OUTER HOUSE, COURT OF SESSION
[2008] CSOH 44
|
CA42/07
|
OPINION OF LORD GLENNIE
in the cause
SPIERSBRIDGE
PROPERTY DEVELOPMENTS LIMITED
Pursuer;
against
MUIR CONSTRUCTION
LIMITED
Defender:
ннннннннннннннннн________________
|
Pursuer:
Walker; Maclay Murray & Spens
Defender: Howie, Q.C., Borland; Harper MacLeod
14 March 2008
Introduction
[1] The
pursuer is a property development company.
The defender is a construction company.
In June 2005 the parties entered into a building contract ("the building
contract") for the design and construction by the defender of a development of
light industrial warehouses, office pavilions and associated works. The detailed provisions of the building contract
are not relevant for present purposes.
In this action the pursuer claims for alleged delays in completing the
works whilst the defender counterclaims for an extension of time.
[2] By
clause 2.10.2 of Appendix 1 to the building contract, the defender
(as Contractor) undertook to execute and deliver to the pursuer (as Employer),
no later than 14 days following a written request from the pursuer so to
do,
"a performance
bond in an amount not less than 10% of the Contract Sum in terms the same as
the draft performance bond set out in Part Five of this Schedule, subject to
such non-material variations as may be required by the Employer, and granted by
a surety approved by the Employer (such approval not to be unreasonably withheld)."
In due course, at the defender's
request, a performance bond in the form of a letter addressed to the pursuers was
issued by the Bank of Scotland ("the bank") in the following terms:
"We, THE
GOVERNOR AND COMPANY OF THE BANK OF SCOTLAND ... are informed that MUIR
CONSTRUCTION LIMITED ... (hereinafter called the Contractor) has entered into a
contract with you in respect of the design and construction of two light
industrial warehouses capable of sub-division and two office pavilions together
with all associated car parking, access roads, service yard areas and external
services at Spiersbridge Avenue, Thornliebank, Glasgow G46 8NL for the original
contract sum of Five million nine hundred and thirty two thousand five hundred
and six pounds and fifty two pence Sterling (г5,932,506.52) and that a Bank
Guarantee for Five hundred and ninety three thousand two hundred and fifty
pounds Sterling (г593,250) is required).
On behalf of the
Contractor we hereby give you our guarantee and undertake to pay to you any
amount or amounts not exceeding in total a maximum of Five hundred and ninety
three thousand two hundred and fifty pounds Sterling (г593,250) in total
inclusive of all interest and costs on receipt of your first demand in writing
on us at this office with your signature thereon confirmed by your Bankers
stating that the Contractor has failed to perform and observe all the
conditions and stipulations of this said contract provided that such amount
shall reduce to an amount not exceeding Fifty nine thousand three hundred and
twenty five pounds Sterling (г59,325) in total inclusive of all interests (sic) and costs on receipt of any first
demand as aforesaid which occurs after the date of issue of the certificate of
practical completion under the contract.
For the purposes of this Bank Guarantee, any determination of the
Contractor's employment under the Contract and/or the legal extinction of the
Contractor shall be conclusive evidence of the Contractor's breach of the
contract.
This guarantee
is valid for written demands received by us on or before the date of issue of
the statement of making good defects under the contract after which date our
liability to you under this guarantee will cease and this guarantee will be of
no further effect.
This guarantee
and the benefits conferred by it may not be assigned by you at any time without
our prior written consent. We shall not
be entitled to assign our rights, obligations or liabilities hereunder without
your prior written consent.
This guarantee
shall be governed by and construed according to the Laws of Scotland."
That bond was in substantially the
same terms as the draft bond referred to in clause 2.10.2. I should note, in particular, that there was
no change to the introductory wording of the second paragraph ("On behalf of
the Contractor") or to the restriction in the penultimate paragraph on the bank's
entitlement to assign its rights, obligations or liabilities under the bond.
[3] On
14 November 2006 the
pursuer made a demand in writing requiring payment by the bank under the bond
of an amount of г503,193.75. The bank
made payment of that amount to the pursuer.
It is averred by the defender, though as yet it is neither admitted nor
proved, that the defender was obliged, in terms of a counter-indemnity granted
by them to the bank, to pay to the bank that same amount and that it did so.
