Page: 564↓
[
Certain owners of house property in Glasgow brought an action of damages against a railway company, on the ground that their houses had been injured owing to the negligent and unskilful manner in which the company had carried out certain operations for the construction of a sewer in the street in which the property was situated. It was proved that in making the necessary excavation the company had adopted a known and approved method of work, which in the opinion of their engineers was the safest in the circumstances, and had exercised all usual precautions in carrying on the work, but that, owing to an abnormal rainfall, the earth behind the sheeting of the trench had been washed away, and a subsidence caused which injured the pursuers' houses. The jury returned a verdict for the pursuers. The Court granted a new trial, on the ground that the verdict was contrary to evidence, the defenders having exercised all reasonable and proper care, and the injury having been caused by an occurrence of so unusual a nature, that they could not be expected to foresee and provide against it.
The Caledonian Railway Company in August 1892, in the course of operations authorised by the Glasgow Central Railway Act 1888, sec. 41, sub-sec. L, cut a trench about 28 feet deep in Stevenson Street, Glasgow, between the centre of the street and the south pavement, for the purpose of diverting a sewer which interfered with an underground railway in course of construction. Upon 23rd August while the trench was open there was an abnormally heavy downpour of rain in consequence of which the street and trench were flooded, the soil behind the sheeting on the north side of the trench was washed away, an old sewer was broken, the struts canted over, and the houses fronting the pavement on the south side subsided.
Colonel A. F. Kidston, 42nd Highlanders, and Mr Robert M'Lure, writer, Glasgow, joint proprietors of the houses, brought an action of damages for £3000 against the Caledonian Railway Company, in which they averred, inter alia, that “the subsidence of the street which brought down the walls of the pursuers' property, and otherwise damaged their tenements, was caused by the unskilful and negligent manner in which the defenders, or those for whom they are responsible, excavated the soil in front of the tenements. In particular, the defenders proceeded to construct the sewer in front of the pursuers property by open casting instead of’ tunnelling. The method of construction by open casting is extremely dangerous at such a depth; the only safe method is by tunnelling. Further, the defenders conducted the open casting in a careless and inefficient manner…. In addition, there were no precautions taken to divert the rainfall from the trench. Upon the day of the accident there was a considerable fall of rain, and in consequence of the failure of the defenders to construct a dam, or to use some other well-known contrivance to force the rain into the nearest open grating, the rain found its way into the trench, washed away the earth behind the sheeting, and caused the sheeting to collapse, and a subsidence took place. The said rainfall was not abnormal, and was one of the dangers which the defenders should have anticipated, and taken proper precautions to meet. The defenders were bound, in the exercise of their statutory powers, to execute the works with skill and care, and, looking to the excessive depth of the cutting, its proximity on the one side to the pursuers' property, and on the other to the existing old sewers, and further to the treacherous nature of the strata through which it ran being constructed, and to use the best known methods for protecting the properties adjoining the works from injury by subsidence or otherwise. In this they failed as above mentioned, and carried on the work unskilfully, negligently, and recklessly, and thereby caused the injury to the pursuers' property.”
The pursuers pleaded—“(1) The defenders
Page: 565↓
having carried out the operations authorised by statute in an unskilful, negligent, and reckless manner, are liable in damages to the pursuers, the adjoining proprietors, for the loss, injury, and damage to their property.” The defenders pleaded—“(3) The operations in question having been authorised by statute, and conducted in all respects in terms of and in pursuance of the same, the defenders are not liable to the pursuer. (4) Damnum fatale. (5) Any loss which the pursuers may have sustained not having been caused by the fault of the defenders, they are entitled to absolvitor.”
The following issue was approved—“Whether, in or about the month of August 1892, the defenders carried on operations for the construction of a sewer in Stevenson Street, Glasgow, opposite the pursuers' property there, in an unskilful and negligent manner, in consequence of which the pursuers' said property was injured, to the loss, injury, and damage of the pursuers? Damages laid at £3000.”
The case was tried in January 1894 by Lord Low and a jury.
From the evidence, which is fully referred to in Lord Low's opinion (below), it appeared that all ordinary care and precaution had been taken, that the sheeting was driven in by hand to prevent the vibration which would have been caused by steam piling, and that open casting was adopted as being in the opinion of the engineers safer than tunnelling by air pressure, although Sir William Arrol, however, gave evidence in favour of the latter method. It also appeared that on the day in question the rainfall was 1·35 inches, although there was only one shower lasting about twenty minutes, and that the water was running along Stevenson Street some 10 inches high.
The jury returned a verdict for the pursuers, and assessed the damages at £1542, 6s. 8d.
The defenders moved for a new trial, and argued—(1) There was absolutely no evidence of negligence. Whether they had adopted the best possible method or not was beside the question if they had used a well-recognised and approved method. In fact, the other methods would have been attended with greater risk, although flooding could not have occurred with tunnelling; but (2) such flooding was almost unprecedented and could not have been foreseen. The rainfall that day, even for Glasgow, was so exceptional as to be unequalled during the last quarter of a century. This was of the nature of damnum fatale— Tennent v. Earl of Glasgow, March 3, 1864, 2 Macph. (H. of L.) 22.
Argued for the pursuers—(1) This was eminently a question for the jury, whose verdict should not be interfered if there was some evidence showing negligence— Kinnell v. Peebles, February 7, 1890, 17 R. 416. Here, further, care should have been taken by making a more efficient dam by tunnelling, as advocated by Sir William Arrol, or at least by employing steam piling which would have allowed stronger sheeting to be used. (2) In a place like Glasgow, liable to very heavy falls of rain, flooding should have been adticipated and provided against. This was not a damnum fatale and the damage was caused not by water running down its natural channel, or even down the street, but along a trench made by the defenders. The remarks of the Lord Chancellor (Westbury) in Tennent's case (above), when applied to the circumstances here, were in the pursuers' favour, as was Kerr v. Earl of Orkney, December 17, 1857, 20 D. 298, also a case of excessive rainfall.
At advising—
Page: 566↓
The case therefore stands thus:—The engineers of the company after full consideration adopted a well-known and approved method of doing the work. The only other practicable method was one which had never up to that time been applied to the construction of a sewer—in Scotland at least—and to adopt which would have been to try an experiment. In these circumstances I am of opinion that the evidence does not justify a verdict that there was negligence or want of skill as regards the method adopted.
Then just one word as to the way in which the accident happened. It seems to be quite certain that if it had not been for the extraordinary heavy rainfall on the 23rd August the work would have been carried through without any injury, or with only a little widening of one or two old cracks in the house on the south side of the street. But on that day there came a very extraordinary rainfall which washed away the material behind the sheeting on the north
Page: 567↓
Page: 568↓
Page: 569↓
The Court granted a new trial.
Counsel for the Pursuers— Lorimer— M'Laren. Agents— Cowan & Dalmahoy, W.S.
Counsel for the Defenders— Clyde. Agents— Hope, Todd, & Kirk, W.S.