FIRST DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord PresidentLady CosgroveSir David Edward, Q.C. |
[2006] CSIH 12A225/05; A226/05 OPINION OF THE COURT delivered by TEMPORARY JUDGE SIR
DAVID EDWARD, Q.C. in RECLAIMING MOTIONS by SCRABSTER HARBOUR TRUST Pursuers and Reclaimers; against MOWLEM plc, trading as
MOWLEM MARINE Defenders and Respondents: and MOWLEM plc, trading as
MOWLEM MARINE Pursuers and Respondents; against SCRABSTER HARBOUR TRUST Defenders and Reclaimers: _______ |
Alt: Davidson, Q.C.; MacRoberts
(for Scrabster)
Introduction
[3] The issue in
both cases is the same - namely, whether a letter dated
[4] Scrabster
contend that the letter of 15 September 2004 was invalid as a notice requiring
arbitration because it did not comply in a number of respects with the
requirements of Article 1:3 of the Scottish Arbitration Code ("the Code"). In particular, it did not comply with the
requirements of Article 1:3(g) of the Code in that it did not propose the name
of an arbiter. (The Code uses the term
'arbitrator' rather than 'arbiter', presumably because it is intended for use
outside as well as within
[9] The terms of
Mowlem's letter of
The Contract between
the Parties
[10] The contract
between the parties provided, so far as material, as follows:-
"The Conditions of Contract referred
to in the Tender shall be the Conditions of Contract (Fifth Edition) prepared
by the Institution of Civil Engineers ... dated June 1973 (Revised January 1979)
... including ... ICE/5th Edition/HGCR/March 1998; ... ICE/ScotArb/April
2001, ... with addendum's(sic), alterations and special conditions as shown in Part 2 below
and these conditions shall be deemed to form and shall be read and construed as
part of this Contract".
[11] The only
relevant "addendum, alteration or special condition" provided as follows:-
"Clause 67 APPLICATION TO
Sub-Clause (1) is deleted and
substituted by the following:-
If the Works are situated in Scotland
the Contract shall in all respects be construed and operate as a Scottish
contract and shall be interpreted in accordance with Scots law and where any
dispute in connection with the Contract is to be determined by a Court that
Court shall be either the Court of Sessions (sic), Edinburgh or a Sheriff Court in Scotland".
"Clause 66(9)
Arbitration
(a) All
disputes arising under or in connection with the Contract or the
carrying out of the Works other than failure
to give effect to a decision of an adjudicator shall be finally determined by
reference to arbitration. The party
seeking arbitration shall serve on the other party a notice in writing (called
a Notice of Arbitration) to refer the dispute to arbitration.
(b) Where
an adjudicator has given a decision under Clause 66(6) in
respect of the particular dispute the Notice
of Arbitration must be served within three months of the giving of the decision
otherwise it shall be final as well as binding.
Clause 66(10)
Appointment of arbitrator
(a) The arbitral tribunal
shall be appointed by agreement of the parties.
President or Vice- President to act
(b) Failing agreement of the parties as
aforesaid at sub-clause (a) above
the following shall apply.
(i) Reference at Articles 3.5 3.6 3.7 3.8
and 6.2 of the Code to the
Chairman of the
(ii) 'President' means the President for the
time being of the
Institution of Civil
Engineers or any Vice President acting on his behalf or such other person as
may have been nominated in the arbitration agreement to appoint the arbitrator
in default of agreement between the parties.
Clause 66(11)
Arbitration -
procedure and powers
(a) Neither party shall be limited in the arbitration to the evidence or
arguments
put to the Engineer or to any adjudicator pursuant to Clause 66 (2) or 66(6)
respectively.
(b) Unless the parties
otherwise agree in writing any reference to
arbitration may proceed notwithstanding that the
Works are not then complete or alleged to be complete.
Clause 67
(1) If
the Works are situated in Scotland the Contract shall in all respects be
construed and operate as a Scottish contract and shall be interpreted in
accordance with Scots law and where any dispute in connection with the Contract
is to be determined by a Court that Court shall be either the Court of Sessions
(sic), Edinburgh or a Sheriff Court
in Scotland.
