Page: 217↓
[Sheriff Court at Duns.
A builder brought an action against the proprietor of a mansion-house for the balance of the amount averred to be due to him under contract for mason-work in connection with alterations and additions to the mansion-house. The proprietor refused to pay the sum sued for except under deduction of, inter alia, a sum limited to £150, which he alleged was due to him under the contract as penalty for delay in the execution of the work.
By the terms of the contract the pursuer undertook to have the whole work “entirely completed” by 1st May 1897 under “a penalty of 10s. per day that the mason-work remained unfinished beyond that date.” Further, by the contract the defender had reserved to him power “to make any alterations on and to increase, lessen, or omit any portion of the works,” while it was provided that extra work, if any, should form no ground for deviating from the dates above fixed for the completion of the work unless specially certified by the architect at the time.
Proof was led, which showed (1) that the mason-work was not completed till July 1898; (2) that extra work was ordered by the defender during the progress of the operations, and that some of this extra work was ordered after 1st May 1897; (3) that during the whole progress of the operations the architect repeatedly remonstrated with the pursuer for delay, caused by the latter not putting a sufficient working staff on the job, without any excuse being offered by the pursuer; and (4) that no application was made at any time by the pursuer to the architect for a certificate that the extra work formed a ground for delay. The proof did not show clearly what extent of the work was completed by 1st May 1897, what extras were ordered after that date, how far extras ordered before that date hindered the completion of the work at that date, or how much time was occupied after that date by the execution of extras.
Held ( dub. Lord Young) that the fact that some of the extra work had
Page: 218↓
been ordered after 1st May 1897 did not of itself prevent the enforcement of the penalty clause, that the onus was upon the pursuer to show that the extra work ordered by the defender had been the cause of the delay in completing the work, that the pursuer had failed to discharge this onus, and that the defender was therefore entitled to deduct from the amount claimed by the pursuer £150 as penalty for delay in terms of the contract.
In the beginning of 1896 Robert Fitzroy Bell resolved to make additions and alterations to his mansion-house of Temple Hall. The architect for the work was James Jerdan, Edinburgh. Henry Steel, builder, Greenlaw, contracted to execute the mason-work in connection with the building. His original estimate was £2240, but owing to certain portions of the work not being definitely decided upon by Mr Bell at the time, though specified in the schedule, the amended estimate amounted to £1491, 5s. l0d. During the progress of the work alterations on and additions to the original plans were made and carried out, so that the gross amount admittedly due to the pursuer for work actually done was about £2500.
The general conditions and regulations signed by Mr Steel on 13th May 1896, as relative to the contract, contained the following clauses:—“5. No deviation shall be made from the drawings, specifications, and schedule of measurements signed with reference to the contract unless by instructions and drawings from the architect, but in case of such instructions or drawings being given, the contractor must immediately follow them, and such instructions shall in no degree vitiate or invalidate the contract.… (14) The work shall be commenced so soon as the contractor shall receive possession of the site or sites for same, and the contractor shall be allowed from the time of receiving possession, one week for the delivery and arrangement of his plant and materials, and at or upon the expiration of said period of one week the said works shall be commenced and carried on with all due diligence and in regular progression so that the following portions of the work may be completed at or before each of the following dates, viz., that the principal wing, namely that part of house fronting eastwards, have the walls made ready for the roof by the first of October next, and the remaining part of the building, viz. that part of the mansion facing northward, be made ready for the roof by the first January next, and the whole shall be entirely completed at or before the first day of May 1897, failing of which a penalty of 10s. per day that the mason-work remain unfinished beyond that date. Extra work, if any, shall form no ground for deviating from the dates above fixed for the completion of the respective portions of the work unless specially certified by the architect at the time. (15) The architect shall have power to delay or suspend the work during unsuitable weather, or for any other sufficient reason, but the works shall be recommenced after receiving due notice from the architect. The time lost by such delay shall be added to the time allowed for completion.… (21) The contractor must distinctly understand that in case any detail or other drawing, sketch, written or verbal instruction, be given for any part of the works whatever, and it be found that the proceeding with the works in accordance with such detail or other drawing, sketch, written or verbal instructions shall cause any additional expense, whether in the particular trade to which the said detail or other drawing more particularly relates, or cause extra work in other trades, then the contractor must immediately intimate the same to the architect and state what extra expense according to schedule rates is, in his opinion, involved by proceeding with such works. The contractor must not execute any extra work of any kind whatsoever unless upon the written authority of the architect, or any plan or drawing expressly given or signed by him as an extra. 22. The contractor shall, for any extra work which cannot from its character be properly measured and priced, render to the architect a weekly statement of such. No payment for day-work will be allowed unless supported by such vouchers.… 27. Power is reserved to make any alterations on, and to increase, lessen, or omit any portion of the works as may be thought fit, and the value of such alterations, additions, or deductions is to be calculated in strict accordance with the rates in the schedule of measurement signed as relative to the contract, and upon which the original tender is based. Any extras to which the schedule rates cannot be applied will be valued by the architect at current market prices for such work.”
