OUTER HOUSE, COURT OF SESSION
[2008] CSOH 91
|
|
OPINION OF LORD BRACADALE
in the cause
LIGHTWAYS (CONTRACTORS)
LIMITED
Pursuer;
against
NORTH AYRSHIRE COUNCIL
Defender:
|
Pursuer:
Johnston, Q.C., Lindsay: Biggart Baillie
Defender: Bartos, Lindsays
20 June 2008
Introduction
[1] This case
came before me on a motion for an interim
order to suspend the implementation of the decision of the defender's Executive
Committee on 1 April 2008 to accept the tender submitted by Centre Great
(1991) Ltd ("Centre Great") for the lighting maintenance contract 2008/9 for
North Ayrshire ("the contract").
[2] The
contract was a public contract subject to the Public Contracts (Scotland) (Regulations) 2006 ("the
2006 Regulations"). These regulations
have their origin in European Directive 2004/18/EC. In terms of the Regulations the defender was
the contracting authority and the pursuer was an economic operator. The award of the contract was under the
restricted procedure in terms of regulation 16 and was on the basis of the
most economically advantageous tender in terms of regulation 30. There were three tenders. In accordance with the requirements of
regulation 32, notice was given to the pursuer of the award of the contract to
Centre Great. The pursuer made a request
under regulation 32(4) for reasons why the pursuer was unsuccessful and
thereafter two debriefing meetings were held.
The standstill period provided by regulation 32(3) was extended to 9 May 2008 on which date the case first called before me. I heard argument on that date and on
14 May and the defender undertook not to implement the decision of
1 April until I had issued my decision.
[3] The
pursuer claims that in awarding the contract to Centre Great the defender failed
to comply with the 2006 Regulations in four respects. First, there was a failure to treat the
tenderers equally during the tendering process.
Second, there was a failure to comply with the requirements as to the
criteria used to award the contract. Third,
in the scoring exercise there had been a failure to carry out an equal and
transparent assessment of the tenders.
Fourth, there had been a failure to comply with the provisions of
regulation 32 with respect to providing information at the debriefing meetings.
[4] Mr Johnston
Q.C., who appeared on behalf of the pursuer, submitted that in each of these
respects the pursuer had demonstrated a prima
facie case and that the balance of convenience favoured the making of the
order.
[5] Mr
Bartos, who appeared on behalf of the defender, first raised an issue as to
whether the pursuer had title and interest to seek the order, failing which he
moved me to refuse the motion for interim suspension. The pursuer had failed to demonstrate a prima facie case and, in any event, the
balance of convenience favoured the defender.
Title and interest to seek the order
[6] On
3 April 2008 the defender's
Assistant Chief Executive wrote to the pursuer purporting to disqualify the
pursuer from the tendering process. This
was on the basis that certain e-mails sent by the pursuer constituted
canvassing in breach of clause 17 of the Instructions to Tender. Mr Bartos contended that because the pursuer
was disqualified it had no title or interest to seek the order for interim suspension. However, the pursuer does conclude for
reduction of the decision to disqualify and Mr Johnston submitted that there
was a prima facie case that the
disqualification was illegal: the e-mails did not amount to canvassing; the
basis for the purported disqualification did not fall within the scope of the
2006 Regulations as to disqualification; and to disqualify on the basis of the
e-mails was disproportionate. In
addition, even if the disqualification was valid, the pursuer would still have
title and interest to seek the order because breaches by the defender prior to
the disqualification would lead to the contract going out to tender again.
[7] I
do not consider it necessary to go into this issue in any detail. I am satisfied that the pursuer has
demonstrated a prima facie case for reduction of the purported
disqualification and that is sufficient to found title and interest to seek the
interim order.
Failure to
treat the tenderers equally during the process
[8] The pursuer avers that the defender
failed to provide sufficient information to enable the pursuer to tender on an
equal footing with Centre Great.
There were two aspects to this complaint. The first related to information as to the
qualifications, training and experience of employees of Centre Great who
would be likely to transfer to a new contractor under the Transfer of
Undertakings (Protection of Employment) Regulations 2006 ("TUPE"). The second related to information about
planned maintenance.
[9] The
defender did provide the pursuer with information as to the rates of pay of
Centre Great employees, which were lower than the rates of pay paid by the
pursuer. The pursuer avers that it
required to know whether the employees of Centre Great would be suitably
qualified. If it had been aware that
they were so qualified the pursuer could have taken their lower rates of pay
into account in compiling the tender. As
it was, the pursuer had to assume that in order to get suitably qualified staff
it would require to pay its own, higher, rates.
