OUTER HOUSE, COURT OF SESSION
|
|
XA26/08
|
[2009]
CSOH
OPINION OF LADY STACEY
in the cause
Appeal
under the Town and Country Planning Act
by
SCOTTISH BORDERS COUNCIL
Pursuer;
against
THE SCOTTISH MINISTERS
Defender:
ญญญญญญญญญญญญญญญญญ________________
|
Act: J D Campbell Q.C. City of Edinburgh Council, for Scottish Borders Council
Alt: K Springham Scottish Government Legal Directorate
15 May 2009
Introduction
[1] This is
an appeal under the Town and Country Planning (Scotland) Act 20071997 ('the
2007 Act') by Scottish Borders Council ('the council')
against a decision by Mr Philip
G Hutchison, a Reporter appointed by Scottish Ministers ('the
reporter'), to allow a planning appeal by Dr PH Campbell against the refusal by the
council of his application for outline planning permission. The site
address is land adjacent to
Borthwick Hall Lodge, Heriot EH38 5YE. The
application was dated 17 April
2007 and was refused by the
council on 20 August
2007. The reporter decided
the appeal on written submissions by letter dated 22 January 2008.
[2] Mr Campbell
opening
the appeal for the council explained that for Borders Council (hereinafter
'the Council') submitted that the cCouncil
challenged the decision of thea reporter on
appeal to grant outline planning permission.about a
developer contribution in regard to the Waverley Railway. The case
arose out of an application by Dr Peter Campbell permission forThere is
an interested party, Dr Campbell, had who entered
the process and had withdraewn, but
was present in court. . He is no
longer part of the proceedings although he is in court.
Mr Campbell
explained the process by saying that a planning officer will
collate papers and will prepare a report for members. Appeals lie in the hands
of disappointed applicants but not for councils or third parties. In this case tThe
cCouncil
refused the application for the reasons set out and the
applicant (Dr Campbell) appealedin the notification of
refusal by the council to Dr Campbell
dated 20 August
2007 and produced by the Scottish Ministers as 7/7
of process, thus:-
"'The application
fails to comply with Policy G6 of the Finalised
Local Plan 2005 in that no financial contribution towards the reinstatement of the
Waverley Line, as required by the policy, is forthcoming."'
Background
[3] The application had an unfortunate history which is referred to by the reporter. It has no relevance to the decision of the reporter nor of the court and it is mentioned only for completeness. The applicant did not know that his application was to be decided by the committee on the day on which it was decided, as he was in discussion with the legal department of the council on the necessity of his making a developer contribution, and understood that that question would be resolved before the committee was asked to decide on his application. That did not happen and instead the council sent the application for consideration stating that the applicant had refused to pay a contribution.
[4] The Waverley Railway (Scotland) Act 2006 ('the 2006 Act') provides for the raising of contributions to the cost by local authorities. Section 39 enables the council to require developer contributions from those who seek planning permission. The section is in the following terms.
"'(1)
Section 75 of the 1997 Act, section 69 of the Local Government (Scotland) Act
1973 (c.65) and Part 3 of the Local Government in Scotland Act 2003 (asp 1)
shall, in their application to the relevant planning authorities have effect in
accordance with following provisions of this section.
(2) Subject to subsections (5) to (8) below a relevant planning agreement may include provisions relating to or to development supporting or otherwise connected with the authorised works.
(3) A relevant planning authority shall not be precluded from entering into a relevant planning agreement which includes provision relating to, or to development supporting, or otherwise connected with, the authorised works by reason only of the fact that all or some of the authorised works are located outwith the local government area of the planning authority concerned.
(4) subject to subsections (5) to (8) below, in any relevant planning agreement made pursuant to this section financial provisions relating to the authorised works may require the payment of developer contributions towards the cost of providing the authorised works or any development relating to supporting to otherwise connected with the authorised works.
(5) The developer contributions obtained by the relevant planning authorities towards the cost of providing the authorised works shall not in aggregate exceed the total of the sums necessary for the purpose of providing the authorised works.
(6) No developer contribution under subsection (4) above shall be required more than 30 years after the opening of the railway works for public use.
(7) For the purposes of this section and section 40 below the sums necessary for the purpose of providing the authorised works include all sums from time to time payable for that purpose, and (without prejudice that generality) include interest payments loan charges and sums payable under or in consequence of any financial support contract.
(8) Accordingly, developer contributions may be required at any time during the currency of a loan agreement or a financial support contract.
(9) A requirement for developer contribution does not amount to the raising of money by making a levy or imposition within the meaning of section 22 (7) of the Local Government in Scotland Act 2003 (asp1)."