[4] The
defender avers in its counterclaim that the grounds upon which the pursuer
called on the bond, as set out in the demand served on the bank, were erroneous
and without foundation in that it was not in breach of contract as
alleged. In these circumstances, it
contends that the pursuer is obliged to account to it for the sums received
under the bond. The basis upon which the
defender contends that the pursuer is obliged to account to it for such sums is
a term which it says is to be implied into the building contract that "in the
event that ... the pursuer should make a call on the bond it would account to the
defender for the proceeds of the bond, retaining only the amount equivalent to
any loss suffered by the pursuer as a result of the defender's breach of
contract, if any". It is contended that
such a term requires to be implied as a matter of business efficacy. This is supported by a number of
averments. It is averred, in particular,
that a reasonable man in the position of the defender would require such a term
for his own protection; that no reasonable man in the position of the pursuer would
refuse to accede to it; and that without such a term, the building contract would
operate, relative to the bond, in a way which would not be the way in which
practical business men in the construction industry on both sides of the
transaction would reasonably have expected it to operate. The defender goes on to say that the bond
conferred a considerable commercial advantage on the pursuer by providing an
unquestionably solvent source from which the pursuer could claim monies for an
alleged breach of the building contract.
The monies could be obtained by the pursuer from the bank under the bond
without proof of breach or damage and without prejudice to any further claims
the pursuer may have for a greater sum by way of damages. In those circumstances, "the obligation on
the pursuer to account to the defender ... is a necessary corrective if a balance
of commercial fairness is to be maintained between the parties." That formulation borrows heavily from the
cases to which I shall refer.
[5] There
is a dispute between the parties as to whether the defender was in breach of
the building contract as alleged and, if so, as to the amount of any damages to
which the pursuer is entitled. That
dispute has yet to be resolved. A proof
before answer has been appointed. However,
the parties are also at issue as to whether, assuming that the pursuer is
ultimately found to be entitled to less than it demanded and was paid under the
bond, it is obliged to account to the defender for that excess. The pursuer's case is not that it is entitled
to hold on to any such excess but that its duty to account is owed to the bank
and not to the defender. Its concern is
that if it were to make payment of that excess to the defender, it would run
the risk of being sued for the same amount by the bank. The parties have agreed that it is sensible
to have this issue decided at debate before the proof.
The
performance bond issue
[6] The
question for decision at debate before me is this: where a demand has been made
on a performance bond in an amount which is ultimately found to exceed the sum
due to the party making the demand, is that party obliged to account for that
excess (a) to the bank or (b) to his opposite contracting party?
Submissions
[7] For
the pursuer, Mr Walker said that there were three contracts to be
considered, namely: the bond contract, i.e. the contract on the performance
bond between the pursuer and the bank; the building contract, between the pursuer
and the defender; and the banking contract, between the defender and the bank,
pursuant to which the bank agreed to issue the performance bond. All had to be taken into account, since any
term implied into one of those contracts might impinge upon the others; and, in any event, the entire contractual
framework is relevant to deciding whether the implication of a term in one of
the contracts is necessary or appropriate.
The pursuer accepted that if the amount of damages to which it was found
entitled was less than the sum paid to it by the bank pursuant to the demand
under the bond, it could not keep that excess.
The question was: to whom should it account for the excess and what was
the route by which that could be achieved?
Both sides accepted that none of the contracts provided expressly for
such an event. Accordingly, it was
necessary to imply a term. But into
which contract? He submitted that the
most sensible route was by implication of a term into the bond contract that in
such circumstances the pursuer would repay the excess to the bank, matched by a
corresponding term to be implied into the banking contract under which, if it
had already been paid by the defender, the bank would repay the like amount to
the defender. If it was accepted that
such terms were to be implied into the bond contract and the banking contract,
there was no need for any implication into the building contract.
