as a result of which
they sought a contribution from the reclaimers to the costs that they had
incurred in consequence. The reclaimers refused to make any such
contribution. Thereafter non-compliance reports were issued to the reclaimers,
which indicated the defects that the respondents claimed to have identified in
the pipes concerned. These reports were disputed. Following that,
negotiations took place with a view to attempting to resolve the issues between
the parties.
[6] During the course of these negotiations,
Mr Grant Webster, of the reclaimers, sent an e-mail to Mr David Neill, of
the respondents, dated 4 March 2004. Because of its significance in the context of the present
action, it is right to quote it in full:
"David,
Thank you for your proposal. The changes you suggest on the throat dimensions are a positive step in helping us to resolve the dimensional issues.
The engineers have completed their assessment and are of the view that opening up the throat by the amount you indicate would be possible with the existing blocker design. We would expect however that the clad thickness would also be affected in proportion to the total wall thickness. Also while this will help with the minimum wall it could still compromise the max. tolerance.
Unfortunately however this does not remove the basic problem which is that we do not believe that between us we understand the process variables sufficiently well to provide the guarantees you require on an on-going production basis. For example while the proposal helps address the dimensional problems the main reason for rejecting the pipe on the last two runs has been lack of clad adhesion. This is something we cannot accept as our liability - either for future business or on the most recent extrusions.
As a consequence therefore we can only commit to further extrusions at your risk. Agreeing to an arrangement you describe does not make good business sense for us given the level of uncertainty there is in the manufacture of the product.
We will commit to control the process variables of forge temperature, soak time etc plus provide access to your people to witness the extrusion runs but given these are within tolerance we would require you to accept the product of these extrusions at full value.
Having said all of the above, we still recognise the potential of the Proclad product for the future. As a consequence we would be prepared to make one more extrusion run on the basis that in the event of a failure your liability would be limited to our manufacturing costs i.e. 85% of the current sales value. If the product was acceptable Proclad would pay the full price but for any unusable pipe your liability would be limited to our on-costs. A commitment on our part to future extrusions would be contingent on the results of this run.
As you know I am available on Friday but out of the plant next week. If you need to contact someone John Harkness, our Manufacturing Director will be on-site.
Regards,
Grant".
[7] A reply to the e-mail of 4 March 2004 was sent by Mr David
Neill to Mr Grant Webster on 22 March 2004. In view of its
significance, once again it is appropriate to quote its terms in full:
"Grant
With reference to your e-mail of 4 March; we have reviewed the content and we cannot agree to the terms you have outlined, and following our internal discussions you left us with no alternative but to advise our customer of the situation that exists between our companies.
Due to the seriousness of the situation we have since had a visit from our customers' senior management, and with regret they have cancelled the remainder of the contract on us. This situation has had a negative impact on the Thunderhorse project, and left them with no alternative. I must also advise you that the contractual status between our customer and Proclad International is irreversible.
Due to the seriousness of the situation we must advise you to expect that any invoices that are due payment are on hold pending compilation of our claim reflecting materials and products supplied which did not comply to the agreed specifications. We anticipate the value of the claim will be substantially more than the value of the unpaid invoices and the balance of the contract price.
David Neill
Technical Director
Proclad International Limited"
The present action
[8] Following
upon the foregoing events, the reclaimers raised the present proceedings, in
which they claim certain sums as payment of the unpaid price of goods supplied
by them to the respondents and a further sum as damages flowing from the
respondents' alleged breach of contract. The respondents have lodged a
counterclaim in which they seek a certain sum in respect of damages said to
flow from the reclaimers' alleged breaches of contract. The procedure followed
in the action in the Commercial Court has unfortunately been long and involved. After
adjustment of the parties' pleadings, the commercial judge ordered that the
action should proceed to a preliminary proof on two matters: (i) the terms
and conditions applicable to the parties' contract and in particular, whether
the respondents' standard terms and conditions formed part of the contract;
and (ii) whether or not the respondents' conduct in accepting and making
payment for extruded pipes that did not conform to the tolerances agreed on 30
September 2002 precluded the respondents from relying on those tolerances. The
preliminary proof took place over a period of sixteen days between 23 June 2005 and 13 September 2006. Thereafter the
commercial judge issued an opinion dated 31 December 2007. In it, he found that the
parties had entered into a series of individual contracts for the supply of
quantities of Wex and Ex pipes. Under those contracts, the reclaimers had
agreed to tolerance the inside diameter and overall thickness of the pipes as
clad, to the dimensions set out in the e-mails of 30 September and 17 October 2002. However, he found that
the reclaimers had not agreed to tolerance the thickness of the clad of the
pipes. Nor had the reclaimers warranted that the pipes would be suitable for
use by FMC. He further found that, if he were wrong in the last conclusion and
if the reclaimers had agreed to tolerance the thickness of the clad, the
respondents had not waived their contractual rights in respect of that
obligation. In the light of his findings, after a By Order roll hearing on 22 January 2008, the commercial judge
granted decree in favour of the reclaimers against the respondents for payment
of the sum concluded for in the second conclusion of the summons. Thereafter,
following further procedure, on 29 January 2009, the commercial judge allowed a
second preliminary proof in relation to certain issues that the parties agreed
had arisen. These were, first, whether the e-mail sent by the reclaimers to
the respondents on 4 March 2004 was a repudiation of the parties' contract and
demonstrated the reclaimers' intention not to perform fundamental contractual
obligations to carry on extrusions; and, second, whether the e-mail sent by
the respondents to the reclaimers on 22 March 2004 amounted to confirmation by
the respondents that they were accepting the earlier e-mail as a repudiation,
or whether that e-mail was itself a repudiation of the parties' contract. That
preliminary proof took place over a period of eight days in April 2009. On 3 July 2009, the commercial judge
issued an Opinion in which he made the following findings:
"1. The reclaimers' e-mail of 4 March 2004, read in context, was a repudiation of the contract between the parties and demonstrated the reclaimers' intention not to perform fundamental contractual obligations to carry on extrusions;
2. The e-mail of 4 March 2004, read in context, did not relate only to clad thickness;
3. The respondents' e-mail of 22 March 2004 amounted to confirmation by the defenders that they were accepting the e-mail of 4 March 2004 as a repudiation of the contract; and
4. The e-mail of 22 March 2004 did not amount to repudiation by the respondents of the parties' contract."
In the light of those findings the case was put out on the By Order roll for a discussion of further procedure. That hearing took place on 10 July 2009. On that occasion, the commercial judge pronounced an interlocutor in which he (i) sustained the respondents' first plea-in-law and excluded from probation certain averments in articles 3 and 4 of Condescendence, (ii) sustained the respondents' third plea-in-law to the extent of holding irrelevant the defence on the merits in Answers 8, 9 and 10 to the counterclaim, and (iii) restricted proof of the averments in Statements of Fact 8, 9 and 10 in the counterclaim to quantum. He then granted leave to reclaim against that interlocutor. As a consequence, he also discharged a further diet of proof which had been due to commence on 25 August 2009. Against that interlocutor and the interlocutor of 3 July 2009 the reclaimers have now reclaimed to this court. Review of the commercial judge's interlocutors is sought on two bases. The first basis is that he erred in the application of the law relating to repudiation to the facts established by the evidence. The second basis is that he erred in basing his decision on an implied term that was not contended for by either party, upon which no evidence had been led, and which had not been the subject of submissions to him.
