OUTER HOUSE, COURT OF SESSION
[2007] CSOH 05
|
P1504/05
|
OPINION OF LORD REED
in the petition of
SHETLAND
ISLANDS COUNCIL
Petitioners;
for
Judicial Review of
a decision by LERWICK PORT AUTHORITY
Respondents:
ннннннннннннннннн________________
|
Petitioners: Anderson, QC; Williamson:
Shepherd & Wedderburn, W.S.
Respondents: Dunlop, QC; C Kelly:
Digby Brown
12 January 2007
Introduction
[1] One of the finest
natural harbours of the British Isles lies in the Sound of Bressay in Shetland,
between Mainland, the largest of the Shetland Islands, and Bressay, a smaller
island to the east. The harbour has
provided a safe anchorage for centuries, and is the reason for the development
of Lerwick, the principal settlement of Shetland, on the Mainland side of the
harbour.
[2] Lerwick
is a fishing port, a centre of marine support for the offshore oil and gas
industry, a ferry port with services to other ports in the United
Kingdom, the Faroes, Norway
and Iceland,
and a port for general cargo. It is also
popular with cruise ships and yachts [7/39].
With two entrances, from the north and the south, the harbour is open to
shipping in all weathers and operates around the clock [7/36]. The Sound of Bressay is therefore described in
one of the petitioners' documents as "a key shipping corridor" [10/4, p 44]. Over 2000 jobs are said to be dependent on
the harbour [7/39]. A car and passenger
ferry operates between Lerwick and Bressay, which had a population of 377 at
the last census [10/4].
[3] In
the present proceedings Shetland Islands Council (the petitioners), who are the
local authority, seek judicial review of a decision by Lerwick Port Authority
(the respondents) to revise their dredging proposals for the navigation channel
in the Lerwick North
Harbour. The petitioners wish to construct a bridge
between Mainland and Bressay. They claim
to have had a bridge designed on the basis of information obtained from the
respondents as to their proposals for the future dredging of the navigation
channel between the islands. They have
applied for statutory consents in respect of that design. They intend to promote private legislation
which, if enacted, would authorise them to implement that design. They are concerned that the respondents have
revised their proposals, and that the revised proposals, if implemented, will
necessitate the re-designing of the bridge, causing the petitioners delay and
expense. They challenge the respondents'
decision to revise their dredging proposals as being in breach of a legitimate
expectation. The legitimate expectation
in question is substantive rather than procedural: the petitioners maintain that, by reason of
their expectation, the respondents are not entitled to adopt or implement their
revised proposals. The application for
judicial review also challenges the respondents' decision on grounds of
personal bar and unreasonableness, and in addition challenges the respondents'
proposals in respect of the disposal of the dredged materials as being in
breach of the Lerwick Harbour Order Confirmation Act 1974 ("the 1974
Order"). The application also complains of
a failure to carry out an environmental assessment in respect of the dredging
proposals. That complaint is directed
against the Scottish Ministers (as having failed to require that such an
assessment be carried out) as well as the respondents.
[4] At
the commencement of the first hearing, however, the court was invited on behalf
of the petitioners to dismiss the petition so far as directed against the
Scottish Ministers. During the course of
the first hearing, the court was also informed that the complaint concerning
the alleged failure to carry out an environmental assessment was not being
insisted in; nor was the case based on
personal bar; nor was the case based on
an alleged failure to comply with the 1974 Order. The challenge to the reasonableness of the
respondents' proposals was also qualified in the course of the hearing, as
explained below, so as to be predicated on the proposals being, in the first
place, contrary to the petitioners' legitimate expectation.
[5] In
these circumstances, the petitioners seek two orders, which can be summarised
as follows: first, reduction of the
respondents' decision to revise their dredging proposals; and secondly, interdict against the
respondents from dredging the North Harbour in implementation of their revised
dredging proposals, insofar as such dredging would take place outside the
limits of the dredged channel originally proposed, as indicated on a drawing
provided to the petitioners on 9 January 2004 by the respondents'
consultant civil engineers, Arch Henderson & Partners ("Arch Henderson"),
until a final decision in respect of the petitioners' bridge proposal has been
taken under the Roads (Scotland) Act 1984 ("the 1984 Act").
[6] At
the conclusion of the first hearing, parties lodged a joint minute [19] in terms
of which they agreed, in effect, that the matter to be determined at the first
hearing was the petitioners' contention that they have a legitimate expectation
that the respondents will not depart from their original dredging
proposals. Counsel explained that the
parties were agreed that the existence of a legitimate expectation (by which,
it was agreed, they meant a substantive legitimate expectation) included, in
this case, not only a representation on which it was reasonable to rely, but
also detrimental reliance. The question
whether the respondents' decision to proceed with revised proposals, despite any
legitimate expectation and any detrimental reliance, was unreasonable and ultra vires, or whether the public
interest might justify the respondents' failing to fulfil any expectation which
they might have created, was to be left over to a second hearing, if
necessary. The reason for splitting the
issues in that way is explained below:
in short, it is because the parties were agreed that the question
whether the petitioners had acted in reliance upon a legitimate expectation
should be determined at the present stage, on the basis of the material
presently before the court, whereas issues of fact had been raised by the
petitioners during the hearing, relating to the reasonableness of the respondents'
revised proposals, which were not yet focused in the pleadings, and which might
require the leading of evidence in some form.
[7] The
parties also agreed in the joint minute that, in approaching the matters to be
determined at the first hearing, the court should proceed on the basis of the
pleadings and submissions of parties, two joint minutes (agreeing certain
matters of fact) which had been lodged during the hearing [15 and 17A], and the
documents referred to in counsel's submissions.
It was also agreed that the documents were what they bore to be and were
an accurate record of any statements which they recorded. It was further agreed that the court should
repel the petitioners' pleas relating to personal bar, to the 1974 Order, and
to EC law. So far as the two remaining
pleas were concerned, it was agreed that the court should determine the
petitioners' plea in respect of legitimate expectation. It was accepted by counsel for the
petitioners in the course of the argument that, if that plea were repelled, the
petition should be refused. If the plea
were sustained, the court should deal at a second hearing with the plea of
unreasonableness.
[8] Finally,
by way of introduction, I note that this is the second of three related
applications for judicial review. As
explained below, in 2005 the court granted an application by the present
respondents for judicial review of the Scottish Ministers' decision not to
"call in", under planning legislation, the present petitioners' notice of
intention to develop the bridge. That decision
was quashed by the court. Having
reconsidered the matter, the Scottish Ministers took the same decision in 2006. An application by the present respondents for
judicial review of that decision has not yet been heard.
The factual background
[9] Lerwick
Harbour (by which I mean the area
of water falling within the jurisdiction of the respondents) lies in a north-west/south-east
orientation, with Mainland to the west, and Bressay to the east. The northern entrance to the harbour from the
open sea is a channel between the two islands, about half a mile in
length. The northern end of that
entrance lies between Greenhead, on the Mainland side, and Turra Taing, on the Bressay
side. The southern end of that entrance
lies between Point of Scotland (or Scattland), on the Mainland side, and
Heogan, on the Bressay side. To the
south of Point of Scotland, the channel opens up into a bay, known as the North
Harbour. At the southern end of the North Harbour
the water narrows, at a promontory on the Mainland side known as North Ness. To the south of North Ness,
the water opens up again into another bay, known as the South
Harbour. At the southern end of the South
Harbour lies the south entrance,
with the open sea beyond. It was agreed
by counsel that the seabed is vested in the Crown.
[10] As a natural harbour with both a north and south entrance, Lerwick
Harbour has proved to be an ideal
port. It has undergone development since
at least the seventeenth century, and particularly in the last 100 years. Historically, activity was focused on the
Mainland side of the South Harbour,
and it was there that the town of Lerwick
developed. From the original
"lodberries" at the south end of the harbour, expansion during the heyday of
the herring industry required the development of piers and wharves northwards,
past North Ness and into the North Harbour. The advent of roll on/roll off ferries, and
increased fishing activity, required expansion further north in the 1970s. During the same period, oil services bases were
established in the North Harbour
and the Greenhead area. In the late
1990s, deepwater quays, a turning basin and a dredged navigation channel were
created to cater for larger oil and fishing vessels. In 2002 a new ferry terminal was completed at
Holmsgarth, to the south of Point of Scotland, to accommodate a larger
generation of passenger and freight vessels [6/2]. Docks and piers now line the coast for
approximately three kilometres to the north of the town, as far north as
Greenhead. They include the Shetland
Catch fish factory at Gremista Pier, to the south of Point of Scotland. What I have described as the northern
entrance to the harbour, between Greenhead and Point of Scotland, has itself
become a significant commercial and industrial area. The Bressay side of the harbour remains
undeveloped and comprises rough grazing land with scattered crofts [10/4; 7/34].
[11] In 1997 the petitioners decided to investigate the possibility
of replacing the Lerwick to Bressay ferry with a fixed link [7/10]. In December 1998 they instructed Halcrow
Crouch ("Halcrow"), consulting engineers, to undertake a feasibility
study. Halcrow were to investigate
locations at Greenhead, Point of Scotland and North Ness,
and to identify a number of options at these sites, including different forms
of bridge and tunnel. Their brief did
not require them to consult interested parties or to address the implications
for navigation. During a site visit,
Halcrow had a meeting with the respondents and were provided with information
about "their intentions with regard to future dredging operations" [6/1, para
2.2.1]. Halcrow appear to have submitted
the feasibility study in April 1999 [6/1].
[12] Halcrow noted that, at Point of Scotland, the navigation
channel was approximately 95 metres wide and was close to the centre of the
waterway. The water was relatively
shallow, shelving from the shoreline on both sides to 5 metres below chart
datum (‑5m CD) at the edge of the navigation channel. The navigation channel was dredged to -6m CD,
but the respondents had stated that it was their intention to dredge the
channel to -7.5m CD at some date in the future.
[13] In relation to navigational clearance, Halcrow noted that,
although the navigational channel at all the sites under consideration was
around 100m wide, a greater clear width would be required at Point of Scotland
if a bridge were to be located there:
"A potential problem with the
Point of Scotland crossing raised by the Harbour Trust [i.e. the respondents]
was that vessels entering the harbour through the north channel have to swing
sharply at this location to avoid the middle ground [an area of shallow water
to the south of the channel] and berth at the Gremista Quay or other harbour
berths. This manoeuvring therefore has a
bearing on the clear width of channel required between supports and the Harbour
Trust have requested that a clear width of 150m be provided" [para 3.5].
Halcrow observed that it might be
worthwhile to undertake ship simulation studies for a design vessel (i.e. a
vessel selected as suitable for the purpose of designing the bridge), to
determine the minimum clear width required [para 4.1.2]. Halcrow also noted that their instructions
required them to assume a vertical clearance from high water level to the soffit
of any bridge of 40m [para 3.5].
[14] In relation to the figure of 150m, I was informed by counsel
for the respondents that the respondents had no recollection of that figure
being mentioned, although a figure of 160m had been discussed. Since all the other documents refer to a
figure of 160m, as explained below, it may be that the figure of 150m was a
mistake. Whether the figure was 150m or
160m is not in any event important.
[15] Halcrow considered a number of options for bridges or tunnels
at the three locations in question.
Drawings for box girder bridges at Point of Scotland were provided for
three possible main spans: 125m, 160m
and 260m. It is apparent from the
drawing of the bridge with the 160m main span that the measurement of 160m was
not the clear width of channel between the central piers, but was measured
between the centres of the piers. Since
the report envisaged that the piers would be supported on reinforced concrete
caissons with abutments (which would sit on the seabed and would extend upwards
to a level above high water springs) [paras 4.1.2 and 5.2], the clear width
would be significantly less than 160m.
[16] The report concluded that Point of Scotland was the preferred location
and that a fixed bridge was the preferred option. The report stated:
"The choice of bridge option will
ultimately depend on the navigation clearances agreed with the relevant
authorities."
[17] In the light of the report, the petitioners decided that
further studies should be undertaken, including an assessment of the views of interested
bodies. On 22 October 1999 the petitioners wrote to the
respondents, explaining that they were carrying out such an assessment to
assist in deciding whether or not to proceed with the project, and inviting the
respondents to provide their views on the effects of the proposed bridge [7/40]. The respondents were informed that the
vertical clearance would almost certainly be 40m, and that the main span would
be at least 125m between pier centres [7/41].
The respondents' Chief Executive, Mr Wishart, replied on 4 November
that the respondents had already indicated a strong preference for the proposed
bridge to have a main span of at least 160m but that he would revert to the
petitioners once the matter had been considered by the respondents' board [7/42]. [18] Mr Wishart
wrote again to the petitioners on 17 November
1999:
"This matter was again considered
by Lerwick Port Authority Board Members at their meeting yesterday and they
asked me to inform you of their observations at this time.
...
╖
The proposed air draught of 40m minimum in the
main span above Mean High Water Springs is acceptable.
╖
The main span of the bridge should have at least
160m clearance. This is in the interests
of marine safety to avoid as far as possible risk to shipping with ensuing
injury or loss of life, damage to vessels and serious environmental damage to
our clean environment.
It is pointed
out that from time to time large vessels or disabled vessels enter the harbour
from the north. To do so they are
accompanied by tugs - one at either end.
To turn or manoeuvre a 'dead ship', it is necessary for the tugs to
swing away from the direction of the forward movement and to do so obviously
manoeuvring space is required.
It is also
pointed out that in order to protect the Port Authority's right to dredge the
north channel to a deeper level, it will be necessary to have at least 160m
clear width so as not to disturb the integrity of the supporting piers" [7/44].
In the light of
subsequent events, it is important to note that the respondents requested "at
least 160m clearance": the minimum
distance of 160m would therefore be measured between the inner faces of the
bridge structure, rather than being measured between the centres of the piers.
[19] The next relevant document is a report on the
petitioners' feasibility study [10/2], which was submitted by the petitioners'
roads engineer to their Resources Committee on 1 February 2001.
[20] The report stated that it was intended to
conclude the feasibility study. It noted
that the first part of the study had been a technical appraisal of the various
options. That had concluded that the
best option would be a bridge between Heogan and Point of Scotland, which could
be built for about г15m. The second part
of the study had been an appraisal of social and economic issues. The report noted that there was provision in
the current capital programme of г15m to build the bridge between 2003/04 and
2006/7. It concluded that the proposal
had been thoroughly studied. It
recommended that the Resources Committee should recommend that the council
approve in principle that a bridge be built, and that a steering group be
established to take the project forward.
The report contained no mention of the points which the respondents had
made in their letter of 17 November
1999. There was no reference
in the report to any possible implications for the respondents.
[21] I was informed by counsel for the
petitioners, in their submissions, that the Resources Committee accepted the
recommendations in the report. A
steering group (the Bridge Project Team) was established, headed by the
petitioners' Mr Craigie. A budget
of г15.559m was allocated to the project [7/6].
[22] On 21 October
2002 Mr Craigie wrote to Mr Wishart, stating:
"I feel the
[respondents'] Board would be better informed if they had the opportunity to
discuss how each of the various parameters impacts on the viability of the
bridge. For example, reducing the span
to 125m and the air draft to 30m could reduce costs by up to г3m. A further reduction in span would further
reduce costs. ... I believe a presentation
[by the petitioners] to the Board followed by an open discussion would resolve
this. We need to do this prior to
11 November [when the respondents' board was next due to meet], bearing in
mind that time is very much against us if we are to secure EU funding" [7/45].
In relation to
the last sentence, is appears that Shetland had ceased to be designated as an Objective 1
area for the purposes of grant aid under the European Regional Development Fund
at the end of 1999, but that a transitional
fund had been established on which the petitioners could draw [6/1, para
10.2.1]. In order to secure EU funding,
the project had to be completed by the end of 2006 [7/6].
[23] Mr Wishart replied to Mr Craigie
the same day:
"When I
mentioned to you that the Board plans to discuss the matter of the bridge
parameters and review this I believe it will be, if anything, to increase the
parameters not to reduce them. We have
already had vessels with an air draft of 37.5 metres using the north entrance
and as one trawler skipper said, 'It's narrow enough already'. The Port
of Lerwick employs around 1,200 people
directly and its history of continual development is not expected to suddenly
stop. It is impossible to conceive
therefore that a stranglehold will be put on one of the biggest collective
employers in Shetland for the sake of a Council budget set some five years ago. Lerwick Port Authority is very supportive of
the bridge project but it is imperative that a very long term view is taken of
this development and that the bridge is designed and built with a broad vision
of the long term future" [7/46].
[24] The respondents then commissioned a study
from Arch Henderson on the impact of the proposed Bressay
Bridge option on future port
development and operations. Arch Henderson
reported in January 2003 [6/2].
[25] The report began by giving an overview of
the harbour. It noted that plans were
currently being made to accommodate predicted growth in the pelagic fish
processing industry and the offshore decommissioning industry. The related developments were planned for the
North Harbour. It was also noted that the total tonnage of
vessels using Lerwick Harbour
had increased. The report stated:
"The remainder
of this report by Arch Henderson & Partners provides relevant cost
development information and navigational data that will need to be considered
and addressed by parties involved in the planning, design, funding and construction
of the proposed Bressay Bridge in order that a minimal impact on future port
development and harbour operations is achieved."
[26] In relation to the layout of the North
Harbour, the report noted that there was a dredged navigation channel (-9m CD),
dating from 1998, through the northern part of the north entrance, at Turra
Taing, with a dredged turning basin to its south, beside the deep water quay
development at Greenhead. In the
southern part of the north entrance there was the dredged navigation channel previously
mentioned (-6m CD), dating from 1990, which passed between Point of Scotland and
Heogan into the North Harbour, where it then bent in the direction of the
Shetland Catch factory at Gremista Pier.
The Shetland Catch factory had undergone recent development, including
the construction of a deep water quay and the largest pelagic fish cold store
in Europe. The
proposed bridge would cross directly above the -6m CD navigation channel.
[27] The report noted that respondents had in
2002 commissioned a report into suitable sites for further expansion by
Shetland Catch. The conclusion had been
that Gremista Quay was the only suitable area.
The current proposal was for a large reclamation area (i.e. an area
currently under water, which would be in-filled and reclaimed) and an
additional 390m of berthing with a draft depth of -9m CD, suitable for the new
generation of pelagic trawlers, refrigerated vessels and general shipping. That proposal was illustrated on a drawing,
prepared by Arch Henderson, appended to the report. The drawing shows a wider and deeper
navigation channel (-9m CD) at Point of Scotland. As illustrated, the channel would lie in a
different orientation from the existing channel, lying broadly north/south,
rather than north-west/south-east. It
would lead into a turning basin (-9m CD) serving the new deep water quay and
the Shetland Catch development at Gremista.
In relation to the drawing, the report stated:
"The proposed
future navigation channel requirements shown ... have been established based on
this anticipated development [i.e. the current proposal for the development of
the Gremista Quay area] together with other future port design criteria and
available vessel data. The following
section of this report discusses further the proposed future layout
requirements of the navigation channel, other design parameters and how these
must be assessed and developed into any future bridge proposals."
