EXTRA DIVISION, INNER HOUSE, COURT OF SESSION |
|
Lord Cameron of Lochbroom Lord Johnston Lord Dawson
|
P111/01 OPINION OF THE COURT delivered by LORD JOHNSTON in RECLAIMING MOTION in the cause ROBBIE THE PICT Petitioner; against MILLER CIVIL ENGINEERING LIMITED and OTHERS Respondents: _______ |
Act: Party
Alt: Reid, Q.C.; Shepherd & Wedderburn, W.S. (First and Third Respondent): Menzies, Q.C., R. Henderson (Scottish Ministers)
8 August 2001
[1] This is an appeal at the instance of the petitioner against the refusal of the Lord Ordinary to grant interdict against the respondents and their servants and agents, or anyone on their behalf, from demanding any toll from the petitioner in respect of the Skye Bridge between Kyle of Lochalsh and Kyleakin in Inverness-shire ("the crossing") with certain ancillary demands. The Lord Ordinary rejected the claim essentially on matters of substance and principle.
[2] In the Outer House the main argument submitted by the petitioner related to whether or not the authority given to persons collecting the toll so to do had been consented to by the then Secretary of State in relation to his power to grant assignations to persons other than himself to collect tolls, whether in writing or not. In his initial submissions to us the petitioner did not refer to that question to any material extent but rather raised separate questions which he elaborated in his reply to the respondents' submissions. In his final submissions counsel to the first respondents pointed out that the indulgence that the court had granted the petitioner as a party went far beyond what would be normally permissible in an appeal relating to specific grounds of appeal and the Lord Ordinary's opinion. Be that as it may, we will, however, deal with each of the matters that were submitted to us by the petitioner.
[3] Before doing so it is necessary to examine the legislative framework in some detail. Part II of the New Roads and Street Works Act 1991 ("the 1991 Act") introduced statutory powers whereby the Secretary of State or a local roads authority providing a new "special road" might be authorised to charge tolls by virtue of a "Toll Order". The Crossing is part of a "special road" provided by the Secretary of State. Section 27(2) of the 1991 Act provides that a Toll Order relating to a special road to be provided by the Secretary of State shall be made by the Secretary of State. Sub-section (3) provides that the making of such a Toll Order is subject to certain procedural requirements including those in Part IIA of Schedule 1 to the Road (Scotland) 1984 ("the 1984 Act"). Sub-section (4) of Section 27 states that, so far as practicable, the proceedings required by Part IIA of Schedule 1 to the 1984 Act shall be taken concurrently with the other statutory procedures for the making of a special road scheme. Sub-section (5) provides that the Secretary of State shall not make or confirm the scheme or the Toll Order unless he makes or confirms them both. Part IIA of Schedule 1 to the 1984 Act was inserted by Paragraph 96 of Schedule 8 to the 1991 Act, read along with Section 168(1) of the latter Act. It makes provision for advertisement of a proposal to make a Toll Order; for facilities for the public to inspect the draft Toll Order; and for interested parties to give notice to the Secretary of State of objections to the proposed Toll Order. Part IIA of the 1984 Act includes Paragraph 14A(3) which is in these terms:
"Where it is intended that the proposed Toll Order shall authorise the special road authority to assign their rights to charge and collect tolls, the Secretary of State or, as the case may be, the local road authority shall make a statement containing such information as may be prescribed with respect to that assignation and the person to whom the rights are intended to be assigned, and:-
(a) the statement shall be made available for inspection with the copy of
the Order to which the Notice under sub-paragraph (1) (i.e. the Notice advertising the proposal to make a Toll Order relates); and
(b) the Notice shall state that such a statement will be so available."
The terms of sub-paragraph (3) of Paragraph 14A of Schedule 1 to the 1984 Act evidently stem from the provisions of Section 28 of the 1991 Act, which include the following:-
"(1) A Toll Order may authorise the special road authority in whose name it
is made to assign, subject to subsection (2), to a person, for such period and subject to such terms and conditions as they think fit, their rights under a Toll Order to charge and collect tolls.
(2) A special road authority may grant such an assignation only to a person
who has undertaken such obligations as may be specified in the assignation with respect to the design, construction, maintenance, operation or improvement of the road.