The submissions of the reclaimers
[9] When
this matter came before us, the solicitor advocate for the reclaimers moved the
court to recall the interlocutor of 10 July 2009 and to pronounce an
interlocutor (i) sustaining the pursuers' fifth plea-in-law in the principal
action to the extent of holding irrelevant the defenders' averments regarding
the pursuers' e-mail dated 4 March 2004 amounting to a repudiation of the
contract and that by deleting the averments in Answer 3 from "On
4 March 2004, the pursuers intimated by e-mail ...." to "... substantially in
excess of the sums sued for by the pursuers.", (ii) sustaining the first
plea-in-law for the pursuers in the counterclaim and excluding from probation
the defenders' averments in Statements of Fact 8, 9, and 10 in the Counterclaim, and (iii)
restricting the proof to the claims made in article 4 of Condescendence in
the principal action, and Statements of Fact 3, 4, 5, 6, 7 and 11.
Alternatively, it was submitted that the commercial judge's interlocutor of 10 July 2009 should be recalled and
the cause remitted to a different commercial judge to consider the issue of the
implied term de novo in the light of further pleadings and further
argument. As an alternative to this motion, the solicitor advocate for the
reclaimers suggested that the court might express its opinion on the
controversial issues to be discussed, following which the form of the
interlocutor to be pronounced in implement of that opinion could be the subject
of further discussion at a By Order roll hearing.
[10] In developing his submissions, the solicitor
advocate for the reclaimers relied upon the extensive written submissions which
had been lodged, which, on account of their length and character cannot conveniently
be summarised here. However, he indicated that certain aspects of those
written submissions would be elaborated in argument. He opened his submission
by making a number of detailed points regarding the process of the extrusion of
blockers, with a view to the production of clad pipes. It was a feature of the
background that the thickness of the cladding metal had only been capable of
being measured accurately since August 2003 along the length of the extruded
pipes. Prior to that time, its thickness could be measured only at the ends of
such pipe. It would be wrong to say that the process of extruding clad pipes
was wholly experimental, but, on the other hand, there was an element of
uncertainty as regards the outcome in any particular case. The extrusion
process was based upon an assumption that the extrusion would affect both metallic
elements of the blocker equally. Also, it had to be recognised that the
temperature at which extrusion took place was a compromise figure, based on the
optimum temperature for each component of the clad blocker. In this connection
reference was made to passages in the commercial judge's Opinion dated 31 December 2007 at pages 31, 33, 34 and
35 of Appendix A. It was submitted that this aspect of the background
tended to undermine the commercial judge's finding of an implied term in the
contract in paragraph [24] of his Opinion of 23 July 2009. What was said in
paragraph [17] of the written submissions had to be emphasised. The
reclaimers had not been in a position to warrant the thickness of the cladding
material after extrusion: that immediately was inconsistent with the implied
term found by the commercial judge. The reclaimers had agreed to tolerances
for the inside diameter of the extruded pipe after cladding and the overall
thickness of the pipes, as set out in the e-mails of 30 September and 17
October 2002; but they had not agreed to tolerances for the thickness of the
cladding.
[11] The Dinsley machine, which was capable of
measuring the thickness of the cladding material in extruded pipes along their
length, had become available only after the contract had been entered into.
Plainly that circumstance bore upon the question of whether any condition, such
as contemplated by the commercial judge, could be implied into the contract.
These matters were referred to by the commercial judge in paragraph [24]
of his Opinion of 31 December 2007, at page 30 of Appendix A.
[12] The solicitor advocate for the reclaimers
then proceeded to examine in detail the several contracts between the parties
dealt with in paragraphs [8] to [17] in the commercial judge's Opinion of 31
December 2007. The final order was for sixty 5-inch Wex pipes, as described in
paragraph [17] of that Opinion. It was uncontroversial that the
correspondence which passed between the parties in March 2004 related to the
final contract.
[13] On the subject of the implied term, it was
submitted that it had been inappropriate for the commercial judge to have
resorted to the implication of a term in the relevant contract in a context in
which the existence and content of such a term had not been explored in the
normal way in adversarial proceedings. The fact was that there were no
averments bearing directly on the implied term, no evidence had been led
relating to it, and no submissions had been made in relation to it. The
commercial judge had been in error in resorting to an implied term in these
circumstances. If that were correct, the question then would become what the
effect of that error was on his decision. He would consider that later.
[14] Turning to the reclaimers' position in
relation to the e-mails of 4 March and 22 March 2004, it was submitted
that the former of these, read in context, was not a repudiation of the
contract between the parties; rather its terms demonstrated that the reclaimers'
intention had been to adhere to their contractual obligations. Furthermore,
read in context, the latter of the two e-mails did amount to a repudiation of
the contract on the part of the respondents. It was necessary to a proper
interpretation of these e-mails that the evidential background to them should
be understood. That was dealt with in paragraphs [56] to [117] of the written
submissions.
[15] While it was thought unlikely that there
would be serious dispute about the applicable legal principles relating to
repudiation of a contract, it was nevertheless submitted that the commercial
judge had erred in holding that the test for whether or not there had been a
repudiation of the contract was whether the party's conduct demonstrated an
intention to abandon the contract, or to refuse further performance. Instead,
he ought to have concluded that the test was whether or not the party's conduct
demonstrated a clear and unequivocal intention to abandon the contract, or to
refuse further performance under it. The formulation of the test favoured by
the reclaimers was derived from the relevant authorities. In particular, it
was based heavily upon what was said in Woodar Investment Development Ltd v
Wimpey Construction UK Ltd [1980] 1 W.L.R. 227. Reliance was placed on
the observations of Lord Keith of Kinkel at page 294 and of Lord Wilberforce at
page 281. That case emphasised just how clear words or actions had to be in
order to constitute a repudiation and how reluctant the courts were to hold
that a contract had been repudiated before the time for performance had
arrived. If a party proposed to perform a contract on terms different from
those agreed, that would be a repudiation of the contract only if it were also said
that that party would not perform except on the new basis proposed. Reliance
was placed on Blyth v The Scottish Liberal Club 1982 SC 140, at page 143 and on
the observations of Lord Hamilton, as he then was, in Edinburgh Grain Ltd
v Marshall Food Group Ltd 1999 S.L.T. 15, at page 23. It was
accepted that the commercial judge had been correct when he said that e-mails
were plainly commercial documents, drafted by commercial men, and had to be
construed as such. Further, it was submitted that an alleged repudiation had
to go to the root of the contract; it had to amount to a clear indication that
a party had renounced its obligations under the contract; and that the words or
conduct must amount to an absolute refusal to perform its part of the
contract. In addition, it was necessary to look at the whole circumstances of
the case when considering the actings of a party alleged to have repudiated the
contract. An allegedly repudiatory act might take on a wholly different
complexion when viewed in its proper context. Finally, words or actions had to
be viewed objectively through the eyes of a reasonable person, who was one
experienced in the particular industry, trade or profession in question and
duly informed of the salient features of that industry, trade or profession,
and of the terms of the contract in question, at the material time.