From time to time during the progress of the work Mr Steel received payments to account, amounting in all to £2310. In November 1899 he raised an action in the Sheriff Court at Duns against Mr Bell for £348, 9s. 3d., the balance which he alleged to be due to him.
The defender admitted certain items in the pursuer's claim and denied liability for others. He averred that the pursuer had been very dilatory in carrying out his contract, that instead of. being finished with the work by 1st May 1897 it was between one and two years after that date before he had completed the work; that the pursuer was therefore liable in a penalty under the contract, and that although the defender was justly entitled to claim for a much longer period he was willing to restrict the penalty to £150, being as for a period of 300 days.
The defender pleaded, inter alia—“(5) The pursuer having failed to complete his contract within the specified time he is liable to the defender in the penalty provided therefor by the contract, and the sum claimed by the defender in respect thereof being well within the amount so due, the defender is entitled to take credit for the same in the settlement with the pursuer.”
Page: 219↓
The pursuer explained that the delay in completing the work was caused by repeated alterations made on the plans by the defender, by inclemency of the weather, and by damage caused by storms.
Proof was led before the Sheriff-Substitute ( Dundas) and disclosed the following facts—(1) The mason-work was not completed till July 1898, fourteen months after 1st May 1897, the date fixed in the contract. (2) A large quantity of extra work, both in the way of alterations and additions, was ordered by the defender during the progress of the building, and some of this extra work was ordered after 1st May 1897. (3) Strong remonstrances, beginning ten days after the pursuer got possession of the ground, and continuing during the course of the work, had been made, both verbally and in writing, by the architect, for delay caused by the pursuer not putting a sufficient working staff on the job, and no reply was shown to have been made or excuse offered, even when after 1st May 1897 it was pointed out to him that the penalty days were running. (4) No application was made at any time by the pursuer to the architect for a certificate under clause 14 of the general conditions and regulations, signed as relative to the contract, to the effect that the extra work had caused delay. The proof did not show clearly what extent of the contract work was completed by 1st May 1897; what orders for alterations on or additions to the work as set forth in the specification were given after that date; how far alterations or additions ordered before 1st May 1897 hindered the pursuer from completing his contract work before that date, and how much time after 1st May 1897 was occupied with additions or alterations on the specified work.
On 16th March 1900 the Sheriff-Substitute pronounced an interlocutor disposing of the items of the pursuer's claim, partly in his favour and partly against him, and finding that from the sum due him there fell to be deducted, inter alia, “a sum of £150 in name of penalty for breach of contract.”