(2) In the application of these Conditions
and in particular Clause 66 thereof
(a) any reference
to arbitration under these Conditions shall be conducted
in accordance with the
law of Scotland "The Scottish Arbitration Code 1999" prepared by the Scottish
Council for International Arbitration the Chartered Institute of Arbitrators
(Scottish Branch) and the Scottish Building Contract Committee together with
the ICE Appendix (2001) thereto or any amendment to or modification of the
Appendix being in force at the time of appointment of the arbitrator. Such
arbitrator shall have full power to open up review and revise any decision
opinion instruction direction certificate or valuation of the Engineer or an
adjudicator.
(b)-(d)
[Effect has been given to these sub-clauses above]
(e) notwithstanding
any of the other provisions of these Conditions or of
the Code (including in particular Articles 22.7 and 22.8) nothing
therein shall exclude or be construed as excluding recourse to the Court of
Session under Section 3 of the Administration of Justice of (
(f) [not relevant here]
(g) [not relevant here]
(h) The application of Articles 1.6 1.8 1.9
and 1.10 of the Scottish
Arbitration Code 1999
shall be subject to the provisions of Clause 66(2) of the Contract unless the
Arbitrator otherwise directs. [Note: the effect of this provision is that disputes giving rise to
counterclaims must first have been submitted for decision by the Engineer.]".
The Scottish Arbitration Code
[13] Article 1 of
the Code provides,
so far as material, as follows:-
"Commencement of Arbitration
1:1 The party commencing
arbitration (the Claimant) shall give to the other party (the Respondent) a
Notice of Arbitration.
1:2 Arbitral proceedings shall be deemed to commence
on the date on which the Notice of Arbitration is received by the Respondent.
1:3 The Notice of Arbitration shall include the
following:
(a) The full names and
addresses of the parties (including
telephone, facsimile, telex numbers and e-mail
addresses if known).
(b) A reference to the
arbitration clause or the separate arbitration
agreement that is involved.
(c) A short statement of the
Claimant's claim, including the nature
of the claim, the sum or sums claimed, and the
Respondent's defence if known to the Claimant.
(d) The relief or remedy
sought.
(e) A demand that the matter
be referred to arbitration.
(f) If the arbitration
agreement calls for each party to appoint an
Arbitrator, the name and address (and telephone,
facsimile, telex number and e-mail address if known) of the Arbitrator
nominated by the Claimant.
(g) If the arbitration
agreement does not call for each party to
appoint an Arbitrator, a proposal by the Claimant of the
name of an Arbitrator with his full name and address (and his telephone,
facsimile, telex number and e-mail address if known).
(h) Within thirty days after
receipt of the Notice of Arbitration the
Respondent shall deliver to the Claimant a Notice of Defence.
Failure to deliver a Notice of Defence shall not delay the arbitration. If
there is such a failure all claims set forth in the Notice of Arbitration shall
be deemed to be denied.
1:4 The Notice of Defence
shall include:-
(a) Any comment on article 1:3(a)
(b) or (e) that the Respondent considers
appropriate.
(b) A short statement of the
Respondent's defence.
(c) If the arbitration
agreement calls for each party to appoint an Arbitrator
the name and address (and telephone, facsimile,
telex and e-mail address if known) of the Arbitrator nominated by the
Respondent.
(d) If the arbitration
agreement does not call for each party to appoint an
Arbitrator, then the Respondent shall intimate whether he accepts
the Arbitrator nominated by the Claimant and, if he does not accept him, the
names and addresses of the candidates whom the Respondent proposes.
[NOTE: There is no Article 1:5]
1:6 The Respondent may include in the
Notice of Defence any counterclaim within the scope of the arbitration clause.
If so, the counterclaim in the Notice of Defence shall include those matters in
Article 1:3 (b)(c)(d) and (e).
1:7 If a counterclaim is
asserted in the Notice of Defence, within 30 days after its receipt, the
Claimant shall deliver to the Respondent a reply to the counterclaim which
shall include the same matters as provided for in the Notice of Defence in
Article 1:5.