[16] Turning to the issue of the implied term
found by the commercial judge, it was said that the Privy Council had recently
considered issues relating to implied terms in Attorney General of Belize
& Others v Belize Telecom Ltd [2009] 1 WLR 1988. Many of
the traditional and well-known authorities relating to implied terms were
considered, including The Moorcock (1889) L.R. 14 P.D. 64. In that
latter case, Lord Esher, M.R., made it clear that, in a case where a
condition had to be implied, the question was what was the least onerous duty
which could be implied. On any view, the commercial judge's implied condition
fell foul of this principle. In that connection reference was made to
paragraph [24] of his Opinion of 3 July 2009. However, in the absence
of pleadings, evidence and submissions on the topic, he should not have implied
any condition at all.
[17] The solicitor advocate for the reclaimers
then proceeded to address the application of the law relating to repudiation of
contract to the facts of the case. He relied on what was said in
paragraphs [118] to [142] of his written submissions. The conclusion
reached by the commercial judge in paragraph [29] of the Opinion of 3 July 2009 was erroneous. In
paragraph [24] of his Opinion, the commercial judge had reached the
conclusion that a term had to be implied in the contract to give it business efficacy
and he had stated his conclusion as to the content of that term. It was
submitted that that conclusion was central to the case and, in particular, to
the conclusion that repudiation had resulted from the e-mail of 4 March 2004. It was quite evident
that problems had occurred in relation to the level of cladding in the pipes
being extruded. However, the root cause of that problem was never
investigated. There might have been a number of explanations for the problem,
which had been the subject of a discussion between the parties and of e-mails,
in particular those of 19 February 2004 and 24 February 2004. There was a level of
misunderstanding during the course of the correspondence and associated
discussions. Against that background, the implication of any contractual term
would have been a matter of great delicacy.
[18] Turning to the language of the e-mail of 4 March 2004 itself, it was quite
evident from the first and second paragraphs that the parties were
considering positive steps towards the resolution of the problem being
encountered. That undermined the whole idea of a repudiation. In the third
paragraph, the problem of clad adhesion was considered. The reclaimers had
stated that they could not accept liability for pipes suffering in that
respect. That proceeded upon a proper view of the contract, in which there was
no implied term of the kind identified by the commercial judge.
[19] The fourth and fifth paragraphs of the
e-mail had to be read together and in the light of the relevant background
circumstances. Reading these two paragraphs in that way, a reasonable man
would have concluded that the reclaimers were seeking to identify those parts
of the process which they could control and which might have a bearing on the
defects being reported. The reclaimers had indicated a preparedness to control
those variables. In addition, they would continue to meet the overall
dimensional requirements of the contract. Reference was made to the detailed
submissions in paragraphs [134] to [137] of the Written Argument. It could not
be said that the content of those paragraphs amounted to repudiation of the
contract, as properly understood.
[20] The contents of the sixth paragraph of the
e-mail were important. In it there was advanced an alternative proposal for
the future with an offer to conduct a further extrusion run on the basis there
described. That was quite inconsistent with the notion of repudiation. While the
seventh paragraph of the e-mail was an indication of opportunities for
further discussion, again it was inconsistent with repudiation.
[21] Turning to the e-mail of 22 March 2004, the respondents'
position was that it amounted to an acceptance by them of the reclaimers'
repudiation, which thereby resulted in the rescission of the contract. Their
alternative contention that that e-mail did not terminate the contract was erroneous.
If the e-mail of 4 March 2004 was not to be seen as a repudiation of the contract, then
undoubtedly that of 22 March 2004 was a repudiation of it by the respondents, which was
accepted by the actings of the reclaimers.
[22] Turning to the commercial judge's treatment
of the implied term which he found to be part of the contract, submissions had
already been made concerning the illegitimacy of the implication of a term in
the absence of pleadings, evidence, if necessary, and submissions on the topic.
However, if for a moment it was assumed that it was proper in the circumstances
of this case to consider the implication of the term found by the commercial
judge, it was submitted that having regard to the evidence in the case, no such
term could properly be implied. Production of Wex pipe was different from the
production of a mono-wall pipe, principally because the extrusion involved two
different metals at the same time. They would not necessarily have the same
optimum extrusion temperature. It might even have been the case that there was
no temperature at which the two metals would extrude proportionately and in
which the metallurgical bond would remain intact. Similarly there was an
element of uncertainty regarding the time for which it was necessary to heat
the blockers prior to extrusion. There had been an assumption underlying the
parties' dealings that in the Wex process, the two metals would extrude
proportionately, but the fact was that that could not be guaranteed by the
pursuers. While it was maintainable that the reclaimers had been obliged in
the case of Wex pipes to warrant certain aspects of the process of extrusion,
the evidence suggested that the carrying out of extrusion in that particular
manner did not guarantee a particular result in relation to clad adhesion and
thickness. Thus the implication of the term selected by the commercial judge
was in conflict with the evidence. If a term was to be implied in the
contract, which the reclaimers did not necessarily accept, it could not be the
term identified by the commercial judge. A term to be implied would require to
refer to the tolerances within which the process variables were to be held. It
would have to recognise the fact that the process was, to some extent, an
experimental one. In that context the term implied by the commercial judge, in
effect, placed the whole risk of the project upon the reclaimers, for which
there was no justification. That circumstance highlighted the necessity for
the issue of the possible implication of a term to be explored firstly in the
pleadings, then in the evidence, and then in the submissions. None of that had
been done. If the term was one on which the respondents required to rely, they
should have pled it and endeavoured to support their contention.
[23] There remained for consideration the
consequences of the commercial judge's decision to imply the term that he had
selected. In particular, the question arose of whether that decision could be
shown to have affected the outcome of this part of the case. In that
connection it was submitted that the interpretation of the vital e-mail of 4 March 2004 depended upon the terms
which were properly to be seen as part of the contract. Whether a contract was
repudiated by the adoption of a certain position necessarily depended upon the
contractual terms. In all the circumstances, the effect of the commercial
judge's implication of the term selected by him was so fundamental that it
should be seen as undermining his reasoning in relation to the primary issue in
the case, which was the question of the proper meaning and effect of the e-mail
of 4 March
2004. For
these reasons also, the reclaiming motion should be allowed.
