OUTER HOUSE, COURT OF SESSION |
|
CA163/03
|
OPINION OF LORD EASSIE in the cause RITCHIE BROTHERS (PWC) LIMITED Pursuers; against DAVID PHILP (COMMERCIALS) LIMITED Defenders:
________________ |
Pursuers: S. Walker; Lindsays W.S.
Defenders: John S. MacKenzie, Solicitor-Advocate; Masons
14 April 2004
[1] In this action the pursuers seek to enforce a decision by an adjudicator to whom a dispute arising out of a construction contract between the parties was referred in terms of the Scheme for Construction Contracts (Scotland) Regulations 1998 (SI 1998/687) - "the Scheme". The defenders plead that the decision of the adjudicator is ultra vires and should be set aside ope exceptionis. [2] All the relevant facts have been agreed in a joint minute. The first head of the joint minute deals with the construction contract, which was concluded by exchange of letters in 2002. (The pursuers are the contractors: the defenders are the employer.) The remaining agreed facts relevant to the issues debated before me are as follows:(i) The pursuers sent the Referral Notice to the adjudicator under cover of the letter dated 18 September 2003 (No 7/2 of Process);
(ii) The letter dated 18 September 2003 (No 7/2 of Process) and undated Referral Notice was posted to the adjudicator on 18 September 2003;
(iii) The letter dated 18 September 2003 (No 7/2 of Process) was posted by Special Delivery reference SU068103839GB;
(iv) The Royal Mail attempted delivery of the letter dated 18 September 2003 (No 7/2 of Process) on Friday 19 September 2003;
(v) Monday 22 September 2003 was an Edinburgh Trades holiday.
(vi) The Referral Notice was collected by the adjudicator on Tuesday 23 September 2003 from Dalkeith Delivery Office;
(vii) On 21 October 2003 the representative of the defenders wrote to the adjudicator (No 7/4 of Process) challenging his jurisdiction;
(viii) The adjudicator by faxed letter dated 21 October 2003 (No 7/4 of Process) requested the pursuers' consent to postpone his decision until at least Thursday 23 October 2003.
(ix) The pursuers confirmed their consent by faxed letter dated 21 October 2003 (No 7/5 of Process);
(x) On 23 October 2003 the adjudicator wrote to the parties (No 7/6 of Process) requesting inter alia payment of his fee;
(xi) On 27 October 2003 the pursuers wrote to the adjudicator (No 7/7 of Process) inter alia indicating that they would pay the adjudicator's fees;
(xii) On 27 October 2003 the adjudicator delivered his decision and posted his reasons to the parties (No 7/8 of Process).
By way of clarification of head (x), it may be noted that in requesting payment of his fee the adjudicator informed parties that he had made his decision.
[3] Put very shortly, the ground upon which the defenders say that the decision was ultra vires the adjudicator is that the decision was, on their contention, reached after the expiry of the time stipulated in the Scheme for the adjudicator to reach a decision. In briefest summary, the pursuers for their part contend that the decision was not late; but even if it were late, that does not render the decision null. [4] Section 108(1) of the Housing Grants, Construction and Regeneration Act 1996 provides that a party to a construction contract "has the right to refer a dispute arising under the contract for adjudication under a procedure complying with this section". The construction contract negotiated by the parties to this action did not make provision for adjudication of disputes. Accordingly, by virtue of section 108(5) of the Act, the Scheme applied to the contract between the parties. The particular provisions of the Scheme bearing upon the issues arising in this litigation are respectively paragraphs 7 and 19 which are in these terms:"7.-(1) Where an adjudicator has been selected ... the referring party shall, not later that seven days from the date of the notice of adjudication, refer the dispute in writing ('the referral notice') to the adjudicator.
(2) A referral notice shall be accompanied by copies of, or relevant extracts from, the construction contract and such other documents as the referring party intends to rely upon.
(3) The referring party shall, at the same time as he sends to the adjudicator the documents referred to in sub-paragraphs (1) and (2), send copies of those documents to every other party to the dispute.
19.-(1) The adjudicator shall reach his decision not later than -
(a) twenty eight days after the date of the referral notice mentioned in paragraph 7(1);
(b) forty two days after the date of the referral notice if the referring party so consents; or
(c) such period exceeding twenty eight days after the referral notice as the parties to the dispute may, after the giving of that notice, agree.
