OUTER HOUSE, COURT OF SESSION
[2007] CSOH 117
|
CA100/05
|
OPINION OF LORD DRUMMOND
YOUNG
in the cause
JOHN STIRLING
trading as M & S CONTRACTS
Pursuer;
against
WESTMINSTER
PROPERTIES SCOTLAND LIMITED
Defenders:
ннннннннннннннннн________________
|
Pursuer: S Smith; MacRoberts
Defenders: Richardson; Morton Fraser
9 July 2007
[1] In October 2004 the parties entered into a contract for
certain internal and external refurbishment works to be carried out by the
pursuer at premises at 7 Orchard Road,
St Annes, belonging to the defenders.
The terms of the contract were contained in a letter of appointment
dated 13 October 2004
issued to the pursuer by project managers acting on behalf of the defenders,
which incorporated the defenders' specification, description of works, contract
drawings and the JCT standard form of Agreement for Minor Works MW 98
(including Amendments 1-5). The parties
were in agreement that the contract was contained in those documents. It is significant for the purposes of the
present opinion that the contractor was identified as the pursuer; the letter
of appointment, which identified the contractor, was addressed to "John
Stirling, M&S Contracts". The
contract was a construction contract within the meaning of Part II of the
Housing Grants, Construction and Regeneration Act 1996; consequently, in terms
of clause 8.1 of the contract either party was entitled at any time to refer
any "dispute or difference" arising under the contract to adjudication.
[2] A company known as M&S Contracts Limited was incorporated
on 5 November 2004. The pursuer was at all material times the
sole director of the company. As will
appear, a substantial number of the documents issued for the purposes of the
parties' contract either proceeded in the name of that company or were issued
to that company. The significance of the
company's involvement is a matter of some importance, and I will return to it
subsequently. The company was
incorporated after the contract between the parties was concluded.
[3] Works were duly carried out under the contract; invoices were
issued and payments were made in respect of those invoices. On 11 July 2005 Kerr Baxter Associates, the
contract administrators, issued Certificate for Payment No 6, which certified
that the sum of г48,667.50 plus VAT was due for payment to the contractor
within 14 days of the date of issue of the certificate. In that certificate the contractor was
referred to as "M&S Contracts". On 14 July 2005 an invoice for that sum
was issued to the defenders by M&S Contracts Limited. Thereafter, Kerr Baxter Associates received a
letter dated 19 August 2005
bearing to have been written by G. Stirling on writing paper headed "M&S
Contracts Limited"; the letter stated
"As you are
aware, we are excessively overdue on Certificate for Payment No 6. This has a valuation date of 4th July 2005 and an issue
date of 11th July 2005. The certificate is overdue and has not been
paid, which is a breach of the employers contract".
The writer of the letter went on to
state that interest at 5% would be charged, and that under clause 4.8 of the
JCT conditions the contractor was entitled to suspend the works in view of the
non-payment. By letter dated 2 September
2005 Longworth Consulting Worldwide Limited, a firm of claims consultants who
were acting on behalf of the pursuer, gave notice to the defenders of the
pursuer's intention to refer to adjudication the defenders' failure to make the
payment due in terms of Certificate No 6.
That letter bore the heading "M&S Contracts Limited v Westminster
Properties Scotland Ltd". Thereafter M&S Contracts Limited served a notice
of adjudication dated 9 September 2005 on the defenders stating its
intention to refer to adjudication the dispute arising from the defenders'
non-payment of the sums certified as due in Certificate No 6.
[4] By
letter dated 22 September 2005 to the adjudicator, copied to
M&S Contracts Limited, the defenders advised that in view of the date of
M&S Contracts Limited's incorporation it could not have been a party to the
contract concluded on 13 October 2004.
Thereafter M&S Contracts Limited abandoned its adjudication; the
decision was intimated by letter dated 24 September 2005 from the company to the adjudicator,
which was copied to the defenders. By
letter dated 24 September 2005 addressed to the company and the
defenders the adjudicator resigned office.
The pursuer then served a notice of adjudication dated 26
September 2005 on the defenders stating his intention to refer to adjudication the
dispute arising from the defenders' non-payment of sums certified as due in
Certificate No 6. Apart from the
identity of the referring party, that notice of adjudication is in materially
the same terms as the notice of 2 September 2005.
By letter dated 27 September 2005 the adjudicator advised the parties
that he accepted appointment in respect of the adjudication. The pursuer then served a referral notice
dated 27 September 2005 on the defenders, referring to
adjudication the dispute arising from the non-payment of the sums certified as
due in Certificate No 6. The defenders
disputed the jurisdiction of the adjudicator to act in relation to the matters
set out in the notice of adjudication of 26 September 2005.