[24] The solicitor for the reclaimers went on to
deal with certain miscellaneous matters raised during the course of his
submissions. It had been held at an earlier stage that there had existed
between the parties not a single contract but a series of separate contracts.
The question had been raised as to which particular contract might be affected
by the alleged repudiation. As at March 2004 only four pipes from an earlier
order remained to be completed. The remaining work to be done related to the 5-inch
pipes which were the subject of the final order. The reclaimers' submission
was that the respondents' repudiation affected those groups of pipes.
[25] There had been some discussion concerning
what the commercial judge had said in his second Opinion in this case at
paragraph [36], where he referred to the Wex process being for the
production of a "clad pipe". That simply reflected the assumption that had
been made that extrusion of a clad blocker would be proportionate. That
assumption unfortunately had proved to be wrong. Thus it might be that the
conclusion of the contract had been affected by that error, but that particular
characterisation of the situation was not relied upon by either party.
[26] In relation to the interpretation of the
e-mail of 22 March 2004, James Schaffer Ltd v Findlay Durham &
Brodie [1953] 1 W.L.R. 106 was of assistance, containing as it did a
definition of what was involved in repudiation. Reference was made
particularly to page 115.
[27] In the event that the court considered that
it was appropriate that the question of an implied term should be considered,
it was submitted that the procedure identified in Kennedy v Norwich
Union Fire Insurance Society Ltd 1993 S.C. 578 should have been followed.
If the commercial judge considered that an issue concerning a possible implied
term had arisen in the case, he ought to have taken steps to indicate that to
the parties before reaching a decision on it, perhaps by putting the case out
By Order for consideration of what should be done in relation to the matter. Following
such a procedure would have given the parties the opportunity to consider and
make submissions about the matter in question. That type of procedure was
approved in Macphail's Sheriff Court Practice 3rd Ed.,
paragraph 17.28. The adoption of the course followed by the commercial
judge here was similar to the course taken by the Lord Ordinary and disapproved
in Kay's Tutor v Ayrshire & Arran Health Board 1987 S.C. 145
at pages 153 and 162. In these circumstances, if the reclaimers' primary
contentions were rejected, it was submitted that the commercial judge's
interlocutor of 10 July 2009 should be recalled and the cause remitted to a
different commercial judge to consider the issue of the implied term de novo,
in the light of further pleadings, and, if necessary, evidence and argument.
Submissions of counsel for the
respondents
[28] Counsel
moved the court to refuse the reclaiming motion and adhere to the two
interlocutors of the commercial judge, dated 3 and 10 July 2009. If the court were
not prepared to follow his decision in relation to the implied term, it should
hold that his reasoning did not wholly depend on that term. He went on to draw
attention to the terms of the respondents' written submissions, which, because
of their extent, cannot conveniently be summarised here.
[29] Criticism had been directed against the
judgment of the commercial judge in respect of the test which he had employed
in relation to the issue of whether or not there had been repudiation of the
contract. That controversy was sterile. It was submitted that the commercial
judge had adopted the appropriate test. In this connection reference was made
to section 3 of the written submissions. The commercial judge had relied upon
the formulations of the concept of repudiation found in Edinburgh Grain
Limited v Marshall Food Group Limited 1999 S.L.T. 15 which did not
use the qualifying expression "clear and unequivocal". In any event, in
relation to the facts of this case and, in particular, to the terms of the
e-mail dated 4 March 2004, there was nothing referred to in the judgment that
could be described as equivocation on the part of the reclaimers.
[30] Turning to the matter of the contractual
obligations of the parties, it was submitted that plainly the respondents were
responsible for the preparation, including welding, of the blockers to be
extruded. The later stages of the process of preparation of a clad pipe were
the responsibility of the reclaimers, whose obligation it was to carry out
effectively the extrusion process so as to produce a clad pipe. However, the
terms of the e-mail of 4 March 2004 and the evidence which had been led at the preliminary proof
concerning the context of it indicated that the reclaimers were not in fact
prepared to perform the contract upon that basis. That amounted to a
repudiation, as the commercial judge had found. What the reclaimers were
offering to do in that e-mail was simply to produce pipes from the blockers
supplied that conformed to certain tolerances as regards their dimensions.
Counsel then proceeded to discuss the commercial judge's findings in detail.
It was submitted that there was no flaw in his reasoning. Essentially the
reclaimers' obligation had been to undertake extrusions in order to produce a
clad Wex pipe which conformed to the agreed tolerances. Thus they required to
carry out properly the processes for which they were responsible. As regards
problems in adhesion, there might be more than one cause for them. An
examination of the evidence showed that there had been a clear acceptance that
failure on the part of the reclaimers to carry out the processes for which they
were contractually responsible was a breach of their contractual obligations.
That was the background to the e-mail of 4 March 2004.
[31] There was no difference of view between
parties in relation to the law regarding the implication of contractual terms.
It was to be found in the Attorney General of Belize & Others v Belize
Telecom Ltd, particularly paragraph 27 of the judgment of the Board.
Reference was also made to The Moorcock (1889) L.R. 14 P.D. 64, and the
observations of Bowen, L.J. at page 68. Applying these principles to the
circumstances of this case, it was submitted that what the commercial judge had
done was to look at the structures of the contract and, in particular, the
allocation of responsibilities in relation to the Wex process and to set out an
implied term which expressed what the contract actually meant in the business
context involved. Reliance was also placed on Mannai Investment Co Ltd v
Eagle Star Life Assurance Co Ltd
[1997] AC 749, at
page 771.
[32] It had been said on behalf of the reclaimers
that the contractual term implied by the commercial judge had "come out of the
blue". The answer to that point lay in the pleadings and, in particular, in what
was stated in Statement 4 for the respondents in the counterclaim at page
31B-D of the reclaiming print. Those averments, although not expressly
referring to an implied term, amounted to an assertion of the existence of the
term identified by the commercial judge. The situation was dissimilar to that
which existed in Kay's Tutor v Ayrshire & Arran Health Board,
(supra). However counsel accepted that no submissions had been made to the
commercial judge, prior to his issue of his Opinion dated 3 July 2009, to the effect that a
term was properly to be implied into the contract. He accepted that there had
been no submissions relating to any tolerances affecting the cladding element
of the pipes.
[33] Even if the commercial judge was in error in
reaching the conclusion that the contractual term identified by him was to be
implied, it was submitted that his conclusion relating to the character of the
e-mail of 4 March
2004 could
and should survive. In that connection, reference was made to the detailed
points made in paragraph 9.1 of the respondents' written submissions and
following. The commercial judge's conclusion in paragraph [27] of his Opinion
that the e-mail of 4 March 2004, taken as a whole, involved statements by
the reclaimers which proceeded on the basis that they were not bound by any
obligation to make further extrusions. It was that feature of the e-mail in
question that led to the conclusion that the contract had been repudiated.
