OUTER HOUSE, COURT OF SESSION
[2006] CSOH 145
|
CA158/04
|
OPINION OF LORD REED
in the cause
MOYARGET
DEVELOPMENTS LIMITED
Pursuers;
against
MRS ROVE MATHIS AND
OTHERS
Defenders:
ญญญญญญญญญญญญญญญญญ________________
|
Pursuers: Borland; MacRoberts
Defenders: Sandison;
Brodies, WS
15 September 2006
Introduction
[1] In
this action the pursuers, a company engaged in property development in the
North of Scotland, seek payment of ฃ527,535.05 from the defenders in respect of
work which they claim to have carried out on their behalf in connection with
the proposed development of a site in Dingwall.
[2] The
action was commenced in September 2004.
The summons was adjusted in March, April and June 2005. As then formulated, the pursuers' claim
proceeded on the basis that, although they carried out work on the instructions
of the defenders, they did so while the parties conducted negotiations with a
view to formalising their relationship.
A draft contract was proposed, and various revisions were produced, but
no final agreement was reached. In
particular, the parties did not agree the remuneration which would be paid to
the pursuers for the services which they provided. In these circumstances, the pursuers
maintained that a contract was implied, in terms of which they were entitled to
be remunerated on the basis of quantum
meruit, or alternatively that they were entitled to payment on the basis of
unjust enrichment.
[3] In
answer, the defenders maintained that agreement had been reached at a meeting
on 7 February 2002 as to the circumstances in
which the pursuers would be entitled to be paid. They further maintained that those
circumstances had not come to pass; and
that the pursuers had in any event acted in breach of contract, entitling the
defenders to terminate the pursuers' instructions, as they had done. The pursuers on the other hand maintained
that, even if there was an agreement such as the defenders alleged, the
defenders had acted in breach of the agreement by wrongfully terminating the
pursuers' instructions before matters had progressed to the stage at which (but
for the termination of their instructions) they would have become entitled to
payment under the alleged agreement.
[4] In
these circumstances, the parties agreed that it was appropriate to determine,
as a preliminary issue, the question whether any agreement had been reached on
or around 7 February 2002 as to the basis on which the pursuers might be
remunerated for carrying out the work they were instructed to do in
facilitating the development of the site, and, if so, what the terms of that
agreement were.
[5] After
hearing evidence, I issued an opinion on 20 October
2005
in which I arrived at the following conclusion:
"In these circumstances, I
find that agreement was reached on or around 7 February 2002 between the
pursuers on the one hand and the defenders on the other as to the basis upon
which the pursuers might be remunerated for the carrying out of the work they
were instructed to do in facilitating the development of the site at Chestnut
Road/Tulloch Castle, Dingwall. The terms
of that agreement were that the pursuers were to be paid a fee in the event
that planning permission was granted for the development of the site as a
consequence of the pursuers' submission of an application for such permission
in accordance with the defenders' instructions.
I appreciate that the foregoing terms require further elaboration in
order to establish, in greater detail, what further terms were implied. Issues of that kind were not however explored
in any detail in evidence or in submissions.
It is sufficient at this stage to state the terms of the agreement in
the general language in which the parties might themselves have expressed their
understanding, at the time, of what had been agreed."
[6] The
case was put out for a hearing on further procedure in the light of those
findings. It was then agreed that
certain of the pursuers' pleas-in-law (predicated on the absence of any
agreement as to their remuneration) should be repelled, and that one of the
defenders' pleas-in-law (challenging such of the pursuers' averments and
pleas-in-law as were predicated on the absence of any such agreement) should be
sustained.
[7] There
then followed a process of amendment of the pleadings, initiated by the
pursuers. A minute of amendment was
lodged in December 2005 and adjusted in early March 2006. The defenders then gave written notice of
their intention to seek a debate on the relevancy and specification of the
pursuers' averments, focusing in particular on the pursuers' contention that
the parties' agreement contained an implied term that the pursuers would have a
continuing authority to act on behalf of the defenders following the submission
of the planning application to the planning authority. The pursuers' minute of amendment was then
further adjusted, in March and May 2006, to give greater specification in
relation to that and other matters.