1:8 Failure by the Respondent to
include a counterclaim in the Notice of Defence shall not preclude the
Respondent from making a counterclaim at a later stage of the proceedings, if
the arbitral tribunal in its absolute discretion is prepared to permit it. Any
such counterclaim shall include those matters in Article 1:3. (b)(c)(d) and (e).
1:9 If any party has been
served with a Notice of Arbitration he may, at any time before the arbitral
tribunal has been appointed, give Notice of Arbitration in respect of any other
disputes which fall under the same arbitration agreement. All disputes
identified in such Notice of Arbitration shall be consolidated within the same
arbitral proceedings.
further Notice of Arbitration to the other, and to the arbitral
tribunal, referring any additional dispute which falls under the same
arbitration agreement to the arbitral tribunal proceedings and, whether or not
the other party consents to that other dispute being referred to the
proceedings, the arbitral tribunal may in its absolute discretion order that
the additional dispute should be referred to and consolidated within those same
proceedings or that it should not be so referred and consolidated."
[14] Article 3 of the Code provides, so far as material, as
follows:-
"Constitution of the Arbitral Tribunal, Number of
Arbitrators and Procedure for Appointment
3:1 The expression "the Arbitral
Tribunal" in this Code includes a sole Arbitrator or all Arbitrators where more
than one. All references to an Arbitrator shall include the masculine and the
feminine, and Arbitrator shall include Arbiter.
3:2 The parties are free to
agree on the number of Arbitrators. If they have not agreed, a single
Arbitrator shall be appointed.
3:3 If the parties have agreed that there shall be
more than one Arbitrator and the Claimant has nominated an Arbitrator in
accordance with Article 1:3(f) but the Respondent fails within thirty days of
receipt of the Notice of Arbitration either to deliver a Notice of Defence at
all, or to include in the Notice of Defence the name and address of another Arbitrator,
the parties shall be deemed to have agreed on a single Arbitrator and the
Arbitrator nominated by the Claimant shall be appointed as the sole Arbitrator.
3:4 If the parties have agreed
that there shall be a single Arbitrator and the Claimant has proposed an
Arbitrator under Article 1:3(g), and the Respondent does not intimate
non-acceptance of that Arbitrator within thirty days of the Notice of
Arbitration, then the Arbitrator proposed by the Claimant shall be appointed as
the sole Arbitrator.
3:5 Where the parties have agreed
a single Arbitrator be appointed and each has nominated an Arbitrator, they
shall endeavour to agree on the single Arbitrator within thirty days of
delivery of the Notice of Defence. If they cannot agree within that period either
party may apply, in the case of a domestic dispute to the Chairman of the
Chartered Institute of Arbitrators (Scottish Branch), and in the case of an
international dispute to the Chairman of the Scottish Council for International
Arbitration, to appoint the Arbitrator.
3:6 Where parties have agreed on an arbitral tribunal
of three and each has appointed an Arbitrator then unless the parties have
agreed on another method of appointment the party-appointed Arbitrators shall
endeavour within thirty days of the delivery of the Notice of Defence to agree
upon a third Arbitrator who shall be the chairman of the arbitral tribunal, or
if the parties have so agreed shall act as oversman. If the party-appointed
Arbitrators do not reach agreement within that time either party may apply in
the case of a domestic dispute to the Chairman of the Chartered Institute of
Arbitrators (Scottish Branch) and in the case of an international dispute to
the Chairman of the Scottish Council for International Arbitration, to appoint
that third Arbitrator or oversman.
3:7 Where application has been
made to the Chairman of the appropriate body to appoint an Arbitrator and that
Chairman refuses or fails to make an appointment within thirty days of the
application, either party may apply to the Court of Session,
3:8 Where the Chairman of the appropriate body is
unavailable or unable to act, a Vice-Chairman may act in his place.
3:9 For the purposes of this
Article the parties prorogate the exclusive jurisdiction of the Court of
Session,
The ICE Appendix (2001) to the
Scottish Arbitration Code
[16] The ICE
Appendix (2001) to the Code, Section 1.1 provides:
"Commencement of Arbitration
If a contract does not define when a
dispute or difference shall arise, then a dispute or difference shall be deemed
to arise when a claim or assertion made by one Party is rejected by the other
Party and that rejection is not accepted or no response to the claim is
received within a period of 28 days.