[28] In relation to the future design of the North
Harbour access channels, the report
noted that there was no standard method for channel design: each design was site specific. There were however published guidelines,
including those published in 1995 by the Permanent International Association of
Navigation Congress (PIANC). The factors
considered were the design ship characteristics (including size,
manoeuvrability and trends in vessel development), environmental and physical
conditions (including wind data, tidal information and currents), and
navigational, operational and human factors (such as ship handlers'
performance, skill and knowledge).
[29] In relation to vessel data, information
available in December 2002 suggested that the most critical data related to
proposed new build pelagic trawlers, with a draft of over 8m, and the new
passenger ferry Norrona, with an air
draft of 42.8m. I was informed in
counsel's submissions that the Norrona was
a regular visitor to Lerwick, but could at present enter and leave the harbour
only by the south entrance, as her draught was too great for the north entrance,
and she was too long from bow to stern to make the turn to the south of Point
of Scotland. In relation to navigational
aspects, the existing navigation channel through Point of Scotland was
recognised by some vessel operators as a restricted channel. The dredging of the outer access channel at
Turra Taing had increased tidal flow, causing some vessels to drift to the west
side of the Point of Scotland navigation channel. It was recognised that during any further
development of the channel the dredged width would need to be increased and its
orientation moved to a north/south axis, in order to cater for larger vessels
and improve navigation and manoeuvrability.
[30] The report continued:
"Based on
predicted future vessel size and draft then the navigation channel width will
need to be increased to 100m with the overall dredged channel 120m wide and -9m
CD depth. The anticipated distance
between bridge pier foundation supports corresponds to a minimum 160m but this
dimension can only be finalised and agreed once site investigation information
confirms final side slope stability characteristics of dredged channel. From the vessel data table above and after
consideration of the Significant Wave Height and tidal surge likely then the
required air draft under any part of the bridge structure needs to be a minimum
clearance of 50m above Mean High Water Springs of +2.2m CD" [para 5.0].
In relation to
the need for the dredged channel to be wider than the navigational channel, the
report explained:
"The maximum
channel width is a function of largest ship beam and length; maximum drift angle to current and wind; and an allowance for yawing due to wind
effects."
[31] The suggested arrangement was illustrated
by a drawing appended to the report (Appendix D). The drawing shows a dredged channel 120m in
width. To either side of the dredged
channel there is a side slope, sloping down from the undredged part of the
seabed to the base of the dredged channel.
No dimension is stated on the drawing for the side slope: as the passage quoted above explained, that dimension
would depend on the stability characteristics of the slope, which could only be
determined by site investigation. To the
side of each side slope the drawing shows a berm, between the top of the slope
and the edge of the bridge structure: in
other words, an area of the seabed which has been left clear in order to reduce
the pressure exerted by the bridge on the slope, so as to prevent the slope
from collapsing (the idea is illustrated by the original meaning of "berm", to
denote the space left by castle architects between the moat and the base of the
castle wall). The berm is described on
the drawing as a "minimum 10m berm": a
minimum, presumably, because the appropriate dimension would have to be
determined after site investigation. The
drawing has a scale, and it is possible to measure the distance between the
inner edges of the foundations of the bridge piers, i.e. the clear width. That measurement is 160m: 120m for the dredged channel, plus the minimum
10m for each berm, plus an allowance of 10m for each side slope. As the passage quoted made clear, however,
that measurement was a minimum, which assumed that the site investigation would
permit the minimum berm, and that the slope characteristics would be such that
each side slope would be 10m. In that
regard, the report noted that previous dredging at Point of Scotland had
involved drilling and blasting, which could open up fractures and faults, with
localised weakening of the strength of the rock. The report also observed that the difficulty
of blasting adjacent to any bridge foundation, and the much higher cost of
alternative dredging techniques, were matters to consider over the lifetime of
any bridge structure.
[32] The report concluded:
"2.0 The proposed bridge crossing at Point of Scattland
is at a location of proposed future development of the North
Harbour area. This report demonstrates that future
development of the port at this location will require a minimum navigation
channel of 100m, dredged channel width of 120m and depth of -9mCD with a
minimum air draft to any structure of 50m above Mean High Water Springs
(+2.2mCD). A 12 degree clockwise
rotation of the access channel is also proposed as part of future developments.
3.0 Dredging operations to create the above
future navigational requirements could create significant conflict with any
in-situ bridge structure and it will therefore be a requirement to consider
dredging of the effected area of navigation channel as part of any civils
contract for constructing the proposed bridge structure. The anticipated distance between bridge pier
foundation supports corresponds to minimum 160m but this dimension can only be
finalised and agreed once future site investigation information confirms side
slope stability characteristics of dredge channel."
[33] The respondents provided the petitioners with a copy of the
report. The petitioners in turn sought a
response from Halcrow. Halcrow's
response [7/47] did not consider the question of the span of the bridge, but
was concerned almost entirely with the question of the vertical clearance. In that regard, Halcrow said that a clearance
of 50m would add about г5m to construction costs. They suggested that taller vessels currently
using the port, such as the Norrona
and Royal Navy destroyers, could instead be restricted to the south
entrance. Mr Craigie forwarded
Halcrow's response to the petitioners on 20 January 2003, observing that the project would
not be financially viable with a 50m clearance.
He also stated:
"I fully recognise that the Port
Authority has not adopted a position regarding the report and the contents of
the report represent the views and the opinions of your Consultants at this
stage" [7/47].
[34] On 27 January
2003 the parties met. It was
noted that the Arch Henderson report had concluded that the requirements for
the bridge should be a "50m air draft" and a "160m distance between columns",
and that the "preliminary bridge design" had been developed on the basis of a
40m air draft and a 160m main span. It
was noted that "in order to secure substantial European funding this project must
be complete by the end of 2006" [7/6].
[35] During 2003 the respondents obtained estimates from Arch
Henderson for the dredging works which had been proposed in their report
[6/3]. It is a matter of agreement
between the parties that during 2003 the only dredging proposals which the
respondents were considering carrying out as their next dredging campaign were
those contained in that report, and that this was made known to the petitioners
[17A].
[36] In order to proceed with the bridge proposal, the petitioners
required a variety of statutory permission and orders. Under planning legislation they were
required not only to apply for planning
permission but also (as they were both the planning authority and the proposed
developer) to publish a notice of intention to develop, and, in the event of
representations being made, to notify the Scottish Ministers, in accordance
with regulation 4 of the Town and Country Planning (Development by Planning
Authorities) (Scotland) Regulations 1981 (SI 1981 No 829) as amended. Under roads legislation they required to
promote a roads scheme. Other consents
and orders were also required. During
2003 the petitioners decided to proceed with the planning application in advance
of the roads scheme [7/7].
[37] On 18 December
2003 Mr Spall of the petitioners wrote to Mr Wishart,
stating that the project team had reviewed the general arrangement of the
proposed bridge in line with the information provided by Arch Henderson and
other data available to them. A
technical problem had emerged: the
various information sources were not in accord regarding the exact position of
the existing navigation channel. Mr Spall
observed that it was important that the petitioners' and the respondents'
technical advisers were in agreement regarding the fundamental data, and said
that it was intended to arrange face-to-face meetings to reconcile the information
available. Mr Spall continued:
"In terms of the design there are
a number of options available to adjust pier positions etc but in order to
avoid unnecessary costs and abortive work, detailed discussions at a technical
level will first be held to establish which options can be developed further."
[38] Mr Spall went on in the letter to discuss the notice of
intention to develop ("NID") which the petitioners had to give in relation to
the application for planning permission to construct the bridge and the
associated road works, as explained above. In that regard, Mr Spall wrote:
"As you are aware, there is
pressure to process the Notice of Intention to Develop in order to meet the
project deadline. Clearly, there was
insufficient time to complete these detailed discussions before the NID advert
had to be placed in the paper on Wednesday 17 December. However, the NID is structured in such a way
that the final detail surrounding the outstanding issues can be incorporated in
the final design. This approach is in
keeping with the discussion we had last week when I indicated that the Council
would have to go forward with a proposal that is deliverable within the
budgetary constraints and then take on board, as far as possible, amendments to
deal with concerns or objections expressed.
...
I am keen to ensure that open and
frank dialogue continues on the issue of the bridge, therefore this letter is
sent to advise you of our intentions while giving reassurance that your very
real concerns will be fully addressed as the formal consultation proceeds"
[7/7].
[39] Although the letter stated that "we have advertised the NID",
the notice was not in fact issued and advertised until 24 December 2003 [6/4; 6/5]. It
gave notice that the petitioners intended to construct a bridge 717m in length
between Point of Scotland and Heogan, with new connecting roads and junctions linking
it to the existing road network, in accordance with plans submitted with the
notice. It also gave notice that an
environmental statement had been prepared.
The notice was accompanied by an application by the petitioners for detailed
planning permission in accordance with the accompanying plans and drawings
[40] In considering the application for planning permission, it is
necessary to bear in mind that (as was common ground between the parties) the bridge
structure above the Sound of Bressay, including the piers supporting the
central span of the bridge, falls outside the scope of planning legislation (Argyll and Bute District Council v Secretary of State for Scotland 1976 SC
248). At the same time, as counsel for
the petitioners explained, the design of the bridge structure as a whole
depends on the location of the central piers:
for engineering reasons (including regulations governing the gradients
of roads and bridges, and the curvature of roads), a change in the location of
the central piers (other than a minor adjustment) would affect the remainder of
the bridge structure and the alignment of the roads connecting the bridge to
the main roads network. The planning
application (and the subsequent compulsory purchase notice) depended on a view
being taken as to where the central piers were to be located, even though the
piers did not themselves fall within the scope of the planning application (or
of the compulsory purchase notice).
[41] The drawings and plans which accompanied the planning
application and the notice were prepared by Halcrow, and were variously
labelled "Preliminary", "Issued for Information" and "Issued for Discussion". They showed the location and spacing of the
piers. One plan (TB-BRES-100 Rev F),
dated 22 October 2003
and labelled "Issued for Information", showed the relationship between the
bridge and a 120m dredged channel [10/3(ii)].
It showed a distance of 160m between the centres of the main piers. The distance between the centre of each pier
and the edge of the dredged channel was shown as 20m. The clear width - the distance between the
inner edges of the main pier structures - was not stated on the plan, but would
appear to have been 134m. The vertical
clearance was shown as 40m. The pier
foundations were annotated: "Provision
for ship impact to be confirmed." In
relation to that matter, another drawing (TB/BRES/SK 101 Rev A), labelled
"Issued for Discussion", showed the foundations as being protected within "rock
islands" [10/3(iii)]. The dimensions of
the rock islands were not stated.
[42] The bridge shown on the first Halcrow drawing (TB-BRES-100 Rev F)
thus departed in two important respects from the recommendations made by Arch
Henderson. First, the central span was
considerably narrower than the 160m minimum clear width which Arch Henderson
had indicated would be necessary. Secondly,
the vertical clearance was 40m, rather than the 50m minimum recommended by Arch
Henderson. The second drawing
(TB/BRES/SK 101 Rev A) was similarly incompatible with the information as to
the clear width requirement provided by the respondents and their consultants.
[43] The environmental statement [10/4] stated (at para. 2.1):
"The bridge ... will have a minimum
air draft of 40m above Mean High Water Springs (MHWS) under the central span,
which will be 160m wide."
A footnote added:
"The width of the main span is
under review in consultation with Lerwick Port Authority".
A later passage (at para 2.3.2)
stated:
"The proposed design is
illustrated in Figure 2.2 ... The central
span will be 160m wide".
A footnote added:
"The final details of the bridge
are under development in consultation with the Port Authority. The central span may be wider in the final
scheme."
Figure 2.2 showed a central span of
160m as measured between pier centres.
The clear width was significantly less, and depended on the width of the
pier structures, which were annotated "Provision for ship impact to be confirmed". The dimension between each edge of the dredged
channel and the nearest pier centre was shown as 20m. In relation to the rock islands, the
environmental statement stated:
"The cofferdams [i.e. sheet piled
structures constructed around the intended working area, to keep the sea out] for
the main piers will be incorporated in the permanent works to act as ship
protection [p IV]" [ p 10].
[44] As Mr Spall had requested in his letter of 18 December 2003, a meeting of
the parties' technical advisers was arranged.
It took place during the afternoon of 9 January 2004 at the offices of Arch Henderson, and
was attended by Mr Manson and (for part of the meeting) by Mr Sandison,
both of Arch Henderson, and by Mr Allan of the petitioners. Mr Manson was a senior engineering
technician. Mr Sandison was an
associate. It appears, from the
information I was given by counsel, that it emerged at the meeting that the
parties (or their advisors) were using different computer systems for the
presentation of data, with the consequence that neither party could overlay the
other party's data on to its own system.
That problem was resolved at the meeting. A drawing was produced at the meeting,
showing the agreed position of the existing navigation channel, and also
showing the position of the proposed new channel. Later that afternoon, following the meeting, Mr Manson
sent an e-mail [6/7] to the petitioners' Mr Craigie:
"Further to the meeting in our
office this afternoon between John Manson and Andy Sandison (Arch Henderson)
and Kenn Allan (SIC) we can confirm that all parties are in agreement as to the
location of the existing dredged channel.
This is shown on the enclosed AutoCad drawing.
The location has been agreed,
with the grid shown matching that shown on the Halcrow drawing of the bridge we
received yesterday. Both surveys are in
the same format and can be directly overlayed.
We have also shown the line of
the proposed new dredged channel which Lerwick Port Authority wish to carry
out.
Therefore this drawing of the
channel will supersede all previous lines shown on Arch Henderson drawings and
Halcrow drawings.
Please confirm receipt of this
drawing, and the action to incorporate it on all existing and future bridge
drawings."
[45] The attached drawing showed the location of the existing
dredged channel. It also showed what was
described as a "120m wide proposed channel", bounded on either side by lines
labelled "edge of proposed dredged channel".
Beyond each of the lines, there was another line labelled "top of
sideslopes to proposed dredged channel".
A docquet on the drawing stated:
"The above data relating to the
existing channel position has been agreed as correct at a meeting between John
Manson (Arch Henderson) representing Lerwick Port Authority, and Kenn Allan
representing Shetland Islands Council on 9 January
2004. The information for
the channel positions was taken from the original setting out drawing for the
1990 harbour dredging contract ...
Proposed new 120m wide channel
(position of top of slopes (10m from main channel edge) running from SOP1 to
SOP3 [positions on the drawing] added 09/01/2004.
All existing and future Bressay
Bridge drawing to be updated to
show this information as the current lines for both the existing channel and
proposed channel."
[46] The petitioners did not respond to the e-mail or acknowledge
receipt of the drawing [6/19, para 6.6.4].
It is a matter of agreement between the parties that the e-mail was
copied to Ms Laurenson, the Deputy Chief Executive of the respondents, that she
printed a hard copy of it the same day, and that she cannot recollect whether
the drawing was attached. It is also a
matter of agreement that she would not in any event have been able to open the
attachment [15].
[47] On 13 January
2004 the respondents submitted objections to the planning
application [6/8]:
"4. The objectors and their engineering advisers, in so far as
they can determine the position from the Planning Application and supporting
drawings or plans, believe the proposed development is likely to obstruct or
impede the performance of their functions as Harbour Authority in terms of the
Lerwick Harbour Acts and Orders 1877 to 2003 and various other general Acts
and/or to interfere with the reasonable requirements of navigation over the
waters, namely Lerwick Harbour. However,
due to lack of salient design and construction information the objectors and
engineering advisers are not able to advise fully on these aspects.
Matters of concern include the
absence in the Application and supporting drawings or plans of precise details
of the location and dimensions of the bridge, including supporting pillars, in
relation to the navigation channel. No
design data and maintenance information in respect of the proposed bridge is
given. In addition, the width of its
central span, as proposed, would be insufficient to permit safe maintenance and
future development of the navigation channel.
No details are given of the Hydrological study and Hydrodynamic
modelling study referred to in the Environmental Impact Assessment and the
effect of the proposed development on the harbour and vessels using same during
both the construction and post construction periods.
In respect of dredging it may not
be possible to dredge at all post-construction or if dredging is possible the
costs are likely to increase substantially.
In any event no information is provided as to how pier foundations are
to be constructed or the protection of same from future dredging of the
channel".
Concern was also expressed that the
rock islands would restrict the width of the channel and therefore increase the
speed of the water flowing through it, rendering the channel less safe for
navigation, and reducing the size of the vessels able to use it.
[48] On 19 January
2004 the respondents submitted objections to the environmental
statement [6/8]:
"A. (i) The indicated width
of the bridge span over the navigational channel is insufficient and in
particular insufficient to accommodate its future development. The minimum width needs to be 160 metres
measured between the inner edges of foundations adjacent to said channel. This objection presupposes pre-dredging of
the navigational channel by the applicant.
If this is not intended to take place then the minimum 160 metre width
referred to will almost certainly need to be increased in order to accommodate
potential future development.
(ii) Information on drawings, which is both conflicting and
inadequate, has been provided regarding cofferdams in their use as ship protection
or part of the temporary causeways becoming permanent as man made rock
islands. The position is, therefore,
unacceptably uncertain and their impact cannot be assessed.
...
(iv) Insofar as the ES comments on the effect of the temporary
causeways/islands, the studies are absent and no detailed information on this
topic is given. No consideration has
been given to the effects of the bridge on navigation of vessels except in
relation to air draft. This gives rise
to serious actual and potential concerns regarding likely difficulties, details
of which are contained in the annexed initial comments and concerns, with
diagram annexed, by Captain Archer T L Kemp, Harbourmaster of Lerwick Harbour,
which comments and concerns form part of these objections.
...
(vi) There is a failure to appreciate that not only is the
navigational channel used by vessels entering from the north but also it is in
regular use by internal harbour traffic including, for example, vessels
entering from the south, reefer vessels loading cargo at the Greenhead base and
Gremista, inshore and pelagic fishermen, pleasure craft, pilot cutters, Lerwick
Port Authority work boats and the like.
The suggestion that
vessels can go round Bressay [i.e. so as to enter the harbour by the south
entrance] if the channel is blocked or restricted is unreasonable and
unsatisfactory and does not conduce to the efficient running of Lerwick Harbour
...
(vii) If a large vessel such as the Norrona, which recently grounded in
Torshavn harbour [in the Faroes], were to ground in the North Ness channel, the
objectors would be faced with the prospect of harbour traffic, e.g. the
NorthLink ferries which berth at Holmsgarth requiring to use the north channel
until the North Ness channel was cleared.
No assessment has been made of the impact of the bridge in such an
event."
Captain
Kemp's observations, which were incorporated into the objections, emphasised
the difficulty of navigating the existing channel, as a result particularly of
tidal flows, and expressed concern that the further restriction of the channel
would exacerbate that problem.
[49] On 17 March
2004 a meeting was held between the respondents' and the
petitioners' officials. The minute
records [7/8]:
"MC
[Mr Craigie of the petitioners] said that from previous discussion and
correspondence with LPA [the respondents] it was known ... that there were
elements of the draft proposals which they felt were unacceptable.
...
AW
[Mr Wishart of the respondents] said that the potential for future
dredging had to be carefully protected.
