Robertson Group (Construction) Ltd v. Amey-Miller (Edinburgh) Joint Venture & Ors [2005] ScotCS CSOH_60 (10 May 2005)
OUTER HOUSE, COURT OF SESSION [2005] CSOH 60 |
|
CA80/03
|
OPINION OF LORD DRUMMOND YOUNG in the cause ROBERTSON GROUP (CONSTRUCTION) LIMITED Pursuer; against (FIRST) AMEY-MILLER (EDINBURGH) JOINT VENTURE; (SECOND) AMEY PROGRAMME MANAGEMENT LIMITED and (THIRD) MILLER CONSTRUCTION (UK) LIMITED Defender:
________________ |
Pursuers: Howie, QC; Pinsent Masons
Defenders: Glennie, QC, Thomson; MacRoberts
10 May 2005
[1] The first defenders are a joint venture entered into between the second and third defenders. Prior to July 2001 they had undertaken responsibility under certain Private Finance Initiative arrangements for extensive refurbishment works at the Royal High School, Edinburgh. In that month the pursuers submitted a tender to the first defenders to carry out the works in question, and in August and September 2001 they submitted revised tenders. Thereafter the pursuers and the first defenders entered into negotiations with a view to concluding a formal contract for the refurbishment works. It was intended that the formal contract should be a lump sum contract with a contract sum of £7,836,569.97; the contract would, however, be subject to the familiar JCT Conditions, which of course provide for the adjustment of the contract sum to take account of variations and a range of other matters. It was necessary that the work on site should begin in mid October. Consequently, in October 2001 the pursuers and the first defenders entered into a contract of an essentially temporary nature in terms of which the pursuers were to start the refurbishment work at the High School. The terms of that contract are contained in a letter from the first defenders to the pursuers dated 12 October 2001; those terms were accepted by the pursuers by their starting work on the project in accordance with the first defenders' instructions.
[2] The first defenders' letter of 12 October 2001 begins by confirming that the first defenders intended to enter into a contract with the pursuers for the refurbishment, remodelling and construction works at the High School. Thereafter it dealt with a number of matters material to the negotiation of the formal contract, and then set out the terms on which the pursuers were to begin work prior to the conclusion of a formal contract. The material passage is as follows:"We would state that whilst it is our intention to enter into a contract with you for the entire Works at Royal High, that in view of the delays in reaching Financial Close, that we are obliged to limit the spending to a notional figure of £500,000, at this time and the authority of this letter is restricted to such. In the event that Financial Close cannot be reached, for whatever reason, then any losses incurred, including but not restricted to loss of profit, shall be related to the spending limit of £500,000 and not the entire Contract Sum.
The foregoing restriction upon spending and authority, shall be lifted as soon as we can obtain Financial Close and we trust you shall appreciate the temporary difficulty that forces this situation.
The Contract Sum applicable to the entire Contract Works shall be £7,836,569.97, as per the appended summary sheet.
We would request that you proceed with the Works forthwith upon the basis of this letter as your authority. Should a formal contract fail to be entered into for any reason other than the default or negligence of Robertson Construction, then all direct costs and directly incurred losses shall be underwritten and reimbursed by the Joint Venture. We would state that the Joint Venture Partners shall be held liable Jointly and Severally for the commitments incurred by the Joint Venture under this agreement".
The dispute between the parties centred on the construction of the last paragraph of the foregoing passage.
[3] The spending limit of £500,000 referred to in the first of the paragraphs quoted from the letter of 12 October 2001 was subsequently increased by the defenders; the last authorized increase, contained in a letter of 12 September 2002, brought the maximum sum up to £5,000,000. It was a matter of agreement that the contract whose terms are contained in the letter of 12 October 2001 was intended to operate as a "stop-gap" contract pending the conclusion of a formal contract between the parties, such formal contract to be based on an amended version of the JCT 98 Conditions. In fact, however, the parties never reached agreement on the terms of a formal contract. The pursuers proceeded to carry out works in accordance with the authority conferred by the letter of 12 October 2001, and interim payments for such work were made by the defenders to the pursuers. By October 2002 it became apparent that the parties would not be able to reach agreement on the terms of a formal contract. By that time the pursuers had reached the spending limit specified in the letter of 12 September 2002, and the pursuers' authority conferred by the letter of 12 October 2001 was accordingly terminated. Thereafter the pursuers raised the present action against the defenders in which they seek payment of the sum of £863,117.35. That sum is said to represent the amount that remains due by the defenders to the pursuers for the work carried out under the contract of 12 October 2001. The defenders dispute liability to pay that sum, and have themselves lodged a counterclaim in which they seek payment of sums totalling £441,937.36; those sums represent costs which the defenders claimed to have sustained as a result of late completion and defective performance of the works by the pursuers and the loss of certain items for whose storage the pursuers were responsible. After sundry procedure the parties prepared notes of argument and the parties were allowed a debate on the matters referred to in those notes.
