1. In
or about November 1995 the plaintiffs, a husband and wife, retained the first
and second-named defendants, a firm of solicitors (“the
solicitors”), to act upon their behalf in the purchase of a dwelling
house at 3 Strangford Gate, Newtownards which was being sold by the third and
fourth-named defendants (“the vendors”). The solicitors acted on
behalf of the plaintiffs who eventually purchased the premises for the sum of
£90,000. However, the plaintiffs subsequently discovered that no
Building Control Approval or Final Architects Certificate had been issued
in respect of the purchased premises nor were the premises the subject of a
National House Building Council warranty.
2. On
the morning of the hearing the solicitors formally admitted liability for
negligence and breach of contract in failing to inform and advise the
plaintiffs that this documentation did not exist in relation to the subject
premises and, accordingly, the only issue which remained to be considered was
that of damages.
3. Mr
Ferriss QC and Ms Daynes appeared on behalf of the plaintiffs while
Mr Kennedy QC and Mr Marrinan represented the defendants. I
gratefully acknowledge the assistance which I derived from the clear and well
constructed submissions, both written and oral, placed before the court by both
sets of counsel.
4. The
plaintiffs, who have two children aged 13 and 10, decided to purchase
3 Strangford Gate in 1995 and engaged the defendant solicitors (“the
solicitors”) to advise them in relation to the transaction. The
premises were purchased for £90,000, the major portion of which was
provided by way of a mortgage of £83,512 from the Woolwich Building
Society.
5. The
plaintiffs were very attracted to 3 Strangford Gate and, in the course of
giving evidence, Gary McBlain described the premises as their “dream
home” where they intended to spend “the rest of their days”.
They moved into 3 Strangford Gate on 5 January 1996, but within about 4-5 weeks
the first defect became apparent when the main staircase started to become
detached from the wall. Arrangements were made for someone to attend in order
to repair the staircase, but when that person arrived he confirmed that the
damage was so extensive as to be beyond his capabilities. The
plaintiffs’ contacted Newtownards Building Control and, when the
inspectors attended, they informed the McBlains that no final Building Control
Approval Certificate had ever been obtained. Within a relatively short period
of time significant damp appeared in the front living room, the dining room and
a child’s bedroom above the living room. In cross-examination Mr McBlain
agreed that, by November 1996, he appreciated that it would cost approximately
£9,600 to carry out the remedial work sought by Newtownards Borough
Council before it would consider granting the appropriate certificate, but he
said that he would not have been prepared to spend this money because there was
no guarantee that, even if the work was done, a Certificate would be
forthcoming, he would not have been able to raise the money and he and his wife
believed that a great deal more work was necessary.
6. Both
sides called expert chartered surveyors in relation to the defects which have
developed in the subject premises – Mr Wilson on behalf of the plaintiff
and Mr Woods on behalf of the defendant. Agreement was reached between
the experts that the cost of repairing the problems with the damp-proof course,
the rain water goods, the roof lead work, staircase, the external manholes and
the ventilation in the roof space would amount to £7,600. There were two
areas of disagreement which related to repairs to the cavity walls, with the
associated insulation, and the structure of the ground floor. Mr Wilson
expressed the opinion that the only satisfactory way of dealing with the cavity
walls and insulation was to remove the outer skin and fix insulation board to
replace the loose insulate which had not been installed under adequate pressure
leading to the creation of voids. Mr Wilson also believed that, as a result of
failure to properly install the damp-proof membrane during the course of
constructing the floor, the conditions for rising damp had been created. He
felt that the only way to deal adequately with this problem was to excavate and
re-lay the floor. If all this work was carried out he and Mr Woods agreed that
a reasonable price would be £31,000.
7. For
his part, Mr Woods, on behalf of the defendants, did not accept that it was
necessary to excavate and re-lay the floor and he considered that the problem
with damp could be remedied by carrying out repairs to the chimney breast and
to the surrounds of six windows. Mr Woods and his partner had costed the
repairs which they considered to be necessary to remedy the defects at
£6,120 for the damp in the walls together with some £200 for repairs
to the floor.