Among the grounds on which jurisdiction was disputed was the contention
that no dispute had crystallized between the pursuer and the defenders. The adjudicator issued a decision to the
parties on 25 October 2005; in that decision he rejected the
contention that there was no dispute between the parties in respect of Certificate
No 6. In his decision the adjudicator
further determined that the defenders should pay the pursuer the sum of
г48,667.50 plus VAT of г8,516.81, totalling г57,184.31, pursuant to Certificate
for Payment No 6, those amounts to be paid within 14 days of the date of the
decision. He further ordered the
defenders to pay interest amounting to г1,152.97 on the foregoing sum,
continuing interest at a daily rate of г12.67 from 26 October 2005 until
payment, and his own fees amounting to г4,773.44, inclusive of VAT.
[5] The
pursuer has raised the present action against the defenders for enforcement of
the adjudicator's decision. In their
defences the defenders contend that no dispute existed between the present
parties prior to the notice of adjudication served by the pursuer on 26
September 2005; consequently the adjudicator lacked jurisdiction, and his decision is a
nullity. In the course of the incidental
procedure in the action a number of other issues arose between the parties, but
all of these have now been resolved by agreement. It has been agreed in particular that the
parties to the action were the parties to the contract for the refurbishment
works at 7 Orchard Road.
The only issue that remains for decision is whether a dispute or
difference existed between the present parties prior to service of the notice
of adjudication.
[6] The
material facts were agreed between the parties in a joint minute, and counsel
on both sides made it clear that they were anxious that the action should be
resolved at debate. For the pursuer,
counsel contended that I should grant decree de plano in terms of the conclusions of the
summons. For the defenders, it was
contended that I should pronounce decree of absolvitor in view of the extent of
the agreed facts; failing absolvitor I should dismiss the action.
[7] Counsel
for the pursuer submitted that a dispute between the parties in relation to the
sums certified in Certificate for Payment No 6 arose prior to the start of the
adjudication. It might have arisen as
soon as the 14-day period referred to in the certificate expired, or possibly
shortly thereafter. If that were not so,
the dispute arose at a reasonable period following the expiry of the 14-day
period; that would certainly have occurred before the notice of adjudication
was served on 26 September 2005.
At the latest the dispute between the present parties can be said to
have arisen on 24 September 2005, when the company, M&S Contracts
Scotland Limited, abandoned its adjudication.
That was also before the notice of adjudication in the pursuer's name
was served. On any of these approaches,
however, it is clear that the critical question is whether a "dispute or
difference" between the present parties can be said to have crystallized before
the notice of adjudication was served on 26 September
2005.
[8] The
meaning of the expression "dispute or difference" was considered in Amec Civil Engineering Ltd v Secretary of State for Transport,
[2005] 1 WLR 2339. In that case, which
concerned provisions in the ICE Conditions of Contract rather than adjudication
provisions in the JCT forms, the judge at first instance, Jackson J., reviewed
the authorities on the matter and set out the law in a series of numbered
propositions; these were accepted as accurate when the matter reached the Court
of Appeal, and the judges of the latter court made it clear that they accepted
those propositions, subject only to certain additional observations. The propositions are found stated in the
opinion of May LJ at paragraph [29], and so far as material are as follows
"1. The word 'dispute'... should be given its
normal meaning. It does not have some
special or unusual meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word 'dispute',
there has been much litigation over the years as to whether or not disputes
existed in particular situations. This
litigation has not generated any hard-edged legal rules as to what is or is not
a dispute. However, the accumulating
judicial decisions have produced helpful guidance.
3. The mere fact that one party... notifies the
other party... of a claim does not automatically and immediately give rise to a
dispute. It is clear, both as a matter
of language and from judicial decisions, that a dispute does not arise unless
and until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge
that a claim is not admitted are Protean.
For example, there may be an express rejection of the claim. There may be discussions between the parties
from which objectively it is to be inferred that the claim is not
admitted. The respondent may
prevaricate, thus giving rise to the inference that he does not admit the
claim. The respondent may simply remain
silent for a period of time, thus giving rise to the same inference.
5. The period of time for which a respondent may
remain silent before a dispute is to be inferred depends heavily upon the facts
of the case and the contractual structure.
Where the gist of the claim is well known and it is obviously
controversial, a very short period of silence may suffice to give rise to this
inference....