[8] Mr Walker
reminded me, under reference to McBryde, The
Law of Contract in Scotland, 3rd ed. at para.9-68 - 9-71, of the
test for implication of terms. The
defender's pleaded case was that the term was to be implied for reasons of
business efficacy. For this approach to
succeed, it must be shown inter alia (a)
that the term was necessary to make the contract work in the way the parties
must have intended it to work (or, as it sometimes put, to give it the business
efficacy which the parties must both have intended that it should have); (b)
that the suggested term was reasonable; and (c) that the term was so obvious ("it
goes without saying") that the parties would readily have agreed to it had it
been suggested to them. Those tests, he
submitted, were readily satisfied so far as concerns the terms which he argued
were to be implied into the bond contract and banking contract. They were less easily satisfied in relation
to the building contract. As an example
of the potential difficulty of implying the term into the building contract,
Mr Walker raised the spectre of insolvency. If, in such a case, the pursuer was required
to account for the excess to the defender, and the defender was insolvent, the
payment by the pursuer would go into the pot for the general body of creditors
of the defender. Unless it had been paid
already by the defender, the bank would lose out. He posed the question whether, having regard
to that factor, it could be said that at the time of entering into the contract
the bank would readily have agreed that the excess would be paid not to it but
to the defender; and answered it in the negative. By contrast, if the terms
were implied into the bond contract and the banking contract, the bank would be
able to sue the pursuer for the excess and the overpayment would be truly
reversed. If the bank had already
received payment from the defender, it would then account to the defender for
the amount received. As to whether the
liquidator could force the bank to sue, Mr Walker said that this presented
no difficulty, since the bank would obviously grant an assignation to the
defender in a case where it was already in funds from the defender; and there
was, he argued, an implied term in the banking contract that the bank would do
so in such an event.
[9] For
the defender, Mr Howie Q.C. did not dissent from Mr Walker's submission as
to the test for implication taken from McBryde, but he drew my attention to the
case of Mosvolds Rederi A/S v Food Corporation of India (The "Damodar
General T. J. Park" and "King Theras") [1986] 2 Lloyd's Rep. 68 where Steyn
J, as he then was, pointed out, at p.70, that the "obviousness" or "officious
bystander" test (Shirlaw v Southern Foundries (1926) Ltd [1939] 2
KB 206) could be considered as a separate test from that of business efficacy. In that case he held that the Shirlaw test was satisfied whilst the
business efficacy test was not.
[10] Mr Howie noted that the terms of the bond prohibited the bank
from assigning its rights thereunder without the consent of the pursuer. The right of the pursuer to withhold consent
was not qualified by any test of reasonableness. This removed one of the essential planks of
the pursuer's implied term trilogy, namely the term which Mr Walker submitted
should be implied into the banking contract that the bank would assign to the
defender its right to repayment from the pursuer of the excess paid under the
bond. There was no room for such an
implication into the banking contract if, under the terms of the bond, the
pursuer could refuse consent to the assignation - by refusing its consent, the
pursuer could, in effect, hold onto the money, since the bank would not be
interested in pursuing in its own name a claim for repayment if it had already
been paid by the defender. Further, he
pointed out that the terms of the bond were substantially those set out in the
building contract. There was therefore no
occasion for any separate negotiation between the bank and the defender over
the terms of the banking contract, or between the pursuer and the bank over the
terms of the bond. It was fanciful, therefore,
to ask what the parties to those particular contracts would or would not have
been willing to agree. It was fanciful
also to think in terms of any discussion, however notional, between the parties
to those contracts into which the officious bystander could have had the
opportunity to interpose his uncalled-for suggestion: c.f. Shirlaw
v Southern Foundries.
[11] Mr Walker had accepted that a term had to be implied somewhere
in the set of contractual relationships which he had outlined. It was clear, therefore, that the test of
necessity was satisfied at least at that broad level. The remaining question was which implication
made the most sense or was least repugnant to the way in which the parties to
the contracts would have intended them to work.
Mr Howie submitted that the obvious place for the term was in the
building contract. The claim for
re-payment of the excess involved a detailed consideration of the merits of the
dispute under the building contract. The
bank had no interest in this. It was
unrealistic to think that the bank would wish to undertake an obligation to sue
to recover any excess paid under the bond.
The bank knew nothing about the merits of any dispute under the building
contract. It did not wish to be involved
in that. Its obligation to pay under the
bond was an absolute obligation to pay upon a demand by the pursuer in the
required form, regardless of the accuracy of the statements in the demand. It was not interested in the underlying
merits. If it were the case that it was
the bank that could sue on the bond for the excess, the bank would be
undertaking the burden of seeking to prove in litigation with the pursuer that
the defender was not in breach of contract or, if it was, that the damage
suffered by the pursuer was less than the amount called under the bond. That was not a task that a reasonable banker
would want to undertake, not only because of the difficulty of running such a
case, but also because of the expense.