Thus the council is enabled by the 2006 Act to enter into planning agreements which require developers to pay a sum of money towards the cost of the railway.
[5] The council adopted policy G5 in relation to developer contributions generally and Policy G6 in relation to developer contributions related to railway reinstatement. Each is printed in 7/8 of process as part of the papers prepared by the planning officer for the committee which was asked to decide on the application. Policy G5 is in the following terms:-
"POLICY G5 DEVELOPER CONTRIBUTIONS
'Where a site is otherwise acceptable
but cannot proceed due to deficiencies in
infrastructure and services or to environmental impacts,
any or all of which will be created
or exacerbated as a result of the development ,
the Council will require developers to make a full or part contribution through
s.75 or alternative legal Agreements towards
the cost of addressing such deficiencies.
Each application will be addressed to determine the appropriate level of contribution guided by: the requirements identified in the Council's Supplementary Planning guidance on developer contributions: planning or development briefs; outputs from community or agency liaison; information in settlement profiles; other research and studies such as Transport Assessments; the cumulative impact of development in a locality; provisions of Circular 12/96 in respect of the relationship of the contribution in scale and kind to the development.
Contributions may be required for one or more of the following:
1. Treatment of surface or foul waste water in accordance with the Plan's policies or preferred methods (including SUDS maintenance)
2. Provision of schools, school extensions or associated facilities all in accordance with current educational capacity estimates and schedule of contributions;
3. Off site transport infra structure including new roads or road improvements Safer Routes to School, road safety measures, cycleway and other access routes subsidy to public transport operators; all in accordance with the Council's standards and any Green Travel Plan.
4. Leisure, sport, recreation play areas and community facilities either on site or off site;
5. Landscape, open space, trees and woodlands including cost of future management and maintenance;
6. Protection, enhancement and promotion of environmental assets either on site or off site having regard to the Local Biodiversity Action Plan and the Council's Supplementary Planning Guidance on Biodiversity, including compensation for any losses and /or alternative provision;
7. Provision of other facilities and
equipment for the satisfactory completion of the
development that may include:
measures to minimise the risk of
crime; provision for
storage collection and recycling of
waste, including communal facilities and
provision of street furniture."
Policy G6 is in the following terms:-
"POLICY G6 DEVELOPER CONTRIBUTIONS RELATED TO RAILWAY REINSTATEMENT
In accordance with provisions of the Waverley Railway (Scotland) Bill 2003, the Council will seek developer contributions towards the cost of providing the Waverley rail link from many developments that may be considered to benefit from, or be enhanced by, the re-instatement of the rail link. The post codes affected and level of contribution sought will be in accordance with council decision of 5 October 2004 or from any subsequent Council decision during the Local Plan period.
Justification
The policy is specifically geared to seeking developer contributions towards the cost of the Waverley Railway in post code sectors where new housing development is considered to benefit from or be enhanced by the rail link. In turn this policy will assist in providing funding for the railway which will provide considerable social economic and environmental benefits to the area.
The approach to developer contributions in these special circumstances is set out in the Waverley Railway (Scotland) Bill 2003. It is acknowledged that this policy represents a change in the way that the existing Section 75 regime operates.
The Bill provides for a rail link between Edinburgh and Central Borders. The postcode sectors affected by this policy are therefore concentrated in the Housing Market areas in the Central Borders and North and South Roxburgh. In the longer term, the aim is to achieve a rail link through to Carlisle as provided for in the Structure Plan ands the route is safeguarded in both plans.
At the time of
writing the Bill is still proceeding through
the Parliamentary process and subsequent events
may alter the provisions of thus policy."
The council decided in 2004
on a list of post codes which were areas which would benefit from the reinstatement of the
railway line; applications for planning permission for
sites in those post codes would therefore be asked to pay a contribution. The
council's Director of Planning and Economic Development
reported to the council's
Executive Committee on 17 October 2006 on the subject of Waverley Project Developer Contributions. His
report was produced to the
committee when considering Dr Campbell's application, and
was available to the reporter. It is produced in 7/8 of
process. As I understood it both
parties were content to proceed on the
basis that the Executive
Committee had resolved to act as
recommended in the
report. The
report advises that the Waverley Railway (Scotland) Act 2006 has
received Royal assent. A requirement to provide
a station at Stow was included in the
act, though not in the bill in 2004. The report is to the
effect that it is thought appropriate to extend
the area within which developer contributions should be
sought to include the North Ettrick and Lauderdale Housing Market area. A list of post
codes is provided. The post code of the application site is in the
list.
