OUTER HOUSE, COURT OF SESSION |
|
CA71/01
|
OPINION OF LORD MACFADYEN in the cause JOHN MOODIE & CO and OTHERS Pursuers; against COASTAL MARINE (BOATBUILDERS) LTD
Defenders: ________________ |
Pursuers: Stewart, Q.C.; Morton Fraser
Defenders: A.M. Clark; Henderson Boyd Jackson, W.S.
19 September 2002
Introduction
The pursuers' pleadings
Clause 12
"12 |
GUARANTEE |
||
12.1 |
During the period of 12 months after the Delivery Date, the Contractor [the defenders] shall be responsible for the rectification, at the Contractor's cost, of any defect, failure or breakdown of the Vessel and/or its equipment caused by faulty materials or workmanship supplied by the Contractor or any Sub-Contractor. |
||
12.2 |
The Contractor shall not be responsible for:- |
||
(a) |
damage caused by fair wear and tear, lack of maintenance, alteration or addition to the Vessel by the Purchaser [the pursuers] or negligent operation of the Vessel; or |
||
(b) |
faults arising from the construction design with the exception of items designed by the Contractor or any Sub-Contractor. |
||
12.3 |
The Purchaser will notify the Contractor in writing within 10 days after any defect, failure or breakdown has occurred. |
||
12.4 |
In the event of any dispute about whether a defect, failure or breakdown has occurred for which the Contractor is responsible under clause 12.1, the Vessel will be inspected by the SFIA [Sea Fish Industry Authority] whose decision on the dispute shall be binding on the parties. The parties shall have the right to be present at such inspection. All costs of such inspection shall be borne by the Contractor in the event that the SFIA |
||
decides that the defect, failure or breakdown is the Contractor's responsibility under clause 12.1. In all other cases, the said costs shall be borne by the Purchaser. |
|||
12.5 |
The Contractor shall have the right to carry out any rectification work required under clause 12.1 at the Shipyard [i.e. the defenders' shipyard in Eyemouth] or another shipyard nominated by the Contractor. The Contractor shall meet the cost of sailing or towing the Vessel to the Shipyard or such other shipyard including the cost of fuel, oil, crew and flights, where appropriate. If it is inconvenient for the Purchaser for the said work to be carried out at the Shipyard or at the other shipyard nominated by the Contractor and the cost of the said work is estimated not to exceed £20,000, the said work may, subject to prior notification of the cost being given to the Contractor, be carried out at a shipyard selected by the Purchaser. In that event, the Contractor shall pay for said work or, on demand, reimburse the Purchaser for the cost of said work. |
||
12.6 |
In the case of machinery not manufactured by the Contractor, the Contractor's guarantee under clause 12.1 will be extended or limited (as the case may be) to the equivalent of any guarantee which may be given by the manufacturer of that machinery except that the Contractor's guarantee as regards work in adapting or installing the machinery shall not be restricted in any way. The Contractor shall notify the Purchaser of the guarantee period relating to such machinery not manufactured by it at least 3 months prior to the Delivery Date, failing which the Contractor's guarantee under clause 12.1 shall apply. |
||
12.7 |
In no circumstances shall the Contractor be liable for any losses consequential on any breakdown or machinery failure including but not limited to loss of fishing." |
The parties' averments about Clause 12.7
"Accordingly, the defenders are not liable for the consequential losses claimed by the pursuers."
In Answer 8, they aver:
"In terms of clause 12.7 the defenders are not liable for any of the losses in relation to the failure of the engine/gearbox coupling."
In Answer 9, they make substantially the same averment in relation to "any of the losses consequential upon any failures allegedly caused by excessive vibration". Their fourth plea-in-law is in the following terms:
"The defenders not being liable for the losses claimed by the pursuers in terms of the contract between the parties, the defenders should be assoilzied."