Much better for the bank to be able to rely upon its counter-indemnity
from the defender at the time the bond is called. It could adjust its rates to take account of
its assessment of the defender's creditworthiness. On the hypothesis that the bank had the right
of action for recovery of the excess, Mr Walker had submitted that these
difficulties could be overcome by an assignation of the right of action by the
bank to the defenders. This did not work
because of the restriction on assignation (see above). But the assignation route did not work anyway,
because if the bank had been paid by the defender pursuant to its
counter-indemnity it would not have suffered any loss and would have no claim
to assign. And, he asked rhetorically,
on what basis in law did the bank have a claim in any event? It had done what it contracted to do. It had paid in response to a valid
demand. The merits or otherwise of that
demand were res inter alios acta so far as the bank was concerned. There was no failure or default of any kind by
the pursuer so as to put the pursuer in breach vis-р-vis the bank. Assuming, as would usually be the case, that
the bank had been paid under the counter-indemnity, what interest did it have
to recover from the pursuer? All this
pointed against there being an implied term in the bond contract. Put simply, if the officious bystander had
asked what would happen if it later turned out that the pursuer had claimed
more under the bond than he was ultimately found entitled to by way of damages
under the building contract, it was far from obvious that the parties (i.e. the
pursuer, the defender and the bank) would have answered: "of course, the
pursuer will repay the bank". Having
regard to the bank's right to be indemnified by the defender for the full
amount of its payment under the bond, it was far more likely that they would
all have agreed that it should be sorted out between the parties to the
underlying dispute, i.e. between the pursuer and the defender.
[12] Mr Howie submitted that the insolvency problem was more
apprehended than real. The bank holds a
counter-indemnity from the defender.
When the pursuer makes a demand upon the bond, the bank will claim from
the defender under its counter-indemnity.
If, at that stage, the defender is insolvent, that is the risk that the bank
takes in agreeing to put up the bond. It
will have made an analysis of the position of the defender before agreeing so
to do. Any later insolvency by the
defender, after it has paid on the counter-indemnity, will not affect the bank.
[13] In the course of submissions on this point I was referred to
the following authorities: Cargill
International SA v Bangladesh Sugar
& Food Industries Corp. [1996] 4 All. E.R. 563 (Morison J) and [1998] 1 WLR 461 (Court of Appeal); Comdel
Commodities Limited v Siporex Trade
SA [1997] 1 Lloyds' Rep 424; Seepong
Engineering Construction Co Limited v Formula
1 Administration Limited (Langley J, unreported, 25 February 1999); Australasian Conference Association v Mainline Constructions PTY Limited (in
liquidation) [1978] 141 C.L.R. 335; and Wood
Hall Limited v The Pipeline Authority
and Another [1979] 141 C.L.R. 443.
Insofar as they touched upon the point at issue before me, they
supported the position of the defender.
However, Mr Walker submitted that, with the exception of the decision in
Australasian Conference Association v
Mainline Constructions, which he
argued was distinguishable, the point did not arise for decision in those cases
and therefore any comments on the issue were obiter. In addition, I was
referred to passages from a number of well-known textbooks, namely: Hudson's Building & Engineering
Contracts (11th ed.) at para.17.078, both in the main volume and
in the Supplement thereto under reference to the same paragraph; Keating, Construction Contracts (8th
ed.) at para.10-36; Andrews and Millett, The
Law of Guarantees (4th ed.), at paras.16-033 and 16-034; and Benjamin's Sale of Goods (7th
ed.), at paras.23-288 and 23-289.
Discussion
[14] In some cases it is necessary to decide whether, after demand
is made upon a bond and payment is made by the bank, the party receiving
payment is entitled to retain the full amount of that payment regardless of the
loss he has actually suffered, or whether he is obliged to account for the
difference between the amount of the payment to him under the bond and the
amount of his loss. That was the main
issue in Cargill v Bangladesh Sugar & Food Industries Corp.
where it was argued, unsuccessfully, that there was no duty to account at all. There are cases, of which Seepong Engineering Construction v Formula 1 Administration Limited is one,
in which it has been held that there was to be no accounting after the bond was
called. But absent clear words to the
contrary, I would expect that in the normal case the calling of a bond will be
followed in due course by an accounting under which the party receiving payment
thereunder will retain only the amount of his proved losses. I do not need to decide this point since, as
I have indicated, both counsel agree that under the contractual arrangements in
place in the present case the pursuer is not entitled to retain any more than
he is ultimately found to be entitled to in the dispute under the building
contract. He must account for the
excess.
