OUTER HOUSE, COURT OF SESSION [2007] CSOH 163 |
|
CA161/04 |
OPINION OF LORD DRUMMOND YOUNG in the cause R.A. LOGAN &
CO, SOLICITORS, a firm and ROBERT ANDREW LOGAN and
HENRY CUNNINGHAM COUCHLIN, the whole
partners thereof Pursuers; against STEPHEN BOWMAN
MAXWELL Defender: ________________ |
Defenders:
[1] Prior
to and during the year 2000 the firm of R.A. Logan & Co had four profit-sharing
partners, namely the two individual pursuers, the defender and Carolyn Jayne
Paton. The terms of the partnership were
ultimately regulated by a partnership agreement dated
[2] Clause
16(b) of the partnership agreement provides that, upon the retiral of any
partner from the firm, a balance sheet is to be made up as at the date of
retiral. It is a matter of agreement
that such a balance sheet required to include up-to-date values for the
heritable property owned by the firm and the work in progress of the firm. The firm's accountants were instructed to
prepare accounts for the period to
[3] Defences
were lodged in which it was contended that the work in progress included in the
draft accounts was understated; if the work in progress were increased, it was
averred that a share of it would be attributed to the defender's capital
account, which would have the result of reducing the deficit. Initially other objections were taken by the
defender to the draft accounts. After
sundry procedure the parties agreed that the only area of dispute between them
was as to the valuation of the work in progress of the firm as at
"The
Lord Ordinary...
...
2. in respect
(a) that the parties have confirmed that the
only area of dispute between them is as to the valuation of the work in
progress of the firm R.A. Logan & Co, solicitors, as at 8 December 2000;
(b) that the parties have agreed to dispense
with proof of the value of the work in progress; and
(c) that the parties have agreed to remit the
valuation of the work in progress as at 8 December 2000 to a man of skill and
to be bound by the man of skill's valuation, save in the case of manifest error
by the man of skill,
on joint
motion, remits to Mr Robert Kerr, chartered accountant of Messrs French Duncan,
375 West George Street, Glasgow (i) to examine the books, records and bank
statements of the pursuers and such other documents as the parties may submit
to him ought to be so examined and (ii) to receive the submissions of the
parties in such form as he shall consider appropriate, and thereafter to assess
the value of the work in progress of the firm R.A. Logan & Co, solicitors
as at 8 December 2000 and to report the said value to the parties and to the
Court;
...".
[4] Thereafter
Mr Kerr produced a report dated
"In line
with accepted accounting principles, all work in progress should be valued at
the lower of cost or net realisable value.
In valuing the WIP we would ordinarily look at the primary documentation
(ie timesheets and files) in order to confirm the amount of time incurred on
each particular job. This would then
allow us to calculate the cost of the WIP at the relevant date. Thereafter, we would review the receipt of
monies to confirm that the sums received relating to the WIP were not less than
the cost at the relevant date".
Mr Kerr then reviewed the various
categories of the partnership's work. In
relation to criminal cases, he noted that all case files had been
destroyed. Consequently it was impossible
to refer to primary documentation for evidence of the WIP value. The only method of valuing the WIP would be
to review sums received after
[5] In
relation to civil cases, civil legal aid cases were similar in nature to solemn
criminal cases in that the fees paid were based on the work done. For solemn criminal cases computer records
were available detailing the work done, but no such records existed for civil
cases. Although the pursuers stated that
"the vast majority" of files were available, not all files were
available and it was therefore impossible, given the lack of records, to value
civil legal aid cases accurately at the relevant date. Any valuation would be likely to be
materially inaccurate given the inability to apportion any fees received
accurately, in view of the lack of records.
A similar point applied to civil legal advice and assistance, privately
funded civil court work and conveyancing work; the records were unavailable and
the accurate valuation of WIP was accordingly impossible. Similarly, given the information that was available,
an accurate valuation of the WIP arising out of financial services would be
impossible. In relation to civil cases,
it was noted that a number of civil cases contained in the pursuers' work in
progress analysis remained unpaid; these totalled £22,000, which represented
17% of the total balance of work in progress prepared by the pursuers.