[4] Most of the matters in dispute in the notes of argument related to the details and specification of the parties' respective claims. In the course of the debate, however, counsel agreed that certain items would have to be deleted from their claims and that greater specification was required in respect of certain other items. That will obviously require amendment, and counsel were in agreement that I should not consider the details of the pleadings before the amendment process was complete. Nevertheless, one important issue of principle remained in dispute between the parties, and counsel asked me to reach a decision on that issue before amendment took place, because my decision would affect the basis for such amendment. That issue was the meaning of the expression "all direct costs and directly incurred losses" as it is used in the last of the paragraphs quoted above in the letter of 12 October 2001.
[5] The defenders contended that the use of that expression restricted sums due to the pursuers to costs directly attributable to the High School contract. These would include the cost of labour, plant and materials used on the particular contract. On the other hand they would exclude costs attributable to the pursuers' enterprise considered as a whole; that would exclude head office overheads. The expression would also exclude any element of profit on the contract. If the pursuers were to make a profit in respect of works carried out at the High School, that could only occur under the formal contract that was contemplated by the parties. The pursuers, by contrast, contended that the expression "all direct costs and directly incurred losses" permitted them to recover not only the cost of labour and materials expended on the High School contract together with the cost of plant and sums paid to subcontractors but also an appropriate sum to cover their head office overheads and an appropriate element of profit.
[6] The expression "all direct costs and directly incurred losses" is not used in any of the standard forms of building contract. Nevertheless, it clearly bears some similarity to the well-known phrase "direct loss and/or expense" found in the JCT forms of contract. In each case the expression contains two elements, costs and losses in the present contract and loss and expense in the JCT forms. In my opinion these correspond to each other. The words "cost" and "expense" are regularly used as synonyms. Both denote sums expended or outlays; the idea is that the claimant is entitled to recover monies that he has been compelled to pay in consequence of an event with contractual significance. In my view the words "loss" and "losses" likewise correspond to each other. Their meaning is somewhat more complicated, however, and I discuss it in paragraph [9] below.[7] Both in the present contract and in the JCT forms, the two basic elements of cost and loss are qualified by the words "direct" or "directly". The significance of the word "direct" as used in the JCT forms of contract has been the subject of a number of judicial decisions, both in Scotland and in England. The result of these can be summarized in two propositions. First, the word "direct" in the expression "direct loss and/or expense" is concerned with remoteness of loss, not with causation. Secondly, the word denotes that the loss or expense in question must flow naturally from the contractual event relied on by the claimant, in the sense of the first rule in Hadley v Baxendale, (1854) 9 Ex 341. In Scotland both of those propositions were relied on in Ogilvie Builders Ltd v City of Glasgow District Council, 1995 SLT 15, a case involving the recoverability of finance charges by a contractor. In that case, Lord Abernethy followed the earlier decisions in England and Wales in FG Minter Ltd v Welsh Health Technical Services Organisation, (1980) 13 BLR 1, and Rees & Kirby Ltd v Swansea City Council, (1985) 30 BLR 1. On the basis of these cases, he held that the question that he had to decide was one involving measure or remoteness of damage rather than causation. While the word "direct" is frequently used in a causal sense, that is not its meaning in the context of the phrase "direct loss and/or expense". For loss or expense to be recoverable, it must obviously be caused by a contractually relevant matter (in the context of condition 26(1) of the JCT forms, one or more of certain matters materially affecting the regular progress of the works), but not all such loss or expense can be recovered. The only loss or expense that can be recovered is "direct" loss or expense. The word accordingly signifies something additional to and different from the mere existence of a causal connection: see 1995 SLT 21D-F.
[8] Lord Abernethy went on to review the case law following the decision in Hadley v Baxendale, and concluded
"In my opinion that picture that emerges from the authorities clearly demonstrates that for a long period of time both in Scotland as well as in England the words 'naturally', 'directly and naturally', 'naturally and directly' and 'directly' have been used interchangeably in this field of law to convey the same meaning. ... In my opinion therefore it is now well established, in Scotland as, it appears, in England also, that in the law of contract 'direct' loss or damage is loss or damage that flows naturally in the sense used in the first branch of the rule in Hadley v Baxendale. I am of opinion, therefore, that in the absence of any other meaning provided for by the parties' contract that is the meaning to be given to the word 'direct' in the phrase 'direct loss and/or expense' in cl 26(1)".