Centre Great, on the other hand, as the incumbent contractor would know
all about the qualifications and experience of its employees. This information had been requested by the
pursuer but the defender had not provided it.
[10] In
relation to planned maintenance it is averred that the only information given
was the names of the towns in which maintenance was proposed in 2008/9. The pursuer had requested more detailed
information in relation to planned maintenance but that had not been forthcoming.
[11] Mr
Johnston submitted that by refusing to give this information which had
reasonably been requested under regulation 16(20) the defender had breached the
2006 Regulations with the result that it had failed to treat the economic
operators equally.
[12] Mr Bartos
pointed out that the pursuer could not know in any event how many employees of
Centre Great would in fact move under TUPE.
That itself was an imponderable in the formulation of the tender. In addition, he pointed out that it was a
reasonable assumption for the tenderer to make that the employees presently
doing the job were suitably qualified.
He also pointed out that the differentials of pay between Centre Great
and the pursuer were not very great.
[13] Regulation
4(3) provides that:
"A contracting authority
shall -
(a) treat economic operators equally and without discrimination;
and
(b) act in a transparent and proportionate manner."
Regulation 16(20) provides that the contracting
authority "shall supply such further information relating to the contract
documents as may be reasonably requested by an economic operator". The contract documents are defined in
regulation 2 as meaning,
"the invitation to tender
for or to negotiate a contract, the descriptive document (if any), the proposed
conditions of contract, the specifications or descriptions of the goods,
services, work or works required by the contracting authority and of the
materials or goods to be used in or for such work or works, and all documents
supplementary thereto."
[14] The importance
of the principle of equal treatment of tenderers for a public works contract is
stressed by the European Court of Justice in the case of SIAC Construction Ltd v County
Council of the County of Mayo [2001] 1 ECR 7725. At paragraph 34 it is stated:
"More precisely, tenderers
must be in a position of equality both when they formulate their tenders and
when those tenders are being assessed by the adjudicating authority."
(See also Aquatron
Marine v Strathclyde Fire Board
2007 CSOH185, Lord Carloway, unreported).
[15] As a
preliminary point Mr Bartos submitted that the information sought did not
relate to contract documents. It seemed
to me that the contention of Mr Johnston that a broad definition of
contract documents was the appropriate approach and that it would be relevant
to ask questions about employees who might transfer under TUPE and issues in
relation to planned maintenance.
[16] It is
necessary to look in a little detail at the factual picture which emerges from
the averments and the productions. On 13 January 2008, the pursuer sought confirmation from the defender
that the current work force who may transfer under TUPE had all the necessary
qualifications to work on the contract.
Reference was made to a number of specific qualifications and it was
assumed that the defender held these records as the current contract
required. The response of the defender
is found in Contract Bulletin No 3 (production 6/15) where the following
appears:
"Q3. Please confirm that staff subject to TUPE transfer have all
necessary qualifications to work on this contract.
A3. Information required under TUPE regulations will be provided to
tenderers when it becomes available."
It was confirmed at Answer 14 that the TUPE
regulations applied to both the current contract and the contract under tender
process.
[17] By
email sent on 5 February 2008 (production 6/30) the
pursuer again raised the issue of the qualifications of the staff to transfer
under TUPE and requested timeous supply of this information. In reply the defender stated "the Council
shall comply with the requirements of the Statutory Instrument 206/246, as
referred to in paragraph 66 of the Tender Document."
[18] In
Contract Bulletin No 5 (production 6/17) at Question 5 the issue of
the qualifications of the transferring employees was again raised and further
specific details identified. The reply
was that the defender had passed this request for more detailed information on
to the current contractor, who had already provided TUPE information. Any further information that would be
released by the current contractor would be issued to all tenderers.
[19] In
Contract Bulletin No 6 at Question 7 the issue of the
qualifications of the transferring employees was again revisited and the
defenders simply referred to earlier answers indicating that it had nothing to
add. Questions 9 and 10 referred to
the same issue.
[20] In
production 6/16, Contract Bulletin No. 4A, at Question 3, the pursuer
sought the record of the last three years for planned maintenance completed and
to be completed in order that it could supply a more accurate plan for the
planned maintenance within the contract.