That did not depend on any requirement to imply a term in the contract.
Furthermore, in paragraph [27] of his opinion, the commercial judge had
drawn attention to the sixth paragraph of the e-mail in question. It offered
one more extrusion run on the basis there suggested. That was plainly
inconsistent with the existing contractual terms, as was what was identified in
the latter part of the same paragraph. These conclusions were consistent with
the commercial judge's implied term, but did not require that implied term to
be recognised before they could be seen as valid. It was pertinent to notice
that what was said concerning the implication of the term in
paragraph [24] of the Opinion of 3 July 2009 was quite consistent with
what had previously been said in paragraph 36 of his Opinion, dated 31 December 2007. In all the
circumstances, the reclaiming motion should be refused.
Conclusions
[34] It
appears to us that the three principal issues which arise in this reclaiming
motion are these: (1) whether the e-mail from Grant Webster to David Neill,
dated 4 March 2004, properly construed in its context, amounted to a
repudiation of the parties' contractual relationship by the reclaimers; (2) on
the assumption that the e-mail of 4 March 2004 did not amount to such a
repudiation, whether, properly construed, the e-mail from David Neill to Grant
Webster, dated 22 March 2004, amounted to a repudiation of the parties' contractual
relationship by the respondents, which was accepted by the reclaimers'
subsequent actings; and (3) whether the decision by the Lord Ordinary,
expressed in paragraph [24] of his Opinion, dated 3 July 2009, that
on the ground of business efficacy it was necessary to imply a term in the
contract between the parties to the effect that each party was liable for the
consequences of any defects that might arise as a result of the manner in which
that party carried out its own processes, was sound. We shall deal with each
of these issues in turn.
[35] Dealing then with the first of the issues
just mentioned, in our judgment, the law on repudiation, as an anticipatory
breach of contract, is well settled and, for present purposes, we see no need
to innovate upon those statements of principle which have been deemed
sufficient in the past. Where verbal or written communications are in issue,
the key requirement, as we understand it, is that before a repudiation can be
held to have occurred, there should be an objectively clear indication that,
for whatever reason, material contractual obligations are not going to be
performed at the due date. The other party to the contract would then have the
option, either to accept the repudiation and consequently to rescind the
affected relationship, or alternatively to insist on continued performance of
the contract in its existing form. It is only where such an anticipatory
breach of contract is clearly established following an objective assessment of
the circumstances that the relevant option can arise at all.
[36] As Lord Wilberforce put it in Woodar
Investment Development Ltd v Wimpey Construction UK Ltd, (supra),
at page 283: "... Repudiation is a drastic conclusion which should only be held
to arise in clear cases of a refusal, in a matter going to the root of the
contract, to perform contractual obligations". Many judicial statements to
substantially the same effect are to be found elsewhere. In Freeth &
Another v Burr (1874) L.R. 9 C.P. 208, Lord Coleridge
C.J. said at page 214: "The principle to be applied in these cases is,
whether the non-delivery or the non-payment amounts to an abandonment of the
contract or a refusal to perform it on the part of the person so making
default." This echoed a passage on the previous page of his opinion, in which
he described the search as being for "... Intimation of an intention to abandon
and altogether to refuse performance of the contract." In Scotland, nearly two
decades after the decision in Woodar Investment Development Ltd v Wimpey
Construction UK Ltd, (supra), was approved by the Second Division of the
Court of Session in Blyth v Scottish Liberal Club, the matter was
again considered by Lord Hamilton, as he then was, in the Outer House in Edinburgh
Grain Ltd v Marshall Food Group Ltd. At page 22 he said this:
"What, in my view, is required for repudiation is conduct demonstrative of an
intention not to perform fundamental contractual obligations as and when they
fall due."
[37] Objective analysis of a claimed repudiatory
statement will require the court to consider its terms in the light of the
whole surrounding circumstances, and, from the perspective of what a reasonable
person in the position of the recipient might legitimately understand.
Evidence of what individual participants may subjectively have thought or
intended is of little or no relevance, in our opinion. What really matters is
the tenor of the communication, as objectively ascertained by the court. In Woodar
Investment Development Ltd v Wimpey Construction UK Ltd,
Lord Keith, at page 297, desiderated "... a clear indication by [a
contracting party] that he does not intend to perform his obligations under it
when the time for performance arrives", and Lord Wilberforce, at page 281,
confirmed that "... subjective intention is not decisive: ... there remains the
question whether, objectively regarded, [the appellants'] conduct showed an
intention to abandon the contract." Similarly in Edinburgh Grain Ltd v Marshall
Food Group Ltd, Lord Hamilton, at page 23, confirmed that in this context
the issue was always whether a party's conduct, "... viewed objectively as a
whole", conveyed a clear intention that he would not or could not perform. In
a commercial context, of course, documents and communications must normally be
construed in a commonsense way and by reference to the reasonable understanding
of commercial men.
[38] Against that background, the reclaimers
contended, somewhat tentatively, that in approaching the issue of repudiation,
the commercial judge had misdirected himself by applying the wrong test. The
suggestion was, in brief, that any statement of principle must include the
combined adjectives "clear and unequivocal" with reference to a demonstrated
intention, and that, in failing to acknowledge this, the commercial judge had
fallen into error and had been too ready to identify a repudiation where none existed.
In our view, this argument is without merit, and we are unable to accept that
in paragraphs [19] to [21] of his Opinion, the commercial judge misdirected
himself as to the proper test to be applied. For a given intention to be
"demonstrated", "indicated", or "shown", it is self-evident that an equivocal
lack of clarity will not suffice, and, in bearing to follow settled lines of
authority, we do not think that the commercial judge's approach can be
criticised in that respect.
[39] There are, however, two inter-related areas
of concern to which we must now advert. The first is the commercial judge's
unqualified assertion at the end of paragraph [21] of his Opinion that:
"If a party proposes to continue on terms that are fundamentally different from
the existing terms, that too will amount to a repudiation." To our mind, that
statement, as it stands, goes too far. We consider that a contracting party
must always be entitled, especially in altered circumstances, to propose or
suggest a future variation of the relevant contractual terms for the other
contracting party to consider. Provided that a refusal to perform on existing
terms is not simultaneously demonstrated, it does not seem to us that the mere
tabling of such a proposal or suggestion will necessarily amount to repudiation
of the contract. In this particular respect, therefore, we consider that that
the commercial judge may have approached the critical e-mail of 4 March 2004 on a wrong footing.