Note.—“This has been a most troublesome case, partly owing to its great bulk, but chiefly to the fact that the parties are not yet in a position to close their accounts. Their rights interse are defined by contract, and it is to the contract that we must go to ascertain what those rights are. The contract is in the form of an agreement appended to the specification, and signed by the pursuer on 13th May 1896. By it he bound himself to have different portions of the mason-work completed by different dates, which were not to be extended on the plea of any additions to or alterations of the plans, and to finish the whole by 1st May 1897, under penalty of ten shillings for each day that the work remained unfinished. The work was not completed till upwards of a year after the contract time, and the defender claims £150 of penalty. The pursuer maintains that the delay was caused by incessant alterations of the plans while the work was in progress, while the defender attributes it to the dilatoriness of the pursuer, and to his employing much too small a staff of workmen. The answer to the pursuer's contention is, that the contract gives to the architect unlimited and absolute power to determine any and every question that might arise in the course of the work, and to order any additions or alterations on the plans which he might think fit, without appeal to anyone. I have not sufficient practical knowledge of building contracts to say whether such a condition is usual. It is certainly very stringent, and I can easily see that it might bear hardly on the pursuer; but he signed the conditions with his eyes open, and he has no right to be relieved of his bargain merely because it turns out to be a bad one. On the other hand, it is, I think, clearly proved that the pursuer never made even an attempt to get his work finished within the contract time. That is shown both by the evidence and by the voluminous correspondence. I need not go into it in detail, but it appears from Mr Jerdan's evidence that within ten days of the signing of the contract he began a whole series of letters at short intervals, complaining of the pursuer's slowness in getting on with the work. Looking to the terms of the agreement, I do not think the pursuer's contention would have availed him in any case, still less will it do so when he never even tried to get the work done within the time which he had contracted for.” …
The pursuer appealed to the Sheriff ( Vary Campbell), who reversed the Sheriff Substitute's judgment as regards the pursuer's liability under the penalty clause, and pronounced the following finding—“Finds in law, and on a construction of the written contract for the mason-work at Temple Hall, that the defender is not entitled to enforce the penalty clause therein contained, by reason of his not having given his full orders for the work before 1st May 1897, being the date for completion of the whole work, and from which the penalty was intended to run.”
Note.—… “With regard to the penalty amounting to £150 claimed by the defender under the Temple Hall contract, I agree with the Sheriff-Substitute that, assuredly on the evidence, written and oral, the defender has much reason to complain. The pursuer got possession on signing his contract upon 13th May 1896. He contracted to finish his part of the work by 1st May 1897, and he did not finish for some fourteen months, or more than a year, after this date.
“The provisions of the Temple Hall contract bearing on the penalty clause are articles 1, 27, 5, and 21. The general effect of these clauses is to reserve to the employer full power to make alterations and order new work at any time under the contract, and without prejudice in any way to its validity. The penalty clause itself (article14) after fixing 1st May 1897 as the contract-date for finishing the whole mason-work, provides ‘a penalty of ten shillings per day that the mason-work remains unfinished after that
Page: 220↓
date.’ It is also specially provided in the same clause that extra work is to form no excuse for delay ‘unless specially certified by the architect at the time.’ The architect has also power to make allowance for ‘unsuitable weather, or for any other sufficient reason.’ “The pursuer has no time certificates or allowances from the architect; and the defender, with the full approval of the architect as a witness, proposes, after making all reasonable allowances, to charge three hundred days at ten shillings per day, i.e., £150, under this penalty clause.
“The condition that the contractor shall pay a penalty (which I take here to mean liquidated damages) if he fails to finish by a given date, implies, as in all other contracts, that the employer shall have done nothing on his side to prevent fulfilment of the condition. In some building contracts, even where alterations or extras are allowed without prejudice to the contract, the mere ordering of such new work will prevent the exaction of the penalty— Holme v. Guppy, 3 M. & W. 387; Westwood v. Secretary for India, 7, L.T. 736; M'Elroy v. Tharsis Company, 5 R. 161; Robertson v. Driver's Trustees, 8 R. 555. This result is avoided in the present contract by the provision that extra work shall form no excuse unless certified by the architect for a time allowance. If, accordingly, the original plans, with all the alterations, had been in the pursuer's hands before 1st May 1897 I would have listened to no excuse of extra work or bad weather not verified by certificates— Jones v. St John's College (1870), L.R., 6 Q.B. 115. The pursuer having accepted the new orders must complete the whole work without fail by the date agreed on under penalty, unless relieved by the architect in due form. But, on the other hand, the employer, if he is to exact the penalty for non-completion by the appointed date, must have given out his orders for the whole work before that date. The contractor was entitled to know before that date the whole expected of him, so as to have the chance, by putting more men on the job, or otherwise, of finishing up to contract time. This was not the case here. The architect says—‘I admit that additions were made to the building after 1st May 1897. I cannot say that I knew at 1st May 1897 what was going to happen in regard to additions. I think that the alterations were made more or less by Mr Bell and myself as the building proceeded; they were not part of a definite, completed plan.’ No doubt the pursuer's delay to proceed did not deprive the defender of his contract right to order extras during progress of the work, and there is something to be said for the architect's view—‘If the pursuer had got on faster with the work, my additional extras would have been given much earlier;’ and again, ‘The delay in giving instructions was caused principally by delay of the pursuer in his work.’ It is difficult, if not impossible, for me to find out on the evidence how much new work was ordered after 1st May 1897. It is enough, however, as tc the penalty clause, that the pursuer had admittedly not received his full orders by 1st May 1897, and so could not by any possibility have completed the whole work by that date. I think, accordingly, that the defender cannot enforce the penalty clause; but I shall reserve to him any claim he may have for damages as for breach of contract by unreasonable delay— Russell v. Da Bandeira, 1862, 32 L.J., C.P. 68; Dodd v. Churton [1897], 1 Q.B. 562; Hudson on Building Contracts, pp. 240–1.” …
The defender appealed. By agreement between parties the only question raised was the defender's claim under the penalty clause, the Sheriff's interlocutor quoad the other matters dealt with by him being acquiesced in.