[8] At the
conclusion of the amendment process a debate was fixed on the defenders' plea
to the relevancy and specification of the pursuers' averments, the defenders
having by then given notice of the points which they wished to argue. These related, first, to the pursuers'
averments concerning the implied term;
secondly, to the related question whether, if the pursuers had the
continuing authority contended for, the defenders were under any obligation in
relation to advice or proposals put forward by the pursuers after the
submission of the planning application, and, if so, what obligation; and thirdly, to the related point that the
pursuers' pleadings did not suggest that the defenders had failed to give the
pursuers any instructions in relation to any matter pertaining to the
application prior to its "deemed refusal", two months after its submission, or
prior to the termination of the pursuers' authority. Following the fixing of the debate, the
pursuers lodged a note of argument which reiterated the terms of their pleadings
in relation to the implied term, and referred to some of the authorities
discussed below.
The pursuers'
case as pleaded
[9] In
their pleadings as now amended, the pursuers aver that their director,
Mr Duncan, was approached by the first defender's brother, Mr Haig,
in November 2001 with a view to the pursuers' assisting in the development of
the site, which was owned by the defenders.
Mr Haig indicated that the first defender (Mrs Mathis) wished
to explore the possibility of developing the site; and, to that end, wished to draw on the
pursuers' expertise in development work.
Mr Duncan investigated the potential for planning permission being
granted in respect of the site, then met the first defender and her husband in
January 2002 to discuss his initial views.
A further meeting took place on 7 February
2002. In relation to that meeting, the pursuers
aver:
"The meeting discussed the
progress which Mr Duncan had made with his investigations... No agreement was reached as to the basis upon
which development of the site would proceed.
Mr Duncan was, however, instructed... to continue his work in progressing
the development of the site."
[10] The
pursuers' averments continue:
"Explained and averred that
(as the court has held) the terms of the parties' agreement were that the
pursuer was to be paid a fee in the event that planning permission was granted
for the development as a consequence of the pursuer's submission of an
application for such permission in accordance with the defenders' instructions.
It was an implied term of the parties'
agreement that the pursuer would have continuing authority to act on behalf of
the defenders during the planning phase, i.e. up until the point at which the
planning application was determined."
[11] The
basis for the implication of that term is then stated:
"The said term requires to
be implied in order to give the parties' agreement such business efficacy as
they must have intended that it should have.
The said term reflects the presumed intention of the parties. Its implication is necessary in order to
produce the result that the parties to the agreement must have intended. Without the said term, the pursuer would have
been unable to influence how the development was taken forward in the planning
phase, and, in particular, would have had no influence, following the
submission of the planning application, in relation to whether that application
was ultimately granted by the planning authority. In that event the pursuer would have been
unable to influence whether it might ultimately be paid its fee. Every reasonable man in the position of the
pursuer would seek such a term for his own protection, and no reasonable man
would refuse to accede to it."
The pursuers then go on to aver that the defenders
acted in breach of that implied term, by terminating their authority to act by
letter dated 6 July 2004.
[12] The
pursuers later aver:
"As to the defenders'
averments anent the deemed refusal of the planning application, following the
submission of the application the pursuer advised Mr Haig that it had been
'called in' for review by the planning authority. Thereafter, the pursuer received no further
instructions from Mr Haig or the first defender in relation to the application. Accordingly, esto the application lapsed, it did so for want of instructions
from Mr Haig or the first defender in relation to the application."
As I understood the explanation of these averments
given by counsel for the pursuers in the course of his submissions, by "called
in" was meant a decision by the local planning authority that the application
should be dealt with by staff at its offices in Inverness rather than by the
local planning officer in Dingwall, and by "lapsed" was meant the deemed
refusal of the application (for the purposes of any appeal) two months after
its submission, by virtue of regulation 14(2) of the Town and County
Planning (General Development Procedure) (Scotland) Order 1992 (SI 1992 No.224)
and section 47(2) of the Town and Country Planning (Scotland) Act
1997. In relation to the latter point,
it appears from the pursuers' averments that they submitted on application for
detailed planning permission, with (they aver) the agreement of the
defenders. Although the date on which it
was submitted is not averred by the pursuers, it appears from the submissions
at the debate that there is no dispute that the date was 8 April 2004, as averred by the defenders. The deemed refusal would therefore have
occurred some weeks before the pursuers' instructions were withdrawn on 6 July 2004.