[6] Mr
Kerr further commented that, as had been noted, the records available were
incomplete. While there was a record of
all files opened in the period from
"Our
remit was to provide a valuation of the work in progress of R A Logan & Co
as at
We have
informed the solicitors for both parties of our inability to value the work in
progress. Levy & McRae, on behalf of
the Pursuer, have contended that... I am compelled to provide a value to you,
no matter how heavily caveated that value may be. However, I consider that, given the absence
of material books and records relating to work in progress, any figure I provide
would be likely to be so inaccurate as to be valueless. Reluctantly, I therefore conclude that as a
result of the books and records being materially incomplete, I am unable to
provide a valuation to the Court of the work in progress of R A Logan & Co
as at 8th December 2000".
[7] The
pursuers lodged a note of objection to Mr Kerr's report. This challenged the report on the following
grounds:
(a) The reporter had failed to fulfil his
remit. It appeared from the terms of the
report that the work in progress was capable of valuation, but the reporter
declined to assess its value. The
concern expressed in the report was that the valuation would be insufficiently
precise, but the remit imposed no demands on the reporter as to the requisite
standard of precision.
(b) The report gave no intelligible reasons
for the conclusion reached on the valuation of summary legal aid fixed fee
cases. The pursuers had submitted that
incomplete fixed fee cases should be given a flat rate value of £250; that
reflected the practice of the Scottish Legal Aid Board in cases where there is
a transfer of the legal aid certificate prior to the conclusion of the
case. That practice was used regardless
of how much or how little work had been done prior to transfer. £250 should therefore be regarded as the net
realizable value of each file. The
pursuers had not kept records of time spent in respect of such cases since no
such record was required for billing purposes; the fee generated was fixed
regardless of the time spent.
(c) In respect of solemn criminal files,
where detailed accounts had to be rendered to the Scottish Legal Aid Board, the
reporter noted that it was possible to apportion each account precisely, but
then rejected that approach because tracing numbered remittances to the day
book to identify the file reference was impracticable given the number of
remittances and the fact that the day book was in chronological order. The fact that this task was onerous or
time-consuming did not make it impractical.
It was essentially a straightforward clerical exercise.
(d) The report disclosed an error in respect
of civil files. The reporter noted that "not
all" files were available, but made no attempt to quantify what was
missing. The reporter did not consider
whether any difficulty caused by the missing files could be met by the use of
an assumption or an estimate. Moreover,
no mention was made of conveyancing or executry files.
(e) The reporter noted that civil cases
valued at £22,000 had not in fact been paid five years later. Significance appeared to be attached to this
fact, but no explanation was given of its impact. The obvious inference was that files that
were assessed as having a work in progress value in December 2000 had in fact
no value, since no funds had been received five years later. That could have been dealt with by
substituting a work in progress figure of nil for each such file.
(f) The report recorded erroneously that
the list running to 34 pages and 1400 files was an accurate record of all files
opened by the firm in the accounting period to
(g) The report mentioned an additional 50
files, with a value of £10,900, which did not feature in the pursuers'
valuation. In fact an explanation had
been given by the pursuers at the meeting held on
(h) The reporter had failed to give
consideration to the possibility that the parties might be able to agree any
items where precise apportionment was difficult. In respect of financial services work, the
pursuers would be prepared to adopt the valuation assumption most favourable to
the defender, which was that the whole of each fee generated from business that
was live as at the valuation date related to work done prior to that date.
(i) The report made no attempt to assess
whether work in progress might be valued by considering what proportion of
annual turnover would be carried as work in progress and thereafter applying
such a percentage to the disclosed turnover of the firm.
(j) The report stated that work in progress
fell to be valued at the lower of cost and net realizable value. Nevertheless, no attempt was made to consider
whether cost was capable of being valued.
Cost would consist of overhead and salary cost, and a notional cost for
time spent by profit-sharing partners.
Information on these matters was readily available from the firm's
accounts, which dealt with the
percentage profit generated by the firm and thus the overhead element.