6. If the claimant imposes upon the respondent a
deadline for responding to the claim, that deadline does not have the automatic
effect of curtailing what would otherwise be a reasonable time for
responding. On the other hand, a stated
deadline and the reasons for its imposition may be relevant factors when the
court comes to consider what is a reasonable time for responding.
7. If the claim as presented by the claimant is
so nebulous and ill-defined that the respondent cannot sensibly respond to it,
neither silence by the respondent nor even an express non-admission is likely
to give rise to a dispute for the purposes of arbitration or adjudication".
May LJ, at paragraph [31], commented
that the expression "dispute or difference" seemed to be less hard-edged than "dispute"
alone. In addition, he commented that in
many instances it will be quite clear that there is a dispute. If the claims are major, it is likely that
they will be contested and arbitration may well be probable and necessary. In such cases commercial good sense did not
suggest that the clause in question should be construed with legalistic
rigidity so as to impede the parties from starting the arbitration
proceedings. That tended to favour an
inclusive interpretation of what amounted to a dispute or difference.
[9] Some
assistance in the construction of the word "dispute" is found in Fastrack Contractors Ltd v Morrison Construction Ltd, [2000] BLR 168, where Judge Thornton QC stated (at paragraph [20]) that a "dispute"
is "whatever claims, heads of claim, issues, contentions or causes of action are
then in dispute which the referring party has chosen to crystallize into an
adjudication reference". If a
jurisdictional challenge is mounted, it is necessary to consider what was
actually referred, and that involves a careful characterization of the dispute
referred. That exercise is not to be
determined solely by the wording of the notice of adjudication, since that
document, like any commercial document having contractual force, requires to be
construed against the underlying factual background. At paragraph [27] of the same case Judge
Thornton stated that a "dispute" can only arise once the subject-matter of the
claim, issue or other matter has been brought to the attention of the opposing
party and that party has had an opportunity of considering and admitting,
modifying or rejecting the claim or assertion.
[10] The
expression "dispute or difference" occurs in forms of construction contract
that, with certain modifications, are in use both in Scotland and in England and Wales. The approach to the interpretation
of the expression that is used in the two foregoing cases is in my opinion
wholly consistent with Scots law and should be followed in Scotland, at least in relation to the
standard forms of construction contract.
In essence, that approach is as follows.
The word "dispute" is an ordinary word, and should be given its ordinary
meaning. The notion of a "difference" is
slightly wider than that of a "dispute"", but once again the word is in
common use and should be given its ordinary meaning. The fundamental feature of a "dispute or
difference" is an element of disagreement as to the parties' rights and
obligations. That can appear from the
express terms of the parties' correspondence or by implication from their
conduct. Such an implication may appear
from the mere failure of the respondent to act, but in such cases it must be
clear in all the circumstances that there is a disagreement between the parties
as to their respective rights and obligations.
If there has been prior correspondence that identifies an area of
disagreement, the inference that a dispute or difference exists between the
parties may readily be drawn from their conduct. In the absence of prior correspondence, it
may not be so easy to draw such an inference. Where the conduct of the
respondent is relied upon to yield the inference that a dispute or difference
exists, it must be clear that such conduct, for example a failure to pay, has
not been the result of mere lack of funds or administrative oversight. If that is the only reason for the failure to
pay, it cannot be said that there is anything in the nature of a disagreement
between the parties as to their respective rights and obligations.
[11] The
first contention for the pursuer was that a dispute between the present parties
over the sum certified in Certificate No 6 arose on or shortly after the expiry
of the 14-day period referred to in the certificate. The origin of that 14-day period is found in
clause 4 of the contract conditions.
Clause 4.2.1 provides that the contract administrator must, at intervals
of four weeks, certify progress payments of 95% of the total value of the work
executed and the value of materials and goods reasonably and properly brought
upon the site. The clause continues with
a statement that "The final date for payment by the Employer of the amount so
certified shall be 14 days from the date of issue of the certificate". Clause 4.4 provides that, not later than five
days after the issue of a certificate of payment pursuant to clause 4.2.1, the
employer is to give a written notice to the contractor specifying the amount of
the payment proposed to be made in respect of the amount stated as due in the
certificate. Not later than five days
before the final date for payment of the amount that is due the employer is
authorized to give a written notice to the contractor specifying any amount
proposed to be withheld or deducted from that notified amount, the grounds for
such withholding or deduction, and the amount of the withholding or deduction attributable
to each ground. If no such notice is
given by the employer, the employer must pay the amount stated as due in the
certificate.