Consideration of the application by the council
[6] In the submission by the planning officer of the council to the committee which considered the application there is no adverse comment except in relation to compliance with policy G6. The planning officer stated that the application was located within a post code sector identified in the supplementary planning guidance revised in 2006 to take account of the benefits to be derived from the additional station proposed at Stow. The officer summarised the objections raised by the applicant thus:-
ท The development would not benefit since the line would make access to the bus stop more difficult.
ท The new road and bridge required to cross the line would increase traffic speeds and be detrimental to road safety.
ท The rail link will not provide an enhanced public transport service to Edinburgh since the bus service is as quick and more accessible.
ท
Prices in the
area will be depressed relative eto the
central Borders where properties will benefit from the
rail link.
ท Other post code sectors that will derive benefits will not have to pay a contribution.
He then set out his reasons for recommending refusal thus:-
"'Planning authorities are
advised that planning agreements related to the payment of
contributions towards off site infrastructure must be
clearly related to the
development and the extent of
contribution required should relate in scale and kind. This
approach was followed when the supplementary guidance was originally
formulated, and extended in 2006, whereby it covers
postcode areas which are considered to
benefit from the provision of
a rail service to the Borders,
and the development of a station
at Stow. It is considered that the
extent to which the catchment area approach should
be challenged is a matter to be considered when reviewing the
policy, as opposed to varying the approach
on a case by case basis. It is considered that
the policy applies to this development
since the benefits
to be derived form the rail
link directly relate to the catchment area within
which the development is
located and that the contentions raised by the
applicant are not sufficient for the contribution to be
waived in this case.
On the basis that the applicant is not willing
to pay the contribution, the application
therefore fails to comply with Policy G6 of the Finalised Local
Plan and. accordingly, is
recommend for refusal."'
Consideration by the reporter of the appeal.
[7] The papers on which the reporter decided the appeal included the paper prepared by the planning officer quoted above. The reporter's decision was to grant the appeal. In his decision letter at paragraph 4 he stated that the appeal turned on whether policy G6 should be applied to the appeal. In paragraph 6 the reporter found that the application fell within the geographical scope of policy G6, as revised by a council decision of October 2006, and that the application was at odds with the requirement of the policy.
[8] The
reporter went on in paragraph 7 of his decision letter to
consider whether the developer contribution
was justified. He
noted that the
appellant had put forward a compelling argument that it
was not justified, but that the council had restricted itself to a
statement without any amplification or reasoned arguments that "'the
benefits to be derived from the rail link apply to this site, given that it
would benefit from a significantly enhanced public transport service....based
on the provision of a station at Stow." ' The
reporter found that the written submissions from Dr Campbell:
"'showed
very clearly that occupiers of the development would
be extremely unlikely to use or benefit from the reopened Waverley line (and Stow station
in particular). To access the station at
Stow (the addition of which
drew the above post code sector within
the scope of policy G6) occupiers would have to travel
3 km into Heriot and another
12 km to the south
by the A7 (T)-unless they use a
narrow twisty road for a similar distance on the
south bank of the Gala Water. The
station at Gorebridge would be a
good 2 km closer and of incomparably greater
appeal for anyone travelling to and from Edinburgh. Travel to and from Galashiels would present no real
incentive to park at Stow when another 11 km of uncongested A7(T) would take
travellers right into Galashiels. I do
not need to rely on speculation that the bus
services on the A7 (T) may well be less
attractive when the railway reopens."'
[9] In
paragraph 8 the reporter found in favour of the arguments put up
by Dr Campbell that
there would be no benefit to the proposed development from the
authorised works. He found
that a
developer contribution under policy G6 could not reasonably be
demanded in view of the site's particular geographical context. The
reporter referred to the circular 12/1996 "'Planning
Agreements"' and in
particular paragraphs 12 and 13. He found
that planning agreements had to be
reasonable and that there must be a connection between the proposed
development and the payments sought from the developers. If this
related to public transport then
the benefit must not be too remote. He
concluded that the connection between the
site and the rail link and Stow station
was too remote. There was no reason to
refuse the permission other than that
the contribution had not been paid. Thus the reporter
found that the contribution should not have been requested, and granted the
permission subject to
certain conditions which
are not relevant to this appeal.
on a single ground that he had not been willing to
pay approximately ฃ1700 in respect of a contribution to the railway. The case
went to the Reporters Unit byand Mr Hutchison decided
the appeal on written submissions. The application was made
on 24 April 2007 and refused on 20 August 2007. The Reporter allowed the
appeal and issued his letter on 22 January 2008. That
letter is appended to the appeal documents.