The draft requirements of vessels likely to be using the port were
constantly being increased. The design
of the bridge should not therefore inhibit dredging in the vicinity of the
middle piers ...
AW
referred to correspondence from 1998 and 1999 setting out LPA's position on
bridge dimensions. Two letters from LPA
were demonstrated which clearly indicated requirements including a 160 metre
clear width requirement. AW said that
another option was to increase the centre span to, for example, 180
metres. This would move the piers clear
of the navigable channel. MC said that
this was still a possibility but that it would involve extra cost. The report to Council will present such options,
with attendant costs."
Mr Wishart
was asked to explain his suggestion of a central span of 180m:
"AW
explained that this was based on an official navigable channel width of 100
metres. 10 metres on each side of this
had to be added as an allowance for 'navigational buoy excursion' plus another
10 metres each side to account for the construction of a stable dredged slope
and a further 10 metres berm (ledge at edge of slope) to the inner side of pier
base. 20 metres is assumed as the
diameter of the central pier foundation structures. He felt that 180 metres between centres would
be required to ensure that the pier bases were far enough from the edge of the
dredged channel. This would allay LPA
concerns regarding future dredging."
As
counsel for the petitioners acknowledged in argument, Mr Wishart's suggestion
of a span of 180m, measured between pier centres, was effectively the same as
the earlier request for 160m clear width, if the diameter of the pier
structures was assumed to be 20m. The
only new matter was Mr Wishart's explanation that the 120m channel
included an allowance of 20m for navigational buoy excursion. In relation to that matter, it was explained
in submissions during the first hearing that the navigation buoys are anchored
by chains, which are more or less taut depending on the state of the tide. To the extent that the chain is slack, the
buoy can drift.
[50] Mr Sandison of Arch Henderson said at
the meeting that the respondents now intended to dredge the channel to a depth
of -10m CD. He also expressed concern
that the proposed design of the pier foundations was inadequate and did not
comply with the relevant guidelines regarding ship collision. Mr Wishart said that this concern also
would be abated if the main span, measured between pier centres, was extended
to 180m. Mr Craigie responded "that
this option would be costed and presented to the Council along with the
others".
[51] Mr Wishart also raised again the issue
of the increasing draught of vessels using the port:
"The
current pelagic fleet can draw as much as 8.5 metres. The Icelandic vessels which may use the port
in the future draw up to 10 metres. The
freedom to dredge in this area in future was therefore a major concern."
It
was noted that the bridge foundation would need to be reconsidered if the
dredge depth were increased to -10m CD.
Concern was also expressed about the effect of the bridge construction
on the current flowing through the channel, and thus on navigation.
[52] General observations made by Mr Wishart
were also noted:
"He
explained in some detail the highly competitive nature of ports and their
businesses, particularly Oil and Fishing.
Any impediment or restriction to free and safe vessel movement would be
picked on by a competitor as a good reason for existing and potential customers
to avoid Lerwick. MC acknowledged this ...
AW
said that LPA had a duty to protect the interest of the harbour and could
therefore not compromise on navigational issues. He felt that SIC have the ability to resolve
the issues by increasing the funding for the project."
[53] On 13
April 2004 Mr Sandison of Arch Henderson wrote to the petitioners'
planning department, stating that they had been commissioned by the respondents
to procure contract drawings and tender documents for proposed dredging and
land reclamation works, which were anticipated to commence in March 2005 [6/9]. The letter continued:
"As
part of this procurement, we are currently carrying out consultation with
businesses in the area that may be affected by the works together with
submission of all marine consent application to various statutory bodies.
We
attach general drawing for the proposed works for your records ... while the
works do not form part of local authority planning legislation, we would
welcome any comments you may have regarding the proposed works."
A
general drawing of the proposed works was enclosed. In the area of the proposed bridge, the
drawing indicated that the channel was to be dredged to -10m CD. The width of the dredged channel was not
stated, but could be measured from the drawing as 120m.
[54] A further meeting between the petitioners'
project team and the respondents' officials took place on 21 April 2004. A note of the meeting [7/9] records:
"7. All agreed it was
unlikely LPA would withdraw its objections to the NID ...
8. SIC project team's
design is very much a 'work in progress'.
They are looking at various engineering solutions, including a totally
different method of construction, to try and meet objectors concerns but remain
within SIC budget.
9. Discussed how long
they were going to try and engineer issues away - not much time left with
ERDF application due in September.
...
12. SIC project team say
that the NID being passed to the Scottish Executive is only relevant in the
context of the onshore parts of the project.
An application under the Roads Act and the Works Licence Application
will deal with the navigation issues.
...
15. SIC project team still
appear not to want to bend at all, keep mentioning reducing the width of the
dredged channel - LPA keep saying this is not negotiable ...
16. LPA repeated its
fundamental requirement for 160m clear span width between pier bases, unchanged
from 1998. This may mean 180m between
pier centres.
...
19. LPA expressed lack of
confidence in the Hydrodynamic modelling done by Halcrow. Requested an independent model.
20. Michael Craigie
reluctant to commit to this, however team did say that enhanced modelling would
be necessary as the final design progressed, perhaps there would even be a
different design of bridge to be modelled."
[55] On 4 May
2004 a report was submitted by the project team to the petitioners'
Infrastructure Committee [7/10;
10/9]. It stated:
"5.6 The Team will consider
the potential costs and benefits of increasing the span of the bridge to at least
180m. The LPA and other objectors raised
concerns about the proposed span of 160m primarily because of navigational
issues.
5.7 As an alternative to
increasing the span, the Team will explore, in consultation with the LPA, the
potential to reduce the width of the proposed dredged channel from 120m to the
minimum 100m through the use of navigational aids.
...
5.12 If the Council is to be
in a position to secure ERDF funding for the construction of the Bressay
Bridge, there are specific elements
of the project that must continue to be progressed. These are:
...
╖
Completion of further options appraisal;
╖
Development of the detailed design of the final
option;
...
╖
Development of the final cost model. This must be concluded before the Council
makes a final commitment to build the bridge;
...
6.2 These costs [i.e. the
estimated cost of the bridge] can only be identified when all the objections have
been addressed and the details of the project finalised. Indicative additional costs for addressing
some specific objections such as moving the bridge location to the north or
increasing the span of the current option, are included in Appendix 1 for
information."
The appendix
referred to [7/11] was a report by Halcrow and other consultants instructed by
the petitioners, dated May 2004. It
stated:
"11.6.1 The Team will further explore options to increase the main
span of the bridge to at least 180m in order to address the LPA's concerns
regarding future dredging in the North Channel and all
objectors concerns about the perceived navigational hazard of the current 160m
design.
11.6.2 As an alternative to
increasing the span, the Team will explore, in consultation with the LPA, the
potential to reduce the width of the proposed dredged channel from 120m to the
minimum 100m".
[56] The notice of intention to develop, with
the planning application and the environmental statement, was submitted by the
petitioners to the Scottish Ministers on 13 May 2004, together with the objections made by
the respondents and others, in accordance with regulation 6 of the 1981
Regulations [10/33].
[57] On 17 May 2004 Mr Sandison, the
respondents' administration manager, sent an e-mail to Mr Nicolson of the
petitioners [6/10].
"Our recent
telephone conversations when you advised that you would like to arrange a brief
meeting to discuss the following main issues refers:
...
2. LPA dredging operations.
3. New channel alignment.
I am afraid
that the date and time you have suggested is not suitable for us owing to
various personnel being on leave and other workload/commitments.
In order to
assist you in the meantime, I detail below a brief response regarding each of
the above issues that may assist you in the meantime.
...
2. Our dredging
proposals have not fundamentally changed from the information prepared by Arch
Henderson LLP and provided to you previously.
3. Our new channel
alignment has not changed from the information prepared by Arch Henderson LLP
and provided to you previously.
I
hope that this information is of use to you in the meantime ..."
[58] On 3 June
2004 the petitioners applied to the respondents for a works licence
under the 1974 Order. The application
was not produced during the present hearing, but appears to have been in
respect of a bridge "with a main span of 160m providing an air draft of 40m
minimum over the proposed 120m wide dredged channel" [7/14]. Following advertisement of the application, objections
were received from five companies operating in the port [10/11].
[59] On 22 June
2004 the Scottish Ministers decided that they did not require the
petitioners to make an application to them for planning permission in respect
of the development described in the notice of intention to develop. Planning permission was then deemed to have
been granted by the Scottish Ministers, by virtue of regulation 6(3) of the
1981 Regulations. The respondents
applied for judicial review of the Scottish Ministers' decision. A first hearing was fixed for 20 and 21 January 2005.
[60] On 28 June
2004 the petitioners informed the respondents that the additional
cost of increasing the central span from 160m to 180m (measured between pier
centres) would be in the region of г750,000, excluding the cost of road
realignment [7/12].
[61] On 29 June
2004 the petitioners made a roads scheme in respect of the proposed
bridge under section 75(3) of the 1984 Act [10/5]. The scheme was published on 2 July 2004. The scheme stated that the petitioners were
"hereby
authorised to construct, along the route described in Schedule 1 hereto, as
part of a public road, a bridge ... in accordance with Schedule 2 to the Scheme
..."
Schedule
1 specifies the route of the public road, as shown in Plan 1. Plan 1, dated 31 May 2004, shows the central piers positioned
asymmetrically relative to the proposed 120m dredged channel. No dimensions are stated, other than for the
width of the proposed channel. The route
shown in Plan 1, and the location of the central piers shown there, appear to
be the same as in the plans in respect of which planning permission had been
granted [10/3, plans (i) and (iv)], as was to be expected.
[62] Schedule
2 is headed:
"Specification of bridge over Bressay Sound showing
the position, clearance for passage of vessels and dimensions of the proposed
bridge."
Under
the heading, "Position", it states that the position of the proposed bridge is
shown on Plan 1. Schedule 2 continues:
"Clearances for the passage of vessels
Ten
piers shall support the final bridge construction. The central span of the proposed bridge
between piers five and six, measures one hundred and sixty metres or thereby
and crosses over the existing 90 metre or thereby channel. The said 90 metre or thereby channel is shown
edged in green on Plan 1....
The
central span of the proposed bridge accommodates a height clearance of 40
metres above Mean High Water Springs over a 120 metre or thereby width.
The
120 metre or thereby width and the 40 metre clearance are shown in ... Plan 2 ..."
It
is to be noted that, although the proposed 120 metre dredged channel is shown
on Plan 1, the passage quoted from Schedule 2 does not refer to that
channel, but to "a 120 metre or thereby width" shown on Plan 2. Schedule 2 also states that "the dimensions
of the proposed bridge are shown on the said Plan 2".
[63] Plan 2, dated 3 February 2004, is (as counsel for the petitioners
accepted) one of the Halcrow drawings which accompanied the planning
application (drawing TB-BRES-100 Rev F), with some of the details omitted. The design of the bridge appears to be
identical to that shown in the earlier drawing:
the dimensions and gradients stated in the two drawings are the
same. Plan 2 shows the central piers
positioned symmetrically relative to an area of the seabed 120m wide, where the
words "navigational clearance" appear. The
120m width shown in Plan 2 cannot be the proposed 120m channel shown on Plan 1,
since the piers are not positioned symmetrically relative to that channel. Plan 2 shows a vertical clearance of 40m
across the 120m width. There would not
however be a 40m clearance across the whole of the proposed 120m channel shown
on Plan 1, if the design of the bridge were as shown in Plan 2, since the main
span of the bridge is not centred over the channel, as it is over the 120m
width. Plan 2 also shows a dimension of
160m between pier centres, and a dimension of 20m between each pier centre and
the edge of the "120m width". The
dimension of the pier structures is not stated.
The note which appeared on drawing TB-BRES-100 Rev F relative to the
foundations ("Provision for ship impact to be confirmed"), to allow for
cofferdams, rock islands or other forms of protection from impact, has been
omitted.
[64] Schedule 2 continues:
"Proposed dredged channel
Plan
1 ... shows the edges of a 120 metre wide channel ... that Lerwick Port Authority
has proposed to dredge in the future. It
is shown in this Scheme to indicate that should the channel be dredged to 120
metres the proposed bridge would be able to accommodate that width of channel
as well as the existing 90 metre channel."
For
the reasons I have explained, a bridge constructed as shown in Plan 2, and
located as shown in Plan 1, would not allow a 40m vertical clearance across the
width of the channel.
[65] When this matter was raised during the
present hearing, counsel for the petitioners said that it was accepted that
Plan 2 was inaccurate. It had not been
intended to show the exact relationship between the navigational "envelope"
(i.e. the 40m clearance across a 120m width) and the centre span, but rather to
illustrate the principle that a suitable navigational envelope could be
provided. A further drawing [6/32],
prepared for the purposes of the hearing, was produced to demonstrate how the
envelope would be provided. This drawing
shows the central piers located as in Plan 1, with the central span positioned
asymmetrically relative to the proposed 120m channel. Pier 6 (the eastern central pier) is shown as
being taller than pier 5 (the western central pier), so as to move the 120m
envelope closer to pier 6, bringing it into alignment with the 120m
channel. Counsel explained that the
difference in height between piers 5 and 6, and the consequent alignment of the
road, were also shown on one of the drawings accompanying the planning
application (Drawing No. TB-BRES-R-05) [10/3(i)]. The distance between the centres of the piers
is 160m, with each pier having foundations surrounded by impact protection
consisting of concrete and granular fill, with a diameter of 26m. The clear width between the piers is
therefore 134m, which is 26m less than the minimum the respondents' officials had
said would be required. The space
between the edge of the 120m channel and the nearest rock island is shown as 3.25m
on the east side, and 10.75m on the west side.
The respondents' officials had requested a minimum of 20m on each side.
[66] In relation to this drawing, counsel said
that the works licence application and the application under the Coast
Protection Act 1949 ("the 1949 Act") defined the positions of the central piers
in terms of latitude and longitude to an accuracy of 0.01 of a minute, which
was equivalent to ▒ 4.7m. In response to
counsel for the respondents' observation that a margin of 3.25m between the
pier and the edge of the channel was incompatible with a tolerance of ▒ 4.7m -
in other words, that the pier might in the event be located in the channel -
and that the margin was less than the minimum stipulated in the relevant
guidelines, counsel for the petitioners responded that these were not matters
for the court. It was accepted that the
piers would have to be located with a higher degree of accuracy than was
envisaged in the works licence application or the application made under the 1949
Act. Whether the design was achievable
was not a matter for the court.
[67] On 29
July 2004 the respondents instructed Eagle, Lyon
and Pope ("ELP"), port and marine consultants, to carry out an assessment of
the navigational impact of the proposed bridge [7/36, para 1.2.1].
[68] On 13 August
2004 the respondents submitted objections to the roads scheme [6/21; 10/36].
These were generally in similar terms to the respondents' objections to
the planning application and the environmental statement, and also stated:
4. ... Due to these
concerns, LPA has commissioned Eagle, Lyon and Pope to
investigate and report on all safety issues relating to navigation through the
channel both during and post construction.
...
6. The indicated width
of the bridge span over the navigational channel is insufficient and in
particular insufficient to accommodate its future development. The width will need to be increased in order
to accommodate potential future development and in particular the proposed
alteration and widening of the existing navigational channel by LPA to a width
of not less than 120 metres to meet the needs of increasingly large vessels.
In this regard we
annex a drawing by LPA's engineering advisers Arch Henderson LLP. Lerwick, namely drawing number 202576-30
dated August 2004 which clearly demonstrates the conflict between Lerwick Port
Authority's proposed new dredged channel and Shetland Islands Council's
proposed position of piers 5 and 6 which support the central span of the
proposed bridge.
...
14. The air draft of the
bridge namely 40 metres is insufficient to accommodate the air draft of vessels
... with air drafts in excess of 40m presently using Lerwick
Harbour."
The
Arch Henderson drawing referred to [7/13] was prepared on the basis that the
main span would be centred over the proposed 120m channel, as shown in Plan 2
of the road scheme. Even so, the drawing
shows piers 5 and 6 as encroaching into the areas of the side slopes; and there is no space for a berm on either
side.
[69] During August 2004 the parties received a
report on the economic impact of a bridge to Bressay which they had jointly
commissioned from DTZ Pieda Consulting [7/39].
It concluded that, in a best case scenario, the bridge would generate an
additional two jobs. It noted that the
average tonnage of vessels at Lerwick
Harbour had almost doubled over the
previous five years:
"[T]he
information available on vessel size supports an overall trend of vessel growth
with some evidence that oil related and ro-ro vessels are undergoing more
significant expansion."
The report also
noted:
"Both [the
petitioners and the respondents] have already clearly stressed that further
examination of technical areas such as hydro-dynamic modelling is
required. Until further examinations are
completed potential impacts on navigational issues and maritime safety cannot
be assessed in a robust manner" [para 5.9].
In relation to
the oil decommissioning market, the report concluded:
"[I]t would
not be unreasonable to assume that Lerwick Harbour may capture up to a fifth of
the overall Scottish share of the decommissioning market, around г860m" [para
6].
The annual
income in Lerwick which could be derived from decommissioning was estimated at
г22.7m, equivalent to 265 jobs.
[70] On 27 August
2004 the respondents refused the petitioners' application for a
works licence [7/14; 10/10; 10/11].
The reason given for the decision was:
"... that the
works for which a licence has been applied for if constructed in accordance
with the Application and its accompanying plans, sections and particulars are
likely to obstruct or impede the performance of the Authority's functions under
the Lerwick Harbour Acts and Orders and are likely to interfere with the
reasonable requirements of navigation ...".
Along with the
decision, the respondents provided the petitioners with papers which included
the Summary and Conclusions sections of the draft of the report which they had
commissioned from ELP [7/15]. In the
draft report, issued on 20 August 2004, ELP had calculated the width
requirements of the dredged channel using International Navigation Association
(INA, formerly PIANC) methods, taking as design vessels the Maersk Assister (a vessel of a class
which already used the channel), and the Norrona. These required (according to the INA
method of calculation) a dredged channel width of 105.6m and 150.5m
respectively. If these widths were to be
reduced, then a series of simulations should be carried out. The draft report also stated:
"7.2.1 The obvious mitigation for all concerns
regarding the bridge construction is for vessels to use the South access
channel, instead of transiting the proposed bridge site. This is too simplistic an answer and quite
apart from the additional steaming time that may be involved (up to 16 nautical
miles) the reason that the port can maintain a high level of accessibility in
extreme environmental conditions is that it will be possible (with few
exceptions) to enter the port from either the north or south dependent on the
prevailing wind direction. Without this
dual access arrangement downtime at the port may significantly increase thus
making it less attractive to potential customers."
[71] On about 27 August 2004 the
petitioners applied to the Scottish Ministers for consent under section 34 of
the 1949 Act, which prohibits the carrying out of operations detrimental to
navigation without their consent. The
application described the works involved as the construction of a bridge "with
a main span of 160m providing an air draft of 40m minimum over the proposed 120m
wide dredged channel" [10/6]. The accompanying drawings were not produced
at the present hearing. The application
was subsequently withdrawn, as the co-ordinates given in the application were
incorrect. A fresh application was
submitted on 19 November 2004. It has not yet been determined.