Especially where the respondents' constructive e-mail of 27 February 2004
apparently contained a radical proposal which was not held to jeopardise the
continuing validity of the parties' contractual relationship, it is difficult
to see why apparent counter-proposals in the reclaimers' response of
4 March 2004 should have been treated in a different way.
[40] The second related concern is the uncertain
state of the parties' pre-existing contract. On the one hand, e-mails of 30 September 2002 and 17 October 2002 confirmed that the
reclaimers were contractually obliged to achieve certain dimensional tolerances
in all finished pipes. Further, in the e-mail of 27 July 2003, the reclaimers also
undertook responsibility for the proper conduct of the extrusion process as
such. This, it was agreed, would include such features as adequate furnace
"soak time", appropriate extrusion pressures and temperatures and a sufficient
level of lubrication. Following the preliminary proof held at an earlier
stage, however, the commercial judge declined to hold that the reclaimers were
bound, expressly or by implication, to deliver an acceptable end product in
relation to "clad thickness" or "clad adhesion". On the contrary, as confirmed
at paragraph [2] of his Opinion of 3 July 2009, the commercial judge
held
"... The pursuers warranted that the inside diameter and overall wall thickness of the pipes would meet certain dimensions and tolerances ... The pursuers did not, however, agree to tolerance the clad thickness of the pipes, nor did they warrant that the pipes would be suitable for use by the defenders' ultimate customer, FMC."
[41] On the evidence, both parties had assumed
that the clad layer would extrude proportionately with the surrounding carbon
steel component, and there was no certainty whether this could or would be
achieved. At paragraph [36] of his Opinion of 31 December 2007, moreover,
in considering the hypothesis of an extruded pipe proving to incorporate either
no steel or no cladding, the commercial judge expressed the view that:
"If, accordingly, either the carbon steel or the cladding were absent in a significant part of the pipe that would involve a breach of contract (although the responsibility for the breach might be in dispute, depending on its cause)."
What the commercial judge appeared to be saying in that passage is that the situation envisaged would amount to a breach of contract, but that it was not possible, in the absence of knowledge of the cause of the situation, to say whether the breach was on the part of one party or the other - a somewhat odd position. However, the passage does confirm the ongoing uncertainty as to responsibility for such a situation in the context of the contract in question. By February 2004, moreover, the parties appear to have had no clear idea as to who should bear responsibility for pipes rendered unusable by "tearing", that is, separation of the clad layer from the surrounding carbon steel. That was apparently because the cause might lie either with the features inherent in or limitations of the reclaimers' extrusion process, or alternatively with welding or clad-quality defects attributable to the respondents. In any event, as recorded at paragraph [10] of his Opinion, dated 3 July 2009, the commercial judge was not in a position to decide whether pipes rejected by the respondents were in fact defective. All that could be said was that the respondents had expressed dissatisfaction on certain grounds, and that this was known to the reclaimers.
[42] So far as appears from the commercial
judge's Opinions of 31 December 2007 and 3 July 2009, the parties'
contractual arrangements contained no express provision as to which of them
must bear the risk of or responsibility for the phenomenon of "tearing", or
separation of the clad bond, were that to materialise. It may be that, for
this reason, the commercial judge felt it necessary to search for some implied
term to fill that void, with which we deal later in this Opinion; but, for
present purposes, we are inclined to regard the contractual uncertainty in this
area as having a particularly significant bearing on the proper construction of
the critical e-mail of 4 March 2004. In these circumstances of
uncertainty as to contractual obligations just described, in our view it might
be wholly understandable and not unreasonable for parties to table proposals or
suggestions designed to cater for emerging difficulties which the terms of the
contract did not contemplate and the precise cause of which remained
uncertain. It seems to us that such a course of action must be harder to
characterise as repudiatory conduct than would be the making of proposals or
suggestions for deviation from contractual terms that were clear. In reaching
his conclusions, the commercial judge failed, in our view, to give due weight
to these particular considerations.
[43] Against the background of the developments
summarised above, the respondents' e-mail of 27 February 2004 seems to us to merit
particular attention as part of the context in which the subsequent e-mail of 4 March 2004 was sent. Previous
communications between the parties had been amicable and constructive despite
the emergence of "clad adhesion" and other problems on the last three extrusion
runs. A meeting held between the parties on 24 February 2004 seems to have been
cordial and, as the commercial judge acknowledges in paragraph [14] of his
Opinion of 3
July 2009,
the e-mail which followed it was generally conciliatory in tone. However, it
can be seen to contain an overt stipulation by the respondents which sought, on
the basis of allegations of mechanical damage and tearing, to blame lubrication
problems on the reclaimers and thus to hold them responsible for any pipe
deemed unusable due to recurrence of this damage. The relevant passage is in
the following terms:
"As we have now carried out several hundred extrusions without any internal tearing, and in the recent batches that have been run we have had several with mechanical damage to the internal bore, and tearing it would suggest we have a lubrication problem. Any re-occurrence of this defect resulting in scrap would also be Wyman-Gordon's liability."
The respondents then followed that up with defect notes and a covering e-mail on 29 February 2004, relative to seven out of eleven affected pipes, and these were augmented under cover of another e-mail on 14 March 2004.
[44] With all of these factors in mind, we consider
that the commercial judge erred in construing the reclaimers' response in the
e-mail of 4
March 2004
as an outright repudiation of the parties' contractual arrangements. As
already observed, the parties' contractual documents were silent on the subject
of responsibility for "clad thickness" and "clad adhesion" problems. As we
explain later in this Opinion, we consider that the commercial judge fell into
error in seeking to fill that void with a purported implied term. His decision
to do so, it appears to us, must inevitably have affected his approach to the
interpretation of the e-mail of 4 March 2004. Over and above that, the terms and the tone of that
critical e-mail, read fairly and in context, do not strike us as having the
character of repudiation. At most, the e-mail may be thought to contain
counter-proposals to those advanced in the e-mail of 27 February 2004 for the regulation of
past and future clad adhesion problems.
[45] Looking now at the detail of the critical
e-mail of 4
March 2004,
the opening paragraph is self-evidently positive and constructive, and the
closing paragraph bears to offer special arrangements for a response from the
respondents. After a discussion of clad thickness and overall wall tolerances
in paragraph two, the third paragraph then makes it clear that, while
dimensional tolerances were still for the reclaimers to address, they could not
accept liability for all clad adhesion problems as stipulated by the respondents
in their e-mail of 27 February 2004: "This [lack of clad adhesion] is
something we cannot accept as our liability - either for future business or on
the most recent extrusions." Importantly, the fourth paragraph begins with the
words "As a consequence, therefore...", thereby linking what follows to what had
gone immediately before, and the reclaimers then proceed to confirm
unwillingness to accept the respondents' proposed "arrangement" given the level
of uncertainty involved in the manufacture of the product. On a fair reading,
the "arrangement" in question would appear to be the stipulation regarding clad
adhesion in the respondents' e-mail of 27 February 2004.
[46] In that overall context, we do not think
that the first sentence of the fourth paragraph can reasonably be read as
referable to anything other than what was plainly under discussion, namely the problem
of clad adhesion. That was what the reclaimers were, by way of
counter-stipulation, suggesting should be at the respondents' risk, and it is
highly significant that the whole of the fifth paragraph confirms the
reclaimers' continuing commitment to controlling "... the process variables of
forge temperature, soak time etc." Full value acceptance of extrusions by the
respondents was predicated on "these " being within tolerance and, like the
previously suggested allocation of risk, this proposal does not appear to us to
undermine the reclaimers' established contractual responsibilities for the
future.