In reply the defender identified the areas in which planned maintenance
had been carried out during the previous three years. It went on to state that planned maintenance
was proposed for the period 2008/2009 in a number of identified areas. No further detail was given.
[21] In
Contract Bulletin No 5 (production 6/17), the pursuer sought further
information in relation to planned maintenance.
Three questions were raised.
First, in order to create a detailed plan for planned maintenance the
pursuer sought more information than the names of the towns where maintenance
was intended. It requested specific
detailed information. It also sought
further detail in relation to section 4 of the Bill of Quantities. The pursuer raised a concern that as the
incumbent contractor had the information to hand it was possible that the
pursuer could be disadvantaged in the award process. In reply, the defender stated that detailed
inventory information was contained in the Council's database to which the
present and all previous contractors and tenderers had had no access. The defender advised that tenderers should
note that the approximate quantities requested were laid down in the Bill of
Quantities and these quantities should be used when preparing tender
submissions.
[22] In
Contract Bulletin No 6 the question of the information in relation to
planned maintenance was again raised at Question 1. In reply it was stated that the present
contractor did not have access to inventory information and had not been
requested to carry out planned works of any nature in the areas listed for
2008/2009. He was therefore no better
placed than any other tenderer in preparing a submission. It was added that it was intended to issue a
zip copy of the entire Council database inventory to tenderers. However, it was stated that submissions
should be made using the data provided with the contract document.
[23] In my
opinion, in relation to the question of the qualifications, experience and
training of employees, there was some force in the points made by
Mr Bartos. I also note that in
Contract Bulletin No 5 (production 6/17) at question 5 in
relation to the issue of qualification of employees, the defender indicated
that they were passing on the request for more detailed information to the
current contractor. Furthermore, in
relation to the request for further information about planned maintenance it appears
that all tenderers were in the same position.
It seems to me that on this aspect of the case the position of the
pursuer is weak. I have considerable
doubt as to whether it has raised a prima
facie case of inequality of treatment based on a failure to provide
requested information; if it has done so, the case is weak.
The award
criteria
[24] Mr Johnston criticised the defender for
failing to keep separate the criteria used to sift potential tenderers, the
qualitative selection criteria, and the criteria used to make the award, the
award criteria.
[25] Mr
Johnston drew attention to Production 6/31 which is the guidance issued by the
Scottish Government known as the Scottish Public Procurement Toolkit. In section 6, Supplier Selection and
PQQS are dealt with. In this section
under the heading of "Supplier Appraisal" it is stated that the selection
process prior to the issuance of an invitation to tender is a backward looking,
not forward looking process. That is,
the criteria for selection should concentrate on the general suitability of the
candidate supplier for the project, as opposed to the specific means by which
the candidate would implement the contract. The intention of this stage of the
procurement process is to expedite proceedings by eliminating unsuitable
candidate suppliers and thus save time and resources which would be
unnecessarily expended on a detailed examination of unrealistic bids.
[26] Section 7
of the toolkit deals with tender issue and analysis. At page 3 of 9 the advice is that where the
tenders are to be evaluated on the basis of which is the most economically
advantageous, it is necessary that a list of weighted criteria be selected upon
which the decision can be based. It is
stated:
"The criteria thus
identified must relate directly to the subject matter and must provide an
economic advantage to the contracting authority. The criteria will relate to key performance
requirements and adherence to specification.
Each award criterion can be clearly defined, so that there is a common
understanding of what it means. Good
criteria will insist not only in ensuring that bid responses are clearly
addressed to the aspects of the specification that are key areas of concern,
but will allow the tendering panel to make a fair and equal comparison of the
bids in capability, commercial, technical (including performance) and financial
terms. The award criteria must relate to
the goods, services or works to be provided and not to the suitability of the
supplier. The selection of suppliers is
subject to a separate set of rules outlined in the supplier's selection and
PPQS items."
Examples are given including price, delivery,
aesthetic and functional characteristics, after sales service and technical
merit.
[27] Production
6/2 is the Contract Notice. Paragraph
III.2 is headed "Conditions for Participation" which were the criteria for the
pre-qualifying stage. These were listed
as the personal situation of the economic operators, including requirements
relating to enrolment on professional or trade registers; their economic and financial capacity; and their technical capacity. Paragraph IV.2 was headed "Award Criteria"
and indicated that the basis of the award would be the most economically
advantageous tender in terms of the criteria stated in the specifications, in
the invitation to tender or to negotiate or in the descriptive document.