Subject only to the due observance of any condition precedent in the
Contract or the Arbitration Agreement either Party may then invoke arbitration
by serving a Notice of Arbitration on the other Party."
Annexed to the Appendix is a 'Sample' Notice of Arbitration
in the following form:
"To (Name of Respondent)
(Address
of Respondent)
Date
NOTICE
OF ARBITRATION
(Contact name)
We consider the following dispute(s)
or difference(s) have arisen between us:
We now give notice that we require the(se) dispute(s) or difference(s) to be referred to
arbitration.
Yours faithfully
For
and on behalf of
(Claimant's name)".
The Lord Ordinary's
Decision
Submissions of the
Parties in the Inner House
[24] Counsel for
Scrabster again founded on dicta in
the English cases cited to the Lord Ordinary (Mannai Investment Co Ltd v
Eagle Star Life Assurance Co Ltd [1997] AC 749, Burman v Mount Cook Land Ltd
[2002] Ch 256, and Fernandez v McDonald [2004] 1 WLR 1027) and the
judgment of Lord Prosser in Muir
Construction v Hambly 1990 SLT
830. These cases supported the
proposition that, where the contract required a notice to comply with certain
conditions or criteria, a notice that did not so comply was invalid. Counsel founded, in particular, on the dictum of Lord Hoffmann in Mannai:
"If the clause had said that the
notice had to be on blue paper, it would have been no good serving a notice on
pink paper, however clear it might have been that the tenant wanted to
terminate the lease." ([1997] AC at page 776 A-B)
Decision
Was Article 1:3 of the Code
incorporated in the Conditions of Contract?
The cases relied on by Scrabster
"At present, the applicable law is
clear and well settled, and [counsel for the landlord] informed your Lordships
that disputes were rare. In these
circumstances, the change in the law now proposed would not, in my opinion, be
justified." (page 761G).
"There is no justification for
placing notices under a break clause in leases in a unique category. Making due allowance for contextual
differences, such notices belong to the general class of unilateral notices
served under contractual rights reserved, e.g. notices to quit, notices to
determine licences and notices to complete ... To these examples may be added
notices under charter parties, contracts of affreightment, and so forth. Even if such notices under contractual rights
reserved contain errors they may be valid if they are 'sufficiently clear and
unambiguous to leave a reasonable recipient in no reasonable doubt as to how
and when they are intended to operate'." (page 768
E-G).
(We were not referred to any Scottish authority, and we have
found none, in which special significance or treatment has been accorded to
notices served under "contractual rights reserved".)
[41] Dealing with Hankey, Lord Steyn said:
"Hankey
v Clavering was decided more than
half a century ago. Since then there has
been a shift from strict construction of commercial instruments to what is
sometimes called purposive construction of such documents. Lord Diplock deprecated the use of that
phrase in regard to the construction of private contracts as opposed to the
construction of statutes. ... That is understandable. There are obvious differences between the
processes of interpretation in regard to private contracts and public statutes.
... It is better to speak of a shift towards commercial interpretation. ...
In determining the
meaning of the language of a commercial contract, and unilateral contractual
notices, the law therefore generally favours a commercially sensible
construction. The reason for this
approach is that a commercial construction is more likely to give effect to the
intention of the parties. Words are
therefore interpreted in the way in which a reasonable commercial person would
construe them. And the standard of the reasonable commercial person is hostile
to technical interpretations and undue emphasis on niceties of language. In contradistinction to this modern approach
Lord Greene MR's judgment in Hankey ...
is rigid and formalistic. Nowadays one expects
a notice to determine under a commercial lease to be interpreted not as a
'technical document' but in accordance with business common sense ... After all,
there is no reason whatever why such a document must be drafted by a lawyer. Qualitatively, the notices are of the same
type as notices under charter parties and contracts of affreightment. Such notices, even if they entail the
exercise of important options, are habitually drafted by commercial men rather
than lawyers. It would be a disservice
to commercial practice to classify such notices as technical documents and to
require them to be interpreted as such.