[47] Up to this point in the e-mail, we can detect
no demonstrated intention on the part of the reclaimers to withdraw from all of
their obligations under the contract. Even if relevant, therefore, the respondents'
evidential claims regarding the e-mail of 4 March 2004, summarised by the commercial
judge at paragraphs [17], [27] and [28] of his Opinion of 3 July 2009, strike us as entirely
unwarranted. Ex facie the reclaimers were not refusing to meet
dimensional tolerances, nor were they seeking to abdicate responsibility for
controlling the extrusion process as such. They were not, in other words,
threatening non-performance of any of the obligations which the contract placed
on them, and we do not see how any reasonable commercial recipient of the
e-mail could properly have concluded otherwise.
[48] As regards the sixth paragraph of the e-mail
of 4 March
2004, once
more, it starts off on a positive note, looking to the future of the Proclad
product and proposing a special extrusion run to see if the emergent problem
could be resolved by adopting certain measures which had been under
discussion. To our mind, the "failure" there mentioned, taken in context, related
to the matter of clad adhesion, and not, as the respondents asserted, and the commercial
judge found, to any failure of the extrusion process from whatever cause. If
all went well, the respondents would pay the full price, but if clad adhesion
still proved to be a problem, despite all contractual tolerances and process
requirements being met by the reclaimers, the respondents would pay the
reclaimers' on-costs only. In that latter case, of course, the respondents
could no longer seek to blame lack of lubrication or mechanical damage, and the
cause of the clad adhesion problem might then rest with them. With these
possibilities in mind, it is perhaps unsurprising that, in the final sentence
of the paragraph, the reclaimers should have wished to defer further
commitments until the results of the special run were known.
[49] Taking all of these considerations into
account, there is, in our opinion, every reason to regard the e-mail of 4 March
2004 as containing a combination of (i) reassurances that the reclaimers would
continue to adhere to their established contractual obligations regarding
dimensional tolerances and process variables; and (ii) counter proposals for
consideration as to how the parties might best regulate the emergent problems
with clad adhesion for which no contractual provision had yet been made. From
beginning to end, as it seems to us, the general tone of the communication was
constructive and forward-looking, and, without ignoring or misreading its major
contents, we can see no way in which the respondents or, in turn, the commercial
judge, could legitimately have treated it as a repudiation of the parties'
contractual relationship. If the contract was so obviously repudiated as the
respondents ultimately maintained, it is hard to see why they followed it up
with the apparent contractual intimation of rejection notes ten days later. It
is equally hard to see why their purported "acceptance" of the alleged
repudiation was delayed for a further eight days during which they apparently
acquiesced in the determination of their principal contract with FMC. What is
clear is that the respondents, at some point over a period of nearly three
weeks, determined to treat the e-mail of 4 March 2004 as a repudiation of the
parties' contract, and that they did so without taking any steps to try to
clarify the position with the reclaimers. They must therefore, in our view, be
taken to have assumed the risk of their purported reading of the reclaimers'
e-mail being deemed untenable, and consequently of their own e-mail of 22 March 2004 being considered
repudiatory in its own right.
[50] We turn next to consider the second of the
principal issues which we see as arising in this reclaiming motion, namely that
concerning the character and effect of the e-mail of 22 March 2004. In
our view, that e-mail must be construed as independently repudiatory of the
respondents' obligations under their contract with the reclaimers. While the
e-mail of 22
March 2004
is couched in somewhat opaque and oblique language, and while it does not
expressly bear to terminate anything, in our opinion, the whole tenor of that
communication is negative. It commences with a rejection of "the terms you
have outlined". It then goes on to narrate that the respondents considered
that they had no alternative but to advise their customer, FMC, of the
situation existing between the parties. In the second paragraph, it narrates
that FMC had "cancelled the remainder of the contract on us". It informs the
reclaimers that the "contractual status between our customer and Proclad
International is irreversible". We take that to mean that, so far as the
respondents were concerned, their contract with FMC was at an end.
[51] The third paragraph of the e-mail contains
warnings regarding the expected value of the claims being compiled by the
respondents against the reclaimers. We consider that the language of the third
paragraph of the e-mail amounts to a clear indication that the respondents
considered that their contractual arrangements with the reclaimers, save for
the assertion of claims of damages, were at an end.
[52] Since the contractual arrangements between
the reclaimers and the respondents were admittedly not directly dependant on
the continuance of the respondents' contract with FMC, and while the
respondents could, no doubt, have chosen to proceed with the former
notwithstanding the loss of the latter, that was not what was done. The e-mail
of 22 March 2004, in our view clearly
indicated a decision not to proceed in that way. It is quite evident that the
respondents intended to proceed on the basis that the contractual arrangements
between them and the reclaimers were finally at an end, and in our view, the
reclaimers were then left with no realistic alternative but to accept that as a
repudiation of the contract.
[53] We turn now to the third of the principal
issues requiring consideration, the matter of the term implied into the
contract between the parties by the commercial judge. He deals with this
matter in paragraph [24] of his Opinion of 3 July 2009. After considering the
conditions of the contract dealing with the dimensions of the finished product and
other matters he states:
"... but they do not deal with other defects that might arise as a result of the way in which the pursuers' or defenders' processes were carried out. Liability for defects of the latter sort does not appear to have been considered in the parties' discussions prior to February 2004, and it was only in that month that the parties' obligations in relation to other defects came under serious consideration. In my opinion, in the absence of any express term, a term must be implied into the parties' contracts to deal with the allocation of risk in such circumstances. I reach this conclusion for two reasons. First, the allocation between the parties of a risk that has actually come to pass is plainly of critical importance, because one or other of the parties must bear that risk. Secondly, the only alternative to an implied term is that the risk is simply allowed to remain where it falls. That would in my view be unsatisfactory, because it involves allocating risk on an arbitrary basis that does not have regard to the structure of the contract or the circumstances in which the risk falls to be allocated. For these reasons I am of opinion that the implication of a term is necessary on the ground of business efficacy. So far as the content of the term is concerned, I am of opinion that the reasonable and natural implication is that each party was liable for the consequences of any defects that might arise as a result of the manner in which it carried out its own processes. Thus if, for example, a defect arose because of the manner in which the defenders applied cladding to the blocker, the consequences would be the defenders' responsibility, and they would be liable for any resulting losses. Likewise, if a defect arose because of the manner in which the pursuers carried out the extrusion, for example, because of inadequate lubrication, the contrary would hold and the pursuers would be liable for any resulting losses. That appears the proper allocation of risk because it involves holding each party liable for the processes that are under its control and within its peculiar expertise."