[12] Counsel
for the pursuer submitted that clauses 4.2 and 4.4 impose a tight contractual
timetable which permits the employer to state by notice what sum it was
prepared to pay or withhold. If there is
such a contractual structure, he submitted, there is no need for the contractor
to make a claim as such. The question of
whether the sum certified was payable arose as soon as the certificate was
issued by the contract administrator, because at that point the employer had 14
days to consider its position; if the employer did not give notice specifying a
proposed withholding or deduction, with grounds, it was obliged to pay the
amount stated in the certificate.
Consequently the case was not one where the employer could simply sit on
the matter; if no action is taken within the 14-day period the sum certified
becomes due.
[13] The
pursuer's argument on this point was attractively presented, but I am of
opinion that it reads too much into the terms of clauses 4.2 and 4.4. The purpose of those clauses is to provide a
mechanism for interim certification of payments, and in so doing to provide a
mechanism for identifying disputes as to the amount that is actually due
following each certificate. The critical
point about that mechanism, however, is that it involves the giving of a
written notice specifying the amount that the employer proposes to pay and a
further written notice specifying any amount proposed to be withheld or
deducted, together with the grounds for such withholding or deduction. Thus, on the contractual scheme, any
disagreement that emerges as to the parties' respective rights and obligations
should appear in writing. It follows
that the mere failure to pay is not enough to give rise to a "dispute or
difference". Such failure could be due,
for example, to lack of funds or a simple administrative oversight or a
communication's going astray. In these
circumstances it could not be said that there was anything of the nature of a
disagreement between the parties as to their respective rights and obligations.
[14] As
matters progressed, however, the defenders failed to dispute the amount due in
Certificate No 6, whether using the contractual mechanisms or otherwise, and
failed to make payment of that amount.
Importantly, they failed to give any reason for their non-payment. Correspondence passed, albeit in the name of
the company; I deal with the significance of this feature in the following
paragraphs. In that correspondence,
however, neither the defenders nor their contract administrators gave any
indication that they were unable to pay through, for example, lack of funds, or
had simply overlooked the need to pay.
The fact that correspondence passed is significant, because it gave the
defenders a good opportunity to explain their failure to pay, and they failed
to make use of that opportunity. It also
tended to eliminate the possibility that a letter had simply gone astray. The contractual structure is significant to
this extent: as explained in the preceding paragraphs, clauses 4.2 and 4.4 were
intended to identify any problems arising out of a certificate within a fairly
short time, and if no such problems are identified but payment is not made the
natural inference is that the employer disputes any obligation to make the
payment. In the whole circumstances, I
am of opinion that the inference must be drawn that a genuine disagreement
existed between the parties as to their respective rights and obligations
following the issue of Certificate No 6.
The pursuer contended that the full amount stated in the certificate was
due; the defenders disputed that that sum was due. In the light of the correspondence, I am of
opinion that such an inference should have been drawn by the beginning of
September 2005; at the latest, I consider that it must have been drawn by 24 September 2005, when the company abandoned its adjudication. In either event a disagreement as to the
parties' rights and obligations under Certificate No 6 existed before the
present pursuer served notice of adjudication.
On that basis I am of opinion that a "dispute or difference" existed
prior to the start of the adjudication.
[15] The
correspondence in July, August and September 2005 passed generally in the name
of the company, M & S Contracts Limited.
Thus the invoice for the sum due under Certificate No 6, issued on 14 July 2005, was in the name of the company. Likewise, the letter of 19 August 2005 addressed to the contract administrators, referred to
in paragraph [3] above, was typewritten on the writing paper of the
company. For the defenders it was
contended that these documents, and other documents which proceeded in the
company's name, should be read according to their strict terms; because they
proceeded in the company's name, they could not affect the legal position as
between the defenders and the pursuer as an individual.
[16] If the
doctrine of separate corporate personality is applied with its full rigour, the
defenders' argument is clearly correct. I am nevertheless of opinion that this
is too simplistic an approach. In
commercial practice, it is not unusual to discover that the niceties of the
doctrine of separate corporate personality are ignored. Where, for example, a contract has been
concluded in the name of an individual trader but the individual then transfers
his business to a company, it is frequently found that correspondence after the
transfer proceeds in the name of the company rather than the individual,
despite the fact that it is the individual who is the contracting party. In such a case, if the correspondence is
construed literally as proceeding in the name of the company, the result is
likely to be nonsensical, as the company is not a party to the contract to
which the correspondence obviously relates.