"With reference to the defenders' averments in answer, clause 12.7 of the parties' contract is referred to, under explanation that that clause is not effective to exclude liability for the losses condescended upon, being directed only at restriction of the liability of the defenders under the express contractual warranties, and not restriction of their liability under the general law."
The defenders' submissions
"Whether a clause limiting liability is effective or not is a question of construction of that clause in the context of the contract as a whole. If it is to exclude liability for negligence, it must be most clearly and unambiguously expressed, and in such a contract as this [i.e. a standard form contract], must be construed contra proferentem. I do not think that there is any doubt so far. But I venture to add one further qualification, or at least clarification: one must not strive to create ambiguities by strained construction, as I think the appellants have striven to do. The relevant words must be given, if possible, their natural plain meaning. Clauses of limitation are not regarded by the courts with the same hostility as clauses of exclusion: this is because they must be related to other contractual terms, in particular to the risks to which the defending party may be exposed, the remuneration which he receives, and possibly also the opportunity of the other party to insure."
Lord Fraser of Tullybelton said (at 60-61):
"The question whether Securicor's liability has been limited falls to be answered by construing the terms of the contract in accordance with the ordinary principles applicable to contracts of this kind. The argument for limitation depends upon certain special conditions attached to the contract prepared on behalf of Securicor and put forward in their interest. There is no doubt that such conditions must be construed strictly against the proferens, in this case Securicor, and that in order to be effective they must be 'most clearly and unambiguously expressed' - see Pollock & Co v Macrae 1922 SC (HL) 192, 199 per Lord Dunedin. ...
There are later authorities which lay down very strict principles to be applied when considering the effect of clauses of exclusion or indemnity - see in particular ... Canada Steamship Lines Ltd v The King [1952] AC 192, 208 ... [and] Smith v UMB Chrysler (Scotland) Ltd 1978 SC (HL) 1. In my opinion these principles are not applicable in their full rigour when considering the effect of clauses merely limiting liability. Such clauses will of course be read contra proferentem and must be clearly expressed, but there is no reason why they should be judged by the specially exacting standards which are applied to exclusion and indemnity clauses. ... It is enough in the present case that the clause must be clear and unambiguous."
Further support for giving the language of a limitation clause its natural meaning and avoiding the discovery of ambiguity by a process of strained construction was to be found in George Mitchell (Chesterhall) Ltd v Finney Lock Seeds Ltd [1983] 2 AC 803, per Lord Bridge of Harwich at 813H-814A.
"70. Clause 17.5 in its standard unamended form was an orthodox defects liability clause ... Clauses of this kind do not limit or exclude liability. Typically they confer additional rights and obligations requiring the contractor or supplier to undertake additional work to rectify defects which appear within a defined time after completion without additional payment. They may be seen as benefiting both parties.
71. ... The amended clause was no longer only a defects liability clause. Whatever its precise meaning, it contained limitations of liability. It was not a clause which excluded all liability. It was to be construed in accordance with the principles which Lord Justice Evans has referred to... [His Lordship then quoted passages from the speeches of Lord Wilberforce and Lord Fraser in Ailsa Craig v Malvern.] ...
74. In my judgment, the meaning of cl. 17.5 is as follows. The first part of the first sentence obliged and entitled British Steel to remedy, at their own expense at the contracted point of delivery, defects in the Work due to faulty design, materials or workmanship which appeared within ... 18 months of the date stated in the Purchase Order. ... The words 'at which time all liability of the Supplier relating to the Work shall terminate' mean what they clearly say. 'All liability ... relating to the Work' embraces all liability arising out of the contract and its performance. It is true that the words appear in a sentence dealing with the supplier's obligation to remedy defects and that the next sentence deals with the same subject matter. But they are part of a clause whose evident purpose is to limit British Steel's liability within commercially acceptable bounds. The words themselves are not apt to limit only the liability imposed on British Steel by cl. 17.5 itself, which is limited in time anyway without them. Nor are these clear words to be tortured so as not to apply to exclude liabilities of British Steel which might be framed in negligence."