The first rule in Hadley v Baxendale refers, of course, to damages "arising naturally, i.e., according to the usual course of things, from such breach of contract itself". In my opinion that is the meaning that must be accorded to the words "direct" and "directly" in the parties' contract in the present case; I can find nothing in the agreement or in the surrounding circumstances to suggest that any other meaning was intended.
[9] Both the contract under consideration in the present case and the JCT forms use the word "loss" or "losses". The general significance of the word "loss" is that a person does not have something that he had or would otherwise have had but for an event with legal significance. In cases involving breach of contract the general principle is that the innocent party is entitled to be put in the same position as he would have been in if the contract had been performed; the difference between that position and the actual position in which the innocent party finds himself is accounted a loss. It is obvious that a loss of that nature may include a both loss of profit and a contribution to general overheads. The present case, of course, does not involve a breach of contract; it rather involves a specific contractual entitlement to remuneration. Nevertheless, it is of the nature of a contract that the party who supplies goods or services expects, or at least hopes, to make a profit. The intention to make a profit lies at the heart of all, or nearly all, commercial activity, and the law must recognize that elementary economic fact. I am accordingly of opinion that the failure of a contractor to make a profit should be accounted a "loss" not only in calculating damages for breach of contract but also in construing contractual terms relating to payment for goods and services. The same is true of earning a contribution to general corporate overheads; indeed, until such a contribution has been earned it probably cannot be said that any profit has been generated.[10] If the word "losses" did not cover general overheads and an element of profit, the pursuers would have to carry their corporate overheads from other sources of income, with no contribution from the works at the High School unless a formal contract were concluded. Likewise, the pursuers would have no possibility of profit from those works unless a formal contract were concluded. I do not think that a probable construction. Indeed, the head office overheads are likely to cover such matters as accounting and bookkeeping work carried out in respect of the present contract; they will also cover the salaries of draughtsmen and surveyors employed at head office who can be expected to perform work for the purposes of the present contract. Thus part of the general overheads will be referable to work carried out on the present contract. If the defenders' construction is correct, however, no contribution towards the cost of that work would be earned from the contract, unless the salaries of draughtsmen, surveyors, accounting staff and the like can be allocated on some sort of time basis. Such a procedure would be unusual, at least for accounting staff, and complicated. I do not believe that it would have been within the parties contemplation when work started following the letter of 12 October 2001.
[11] No doubt it can be said that the pursuers would have the hope of a profit from the formal contract if it were concluded. The contractual arrangements set out in the letter of 12 October 2001, however, only operate on the hypothesis that no formal contract is concluded. If a formal contract were concluded, it is obvious, I think, that the work already done would be subsumed into the formal contract. That is clear from the fact that the letter of 12 October 2001 refers to a specific contract sum applicable to the entire contract works. Consequently the possibility of a profit on the formal contract does not appear relevant on the hypothesis on which the arrangements in the letter of 12 October 2001 operate.
[12] It follows in my opinion that both costs, in the sense of expenditure, and losses, in the sense discussed in paragraph [9], are recoverable under the formula used in the parties' contract. In every case, the costs or losses must be such as arise naturally, in the usual course of things; that is the significance of the words "direct" and "directly incurred", interpreted in the manner suggested in paragraph [8]. That, however, raises the question of the event from which the costs or losses must arise. It seems clear in the present contract that the relevant event is an instruction from the defenders to the pursuers to carry out work at the High School. Actual items of expense incurred in carrying out such an instruction, such as tradesmen's wages, the hire of plant, the cost of materials, payments due to subcontractors and the costs of maintaining a site establishment will be recoverable as costs. In addition, on the construction that I have adopted, the pursuers will be entitled to a contribution towards their general corporate overheads, and also to an element of profit, based on the content of the relevant instruction. It seems to me to be quite natural to describe such items as arising naturally, in the usual course of things, from the instructions to carry out work. Moreover, if no recovery were permitted, the failure to earn a contribution to overheads and a profit would in my view properly be described as a "loss". The calculation of such a loss will normally be achieved by determining appropriate percentages to cover general overheads and profit, based on the actual costs of carrying out the instruction (that is, the costs of labour, plant, materials, subcontractors and site overheads). I do not think that there should be any great difficulty about determining an appropriate percentage. Quantity surveyors and estimators are well used to determining appropriate percentages for general overheads and profit, and if necessary expert evidence can be led as to what is an appropriate allowance. [13] The construction that I have adopted is I think supported by the decision of Judge Geoffrey Vos QC in Chiemgauer Membran und Zeltbau GmbH v The New Millennium Experience Company Ltd, 15 December 2000. That case involved a contract which gave the defendants, the employer, a right to terminate the employment of the plaintiffs, a specialist contractor. If they did so, however, they were obliged to make certain payments to the plaintiffs. These included "Any direct loss and/or damage caused to the Trade Contractor [the plaintiffs] by the determination". The defendants terminated the plaintiffs' employment, and the plaintiffs submitted a claim for inter alia loss of profit, on the basis that their loss of profit on the contract was "direct loss and/or damage". That claim was upheld. Judge Vos began (at paragraph 29) by considering the natural meaning of the words, and stated that he would expect them to include any loss of profit that the contractor would have made directly from the contract had it not been terminated. He then considered counsel's submissions, which made reference to Hadley v Baxendale and FG Minter Ltd v Welsh Health Technical Services Organisation, and concluded (at paragraph 36):"It seems to me that both the terms 'direct loss and/or damage' and 'direct loss' have clear and established meanings. Both terms refer to losses that are comprised in the first limb of the rule in Hadley v Baxendale, namely those which arise naturally and in the ordinary course of things. Subject to questions of mitigation... loss of profit does indeed arise naturally and in the ordinary course of things from the termination of the Contract in these circumstances".