(3) In this Part, a person to whom the rights under a Toll Order to charge
and to collect tolls have been assigned is referred to as a Concessionaire.
(4) References in this Part to a person authorised to charge tolls include
references to a Concessionaire.'
Section 35(1) of the 1991 Act further provides that:-
'The rights of a Concessionaire under an assignation granted under Section 28(1) may, with the consent of the special road authority, be assigned by the Concessionaire."
Section 37 of the 1991 Act provides thus:-
"(1) The Secretary of State may make provision by regulations with respect
to the collection of tolls in pursuance of a Toll Order.
(2) Different provision may be made for different types of road or
different types of tolls, or for particular roads or particular tolls.
(3) Regulations may, in particular, impose requirements with respect to:-
(a) the displaying of lists of tolls; and
(b) the manner of implementing changes in the amount of tolls;
and where any such requirements are imposed, a toll may not be demanded unless they are, or as the case may have been, complied with.
(4) A person who, in respect of the use of a road to which a Toll Order
relates, demands a toll:-
(a) which he is not authorised to charge; or
(b) which by virtue of subsection (3) may not be demanded;
commits an offence and is liable, on a summary conviction, to a fine not exceeding level 3 on the standard scale."
[4] In pursuance of the power given to him under Paragraph 14A(4) of Schedule to the 1984 Act, the Secretary of State on 26th September 1991 made The Assignation Statement (Prescribed Information)(Scotland) Regulations 1991 (S.I. 1991/2152) which came into force on 21st October 1991, being the date on which Sections 27 to 41 of the 1991 Act also entered into force. In Regulation 2, the expressions "Assignation Statement" and "Concessionaire" are duly defined in terms relating them to the statement and the proposed assignee referred to in Paragraph 14A(3) of Schedule 1 to the 1984 Act. Regulation 3 is in the following terms:-
"3. An Assignation Statement shall contain the following information:-
(a) the identity of the Concessionaire;
(b) where the Concessionaire is a company with issued share
capital, the identity of each member of the company who is the registered owner of at least ten per cent of the issued share capital at the time the Assignation Statement is made available for inspection under Paragraph 14A(3) of Part IIA of Schedule 1 to the 1984 Act;
(c) the proposed length of the concession period and any provision
to be incorporated in the Assignation for early termination of the concession period;
(d) a summary of any obligations to be undertaken by the
Concessionaire during the concession period in relation to the maintenance, operation , or improvement of the toll road;
(e) a summary of any obligations undertaken by the
Concessionaire in return for the rights to charge and to collect tolls in relation to:-
(i) the steps to be taken to minimise the risk of adverse
environmental effects arising out of the construction or operation of the toll road;
(ii) the provision of service stations or other buildings or
facilities to be used in connection with the toll road and any special requirements for services to be offered by such stations or other buildings or facilities;
(f) a summary of any undertakings to be given by the
Concessionaire with regard to the stopping up, diversion, improvement, or any other alteration of any road which will cross or enter the route of the toll road, or will be otherwise affected by the construction or improvement of the toll road, and with regard to the construction of any new road for purposes connected with any such alterations as aforesaid."
[5] In addition there is one other legislative provision which is of importance to be found in Schedule 2 to the 1984 Act which contains four paragraphs relating to action that can be taken by a person aggrieved by the relevant Scheme or Order as the case may be. The important paragraph is 4 which is in the following terms:
"...(an)...Order to which this Schedule applies shall not either before or after it has been made or confirmed be questioned in any legal proceedings whatever and shall become operative on the date on which the notice required by paragraph 1 is first published or on such later date if any as may be specified in the Scheme or Order".
[6] As the Lord Ordinary records the Secretary of State initiated procedures which resulted, in due course, on 26 June 1992 in the Special Road Scheme Order (S.I. 992/1499) and the Toll Order (S.I. 1992/1501) necessary to enable the construction of the bridge to proceed. These Orders were made following a public inquiry
[7] Article 3 of the Toll Order provides:
"3. The Secretary of State as special road authority is hereby authorised:-
(a) subject to Article 4, to charge tolls in respect of the Crossing in
relation to tolled traffic using the Crossing during the toll period; and
(b) subject to Section 28(2) of the Act, to assign his rights to
charge and to collect tolls to a person for such period and subject to such terms and conditions as the Secretary of State thinks fit."