"The Contractor shall not be liable to the Sub-Contractor for any matter or thing arising out of or in connection with this Sub-Contract or the execution of the Sub-Contract Works unless the Sub-Contractor has made a written claim in respect thereof to the Contractor before the Engineer issues the Maintenance Certificate in respect of the Main Works, or, where under the Main Contract the Main Works are to be completed by sections the Maintenance Certificate in respect of the last of such sections in which the Sub-Contract Works are comprised."
The earlier provisions of Clause 15 regulated the procedure by which the sub-contractor was to be paid for his work under the sub-contract. The arbiter accepted the sub-contractor's argument that Clause 15(6) was not of general application, but was restricted by its context to claims for payment under Clause 15, and thus did not apply to the claims made in the arbitration. In reaching the opposite conclusion, the Court observed (at 255 and 256 in paragraphs [7] and [9] of the Opinion of the Court delivered by Lord President Rodger):
"The language of cl 15(6) is wide and, we must assume, deliberately so. The contractor is not to be liable 'for any matter or thing arising out of or in connection with' [emphasis added] the subcontract or the execution of the subcontract works. The use of the word 'any' coupled with the phrase 'in connection with' is designed to give the subclause a broad application. Indeed counsel for the claimants accepted that, were it not for its position at the end of cl 15, there would be nothing to suggest that the scope of the provision was limited in such a way as to make it inapplicable to the claims in the arbitration. He argued, however, that the subclause should not be read in isolation, but in its context in cl 15. So read, he said, it applied only to claims made by a subcontractor for payment under cl 15 and therefore not to the kinds of claim put forward here. ...
... The only question is whether the immediate context of the provision has the effect of narrowing its scope so that it covers only claims under that clause. Counsel for the claimants suggested that, if the provision had been intended to apply not merely to claims under cl 15 but more generally to all claims, then it would, more naturally, have been found as a separate clause. We see some force in the view that a separate clause might have been appropriate. But, inevitably, his argument amounts to saying that the same provision would have been of general application if it had been formulated as a separate clause, but is of only limited application because it occurs as a subclause in cl 15. While less generous words might indeed be cut down by their position within cl 15, we are unable to hold that the context has the effect of limiting cl 15(6), worded as it is, to claims under cl 15(1). Had the draftsman of the contract form intended to limit the subclause in this way, we should have expected it to refer back specifically to cl 15(1)."
The pursuers' submissions
"Explained and averred that the engine, its gearbox coupling and the said bolts were not designed by the defenders. The defenders installed the engine/gearbox coupling entirely in accordance with the engine manufacturer's specification. The defenders were under no obligation, when installing the engine, to check the length of the hole in the flywheel."
The exclusion of responsibility for design faults contained in Clause 12.2(b) did not, however, extend to items designed by "any Sub-Contractor". The engine manufacturer was a subcontractor within the meaning of that expression as defined in Clause 1.1. Those averments should therefore be excluded from probation.
"Clauses in similar terms are common in contracts for the construction of fishing vessels. The Terms and Conditions for Construction of a Fishing Vessel as adopted by the British Boatbuilders Association exclude liability for consequential loss."
Those averments, Mr Stewart submitted, had no bearing on the issue of the proper construction of Clause 12.7, and should therefore be excluded from probation.
Discussion
"In no circumstances shall the Contractor be liable for any losses consequential on any breakdown or machinery failure including but not limited to loss of fishing", (emphasis added).
It seems to me that the plain meaning of the words of that clause is that it excludes liability on the defenders' part for losses of the type to which it refers, irrespective of the circumstances in which, or the ground on which, a claim may be advanced against them for recovery of such losses. The words "In no circumstances" and "any losses" emphasise the generality of the provision. There is nothing in the language of the clause which compels the reader to look elsewhere for assistance in understanding its meaning. It is not a provision that can only be given an understandable meaning by reference to its context.
Result
[42] For the reasons which I have explained above, I shall therefore -