Mr
Campbell went to statement 4 and outlines how that
sets out a scheme for developer contributions. The
Waverley Railway has long been an aspiration of local authority and government
and they have now passed the Waverley Railway
(Scotland) Act 2006 and that Act provides
for the raising of contributions by local authorities. Section 39 of it enables
the Borders Council to require
developer contributions from developers. Governmentandauthoritiesenteringdevelopment
supporting or otherwise connected with the authorised works by
reason only of the fact that all or some of the authorised works are
located outwith the local government area of the planning authority concerned.
(4)
subject to subsections (5) to (8) below, in any
relevant planning agreement made
pursuant to this section
financial provisions relating to the
authorised works may
require the payment of
developer contributions towards the cost of providing
the authorised works or nay development relating to supporting
to otherwise connected with
the authorised works.
(5) The developer contributions
obtained by the relevant planning auhtoriites towards the cos tof providing the
authorised works shall no tin aggregate exceed the total of ht esums necessary for ht epurpose
of providing h teauhtorised works.
(6) No
developer contribution under subsection (4) above shall be required more than
30 years after the opening of the railway
works for public use.
(7) For the purposes of this section
and section 40 below the sums necessary for the purpose of
providing the authorised works
include all sums from time to time payable for that purpose, and
(without prejudice that generality)
include interest
payments loan charges and sums payable
under or in consequence of any financial support
contract.
(8)
Accordingly, developer contributions may be required at any time during the currency
of a loan agreement or a financial support
contract.
(9) A requirement fro
developer contribution doe snot amount to the raising of money by making a levy or imposition within
the meaning of section 22 (7)
of the Local Government in Scotland Act 2003 (asp1).
Thus the Council
is enabled by the act to enter into planning
agreements which require developer to pay a sum of money towards the cost of
the railway. Th eocuncil decided
to require such contributions as set out in their policy G6. Th policy provides
that the council 'will seek developer contributions towards
the cost of providing the Waverley rail link from any developments that
may be considered to benefit from or
be enhanced by there instatement
of the rail link.
There follows a list of post codes which are said to be those in
which development is expected to benefit from or
be enhanced by the rail link. This was
revised in October 2006
and the post
code in which the
development for which Dr. Campbell made
application is included in the list .
Submissions on behalf of the council
The
areas within which such contributions can be sought are delineated by post
codes. It came into force in 2004 as is set out in statement 5.
In 2006 the Council
resolved to extend the catchment area to get additional contributions from and
after October 2006. These resolutions got into the local plan, which is part of
the statutory development plan. For this see section 25 of the Town and
Country Planning Act 1997.[10] Mr
Campbell submitted that the policy of the Council was that any development
within the listed post codes was subject to the
requirement of a contribution, because the council had
decided that areas within
these postcodes would
benefit from or be enhanced by the building
of the railway. This he
said was a decision that the council was
entitled to take; and was a decision with which
the reporter was not entitled to interfere. As a
fall back position he argued that if the reporter
was entitled to look
at the policy as it affected
the individual application then he had
failed to do so
properly. When this matter came to the Reporter it can be
seen that the decision letter in paragraph 1 is an echo of section 25. All
that can be identified from the papers is in Policy H5. In paragraph 3 the Reporter
focuses on Policy G6 being his reason for refusal. He sets out the decision of
2004 translated to the local plan. The areas are those expected to benefit or
to be enhanced by the existence of the railway. The Reporter is correct when
he says that G6 is not likely to change. In paragraphs 5 and 6 it is stated
correctly that the Council perceived that this developer contribution was
resisted. The Reporter says "I concluded it fell within G6".
In paragraph 7 however he goes on to discuss whether or not the development
contribution is justified. At paragraph 8 he gives his conclusions. The
Council take issue with his giving his view in paragraph 8. Thus Mr Campbell
argued that G6The
Council say that this is a
provision of compulsory application. The Council's position on
fallback, is that Iif it is not compulsory,
in any event, the Reporter did has not taken
into account all matters and has reached a decision by an
erroneous exercise of his discretion. So thHe
summarised
the Council's position can be summed up in
the following way:
"1.
The
reporter had acted His action is ultra vires or
2. The reporter had exercised
his His discretion has been exercised wrongly."
One can see from statement
5 that the Reporter was made aware of the appellant's stance. See section 69
of the Act. The minutes were not before the Reporter but Miss Springham
does not say that they were not adopted and he does not understand this to be
in dispute. The material which the Reporter either had or ought to have had
was section 25 of the 1997 Act, the 2000 Act in
particular, section 39. In paragraph 8 of the appeal it can be seen that K5
requires contributions and G6 requires contributions for the rail link from
this postcode area. Mr Campbell's argument was that if the Ministers do
not like the policy they should review it but should not vary on a case by case
basis.