[15] It is agreed between the parties that the obligation on the
pursuer to account for any excess must rest upon an implied term in one of the
contracts to which it is a party. The
"business efficacy" test for implication of terms has at its heart the
proposition that the term sought to be implied must be necessary in order for
the contract to work as it must have been intended to work. The qualification is important, since all
contracts will work in some way or other.
Both parties are here agreed that it is necessary to imply a term
somewhere in the tripartite relationship between the pursuer, the defender and
the bank. Otherwise the building contract
will not work as the parties to it must have intended it to do, since there
would be no mechanism for the repayment by the pursuer of any excess paid to it
under the bond. Once this is accepted,
the test of necessity is met. It cannot
be right then to ask whether, in relation to each of the three contracts, it is
necessary to imply a term to achieve repayment.
That would be a reductio ad
absurdum. By that test, it would not
be necessary to imply a term into the bond contract because the desired result
could be achieved by an implication in the building contract. And it would not be necessary to imply a term
into the building contract because the result could be achieved by an
implication in the bond contract.
Adopting this approach, it would be impossible to imply into either
contract a term which both parties accept had to be applied into one of
them. Accordingly, I take the necessity
test as being satisfied by the fact that it is necessary to imply a term into
one of the contracts between the parties.
The question then becomes one of evaluating which implication best gives
the business efficacy to the transaction as a whole which the parties to it
must have intended.
[16] If a term is to be implied into the bond contract with the bank
that the pursuer will account to the bank for that excess, that term must be
matched by a corresponding term in the banking contract between the bank and
the defender in terms of which, if it has already received payment from the
defender under the counter-indemnity, the bank will reimburse the defender in a
like amount. If, on the other hand, a term
is to be implied into the building contract that the pursuer will account to
the defender for that excess, then there is no need to imply a corresponding
term into the banking contract between the defender and the bank, since the defender's
obligation to pay the bank arises out of the counter-indemnity which will already
be in place.
[17] The need, on the pursuer's case, for a corresponding term in
the banking contract does not seem to me to carry much weight, since in the
circumstances where it is needed (i.e. where the duty to account is to the
bank) it will be implied without difficulty.
There is a greater problem, however, with the pursuer's proffered
analysis. That is to do with how, if the
right lies with the bank, the defender can force the bank to sue effectively
for the excess. The problem is both
legal and practical. I have already
adverted to the practical difficulties of the bank having to undertake the suit
at great expense to itself in respect of a dispute about which it knows nothing
and in the outcome of which, because it has the benefit of a counter-indemnity
from the defender, it has no interest.
The legal difficulties are no less pressing. Is the bank to be left on its own to sue, or
is it to be under the instructions of the defender as a kind of dominus litis? What terms are to be implied as regards
expenses? Is the bank to be held liable
to the defender for its conduct of the litigation? Are there to be implied into the banking
contract reciprocal obligations on the defender to co-operate in the
litigation, to provide documents and witnesses, to act diligently, etc.? How are claims to privilege or
confidentiality to be dealt with? It is
not, of course, impossible to draft an agreement to deal with all these points,
but in the absence of a detailed agreement the scope for disputes and uncertainty
is obvious. Put shortly, it is not the
sort of case where, had the officious bystander raised the question of what was
to happen, one could envisage the bank and the defenders retorting in unison:
"of course, the defenders are entitled to require the bank to sue ...". The solution might lie in an assignation; but
the term of the bond limiting the bank's entitlement to assign its rights under
the bond - which term was in the draft bond attached to the building contract
and therefore must have been in the contemplation of both the pursuer and the
defender at the time of entering into the building contract - precludes the
implication of a term in the banking contract that the bank will, if requested
so to do and if it has been paid by the defender under the counter-indemnity,
assign to the defender its claim against the pursuer for recovery of the
excess.