[28] Production
6/11 is the pre-qualification questionnaire.
It dealt with the following issues:
financial status; business probity; service operations; quality; health
and safety; equal opportunities; environmental; business continuity; and
technical matters.
[29] Before the meeting of the Executive Committee
on 1 April there was a report by the Corporate Director (Property
Services) on the tenders, together with two appendices
(production 6/5). In
appendix 2 the tender evaluation model is detailed and the criteria which
were scored are listed. Mr Johnston
submitted that some of these did not properly arise at this stage and were
matters more suitable for pre-qualification evaluation. In particular, Appendix 2 included reference
to plant and equipment; staff structure; and Health and Safety policy. Mr Johnston submitted that these issues
related to the suitability of the contractor.
Further, it was claimed that at the debriefing it was said that the
reference to the project plan related to the contractor's ability to perform
the contract. That was not an
appropriate consideration for the award stage.
[30] The
criteria for making the award of a public contract are dealt with at
regulation 30. Regulation 30(2)
provides:
"A contracting authority
shall use criteria linked to the subject matter of the contract to determine
that an offer is the most economically advantageous including quality, price,
technical merit, aesthetic and functional characteristics, environmental
characteristics, running costs, cost effectiveness, after sales service,
technical assistance, delivery date and delivery period or period of
completion."
[31] Mr Johnston
relied on the decision of the European Court of Justice in Lianakis v Alexandroupolis,
issued on 24 January 2008. In that case the criteria set out in the
contract notice were: (1) the proven experience of the expert on projects
carried out over the last three years;
(2) the firm's manpower and equipment; and (3) the ability to complete
the project by the anticipated deadline, together with the firm's commitments
and its professional potential.
Analysing the criteria appropriate to making an award on the basis of
the economically most advantageous tender, the judgment of the court states:
"29. However, although in the latter case, article 36(1) of
Directive 92/50 does not set out an exhaustive list of the criteria which may
be chosen by the contracting authorities, and therefore leaves it open to the
authorities awarding the contracts to select the criteria on which they propose
to base their award of the contract, their choice is nevertheless limited to
criteria aimed at identifying the tender which is economically the most
advantageous....
30. Therefore, 'award criteria' do not include criteria that are
not aimed at identifying the tender which is economically the most
advantageous, but are instead linked to the valuation of the tenderer's ability
to perform the contract in question.
31. In the case in the main proceedings, however, the criteria
selected as award criteria by the contracting authority relate principally to
the experience, qualifications and means of ensuring proper performance of the
contract in question. Those are criteria
which concern the tenderer's suitability to perform the contract and which
therefore do not have the status of award criteria pursuant to
article 36(1) of Directive 92/50.
32. Consequently it must be held that, in a tendering procedure, a
contracting authority is precluded by articles 23(1), 32 and 36(1) of Directive
92/50 from taking into account as award criteria rather than as qualitative
selection criteria the tenderers' experience, manpower and equipment, or their
ability to perform the contract by the anticipated deadline."
[32] Mr
Bartos referred to a decision of the Court of First Instance in the case of Renco SpA v Council of the European
Union 2003 ECR II 171. The award
criteria in this case included the experience and competence of the permanent
team in providing services similar to those described in the contract
documents; the experience and technical
competence of the undertaking; a proposal made with regard to the safety
coordinator; the quality of any sub-contractors
and supplies proposed; the technical
quality of the equipment and materials proposed; and the measures proposed for observing the
prescribed time limits for completion.
In paragraph 66 of the judgment it was noted that the provision of
article 30(2) of Directive 93/37 left it open to the Council to choose the
criteria on which it proposed to base its award of the contract, provided that
the criteria chosen were aimed at identifying the offer which is economically
the most advantageous. In order to
determine the economically most advantageous tender, the Council must be able
to exercise its discretion, taking a decision on a basis of qualitative and
quantitative criteria that vary according to the contract in question. The Court of First Instance goes on to point
out in paragraph 67 that article 36(1)(a) of the Directive cannot be
interpreted as meaning that each of the award criteria used by the contracting
authority to identify the economically most advantageous tender must
necessarily be of a purely economic nature, because it cannot be excluded that
factors which are not purely economic may influence the value of a tender from
the point of view of the contracting authority.