That contract is in the name of the individual. In these circumstances the only sensible
inference will normally be that the company, in conducting the correspondence,
is acting as an ad hoc agent for the
contracting party, the individual. That
is in my opinion in accordance with the obvious intention of the parties. A similar inference can readily be drawn in
cases involving a group of companies where a contract is in the name of one
company but correspondence is conducted by another company in the group. An analysis in terms of ad hoc agency allows the contracting party to remain in place as
the subject of the contractual rights and obligations; at the same time the
correspondence is allowed to bear the meaning that was obviously intended by
the parties, as relating to the rights and obligations arising under that
contract. This analysis is, however, subject to one important limitation: it
applies to correspondence, invoices, contractual notices and the like, where no
special formality is expected; where, however, matters enter a formal process
such as litigation or adjudication, formality is expected and the correct party
must be named. I return to this matter at
paragraph [20] below.
[17] Such an
analysis is in my opinion entirely in accordance with the general principles
that apply to the construction of documentation issued under commercial
contracts. The present case relates to
the interpretation of letters and other documents that have been sent in order
to assert or discuss the parties' rights and obligations under a contract. I consider that the principles applicable to
the construction of such documents are essentially the same as those that apply
to the construction of the contract itself.
As with the contract, such documentation must be construed objectively,
according to the standard of a reasonable third party. It must be construed in context. In construing post-contractual documentation,
the most important feature of the context will normally be the contract itself,
because such documentation is intended to assert, implement, debate or
otherwise deal with the parties' rights, obligations, powers and liabilities
under that contract. The context may, however, include the surrounding
circumstances, for the purpose of discovering the facts to which the
documentation refers and its commercial objectives. The principle here is essentially the same as
that applicable to the construction of a contract itself, as laid down in such
cases as Charrington & Co Ltd v Wooler, [1914] AC 71, at 80 per Lord
Kinnear and at 82 Lord Dunedin, Prenn v Simmonds, [1971] 1 WLR 1381; Reardon Smith Line Ltd v Hansen-Tangen, [1976] 1 WLR 989, Bovis Construction (Scotland) Ltd v
Whatlings Construction Ltd, 1994 SC 351, at 357 per Lord President Hope, Bank of Scotland v Dunedin Property Investment Co Ltd, 1998 SC 657, at 665 per Lord
President Rodger, at 670-671 per Lord Kirkwood, and at 676-677 per Lord Caplan,
Waydale Ltd v DHL Holdings (UK) Ltd (No 2), 2002 SLT 224, at 229 per Lord
Hamilton, and Glasgow City Council v Caststop Ltd,, 2002 SLT 47, at 56 per
Lord Macfadyen. The contract and the
correspondence must be construed as a totality.
As with a commercial contract, post-contractual correspondence and other
documentation should be given a commercially sensible construction; that is an
example of the wider rule that construction that yields a reasonable result
should be preferred over one that does not:
Glasgow City Council v Caststop Ltd, supra, at 56-57 per Lord Macfadyen.
[18] For
present purposes the most important of these principles is the need to construe
post-contractual correspondence and other documentation in the context of the
contract to which it relates. In the
light of that consideration, the most natural interpretation of such documents
is that they relate to the rights and obligations that arise under that
contract, and therefore to the parties to that contract, since they are the
only persons who have rights and obligations under the contract. On that basis, if a letter proceeds in the
name of a company or individual who is not a party to the contract, the context
strongly indicates that it is meant to relate to the rights and obligations of
the contractual parties. The most
straightforward means of achieving that result is through the concept of ad hoc agency. That result is further supported by the
principle of objective construction; in my opinion a reasonable third party who
examines a letter proceeding in the name of a non-party would naturally
construe it as relating to the parties to the contract, provided that the
contract itself was sufficiently clearly identified in the letter. Further support for the same result may be
found in the surrounding circumstances; where the writer of the letter is
obviously connected with the party to the contract, as with a company that has
succeeded to a sole trader or two companies within the same group, the
inference is that one is writing on behalf of the other. Finally, the inference that the letter or
other documents is issued on behalf of the contracting party is strongly
supported by the principle that documentation should be given a commercially
sensible construction. If a letter that
obviously relates to a contract is not construed as relating to the parties to
that contract, the result is likely to make no sense in either legal or
commercial terms.