[13] The
pursuers further aver:
"As regards the alleged
difficulties with the planning application condescended upon by the defenders,
one of the normal purposes of submitting such an application is to 'flush out'
any issues which the planning authority might have in relation to a proposed
development. The issues which had been
discussed by the pursuer's Mr Duncan and the local planning officer, prior
to the pursuer's authority to act in relation to the project being terminated,
were not such as to indicate that there was a fundamental obstacle to the
application being granted. Discussion of
such issues with the local planning authority following the submission of a
planning application is a perfectly normal part of the planning process."
[14] The pursuers
go on to aver:
"Esto there was an agreement as condescended upon by the defenders [viz. the agreement which was found
proved at the preliminary proof], the defenders acted in material breach of
that contract by wrongfully terminating the pursuer's authority to act relative
to the project, as aforesaid. As a
result, on that hypothesis, the pursuer has sustained loss and damage. In those circumstances, but for the said breach
the pursuer would have proceeded with the planning application; and planning permission would have been
obtained."
[15] Finally,
I note the pursuers' averments:
"With regard to the
defenders' averments anent alleged repudiation of the agreement by the pursuer,
it is explained and averred that there was no such repudiation. Indeed,
the pursuer had performed its part of the bargain by submitting the planning
application, as aforesaid" (emphasis added).
The
submissions for the defenders
[16] In seeking the dismissal of the action,
counsel for the defenders submitted that the basis upon which the term in
question was sought to be implied was that it was necessary to give business
efficacy to the contract (as counsel for the pursuers confirmed). The criterion to justify an implication of
that kind was necessity, not reasonableness: The
Moorcock (1889) 14 PD 64; Liverpool City Council v Irwin [1977] AC 239; Scally v
Southern Health Board [1992] 1 AC 294
at pages 306-307 per Lord Bridge
of Harwich.
[17] One
consequence of the criterion of necessity was that a term could not be implied
where there were a number of different terms to which the parties might have
agreed. Reference was made to the speech
of Lord Pearson (with which Lord Guest, Lord Diplock and Lord Cross of Chelsea expressed agreement) in Trollope & Colls Ltd v North
West Metropolitan Regional Hospital Board [1973] 1 WLR 601. The case concerned a building contract under
which the work was to be done in three phases, with fixed dates for the
completion of each phase. Phase III
was to begin six months after the issue of the certificate of practical
completion of phase I. In the
event, a delay in the completion of phase I reduced the time available for
the completion of phase III. The
question was whether there was an implied term under which an extension of time
was allowed.
[18] At
first instance, Donaldson J held that no such term could be implied, citing a
passage from the judgment of Scrutton LJ in Reigate
v Union Manufacturing Co (Ramsbottom) Ltd
[1918] 1 KB 592 at page 605:
"A term can only be implied
if it is necessary in the business sense to give efficacy to the contract; that is, if it is such a term that it can
confidently be said that if at the time the contract was being negotiated some
one had said to the parties, 'What will happen in such a case', they would both
have replied, 'Of course, so and so will happen; we did not trouble to say that; it is too clear'. Unless the court comes to some such
conclusion as that, it ought not to imply a term which the parties themselves
have not expressed."
Donaldson J applied that test to the facts of the case
before him, stating, as quoted by Lord Pearson at page 606:
"When I come to imagine the
answers of the parties if asked as they signed the contract, 'What happens
about the time for completion of phase III, if completion of phase I is
delayed?' I am quite unable to discern
any certain answer."
[19] In the
Court of Appeal, Cairns LJ cited another deservedly well-known dictum, from the
opinion of Lord Wright in Luxor (Eastbourne) Ltd v Cooper [1941] AC
108 at page 137:
"But it is well recognised
that there may be cases where obviously some term must be implied if the
intention of the parties is not to be defeated, some term of which it can be
predicated that 'it goes without saying', some term not expressed but necessary
to give to the transaction such business efficacy as the parties must have
intended. This does not mean that the
court can embark on a reconstruction of the agreement on equitable principles,
or on a view of what the parties should, in the opinion of the court,
reasonably have contemplated. The
implication must arise inevitably to give effect to the intention of the
parties."