[8] Following
the lodging of the note of objection, by interlocutor dated
(b) Generally accepted accounting principles
would require that a fixed fee should be apportioned on the basis of the work
undertaken. While time records might not
be kept, one would expect the file to provide details of how far the work had
progressed by the accounting date, or at least allow the fee to be apportioned
pro rata on the basis of when the work started and finished.
(c) In relation to solemn criminal cases, 'the
shambolic nature of the Pursuers' records' made an accurate valuation almost
impossible. This view had been concurred
in by a law accountant introduced by the pursuers.
(d) Three issues were raised by this
objection: whether the time and line legal aid accounts could be used to value
work in progress; whether the impact of missing files could be mitigated by
using an assumption or estimate; and the question of conveyancing or executry
files. In relation to the first of these
points, primary documentation was missing, and consequently the reporter had no
way of knowing how many files had a work in progress value as at
(e) The reporter considered the fact that
£22,000 of the pursuers' work in progress calculation remained unpaid was
relevant because it suggested that the pursuers' valuation was at least 17%
inaccurate. Consequently the reporter
felt that little reliance could be placed on that valuation.
(f) The colleagues of the reporter who had
represented him at the meeting of
(g) The reporter's colleagues who had
attended the meeting on
(h) The note of objection was the first
occasion when it had been suggested that the parties might agree items where
precise apportionment was difficult. The
reporter did not consider his role to involve mediation between the parties; it
was rather to assess the value of work in progress.
(i) The reporter had been instructed as a
man of skill to examine the books and record of the firm and to assess the
value of work in progress. Given the
records available, the reporter considered that it was not possible to do that
in a way that would result in a reasonably accurate figure. To perform a calculation based on cost, in
the manner suggested by the pursuers, would produce a figure; nevertheless, it
would be impossible to say with any certainty whether that figure was even
remotely accurate. Such a calculation
would not require a "man of skill".
[9] Thereafter
the defender lodged answers to the note of objection, and the Court appointed
parties to be heard on the note of objection and answers. Counsel for the pursuers submitted that the
Court should send the report back to the reporter for reconsideration of all
the points raised in the note of objection.
He submitted that such a course was competent where the reporter's remit
had not been exhausted; where the remit had been exceeded; where objections
disclosed a point or issue of principle on which the reporter might have gone
wrong; and where there were no reasons or inadequate reasons for the reporter's
conclusions. Reference was made to Williams v Cleveland and Highland Holdings Ltd, 1993 SLT 398, Rowat v Whitehead, 1826, 5 S 19, Edinburgh
Northern Tramways Co v Mann,
1896, 23 R 1056, Johnston v Johnston, 20 January 1999, unreported,
and Allied Dunbar Assurance PLC v Superglass Sections Ltd, 20 August
2004, unreported; and also to Maclaren on Court of Session Practice at pages
503 and 507-508, Maxwell on Court of Session Practice at page 314, and Court of
Session Practice, edited by Lord Macfadyen, at paragraphs [273] and
[2265]-[2270]. Thereafter counsel
developed the points in the pursuers' note of objection; I will deal
subsequently with the individual grounds of objection.
[10] Counsel
for the defender invited me to refuse the pursuers' motion to send the report
back to the reporter for reconsideration.
If I refused the pursuers' motion, I should pronounce decree of
absolvitor, because the report had followed an inquiry into the merits of the
dispute between the parties. He
submitted that the report had taken the place of proof, and the parties were
bound by its terms unless it disclosed a manifest error of law on its
face. Errors of fact were not open to
challenge. Moreover, it was not a valid
objection to the report that an alternative approach might have been taken by
the reporter; the way in which an expert sets about his task is not open to
challenge. In addition, the reporter was
an office holder from the Court; in that capacity he was entitled to the
presumption that he had acted regularly and had discharged his duty. Counsel referred to certain of the cases
cited on behalf of the pursuers, and also to Hunter v Duke of
Queensberry's Executors, 1827, 6 S. 89.