[72] On 31 August
2004 the petitioners' officials reported to the Infrastructure
Committee, in relation to the bridge proposal:
"The project
is currently progressing through the various consents processes and detailed
design will commence soon" [7/16].
[73] ELP's report in its final form ("the first
ELP report") was issued on 2 September
2004 [7/36; 10/18]. It was in similar terms to the draft
mentioned above. It noted that the current
design, on the assumption that the piers were positioned symmetrically to the
proposed channel, allowed 7m between the edge of each pier and the edge of the
channel (the inner edges of the piers being 134m apart, and the channel being
120m wide). That did not allow for any side
slope, and left little room for a berm.
The report noted that there had been eleven groundings in the area of
the proposed bridge during the previous 10 years. It advised:
"The required
channel width at the proposed bridge site should be in accordance with INA
recommendations or tested with a series of fast time manoeuvring simulations,
to be appropriate to the expected traffic population of the port" [para 6.2.7].
In view of that
advice, the respondents decided to instruct ELP to carry out manoeuvring
simulations based on their proposed 120m navigation channel, and provide a
second report. The petitioners were
provided with a copy of the first ELP report [7/19].
[74] On 2 September
2004 the petitioners wrote to Mr Wishart, asking
"the port
authority to specify what modifications would be required to the proposed
bridge in order to satisfy your requirements and remove your objections. The purpose of seeking the information is so
that the members can have your requirements properly evaluated and costed. A meeting can then be held at the most senior
level with all the information on the table.
It may be that
you feel that you have already stated what your requirements are but it would
greatly assist if you could set them out in response to this request so that
there is no dubiety about what you would wish the Council to do" [10/12].
[75] On 8 September
2004 (the letter being mistakenly dated 18 September 2004) Mr Wishart replied
[7/17; 10/13]:
"[Y]ou will be
aware that the size of vessels using the north harbour has increased
substantially and this has therefore necessitated a review of our position. Expert advisors have already provided
guidance in this respect based on the International Navigation Association
method for calculating channel width requirements. We wish to have these recommendations tested
with a series of manoeuvring simulations for ships now using the north harbour
and also for ships whose owners have indicated that they would prefer to use
the north channel if it were dredged sufficiently. Once we have received and included our expert's
report in an overall assessment of requirements, I will contact you again, at
which time I hope we will be able to jointly move forward."
[76] On 21 September
2004 the petitioners appealed to the Scottish Ministers under the
1974 Order against the respondents' decision to refuse their application for a
works licence [10/15].
[77] By letter dated 15 October 2004 Mr Spall of the
petitioners wrote to the respondents complaining about a lack of co-operation,
and asserting (incorrectly) that the respondents had "consistently stated the
minimum requirements as 40m air draft and a 100m navigation channel"
[7/18; 10/16].
[78] Mr Wishart replied by letter dated 18 October 2004 [6/22; 7/19;
10/17]:
"[W]e have
said in writing from 1998 that we require at least 160m clearance between the
bases of the main stanchions, that we would require the channel dredged to 8
metres depth and that the air draft would certainly require to be not less than
40 metres. ...
During the
past six years we have found that the proposed dredged depth of 8 metres
is not adequate for many of today's ships and that the proposed air draft is
insufficient for many of the vessels that now use the harbour. It is also very likely that the centre span
width will have to be increased. We have
already made available to you a study by Eagle Lyon Pope that should, as
advised to Michael Craigie, give you a good 'steer' on centre span width
requirements.
... I have also
made it clear on different occasions that a statement of our requirements will
not necessarily satisfy the objectors to the bridge proposal who are mostly
significant businesses and employers in the port and whose views, in respect of
the Council's Work Licence Application, we are statutorily obliged to
consider.
... I am
confident that we will win some of the Frigg oilfield decommissioning work as
well as work arising from the renewed interest in West of Shetland offshore oil
exploitation. Many of the present
generation of oil related vessels would not be able to pass through the north
channel if the present bridge proposals were to go ahead. The proposed bridge would effectively cut the
harbour in two. Even the latest local
trawlers require 9 metres of water and this gives a strong indication that
still more dredging will be necessary in the long term. We would be failing in our duty as port
operators if we did not guard against threats to the port's ability to continue
to allow freedom of navigation for all types of shipping, particularly as ships
continue to increase in size. We must
not be inhibited in opportunities to fully utilise existing infrastructure, nor
prevented from developing the port so as to attract future generations of
shipping."
[79] On 28 October 2004 ELP issued their report on
ship manoeuvring simulations ("the second ELP report") [7/37; 10/30].
The simulations were carried out for a proposed 120m dredged
channel. The vessels were taken to be
the Norrona and a generic
tanker. Weather conditions and tidal
currents were adopted on the basis of the existing operational limits of the
port. It was found that runs for both
the ferry and the tanker could not be completed in a satisfactory manner, in
either a northbound or a southbound direction, when the current was running
from astern of the vessel. The report
concluded that the width and orientation of the channel should be
re-considered.
[80] On 29 October 2004 the respondents wrote to
the petitioners [6/22; 7/20; 10/19]:
"We have had further studies undertaken of
our proposed dredging of the north harbour.
We have found that the whole length of the channel from the north
entrance at Turra Taing to the south end at Point of Scotland will need to be
re-orientated. Our studies are not yet
complete but we are examining firstly, the effects of moving the north end of
the channel to the east with the south end being moved to the west and
secondly, the widening of the channel in places particularly at the south end
on the west side to at least 140 metres...
Clearly, this means that changes will be required to the width and
position of the bridge's centre span.
Turning to air draft, you are aware that
there are specific Objections to the granting of a Works Licence in this
regard. Two Objections specified a
minimum air draft requirement of 50 metres.
I pointed out in my letter of 18 October 2004 to you that we are statutorily obliged to
consider these points. Besides, we now
have numerous vessels using the harbour with an air draft in excess of 40
metres. The recent announcement
regarding Frigg field decommissioning underlines our strategic view that the
proposed bridge height will require to be increased."
[81] In the light of the second ELP report, Arch Henderson had made
revisals to the proposed navigation channel, as described in the respondents'
letter dated 29 October 2004. On 11 November
2004
the respondents instructed ELP to carry out further simulations in respect of
the revised proposals.
[82] A meeting between representatives of the parties was held on 13 December 2004. A note of the meeting [10/21] records:
"[The respondents] highlighted the
difficulties that the present plans present to the LPA because of the location
of the central support legs and the proposed dredged channel for Lerwick Harbour.
There was some debate on the positioning of
the legs and how that could be altered to accommodate some of the concerns from
LPA ...[The petitioners'] Chief Executive Morgan Goodlad suggested that there may
be opportunities to modify the plans more in line with the requirements to suit
the LPA. ... There was some disagreement at this point on the position of a
bridge leg. ... Allan Wishart [of the respondents] suggested that there may be an
option of a tunnel ... Morgan Goodlad
responded that tunnelling was not discounted but estimates that the SIC Project
Team have on tunnelling suggest that it would be potentially a lot more
expensive and technically more difficult. ... Morgan Goodlad said the SIC should
have an open mind at addressing costs of any changes that may be required to
overcome the problems foreseen by LPA. ...
... [It] was agreed that the SIC would look at
the repositioning of the pillar [i.e. pier 5] and seek costings for the changes
required to the design of the bridge."
I was informed by counsel
for the petitioners that the accuracy of the note was not disputed. At the meeting, the respondents had shown the
petitioners' representatives a drawing of Arch Henderson's revised dredging
proposal [7/35], showing that the west pier of the proposed bridge (pier 5)
would stand in the dredged channel. The
petitioners' Chief Executive requested the co-ordinates of the position which
would be required to locate the pier outside the channel [7/28; 10/23].
The respondents sent the co-ordinates on 16 December
2004. The petitioners' Chief Executive passed them
on to his officials that day, instructing that there should be "no questioning
by project team just assessment of implications" [10/22].
[83] ELP's report on ship manoeuvring simulations in respect of Arch
Henderson's revised proposal ("the third ELP report") was submitted in draft on
20 December 2004. They concluded that the revised proposal was
a marked improvement, but that the channel should be widened to 140m.
[84] On 23 December 2004 the respondents wrote again
to the petitioners [6/22; 7/25]:
"[O]ver the past few months it has emerged
clearly that the orientation of the dredging for the north channel has to be
altered with the south end moving west and the north end moving east to create
as straight a line as possible for ships transiting the channel. This means that the proposed bridge's west
side main pier will be located in the dredged channel ... However we are now in the final stages of
deciding the precise position of the dredging line on the west side. To assist in making that final decision we
will be taking further core samples early next year and when they have been
analysed that information will be made available to the prospective dredging
contractors. Once that process has been
completed we will advise you of the channel's position and its other relevant
details."
[85] At a meeting of the Bressay Bridge Project Liaison Group on
29 January 2005, at which the respondents were not represented, the
petitioners' Mr Craigie stated that the bridge design had been "drawn up around
a formal agreement between the Lerwick Port Authority and the council that
identified the position of the existing and proposed channel", and had been
"drawn up to the agreed minimum requirements".
There was in fact no formal agreement, and the petitioners had decided
to disregard the respondents' minimum requirements in respect of the clear
width, side slopes and berms.
[86] On 14 March 2005 the petitioners promoted a
compulsory purchase order in respect of land required for the construction of
the proposed bridge and the associated road works, acting under sections 106 to
110 of the 1984 Act. Objections were
lodged. The order has not yet been
confirmed.
[87] At a meeting between the parties on 30 March
2005,
the respondents said that they planned to begin dredging towards the end of
June 2005. The petitioners confirmed
that the distance between the inner edges of the central supports of the
proposed bridge, as presently designed, was 134m. At the same meeting, the petitioners claimed
that the respondents had committed themselves irrevocably to their original
proposals, in consequence of the e-mail of 9 January
2004 [7/27;
10/26].
[88] On the same date the respondents enquired about the
petitioners' assessment of the co-ordinates provided on 16 December 2004 [7/28; 10/23].
The petitioners' officials responded on 5 April
2005
that "to move a bridge leg would require a different bridge design involving a
new consents process, as well as additional expenditure of several million
pounds". The petitioners had a financial
cap in place "which could not be met if several million pounds are added to the
project" [10/24; 10/25].
[89] The final version of the third ELP report was submitted on 5 April 2005. It recommended
a channel of 140m [7/38; 10/31].
[90] On 29 April 2005 the Scottish Ministers
wrote to the petitioners in respect of their appeal against the respondents' refusal
of a works licence under the 1974 Order.
They observed that, by virtue of section 13(1) of the 1974 Order, a
works licence was not required where the works were "specifically authorised
under any enactment". They also observed
that the works licence application was in respect of works for which sanction
was also sought under the 1984 Act. In
the circumstances, they did not propose to consider the appeal pending the
outcome of the application under the 1984 Act [10/28].
[91] In relation to this matter, counsel for the petitioners
explained the petitioners' understanding to be that it had been necessary for
them to apply for a works licence. The
effect of the respondents' subsequent objection to the roads scheme, however,
had been to necessitate private legislation (as explained below). Such legislation, if enacted, would have the
effect of excusing the petitioners from the necessity of obtaining a works
licence, by virtue of section 13(1) of the 1974 Order. It was also envisaged by the petitioners that
the private legislation would deal with the issue of consent under the 1949
Act, and with the authorisation of the proposed compulsory purchase.
[92] On 28 June 2005 this court reduced the Scottish Ministers'
decision not to require the petitioners to make an application to them for
planning permission, the Scottish Ministers having conceded that their decision
had been invalid [6/20].
[93] The respondents placed a contract for dredging operations in
accordance with the advice received from ELP, at a price of г6.5m, with
demurrage running at г2,250 per hour.
Operations were due to begin on 9 August
2005. On 4 August
2005
the petitioners lodged the present application for judicial review. A motion for interim interdict was heard by
the vacation judge and was granted on 5 August.
[94] On 7 October 2005 the Scottish Ministers
wrote to the petitioners in relation to their application under the 1984 Act
(i.e. the roads scheme). They advised that,
since objections had been lodged by the respondents, who were a navigation
authority on whom notice required to be served under paragraph 10 of Schedule 1,
special parliamentary procedures would apply, in accordance with sections 75
and 76(4). In particular, the provisions
of the Statutory Orders (Special Procedure) Act 1945 and the Scotland Act 1998
(Transitory and Transitional Provisions) (Orders Subject to Special
Parliamentary Procedure) Order 1999 (SSI 1999 No. 1593) would apply. These required notice to be given of a
proposed Special Procedure Order, with an opportunity for objections to be
made. In the view of the Scottish
Ministers, if an objection were made by the respondents, the Special Procedure
Order would not take effect until it was confirmed (with or without amendments)
by an Act of the Scottish Parliament.
This would require the introduction of a Private Bill [10/32].
[95] On 15 May 2006 the Scottish Ministers
decided again that the petitioners were not to be required to make an application
for planning permission in respect of the proposed bridge development
[10/33].
[96] On 25 May 2006 the petitioners' solicitors
wrote to the Scottish Ministers in relation to the suggested Private Bill in
respect of the roads scheme [10/34]. They recorded their understanding that the
Scottish Parliament was unlikely to allocate time to the Private Bill which the
petitioners wished to submit, in view of the number of other Private Bills
which were already before the Parliament or were likely to come forward in the
near future. There was an intention to
review the current Private Bill procedure and to replace it with a new
procedure, but "even with a fair wind the new process is unlikely to be
available for use until at least October 2007".
[97] On 16 June 2006 the respondents presented
an application for judicial review of the Scottish Ministers' decision not to
require the petitioners to make an application for planning permission. A first hearing of that application has not
yet taken place.
[98] I was informed by counsel for the petitioners that a draft of a
Private Bill had been prepared, dealing with the issues arising in connection
with the 1949 Act, the 1984 Act and the proposed compulsory purchase.
[99] I was informed by counsel for the respondents that oil
decommissioning work was expected to begin in 2008. The harbour had to be dredged in time, if
decommissioning contracts were to be awarded to companies based in the
harbour. The procurement process for
dredging works was expected to last 6 to 9 months. The dredging itself could take 12 months.
The legislative framework
[100] A number of statutory regimes feature in the
present case. The most important are (1)
the provisions relating to the powers and responsibilities of the respondents
and (2) the relevant provisions of the roads legislation.
1. The respondents' powers and responsibilities
[101] The respondents are the statutory successors of the Trustees of
the Port and Harbour of Lerwick, who were constituted by
the Lerwick Harbour Improvements Act 1877.
Section 5 of that Act provides that the Trustees "shall be conservators
of the harbour". Sections 26 and 27
vested the harbour works (including new works to be constructed) in the
Trustees, subject to the rights of the Crown.
Section 37 provided (so far as material):
"Subject to the provisions of this Act, the
undertaking of the trustees shall consist of the improving, deepening and
cleansing of the harbour or of such portions thereof as the trustees may in
their discretion think fit ..."
The subject of dredging was
dealt with more specifically in the Harbours, Piers and Ferries (Scotland) Act 1937, section 9 of
which provided:
"The following provisions shall have effect
as regards any marine work to which this Part of this Act applies:-
...
(b)
The [harbour] authority may dredge, scour, deepen, and maintain the said
work and the entrances and channels thereof. ..."
It appears from sections 15
and 16 of the Lerwick Harbour Order Confirmation Act 1952 that section 9(b) of
the 1937 Act is applicable to Lerwick Harbour.
[102] Additional powers of dredging were conferred on the Trustees,
within the limits shown on deposited plans, by section 8 of the Lerwick Harbour
Order Confirmation Act 1973.
[103] More importantly, section 8 of the 1974 Order extended the
harbour limits northwards to Greenhead, so as to include the area at issue in
the present proceedings. Section 9(2)
provided:
"The Trustees may deepen, widen, dredge,
scour, cut and improve the sea bed of the harbour and the seaward approaches
thereto, and for such purpose may blast any rock therein."
Section 10(1) conferred on
the Trustees a power to grant "works licences":
"The Trustees may upon such terms and
conditions as they think fit grant to any person a licence to construct, place,
maintain, alter, renew or extend any works on, under or over tidal waters or
tidal lands below the level of high water within the limits of the harbour
notwithstanding any interference with public rights of navigation or other
public rights by such works as constructed, placed, mentioned, altered, renewed
or extended."
The procedure to be followed
by the Trustees when dealing with an application for such a licence is laid
down by section 10(2) - (4). In
particular, subsection (2) requires that the application must be advertised
with a notice
"stating that any person who desires to
object to the Trustees to the granting of the application should do so in
writing stating the grounds of his objection ..."
Subsection (3) provides:
"In deciding whether or not to grant a
licence or as to the terms and conditions to be included in the licence the
Trustees shall take into consideration any objection ... and in granting a
licence the Trustees may require modifications in the plans, sections and
particulars submitted to them by the applicant."
Subsection (4) requires the
Trustees, if they decide to grant a licence, to notify objectors. Section 12 deals with appeals against the grant
or refusal of a works licence. Both
applicants and objectors are given a right of appeal to the Scottish
Ministers. Section 13(1) provides:
"No person other than the Trustees shall -
(a) construct, alter, renew or extend any
works on, under or over tidal waters or tidal lands below the level of high
water within the harbour limits unless he is licensed to do so by a works
licence. ...
Provided that this subsection shall not apply
to the construction, alteration, renewal or extension of any such works ...
specifically authorised under any enactment."
2. Roads legislation
[104] The construction of road bridges over
navigable waters is dealt with by section 75 of the 1984 Act. In particular, section 75(3) provides:
"Provision may be made by a scheme under this
subsection -
(a) made by a local roads authority and
confirmed by the Secretary of State ...
for the construction, as part of a public
road (other than a special road) of a bridge over ... any specified navigable
waters."
The procedure to be followed
in respect of the making of such a scheme is governed by Parts II and III of
Schedule 1 to the Act, to which effect is given by section 75(4). In particular, paragraphs 9 and 10 of
Schedule 1 require that notice of the proposed scheme should be advertised and
also served on the relevant navigation authority, with a period allowed for the
lodging of objections. In the event that
an objection is received from the navigation authority, the Scottish Ministers
are requested by paragraph 11 to cause a local inquiry to be held. That requirement is however subject to
paragraph 19, which is concerned with schemes and orders which are subject to
special parliamentary procedure. In
relation to that procedure, section 76 is relevant. Under section 76(2), a scheme which provides
for the construction of a bridge over navigable waters
"shall include such plans and specifications
as may be necessary to indicate the position, clearances for the passage of
vessels and dimensions of the proposed bridge".
Under section 76(4), if an
objection to a scheme is made by a navigation authority on the ground that the
bridge is likely to obstruct or impede the performance of their functions under
any enactment, or to interfere with the reasonable requirements of navigation,
then the scheme is subject to special parliamentary procedure, and paragraph 19
of Schedule 1 has effect so as to modify
in certain respects the application of the Statutory Orders (Special Procedure)
Act 1945. The consequence is that,
instead of the Scottish Ministers deciding whether to confirm the scheme following
a local inquiry, it is instead necessary for private legislation to be promoted
under the Private Legislation Procedure (Scotland) Act 1936.