(2) Where the adjudicator fails, for any reason, to reach his decision in accordance with sub-paragraph (1) -
(a) any of the parties to the dispute may serve a fresh notice under paragraph 1 and shall request an adjudicator to act in accordance with paragraphs 2 to 7; and
(b) if requested by the new adjudicator and insofar as it is reasonably practicable, the parties shall supply him with copies of all documents which they had made available to the previous adjudicator.
(3) As soon as possible after he has reached a decision, the adjudicator shall deliver a copy of that decision to each of the parties to the contract.".
"First, a distinction must be drawn between two types of court proceedings that may arise out of an adjudication. The first of these is judicial review of the adjudicator's decision. For this purpose, it seems appropriate in Scots law at least to treat an adjudicator as a species of arbiter; consequently the grounds of judicial review will be those that have long been familiar in relation to arbitrations. Essentially, these relate to the jurisdiction of the adjudicator, whether he has acted within the terms of the reference that has been made to him, and to misconduct on the part of the adjudicator. Judicial review is not possible, however, on the ground that the adjudicator has made an error of fact or law provided that his decision cannot be considered irrational. The second type of court proceedings that may arise out of an adjudication is an action to enforce an adjudicator's award. The nature of the latter type of action is described by Lord Macfadyen in Construction Centre Group Limited v Highland Council [2002 SLT 1274] in the following terms ... 'It is, in my view, important to appreciate the nature of this action. In it, the pursuers do not ask the court to endorse the correctness of the adjudicator's decision on the merits of the dispute referred to him. Rather the pursuers merely ask the court to recognise that the parties have bound themselves contractually to implement the adjudicator's decision. The pursuers seek decree from the court, not because they are in the right of the dispute, but because they are contractually entitled to require the defenders to implement the adjudicator's provisional determination of the dispute, whether it be right or wrong.".
Further reference was also made to paragraph [16] in which Lord Drummond Young said, inter alia, that in his opinion the decision of an adjudicator was in exactly the same position as a decree arbitral and in which he observed that the functions of an adjudicator were essentially similar to those of an arbiter.
[17] In his later decision in Costain v Strathclyde Builders Ltd Lord Drummond Young said, at paragraph [7] -"The issue between the parties in the present case turns on the principles according to which judicial control may be exercised over adjudicators in Scots law. For this purpose, I am of opinion that an adjudicator must be regarded as a type of arbiter. An adjudicator is an individual appointed by the parties to a contract to decide one or more disputes arising under that contract. His decision is binding on the parties by virtue of their agreement to that effect. Those are the essential features that characterise an arbiter. I am accordingly of opinion that the well-established rules that govern the judicial control of arbiters apply to adjudicators. Those rules include application of the principles of natural justice. ... Adjudication possesses a number of special features by comparison with the typical arbitration of modern times. But in my view these do not affect the basic rules that apply to judicial control in general ...".
"Adjudication has certain superficial similarities to arbitration; but in my opinion it is a sui generis system of dispute resolution. Whereas arbitration is a form of conclusive resolution of disputes, an adjudication is a form of provisional resolution only. Adjudication does not oust the jurisdiction of the courts or of an arbiter. Its primary purpose is to regulate a dispute ad interim, pending a definitive resolution of it by litigation, arbitration or agreement. The provisional nature of an adjudication is linked with the short time limits within which the process has to be concluded (Scheme, para 19). On that view, I consider that a Scottish adjudicator is not subject to the common law limitation on the powers of an arbiter.".
"While the failure of an adjudicator to produce a decision within the time limits is undoubtedly a serious matter, I cannot think that it is of sufficient significance to render the decision a nullity. The production of a decision two days outwith the time limit provided is not such a fundamental error or impropriety that it should vitiate the entire decision. Such a failure is a technical matter, and it is of significance in the present case that no challenge is offered to the merits of the adjudicator's decision. ..."
Counsel further referred to the judgment of HH Judge Richard Seymour QC, sitting in the Technology and Construction Court within the Queen's Bench Division of the High Court in England and Wales, in Simons Construction Limited v Aardvark Developments Limited [2003] EWHC 2474 (TCC). Reference was made in particular to paragraphs 26ff of the judgment in which His Honour considered whether a failure by an adjudicator timeously to produce a decision rendered the decision unenforceable. Counsel pointed out that in independently concluding that the failure did not have that consequence Judge Seymour also drew comfort from the result arrived at in the St Andrews Bay Development case, as respects that issue.