On the facts of the present case, a joint remit had been made to Mr
Kerr. That meant that the parties had
agreed to accept his judgment as to the level of uncertainty that could be
accepted in the task of valuing work in progress. The remit in the interlocutor of
[11] The
underlying issue is the basis on which parties can challenge an expert report. In my opinion the applicable principles are
as follows. In the first place, an
expert report can be challenged on any of the standard grounds of challenge to
an arbiter's decision at common law.
Thus a report can be challenged on the basis that the expert has failed
to address his remit fully, or has exceeded or otherwise misunderstood his
remit, or has been guilty of some breach of the principles of natural justice,
or of corruption. It is also a ground of
challenge that the report is ambiguous or uncertain, or that it is unreasonable
in its reasoning or conclusions. In the
second place, an expert report is also open to challenge if it appears on the
face of the report that the expert has misdirected himself in law. This is different from the position of an
arbiter. The difference can be explained
by the different functions of an expert and an arbiter. An arbiter is normally charged with reaching
a decision on both facts and law, and it is well established that his decision
on both is immune from challenge at common law.
A reporter, by contrast, is normally charged with making findings in
fact, or in some cases merely providing the Court with information about the
facts. Where there is a remit to a
reporter, therefore, questions of law remain under the control of the Court,
and the Court can interfere with the findings of the reporter if it appears
that he has not applied the law properly.
In Edinburgh Northern Tramways Co v Mann, supra, Lord McLaren indicated (at
23 R 1067-1068) that an expert report might be open to challenge if the expert
has come to "wrong conclusions on some matter of principle". That
case related to an English taxing master to whom the Court had remitted the
accounts incurred in connection with the promotion of a private Act. After
referring to wrong conclusions on a matter of principle, Lord McLaren gives the
example of a finding by the taxing master that the engineer involved in the
proceedings was not entitled to remuneration for time and trouble. That seems to indicate that what was
envisaged was essentially an error of law, albeit an error which affected the
reporter's approach to the facts. A
similar point is made by Lord Penrose in Williams
v Cleveland and Highland Holdings Ltd,
supra, at 401J-K, where reference is made to "some issue of principle
identifiable on the face of the report".
In the third place, at least in some cases, an expert report can be
challenged if the reporter "did not have, or at least did not express,
adequate reasons" for his conclusions:
[12] Apart
from the foregoing grounds, the reporter's conclusions are normally final and
immune from challenge. This point is
made in Maclaren on Court of Session Practice, at 508:
"If the
report has been made on a remit of consent, there can be no objections allowed
to the facts found by the report, so far as they are within the terms of the
remit".
The reason for this is clear: the
purpose of such a remit to a reporter is to obtain a definitive finding on a
disputed question of fact, and to do so without recourse to proof in the
ordinary way; consequently the reporter's conclusions are binding on the
parties. It is of course possible for a
remit to provide that the reporter's conclusions should not be binding in the
normal way, but such cases are exceptional; that is because the rationale of a
remit is to obtain a definitive finding, equivalent to a decision following
proof, by means of a procedure that is
more informal, and hopefully cheaper, than proof. If objection is to be taken to a report, it
is essential that it should proceed on the basis of articulate objections made
to the report, on one or more of the grounds stated above. The law is set out in the opinion of Lord
Penrose in Williams v Cleveland and Highland Holdings Ltd, supra. After reviewing the authorities, Lord Penrose
states, at 401 J-K:
"In my
opinion there is no support in any of [the] authorities for the position
adopted by the [defenders]. On the
contrary the emphasis is on the finality of the reporter's findings subject
only to a remit for reconsideration on the basis of articulate objections made
to the report provided, and on restricted grounds. Whether a further remit is made must, in my
opinion, depend upon the cogency of the objections, considered in the light of
the original remit, and on those objections relating to the performance by the
reporter of his duty under the remit, or to some issue of principle identifiable
on the face of the report".