The judgment goes on at paragraph 68 to state:
"It follows that
article 30(1)(b) of Directive 93/37 cannot be interpreted as meaning that
each of the award criteria used by the Council to identify the most
economically advantageous tender had necessarily to be either quantitative or
related solely to the prices or rates contained in the summary. Various factors which are not purely
quantitative may affect the execution of work and, as a result, the economic
value of a tender. For instance, the
experience and technical competence of a tenderer and its team, the familiarity
with the kind of work covered by the contract in question and the quality of
the sub-contractors proposed are all qualitative factors which, if they do not
reach the level required by the contract, may cause delays in the execution of
the work or make additional work necessary.
It follows that even if some of the criteria mentioned in the contract
documents for assessing a tenderer's competence to carry out the works are not
expressed in quantitative terms, they may be applied objectively and uniformly
in order to compare the tenders and are clearly relevant for identifying the
most economically advantageous tender."
The court concluded that the qualitative criteria used
in that case were not vague and could all be evaluated objectively and
specifically. It was held that they were
transparent and relevant in relation to the nature of the contract and they
sought to identify the most economically advantageous tender.
[33] Mr Bartos
recognised that the decisions of the Court of First Instance in Renco and the Court of Justice in Lianakis were contradictory. In my view it is not necessary for me to
embark on an analysis of a hierarchy of the European Courts in terms of their
persuasiveness. It seems to me sufficient
to recognise that on the basis of the recent decision in Lianakis some of the criteria used by the defender may not fall to
be considered as award criteria. That is
enough in my view to allow me to conclude that in this regard the pursuer has a
prima facie case.
The failure to
carry out an equal and transparent assessment of the tenders
[34] The pursuer avers that the scoring system
employed by the defender offered
complete discretion to the panel members to manipulate the scores on an
entirely subjective basis without any objective constraints.
[35] The
issue of scoring was raised in the bulletins.
Question 16 of Contract Bulletin No 3 (production 6/15) sought
clarification of the "Quality Score" system to be used by requesting three
hypothetical score sheets for illustration purposes. The defender stated that it was considered
that the terms of the contract were clear on this matter and it was not
intended to provide such illustrations.
[36] In
Contract Bulletin No. 4A, Question 5, (production 6/16) the pursuer
asked for the identity of the nominated officials who would evaluate the
quality submissions, together with information about their training and
experience. In reply, the defender
stated that these questions were not relevant to the current tender
process.
[37] By e-mail
sent on 5 February 2008 (production 30) the
matter of the scoring system was again raised by the pursuer who repeated the
request from the previous occasion. The
defender referred to its earlier answer and indicated that it had nothing to
add.
[38] Production
6/33 is a letter from the defender to the pursuer's solicitor in which it is
stated that there were no individual score cards for the tender evaluation
exercise, but rather a consensus view of the entire panel. In addition, the pursuer claims that at the
debriefing meeting on 28 April the pursuer was told that the defender
assessed the tender on the basis of a "feeling".
[39] The
assessment of tenders was weighted so that 60% would be allocated to
consideration of price and 40% would be allocated to considerations of quality. Mr Johnston pointed out that the members
of the selection panel had sight of both the price and quality submissions of
the tenderers; good practice would
require different people to address these separately. The health and safety section had been filled
in in advance and all members had access to it.
As noted above, the panel had arrived at a consensus view rather than
reaching a conclusion though individual scoring and, although this is disputed,
it is averred that they did so on the basis of a "feeling". Mr Johnston submitted that these
considerations demonstrated a lack of objectivity and reflected a failure to
deal with the tenders in a transparent way.
[40] Mr Johnston
relied on regulation 4(3) of the 2006 Regulations and the decision in SIAC (supra).
[41] Mr Bartos
pointed out that a scoring system had been put in place. While any scoring system will involve a
degree of judgement, the scoring system in place was objectively based. The headings in the scoring system gave a
fair indication to the tenderers as to what would be scored. The suggestion that the exercise had been
carried out on the basis of feeling was denied.
The criteria used did not result in an unrestricted freedom of choice on
the local authority.
[42] I note paragraphs 34
and 37 of the SIAC case:
"[34] More precisely,
tenderers must be in a position of equality both when they formulate their
tenders and when those tenders are being assessed by the adjudicating
authority...