Cairns LJ observed (as quoted by Lord Pearson at page
607):
"One reason why in my view
it is impossible to imply the term contended for here is that I cannot find any
means of determining, if the parties had considered there should be some
extension in relation to phase III if phase I were not completed by the
due date, what period of extension would have been agreed."
[20] In the
House of Lords, Lord Pearson affirmed the correctness of a test of necessity,
stating (at page 609):
"An unexpressed term can be
implied if and only if the court finds that the parties must have intended that
term to form part of their contract: it is
not enough for the court to find that such a term would have been adopted by
the parties as reasonable men if it had been suggested to them: it must have been a term that went without
saying, a term necessary to give
business efficacy to the contract, a term which, though tacit, formed part of
the contract which the parties made for themselves."
Since there were at least four possible extensions of
time which the parties might have agreed, none of those possibilities was
obviously what the parties must have intended, and therefore none could be
implied.
[21] In the
present case, counsel submitted, it was clear from the pursuers' averments that
they had submitted an application for planning permission in accordance with
the defenders' instructions. The pursuers
sought to imply a term "that the pursuer would have continuing authority to act
on behalf of the defenders" until the application was determined; but it could not be suggested that the mere
existence of authority would have enabled the pursuers "to influence whether
[they] might ultimately be paid [their] fee".
The argument must be that the pursuers were entitled to exercise such
authority - to do something - and that the defenders were obliged to allow them
to do this. The pleadings offered no clue
as to the nature of this authority. To
do whatever the pursuers chose? To make
proposals, subject to the defenders' veto?
Or were the defenders bound not to seek to control the pursuers'
exercise of their authority arbitrarily or capriciously? Or were the defenders bound to act as a
reasonable person would act in the circumstances? For example, could the pursuers lodge an
appeal, on behalf of the defenders, against the refusal or deemed refusal of
planning permission? Suppose the
planning authority wanted the density of the proposed housing to be reduced,
with consequences for the profitability of the development: were the defenders obliged to acquiesce in
whatever reduction in housing the pursuers were minded to agree to? What if the planning authority wished to negotiate
an agreement to secure "planning gain"?
[22] The
pursuers' pleadings were also wholly inspecific as to how they would have
"proceeded with the planning application" - what they would have done, in the
exercise of their authority - which would have resulted in the granting of
planning permission. Moreover, their
position in their pleadings was that "the pursuer had performed its part of the
bargain by submitting the planning application": what was suggested was a power to act, in
circumstances where the pursuers had already performed their contractual
obligations. A further difficulty
concerned the duration of the supposed authority: it did not apparently expire on the deemed
refusal of the application (since that had occurred prior to the termination of
the pursuers' authority).
[23] The
pursuers' difficulties intensified when one considered the case law concerning
contracts where an agent was engaged to attempt to obtain a beneficial result
for his principal and was entitled to a fee only on the occurrence of that
result. In Luxor (Eastbourne) Ltd v Cooper, for example, the agent was entitled to a fee if the
property was sold by his principal to a purchaser whom the agent had
introduced. The argument that there was
an implied term that the principal would not, without reasonable cause, refuse
to sell the property to a purchaser whom the principal had introduced was
rejected, as not being necessary to give the contract the business effect which
both parties must have intended it should have.
Viscount Simon LC said, at pages 120-121:
"The agent is promised a
reward in return for an event, and the event has not happened. He runs the risk of disappointment, but if he
is not willing to run the risk he should introduce into the express terms of
the contract the clause which protects him."
Lord Russell of Killowen distinguished (at
page 128) contracts under which one party bound himself to do certain
work, and the other bound himself to pay remuneration for the doing of it:
"As I have already
indicated, the case under consideration is quite different from a contract by
which an agent is employed and is by the contract of employment bound to do
specified work for the principal... In such contracts a term must, if not
expressed, necessarily be implied that the principal will do nothing to prevent
the agent from doing the work which the contract binds him to do."