[8] During the course of the procedures leading up to the making of the Toll Order the Secretary of State provided an assignation statement as required by the legislation which statement no. is 7/4 of Process.
[9] On 1 November 1991 notices appeared in the press which gave general notice of the decision of the Secretary of State to charge tolls in respect of the bridge. They also gave notice that the Secretary of State had made a statement with respect to (a) the assignation of the rights to charge and collect tolls and (b) the persons to whom the rights were to be assigned. At the same time information was given as to where both the draft Order and the statement could be examined by any person claiming interest to do so. Further information was given as regards notice of objection to the making of the Order.
[10] The contractual arrangements relating to the construction of the bridge were complicated but the main documents were as follows:
"(a) the 'Concession Agreement' entered into between the Secretary of
State and Skye Bridge Limited (No. 6/7 of Process);
(b) the Operation and Maintenance Agreement ('OMA') between Skye
Bridge and MDJV relating to the operation and maintenance of the Crossing (No. 7/1 of Process); and
(c) a Memorandum executed by all three Respondents and also by The
Miller Group Limited, Dyckerhoff & Wedmann AG, and MDJV (No. 7/2 of Process)."
[11] Against that background the submissions of the petitioner fall to be considered with regard to (1) the issue of consent; (2) the validity of the statement with regard to its form and content and (3) whether it had been properly published in terms of the legislation. Before dealing with each of those issues it has to be noted that the petitioner also raised a separate issue relating to the way in which the tolls being collected was accurately accounted for in terms of the provisions of the proposed Scheme, particularly in relation to the extent to which the backing bankers were taking their share. We do not propose to deal with this issue in any form since it was not shadowed in the pleadings nor in submissions before the Lord Ordinary, nor has any fair notice been given to the respondents that such a point would be taken. In any event, if it has any general bearing on matters at all, it is not a matter for this court. This is a further reason why it should not be considered at this stage of this process.
[12] We can also deal shortly with the issue of consent since, as we have indicated, it was only briefly dwelt upon before us. It is to be noted that the Lord Ordinary decided the question debated before him on an assumption that there had been no written consent by the then Secretary of State to any purported assignation from the original concessionaire to the persons actually collecting the tolls. However, at the end of his opinion he did, on an obiter basis, express the view that in fact no such consent had been given.
[13] The argument before the Lord Ordinary effectively depended upon an interpretation of the OMA which, given that its existence and provisions lay within the knowledge of the Secretary of State, could be sufficient to amount to an acceptance by him that he was agreeable to the involvement of the persons actually involved in the operation and maintenance of the crossing and the collection of the tolls.
[14] There is a long history of litigation in relation to this whole matter. Included in that history is the decision in Alexander Smith and Others v. P.F. Dingwall unreported 16 December 1999, a decision of the High Court of Justiciary in relation to prosecutions against the appellants for not paying the tolls, the opinion being issued by Lord Sutherland. His Lordship dealt with this argument, which was presented to him by the current petitioner as an appellant in that case. His Lordship, having considered the contractual position between the parties which we have already set out above, expressed the opinion that it did not constitute any form of assignation as between the concessionaire and the persons collecting the toll but merely pointed to the existence of an agency agreement in practice. The argument presented before us did not extend beyond the submission presented before the High Court of Justiciary. Nothing said to us persuades us that Lord Sutherland's opinion was in any way ill-founded in his conclusion that the issue of written consent did not arise. We agree entirely with Lord Sutherland and we would simply gratefully adopt his Lordship's reasoning in that part of the opinion where his Lordship dealt with the issue of written consent did not arise.
[15] We therefore turn to deal with the issues that were focused by the petitioner and reclaimer before us.
[16] The reclaimer's principal attack on the validity of the assignation statement was based on the fact that it was not a probative document and was not dated nor was it signed by the Secretary of State. Furthermore, it contained inaccuracies as a matter of fact, not least referring to a different name in respect of the purported assignee. Since, at the end of the day, on the face of it, a person different to that named in the original statement was apparently collecting the tolls the whole process was invalid, it was submitted, because the assignation statement should have been at least updated. He went so far as to suggest that as a consequence a criminal offence was being committed.