[18] The natural implication, so it seems to me, is an implication
of the type for which the defender contends, i.e. an implication of a term into
the building contract that, "in the event that ... the pursuer should make a call
on the bond it would account to the defender for the proceeds of the bond,
retaining only the amount equivalent to any loss suffered by the pursuer as a
result of the defender's breach of contract, if any". I have taken the wording from the defender's
pleading, but nothing turns on particular words used. The sense is clear, and a proposed
implication does not fail the test of certainty simply because its purport can
be expressed in a number of different ways.
A term implied into the building contract has none of the disadvantages
of involving the bank in the merits of the case. It has the distinct advantage of allowing the
issue of what loss, if any, the pursuer has suffered as a result of the
defender's alleged breach of the building contract to be determined in
litigation or arbitration between the parties to that contract. And it further has the advantage that the
dispute is resolved between the parties who have in fact suffered the
consequences of, on the one hand, the breach of contract and, on the other, the
excessive call upon the bond. It is
unrealistic to think that the bank will not have agreed with the defender a
counter-indemnity in terms of which, upon a call being made upon the bond, the
defender will in turn indemnify the bank in the like amount. If the call on the bond is in an amount which
turns out to have been excessive, the party who is out of pocket is the
defender, not the bank; and it seems to me quite natural, and something to
which all parties would have said "of course", that it should be the defender
to whom the pursuer has to account for that excess.
[19] The only potential problem in this is that which Mr Walker
identified in his submissions. If the
defender becomes insolvent after the bond is established by the bank, but
before the bank can claim against it on the counter-indemnity, then the bank
stands to lose. If the liquidator
recovers from the pursuer on an accounting between the parties to the building
contract, the amount recovered will go into the pot for the benefit of all
creditors of the defender and the bank will, unless it has taken some security,
rank as an unsecured creditor along with other unsecured creditors. If the bank has not taken security, it is
true that it will stand to lose in such circumstances. But it does not seem to me that this stands
in the way of the solution put forward by the defender. It is simply a risk that the bank takes, a
commercial risk which it will decide whether or not to take depending upon its
own assessment of the defender's creditworthiness. It can always refuse to issue the bond, or
require some security before agreeing to issue it.
[20] I accept that in none of the English cases did the point with
which I am concerned arise directly for decision. However, those cases point very strongly in
favour of the accounting taking place between the pursuer and the defender and
not between the pursuer and the bank.
Thus, in Cargill International v
Bangladesh Sugar Food Industries Corp.
at first instance, Morison J makes it clear that he is envisaging an
accounting between the parties to the underlying contract. Having cited a number of cases and textbooks,
he concludes at page 571h as follows:
"As a matter of
general principle, therefor, in the light of the commercial purpose of such
bonds, the authorities to which I have referred and the textbook comments, I
take the view that if there has been a call on a bond which turns out to exceed
the true loss sustained, then the party who provided the bond is entitled to
recover the overpayment. It seems to me
that the account party may hold the amount recovered in trust for the bank
(where, for example, the bank had not been paid by him) but that does not
affect his right to bring the claim in his own name. In the normal course of events, the bank will
have required its customer to provide it with appropriate security for the
giving of the bond, which would be called upon as soon as the bank was required
to pay. ... In principle, I take the view that the
account party is always entitled to receive the overpayment, since his
entitlement is founded upon the contract between himself and the beneficiary."
It is clear from the passage as a
whole that "the party who provided the bond" is not the bank but the party to
the underlying contract. The idea that
that party might hold the amount recovered in trust for the bank might appear
to provide a solution to the insolvency problem which Mr Walker raised. However, neither counsel before me wished to
support the notion that that Scots law would recognise a trust in such
circumstances, and on this matter I was referred to an illuminating article by
Professor Gretton, Constructive Trusts
and Insolvency, in the European
Review of Private Law, 3:463-476, 2000.
But that apparent difference between English and Scots law does not
affect the underlying analysis. If the
insolvency problem is not solved in this way, so be it.