[13] It
is also clear in my opinion that normally the binding nature of a reporter's
conclusions extends not only to the terms of the conclusions themselves but
also to the method used to arrive at those conclusions, provided that it is
within the parameters of the remit. In Williams Lord Penrose states, at 401E:
"In my
opinion it is not legitimate for a party to include by way of note of
objections contentions on the approach which the reporter might have adopted in
carrying out the remit which are in substance innovations on the procedure
provided for in the remit, nor to use the procedure by way of objection to
present argument which might have preceded the decision, as distinct from
criticisms of the decision arrived at by the reporter".
In my view this point can be extended
more broadly: in many cases the decision of an expert will depend upon his
judgment as to the proper method to be used, and the expert's exercise of that
judgment will not normally be open to challenge after the event unless it is
outwith the terms of the remit, or unreasonable in all the circumstances. In
other words, the expert is responsible not only for reaching a decision but
also for determining the precise method
that is used in doing so. This point is
of some importance in the present case.
[14] In
Hunter v Duke of Queensberry's Executors, 1827, 6 S. 89, the Lord Ordinary
(Cringletie) stated (at 90):
"If
parties have it in their power to be heard, and are heard fully, and after such
hearing a report is made,... the parties have no right to assume, as they do
here, that the reporters do not judge on the whole of what is laid before them,
and more particularly that they proceed on assumption of facts which do not
exist".
The Court adhered to this
opinion. That seems to me to be a clear
application of the more general principle that an officer of the Court is
entitled to the assumption that he has performed his duty correctly. That is a
further point that is of some significance in this case.
[15] The
remit in the present case, which was of consent, was to examine books and other
documents as submitted by the parties, to receive the parties' submissions,
"and thereafter to assess the value of the work in progress of the firm
R.A. Logan & Co, solicitors as at 8 December 2000 and to report the said
value to the parties and to the Court".
Two important matters emerge in my opinion from this formulation. First, the reporter is intended to produce
the "value" of the work in progress.
This is something other than a guess or an approximation or a range of
values. Secondly, the use of the verb
"assess" indicates that the reporter is intended to produce a figure
for the value of work in progress, but it also indicates in my opinion that the
method that he employs in doing so is a matter for his own judgment; what is
contemplated is not the mere mechanical determination of a figure but something
more subtle and more complex. That is in
any event in accordance with the basic notion of work in progress, which is a
matter for the judgment of a trained accountant. On that basis I am of opinion that the remit
to Mr Kerr involves an agreement by parties to accept his judgment as to the
level of uncertainty that can be accepted in the task of valuing the work in
progress.
[16] The
reporter's conclusion was that no reasonable or prudent accountant could, given
the information available, provide a valuation of work in progress which could
be considered to be reasonably accurate: see paragraph [6] above. He accepted that a guess would be possible,
but he clearly distinguished a guess from a valuation, and considered that his
responsibility to the Court was to provide a valuation rather than a
guess. The pursuers' first ground of
challenge to this conclusion is the general ground that Mr Kerr had failed to
fulfil his remit; his task was to assess the value of work in progress, but he
had expressly declined to do so. In my
opinion that criticism is misconceived.
Determining a figure for work in progress involves important elements of
judgment, but the figure that is so determined must be reasonably
accurate. In the first place, as
indicated in the last paragraph, a direction to "value" the work in progress
indicates that something other than a guess or approximation is involved. In
the second place, the work in progress figure forms an important component in
the firm's accounts, and will be relied upon by the partners of the firm in
determining their financial position inter se; it will also be relied upon in determining
their tax liabilities, and in some circumstances might be relied upon by third
parties such as banks in determining whether to extend credit to the
partners. For these reasons it is important
that the figure should be substantially accurate. Mr Kerr's view was that, because of the
inadequacy of the firm's records, it was impossible to provide anything that
could be considered reasonably accurate.