Chiemgauer was of course concerned with the consequences of termination of the contract; consequently the loss could have amounted to the profit on the whole contract that would have been earned but for the termination. In the present case, by contrast, the loss of profit is much more limited, and is restricted to a reasonable percentage added to the cost of the works ordered by the defenders.
[14] Counsel for the defenders submitted that Chiemgauer should be distinguished because it was concerned with a termination that was to be treated, in terms of the parties' contract, as if it were a breach of contract. That could not be said of the present case. Consequently, if the decision in Chiemgauer were followed literally, the consequences would be that the pursuers were entitled to the whole of the profit that they would have made if the formal contract had gone ahead. That construction, counsel submitted, could not be correct. I agree that such a construction would be wrong. Nevertheless, I do not think that it is the correct construction of the present contract. As indicated in paragraph [11] above, I consider that the losses that can be claimed by the pursuers are those arising from the works instructed by the defenders in accordance with the letter of 12 October 2001. They do not include losses on the formal contract. Indeed, that would not be possible because the letter of 12 October 2001 operates on the hypothesis that no formal contract has been concluded; consequently no losses could arise under the formal contract.
[15] Counsel for the defenders further submitted that the pursuers' construction of the letter of 12 October 2001 was improbable because it gave the contractor a guaranteed profit. The parties' intention, however, was clearly that the works should ultimately be performed under a lump sum contract, which gives the contractor the possibility of making either a profit or a loss. If the formal contract had come into operation, that would undoubtedly be so. Nevertheless, the arrangements in the letter of 12 October 2001 only operate on the hypothesis that no such contract has been concluded. What they set up is in effect a cost plus contract. That form of contract is not unusual. No doubt it is true that such a contract will normally specify a fixed percentage that is to cover both general overheads and profit, whereas the letter of 12 October 2001 does not specify any such percentage. I do not think that that objection is fatal, however. What the present contract allows for is a reasonable percentage to cover general overheads and profit, and I do not think that there should be any insuperable difficulty in determining what is a reasonable percentage.
[16] Counsel for the defenders also argued that the arrangements in the letter of 12 October 2001 should be construed on the basis that they were a holding operation, pending the conclusion of a formal contract. The formal contract might fail to be concluded for a number of reasons, including financial flows under the PFI arrangements for the renovation of the High School. Moreover, the holding arrangements involved limits on authorised expenditure; initially £500,000 was authorized, but over the following year that sum was increased to £5,000,000. These features, it was said, presented a further distinction from Chiemgauer, and also indicated that the parties' intention was not to allow any general recovery of profit under the present contract but to reserve that for the formal contract. In my opinion the answer to these points is twofold. In relation to the holding or temporary nature of the arrangements in the letter of 12 October 2001, the critical point is that those arrangements only operate if no formal contract is concluded; if it is concluded the work done under the temporary arrangements will be subsumed into the formal contract. That is the significance of the lump sum price referred to in the letter. In relation to the expenditure limits that applied to the temporary arrangements, the purpose of these is in my opinion clearly to place limits on expenditure in order to achieve budgetary control. I do not think that the limits on expenditure have any wider significance. I also note that in the first paragraph of the passage from the letter quoted in paragraph [2] above it is stated that losses, including loss of profit, are to be related to the spending limit and not the entire contract sum. That confirms that any claim for losses is to be left within the operative expenditure limit.
[17] For the reasons stated above, I find that the expression "all direct costs and directly incurred losses" as used in the defenders' letter of 12 October 2001 permits the pursuers to recover reasonable sums by way of general corporate overheads and profit. Such overheads and profit must, however, arise naturally, in the usual course of things, from the works instructed by the defenders at the Royal High School under the temporary arrangements contemplated by that letter. I will have the case put out by order to allow further procedure to be discussed in the light of that finding.