[21] Before Cargill
reached the Court of Appeal, Morison J's comments were approved by the Court of
Appeal in Comdel Commodities Limited v
Siporex. The appeal concerned the discharge on grounds
of delay of a mareva injunction. In the
background was a claim by Comdel in an arbitration against Siporex for recovery
of the excess amount demanded by and paid to Siporex under a performance
bond. In giving the judgment of the
court, Potter LJ made the following remarks directed to Comdel's claim (at
page 431):
"The law in this
respect has recently been the subject of an illuminating decision of Mr Justice
Morison in Cargill International SA v
Bangladesh Sugar & Food Industries
Corp. ... in which the authorities are reviewed ... Those authorities are to
the effect that it is implicit in the nature of a performance bond that, in the
absence of some clear words to a different effect, when the bond is called,
there will at some stage in the future be an 'accounting' between the parties
to the contract of sale in the sense that their rights and obligations will
finally be determined at some future date.
The bond is a guarantee of due performance; it is not to be treated as representing a
pre-estimate of the amount of damages to which the beneficiary may be entitled
in respect of the breach of contract giving rise to the right to call for
payment under the bond. If the amount of
the bond is not enough to satisfy the seller's claim for damages, the buyer is
liable to the seller for damages in excess of the amount of the bond. On the other hand, if the amount of the bond
is more than enough to justify the seller's claim for damages, the buyer can
recover from the seller the amount of the bond which accedes the seller's
damages."
Although Comdel's right to claim
was not in issue, I do not consider that it is right to regard this passage as obiter; its right to claim to recover from
Siporex any excess paid to Siporex under the bond was an essential step in the
argument since, had it been the bank rather than Comdel which had the right, the
injunction would presumably have been discharged on that ground without any
need to consider delay.
[22] The appeal in Cargill
International SA v Bangladesh Sugar
& Food Industries Corp. focused principally on the argument that the
arrangements in that case did not allow for any accounting subsequently between
the parties at all, an argument which failed.
The leading judgment was given by Potter LJ. At page 468G he said this:
"If questions of
reasonableness are taken into account and if the usual characteristics and
broad commercial purpose of performance bonds are borne in mind, it seems to me
that the following matters are pertinent to the task of construction in the
case. First, as Mr Hossain
accepted, such a bond is a guarantee of performance. That is not to say it is a guarantee in the
sense that it has all the normal incidents of a contract of surety; it is of
course a contract of primary liability so far as the bank that gives it is
concerned. However, it has the feature
that its purpose is to provide security to the buyer for the fulfilment by the
seller of his contractual obligations. ... Second, its purpose is also that the
buyer may have money in hand to meet any claim he has for damage as a result of
the seller's breach. Third, it confers a
considerable commercial advantage upon a buyer.
Not only does the buyer have an unquestionably solvent source from which
to claim compensation for a breach by the seller, at least to the extent of the
bond, but payment can be obtained from the seller's bank on demand without
proof of damage and without prejudice to any subsequent claim against the
seller for a higher sum by way of damages.
In these circumstances the obligation to account later to the seller, in
respect of what turns out to be an overpayment, is a necessary corrective if a
balance of commercial fairness is to be maintained between the parties."
I note the statement that the
obligation to account is to account to the other contracting party under the
underlying contract. Later, at
page 470F, he emphasised that the bond acted as an obvious incentive for
performance, in that it achieved the effect of early payment against loss
without the need to resort to litigation and
"if it is
sufficient (or more than sufficient) to compensate the buyer, it places the
onus of challenge and recovery upon the seller."
Again, I note that it is the seller
who is said to recover, not the bank. In
the same case Staughton LJ agreed that the appeal should be dismissed. He said this (at page 471F):
"The general
situation as to performance bonds is that they provide that the bank or other
party giving the bond has to pay forthwith, usually on demand. But subsequently there has to be an
accounting between the parties to the commercial contract."
He went on to say this:
"... it seems to
me right to bear in mind that the parties very probably will have known that
that is a general feature of performance bonds.
Is there then wording in this contract which shows a different
intention? In my judgment there is
not. ...
In other words, the bond is to be forfeited when it is called upon in
the circumstances described, the bank must pay, and the money must go to the
Bangladesh Food and Sugar Corporation (sic),
but that does not affect the position which generally applies, as between the
Bangladesh Sugar and Food Corporation and Cargill, that there must be an
accounting."
Again, there is a clear distinction
drawn between the bank's obligation to pay in full and the accounting that will
subsequently take place between the two parties to the underlying contract.