In my opinion that is a view that he was entitled to take. So far as the terms of the remit are concerned,
his duty was to provide a valuation, not a mere guess; if, therefore, the
reporter thought that he could not provide a proper valuation it was his duty
to say so. Moreover, the reporter's
conclusion cannot in my view be criticized at a general level as unreasonable;
he makes it clear that his inability to reach a definite opinion on the value
of the work in progress was the result of the lack of records, and he describes
what was missing in some detail. Counsel
for the pursuers pointed out that the deficiencies were not total, he submitted
that the gaps could be filled by making appropriate estimates. In my opinion it is clear from his report
that Mr Kerr considered whether he could follow such a course and concluded
that he could not. It seems to me that
he was well entitled to reach that conclusion; the figure for work in progress
is a global figure, and if any of the major components is incapable of
sufficiently accurate valuation the global figure must collapse.
[17] The
pursuers' second criticism of the report related to the lack of intelligible
reasons for the conclusion reached on the valuation of summary legal aid fixed
fee cases. In summary, the contention
was that the reporter should have followed the practice of the Scottish Legal
Aid Board and attributed a value of £250 to incomplete cases. The reporter's response was that generally
accepted accounting principles require that a fixed fee should be apportioned
on the basis of the work undertaken; this should be apparent from the file. In my opinion that reason is
intelligible. Moreover, it appears to be
founded on accounting practice. When the
Court remits a matter involving professional practice to an expert reporter,
one of the purposes is to permit the reporter to form a view on professional
practice. In my opinion his view on what
is proper practice cannot be challenged at this stage. In addition, the practice of the Legal Aid
Board can scarcely be decisive in relation to the firm's accounts. The practice is followed, obviously as a
matter of practical expediency, when a file is transferred from one firm to
another; the present case, by contrast, involves the accounts of the firm on
the defender's resignation. In that
situation greater precision might be expected for two reasons: first, the
purpose of the accounting exercise was to fix the partners' whole rights and
obligations inter se, a much more
far-reaching exercise; and secondly the number of files involved was clearly
much greater, with the result that the effect of any inaccuracy might be
multiplied. The result is that I cannot
hold that the reporter was wrong in refusing to follow the practice of the
Legal Aid Board.
[18] The
pursuers' third criticism of the report related to solemn criminal cases; the
reporter had failed to apportion each account because tracing numbered
remittances to the day book to identify file references was impracticable. It was submitted that that might make the
task onerous, but did not make it impractical.
The reporter commented that the "shambolic nature" of the
pursuers' records made an accurate valuation almost impossible, and mentioned
that that view had been concurred in by the pursuers' law accountant. Apportioning the sums due in respect of
solemn criminal cases obviously involves the reconstruction of certain of the
firm's financial records. In that
situation it is a question of judgment as to whether the time and cost involved
is worth while. The reporter considered
that issue and concluded that the effort involved was not justified. In my opinion the reporter was entitled to
come to such a conclusion. This is essentially an aspect of the method that is
used to fulfil the reporter's remit. As
indicated above at paragraph [13], the reporter's judgment on the method that
he adopts in fulfilling the remit will not normally be subject to challenge
after the event. In my opinion that
principle applies to the present case.
[19] The
fourth criticism of the report related to civil files, where it had been noted
that not all files were available but no attempt was made to quantify what was
missing, nor to consider whether any difficulty caused by missing files could
be dealt with by using an assumption or estimate; nor was reference made to
conveyancing or executry files. The
reporter provided a detailed response to this criticism, which is set out at
paragraph [8] above. The essential point
of that response is that primary documentation was missing; thus it was
impossible to know how many files had a work in progress value as at 8 December
2000. In my opinion that answer is
clearly correct; it is impossible to know what is missing unless one knows what
was there in the first place, and the reporter's complaint is that the latter
information was not available. The
reporter was further of opinion that it was impossible to use an assumption to
deal with this problem. Once again, that
answer seems to be clearly correct, and was in any event one that the reporter
was entitled to give. The critical point
here seems to be that it is impossible to know the scale of the work contained
in the missing files. In relation to
conveyancing and executry work, the reporter considered that the absence of an
unknown number of files made accurate valuation impossible. This involves essentially the same argument
as the reporter's earlier answers: it is impossible to know what is missing,
and therefore an accurate valuation is impossible.