[11] Mr Campbell referred to the
material before the reporter in the paper
prepared for the committee. On
looking at the papers prepared by Mr Clarke, the
council planning officer, he can agreed,
without
conceding, that there is some
appearance of the planning officer
weighing up the points made by the applicant rather than simply submitting that
the application of the post code is
decisive. He argued however that the
officer made plain that the
policy should
be applied, as G6 was
designed to recognise benefit to the
community. It was
not appropriate to reconsider the matter application
by application. Mr Clarke is undertaking a balancing
exercise. He does say however that Mr Clark takes the view that this is a
compulsory application.
Mr Campbell went on
to explain that there was discussion in Parliament about the provision of a
station at Stow.
[12] OOn
his esto case, Mr Campbell said
that Dr Campbell
submitted at length that the proposed development would
get no benefit from the railway didn't get any benefit at
all. The application of G6 is however designed to
benefit the community area by area and it is not appropriate to look at it
application by application. If however Tthe
rReporter
agreed,
but was entitled to do this he failed to consider
all relevant matters.do so properly with
balance. In paragraph 7 of the decision letter the rReporter
said that he looked at the council report of 2004, the council report
of October 2006 and the local plan. He did not does not
say that he looked at the enabling legislation. The
reporter He said that Dr Campbellthe
appellant hads shown that the occupiers
of
the proposed development would be extremely unlikely to use the
station at Stow for the reasons given, being that it is 15 kilometres to the
south, and so hardly likely to be
attractive if one wished to travel north; it was not
attractive for those wishing to travel south either, due to
the necessity of getting there by
car before being able to use the railway. The
reporter did find that the station at . Note
that he makes reference to the station at Gorebridge might
be more attractive. . This
is also a new station and note that this may be relevant.
Mr Campbell
went on to submit that if the language of G6
admits of a discretiondiscretion
there are matters features of increased rail
travel which the rReporter
should have consideredtaken into account.
He
should have taken account of the reduction of road
traffic and pollution by cars; the benefits to the
area generally of
having good public transport; the benefits to society from
the encouragement of rail travel; the fact that the council had
promulgated a policy after consideration; and the benefits of transparency
given that applicants knew in advance eif
they
development they proposed was in the post code listed. All
that the reporter did
was to
consider give distances; he and did
not give any proper consideration to the bigger picture. If the
reporter did give proper consideration to all that he should have considered
then he did no t give reasons
for his decdision which
showed what he made of it all. Thus he
did not fulfil the ht erequirenments
of decision making
as set out in the case of Wordie Properties v Secretary of State
1984 SLT 345discussion about whether
or not there would be an advantage.
[13] Mr Campbell 's
position was that he would moved me invite
me tto quash the decision. which
would mean that it would be remitted back to the directorate and heard again by
the Reporters Unit
.
Miss Springham said that her first
submission was on the general sense of approach under section 239
of the 1997 Act. She would then look at the decision of the Reporter and
thirdly would look at the grounds of challengSubmissions for Scottish
Ministerse in the document put up by the Council.
[14] Miss Springham
directed my attention to the
Scottish Planning Encyclopaedia, ed. Gill, at pages B261
to B264. She submitted that the grounds
of challenge of the reporter's decision were
those provided by the act in s.239 (1) (b)as interpreted in the case
of Seddon Properties v Secretary of State for
the Environment (1981) 42 P.&C.R 26 and conveniently set out at the
foot of page 261 into 262. went to
the Planning Encyclopaedia and looked at the foot of page B261 and the case of Seddon. She
referred to the
case of City of Edinburgh Council v
Secretary of State for Scotland 1998 SC (HL) 33 and to Lord Clyde's
speech at page 44 and 45 for the
proposition that the
decision maker in a planning application has to decide what weight he puts
upon the material before him and
assess it all; matters of planning judgment are for
the local planning authority and the Secretary of State, but not for the courts; and if a decision maker
fails to take account of some material consideration or
takes account if some
consideration which is irrelevant then his decision
will be open to challenge, on the basis that it is irrational or
perverse.
directed my attention towards tab 5 on the original
list of authorities for the Scottish Ministers and asked me to look at Lord
Clyde at page 44. He was looking at section 18A of the previous Act which is
now section 25 of the 1997 Act. He said at page 45 that a decision had to be
irrational or perverse before it should be quashed.