[23] At first instance in that case Morison J cited from Hudson, Keating and Benjamin. I have referred earlier to the current
editions of those books. They continue
to support the proposition that the accounting is as between the parties to the
underlying contract. I would only comment
on two points. The first point is in
respect of a suggestion in Benjamin,
at para.23-288, that the rationale may be that "the making of an excessive
demand is, basically a breach of the beneficiary's underlying contract", so
that the other party to the underlying contract can, in effect, recover the
excess as damages for breach of that contract.
I would not wish to be taken as concurring in this analysis. The authors of Millett and Andrews, at para.16-034, suggest that it may not be a
breach of contract for the beneficiary to make a demand on the performance bond
when there has not in fact been a breach by the other party to the underlying
contract. I agree with that, provided at
least that the demand is an honest one. They
suggest that the duty to account arises otherwise, though they question the
different ways in which it may arise. The
parties here are agreed that the route to recovery is by an implied term. The second point relates to a suggestion in Hudson that the
payment under the bond is made by the bank "as agent for the contractor", so
that (for that reason) it is the contractor not the bank who may sue to recover
the excess. Mr Howie seized on this and
reminded me that in this case the operative part of the bond began with the
words: "On behalf of the Contractor".
There is no necessary inconsistency between the bank, on the one hand,
paying as agent and, on the other, providing its personal guarantee that
payment will be made. However, I do not
consider that that is how such arrangements are normally understood. The bank, at the request of one of the
parties to the contract, gives its own undertaking to pay. I consider that the words "on behalf of ...",
read in the context of the bond as a whole, here mean no more than "at the
request of ..." or "on the instructions of ...".
[24] In Cargill, Morison J
relied upon two Australian decisions.
The more in point of the two is Australasian
Conference Association v Mainline
Constructions PTY Limited (in liquidation).
The somewhat complicated proceedings are succinctly summarised in Cargill at the bottom of p.569. It is clear from both the majority and
dissenting judgments that the question that was determinative of the dispute
was whether the employer was bound to account to the bank or to the
builder. The High Court held that the
employer was bound to account to the builder, i.e. to the other party to the
underlying building contract. Mr Walker
sought to distinguish that case on the basis of a specific term in that
building contract, but he failed to persuade me that that was a valid ground
for distinction. That case further
supports the view to which I have come.
[25] For these reasons I answer the question posed at para.[6] above
in the following way: where a demand has been made on a performance bond in an
amount which is ultimately found to exceed the sum due to the party making the
demand, that party is obliged to account for that excess to his opposite
contracting party? To give effect to
this I shall repel the pursuer's first plea in law in its Answers to the
Counterclaim in so far as directed towards the averments in Statement 7.1 of
the Counterclaim anent the right to recover under the bond for monies which ex hypothesi are not sums to which the
pursuer was entitled in name of damages.
A
pleading point
[26] A discrete point was taken by Mr Walker as to the competency of
the defender's conclusion for count and reckoning as sought to be introduced
into its Counterclaim by a Minute of Amendment.
One aspect of that was dealt with in light of discussion during the
hearing by amendment which was offered at the time and submitted to the court
afterwards. That amendment results in
the claim for count and reckoning running alongside rather than in place of the
claim for payment. I need say no more
about that. But Mr Walker's fundamental
point was that a conclusion for count and reckoning was incompetent when the
party claiming payment can specify the amount of his claim to the penny. He referred me to Maxwell, The Practice of the Court of Session at p.357, to Macfadyen, Court of Session Practice at
para.[2052], and to Marchmont Ltd v Clayton 1989 SLT 725, 728. I do not accept that. All that those passages say is that in such
circumstances an ordinary action is more appropriate. In the present case there is an averment that
the pursuers intromitted with the money when they received it from the bank and
either held on to it or applied it as they did.
The details do not matter. There
might, I suppose, be scope for enquiry into how the money was handled by the
pursuers, what interest was earned, so as to justify the full process of count
and reckoning, but I do not rest my decision solely on that. On the broader ground, I see no reason why a
conclusion for count and reckoning should not be used in a claim for re-payment
of excess amounts received under a performance bond in circumstances such as
the present, particularly since the precise sum (if any) will not be
ascertained until the disputes under the building contract are resolved in the
same litigation.
[27] That was the only opposition to the Minute of Amendment being
received and, indeed, to the Counterclaim being amended in terms thereof. I shall therefore allow the amendment.