Argued for the defender—The penalty provided for under clause 14 was liquidate damages— Elphinstone v. Monkland Iron and Coal Company, Limited, June 29, 1886, 13 R. (H.L.) 98; Johnston v. Robertson, March 1, 1861, 23 D. 646; Law v. Local Board of Redditch [1892], 1 Q.B. 127. These damages had been incurred. The true cause of the delay was the failure of the pursuer to carry on the work with proper diligence and to keep a sufficient working staff at the job. No doubt additions and alterations had been ordered during the course of the work, but these would not have caused delay if the pursuer had used sufficient diligence in pressing forward with his operations. The fact that new orders were given after 1st May 1897 was occasioned through the fault of the pursuer in not having long before that date the work at such a stage as to enable these orders to be timeously issued. The contract laid it down explicitly that the pursuer must receive certificates from the architect that the delay was justifiable, in order to excuse himself for not finishing the work at the date specified, and not having obtained these certificates he had incurred the penalty— Innes v. St John's College, 1870, L.R., 6 Q.B. 115; Dodd v. Churton [1897], 1 Q.B. 562.
Argued for the pursuer—The defender had made no claim for common law damages, but had contended that he was entitled to set off liquidate damages alleged to have been incurred under the penalty clause of the contract. In order to be entitled to enforce the penalty clause the defender must show he had done nothing to prevent the building being completed by 1st May 1897. This onus the defender had not discharged. He had not shown that the alterations and additions which he had admittedly ordered during the progress of the work were such as to make it possible for the pursuer to finish the work within the specified time. Indeed, the proof showed that some of the orders had been given after 1st May 1897, so that to finish the work by that date was an impossibility. A condition must be read into the contract to this effect, that the work was only to be finished by 1st May 1897 provided that no orders for alterations or additions were given which would prevent the work being completed by that date. The pursuer might
Page: 221↓
be liable in common law damages if it could be shown that he unduly delayed the work, but where there was proof as here that additional work was ordered at such a period as to make it impossible to carry out the contract by the time specified, a claim for liquidate damages under the penalty clause could not be enforced— Robertson v. Driver's Trustees, March 2, 1881, 8 R. 555; M'Elroy v. Tharsis Sulphur and Copper Company, November 17, 1877, 5 R. 161; Dodd, supra. At advising—
Such being the character of the contract, the facts as ascertained by the proof seem to be (1) that the pursuer failed to have the work stipulated for completed at any of the respective dates; (2) that he holds no certificates from the architect sanctioning deviation from any of the dates, no such certificates having been applied for; (3) that during the course of the work the pursuer was repeatedly and strongly remonstrated with by the architect both verbally and in writing for delay caused by the pursuer not putting a sufficient working staff on the building, and that it is not shown that the pursuer made any reply to the architect's remonstrances, though these began ten days after the pursuer got possession of the ground, and were continued throughout the whole course of the work, and although it was pointed out to him that penalty days were running, no reply was made or excuse offered; (4) that the work was not finished till a very long period after the contract time; (5) that the pursuer was required to do a very large quantity of work, both in the way of alterations and additions; (6) that some of this extra work was ordered after the final date when the work should have been finished under the contract; (7) that the defender limits his claim of set-off under the penalty clause to 300 days, which is considerably less than the number of days which passed beyond the stipulated time for completion of the work before the building was handed over.
