OUTER HOUSE, COURT OF SESSION |
|
P1193/02
|
OPINION OF LADY PATON in the petition of
SKANSKA CONSTRUCTION UK LTD Petitioners; against (FIRST) THE ERDC GROUP LTD AND (SECOND) JOHN HUNTER Respondents:
________________ |
Petitioners: Bowen, Advocate; Anderson Strathern, W.S.
First Respondents: N.J. Davidson, Q.C.; MacRoberts
Second Respondent: No appearance
28 November 2002
Attempt to suspend a construction contract adjudication
Sub-contract
4.14: Interim and final payments.
4.17: Ascertainment of amounts due in interim payments (including 4.17.2.2: direct loss and expense).
4.23: Adjustment of sub-contract sum (including 4.23.1.1: ... not later than 6 months after practical completion of the Sub-Contract Works the Sub-Contractor shall send to the Contractor all documents necessary for the purpose of the adjustment of the Sub-Contract Sum; 4.23.1.2: ... not later than 3 months after receipt by the Contractor of [said] documents ... a statement of all adjustments to the Sub-Contract Sum to which clause 4.23.2 refers shall be prepared by the Contractor and the Contractor shall forthwith send a copy of the statement to the Sub-Contractor which shall be before the Contractor notifies final payment for the Sub-Contract Works; 4.23.2: The Sub-Contract Sum shall be adjusted ... as follows: ... there shall be added ... 4.23.2.8 any amount ascertained as a result of the application of clause 4.38 [direct loss and expense]).
4.38: Direct loss and expense (including 4.38.1.3: the Sub-contractor shall submit to the Contractor such details of such loss and/or expense as the Contractor requests in order reasonably to enable the ascertainment of that loss and/or expense to be agreed; 4.38.3: Any amount from time to time ascertained as a result of the operation of clause 4.38.1 shall be added to the Sub-Contract Sum or included in the computation of the Ascertained Final Sub-Contract Sum.).
8: Adjudication, including 8.3.2: an Adjudicator must resign where the dispute is the same or substantially the same as one which has previously been referred to Adjudication, and a decision has been taken in that Adjudication [a clause reflecting Regulation 9(2) of the Regulations set out in the Schedule to The Scheme for Construction Contracts (Scotland) Regulations 1998 S.I. 1998 No. 687].
First adjudication
8.9 Summary
8.02 |
Prolongation of Preliminaries |
£ 71,184.66 |
8.03 |
Disruption Expenditure |
£164,321.54 |
8.04 |
Additional Supervision |
£ 38,801.32 |
8.05 |
Head Office Overhead Recovery |
£ 53,026.42 |
8.06 |
Finance and Funding Expenditure |
£ 28,459.00 |
8.07 |
Loss of Opportunity |
£ 18,732.65 |
8.08 |
Claim Preparation Costs |
£ 14,975.00 |
Total |
£ 389,500.59 |
In their Referral Notice No. 6/6 of process, ERDC explain in paragraph 5:
"On comparison of the Referring Party's Interim Application for Payment No. 7 dated 6 September 2001, and the Responding Party's revised calculation dated 19 November 2001, it can be seen that there is no material difference between both parties' valuation of the measured works. The amount in dispute relates almost entirely to the Referring Party's entitlement to direct loss and expense. The Referring Party seeks direct loss and expense in the sum of £389,500.59 whereas to date the Responding Party has paid a total of £128,966.12 against what it categorises as an "extension of time claim" and "disruption". The Responding Party has failed to confirm the basis on which it has calculated this figure."
"I find that [Skanska] is not due to make payment to [ERDC] of the sum of £261,812.57 plus VAT thereon of £45,817.20, or any other sum."
Mr. Fiddes' reasons, No. 6/10 of process, made fairly frequent reference to "insufficient information", "insufficient specification", and "insufficient evidence": see for example paragraphs 2.02, 3.01, 3.02, and 7.00 of his reasons.
Second adjudication, in respect of which interim interdict and suspension sought
"The amount in dispute [£244,011.93 and VAT] relates almost entirely to the Referring Party's entitlement to Direct Loss and/or Expense. The Referring Party seeks Direct Loss and/or Expense in the sum of £372,978.05 whereas the Responding Party has only paid a total of £128,966.12 against extension of time and disruption."
SUMMARY
Prolongation of Preliminaries |
£ 71,184.66 |
Disruption Expenditure |
£196,242.69 |
Additional Supervision |
£ 38,801.32 |
Finance and Funding Expenditure |
£ 28,581.34 |
£334,810.01 |
|
Head Office Overhead Recovery 11.40% |
£ 38,168.34 |
Total |
£ 372,978.35 |
The Referral was made to the second respondent, Mr. Hunter, who accepted office as adjudicator.
Skanska's objection to second adjudication: dispute "the same or substantially the same" as first dispute previously referred to adjudication.
"Having considered the submissions from Anderson Strathern dated 17 and 25 September 2002 and the submission from MacRoberts dated 23 September 2002, I hereby find that I have jurisdiction to proceed.
The reasons for my findings are, in essence, as follows. I am satisfied that the first dispute related to an interim application for payment and I refer the parties to page 2 of the Notice of Intention to refer a dispute to adjudication, served by MacRoberts on 4 December 2001, which refers in paragraph 2 on page 2 to interim application for payment No. 7 and that said interim application represented the Referring Party's calculation of the amount to which it was entitled, at that time, in terms of the Contract between the parties [emphasis added by me].
The current dispute, in my view, relates to an adjustment of the Sub Contract Sum and I am satisfied that these matters are provided for in the Sub Contract Conditions by different clauses and my view is that there is authority for reaching this conclusion which supports [ERDC's] contention, in the cases of Holt Insulation Ltd v Colt International Ltd and Sherwood and Casson Ltd v MacKenzie.
I fully understand [Skanska's] position regarding the substantial overlap but I am satisfied that there is a difference between application No. 7, as an interim payment, and the current matter before me ...".
Skanska's petition for judicial review
Submissions on behalf of Skanska
Submissions on behalf of ERDC
Further submissions on behalf of Skanska
"There were further arguments on whether I could only look at the information made available to Skanska which allowed [them] to make their assessment. I decided that the adjudication clause in the contract between the parties gave me the power to request additional information..."
Counsel also confirmed that additional information had been supplied in response to Mr. Fiddes' requests, and that he had used that information when reaching his decision.
Reply on behalf of ERDC
"Any amount from time to time ascertained as a result of the operation of clause 4.38.1 (direct loss and expense) shall be added to the Sub-Contract Sum or included in the computation of the Ascertained Final Sub-Contract Sum."
Accordingly not all direct loss and expense had to be ascertained within the periods mentioned. Skanska had produced their "ascertainment" of ERDC's direct loss and expense in their final account on 21 March 2002. Their ascertainment was, on their own argument, late.
Opinion
Conclusion