3. Inter-relationship of the works licence application and the
roads scheme
[105] It follows from section 13 of the 1974 Order that, prima facie, the petitioners require a
works licence in order to construct the piers of the bridge within the Sound of
Bressay. They were correct to apply for
such a licence, and the respondents were correct to deal with that
application. The petitioners having
subsequently made a roads scheme, and the respondents having objected to the
scheme as the relevant navigation authority, on the ground specified in section
76(4) of the 1984 Act, it follows that the scheme will be subject to private
legislation procedure. If the scheme is
authorised, then a works licence will no longer be required, by virtue of the
proviso to section 13(1) of the 1974 Order.
If the scheme is not authorised, then the appeal against the refusal of a
works licence will (unless withdrawn) remain before the Scottish Ministers for
determination. In practice, there might be
thought to be little point in persisting with the appeal in such circumstances,
but that would be a matter for the petitioners to consider.
The petitioners' case as pleaded
[106] Since
it was agreed that the court should proceed on the basis of the pleadings as
well as the submissions, it is relevant to note the basis on which the
petitioners' case is pleaded:
"That, during the course of 2003, the
respondents' represented to the petitioners that the depth of the proposed
dredged channel would be -9m CD with a width of 120 metres which the
petitioners then relied upon to design the proposed bridge ... By an email dated 9 January 2004 the
respondents unequivocally advised the petitioners to confirm receipt of the
drawing showing the location and line of the proposed dredged channel 'and the
action to incorporate it on all existing and future bridge drawings' ... The petitioners relied upon these
representations from the respondents, confirmed by and evidence in writing by
the respondents by email dated 9 January 2004 as the basis for defining
the pier positions in their applications for the necessary statutory consents
for the road bridge, including the Notice of Intention to Develop in December
2003, the roads scheme ... and the Compulsory Purchase Order ... Reference is further made to a letter from
Arch Henderson & Partners dated 13 April 2004 together with attached
drawing ... Reference is also made to an email from Victor Sandison the
respondents' administration manager, dated 17 May 2004 ... [Stat 7].
...
The respondents were ... well aware that their
original dredging proposals ... upon which the petitioners had relied, informed
the final design of the proposed road bridge in respect of which the
petitioners are seeking now planning consent.
... [T]he respondents have consistently represented to the petitioners
that the design of the bridge with a 160 metre span would be sufficient to
accommodate the respondents' future dredging proposals ... [I]t was not and could
not have been reasonable for the respondents to believe that the design of the
bridge was not fixed or that the petitioners were seriously considering the
possibility of increasing the distance between the central piers after the
statutory consents process had commenced [Stat 8].
...
... At the time the petitioners commenced the
statutory consents process on 23 December 2003 by issuing a Notice of an Intention to
Develop ... the respondents had represented to the petitioners that they proposed
to widen the North Harbour by dredging a channel of 120m. This was confirmed in writing by the
respondents by email on 9 January 2004 ... In reliance upon these representations,
the petitioners duly incorporated the respondents' proposals into the design of
the proposed road bridge and proceeded to apply for the necessary statutory
consents [Stat 18].
...
[T]he petitioners had a legitimate
expectation that the respondents' dredging proposals would proceed on the basis
of the original proposals ... For these reasons, the decision to revise their
dredging proposals should be reduced ... Separatim,
the petitioners had a legitimate expectation that the respondents would not
implement their revised dredging proposals pending the outcome of the statutory
consents process [Stat 21]."
The submissions for the petitioners
[107] On
behalf of the petitioners, it was submitted that the petitioners had a
substantive legitimate expectation that the dredging works carried out by the
respondents would be 120m in width in the area affected by the bridge
proposals. That expectation was derived
from Mr Manson's e-mail of 9 January 2004, the Arch Henderson letter
(and accompanying plan) of 13 April 2004, and Mr Sandison's e-mail
of 17 May 2004. Junior counsel also founded on the Arch
Henderson report of January 2003, and other communications during 2003, but I
understood senior counsel to depart from that position, as explained
below. The petitioners relied on the
representation in their bridge design, in that the 120m width determined where
they proposed to locate the central piers.
That design was the basis on which the petitioners had sought the
various consents which they required. If
the respondents were allowed to depart from their representation, the proposed
location of the western pier would be within the proposed dredged channel. In these circumstances, the consents would be
unlikely to be granted.
[108] The Arch Henderson report of January 2003 bore
to provide information "that will need to be considered and addressed by
parties involved in the ... design ... of the proposed Bressay Bridge". It bore to discuss "the proposed future
layout requirements of the navigation channel, other design parameters and how
these must be assessed and developed into any future bridge proposals". The respondents had provided the petitioners
with a copy of the report. They had thus
insisted that the contents of the report, including the proposal for a 120m
wide dredged channel, should be incorporated into the bridge design. That had remained their position during 2003.
[109] The matter had been taken further by the e-mail sent by Mr Manson
to the petitioners on 9 January 2004. It referred to the attached drawing as
showing "the line of the proposed new dredged channel which Lerwick Port
Authority wish to carry out", and asked the petitioners to confirm receipt of
the drawing "and the action to incorporate it on all existing future and bridge
drawings". The drawing itself referred
to a "proposed new 120m wide channel", and stipulated:
"All existing and future Bressay Bridge drawing to be updated to show this
information as the current lines for both the existing channel and proposed
channel".
Mr Manson must be taken to
have had ostensible authority, if not actual authority, to represent to the
petitioners the location and width of the proposed channel. That could be inferred from the pleadings,
productions and submissions on which the parties invited the court to determine
the matter.
[110] The drawing attached to Arch Henderson's letter of 13 April 2004 had been consistent with the information contained in
Mr Manson's e-mail. Counsel observed
that the position of the piers in relation to the proposed 120m channel had
been shown on the drawing, and that the covering letter had not suggested that
there was any conflict between the position of the piers and the respondents'
proposed dredging operations. Counsel
said however that the most the petitioners had taken from the drawing was that
it showed the respondents' proposed dredging operations: the petitioners did not suggest that Arch
Henderson had been concerned to show any matter relating to the bridge.
[111] Mr Sandison's e-mail had again indicated that there had been no
change in the respondents' dredging proposals.
[112] The petitioners were entitled to assume that those
representations set out the respondents' final position as to their future
dredging proposals. The bridge was a
permanent structure. Its piers could not
stand in a navigation channel. Any
information provided by the respondents for the purpose of enabling the
petitioners to design the bridge must implicitly be final. If they had wished to leave open the
possibility of dredging a wider channel at some point in the future, they
should have said so. The petitioners had
felt able, in the light of those representations, to proceed with the statutory
consents process, on the basis that their bridge design accommodated the proposed
120m channel.
[113] Counsel acknowledged that the petitioners' design did not provide
the 160m clear width which the respondents had represented was necessary: the clear width provided was 134m. That however was not the representation which
the petitioners had regarded as critical to the design of the bridge. The critical factor for the petitioners in designing
the bridge was the representation as to the width of the proposed channel, ie
120m. The design was based on that
representation, notwithstanding that the space between the central piers was
less than the respondents had said they required. The engineering advice given to the
petitioners by their consultants was that their design was adequate to
accommodate the respondents' plans.
[114] In relation to the last point, counsel said that the petitioners
had been advised that it was unnecessary to make any allowance for a berm or
for a side slope. The petitioners (who
were themselves the harbour authority for Sullom Voe) considered the presence
of side slopes on the plans to be irrelevant to the question whether their proposed
design could accommodate the proposed dredged channel. They had decided to make no allowance for side
slopes. If, in the event, the channel
(including side slopes) was wider than the clear width of 134m for which the
petitioners' design allowed, the petitioners could construct the piers within
the side slopes.
[115] Counsel acknowledged that the latter points were merely ex parte submissions. The court was being invited to resolve the
matter on the documents, without hearing evidence. The petitioners were not saying in the
present proceedings that their design would accommodate a 120m dredged
channel. They were saying, rather, that
any issues as to the ability of their design to accommodate the respondents'
requirements should be dealt with in the statutory consents process. The court was not entitled to consider
whether the petitioners' design was in fact compatible with the respondents'
original proposals: Parliament had confided
that question to a public inquiry.
[116] The location of the piers was thus based on the respondents'
representations as to the width and orientation of the 120m channel,
notwithstanding that the space between the piers was less than the respondents
had said they required. The location of
the piers was critical to the entire design of the bridge, since a change
(other than a minor adjustment) in their location affected the alignment of the
connecting roads, which could in turn affect the scope of the orders sought
under powers of compulsory purchase.
[117] In the event, the bridge design was incompatible with the revised
dredging proposals. The respondents
should not now be allowed to frustrate a consents process which had been based
on their representations. The
petitioners had spent over г1m in total on the consents process. That expenditure would be wasted if the
respondents proceeded with their revised proposals.
[118] In making binding representations as to their future dredging
plans, the respondents were not acting ultra
vires. The power to grant a works licence,
under section 10 of the 1974 Order, demonstrated that the respondents had the
power to permit operations which would interfere with the operation of the
harbour and with public rights of navigation.
[119] In argument, senior counsel accepted that the planning
application made in December 2003 could not be said to have been made in
reliance on a clear representation as to the respondents' final position. Counsel submitted that the petitioners had
however relied on the e-mail of 9 January 2004 and later representations
in proceeding with the roads scheme. The
amount of expenditure incurred in connection with the roads scheme was not
known.
[120] Invited to explain the nature of the expectation or entitlement
(if any) which the petitioners claimed, counsel said that they possessed what
could be described as a right to build the bridge as designed, subject to
obtaining the necessary statutory consents.
Alternatively, they possessed an entitlement as to how the respondents
would exercise their power to carry out dredging.
[121] In support of these submissions, counsel referred to Attorney-General of Hong Kong v Ng Yuen Shiu [1983] 2 AC 629, R v Inland
Revenue Commissioners ex parte MFK Underwriting Agents Ltd [1990] 1 WLR
420, R v Devon County Council ex parte Baker [1995] 1 All ER 73, R v Jockey
Club ex parte RAM Racecourses Ltd [1993] 2 All ER 225, McPhee v North Lanarkshire
Council 1998 SLT 1317, R v North and East Devon Health Authority ex
parte Coughlan [2001] QB 213, R v
Secretary of State for Education and
Employment ex parte Begbie [2000] 1 WLR 1115, Lafarge Redland Aggregates Ltd v Scottish Ministers 2000 SLT 1361, R (Bibi) v Newham LBC [2001] EWCA Civ 607, [2002] 1 WLR 237, R (Zeqiri) v Secretary of State for the Home Department
[2002] UKHL 3, [2002] Imm AR 296, R (Reprotech (Petsham) Ltd) v East Sussex County Council [2002] UKHL 8, [2003] 1 WLR 348, Royal Borough of Windsor and Maidenhead
v Dewar [2003] EWHC 154, and Rowland v Environment Agency [2003] EWCA Civ 1885, [2005] Ch 1.
[122] In the course of the argument, junior counsel for the petitioners
also made criticisms of the ELP reports, and of the respondents' decision to act
on the basis of those reports. It was
suggested that the ships, weather conditions and currents selected for the simulations
were inappropriate, and that the south entrance to the harbour in any event
provided an adequate means of access and egress. Counsel also sought to argue that the
respondents' revised dredging proposals were less extensive than the dredging
recommended in the final ELP report, and therefore failed to implement that report. In that regard, a minute of amendment [16]
was allowed to be received. On these
various grounds, it was argued that the respondents' decision to implement the
revised dredging proposals was unreasonable.
It was however accepted by senior counsel that the petitioners had no
interest in challenging the reasonableness of that decision unless the court
accepted that they had a legitimate expectation that the respondents would
implement the earlier proposals described in Arch Henderson's report of January
2003 and Mr Manson's e-mail of 9 January 2004. It was also accepted that the arguments
relating to the ELP reports involved issues of fact (including issues of which
the respondents had no prior notice) which could not be resolved at the first
hearing, and which would not arise unless the petitioners first established
that they had the legitimate expectation for which they contended. In those circumstances, it was agreed that
the court should not consider those matters at present, but would deal with
them later in the event that the petitioners succeeded in establishing that
they had the legitimate expectation for which they contended. If they did not so succeed, the petition
should be refused.
The respondents' case as pleaded
[123] In their answers, the respondents aver that
they had made it clear to the petitioners from the outset that they would
require at least 160m clear width (or a span of at least 180m, if the
measurement was taken between the centres of the piers). They also refer to the parties'
communications with each other between December 2003 and June 2004, and aver:
"As a result of the foregoing the first
respondents reasonably believed that the design of the bridge was not fixed and
that the petitioners were seriously considering the possibility of increasing
the distance between the central piers. ... The petitioners were well aware that
the first respondents had never accepted that the centre span of the bridge was
wide enough to accommodate their dredging proposals as they stood in January
2004 or their revised proposals as they evolved during 2004" [Ans 8].
It is unnecessary to note
the respondents' other averments, which were reflected in their submissions.
The submissions for the respondents
[124] On behalf of the respondents, counsel submitted that the present
case had a number of unusual features.
First, it was unusual for one public authority to argue that it had a
legitimate expectation as to the future performance by another public authority
of its functions. Secondly, where a
legitimate expectation existed, the connection between the exercise of its
functions by the public authority which had induced the expectation, and the
benefit to the other party if the expectation were fulfilled, was normally
direct: the expectation was, for
example, that the public authority would grant the other party a licence, or
allow the other party to continue living in a nursing home, or accept a late
application by the other party for tax relief.
In the present case, the connection was indirect and contingent. In exercising their power to dredge the
harbour, the respondents were not exercising any function in respect of the
petitioners. The petitioners would not
necessarily benefit from the respondents' abiding by the alleged
representation: the petitioners had to
succeed in their various statutory applications before they could build their
bridge. The party they sought to bind -
the respondents - had made it clear since at least January 2004 that they would
oppose those applications. The
petitioners were thus arguing that the respondents had bound themselves to
preserve intact an area of seabed in order to allow the petitioners to build a
bridge to which the respondents had made clear their opposition. This was inherently implausible. In reality, the case concerned a failed
negotiation. When negotiations broke
down, one party did not normally have an alternative means of binding the
other, by saying, "In the course of the negotiations, I identified what I
regarded as the most important aspect of your position, and decided to make my plans
on the basis of affording you that. I
was entitled to expect that you would do nothing to prejudice my plans." There was an issue of reciprocity.
[125] The starting point was that the petitioners were seeking to
interdict the respondents from dredging the seabed in the areas where they
proposed to construct the pier structures of the proposed bridge. To succeed, the petitioners must demonstrate
that they had a substantive legitimate expectation that the respondents would
not dredge those areas of the seabed, and that the roads scheme was prepared in
reliance on that expectation.
[126] The representation which the petitioners had to establish was
that, if the respondents carried out dredging works, they would not dredge
beyond the 120m channel shown in the Arch Henderson drawings. It was the negative commitment which mattered
to the petitioners. They were not
seeking to hold the respondents to a commitment to carry out any dredging
works. What mattered to the petitioners
was that if dredging works were carried out, they must be only the dredging
works shown in the Arch Henderson drawing.
The problem had arisen because the channel shown on the drawing had been
widened and rotated. Had the respondents
precluded themselves from exercising their power to dredge those additional
areas?
[127] Furthermore, the respondents had to have committed themselves not
to carry out dredging works in those areas of the seabed for a period of time
which, at its minimum, was however long it took for the statutory consents process
to be concluded, and at its maximum (if the consents were to be granted) was
for as long as the bridge was in place.
The necessary representation was therefore that the respondents had
committed themselves not to dredge those areas of the seabed for the indefinite
future.
[128] The representation was said to be derived from five sources. The first was the Arch Henderson report of
January 2003. The report had been
commissioned by the respondents in order to obtain advice about the impact of
the proposed bridge on the future design and operation of the port. The respondents had provided the petitioners
with a copy of the report, so as to make them aware of the advice the
respondents had received. The purpose of
the report was not to give the petitioners a commitment as to the respondents'
future actings. The petitioners' e-mail
of 20 January 2003 acknowledged that the report
represented only the opinions of Arch Henderson. Although the report contained a design for an
improved channel, it did not determine what dredging works were to be carried
out. In dealing with the anticipated
distance between the central pier structures, it referred to a "minimum"
distance of 160m.
[129] The second source was communications during 2003, as agreed by
joint minute. Those did not advance the
petitioners' case: all they showed was
that no other dredging proposals were being considered in 2003.
[130] The third source was the e-mail of 9 January
2004,
following the meeting held that day. As
far as the respondents were concerned, this was a technical meeting, to
reconcile divergent approaches as to how to plot a channel on a map. The meeting would have had a different
character, and would have been attended by different personnel, if the
respondents had thought that its purpose was to commit them to an immutable
dredging proposal. Against the
background of the letter of 18 December 2003, it could not be perceived
as a meeting at which the respondents were to be committing themselves to
anything. That letter did not say that
the petitioners needed from the respondents a statement of requirements for the
channel so that the bridge could be designed around it (unlike the letter of
15 October 2004, expressing a desire for "a clear statement of LPA's
absolute requirements for the bridge" and regretting that "LPA's objections do
not state, in definitive terms, what would be adequate"). The letter did not disclose that the distance
allowed between the pier structures in the current design was only 134m: that had never been spelled out to the
respondents by the petitioners. Further,
the petitioners had now explained that they took a decision to leave no
allowance for slopes or berms at the sides of the channel. That had not been made clear to the
respondents either. Not only was there
no request by the petitioners at that stage for a final position from the
respondents, the respondents had been led to believe by the petitioners that
the bridge design was not final.
[131] The drawing attached to the e-mail showed the position of the
proposed channel, and also of the proposed side slopes. The most that could be taken from those
statements (leaving aside the issue of the authority of Mr Manson to bind the
respondents) was that the dredging works in the respondents' thinking at that
time were those shown on the drawing.
There was nothing in those events to commit the respondents to refraining
from dredging other areas of the seabed for the indefinite future. Furthermore, the design of the bridge allowed
no space for the side slopes or the berms which the respondents had included in
their requirements. It was all very well
for the petitioners to say that the respondents did not require berms or slopes: the petitioners could not claim to have
relied on the respondents' stated intentions, and at the same time say that
they had relied on advice that what the respondents proposed to do was unnecessary.
[132] Two other points were made in relation to the e-mail. The first related to the informality of the
communication. It was not established
that anyone from the respondents had seen the attachment. In any event, was it seriously suggested that
one could found a legitimate expectation on a matter of such significance on
the fact that an official of the respondents was copied in on an e-mail? Secondly, following the e-mail, throughout
the Spring of 2004, the petitioners continued to paint a picture of willingness
to accommodate the respondents' concerns and of flexibility in the design of
their bridge.
[133] The fourth source was Arch Henderson's letter of 13 April 2004. The letter was
sent to an official in the petitioners' planning department, not to the bridge
team. In that it was sent for the
purpose of consultation, it was not a representation that the proposals were
finalised. It could not be understood as
being sent to commit the respondents to carry out the works in the drawing, and
only those works. Nor did the letter
bear to be a part of the correspondence regarding the position of the piers of
the bridge. There was no account of who
saw it or of what was taken from it.