[21] Mr Walker also submitted that the provisional nature of an adjudicator's decision and the thinking behind the legislation meant that the court should in principle enforce adjudicators' awards. He referred to the judgment of Dyson J in Macob Civil Engineering Limited v Morrison Construction Limited [1999] BLR 93, particularly the passage at p 97 in which Dyson J dealt with an argument to the effect that where there is an adjudicator's decision whose validity is challenged the decision is not binding or enforceable as a contractual obligation until it had been determined or agreed that the decision is valid. The view expressed by Dyson J was that if that argument were correct it substantially undermined the effectiveness of the scheme for adjudication. Reference was also made to Watson Building Services Limited v Harrison 2002 SLT 846 in which, at paragraph [21]ff the Lord Ordinary (Lady Paton) set out quotations from a number of judgments in which the nature of adjudication as a means of providing a speedy temporary resolution of a dispute pending its final determination is emphasised. [22] The provisional nature of an adjudicator's decision is, in my view, important to bear in mind in deciding upon the extent to which the principles of the law of arbitration may be transferred to the adjudication process. Adjudication, unlike arbitration, does not deprive the parties - even pending the adjudication process - of access to the courts or to the conclusive determination of an arbitrator. As was clearly expressed by the Second Division in Gillies, adjudication is sui generis. The rules - particularly the technical rules - of arbitration do not automatically transfer to adjudication. It is of course possible and proper to apply the broad principles and limitations of the supervisory jurisdiction exercised by the Court of Session by way of judicial review to adjudication decisions (being the issues with which Lord Drummond Young was primarily concerned) but in my opinion ultimately one must construe the adjudication scheme itself. [23] When one turns to the provisions of the Scheme one finds that the Scheme itself envisages the event that an adjudicator may not, for whatever reason, be able to produce his decision within the stipulated time limits. Thus, sub-paragraph (3) of paragraph 19 enables either party to require the adjudication to start anew with a different adjudicator. Accordingly, where the adjudicator has not proceeded expeditiously to produce a decision, either party may effectively dismiss the adjudicator and substitute another. It appears to me that underlying this provision is the intention that, once initiated, the process of adjudication shall be carried through, even if, where there is a dilatory adjudicator, he requires to be replaced. In my view the implication of this must be that the essential proposition of the solicitor-advocate for the defenders to the effect that on expiry of the 28 day period the adjudicator's jurisdiction lapsed and he was therefore functus officio is misplaced. If correct, the proposition would entail that in such a situation the parties are obliged to go through the process of re-commencing the adjudication process with a different adjudicator - at additional expense and delay - even though the original adjudicator's decision became available within a day or so thereafter. Particularly in light of the nature and purpose of adjudication it would make little sense that the process of adjudication be re-commenced simply because a decision was late. In other words, I consider that on a proper view of the Scheme, the provisions relating to the times in which the adjudicator should reach his decision are directory, rather than mandatory provisions entailing nullity of any late decision. Delay by an adjudicator in producing his decision within those time limits does not bring the adjudication process to an end but enables it to be continued with a fresh adjudicator, should either party so wish. It does not mean that an adjudicator's decision, even if delivered late, is null and unenforceable for want of jurisdiction. [24] In reaching that view I derive support from the judgment in Simons Construction Ltd. The terms of paragraph 19 of the scheme for England and Wales [The Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649] are in similar terms to those of paragraph 19 of the Scheme. Judge Seymour observed, in paragraph 28 of his judgment, as respects paragraph 19 of the scheme for England and Wales that -"That paragraph envisages that, if an adjudicator fails to reach his decision within whatever is the relevant time period in the particular case, any of the parties to the dispute may serve a fresh referral notice and a new adjudicator could be appointed. It must be implicit in that provision that the first adjudicator ceases to have jurisdiction in the relation to the dispute upon the giving of a fresh referral notice, but also that until the giving of a fresh referral notice the original adjudicator retains jurisdiction to determine the dispute.".
I respectfully agree.
[25] For all these reasons I consider that the position adopted by the defenders is misplaced and that their defence to this action is irrelevant. There is no dispute as to the amount of the adjudicator's award or the apportionment of his fee, which reflect the sums sued for, and I shall therefore grant the motion by counsel for the pursuers for decree de plano.