[19] The
foregoing analysis must in my opinion apply to the documents that were issued
in July and August 2005. Thus the
invoice of 14 July 2005, although it proceeds in
the name of the company, M&S Contracts Ltd, must be construed as issued on
behalf of the pursuer. It is clear that
the invoice related to the contract for the refurbishment work at 7 Orchard Road, St Annes; under that
contract it was the pursuer who was the contracting party; consequently the
pursuer was the only person who had any right to issue an invoice. Likewise, the letter of 19 August 2005 sent to Kerr Baxter Associates, the defenders' contract
administrators, must be construed as issued on behalf of the pursuer, even
though it was on the company's writing paper.
The letter referred specifically to 7 Orchard Road, St Annes, and named the
defenders. It indicated that payment was
overdue on Certificate No 6, and pointed out that that constituted a breach of
contract on the part of the employer.
There is no doubt that it related to the contract between the pursuer
and the defenders. Once again, because
the pursuer was the contracting party, the letter could only make sense in the
contractual context if it was written on his behalf. A similar analysis can be applied to the
other documents that passed during July and August. It is in the light of those documents that I
have concluded that a "dispute or difference" existed between the parties to
the action by the beginning of September 2005.
[20] On 2 September 2005 Longworth Consulting wrote to the defenders giving
notice of an intention to refer a dispute to adjudication. The letter was headed "M&S Contracts
Limited v Westminster Properties Scotland Ltd".
The heading continued with a reference to 7 Orchard Road, St Annes, and the details
of the letter indicated that it was the contract for the refurbishment work at
that address that was the subject of the letter. Nevertheless, the text of the letter referred
throughout to the company. This letter
is, I think, in a different position from earlier correspondence. It is a notice of intention to refer a
dispute to adjudication. Adjudication is
a form of provisional dispute resolution, and the letter is accordingly similar
in its import to a solicitor's letter written prior to litigation. At this stage, and in any subsequent
adjudication or court proceedings, I am of opinion that an analysis in terms of
ad hoc agency is not an appropriate
inference. When litigation or
adjudication is threatened, the communings between the parties take on a formal
aspect, and precision is required in the name of the party making the claim.
That inevitably negates the inference that one person is acting on behalf of
another; a formal claim must be made by or in the name of the person who has
the right that is claimed. That is why
in litigation, if an action is raised in the name of the wrong party, the normal
response will be a plea of no title to sue.
In my opinion an analogous argument can be presented in an
adjudication. A similar response can be
made to a letter that threatens litigation or adjudication. At that point, the intervention of formal
proceedings for resolution of the dispute requires formality, and that includes
precision in the identification of the parties.
Consequently the inference cannot be drawn that a company is acting for
the individual who is truly the contracting party, or that one group company is
acting for the other company which has in fact concluded the contract.
[21] At this
stage too, if a claim is intimated or presented in the name of the wrong party,
formal objection would normally be taken, whether through a plea of no title to
sue or otherwise; that in fact happened in the present case, since by letter
dated 22 September 2005 to the adjudicator the defenders' agent pointed
out that the company had been incorporated after the contract was concluded and
hence could not be a party to the contract.
Before litigation or adjudication is threatened, however, there is no
obvious reason other than a concern for strict accuracy for the recipient of a
letter or other document to point out that it proceeds in the name of the wrong
party, provided that there appears to be some sort of relationship between the
person responsible for the letter and the other party to the contract. That
explains why contractual correspondence before the stage of a formal claim is
frequently allowed to proceed in the name of the wrong party. I should add that there are cases where a
party to a contract sues on the contract in respect of losses suffered by
another person to whom, for example, the pursuer has transferred the subject
matter of the claim. In such cases the
pursuer can in a sense be regarded as suing on behalf of that other party, but
he clearly has title to do so because he is the party to the contract; indeed,
that is why the other party cannot sue.
Such cases are accordingly quite different from the situation presently
under discussion.
[22] It
follows that the writer of Longworth Consulting's letter of 2 September 2005 purported to act for the wrong party; the company was
not a party to the contract. That is
clearly the result of an error, but the effects of the error are confined to
the letter and the subsequent attempt to raise adjudication proceedings in the
name of the company. The result is that
the letter and the subsequent referral notice were a legal nullity and cannot
be saved by the concept of ad hoc
agency. The error was discovered fairly rapidly, however, and was accepted by
Longworth Consulting; the adjudication was abandoned, and the decision to do so
was intimated by letter dated 24 September 2005. The adjudicator resigned office. On 26
September 2005 fresh adjudication proceedings were raised in the name of
the present pursuer. At that stage, at
the very latest, I am of opinion that a "dispute or difference" had
crystallized between the pursuer and the defenders. They were the parties to the contract. Certificate No 6 had been issued under that
contract. The defenders had not paid the
sum due in terms of that certificate; nor had they indicated why they had
failed to make payment. In those
circumstances, the inevitable inference is in my opinion that the amount due
under the certificate was disputed. That
clearly involved a disagreement between the parties as to their respective
rights and obligations, which is the essential criterion for a "dispute or
difference".