[24] In the
present case, the pursuers did not suggest that they had an obligation to do
anything after the planning application had been submitted: on the contrary, they averred that "the
pursuer had performed its part of the bargain by submitting the planning
application." The position was therefore
analogous to that in the Luxor case, as analysed by Lord
Wright at page 136: the pursuers
had performed the services contracted for, but their right to payment was
conditional on the occurrence of a future event: namely, the granting of the planning
application. That condition was never
fulfilled, so that the right to be paid never materialised. The position in the present case, once the
planning application had been submitted, also fell within the scope of Lord
Romer's analysis, at page 153:
"The respondent... was not
employed to do anything at all, and would have committed no breach of his
agreement with the appellants had he remained entirely inactive. There was no 'contract of agency'. If A and B agree that B shall do some work
for A for reward, it is no doubt an implied condition of the agreement that A
shall not prevent B from performing his part of the contract, i.e. doing the
work and so earning his reward. But I
can see no ground whatsoever for implying any such condition where B is under
no contractual obligation to do the work... if B is under no obligation to do the
work, why should A be under an implied obligation not to prevent him doing it?"
[25] Counsel
also observed that the desire of the agent to be paid could not be elevated
into a principal aim of the contract, capable of generating implied terms. Reference was made in that connection to the Luxor case at
page 116, per Viscount Simon LC (quoting the judgment of Scrutton LJ in Trollope & Sons v Martyn Brothers [1934] 2 K.B. 436
at page 444), and to Marcan Shipping
(London) Ltd v Polish Steamship Co (The "Manifest Lipkowy") [1989] 2 Ll. L.R. 138
at page 144 per Bingham LJ.
Reference was also made to Mona
Oil Equipment and Supply Co Ltd v Rhodesia
Railways Ltd [1949] 2 All E.R.1014.
The submissions for the pursuers
[26] In support of his motion
that a proof before answer should be allowed on all remaining issues, counsel
for the pursuers began by addressing the legal basis for the implication of a
contractual term, under reference to The
Moorcock, Scottish Power plc v Kvaerner Construction (Repairs) Ltd 1999
S.L.T. 721 and E & J Glasgow Ltd v UGC
Estates Ltd [2005] CSOH 63.
Particular emphasis was placed on an observation made by Lord Macfadyen
in the Scottish Power case at
page 725, in relation to the test of "business efficacy":
"In seeking to
judge whether that test is satisfied, it will ordinarily be helpful to ask the
question posed in William Morton & Co
v Muir Brothers & Co 1907 SC 1211,
namely whether the term is one which in the circumstances every reasonable man
would seek for his own protection and no reasonable man would refuse to accede
to."
Counsel relied on that observation
as relaxing the criterion of necessity and introducing a test of
reasonableness. It seems to me that that
was not Lord Macfadyen's intention, and that his observation has to be read
with care: the words "every" and "no"
are important. It is not the law that,
if the court finds that a term would have been adopted by the parties as
reasonable men had it been suggested to them, that term is implied in their
contract: that is made abundantly clear
by the authorities cited earlier.
[27] In relation to the term sought to be implied in the present
case - that "the pursuer would have continuing authority to act on behalf of
the defenders ... up until the point at which the planning application was
determined" - counsel said that that also imported a continuing obligation, on
the part of the pursuers, to provide services with a view to the eventual
determination of the planning application.
The averment that "the pursuer had performed its part of the bargain by
submitting the planning application" meant only that the pursuers had performed
the obligations incumbent upon them up to that point: not that they had performed the whole of
their obligations under the contract.
The pursuers would, for example, be under a continuing obligation to
attend meetings with the planning authority, to discuss matters with them, to
report on those discussions to the defenders, "and so on". These obligations would continue until there
had been an express determination of the application. The deemed refusal was not a "determination",
within the meaning of the term sought to be implied. A deemed refusal had not been within the
parties' contemplation at the time when the contract was made. The reference, in the implied term, to "the
planning application" included amendments instructed by the defenders. The pursuers' continuing authority and
obligations related to the possibility that the application might be revised. The pursuers would always require to act in
accordance with the defenders' instructions.
Any planning permission obtained had to be acceptable to the defenders,
and any revisal of the application would require therefore to be in accordance
with their instructions. Reference was
made to Alpha Trading Ltd v Dunshaw-Patten Ltd [1981] Q.B. 290
at page 304 per Brandon LJ.
[28] Whether the parties' agreement contained the implied term in
question was to be judged as at 7 February
2002, when the agreement was made.