[15] Miss Springham
submitted that She said that in this case there were
two key issues. The development plan did not include G6. It had
not been finalised at the time. She said that the Reporter
had been asked to look at whether or not there would be any benefit to the
subjects by the station at Stow. She referred to the
papers which had been before the reporter, which
were those before the committee and a
document entitled "'Response to
Grounds of Appeal"' from the
council and now produced as 7/3 of process. The
latter document clearly showed, she submitted, that
the council considered whether said
that the other document was what the Council submitted and is now at 7/3 and
that Dr Campbell may have thought that he was appealing against the
decision of the Council. She said that paragraphs 2 and 3 show that the
Council looked to see if the objections put up by the applicant warranted
a departure from the policy. So Thus the
reporter had been asked to look at whether or not there would be any benefit to
the subjects by the station at Stow. Ttherehe council
had always was an acceptedance by
the Council of the that question of
whether the particular site would benefit was to
be discussed and decided, and so that question was open to the reporter. She submitted that and that
was open to the Reporter. She said that you can also see that from the report
of the Committee at 7/8. t The
correct way to read the policy is that in to
consider every case it must considered whether
there is a benefit to or an enhancement of the site which is the subject of the
application. T. She
said that the postcode simply defines the geographical scope position
and one then has to consider whether there are benefits or not.
She argued
that said that if one looks at the 2006 Act
it
makes it plain that that interpretation is correct. In section 38
of that Act the words "relevant planning agreement" are defined as meaning an
agreement entered into by a planning authority under section 75 of the 1997 Act
in connection with land on which any development can be
expected to benefit from or be enhanced by the
provision of the authorised works. She argued
that the definition there given when read with section 39(2) of the
2006 Act showed that each application had
to be such as to benefit and that that
was a question of fact to be
decided each time. Thus she
argued the reporter had done in this case what he was
obliged to do and what the parties
had invited him to do. that you have to look at
the actual land. This can be seen also from section 39(2). There is then a
question of fact for everyone. That is why the Reporter
considered facts in each case. He did so because the parties asked him to and
that is what he is required to do.
[16] Miss Springham
said that the rReporter's
letter at paragraph 8 referred to the circular which sets out in summary the
proper use of planning agreements. She referred to paragraph 12 and paragraph
13 and she noted that there was no challenge in the appeal by the council to document
to the rReporter
taking this into account.
[17] The reporter had
competing submissions about whether there was any benefit to the development
and so he was being asked to
decide that. The Council did not argue that the Reporter must apply the
policy. Miss Springham's submission was that on a
plain reading of G6 a contribution was justified and required only if a
proposed development would benefit from, or be enhanced
by, the railway. This was,
she said, consistent with 7/3 of the productions and was in 7/8. It was also
consistent with the definition of relevant planning agreement. The reporter
had dealt with the question properly on that basis.
[18] Miss Springham
argued that in terms of
section 37 of the 1997 Act that the
planning authority in dealing with an application had to
have regard to the provisions of the
development plan so far as relevant to the
application and to any other material
considerations. She argued that the existence
of policy G6 was a "'material
consideration"'
to which the planning authority and the reporter
on appeal should give due weight,
but that it was not determinative of an
application . She argued that
the reporter did
give due weight
to the existence of the policy. She then submitted on the
grounds of challenge the following:-
1. The Reporter had no
discretion because policy was mandatory according to the Council and that meant
that if a particular area was in a particular postcode a contribution would be
required. The Scottish Ministers in contrast said that G6 was
a material consideration and so it was a matter for the Reporter to determine
assessment of that and what weight would apply to it. Mr Campbell's second argument
could only succeed if it was argued successfully that the decision was perverse
or irrational on the part of the Reporter. There
was no such argument in the grounds of appeal.thing
about this in the grounds of appeal. Nor was there any argument
that no reasonable reporter would have come to this view. Therefore
Miss Springham's submission was that on a plain reading of G6 a
contribution is only justified and required if a proposed development will be
benefited or enhanced by the railway. This was, she said, consistent with 7/3
of the productions and was in 7/8. It was also consistent with the definition
of relevant planning agreement.
[19]
2. The Reporter
had competing submissions about whether there was any benefit to the
development and they were asking the Reporter to decide that. It is
not correct to say that the Council told the
Reporter that he must apply the policy.
The parties were asking the
Reporter to consider the issue of benefit and that is what he did. It is not
for this Court to go into the planning merits so if it was
accepted that the Reporter was entitled to look at them because he is to use
his planning knowledge then this Court cannot contradict him.