[23] For the
defenders it was submitted that, in order to convert a contractual entitlement
into a "dispute", it was necessary both for the entitlement to be communicated
to the other party and for it to be made clear, by words, conduct or otherwise,
that it was not accepted that there was any such entitlement. In the present case, it was submitted, the
pursuer did not in terms communicate his entitlement to the sums specified in
Certificate No 6 prior to 26 September 2005, when the pursuer intimated
that he intended to refer a dispute to adjudication. That was too late, however. In this connection, counsel referred to
certain passages in Fastrack Contractors
Ltd v Morrison Construction Ltd,
supra, in particular at paragraphs [20] and [27]. In the latter paragraph it was stressed that
the subject matter of a claim, issue or other matter must be brought to the
attention of the opposing party in order that that party might have an
opportunity of considering and admitting, modifying or rejecting the claim. Counsel also referred to the opinion of Rix LJ
in Amec Civil Engineering Ltd v Secretary of State for Transport, supra,
where at paragraph [68] it was pointed out that adjudication was an additional
provisional layer of dispute resolution pending final litigation or
arbitration; there was accordingly a legitimate concern to ensure that the
point at which this additional complexity has been properly reached should not
be too readily anticipated.
[24] I do
not doubt that, for a "dispute" to arise, it is necessary that a contractual
claim should be communicated to the other party and that the other party
should, expressly or impliedly, make it apparent that he rejects the claim in
whole or in part. Whatever the form in
which the parties' attitudes are conveyed, the substance of the matter must
always be that there is a disagreement between the parties as to some aspect of
their contractual rights and duties. In
the present case, I am of opinion that the existence of a disagreement as to
the pursuer's entitlement under Certificate No 6 was apparent by the beginning
of September 2005, or at latest as soon as the adjudication proceedings in the
name of the company came to an end on 24 September. The pursuer had asserted a claim, and the
defenders, despite the contractual time scale and the documents sent to them,
had failed to make payment and had failed to advance any reason to explain such
non-payment. In my opinion that is
sufficient for the inference that the defenders disputed the pursuer's
claim. If that were not so, a party
could adopt the tactic of simply failing to respond to repeated invoices, claim
letters and the like, and thus substantially delay any reference to
adjudication. No doubt an ultimatum
procedure could be used, but I do not think that there should be any need to go
as far as that; silence for a sufficient period in the face of a letter of
claim can be sufficient to yield the inference that the claim is disputed. I am conscious that adjudication is a
provisional procedure. Nevertheless, one
of its major purposes is to ensure contractual cash flow, and that could easily
be frustrated if the courts were to impose unduly strict conditions on the
raising of adjudication proceedings.
[25] Counsel
for the defenders also relied on the fact that documents such as the invoice of
14 July 2005 and the letter to the contract administrators of 19 August 2005 bore to come from M&S Contracts Ltd, not the
pursuer. He submitted that the pursuer
had acted in his capacity as the sole director of the company when invoices
were issued and claims were made in correspondence and in the adjudication
proceedings. The result was that the
claim should be understood as the company's, not the pursuer's. In any event, counsel submitted that the
certificate at which the pursuer founded, Certificate No 6, required to be
construed against the background of the parties' actings. So construed, the reference to "M&S
Contracts" in the certificate should be understood as a reference to M&S
Contracts Ltd. In effect, therefore,
counsel argued that the contractual documentation properly referred to the
company, and that if any agency relationship existed it was through the
pursuer's office as a director of the company.
[26] This
argument is ingenious, but in my opinion it must be rejected. The fact that the contractual documentation
in July and August 2005 proceeded in the name of the company can in my view be
readily explained by the notion of ad hoc
agency, as explained above at paragraphs [16]-[19]. The essential point is that the pursuer, not
the company, was the contracting party.
If the documents are treated as proceeding from the company, that can
only make sense if the company is substituted for the pursuer as the
contracting party. That would require
novation, however, and nothing of the sort is averred. Moreover, novation involves the substitution
of one contracting party for another in respect of both rights and
obligations. That normally requires the
clear agreement of the other party to the contract. Such agreement is not to be inferred
lightly. It is, in any event, contrary
to the agreed facts in the present case.