The factual background had been set out in the opinion issued following
the preliminary proof. The defenders
needed someone to assist them in obtaining planning permission. If Mrs Mathis had been asked whether the
services to be performed by the pursuers were to continue after the submission
of the planning application, insofar as issues might be raised by the planning
authority which could be addressed by the revisal of the application, she would
have agreed: no-one else was interested
in doing the work. Counsel referred in
that regard to paragraph 48 of the earlier opinion, where evidence given
by Mr Haig was summarised. Equally,
from the pursuers' perspective, without the implication of a term that they
were to continue to provide services after the submission of the application,
they would be unable to influence whether the application was granted, in the
event that matters were to be raised which could be addressed by the revisal of
the application.
[29] Counsel also referred to paragraph 63 of the earlier
opinion, where I stated, in relation to the pursuers' Mr Duncan:
"By agreeing to
provide services during the planning phase he would be in a position to
influence decisions as to how the development was taken forward ..."
Counsel interpreted that as a
finding that Mr Duncan would be in a position to affect or influence decisions
as to whether planning permission was granted.
I observe that, quite apart from any other difficulties involved in
relying at this stage on observations in an opinion based on evidence heard at
a preliminary proof, directed to a different issue from that with which the
court is at present concerned, this submission in any event misinterprets what
was said. That may be apparent if the
statement in question is placed in its context:
"In return for deferring
his fees, Mr Duncan would, by entering into such an agreement, be well
placed to obtain an involvement in the construction of the development. It is clear from his own evidence that his
desire to be involved in the construction phase was the motivation for
responding to Mr Haig's invitation in the first place. He pursued that objective consistently
thereafter, as the correspondence demonstrates.
By agreeing to provide services during the planning phase he would be in
a position to influence decisions as to how the development was taken forward,
and might be awarded the contract to carry out the development."
In stating that Mr Duncan would
"be in a position to influence decisions as to how the development was taken
forward", I intended to convey that he would be able to influence decisions in
relation to the future progress of the development once planning permission had
been granted (for example, in relation to the construction of the development
and the sale of the properties): in
particular, in relation to the selection of the main contractor.
Response on behalf of the defenders
[30] Since little if any notice of the pursuers' argument appeared
to me to have been given in either the pursuers' pleadings or the note of
argument lodged in advance of the debate, I allowed counsel for the defenders
an opportunity to respond. Counsel
observed that the note of argument lodged by the defenders six weeks in advance
of the present debate had given notice of the points to be made, and had
afforded the pursuers an opportunity to seek to amend their pleadings in order
to meet those points. Nevertheless, it
had been in the course of the submissions on behalf of the pursuers that the
court, and the defenders, had learned for the first time what their case
was. In particular, there were two
fundamental aspects of the pursuers' case as stated in submissions for which
one would search their pleadings in vain:
first, the suggestion that the implied term imposed a continuing
obligation on the pursuers, after the submission of the application, to attend
meetings, discuss matters with the planning authority, report to the defenders
"and so on" (and not merely a power or authority for them to do so, which was
the case pleaded), and that that obligation would continue until there was an
actual as opposed to a deemed determination of the application; and secondly,
the suggestion as to the defenders' role in this process, namely that they were
not bound to act reasonably, or even not to act capriciously or arbitrarily in
dealing with whatever the pursuers might propose in the post-submission phase,
but were to be entitled to reject anything that was suggested to them, whatever
time and expense had been put into providing the proposal, and however likely
it was that the proposal, if agreed to by them, would secure the grant of
planning permission on favourable terms.
It was unsatisfactory for such fundamental contentions to be advanced
for the first time in the course of debate:
the relevancy and specification of the pursuers' averments depended on
their pleadings, not on the different case argued orally.
[31] Moreover, it was illegitimate for reliance to be placed on
observations or incidental findings made in the opinion issued after the
preliminary proof, which had been concerned with a different issue: Noble v
De Boer 2004 S.C. 548. The present issue was the adequacy of the
pursuers' pleadings on record.