[134] The fifth source was Mr Sandison's e-mail of 17 May 2004. It was sent
in an informal context. It confirmed the
current intentions of the respondents, against the background of their
requirements regarding the clear width.
[135] Neither individually nor collectively did these items amount to a
commitment that the respondents would refrain indefinitely from dredging any
other areas of the seabed.
[136] There was also an issue of vires. On any view, the time for which the
respondents were alleged to have committed themselves was an indeterminate
period. It would be ultra vires for them to commit themselves indefinitely not to
exercise their statutory power to dredge a particular area of the seabed. The respondents had to preserve the option of
following the best advice available regarding what dredging should be carried
out in the interests of navigation. The
petitioners were themselves a public authority, and in particular a harbour
authority with similar statutory responsibilities. The petitioners could not therefore have had
a legitimate expectation that the respondents would proceed with their original
proposals regardless of any change in the requirements of the harbour or in the
advice which the respondents might receive.
[137] There was also an issue as to the authority of employees of Arch
Henderson to commit the respondents on matters of policy. What had the respondents done to clothe Mr Manson
or Mr Sandison with the authority to commit them on such issues? The same point arose in relation to the
e-mail of 17 May 2004 from the respondents'
administration manager. His
participation in the matter would appear to have been minimal. There was nothing to suggest that he was
invested by the respondents with the authority to commit them on matters of
policy.
[138] Finally, it did not appear to be disputed that, in the
circumstances of the present case, detrimental reliance had to be shown in
order for the petitioners to succeed on the basis of legitimate
expectation. The petitioners had a
difficulty, in that reliance must post-date the representation. Here, the statutory consents process began
with the submission of the planning application in December 2003, based on
drawings prepared in October 2003. Those
drawings showed a main span of 160m between pier centres, unchanged since the
original Halcrow report in 1999 set out a box girder bridge at Point of
Scotland with a main span of 160m as one of the options. The inclusion of that dimension in the
planning application was the final significant decision by the petitioners
about the main span of the bridge and, therefore, the last action by the
petitioners about the main span of the bridge.
As at that time, however, there was nothing emanating from the
respondents regarding their dredging proposals which could be said to satisfy
the requirements for a representation.
The petitioners had attempted to meet this difficulty by characterising
as the reliance the submission of the roads scheme. For that to constitute detrimental reliance,
it would be necessary for the petitioners to show that they would otherwise have
acted differently in relation to the roads scheme. They had failed to do so. It was inconceivable that a roads scheme
could have been submitted which was at odds with the planning permission
granted one week earlier. The dimensions
of the main span in the roads scheme were settled when the planning application
was submitted in December 2003.
[139] The petitioners' decision to apply for statutory consents for
their chosen design was not a step which they took because they had secured a commitment
from the respondents. It appeared to
have been taken because they were endeavouring to meet a tight financial and
political timescale. They chose to
proceed before they had secured the agreement of the respondents to an overall
scheme for the two developments.
[140] In assessing the issue of reliance, the court should take into
account that the petitioners' conduct in the autumn of 2004 did not suggest
that they believed that the respondents had already committed themselves to a
particular channel: when the respondents
indicated that they were reviewing their proposals, and, later, that under the
new proposals the position of the west pier would be in the dredged channel,
the petitioners did not assert that the respondents had already committed themselves
and were not entitled to alter their proposals.
The first allegation of any sort of commitment by the respondents was
the statement in January 2005 which referred to their having entered into a
"formal agreement".
[141] Moreover, a substantive legitimate expectation could not be based
on reliance on only one part of a composite message. It was not unfair to the petitioners, if they
acted on only part of what they were being told and chose not to comply with
the remaining part, if the respondents then changed their minds. The petitioners had never made it clear to
the respondents that they were interested in only one piece of information
(namely, the channel width), and had never made it clear how that piece of
information was going to be used.
Furthermore, at the time of the supposed reliance, the petitioners knew
that they had to apply for a works licence, to which third parties were entitled
to object, and that the respondents were under a duty to consider any such
objections, and had a power to require the modification of the petitioners'
plans, including the positioning of the central piers. They could not reasonably proceed on the
basis that the respondents' position was immutable.
[142] In support of these submissions, counsel cited (in addition to
the authorities cited on behalf of the petitioners) Oswald v Ayr Harbour Trustees
(1883) 10 R 472, (1883) 10 R (HL) 85, Birkdale
District Electricity Supply Co Ltd v Southport
Corporation [1926] AC 355, R v Inland Revenue Commissioners ex parte Unilever
plc [1996] STC 681, Docherty v City of Edinburgh Council 2005 SC 598, R (Ghartey)
v Secretary of State for the Home
Department (2001) EWHC Admin 199, [2001] 1 PLR 145, R v Falmouth & Truro Port
Health Authority ex parte South West Water
Ltd [2001] QB 445, South Bucks
District Council v Flanagan
[2002] EWCA Civ 690, [2002] 1 WLR 2601, R
(Association of British Civilian Internees:
Far East Region) v Secretary
of State for Defence [2003] EWCA Civ 473, [2003] QB 1397 and R (Nadarajah) v Secretary of State for the Home Department [2005] EWCA Civ 1363.
[143] I note that the submissions of counsel for the respondents did
not raise the issue of the compatibility of the petitioners' design with the
respondents' requirements in relation to the air draught between the surface of
the water and the underside of the bridge.
Discussion
The legal background
[144] The discussion before me was concerned principally with the law
concerning legitimate expectations and its application to the facts of the
present case, although I was also, at my request, addressed on the case of Oswald v Ayr Harbour Trustees. It
appears to me to be necessary to begin by considering the law relating to the
sea and to harbours, in order to understand the legal context in which any
legitimate expectation would have to arise.
[145] The seabed around the Shetland Islands, including the solum of
the Sound of Bressay, is vested at common law in the Crown, by virtue of the
prerogative (Shetland Salmon Farmers
Association v Crown Estate Commissioners
1991 SLT 166; Smith v Lerwick Harbour
Trustees (1897) 5 SLT 175). Under
the common law, the rights of the Crown are subject to public rights of
navigation and fishing (Crown Estate
Commissioners v Fairlie Yacht Slip
Ltd 1979 SC 156, per Lord President
Emslie at page 169). By virtue of
those public rights, members of the public have a title to object to the
erection of the piers of a bridge in navigable waters, where the piers would
interfere with or obstruct navigation (Orr
Ewing & Co v Colquhoun's Trustees
(1877) 4R (HL) 116). It has been doubted
whether the Crown can convey rights in the seabed which would interfere with
such public rights, without the sanction of Parliament (Lord Advocate v Wemyss
(1899) 2F (HL) 1, per Lord Watson at
page 8; Agnew v Lord Advocate
(1873) 11M 309), although the contrary view has also been expressed (e.g. in
the Shetland Salmon Farmers case).
[146] Public harbours are also vested in the Crown under the common
law, as explained by Erskine's Institute
of the Law of Scotland at II.1.5 and II.6.17:
"Other things, though they be of their own
nature capable of property, are exempted from Commerce in respect of the uses
to which they are destined. Of this last
kind are, first, the res publicae of
the Romans which were common not to all mankind, but to the state or
community; such as navigable rivers,
highways, harbours and bridges etc., the property of which belongs to the state
or kingdom in which they lie, and their use to all the subjects or members of
that kingdom, and to those strangers to whom it allows the liberty of trade,
not only rivers themselves, and their bed, or alveus, but their banks also, are public, in so far as they may be
subservient to the purpose of navigation.
...
All the subjects which were by Roman law
accounted res publicae are, since the
introduction of feus, held to be inter
regalia or in patrimonio principis
as rivers, free ports, and highways ...
But as the regalia of this
sort are little capable of property, and chiefly adapted as the public use, the
King's right in them is truly no more than a trust for the behoof of his
people".
Although that passage refers
to feudal law as the basis of the Crown's right, it appears from the Shetland Salmon Farmers case that the
same result would be arrived at in Shetland (where landownership is based on
udal, rather than feudal, law), although on a different basis.
[147] This position under the common law forms the background to the
legislation of the late eighteenth and, more particularly, the nineteenth centuries,
constituting harbour trustees for the management and improvement of public
harbours. One example of such
legislation is the 1877 Act constituting the respondents' predecessors. Another is the legislation which was at issue
in the Ayr Harbour Trustees case. In that case,
the trustees had exercised powers of compulsory purchase to acquire land. In order to reduce the compensation payable,
they had undertaken not to use their powers in respect of the land in question
in such a way as to interfere with the former owner's access to the harbour
from his remaining land. The question
which arose was expressed by Lord President Inglis (10 R 472 at pages 480-481)
as being
"whether the defenders, as statutory trustees
or commissioners, can bind the trust which they administer by an obligation to
refrain in all time coming from using for certain harbour purposes ground which
they have by compulsory purchase acquired for harbour purposes".
That question was answered
in the negative by the Court of Session.
Lord President Inglis, in whose opinion Lord Justice Clerk Moncreiff
and Lord Mure concurred, emphasised the background of public rights, and the public
interest involved in the fulfilment by the harbour trustees of the statutory
purposes of their trust. In that
connection, the Lord President observed (at pages 481-482) that
"the defenders are nothing but Parliamentary
Commissioners for managing and improving this harbour, which, but for the
provisions of these Acts, or some previous grant, would, like other res publicae, remain vested in the Crown
for the benefit of the nation.... In the exercise of their powers they are merely
the commissioners or agents of the Crown and of Parliament, and the statutes
constitute their mandate, the terms of which they must implicitly follow.... Neither have they any power after acquiring
land for harbour purposes to erect servitudes over it in favour of adjoining
landowners or others, or to make or save money by giving to private parties
such an interest in the land as will prevent its being applied in time coming
to any of the harbour purposes for which at any time, however distant, it may
come to be required".
[148] In the House of Lords, Lord Watson explained the effect of the
harbour legislation as follows (at page 90):
"Section 10 is permissive in this sense only,
that the powers which it confers are discretionary, and are not to be put in
force unless the trustees are of opinion that they ought to be exercised in the
interest of those members of the public who use the harbour. But it is the plain import of the clause that
the harbour trustees for the time being shall be vested with, and shall avail
themselves of, these discretionary powers, whenever and as often as they may be
of opinion that the public interest will be promoted by their exercise."
[149] In the later case of Birkdale
District Electricity Supply Co v Southport
Corporation, where the circumstances were very different, the decision in
the Ayr Harbour Trustees case was
distinguished, but without questioning what the Earl of Birkenhead described
(at page 364) as
"a well established principle of law, that if
a person or public body is entrusted by the Legislature with certain powers and
duties expressly or impliedly for public purposes, those persons or bodies
cannot divest themselves of these powers and duties. They cannot enter into any contract or take
any action incompatible with the due exercise of their powers or the discharge
of their duties".
Lord Sumner explained the
decision in the Ayr Harbour Trustees
case (at page 371) on the basis that the trustees "were to sterilize part of
their acquisition, so far as the statutory purpose of their undertaking was
concerned."
[150] Later authorities (such as British
Transport Commission v Westmorland
County Council [1958] AC 126) support that approach. Although the courts have not readily allowed
public authorities to resile from apparent obligations which have been
voluntarily assumed, they have done so where the apparent obligation was
incompatible with the authority's core responsibilities. The continuing validity of the principle
expressed by Lord Birkenhead is demonstrated by the Ng Yuen Shiu case, where Lord Birkenhead's dictum was cited (at
page 638). It is also illustrated, in a
context closer to that of the present case, by Rowland v Environment Agency,
where it was held that a legitimate expectation could not oblige the respondent
authority to act as if public rights of navigation did not exist.
[151] Turning next to the case law concerned with legitimate
expectations, I was referred by counsel to a large number of authorities in
which a variety of approaches have been adopted. In order to avoid confusion, it appears to me
to be necessary to consider the most important cases in chronological order, so
that the evolution of this rapidly developing area of the law can be
understood. It is also necessary to
emphasise that, although it may be useful for the purposes of taxonomy to treat
the case law on legitimate expectations as forming a distinct body of law, in
reality it is intermeshed with the wider body of public law and depends on
principles of broader application. In a
case with unusual facts, which may not readily fit into the framework or
compartments suggested in some of the cases, it is important not to lose sight
of those broader principles. I should
also note at the outset that the discussion before me proceeded on the basis
that the authorities cited, virtually all of which were English, should be
followed in Scotland. I have no difficulty in proceeding on that
basis in the present case, but I would observe that, in other circumstances, differences
between the law of England and that of Scotland in relation to the effect
of promises might require to be considered.
[152] When the concept of legitimate expectation was introduced into
our public law by Lord Denning in Schmidt
v Secretary of State for Home Affairs
[1969] 2 Ch 149, it was in the context of what Lord Diplock had in Council of Civil Service Unions v Minister for the Civil Service [1985] AC 374 called procedural impropriety: the
expression "legitimate expectation" was used by Lord Denning to describe one of
the circumstances in which, following Ridge
v Baldwin [1964] AC 40, the common
law would require a person affected by an administrative decision to be afforded an opportunity to make
representations. So understood, the
concept was narrower in scope than the concept of the same name which entered
our law a few years later as part of the acquis
communautaire, and which had its origins in European administrative law,
notably in the German concept of Vertrauenschutz: a concept based on the value of legal
certainty, with substantive as well as procedural implications.
[153] In the Ng Yuen Shiu case,
the Privy Council treated the concept of legitimate expectation (at page 638)
as a "principle that a public authority is bound by its undertakings as to the
procedure it will follow, provided they do not conflict with its duty". Over time, however, it came to be accepted
that situations in which a public body had created an expectation as to its
future conduct could give rise to issues warranting judicial review of the
substance of the decision in question.
This development took place initially through the widening of the
concept of "fairness", introduced into the law in the context of procedural
issues, so as to have a substantive content:
R v Secretary of State for the Home
Department ex parte Khan [1984] 1 WLR 1337.
In some cases, the issues were also approached under what Lord Diplock
had described as the "irrationality" head of judicial review, on the basis that
a public body's resiling from an undertaking which it had given, or departing
from a policy which it had published, could in certain circumstances be
unreasonable or could violate accepted moral standards. The issues were also approached in some cases
in terms of the concept of abuse of power.
[154] The latter approach was applied by the House of Lords in the
leading case of R v Inland
Revenue Commissioners ex parte Preston [1985] AC 835, which
concerned an allegation that the Revenue had gone back impermissibly on its
promise not to reinvestigate certain aspects of a taxpayer's affairs. Lord Templeman, giving the leading judgment,
said (at pages 866-867):
"In principle I see no reason why the
appellant should not be entitled to judicial review of a decision taken by the
commissioners if that decision is unfair to the appellant because the conduct
of the commissioners is equivalent to a breach of contract or a breach of
representation. Such a decision falls
within the ambit of an abuse of power for which in the present case judicial
review is the sole remedy and an appropriate remedy. There may be cases in which conduct which
savours of breach of contract or breach of representation does not constitute
an abuse of power. There may be
circumstances in which the court in its discretion might not grant relief by
judicial review notwithstanding conduct which savours of breach of contract or
breach of representation. In the present
case, however, I consider that the appellant is entitled to relief by way of
judicial review for 'unfairness' amounting to abuse of power if the
commissioners have been guilty of conduct equivalent to a breach of contract or
breach of representation on their part".
It is apparent that, at that
stage of the law's development, the relevant principles of public law were
understood as being closely analogous to those of private law.
[155] Ex parte Preston was followed by the Divisional
Court in R v Inland Revenue Commissioners ex parte MFK Underwriting Agents Ltd,
where a taxpayer sought to rely upon what was claimed to be an undertaking by
the Revenue not to enforce full tax liability in certain circumstances. Bingham LJ noted (at page 1568) that it
had not been suggested in Ex parte
Preston that the bargain allegedly made would have been a breach of the
Revenue's statutory duty, and continued:
"[T]he applicants here accept that they must fail if the revenue could
not lawfully make the statements or representations which (it is said) it
did. So if, in a case involving no
breach of statutory duty, the revenue makes an agreement or representation from
which it cannot withdraw without substantial unfairness to the taxpayer who has
relied on it, that may found a successful application for judicial review".
His Lordship accepted (at page 1569) that the
assurances which the Revenue was said to have given were not inconsistent with
its statutory duties. His Lordship continued
(at pages 1569-1570):
"I am, however, of the opinion that in assessing the meaning, weight
and effect reasonably to be given to statements of the revenue the factual
context, including the position of the revenue itself, is all-important .....No
doubt a statement formally published by the Inland Revenue to the world might
safely be regarded as binding, subject to its terms, in any case falling
clearly within them. But where the
approach to the revenue is of a less formal nature a more detailed inquiry is
in my view necessary. If it is to be
successfully said that as a result of such an approach the revenue has agreed
to forgo, or has represented that it will forgo, tax which might arguably be
payable on a proper construction of the relevant legislation it would in my
judgment be ordinarily necessary for the taxpayer to show that certain
conditions had been fulfilled ....First it is necessary that the taxpayer should
have put all his cards face upwards on the table. This means that he must give full details of
the specific transaction on which he seeks the revenue's ruling ...It means that
he must indicate to the revenue the ruling sought....It means that the taxpayer
must make plain that a fully considered ruling is sought. It means, I think, that the taxpayer should
indicate the use he intends to make of any ruling given....Secondly, it is
necessary that the ruling or statement relied upon should be clear, unambiguous
and devoid of relevant qualification.
In so stating these requirements I do not, I hope, diminish or
emasculate the valuable, developing doctrine of legitimate expectation. If a public authority so conducts itself as
to create a legitimate expectation that a certain course will be followed it
would often be unfair if the authority were permitted to follow a different
course to the detriment of one who entertained the expectation, particularly if
he acted on it. If in private law a body
would be in breach of contract in so acting or estopped from so acting a public
authority should generally be in no better position. The doctrine of legitimate expectation is
rooted in fairness. But fairness is not
a one-way street. It imports the notion
of equitableness, of fair and open dealing, to which the authority is as much
entitled as the citizen."
[156] These observations
were made in a particular context, that of dealings between taxpayers and the
Revenue. The approach adopted by Bingham
LJ appears to me however to be of wider application, in so far as it emphasises
the importance of paying close attention to the factual context in determining
the meaning, weight and effect of statements made by public bodies or
officials, and then deciding whether, in the light of those statements, the
decision or action in question is unfair and should not be permitted. In that regard, two of the particular matters
mentioned by Bingham LJ will usually, if not invariably, be relevant. The first is whether the public body was made
aware by the other party of all relevant circumstances: relevant, in particular, to its decision
whether to make a representation, to the level within its organisation at which
such a decision would be taken, and to the terms in which any such
representation would be made. Those
circumstances will usually include the use which is to be made of the
representation sought. The second matter
is whether the representation was clear, unambiguous and unqualified. It has been repeatedly held to be essential
to the existence of a legitimate expectation with substantive effects that
there should have been a clear and unambiguous representation upon which it was
reasonable for the representee to rely. Examples include R v Jockey Club ex parte RAM
Racecourses Ltd, R v Devon County Council ex parte Baker, Docherty v City of Edinburgh Council, R v Falmouth
& Truro Port Health Authority ex parte South West Water Ltd, R (ABCIFER) v Secretary of State for Defence and Rowland v Environment Agency. It is however necessary to bear in mind, in
deciding whether a representation was sufficiently clear and unambiguous to
justify reliance upon it, that the representation has to be construed in the
context in which it was made, as Lord Hoffmann observed in R (Zeqiri) v Secretary of State for the Home Department (at paragraph 44). It is also necessary to remember that more
general principles of administrative law may prevent a public body from
departing from its previous position even in the absence of a clear and
unambiguous representation, in unusual circumstances such as those considered
in R v Inland Revenue Commissioners ex parte Unilever plc, discussed below.