3. Mr Campbell
had argued that the reporter had failed take
account of the matters set out in paragraph 10 of his pleadings,
but these matters were not put before the reporter. The cCouncil
had had its opportunity to place before the reporter such material as it chose.
The
only material additional to that tin the report paper
pout
up to the planning committee was the response to grounds of appeal, 7/3 of
process, in which paragraph 3 raised very briefly the assertions that the site
would benefit from significantly enhanced public transport, and that
application of the post code approach allows for an appropriate means of applying
the policy consistently across areas likely to benefit in a transparent and
clear manner before applicants make their application. The council had
not argued as Mr Campbell now argued that the benefits set out in the pleadings
would apply to the site.
[20] Miss Springham
argued that a reporter was not obliged in
giving his reasons to refer to
every submission made to him. She
reminded me that the reporter was required to make a decision and that
his decision on planning matters should not be disturbed by the court. She
referred to the cases of Tesco v Secretary of State 1995
1W.L.R. 759 and Moray
Ccouncil v Scottish Ministers 2006 S.C.
691. In the
present case, t 4..The
rReporter
had
not said, as was averred in the council's pleadings, did not
say that a contribution could not be made but rather that on the
facts of it it was not warranted. and that is why he used
the word "reasonable". He found
that it was not reasonable seek a contribution. As I
understood her argument, she submitted
that the court should not substitute its own
judgment for that
of the reporter.
[21] Miss Springham
argued that the appeal should be refused.
Reply on behalf of the council.
[22] In
reply Mr Campbell submitted aid that in a
planning appeal there are only two grounds in section 239 of the 1997 Act, being
an excess of power and procedural impropriety. In this
case He said that we are in the ultra vires territory
and he argued that the a decision
taken
by the reporter was which was taken which
involved considering something which should not have been considered or
leaving out something which should have been considered as ultra
vires. Therefore Miss Springham says that one must
say that it is irrational; one does not need to say that one can simply say
that it is ultra vires. He accepted that the Moray
District Council case showed that the court one should was not
to
substitute its ones own discretion decision
on planning matters for that of the inspector. He accepted also
that it was not incumbent on the rReporter
to look
at everything or to mention all that was put before him in his
decision. . He argued
that relevant facts in
owever in this case he said
that the chain starteds
in 2004 with 7/15 of process at paragraph 2.2 wherewhen the
council resolved that it says that
contributions would ill be
sought and that in saying so deciding the
cCouncil
was setting out a compulsory template. This is reinforced by the resolution
passed in 2006 activities. G6 has made that clear
although he accepted it could be read either way. It was clear
that the council did not intend that each
application lying within the listed
post code areas would be decided by examining each
one afresh.However deciding things house by house does not sit
well with a list of postcode areas. As regards to the planning
circular on which the reporter relied, Mr Campbell
argued that he said that it was ten years old and that the
rReporter
had to take it into account rather than be bound by it. He referred to Looking
at paragraph 4 of the circular which he would argued
showed
that that there may be benefit for the
greater good of society may be considered. .
He
argued that In paragraph 12 gave these
are just examples of questions which could be asked. . Mr Campbell
submitted that Thethe issue
"'staring
the
court in the face"' was is whether
the reporter was can he be right to place such relevance
on the
a 1996 circular? He submitted that there
were three points to make.There are three points to
be made. OneFirstly, the
reporter was correct to consider correct to consider
the
circularit. Secondly he was correct to
apply aTwo correct to apply a test of
reasonableness, but in so
doing he should have considered the council's
decision to promulgate the but must consider the
October meeting making the policy decision now known
as G6 and their desire to designate certain post code
areas being areas which the council considered would
benefit. and t Thirdly
the reporter erred in the way in which he applied ree, wrong
to apply paragraph 13. The reporter There gave no was no analysis
of what was considered too remote.
After a short
reply in which Miss Springham repeated most of what she had said already
and both counsel made reference to the case of Tesco v The Secretary
of State 1995 1 Weekly Law Reports 759.
Discussion
[23] In my opinion
the reporter was entitled to consider whether the application for
planning permission was for a development which would
benefit from the re instatement of the railway.
I did not accept Mr Campbell's
argument that the reporter was obliged simply to accept the council's decision
on that matter, and that the only way to argue against such a
policy was by an action to reduce it. In terms
of the 1997 Act the reporter appointed by the Secretary
of State has
power to allow or dismiss the appeal or reverse or vary any part of the
decision of the planning authority and may deal
with the application as if it had been made to
him in the first instance. Thus the
reporter is bound in determining an
appeal to have regard to the provisions of the development plan, so far as
material to the
application, and to any
other material considerations. Policy G6 is a
material consideration to which he has to have regard. In doing
so he is in my opinion entitled to
consider whether the condition which
the council seek to put on the grant of
planning permission is justified given the geographical
relationship between the site and the route of the Waverley rail
link. Therefore I do no t accept
Mr Campbell's
primary argument that the reporter acted ultra vires by
considering the merits of the condition sought by the council.