[54] It would appear to us correct to observe, as
the commercial judge did, that liability for defects in the extruded pipes that
might arise as a result of the way in which the parties' processes were carried
out was not dealt with in the existing contractual arrangements. We would also
agree that the issue does not appear to have been considered in the course of
the discussions between the parties prior to February 2004. Against that
background, the commercial judge appears to reach the conclusion that in that
state of affairs it was necessary to imply a term into the parties' contract to
deal with the allocation of such risk. Thereafter he gives two reasons why he
considers that such a conclusion is justified. For those specified reasons he
is of the opinion that the implication of a term is necessary to give the
contract business efficacy. Thereafter, he states his view as to a term
relating to these matters that he considered might reasonably and naturally be
implied into the contract.
[55] We do not think that it is either
appropriate or necessary to examine the reasons that the commercial judge gives
for reaching that conclusion, save to say this, that it is quite plain that the
reasons which he states for reaching his conclusion on this matter must be seen
as potentially controversial. That much was confirmed to us during the course
of the hearing of the reclaiming motion.
[56] In these circumstances, we consider it
surprising that the commercial judge concluded that it was proper for him to
reach his conclusion regarding an implied term in the absence of any pleadings
in relation to the matter, in the absence of any evidence which either party might
have wished to lead in relation to the matter and without having heard any
submissions on the matter from the parties. In normal circumstances, if a
party to a contractual dispute considered that, for example, in order to give
the contract business efficacy, it was necessary for a particular term to be
implied in the contract, that party could be expected to make an averment to
that effect in the pleadings and, if appropriate, then to lead evidence
concerning the basis for the implication of such a term and to make submissions
in relation to the issue. The other party would then be given fair notice of
what was contended for and have a full opportunity of engaging in any
evidential consideration of the need for the implied term and of making
submissions to the court about it. None of that happened in the present case,
despite the fact that the commercial judge had previously held a preliminary
proof on the subject of the terms of the contract or contracts between the
parties. In these circumstances, we are driven to conclude that the course which
he followed must inevitably be seen as productive of unfairness and injustice
to the parties.
[57] As was said by the late Lord Macphail
in his work, Sheriff Court Practice, 3rd Ed. at
paragraph 17.28:
"It is generally incorrect to decide any matter raised on record which the parties have declined to argue. It is incorrect to decide any matter in dispute on a ground which has not been explored in evidence or argument."
In support of that proposition, with which we agree, the case of Kay v Ayrshire & Arran Health Board is cited. In that connection the observations of Lord President Emslie at page 153 are apt. There he said:
"It is one thing for a judge to lend his assistance to a party litigant to present his case in evidence. That is entirely proper. It is quite another thing and wholly improper for a judge to neglect the principle of doing justice between the parties and of fairness to both parties by going further and giving a decision in favour of one party upon a ground of his own devising which has not been the subject of consideration and exploration at the proof, and of which the opposing party has had no notice whatever. The result, and the inevitable result, of what the Lord Ordinary has done in this case is that the judgment which he has given in the pursuer's favour is quite indefensible and must be recalled."
[58] In our view, if, following a legal debate or
a proof, some matter, whether it be an authority not relied upon, or some issue
not the subject of any submissions before him, occurs to a judge to be material
to his decision, the proper course would be, before giving judgment, to put the
case out By Order, explaining to the parties why he has taken that course and
affording to them the opportunity to make any motion, or present any
submission, to him on the topic in question before he reaches his conclusions
and delivers judgment. That is a course which could and should have been
followed in the present case, if the commercial judge considered that it was
necessary to enter into consideration of the possibility of the implication of
a term in the contract between the parties.
[59] In the light of what we have said regarding
the matter of the term implied by the commercial judge, the question arises of
how the course of action followed by him affects the decision under review.
The answer to that issue must depend upon the bearing that his conclusion as to
the existence of the implied term has had upon his decision in the case. In Kay's
Tutor v Ayrshire & Arran Health Board, the Lord President
considered that the consequence of the Lord Ordinary having devised a
ground of decision in favour of one party, of which the opposing party had no
notice whatever, was that the judgment given in the pursuer's favour was "quite
indefensible and must be recalled". In that case the effect of the conclusion
that the Lord Ordinary reached on the matter of his own devising was very
clear. However, in the present case, in which the circumstances are different,
it is necessary to consider what impact the commercial judge's conclusion about
the implication of the term of his own devising may have had upon his decision
overall. In our opinion, having reached the view that a term with the content
described in paragraph [24] of his Opinion was to be implied in the
contract between the parties, that must inevitably have coloured his approach
to the e-mail of 4 March 2004. As we have held, that e-mail properly fell
to be considered against a background of contractual uncertainty as to
responsibility for the kind of problems in extrusion that were under
consideration at the time. The commercial judge, however, bears to have
approached the question of interpretation in a different way and, in
particular, on the footing that a term of the kind he describes was to be
implied in the contract. For that reason we are driven to conclude that, on
this ground also, his conclusion as to the interpretation of the e-mail of 4 March 2004 cannot stand.
[60] Before parting with this aspect of the case,
we should record that it was tentatively submitted that the respondents had
made averments which could justify the course which the commercial judge took.
In that connection, our attention was drawn to the averments at page 31B-D of
the reclaiming print, appearing in Statement 4 for the respondents in
their counterclaim. Looking at those averments, we cannot conclude that they
give fair notice of a contention by the respondents that an implied term of the
kind devised by the commercial judge was to be seen as part of the contract
between the parties. It would appear from the manner in which the second preliminary
proof was conducted that those averments were not, in any event, understood in
that way.
[61] For all of these reasons we consider that
the commercial judge's findings 1, 3 and 4, which appear in paragraph [36] of
his Opinion are erroneous; Finding 2 may be seen as correct, but
ultimately irrelevant. Thus we consider that the interlocutors of 3 and 10 July 2009 must be recalled and the
case remitted to him to proceed as accords.
[62] We recall that a secondary motion was made
to us, upon the basis that the reclaimers' primary motion was not to be acceded
to, to the effect that the cause might be remitted to a different commercial
judge to consider the issue of the implied term de novo in the light of
further pleadings, evidence and argument upon that topic. In view of the
conclusion which we have reached upon the reclaimers' primary motion, it is
unnecessary to express any view upon that. However, we would simply say that,
having regard to the ample opportunity previously available to both parties, if
so advised, to raise the issue of an implied term, we do not consider that such
a course would have been appropriate. In our view the remaining stages of this
litigation must now proceed upon the basis of the conclusions we have reached
in relation to the e-mails of 4 March and 22 March 2004. In accordance with the
suggestion made to us by the solicitor advocate for the reclaimers, we shall
order that a By Order roll hearing should now be held for the purpose of
settling the form of the interlocutor to be pronounced.
[63] Finally, I would wish to express my
appreciation for the assistance which other members of the court have given to
me in the preparation of this Opinion.