These seem to me to be all the facts necessary for the consideration of the general question now before the Court, which is whether the defender is entitled as against the balance due to the pursuer to assert his right to £150 as representing 300 days during which the work remained uncompleted after the dates stipulated in the contract.
The pursuer contends against any allowance being made on various grounds, First he points to the very large extent of the alterations, which he guages by pointing out that the sum due to the pursuer is increased by the alterations and extras by about 70 per cent. The contention is that such extensive alterations would make it impossible to complete the work by the time named in the contract. I am not satisfied that this has been proved as matter of fact, but even if it were, the contract provides for definite extension of time if such extension should be necessary in consequence of the extent of extra work ordered. That contention must therefore, in my opinion, be rejected. If the pursuer required such extension, and did not apply for it, the defender's rights under the contract cannot be curtailed by evidence founded on calculation whether the time necessary for the alterations on the contract work would carry the work beyond the date. The time to be allowed for the work is flexible if there are alterations ordered, and the equity to which the contracting party is entitled if the work is altered is thereby provided for.
But then it is contended that no extra work could be required of the pursuer after the date when the work was to be completed on the footing that the penalty clause was to remain in force, unless notice by plans or otherwise was given to the pursuer of all such work before the date for the completion of the contract, and this contention the Sheriff has given effect to.
I am unable to agree with the learned Sheriff on the matter. Any such view leads to most anomalous results. The alterations and extras upon a building during erection may become necessary or expedient, or may be found advisable for reasons of appearance, after considerable part of the work has been done, and where the contractor has by delay in the execution of the first portions of the work exhausted the time prescribed while large portions remain undone, he would thereby, if the construction of the pursuer was sound, preclude the person for whom the work Was being done from having any alterations made as it advanced at a later date. I cannot hold that the pursuer by his own default can place the defender in a less advantageous position as regards extra work than he would have been if the work had been completed in its different stages in accordance with the agreement. If he without excuse occupied more time than
Page: 222↓
The pursuer in this case has not been confined in stating his answer to the defender's claim for the contract penalty to proof by certificates of the architect. He has been allowed to prove any case he could make to excuse the non-fulfilment of the work at the specified time. He has, in my opinion, failed to prove any facts to justify his delay. The defender has limited his claim to 300 days although the actual time was longer, and in my opinion he is entitled, in the settlement with the pursuer, to have the amount applicable to that number of days, viz., £150, deducted from the amount brought out as due to the pursuer for the work done.
I therefore think that the interlocutor of the Sheriff should be recalled, and judgment pronounced in terms of the interlocutor of the Sheriff-Substitute, except in regard to the claim for the making of the reservoir, which has been settled by joint-minute of the parties.
Page: 223↓
It is quite true that alterations were made by the defender on the original estimate, and that the amount of the contract price was considerably increased. But it appears from the architect's evidence that this was “caused by the use of more expensive work rather than by an additional quantity of work.” Again, however, one turns to the contract, and there it is distinctly stipulated that extra work, if any, should not warrant any deviation from the date fixed for completion unless certified by the architect. As this latter provision (the architect's certificate warranting or granting an extension of time) is not urged by the defender against the pursuer, the effect of the want of such certificate need not be considered. It was open to the pursuer (from the attitude the defender has taken) to prove that he was delayed beyond the contract time by reason of alterations ordered at a time which made fulfilment of his contract impossible. This he has not done.
I cannot assent to the view urged upon us, and which apparently is the view adopted by the Sheriff, that any order or alteration made or given after the 1st May 1897 per se struck the penalty clause out of the contract. As I have said, it is not established how many alterations were ordered after that date, nor what were these alterations. For anything that appears any such order was given after 1st May 1897 because the pursuer was so much behind already with his work that such alterations were necessarily delayed until then. That would not absolve the pursuer, but would rather accentuate his liability.
The result of my consideration of the case therefore is, that there is a plain obligation imposed on the pursuer by his contract, non-performance of which involved liability for a certain fixed penalty; that non-performance is clearly proved and indeed admitted; that the penalty therefore was incurred; and that no relevant or sufficient answer to the defender's demand for the penalty has been established. The defender has restricted his claim for penalty to £150, and for that sum I think he is entitled to credit in his settlement with the pursuer.