[32] In relation to the contention that the pursuers were under an
obligation to continue to render advice and assistance to the defenders until
the actual determination of the application, counsel asked why the existence of
such a term was obviously necessary, to the extent that it "went without
saying". Why should the pursuers not
simply have an option to continue to act, rather than an obligation to do so,
whatever circumstances might ensue? It
was easy to see why it was now suggested that such an obligation existed: that would enable the pursuers to shelter
under the "non-prevention of performance of an obligation" line of
authority. It was less easy to see the
commercial merit of the contention that the pursuers were to be obliged to
continue to tender a full advice and assistance service to the defenders (or
was it something else?), whatever circumstances might come to exist: circumstances which might radically alter the
assessment of the likelihood of the planning application being granted. The lack of obvious commercial sense was
particularly clear when one considered that the defenders, on the pursuers'
argument, were free to dismiss out of hand any proposals which the pursuers
might put forward. Why should the
pursuers "inevitably" have bound themselves to tender advice and assistance
which might be unwanted, and which the defenders could freely disregard? From the pursuers' perspective, a more obvious
term would have been that they should have the option to continue to provide
advice and assistance to the defenders as long as that appeared to them to be a
sensible commercial proposition. That, however,
was not the term contended for. Equally,
although it was easy to see why it was now suggested that the defenders were
not to be obliged to act reasonably in responding to the post-application
advice tendered to them - namely, because a "reasonableness" term had been
authoritatively held to be unworkable (Luxor)
- from a commercial point of view the pursuers would at least have wished to
stipulate that the defenders should not act arbitrarily or capriciously. No rationale had been advanced for the
contention that the implied term required the continued provision of the
pursuers' services until the actual determination of the application, as
opposed to its deemed refusal.
[33] The implied term contended for would thus produce a situation
where the pursuers were obliged to continue spending time and effort, however
circumstances might change, until a date which neither party could control; and
where the defenders were obliged to continue receiving advice and assistance,
but were not obliged to do anything in response. That was not a commercially sensible result,
let alone so obvious that it would go without saying. The term contended for went far beyond
anything which had previously been accepted as an implied term in any case
cited to the court. Such a term would
only have been reached, if at all, after a process of negotiation between the
parties: it could not have been regarded
as so obviously implicit in the agreement as not to require any mention.
[34] In the light of the implied term now contended for, the
pursuers' averments were irrelevant in respects not previously discussed. The averments that the pursuers received no
instructions from the defenders after advising them that the application had been
"called in" (i.e. was being dealt with in Inverness rather than Dingwall), and
that the application "lapsed" (i.e. there was a deemed refusal) as a result of
the defenders' failure to give some (unspecified) instructions, were obscure to
the point of irrelevance, and incomprehensible if (as appeared to be the
argument) the defenders were not obliged to take any positive action in
relation to the application following its submission.
[35] Similarly, the averment that, but for the termination of the
pursuers' authority, "the pursuer would have proceeded with the planning
application, and planning permission would have been obtained" could now be
seen to be not only wholly lacking in specification, but also irrelevant in a
deeper sense. Nothing was said about how
the pursuers' continuing authority would have brought about the grant of
planning permission: nothing was said
about the problems which would have been raised by the planning authority in
relation to the application, or about the advice which the pursuers would have
tendered to the defenders with a view to surmounting any such problems, or
about what the defenders' response to such advice would have been. Since it was now contended by the pursuers
that the defenders had a free hand to give or withhold instructions to or from
the pursuers, the pursuers' case was perilled on their establishing that they
would have been able to secure the defenders' agreement to whatever it was that
they needed to do in order for planning permission to have been granted. Averments about these matters were crucial to
the relevancy of the pursuers' case.
[36] In a brief response, counsel for the pursuers submitted that Noble v De Boer was distinguishable from the present case, partly because
the present case involved a debate (rather than a proof) following a
preliminary proof, and partly because in the present case the judge who had
heard the preliminary proof was also the judge hearing the debate.
Discussion
[37] I have set out counsel's submissions in detail, as the case was
well argued on both sides; and, in the light of the submissions, I can state my
own reasons relatively briefly.
[38] In commercial proceedings, the court is not necessarily
confined to a consideration of the parties' pleadings in deciding whether the
requirements of relevancy and specification are satisfied: in some cases, there can be scope for
adopting other means by which fair notice of a party's case can be given. In the present case, however, the pursuers'
pleadings are the only formal statement of the pursuers' case before the
court.