[17] Leaving aside the fact that this proposition appeared to be based upon the argument that the right to collect tolls had to be assigned to the collecting company with the written consent of the Secretary of State, which we have already rejected, it fails on a separate ground. It was accepted that the reclaimer in terms of the second Schedule to the 1984 Act, has not timeously made any attempt to attack the validity of the Order or the procedural requirements adopted in relation to the Order in the manner prescribed by that Schedule. It follows that paragraph 4 of the Schedule, upon which counsel for the respondents relied, effectively acts as an ouster clause to deny jurisdiction to this court now to consider any questions of validity of the Scheme, the relevant time limit having long since expired. The general effect of such a clause was considered by Lord Cameron of Lochbroom in Pollock v. Secretary of State for Scotland 1993 S.L.T. 1173 where, after a careful examination of the relevant authorities, his Lordship concluded inter alia that in the absence of bad faith the statutory time limit for an aggrieved person contesting the validity of a Scheme or Order in relevant circumstances did not oust but did limit the jurisdiction of the court, the provision clearly intending to bar any challenge from whatever source it might come after the expiry of the time limit.
[18] We entirely endorse that approach which completely disposes of the substance of the issues raised by the reclaimer in this respect.
[19] However, for the sake of completeness we note that this point was also considered in Smith supra and on page 12 of his opinion Lord Sutherland, inter alia says:
"The definition of concessionaire in Regulation 2 is that it means the person to whom the rights to charge and collect tolls under a Toll Order are intended to be assigned. The information required to be contained in the assignation statement is set out in Regulation 3 and provides inter alia that what has to be contained therein is the identity of the concessionaire, the proposed length of the concession period and the summary of the obligations to be undertaken by the concessionaire. There is an element of futurity in all these matters and thus this, in my view, is a clear indication that the intention of the Regulations was that the assignation statement should precede any concluded contract with the concessionaire. As no Toll Order would be likely to be made until contractual arrangements with the concessionaire were completed it follows that the assignation statement must precede the making of the Toll Order. This confirms the view that the assignation statement should be made public along with the draft proposed Toll Order. There is no statutory provision for any production of an update of the assignation statement in the event of there being a change of circumstance being the issuing of that statement and the ultimate making of the Toll Order. Accordingly, the fact that there may be variations to the position as between the date of the assignation statement and the date of the making of the Toll Order is not something which requires publication and in any event cannot affect the validity of the assignation statement at the time when it was made."
[20] There is nothing we can usefully add to that analysis and it therefore follows that even if paragraph 4 of Schedule 2 to the 1984 Act did not defeat the reclaimer's position or if in some way he was able to get round it, his argument is of no substance.
[21] We would just add that, as regards the so-called change of apparent concessionaire it is clear the change is one of in name only which can be clarified by reference to the Register of Companies. We observe that in the Schedule for Service appended to the present petition the second respondents are designed as having been formerly Skye Bridge Tolls Limited.
[22] That leaves only the issue of publication. Here the submission was that what was done by way of advertisement, to which we made reference, was insufficient and there should have been a proper statutory instrument procedure whereby the documents in question were printed and laid before Parliament being statutory instruments.
[23] We can deal with this matter very shortly. It is quite clear that what is essential is the preparation and publication in the normal sense of the word of the assignation statement together with the draft Order and intimation to the public as to where they may be inspected. That plainly was done. That, in our opinion, is the end of the matter since we do not consider that the procedures that apply to the publication of statutory instruments proper apply in this context at this stage of the process. In any event, we consider that the width of paragraph 4 of Schedule 2 to the 1984 Act is such that this is again properly to be categorised as a challenge to the validity of the Scheme or at least the statement and this again cannot now be made at this stage of the process, being well beyond the statutory time limit.
[24] In these circumstances we are of the opinion that there is no merit in any of the points presented to us by the reclaimer whether within or without the scope of the original reclaiming motion. Accordingly, the appeal will be refused.