When adjudication proceedings were raised in the name of the company,
the defenders, by letter to the adjudicator dated 22
September 2005, pointed out that the company could not have been a party to
the contract because it had been incorporated after the date when the contract
was concluded. That is only consistent
with view that the pursuer's rights and obligations had not been novated to the
company. By contrast with novation, ad hoc agency leaves the contracting
parties in place. That feature makes it
a much more natural inference. So far as
Certificate No 6 itself is concerned, it refers quite clearly to "M. & S.
Contracts", which was the trading name of the pursuer. Novation would be required before that could
be understood as referring to the company, and in the circumstances of the case
that seems to me to be a most improbable inference.
[27] In
developing his argument, counsel for the defenders referred to a number of
specific features of the correspondence and other documentation; these, he
said, indicated that the documents in question were truly the documents of the
company, not the pursuer. He referred to
the sequence of invoices that culminated in that of 14 July
2005. Initially these had proceeded in the name of
M&S Contracts, but starting with invoice No 5, dated 21 April 2005, they had subsequently been issued in the name of the
company. The VAT number had also been
altered. In relation to the letter of 19 August 2006, in which payment of the sum certified in Certificate
No 6 had been sought, no reference whatsoever was made to the pursuer as the
person entitled. Counsel also relied on
the abortive adjudication involving the company. He submitted that when all of these documents
were taken together it should be accepted that the company acted as a
principal, not an agent. That inference,
he submitted, was strengthened by certain other agreed facts. The contractor's insurance appeared to have
been in the name of the company rather than the pursuer as an individual. The notification to the Health and Safety
Executive had been signed by an individual who described himself as contract manager
for the company, on behalf of the company.
Payments made by the defenders had been made into the company's bank
accounts. The vans used by the pursuer
to carry out the work on the contract bore the company's name from 15 March 2005 onwards.
Certain of the invoices from suppliers and subcontractors were issued
the name of the company, although it was accepted that other invoices had been
issued to "M&S Contracts"; counsel submitted that in the latter invoices
that expression should be treated as referring to the company. Finally, other items of correspondence
between the pursuer and the defenders' contract administrators had been
conducted in the name of the company.
The result of all of these actings was that the pursuer, who was a
director of the company, had permitted it to act as principal. Consequently the pursuer was now barred from
asserting that he was the principal.
Reference was made to statements of the law in the Stair Memorial
Encyclopaedia, Agency and Mandate Reissue, paragraph 153.
[28] None of
these matters seems to me to alter the obvious inference that the company acted
as agent for the pursuer as an individual.
The change in the invoices and VAT number can readily be explained by
the fact that the company had begun to act as agent for the pursuer in respect
of the contract. It is a matter of
agreement that all of the first five invoices were paid by cheques issued to
either M&S Contracts (the first three payments) or M&S Contracts Ltd
(the fourth and fifth payments). That
seems to me to indicate that the defenders simply accepted the fact that the
administration of the contract was being carried out by the company. The fact
that the cheques were paid into the company's bank account was a matter of mere
administrative convenience; in any event that would not necessarily be known by
the defenders. The fact that the
company's vans (and no doubt its employees) were used to perform the contract,
and the fact that some invoices from suppliers and subcontractors were issued
to the company, are readily explained by the concept of ad hoc agency. The same is true of the letter to the Health
and Safety Executive. So far as the
insurance is concerned, the only document that was available was a letter from
the insurance broker to the defenders' contract administrators. The policy itself was not available. Thus it is impossible to know what the
precise scope of the insurance was. In
any event, if the contract works were in fact being carried out by the company
as agent for the pursuer, it might well be appropriate that the insurance was
in the company's name. Without the
policy it is impossible to be certain.
None of the matters relied upon by counsel can in my view be considered
as an acceptance that the contract had been novated to the company. Perhaps the strongest point for the defenders
is the fact that the original adjudication was raised in the name of the
company. That is explained, however, by
the simple fact that either the pursuer or Longworth Consulting made a mistake. In these circumstances the argument that the
pursuer was barred from asserting that he was the principal seems misplaced; if
the company were to act as principal the defenders' agreement would be
required, and there is no hint that such consent was either asked for or given.
[29] For the
foregoing reasons I am of opinion that a dispute or difference existed between
the present parties prior to the service of the notice of adjudication on 26 September 2005. On that basis I will repel the pleas in law
for the defenders, sustain the pleas in law for the pursuer and pronounce
decree de plano in terms of the conclusions
of the summons.