[20] The
fifth criticism of the report related to the reporter's reference to civil
cases valued at £22,000 that had not been paid five years later. The reporter commented that that suggested
that the pursuers' valuation of work in progress was materially
inaccurate. In my opinion the reporter
was well entitled to draw that conclusion; indeed, it seems obvious.
[21] The
sixth criticism of the report related to Mr Kerr's assumption that a list of
1400 files was an accurate record of all files opened in the accounting period
to
[22] The
seventh criticism of the report related to Mr Kerr's mentioning an additional
50 files which did not feature in the pursuers' valuation. It was said that an explanation had been
given by the pursuers at the meeting held on 6 June 2006; on that basis, the
files had been properly excluded. In his response to the note of objection Mr
Kerr stated that his colleagues who had attended the meeting on
[23] The
eighth criticism of the report was that the reporter had failed to consider the
possibility that the parties might agree items where precise apportionment was
difficult. In his response to the note
of objection Mr Kerr stated that the note of objection was the first occasion
when it had been suggested that the parties might reach agreement on such a
basis. The reporter did not consider his
role to involve mediation between the parties.
In my opinion that is clearly correct; the reporter's duty was to reach
a valuation of work in progress; it was not to act as a mediator.
[24] The
ninth criticism was that the reporter had made no attempt to assess whether
work in progress could be calculated by treating it as a proportion of annual
turnover. The reporter did not respond to this criticism. Nevertheless, it seems to be covered by his
general observation that, in view of the inadequacy of the records, it was
impossible to come up with any accurate figure.
In relation to percentages of turnover, it cannot be assumed that the
percentage is constant throughout the year.
Invoices are frequently issued and debts collected at particular times
during the year, and these have a direct effect on the figures for work in
progress, debtors and cash. Thus all
those figures may tend to vary during the year.
The exercise that had to be carried out by the reporter does not relate
to a year end but to a time during the partnership's financial year. Thus the use of percentages would be
essentially speculative.
[25] The
tenth and final criticism of the report was that, although the reporter stated
that work in progress should be valued at the lower of cost and net realizable
value, no attempt had been made to consider whether cost was capable of being
valued; cost would consist of overhead and salary costs and a notional cost for
the time of profit-sharing partners. The
reporter's response was that he had been instructed as a man of skill to
examine the books and records of the firm and to assess the value of work in
progress. The method suggested by the
pursuers would produce a figure, but it would be impossible to say with
certainty that that figure was even remotely accurate. In my opinion this is a clear example of the
reporter's exercising his professional judgment in determining how to set about
his task. His exercise of judgment
cannot be criticized at this stage on the mere ground that it was exercised
wrongly. In addition, the pursuers
suggested in their note of objection that information might be derived from the
accounts prepared for previous and subsequent years in order to discover
overheads. That practice is subject to
the difficulty referred to in the last paragraph, that the present case
involves a valuation in the course of a financial year, when costs may for
various reasons be at a misleading level.
In addition, I am of opinion that this ground of objection faces a
logical difficulty: if work in progress should be valued at the lower of cost
and net realizable value, it is impossible to say which is lower without
knowing both figures. Cost would be
higher than net realizable value if the firm were trading at a loss. The reporter had found that it was impossible
to estimate net realizable value, and consequently he could not complete the
exercise on the basis suggested by the pursuers.
[26] On
the foregoing basis I am of opinion that none of the grounds of objection
stated by the pursuers has been established.
The result is that Mr Kerr's report must stand. His conclusion in that report was that he was
unable to value the work in progress of the firm has at
[27] The
significance of that failure is in my opinion as follows. In the accounts put forward by the pursuers
in support of their claim the work in progress is valued at £126,342. That figure has not been proved. That is not the same, however, as saying that
the work in progress was worth nothing.
It is not disputed that the firm had work in progress, but the value of
that work in progress cannot be ascertained.
As counsel for the defender expressed the matter, the value of the work
in progress is "blank"; "blank" is not the same as
"nil". The logic of this is
that the pursuers have failed to prove the value of the assets of the firm as
at