[37]
Further, an award criteria having the effect of conferring on the adjudicating authority an unrestricted
freedom of choice as regards the awarding
of the contract in question to a tenderer would be incompatible with article 29 of Directive 71/305,
as amended."
[43] In my
opinion it is self evident that the scoring system leading to the award of a public
contract under the 2006 Regulations is a area which is particularly vulnerable
to the risk of unequal treatment of tenders and a lack of transparency. A robust approach observing objective
standards is essential. Unrestricted
freedom of choice must be avoided. The
features identified by Mr Johnston seem to me to point towards a prima facie case for the pursuer on this
aspect. It seems to me that the pursuer
may be able to prove that the approach adopted by the defender demonstrated a
lack of objectivity and reflected a failure to deal with the tenders in a
transparent way. The averments that the
members of the selection panel had sight of both the price and quality
submissions of the tenderers; that the panel arrived at a consensus view rather
than reaching a conclusion through individual scoring; and that they did so on
the basis of a "feeling" are matters which, if proved, could undermine the integrity
of the award process. Accordingly, I am
satisfied that the pursuer has demonstrated a prima facie case on this issue.
Failure to
comply with regulation 32
[44] The pursuer contends that the debriefing
process failed to comply with the provisions of regulation 32. There were debriefing meetings on
21 April and 6 May.
Mr Johnston submitted that the information which had been
communicated at these meetings was insufficient to satisfy the requirement of
regulation 32(4) which provides that if the economic operator requests the contracting
authority to give reasons why the economic operator was unsuccessful, "the
contracting authority shall inform that economic operator of the
characteristics and relative advantages of the successful tender."
[45] Production
7/2 is a debriefing Note which was read out at the meeting on
21 April. This was subsequent to a
letter dated 15 April 2008 in which the pursuer was
advised that its tender had not been successful. The letter advised that the evaluation
resulted in the pursuer receiving a score of 96 compared with the winning
tender from Centre Great which scored 97.5. The Note gave the scores of the pursuer for
price and quality and those of the winning tenderer. A number of strengths in the pursuer's
proposal were identified and under the heading "Areas for Improvement" it was
stated that no aspect of the proposal was less than satisfactory but that they
should focus on areas scoring three with a view to improving to four or
five. Under the heading "Relative
Advantages of Centre Great Proposal" the following items were listed: project plans; liaison/communications;
emergency procedures; best value proposals; staff structure and island
capability.
[46] In a
letter dated 23 April 2008 from the solicitors acting
for the pursuer to the defender it is claimed that at the meeting on 21 April 2008 the defender had failed to provide information as
required by regulation 32(4). A
further debriefing meeting was held on 6 May and production 7/3 is a Note
of that meeting. In the Note reference
is made to a letter from the solicitors acting for the pursuer dated 2 May 2008 (which I have been unable to find within the
productions) in which four particular matters on which further information was
wished were identified. The first of
these related to the meaning of each of the contract award criteria
headings. The position of the defender
was that the headings were detailed in the tender documents and that the
Council did not want to qualify, amend or expand on these in any way. In the Council's view, these were self
explanatory and further clarification was not required in order to cover the
characteristics and relative advantages of the successful tender. The second matter on which further
information was sought was "the objective criteria the Council was looking for
in tender submissions when it assessed each of the contract award criteria". It is not altogether clear what is meant by
that but, in any event, the Council's view was that this was a fishing exercise
in contemplation of court proceedings rather than anything relating to the
characteristics and relative advantages of the successful tender. Accordingly, the defender would not provide
such information. The third request
related to respects in which the pursuer's submissions and those of Centre
Great did not meet objective criteria.
The defender's position was that it was intended to explain the
characteristics and relative advantages of Centre Great in respect of those
criteria where they had scored higher than Lightways. The fourth matter related to the quality
scoring system and the defender's position was that the quality scoring system
in the tender document was self-explanatory and that further detail was not
required for the purpose of the debrief.
[47] Thus, the
defender took a narrow view of the phrase "relative advantages" and restricted
the discussion to areas where Centre Great had scored higher than the
defender. As previously noted these
were: the project plan;
liaison/communications; emergency
procedures; best value; staff structure; and island capability. The Note of the meeting demonstrates that
each of these was addressed in some detail and I did not understand
Mr Johnston to complain about the information that was given on these
matters.