[157] In the Jockey Club case, the applicant was a
racecourse owner who claimed to have a legitimate expectation that it would be
allocated race meetings in accordance with a report adopted by the Jockey
Club. Stuart Smith LJ, in whose judgment
Simon Brown LJ concurred, held that there were five conditions which
required to be satisfied in that case before the application could succeed:
(1) a
clear and unambiguous representation;
(2) that
since the applicant was not a person to whom any representation had been
directly made, it was within the class of persons who were entitled to rely on
it, or at least that it was reasonable to rely upon it;
(3) that
it did rely on it;
(4) that
it did so to its detriment; and
(5) that
there was no overriding interest which entitled the Jockey Club to change its
policies to the detriment of the applicant.
[158] The
five-fold test adopted in the Jockey Club
case formed the framework of the petitioners' submissions in the present
case: they proceeded on the basis that
the court's function at this stage of the present case was to decide whether
the first, third and fourth conditions were met (the second condition not being
in issue), leaving the fifth condition to be considered, if need be, at a
second hearing. In a case such as the
present, with a number of unusual features, it seems to me to be necessary to
be guided primarily by the general principles of which the five-fold test
adopted in the Jockey Club case was merely
a particular application.
[159] In that
regard, it is relevant to note the case of Ex
parte Unilever plc, which is a rare example of an application based on an
expectation induced by a public body succeeding in the absence of a clear and
unequivocal representation. The Court of
Appeal concluded in that case that for the Revenue to refuse to accept a late
claim for loss relief, without prior warning, when for many years previously it
had exercised its discretion to accept such claims, would be so unfair as to
amount to an abuse of power. Simon Brown
LJ observed that, although the absence of an unqualified and unambiguous
representation meant that the applicants could not bring themselves within the
category of legitimate expectation with which the MFK and Jockey Club cases
had been concerned, the broader principle operating in this field was that of irrationality
as described by Lord Diplock in the CCSU
case. His Lordship continued (at page
695):
"Unfairness amounting to an abuse of power as envisaged in Preston and the other Revenue cases is
unlawful not because it involves conduct such as would offend some equivalent
private law principle, not principally indeed because it breaches a legitimate
expectation that some different substantive decision will be taken, but rather
because either it is illogical or immoral or both for a public authority to act
with conspicuous unfairness and in that sense abuse its power. As Lord Donaldson MR said in R v ITC,
ex p TSW (1992) Times, 7 February:
'The test in public law is fairness, not an adaptation of the law of
contract or estoppel'.
In short, I regard the MFK
category of legitimate expectation as essentially but a head of Wednesbury unreasonableness, not
necessarily exhaustive of the grounds upon which a successful substantive
unfairness challenge may be based".
The distinction drawn by his Lordship between the
relevant principles of public law and the private law concepts of contract and
estoppel (or, in Scotland, personal bar) has proved
to be important to the development of the law.
I note also his Lordship's use of the expression "conspicuous
unfairness" to describe the circumstances in which the court would
intervene. His Lordship distinguished
(at page 697) between:
"on the one hand mere unfairness - conduct which may be characterised
as 'a bit rich' but nevertheless understandable - and on the other hand a
decision so outrageously unfair that it should not be allowed to stand".
The expression "conspicuous unfairness" was adopted
also by Lord Hoffmann, with whose speech Lord Mackay of Clashfern, Lord Millett
and Lord Rodger of Earlsferry expressed their agreement, in the Zeqiri case, at paragraph 44, and by the
Court of Appeal in the ABCIFER case,
at paragraph 72. The Court is not,
therefore, entitled to intervene on this ground merely because it considers
that a decision can be criticised.
[160] A review
of the previous case law was carried out by the Court of Appeal in R v North
and East Devon Health Authority, ex parte Coughlan, which concerned a decision
by a health authority to resile from a promise given to a severely disabled
patient that a nursing home would be her home for life. Lord Woolf MR, delivering the judgment of the
Court, said (at paras.56-57):
"56. What is still the subject
of some controversy is the court's role when a member of the public, as a
result of a promise or other conduct, has a legitimate expectation that he will
be treated in one way and the public body wishes to treat him or her in a
different way. Here the starting point
has to be to ask what in the circumstances the member of the public could
legitimately expect ...This can involve a detailed examination of the precise
terms of the promise or representation made, the circumstances in which the
promise was made and the nature of the statutory or other discretion.
57. There are at least three
possible outcomes. (a) The court may
decide that the public authority is only required to bear in mind its previous
policy or other representation, giving it the weight it thinks right, but no
more, before deciding whether to change course.
Here, the court is confined to reviewing the decision on Wednesbury grounds ...(b) On the other
hand the court may decide that the promise or practice induces a legitimate
expectation of, for example, being consulted before a particular decision is
taken ...(c) Where the court considers that a lawful promise or practice has
induced a legitimate expectation of a benefit which is substantive, not simply
procedural, authority now establishes that here too the court will in a proper
case decide whether to frustrate the expectation is so unfair that to take a
new and different course will amount to an abuse of power. Here, once the legitimacy of the expectation
is established, the court will have the task of weighing the requirements of
fairness against any overriding interest relied upon for the change of policy".
[161] In
relation to that passage, it is important to note in the present case that the
only outcome with which either party is concerned is what Lord Woolf described
as outcome (c): in other words, the
question the court is being asked to determine is whether lawful
representations have been made by the respondents which have induced in the
petitioners a legitimate expectation of a substantive benefit, which it would
be an abuse of power for the respondents to frustrate in the absence of a
sufficiently overriding interest. If the
court finds, at the stage of the first hearing, that the petitioners have such
a legitimate expectation, the task of weighing the requirements of fairness
against any competing interest is, as I have explained, to be dealt with at a
second hearing. Although that position may
not appear clearly from the pleadings, it was made clear in counsel's
submissions.
[162] Returning
to Ex parte Coughlan, it will be
noted that in the passage quoted above, the court stated that a substantive
legitimate expectation could arise as a consequence of "a lawful promise or practice" (emphasis added). The question whether an expectation as to the
future conduct of a public authority should have substantive as opposed to
procedural effects is another way of asking, first, whether a public authority
should be able to bind itself as to its future exercise of its discretion, and
secondly, whether such an authority should be able to bind itself to act ultra vires. The Court of Appeal's approach in Ex parte Coughlan, consistently with
earlier authority since Ex parte Preston,
implicitly answered the first question in the affirmative (to the extent that a
public authority may be able to bind itself in certain circumstances), and the
second question in the negative.
[163] Some emphasis was placed by counsel for
the petitioners on the case of R v Secretary of State for Education and
Employment ex parte Begbie, which was decided by the Court of Appeal
shortly after Ex parte Coughlan. The case was cited in support of the
proposition that a legitimate expectation could be enforced by the court even
in the absence of detrimental reliance.
To my mind, however, the case illustrates the importance of detrimental
reliance in the type of case with which I am concerned.
[164] Ex parte Begbie concerned a letter
written by the Secretary of State stating that, where a child of primary school
age held a place under the assisted places scheme at an independent school
providing both primary and secondary education, the child would continue to
receive funding under the scheme until the completion of secondary
education. Under the relevant statutory
provision, such a child was to continue to receive funding only until the end
of his or her primary education, unless the Secretary of State decided "in view
of any particular circumstances relating to that pupil" that a longer period
should apply. A further letter,
explaining the statutory position, was sent a few weeks after the first
letter. There had been no detrimental
reliance on the first letter. An
application for judicial review, seeking in effect to enforce the undertaking
given in the first letter, was unsuccessful.
The principal ground of refusal was that "any expectation must yield to
the terms of the statute under which the Secretary of State is required to act"
(per Peter Gibson LJ at
page 1125). A further ground was
the absence of detrimental reliance.
Although it was accepted that there were situations where detrimental
reliance was not necessary (e.g. where an existing practice gave an individual
a legitimate expectation of being treated in the same way as others had been
treated, on the basis of consistency), it was said to be "very much the
exception, rather than the rule, that detrimental reliance will not be present
when the court finds unfairness in the defeating of a legitimate expectation" (per Peter Gibson LJ at page 1124).
[165] The
issue of reliance was considered again in R
(Bibi) v Newham LBC, where the Court
of Appeal adopted (at paras 29-30) a passage from Professor P.P. Craig's Administrative Law:
"(5) Detrimental reliance will
normally be required in order for the claimant to show that it would be
unlawful to go back on a representation.
This is in accord with policy, since if the individual has suffered no
hardship there is no reason based on legal certainty to hold the agency to its
representation. It should not, however,
be necessary to show any monetary loss, or anything equivalent thereto .....
(6) Where an agency seeks to depart from an established policy in
relation to a particular person detrimental reliance should not be
required. Consistency of treatment and
equality are at stake in such cases and these values should be protected
irrespective of whether there has been any reliance as such" (5th edition,
page 652).
[166] The
judgment of the Court of Appeal in Ex parte
Bibi is also of importance for the general approach which was adopted. The court proposed (at paragraph 19) a
three stage approach to all legitimate expectation cases:
"The first question is to what has the public authority, whether by
practice or by promise, committed itself;
the second is whether the authority has acted or proposes to act unlawfully
in relation to its commitment; the third
is what the court should do".
The Court observed that the question whether a
representation had been made without lawful power would be relevant to the
first stage of this approach. The
question whether there had been detrimental reliance was regarded as relevant
to the second stage; and it was in that
regard that the court cited the passage by Professor Craig which was
quoted above. It was also at the second
stage that other factors relevant to the lawfulness of the public body's
decision to adopt a course of action at variance with its previous
representation would be taken into account.
In that regard, the court observed (at paragraph 40):
"It is in our judgment a mistake to isolate from the rest of administrative
law cases those which turn on representations made by authorities".
I respectfully agree.
[167] The
three-stage approach adopted in Ex parte
Bibi is a logical way of approaching the problems involved in this type of
case. In the present case, however, I
was invited to deal with the issue of detrimental reliance at the present
stage, as I have explained, and to leave over to a second hearing, if need be,
the question whether there was an overriding interest sufficient to justify the
respondents' decision. Although the
approach I was invited to adopt is different from that adopted in the Bibi case, it has the pragmatic virtue
of enabling the court to deal at the present stage with all matters which the
parties are agreed can be addressed on the basis of the material presently
before the court.
[168] The case
of R (Reprotech (Pebsham) Ltd) v East Sussex County Council is important
for its clarification that public law in this area is conceptually distinct
from the private law concept of estoppel (or personal bar), the fundamental
point of difference being that the public interest in the exercise of public
functions, and the effect of their exercise on members of the public who are
not parties to the process before the court, require the law to adopt a
different approach from that which is appropriate where only the interests of
those directly engaged need be considered.
In the case, the applicant company had purchased a waste treatment plant
in order to use it to generate electricity, following an expression of opinion
by the county planning officer that such a use would not involve a material
change of use requiring planning permission, and a subsequent resolution by the
respondent planning authority which proceeded on the same basis. The planning authority later decided that
planning permission was in fact required.
On an application for judicial review, the lawfulness of the planning
authority's decision was upheld by the House of Lords. Giving the leading judgment,
Lord Hoffmann observed that a statutory procedure existed whereby a person
could obtain a determination by the planning authority of the question whether
planning permission was necessary for a proposed change of use. That procedure had not been followed, but the
applicant sought to give the resolution the same effect as a statutory
determination. The procedure for making
a statutory determination had a number of important features, which included an
opportunity for members of the public to make representations, and an
opportunity for the Secretary of State to call the matter in for his own
determination. Lord Hoffmann observed
(at paragraph 29):
"It is, I think, clear from this brief summary that a determination is
not simply a matter between the applicant and the planning authority in which
they are free to agree on whatever procedure they please. It is also a matter which concerns the
general public interest and which requires other planning authorities, the
Secretary of State on behalf of the national interest and the public itself to
be able to participate".
That passage appears to me to be relevant also to the
present case, for the reasons explained below.
[169] The case
of South Bucks District Council v Flanagan was cited by counsel for the
respondents as deciding that a legitimate expectation based on a representation
made on behalf of a public body only arose if the person making the
representation as to that body's future conduct had actual or ostensible
authority to make it on its behalf. The
case proceeded on a concession, and the issue was not fully discussed. It appears to have been approached on the
basis of the law of agency. In other
cases involving public authorities, however, it may be necessary to bear in
mind the law governing the delegation of statutory powers. A public authority can of course employ
agents in the execution of its powers;
but the question whether a representation made by an agent (or, for that
matter, by an official) is binding upon the authority may raise questions
relating to the delegation of discretionary powers. In particular, if a public body cannot
lawfully delegate its power of decision-making to a particular person, a
purported delegation to that person will be ultra
vires, and cannot be rendered intra
vires by saying that the person in question had ostensible authority to act
as the body's agent. Since the law
recognises no legitimate expectation (at present, at least) that a public body
will act ultra vires, it cannot, as
it seems to me, give effect to a legitimate expectation founded upon an ultra vires delegation. Equally, the law as it stands cannot,
ordinarily at least, give effect to a legitimate expectation created by a
representation made by an employee or agent of a public authority, even where
delegation would be competent, if there has in fact been no lawful delegation,
since statutory powers can be lawfully exercised only by the body on which they
were conferred, or by a person to whom that body has lawfully delegated the
exercise of its powers. There is a
somewhat equivocal body of case law concerned with this issue, which is
summarised in De Smith, Woolf and Jowell, Judicial Review of Administrative Action, 5th edition,
pages 565-569 (and is also considered in Sales and Steyn, "Legitimate
Expectations in English Public Law: An
Analysis" [2004] PL 564 at pages 577-578) but it was not discussed before me,
and it does not appear to be relevant to the present case. Finally, even where there has been a lawful
delegation, the representation made by the delegatee can only bind the
authority if "it lay within the powers of [the authority] both to make the
representation and to fulfil it", as was said in Bibi at paragraph 46.
In that regard, I note that there is a debate (reflected in the judgment
of May LJ in Rowland v Environment Agency) as to whether the
law should be developed so as to allow an ultra
vires representation to bind in certain circumstances, as the European
Convention on Human Rights may in some cases require. I was not addressed in relation to that
debate; and no issue of Convention rights
is raised in the present case.
[170] Finally,
the case of Royal Borough of Windsor and
Maidenhead v Dewar was cited as a
rare example of one public authority seeking to assert a legitimate expectation
against another: something which Maurice
Kay J expressly assumed (at paragraph 13), but did not decide, was
possible. The case is also relevant in
that the person who had made the representation did not have authority to bind
the body in question. Maurice Kay J
treated the question of authority as relevant to the question whether the
applicant body could reasonably rely on the representation, stating (at
paragraph 13):
"I do not consider it reasonable for a public authority to assume
without more that a member, albeit the Chairman, of another public authority
with which it is connected is in a position to obligate that other public
authority in circumstances such as those prevailing in this case ...[I]t is more
difficult for a public authority [than for a member of the public] to resist
the suggestion that it ought to have known that the person making the
representation had no power to bind his principal".
The present case
[171] In
considering how these legal principles apply to the present case, it is
necessary to begin by examining the factual and legal context. The petitioners desired to construct a bridge
across the Sound of Bressay. In order to
do so, they had to acquire certain land by compulsory purchase, and to obtain
planning permission in respect of the landward parts of the bridge and the
connecting roads. Since the bridge was
to cross directly over a navigation channel within the harbour, and its piers
were to stand on the seabed there, with possible implications for public rights
of navigation and for the future operation of the harbour, those aspects of the
bridge also required authorisation. Such
authorisation had to be granted by the respondents, under section 10 of the
1974 Order, or by the Scottish Ministers on an appeal under section 12, subject
to the proviso to section 13 (applicable where the works were specifically
authorised under any other enactment). One of the effects of such authorisation, in
terms of section 10(1), would be to render lawful any interference which
there might be with public rights of navigation or other public rights, and
therefore to extinguish the right which members of the public would otherwise
have had to object to such interference.
The petitioners also required the authorisation of their roads scheme
under the 1984 Act. The respondents were
the primary decision-making body under the 1974 Order, and were also potential
objectors to the planning application and the roads scheme. In relation to the latter, an objection by
the respondents as the navigation authority would have particularly serious
consequences, since it would necessitate the promotion of private legislation.
[172] As a public authority with ready access to legal advice, engaged
in a major project of this nature, the petitioners can be taken to have been
aware of the relevant statutory provisions and other relevant legal
principles. They would know, in
particular, that the 1974 Order laid down in section 10 a statutory procedure
whereby a determination could be obtained from the respondents as to whether
the piers of the bridge would be permitted to be constructed in particular
locations. Before such a determination
was made, the petitioners would have to notify the public of their proposal by
advertisement, so as to allow objections to be made, in accordance with section
10(2). The respondents would have to
take any such objections into consideration before making their determination,
in accordance with section 10(3). Just
as in the Reprotech case, the
petitioners could not obtain a binding determination by the respondents of
their entitlement to construct piers in any given location without complying
with section 10: they could not, even
with the agreement of the respondents, substitute an informal procedure for the
procedure required by statute. The same
result would also follow from the principle applied in Rowland v Environmental
Agency, if the construction of the piers in the locations where the
petitioners wished to construct them would interfere with public rights of
navigation: those rights could not be
extinguished as a consequence of informal representations, but only by
following the statutory procedure provided by section 10 (or otherwise by
promoting private legislation).
[173] The question then arises as to what legal effect, in principle,
any informal representation by the respondents as to their requirements could
have. For the reasons just discussed,
such a representation could not bind the respondents to grant a works licence,
since they would require to determine any application for such a licence in the
light of any objections received. The
argument of the petitioners, as I understand it, is that although the
respondents could not be bound to grant a works licence, they would
nevertheless be bound by what they had earlier said about their dredging
intentions, in order to fulfil the petitioners' reasonable expectations: in other words, they would not be bound to
allow the petitioners to build their piers in given locations, but they would
nevertheless be bound themselves not to carry out dredging works in those
locations. I find it difficult to
reconcile this approach with the intended purpose of section 10. Section 10(3) provides that the respondents
"shall take into consideration any objection".
The respondents cannot therefore properly disregard any objection to the
works licence application which has implications for dredging requirements in
the area where the application proposes that bridge piers should be
constructed, on the basis that a previous representation has prevented them from
dredging in that area (cf. Stringer v
Minister of Housing and Local Government
[1970] 1 WLR 1281): if the position were
otherwise, the respondents would have pre-empted the statutory procedure, and
undermined the statutory consultation exercise, by their informal dealings with
the petitioners (cf. Reprotech). This point has implications for the
petitioners' legitimate expectations.
