John Mowlem & Company Plc v. Akeler [2002] ScotCS 150 (28th May, 2002)
EXTRA DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord President Lord Kirkwood Lady Cosgrove
|
XA63/01 OPINION OF THE COURT delivered by LORD KIRKWOOD in STATED CASE in ARBITRATION between JOHN MOWLEM & COMPANY PLC Appellant and Claimant; and AKELER (SCOTLAND) LIMITED Respondents: _______ |
Act: Currie, Q.C.; Masons, Solicitors, (Appellant and Claimant in the Arbitration)
Alt: Moynihan, Q.C.; Simpson & Marwick, W.S., (Respondents)
28 May 2002.
"any conflict or ambiguity between this Agreement (including the Conditions but excepting the Contract Particulars) on the one part and the Contract Particulars on the other part then the provisions of this Agreement as hereinbefore referred to in this Clause 5 and the annexed Conditions shall prevail."
"(2) The Contractor warrants to the Employer that the Gross Internal Area of the Units and the constituent parts thereof when constructed will not be less than the areas shown in the Schedule of Areas attached to the annexed Preliminaries and the Units shall have available for use the number of car parking spaces set out in such Schedule of Areas. The Gross Internal Area will be measured in accordance with the Code of Measuring Practice of the Royal Institution of Chartered Surveyors and the Incorporated Society of Valuers and Auctioneers dated November 1993 (Fourth Edition). Such measurement shall be effected in accordance with sub-condition (3) but the Employer's Representative shall carry out such preliminary measurements from time to time as may be reasonably requested by the Contractor (such preliminary measurements to be without prejudice to the final measurement to be effected pursuant to sub-condition (3))."
Condition 2(3)(a) provides inter alia as follows:
"(3)(a) The Contractor shall as soon as possible give written notice to the Employer and the Employer's Representative that the Phase A Works have reached such a state of readiness as to enable the Gross Internal Area of the Units and their constituent parts to be measured...".
SCHEDULE OF AREAS
PHASE A |
PHASE B |
||||
Unit |
Gross Internal Floor Area |
Number of car parking spaces |
Number of car parking spaces |
||
A |
34,100 sq ft |
8 |
62 |
||
C |
27,9000 sq ft |
8 |
52 |
"(2) If the Contractor fails to ensure that:-
each of the Units provides in aggregate the following Gross Internal Areas and the following number of car parking spaces:-
Unit A 34,100 sq ft and 8 car parking spaces in the Phase A
Works and 62 car parking spaces in the Phase B Works
Unit C 27,900 sq ft and 8 car parking spaces in the Phase A
Works and 52 car parking spaces in the Phase B Works
then the Contractor will pay or allow to the Employer liquidated and ascertained damages at the rate specified in Appendix 1 hereto for each square foot by which the amount built is below the Gross Internal Area so specified such payment to be made within five(5) working days of demand after the measurement has been agreed or determined pursuant to Condition 2(3) and the Employer may deduct such sum from any monies due or to become due to the Contractor under these conditions or the Employer may recover the same from the Contractor as a debt."