[48] Under
reference to appendix 2 in 6/5 of process, Mr Johnston pointed out
that there were only seven criteria in which Centre Great had achieved a higher
score which meant that the defender was willing to provide a debrief on only
seven out of seventeen elements. It was
necessary for the pursuer to know how good the submission was in all areas as
it might wish to redirect its efforts among the elements. Mr Johnston contended that there was
nothing in regulation 32(4), read literally or by purpose, to interpret it as
requiring the defender to have to give only information with respect to
criteria where the successful tenderer had a higher score.
[49] Under
reference to Strabag Benelux NV v Council of the European Union 2003 ECR
Vol. 2, 135, Mr Johnston argued that in the present case the pursuer
was left in a state of uncertainty as to why it was unsuccessful.
[50] Mr Bartos
submitted that the information which was provided was sufficient to meet the
requirements of regulation 32.
[51] It is
clear from Strabag that satisfaction
of the obligation under regulation 32(4) depends on whether it puts an
unsuccessful tenderer in a position in which it can clearly identify the
reasons for rejection in order that it can defend its rights and that there
would be sufficient information to enable the court to exercise its
jurisdiction with the standstill period.
Paragraph [55] states:
"... the reasoning followed by
the authority which adopted the measure must be disclosed in a clear and
unequivocal fashion so as, on the one hand, to make the persons concerned aware
of the reasons for the measure and thereby enable them to defend their rights
and, on the other, to enable the court to exercise its supervisory
jurisdiction."
[52] It
seems to me that significant information was made available to the pursuer at
the debriefing meetings, particularly on 6 May. However, in considering whether the pursuer
has set out a prima facie case that
the provision of information was not sufficient to discharge the obligation
under regulation 32(4), it does seem to me that there is room for an argument
as to a broader interpretation of the regulation than the defender was prepared
to concede in the debriefing process.
Accordingly, I am of the opinion that the pursuer has set out a prima facie case. However, having regard to the information
which was made available it seems to me that that prima facie case can be described as weak.
Balance of
convenience
[53] Regulation 47(8) provides the powers of
the court in making an interim order
to suspend the procedure leading to the award; in setting aside the decision;
and awarding damages to an economic operator which has suffered loss or damage
as a consequence of the breach of the Regulations. The court may set aside the
decision and award damages. However, paragraph
(9) stipulates:
"In proceedings under this regulation, the
court shall not have power to order any remedy other than an award of damages
in respect of a breach of their duty owed in accordance with paragraph (1) or
(2) if the contract in relation to which the breach occurred has been entered
into."
Consequently, if an order for interim suspension is not made and the
contract is entered into, the only remedy available is an award of damages.
[54] Mr Johnston
submitted that the balance of convenience favoured the grant of interim suspension. If an order for interim suspension was not made the
contract would be entered into and the pursuer would be left without any rights
under the 2006 Regulations except the right to damages. That was not a satisfactory alternative
remedy. He submitted that damages would
be difficult to quantify. On the other
hand, interim suspension would not
materially prejudice the defender or Centre Great as the contract which was
presently in operation would continue until the procurement exercise had been
completed. Mr Johnston also
contended that the prima facie case
was strong and this should be taken into account in considering the balance of
convenience.
[55] Mr Bartos
explained that in the event of an order for interim
suspension the existing contract would require to continue. He went on to inform me that the existing
contract was more expensive than the new contract as a result of which the
defender would require to pay an additional £23,360 per month in order to
sustain the existing contract.
[56] He
suggested that it would not be particularly difficult to quantify a claim for
damages for the pursuer. It would be a
claim for loss of profit, for lost work.
Such an exercise was commonly encountered in building contracts and it would
not be particularly complex to work out.
[57] I
recognise that if the contract is entered into the only right with which the
pursuer would be left would be the right to damages. While that would certainly put the pursuer at
a disadvantage, I am not persuaded that the difficulties associated with
quantifying damages would be undue. If
the order is made, the defender, which is a local authority, will require to
pay out a significant sum of additional money each month until the matter is
resolved. That seems to me to be
powerful consideration shifting the balance of convenience in favour of the
defender. I do not consider that, looked
at as a whole, the prima facie case
is sufficiently strong to tip the balance back in favour of the pursuer. Accordingly, when I put all the relevant
considerations in the balance I am satisfied that on the balance of
probabilities I should refuse to order interim suspension of the implementation
of the defender's decision to award the contract to Centre Great. I shall reserve the question of expenses
meantime.