If, in view of the terms of section 10(3), the petitioners could not
reasonably expect the respondents to disregard objections which had
implications for dredging requirements in the areas where the petitioners
proposed to construct the piers, then equally, as it seems to me, the
petitioners could not reasonably understand that the respondents had committed
themselves to excluding the areas in question from future dredging
operations. It would make no sense for
the respondents to determine the works licence application on the basis of
their current assessment of dredging requirements, if they were at the same
time prevented from carrying our dredging on the basis of that assessment,
because they were bound by a representation made on the basis of an earlier
assessment.
[174] The difficulty with the petitioners' approach can also be
analysed in terms of the principle exemplified by the Ayr Harbour Trustees case.
In terms of section 5 of the 1877 Act, the respondents are required
to be the "conservators of the harbour", in the public interest. In terms of section 37, their undertaking is
to consist of "the improving, deepening and cleansing of the harbour or of such
portions thereof as the trustees may in their discretion think fit". For the purposes of that undertaking, the
respondents are given more specific powers, including the power under section
9(2) of the 1974 Order to "deepen, widen, dredge, scour, cut and improve the
seabed of the harbour". These are
necessarily powers of a continuing nature, not to be exercised once and for all
by the members of the respondents' board in office at any particular time, but
to be exercised by them and their successors in office, from time to time, in
accordance with the requirements of the harbour at that time. The harbour includes the locations where the
petitioners wish to construct the piers of the bridge. So far as appears from the legislation to
which the court's attention has been drawn, the respondents have no power to
divest themselves of any part of their undertaking, or to abdicate their
responsibility as conservators of the harbour, except insofar as that might be
said to be the practical consequence of their decision to grant a works licence
under section 10 of the 1974 Order. The
latter provision, by empowering the respondents to authorise the construction
or placing of works in the harbour, notwithstanding any interference with
public rights of navigation or other public rights, might be regarded as enabling
them in effect to sterilise part of the harbour as far as certain harbour
purposes are concerned, after public advertisement of the application and the
consideration of any objections. Subject
to that qualification, the respondents are not given any power to determine
that any portion of the harbour is to fall outside the scope of their
undertaking and is, in particular, to be incapable of being improved or deepened. The implication of the petitioners' argument,
however, is that the respondents could bind themselves informally not to dredge
certain areas of the harbour for the indefinite future.
[175] In that regard the submission of counsel for the petitioners was
uncompromising: that any information
provided to the petitioners by the respondents concerning their dredging plans
was implicitly final and immutable, since a bridge is a permanent
structure. It has occurred to me that
counsel might have advanced a seemingly more modest proposition: that the respondents implicitly undertook not
to implement different dredging proposals until the petitioners' various
applications had been determined. Such a
contention would however raise similar difficulties. The implicit undertaking would, in the first
place, be in respect of an indefinite period, which could be expected to last
several years but whose duration could not be predicted. Secondly, and more importantly, the respondents
would be committing themselves not to exercise their statutory power to dredge
the areas in question not only for the period until the petitioners' statutory
applications had been determined, but also for an indefinite period thereafter,
in the event that the applications were to be granted. That contention, as it seems to me, would
raise the same problems as the submission actually made.
[176] The only substantial point of difference from the Ayr Harbour Trustees case would appear
to be that the latter case concerned an undertaking in respect of a part of the
harbour which was being compulsorily acquired, whereas the present case
concerns an alleged undertaking in respect of existing parts of the
harbour. That difference does not appear
to me to be material. As in the Ayr Harbour Trustees case, it appears to
me that the respondents cannot competently divest themselves and their
successors of their statutory powers in respect of areas of the harbour, except
to the extent that section 10 permits them in effect to do so. In the language used by Lord Sumner in the Birkdale case, the respondents cannot
sterilise (or partly sterilise) part of their undertaking by agreeing
informally to exclude areas of the harbour (in particular, parts of the channel
through which all vessels entering the harbour from the north must pass) for
the indefinite future from the ambit of their statutory powers of improvement
and deepening.
[177] For these reasons, the petitioners' argument appears to me to
encounter fundamental difficulties, even before the facts of the case are
considered in greater detail. On such
consideration, however, further difficulties emerge. Taking matters in stages, the petitioners
have never based their case on anything said or done by the respondents prior
to 2003. That can be readily
understood. When Halcrow first sought
information from the respondents for the purposes of a feasibility study, in
the early months of 1999, they were told that, if a bridge were to be created
at Point of Scotland, the "clear width of channel between supports" would
require to be wider than the navigational channel, because of the need for
vessels to swing sharply at that location.
The clear width requested was either 150m or 160m. Halcrow nevertheless provided designs with a
central span of 125m or 160m, measured between pier centres. Later in 1999 the petitioners sought the
respondents' comments on a span of 125m (notwithstanding a reminder that a
clear width of 160m had been requested earlier), addressing their request to
the Lerwick Port Authority. The
respondents' reply, dated 17 November
1999, following a meeting of their board, provided "their
observations at this time" (emphasis
added), and reiterated the need for the main span to have "at least 160m
clearance", in the interests of safety.
Following the petitioners' completion of their feasibility study, the
project team which they then established attempted to persuade the respondents
to agree to a smaller span, in order to reduce costs, but were warned by the
respondents' chief executive that the respondents were liable to require even
more space for navigation.
[178] In their pleadings, and in the submissions of junior counsel, the
petitioners founded on representations said to have been made during 2003. Senior counsel departed from that position,
and accepted that the planning application made in December 2003 had not been
made in reliance on any clear representation as to the respondents' final position. That appears to me to be correct. So far as the Arch Henderson report of
January 2003 is concerned, the contents of the report comprised advice to the
respondents from the engineers they had consulted. On receiving a copy of the report, the
petitioners acknowledged that the respondents had not adopted any position
regarding it. It is also relevant to
note that the report recommended a minimum clear width of 160m, depending on
side slope stability characteristics to be determined on site investigation. The figure of 160m comprised a dredged
channel 120m wide, the side slopes of the channel, and a berm between each side
slope and the nearest pier. So far as
the remainder of 2003 is concerned, it is agreed that "the only dredging
proposals which the respondents were considering
carrying out as their next dredging
campaign were those contained in the Arch Henderson Report.... and that this was
made known to the petitioners" (emphasis added). That agreement does not take the petitioners'
case any further forward.
[179] The next material development was the planning application made
by the petitioners in December 2003. As
I have mentioned, it was accepted in argument on behalf of the petitioners that
the application had not been made in reliance on any clear representation as to
the respondents' final position; and,
for the reasons I have explained, that appears to me to be correct. That is also the implication of the letter
sent by the petitioners to the respondents' chief executive on 18 December 2003. It explained that the planning application
was being made at that time in order to meet the petitioners' timetable, but
reassured the respondents:
"In terms of the design there are
a number of options available to adjust pier positions.... [T]he final detail
surrounding the outstanding issues can be incorporated in the final
design...[T]he Council... have to go forward with a proposal.. and then take on
board, as far as possible, amendments to deal with concerns or objections
expressed... [T]his letter is sent to advise you of our intentions while giving
reassurance that your very real concerns will be fully addressed".
[180] One implication of that letter was that the drawings accompanying
the planning application did not constitute the final design, and that the
positions of the piers, in particular, could be adjusted. There was also an implicit acknowledgement
that the respondents were known to have concerns about the design shown in the
drawings. Despite the terms of that
letter, it appears from the petitioners' pleadings and submissions that the
design of the bridge was in reality fixed in all material respects once the
planning application was made. It was
explained in counsel's submissions that the location of the central piers was
critical to the design of the bridge and the alignment of the connecting roads,
and that the planning application (which, as explained earlier, was for
detailed planning permission), the compulsory purchase order and the roads
scheme were therefore inter-dependent.
That is reflected in the petitioners' pleadings, which draw no distinction
between "the necessary statutory consents", and proceed on the basis that
detrimental reliance began when "the petitioners commenced their statutory
consents process on 23 December 2003"
by applying for planning permission. In
view of the concession in argument that the planning application was not made
in reliance upon any clear representation as to the respondents' final
position, counsel for the petitioners had no alternative but to attempt to draw
a distinction between the planning application on the one hand, and the roads
scheme and the compulsory purchase order on the other hand, and to argue that
the roads scheme in particular was made in reliance upon representations
post-dating the planning application. The
validity of that argument is considered below.
[181] The planning application itself did not reflect the terms of the
respondents' observations on the bridge proposal on 17 November 1999,
which had stated the need for a clear width of at least 160m, in the interests
of safety. Nor did it reflect the terms
of the Arch Henderson report, which had recommended a space of at least 160m
between the inner faces of the central pier structures, for engineering reasons
designed to protect the dredged channel.
The application was in respect of a bridge with a clear width of
134m. The environmental statement which
accompanied the application however held open the possibility of the width of
the central span being increased after consultation with the respondents.
[182] The next material development was the meeting held on 9 January 2004, and the e-mail sent by
Mr Manson following the meeting, which formed the main plank of the
petitioners' case. I note in the first
place that the purpose of the meeting, as explained in the petitioners' letter
dated 18 December 2003,
was to resolve a technical problem relating to the exact position of the
existing channel. The meeting was
accordingly attended not by officials of the respondents but by staff of their
engineering consultants, Arch Henderson, at whose offices the meeting was
held. The technical problem was
resolved, and a drawing was produced at the meeting showing the agreed position
of the existing channel, and also the position of the proposed new
channel. Mr Manson, an engineering
technician employed by Arch Henderson, then sent the e-mail to the petitioners'
Mr Craigie, with a drawing attached, stating that the location of the existing
channel had been agreed and was as shown on the drawing, and adding:
"We have also shown the line of
the proposed new dredged channel which Lerwick Port Authority wish to carry
out."
At the end of the e-mail,
Mr Manson asked Mr Craigie:
"Please confirm receipt of this
drawing, and the action to incorporate it on all existing and future bridge
drawings".
The drawing showed a "120m wide
proposed channel" with 10m side slopes to either side.
[183] Mr Manson's e-mail and drawing appear to me to be consistent with
the respondent's position during 2003:
that, as agreed in the present case, "the only dredging proposals which
the respondents were considering carrying out as their next dredging campaign
were those contained in the Arch Henderson report". The e-mail took the matter further, by
stating that the respondents wished to carry out that proposal. The e-mail did not however say that the respondents
would refrain for the indefinite future from dredging beyond the limits of the
proposed 120m channel, or that a bridge design which failed to accommodate the
allowance for side slopes shown on the drawing would be acceptable to
them.
[184] For reasons I have already explained, I consider that the
respondents could not give up their power to dredge part of the harbour, in
order to permit a third party to carry out permanent works there, except in
accordance with the procedure laid down in section 10 of the 1974 Order. Even if they had the power to do so, a
decision as to their dredging plans would involve the exercise of their
discretionary powers, notably under section 9(2) of the 1974 Order. The exercise of that discretion could not
competently be delegated to their consulting engineers: a decision under section 9 must be taken by
the authority designated by Parliament, and by no-one else. That principle cannot be obviated by
appealing to the concept of ostensible authority, as previously explained. In any event, an engineering technician
employed by the respondents' engineering consultants would not ordinarily have
ostensible authority to exercise the respondents' power to decide on
appropriate dredging operations. In that
regard, it is material to bear in mind that the petitioners are themselves a
public authority, and indeed a harbour authority. The observations of Maurice Kay J in the Windsor and Maidenhead case, quoted
earlier, appear to me to be apposite:
the present case being a fortiori
of that case, where the representation was made by the chairman of the
authority in question rather than by a third party. The fact that the e‑mail was copied to
the respondents' deputy chief executive does not appear to me to be material,
since there is nothing to indicate that she had any more authority than
Mr Manson to exercise the respondents' power to decide where and when to
carry out dredging operations. The
petitioners knew how to go about obtaining a considered and authoritative
statement of the respondents' position, as their letters of 22 October 1999 and 2 September 2004 demonstrate.
[185] It was accepted by counsel for the petitioners that, in
considering the significance of the e-mail, it is necessary to have regard to
the respondents' objections to the planning application and environmental
statement, submitted a few days later.
Those objections reiterated that the petitioners' design was
unacceptable because the central span was too small; they repeated that there needed to be a minimum
of 160m between the inner edges of the pier structures; and they warned:
"This objection pre-supposes
pre-dredging of the navigational channel by the applicant. If this is not intended to take place then
the minimum 160 metres width referred to will almost certainly need to be
increased in order to accommodate potential future development."
The respondents' objections were
reiterated at their meeting with the petitioners' officials on 17 March 2004, when the head of
the petitioners' bridge project team told the respondents' chief executive that
the movement of the piers so as to widen the channel remained a possible
option, which would be presented to the petitioners.
[186] Some significance was attached by counsel for the petitioners to
the letter sent by Mr Sandison of Arch Henderson to the petitioners'
planning department on 13 April 2004.
The letter does not however appear to me to advance their argument. It stated that Arch Henderson had been
commissioned by the respondents to procure drawings and tender documents for
"proposed dredging and land reclamation works".
The purpose of the letter was to obtain the planning department's
comments on "the proposed works". The enclosed "general drawing for the
proposed works" showed a channel which could be measured as being 120m
wide. The letter did not indicate that
the respondents had decided, or were undertaking, to carry out no other
dredging works in the relevant area for the indefinite future; nor, in any event, was the letter sent by the
respondents.
[187] In discussions between the parties' officials, on 21 April and 6 May 2004, the respondents'
"fundamental requirement for 160m clear span width between pier bases" was
reiterated. The petitioners' officials
again indicated that their current design was not final, and that they were
considering a number of options, including an increase in the width of the
central span.
[188] The final statement on which counsel for the petitioners founded
was the e-mail sent by the respondents' administration manager, another
Mr Sandison, to one of the petitioners' officials, Mr Nicolson, on 17 May
2004. The e-mail was sent in response to
Mr Nicolson's request for a meeting. Since
the suggested date and time were not suitable for the respondents' officials,
Mr Sandison wrote:
"In order to assist you in the
meantime, I detail below a brief response... that may assist you in the meantime.
... I hope that this information is of use to you in the meantime."
The information was, in short, that
"our dredging proposals have not fundamentally changed". This e-mail did not bear to be a formal or
definitive statement of the respondents' position. It did not indicate that the respondents had
decided to carry out no other dredging works in the relevant area for the
indefinite future. There is in any event
nothing to indicate that Mr Sandison had any authority to exercise the
respondents' power to decide where and when to carry out dredging
operations.
[189] In relation to Mr Sandison's statement, as in relation to the
other statements on which the petitioners claim to have relied, it may well be
that the petitioners could reasonably have believed that the respondents
intended to carry out particular dredging works. That does not however appear to me to be the
relevant issue. The question is whether
it was reasonable for the petitioners to act on the basis that the respondents
had lawfully committed themselves to carrying out particular dredging works and
only those works; and therefore, by
implication, to not dredging the other areas of the seabed where the
petitioners proposed to locate the piers of the bridge.
[190] One week after detailed planning permission was deemed to have
been granted on the basis of the drawings attached to the planning application,
the petitioners made the roads scheme.
This was relied on by counsel for the petitioners as demonstrating
detrimental reliance on the legitimate expectation supposedly created by the
various statements which I have discussed.
Counsel did not however put forward any basis for establishing
detrimental reliance which was specific to the roads scheme. Counsel did not, for example, have any
information as to the amount of any expenditure involved in the roads scheme. Nor did counsel indicate any respect in which
the design of the roads scheme differed from the design in respect of which the
planning application had been made. So
far as the design was discussed in argument, it appears to have been the same; and the implication of counsel's submissions
about the dependence of the entire design on the location of the central piers
was that the design on which the various statutory applications were based had
been fixed by the time the planning application was made. That is also the implication of the
petitioners' averments referring to "the final design of the proposed bridge in
respect of which the petitioners are now seeking planning consent", and to the
unreasonableness of the respondents' believing "that the design of the bridge
was not fixed... after the statutory consents process had commenced" (the
petitioners having "commenced the statutory consents process on 23 December 2003 by issuing a Notice
of Intention to Develop"). In the
circumstances, the petitioners appear to me to have failed to establish
detrimental reliance.
[191] The subsequent events can be dealt with relatively briefly. In July 2004 the respondents instructed port
and marine consultants, ELP, to carry out an assessment of the navigational
impact of the proposed bridge. It was
that assessment which led to the respondents' decision to undertake more
extensive dredging than they had been proposing earlier in 2004: something of which they gave the petitioners
warning on 29 October 2004,
immediately after the relevant report had been received. By then, the petitioners had on 2 September 2004 requested "the port
authority to specify what modifications would be required to the proposed
bridge in order to satisfy [their] requirements": a request which would be difficult to
understand if the bridge design was immutable.
The respondents' chief executive replied on 8 September 2004 that the respondents were undertaking a
review of their position, with the assistance of expert advice, in view of the
increasing size of vessels using the North
Harbour. The petitioners' apparent failure to react to
that response would have been surprising if the respondents were understood to
have committed themselves irrevocably to a particular position. The same observation might be made in respect
of the petitioners' response to the respondents' letter of 29 October 2004. It appears to have been only some months
later that the petitioners adopted the position that Mr Manson's e-mail
had committed the respondents irrevocably to their original proposals.
[192] In the circumstances, I conclude that no clear and unambiguous representation
was made to the petitioners that the respondents would not carry out dredging
works for the indefinite future in the locations where the petitioners proposed
to construct the central piers of their proposed bridge; that the individuals whose statements are
founded upon could not lawfully have made such a representation on behalf of
the respondents; and that a commitment to
that effect would in any event have been ultra
vires of the respondents, unless it was the corollary of a decision to
grant a works licence in accordance with section 10 of the 1974 Order. I therefore conclude that the petitioners can
have had no legitimate expectation to that effect. I am also not satisfied that
detrimental reliance on any such expectation has in any event been established.
[193] My conclusion that the respondents' conduct is not in breach of
any legitimate expectation of the petitioners is consistent with my broader
conclusion, essentially one of impression (as Lord Mustill observed in R v Inland
Revenue Commissioners ex parte Matrix-Securities Ltd [1994] 1 WLR 334 at
page 358), that the respondents' adoption of revised dredging proposals could
not be regarded as an abuse of power. It
does not appear to me that the respondents have acted with conspicuous
unfairness. On the contrary, it appears
to me that it would be unjust to the respondents, and would confer an unmerited
benefit on the petitioners, if the respondents were compelled to compromise
their plans for the future development of the harbour in order to accommodate a
bridge design which deliberately failed to meet their stated requirements.
Conclusion
[194] For the reasons discussed, I shall repel the petitioners' third
plea-in-law, relating to legitimate expectation, and sustain the respondents'
seventh plea-in-law, which is concerned with the same issue. It was agreed that, in that event, the
petition should be refused. I shall
accordingly sustain the respondents' fourth plea-in-law (which, as counsel
submitted, appears to be the most apt), and refuse the petition.