Nowadays one must substitute for the rigid rule in Hankey ... the standard of a commercial construction." (pages 770E to 771 D)
[42] Lord Hoffmann
took the decision in Hankey as his
starting point, saying that
"Common sense cannot produce such a
result: it must be the result of some
rule of law. If so, what is that rule
and is it correct?" (page 774C)
Having analysed the reasons for the decision, he concluded
that the rule of law in question was "an old rule about the admissibility of
extrinsic evidence to construe legal documents". He went on to characterise this rule as
"extraordinary" and "not merely capricious but also, for reasons which I need
not develop at length, incoherent" (pages 776G, 777E and 778C).
[43] Lord
Hoffmann's grounds for overruling Cadby
and Hankey were that:
"In the case of commercial contracts,
the restriction on the use of background has been quietly dropped. There are certain special kinds of evidence,
such as previous negotiations and express declarations of intent, which for
practical reasons which it is unnecessary to analyse, are inadmissible in aid
of construction. ... But apart from these exceptions, commercial contracts are
construed in the light of all the background which could reasonably have been
expected to have been available to the parties in order to ascertain what would
objectively have been understood to be their intention. ... Why, therefore should
the rule for construction of notices be different from those for construction
of contracts? There seems to me no
answer to this question." (page 779 F-H)
"I pass on to a second explanation
which also seems to me inadequate. Lord
Greene MR said ... that because such notices have unilateral operation, the
conditions under which they may be served must be strictly complied with. I have already said that this principle is
accepted on both sides. But, as an
explanation of the method of construction used in Hankey ..., it begs the question.
If the clause had said that the notice had to be on blue paper, it would
have been no good serving a notice on pink paper, however clear it might have
been that the tenant wanted to terminate the lease. But the condition in clause
7(13) related solely to the meaning which the notice had to communicate to the
landlord. If compliance had to be
judged by applying the ordinary techniques for interpreting communications,
there was strict compliance. The notice
clearly and unambiguously communicated the required message. To say that compliance must be strict does
not explain why some other technique of interpretation is being used or what
that is."( page 776 A-C)
[45] Lord Hoffmann
thus drew a distinction between
(i) a condition that is clear and unambiguous as it stands,
requires no
'interpretation'
and, because it involves the unilateral exercise of a right to bring the
contract to an end, calls for strict compliance according to its terms, and
(ii) a condition that leaves scope for interpretation and
application "in the
light of all the background which could
reasonably have been expected to have been available to the parties in order to
ascertain what would objectively have been understood to be their intention".
We take leave to doubt whether a Scottish court would feel
bound to declare a notice invalid on the ground that it was written on pink
paper rather than blue paper, but the point being made is clear enough and is
confirmed by the way in which Lord Clyde dealt with the matter.
[46] Lord Clyde
focussed the question at issue in this way:
"[T]he question in this appeal is
whether the two letters dated 24 June 1994 and sent by the appellant tenant to
the respondent landlord qualify as effective notices to determine the leases to
which each letter respectively referred.
Their validity as notices has to be tested against the terms of the power under which they were served. (page 780H, emphasis added)
He answered that question thus:
"The standard of reference is that of
the reasonable man exercising his common sense in the context and in the
circumstances of the particular case. It
is not an absolute clarity or an absolute absence of any possible ambiguity
which is desiderated. To demand a
perfect precision in matters which are
not within the formal requirements of the relevant power would in my view
impose an unduly high standard in the framing of notices such as those in issue
here. While careless drafting is
certainly to be discouraged the evident intention of a notice should not in
matters of this kind be rejected in preference for a technical precision." (page 782 C-D, emphasis
added)
[48] These
propositions do not appear to us to be at variance with the law of
Was compliance with Article 1:3 of
the Code a formal requirement for exercise of the power under Clause 69(9)(a) to require that a dispute between the parties be referred
to arbitration?
[62] Further
considerations emerge from consideration of Article 1:3 of the Code itself.
[68] Mowlem's
letter of