The proof before us does not tell us at what times the various alterations were ordered, or enable us to judge to what extent the execution of the work was delayed by these orders. All we know is that several extensive alterations were made by the defender's orders, and that most of these were made after the 1st of May 1897.
The Sheriff “finds in law and on a construction of the written contract for the mason-work at Temple Hall, that the defender is not entitled to enforce the penalty clause therein contained by reason of his not having given his full orders for the work before 1st May 1897, being the date for completion of the whole work, and from which the penalty was intended to run.” And in his note he says—“It is difficult if not impossible for me to find out on the evidence how much new work was ordered after 1st May 1897. It is enough, however, as to the penalty clause that the pursuer had admittedly not received his full orders by 1st May 1897, and so could not by any possibility have completed the whole work by that date.”
I think that the law as laid down by the learned Sheriff proceeds upon a misconstruction of the 14th and 27th conditions of the contract between the pursuer and the defender, and a misapplication of the case of Dodd v. Churton, L.R. [1897], 1 Q.B. 562.
By the conditions of the contract in that case the building was to be completed by 1st June 1893 under a penalty of £2 per week for every week that any parts of the works remained unfinished after that date as liquidate damage, and there was a provision that any authority given by the architects for any alteration or addition in or to the works should not vitiate the contract. The defendant, the employer, maintained that that provision meant that notwithstanding that alterations and additions were ordered, the contractor was bound to complete the whole work within the time named in the contract. The Court of Appeal decided in favour of the contractor, but solely on the ground that the condition to which I have referred that the contract should not be vitiated by orders for alterations or additions, would not bear the construction which the defendant sought to be put upon it, and that therefore, the defendant, having given orders which made it impossible for the contractor to complete the work by the time mentioned in the contract, he was thereby disentitled to claim the penalties for non-completion.
The penalty clause in the contract in this case is very different, because it not only contemplates that orders may be given for extra work, but it provides that such orders shall form no ground for deviating from the dates fixed for the completion of the respective portions of the work unless specially certified by the architect at the time. This shows that the contractor undertook to perform any extra work that might be ordered, and that if he thought that such alterations or extra work would prevent his completing the whole work by the specified dates, it lay upon him at the time to obtain from the architect a certificate
Page: 224↓
Now, these being the conditions of the pursuer's contract, I think the burden was upon him to show that the alterations ordered by the defender were such as to free him from the penalty clause. This he has failed to do. First, he did not apply for and has not produced any certificates granted by the architect entitling him to an extension of time in respect of alterations; secondly, he has not proved at what dates the alterations were ordered, or afforded us any means of judging what effect they had in delaying the work; and thirdly, it is distinctly proved in the case that during the period before the 1st of May 1897, by which time the whole work should have been completed, the pursuer, notwithstanding repeated remonstrances and orders from the architect, obstinatelv refused to put sufficient men on the work, with the result that, for instance, the north walls, which should have been ready for the roof on 1st January 1897, were not ready until the month of July of the same year, two months after the whole work should have been completed.
The work was not finally completed until upwards of 400 days beyond the time when it should have been completed. The defender restricts his claim for penalties to 300 days, amounting to £150. We have no means of judging whether the allowance made by the defender correctly represents the additional time which was necessarily occupied by the contractor in consequence of the alterations ordered. But the burden being on the pursuer in this matter, and he having entirely failed to show the extent to which the delay was caused by the alterations, and in particular having failed to show that any alterations were ordered before the 1st of May 1897 which would have prevented him completing the work by that date, I am of opinion that the defender is legally entitled to plead the penalty clause to the extent to which he asks that it should be enforced. Accordingly, I am for recalling the judgment of the Sheriff and reverting to the judgment of the Sheriff-Substitute.
The Court recalled the interlocutor reclaimed against, and, inter alia, found that there fell to be deducted from the gross apparent balance due by the defender to the pursuer £150 in name of penalty for breach of contract.
Counsel for the Pursuer— Salvesen, Q.C.— Guy. Agents— Dalgleish & Dobbie, S.S.C.
Counsel for the Defender— W. Campbell, Q.C.— Chisholm. Agents— Cairns, M'Intosh, & Morton, W.S.