[39] The pursuer's averments contain no indication that it is
contended that it was an implied term of the agreement between the parties that
the pursuers' obligation to provide services to the defenders was to continue
after the planning application had been submitted. The averment that "the pursuer would have
continuing authority to act on behalf of the defenders ... up until the point at
which the planning application was determined" does not suggest that the
pursuers would have a continuing obligation to attend meetings with the
planning authority, to discuss matters with them, to report on these
discussions to the defenders, "and so on" (whatever that phrase might import). The averments that the pursuers were to be
paid "in the event that permission was granted for the development as a
consequence of the pursuers' submission of an application for such permission",
and that "the pursuer had performed its part of the bargain by submitting the
planning application" appear, at first sight, to imply that the pursuers'
duties were fulfilled once the application was submitted, and that their
entitlement to payment then depended on whether that application was
granted.
[40] Furthermore, the pursuers' pleadings appear to me to provide no
basis for the leading of evidence from which the court could conclude that the
term contended for (and no other term) went without saying as part of the
agreement made on about 7 February 2002; that it was an implication
arising inevitably to give effect to the intention of the parties; that it was
a term which, though tacit, formed part of the contract which the parties had
made for themselves. In that connection,
the contentions now made on behalf of the pursuers give rise to numerous
difficulties, several of which were mentioned by counsel for the
defenders. The pursuers' pleadings do
not, for example, appear to me to lay a foundation for establishing that the
pursuers were necessarily obliged to continue performing services after the
submission of the application, rather than their services coming to an end once
the application had been submitted. I am
also struck by the contention that the pursuers' obligation to perform services
was to continue indefinitely (and, in particular, notwithstanding the deemed
refusal of the application), until the application was actually
determined: something which would not
necessarily happen unless there was an implied term that the defenders were
obliged to make an application for judicial review in order to have the
planning authority compelled to issue a determination, in the event that they
failed to do so voluntarily, or alternatively an implied term that the
defenders were obliged to appeal against a deemed refusal, in order to obtain a
determination on appeal.
[41] Equally importantly, the pursuers' pleadings are entirely
lacking in specification as to what would have happened, if their instructions
had not been withdrawn, which would have resulted in the granting of planning
permission. What were the difficulties
which they would have addressed? What
advice or proposals would they have given the defenders, or how would they have
dealt with the planning authority, so as to overcome the difficulties? How would the defenders have responded to any
such advice or proposals? For what, at
the end of this process, would planning permission have been granted (i.e. the
application as submitted, or a revised version), bearing in mind that the
pursuers' claim is calculated by reference to the cost of the development? In the absence of any notice of the pursuers'
position in respect of this essential part of their case, their averments must
be regarded as irrelevant.
[42] It is an important objective of commercial procedure that cases
should be dealt with expeditiously. I
have narrated the history of the present case.
It is apparent from that history that the court has been generous in
allowing the pursuers time to plead a relevant case. The case has been before the court for
two years. During that time, the
pursuers have adjusted and amended their pleadings on numerous occasions. They have had every opportunity to address
the points made in the present debate.
No doubt advisedly, counsel for the pursuers did not, in the course of
the debate, move for leave to make further amendments.
[43] In the circumstances, I shall sustain the defenders'
preliminary plea, and dismiss the action.
[44] Finally, I note that the pursuers' pleadings, in respect of the
background to the agreement reached on 7 February 2002, and the implied term
said to have been included in that agreement, incorporate a letter from Mr
Duncan to Mrs Mathis dated 25 January 2002, which states:
"The Planning
Officers are prepared for us to submit our proposals for discussion and
amendment, as a means of opening up a dialogue, without us having to submit any
fee. However, once it is agreed what is
acceptable to all, then the fees will be required to be paid on submission of
the formal application."
The implication, quantum valeat, would appear to be that
Mrs Mathis was being told at that time that discussion with the planning
authority, and the "amendment" of proposals, was to precede the submission of
the planning application: the
application was to be submitted "once it is agreed what is acceptable to all". I mention this letter, since it forms part of
the pursuers' pleadings; but I have attached no significance to it in arriving
at my decision, since neither counsel referred to it in the course of the
debate.