[24] Further,
in the circumstances of this case, I agree
with Miss Springham that
the papers before
the reporter do indicate that the parties appeared to ask
the reporter to
consider the merits of the condition. In the papers
submitted by the council to the reporter there is no clear submission
that the policy cannot be questioned. In the
paper prepared for planning committee (on pages 7 and 8) the council
state as follows:-
"'Planning
authorities are advised that planning agreements related to the payment of contributions
towards off site infrastructure must be clearly related to the development
and the extent of
contribution required should relate in scale and kind. This
approach was followed when the supplementary guidance was
originally formulated, and
extended in 2006, whereby
it covers cupost coade
areas which are considered to benefit from
the provision of a rail service to the
Borders, and the development of a
station at Stow. It is considered that the extent
to which the catchment area approach should be challenged is a
matter to ber considered when
reviewing the policy, as
opposed to varying the approach
on a case by
case basis. It is considered that the policy
applies to this development since the benefits to be derived from the rail link directly relate to the catchment area
within which the development is located,
and that the contentions raised
by the applicant are not
sufficient for the contribution to be waived in this
case."'
[25] That submission asserts that the policy should not be varied on a case by case basis, but also asserts that the contentions made by the applicant are insufficient to waive the policy in this case. Thus the council appear to concede that case by case variation is competent and that the argument for such a variation has been considered by them and rejected on the merits. The council does not clearly and unequivocally assert that the policy should always be followed, nor does it make such an assertion accompanied by a fall back position that if the merits are considered on a case by case basis then certain considerations apply. Rather it seem so me to make a confusing submission from which it can be seen that the reporter might well take the view that the council expected the case to be decided on the arguments particular to the merits of the proposed condition in this case.
[26] In the response to grounds of appeal by the council dated 24 09 07 the council stated that the committee which refused the application did so by considering whether the application warranted a departure from the policy, and asserted that that was the correct process. The council asserted that the site would benefit from a significantly enhanced public transport service. There is no specification of why it came to that view. It also asserted that the post code approach allows for an appropriate means of applying the policy consistently in a manner transparent and clear to applicants before they submit their application.
[27] In my
opinion the reporter was correct in
considering the merits and in doing so by considering the
arguments put before him. I am,
however, of the opinion that while
the reporter was correct to consider the merits of the imposition of the condition, he
failed to take into account all relevant matters, or if he took them into
account, that he failed in his decision letter
to show that he had
done so. It is
correct that the council gave little information whereas the applicant set out
his case at some length. Nonetheless
the reporter was advised that the council had considered the matter
and had adopted the policy. He does not
give any reason for apparently
ignoring that. The
reporter does not give any reason for his apparently ignoring the fact that the
G6
was introduced because the council formed the view that those
postcodes brought in by it related to sites which would benefit from the
reinstatement of the railway once it had been decided to include a station at
Stow. He does not deal with the
argument put up, albeit faintly, on behalf of the council
that the post code approach creates certainty and transparency. It is not
clear that the reporter dealt with the decision by acknowledging that
there was a policy and looking at the application to see
if its circumstances justified a
departure from that policy. The
reporter dealt with the matter as though
it were an agreement under section 75 of the 2007 Act, and he did not to refer to
the 2006 Act to put
the matter in context. There is
nothing in the reporter's decision letter which shows that he
considered the wider benefits which might be
thought to exist in
being part of an area which has good public transport, even if there are
arguments to indicate that those living
at the application
site might not
themselves use it. The
reporter referred to the station
at Gorebridge, which does not seem to
have been referred to by
either party and found that it would
be "'of incomparably
greater appeal for anyone travelling to and from Edinburgh."'
I understand that is a reference to a
station to be provided on the Waverley line,
and therefore a reference to a
benefit which may come from the reinstatement
of the railway. This has apparently been raised by the
reporter rather than by
parties. The reporter does not explain his view
on that.
[28] I am of the
opinion that the reporter has not given reasons intelligible to
the informed reader which show that in considering the appeal
against council's decision that a
condition that a developer contribution be paid he considered all relevant
matters. Therefore I allow this appeal,
up holding the council's secondary
argument that the reporter has not shown by his
written reasons that he gave full consideration to all
relevant
matters.