8. In
cross-examination by Mr Ferriss QC, Mr Woods accepted that the NHBC warranty
lasted ten years and the house was only approximately half way through that
period. He also conceded that, even if the remedial work was satisfactorily
completed, he would still have advised a building society considering purchase
to carry out a separate survey because of the history of the premises and the
absence of an NHBC warranty.
9. Expert
valuers were also called by both sides with regard to diminution in value. On
behalf of the plaintiff, Mr McQuitty, who has been an associate of the
Royal Institute of Chartered Surveyors since 1970, expressed the view that
without the NHBC warranty, Building Control Approval or an Architects Final
Certificate in January 1996 the premises would have been worth £60,000.
Mr McQuitty said that he had been involved in a number of cases involving
similar problems and that, in his view, a discount of about one-third seemed
reasonable. Mr McQuitty said that he was very well acquainted with the housing
market in the Newtownards area and that he was familiar with comparative values
in 1996 and at the present time. In his view, if the defects in the subject
premises were remedied and a Building Control Certificate was granted, the
present day value of the house, without either an NHBC warranty or Architects
Final Certificate, would be approximately £165,000. He considered that if
all the documentation was present , the defects repaired and the gardens
landscaped and drained the present value would be about £180,000.
10. Mr
McQuitty was closely and effectively cross-examined by Mr Marrinan on
behalf of the defendants with regard to the comparable properties which he had
considered when attempting to reach a valuation. During the course of
cross-examination Mr McQuitty was compelled to make a number of
significant concessions and, overall, I formed the view that his evidence was
less than impressive. In particular Mr McQuitty referred to No 9 Strangford
Gate as a suitable comparator which was currently on the market for
£190,000 but, eventually he was compelled to concede that No 9 had an
extra bedroom, an extra garage, a conservatory and was 150 square feet
larger than No 3.
11. The
defendants called Mr Rodgers, an estate agent, who is a partner with the
Eric Cairns Partnership and has been in business as an estate agent for
some 25 years. Mr Rodgers stated that it was his estate agency which
originally sold No 3 Strangford Gate to the plaintiffs. Mr
Rodgers confirmed that No 1 Strangford Drive was 1,700 square
feet and currently on the market for £175,000. Mr Rodgers valued the
subject premises at £150,000-£160,000 with the defects remedied, the
garden made up but still lacking both an NHBC warranty and Architects Final
Certificate.
12. In
arriving at the conclusions which I have reached I have taken the following
factors into consideration:
13. Prior
to the hearing, the plaintiffs had steadfastly maintained that they should be
compensated on the basis that the subject premises should be demolished and a
new house re-erected on the site. The plaintiffs were not supported in this by
their expert witnesses, Mr Ferriss QC conceded that such an approach lacked
legal authority and, in the circumstances, I reject this submission as a proper
basis for compensation.
14. As
I have noted above, there is no difficulty in identifying the relevant
differential in value at the time of purchase which has been established at
£30,000. The cost of necessary repairs assessed by the plaintiffs’
witnesses, to include the sums which Mr Wilson, chartered surveyor, recommended
would be necessary to meet NHBC requirements came to £39,350. However, in
my opinion, to allow compensation at this level would be to compensate the
plaintiffs on the basis of a warranty given by the defendants contrary to the
principles set out in the
Banque
Bruxelles
decision. Such a figure significantly exceeds the diminution in value at date
of purchase and to use it as a basis for compensation would provide the
plaintiffs with a bargain which would not have been available even if the
defendants had properly performed their contract and would permit recovery upon
a warranty basis – see
Phillips
v Ward
[1956] 1 All ER 874;
Watts v Morrow
[1991] 4 All ER 937.
15. As
an alternative to the diminution in value at the purchase, Mr Ferriss QC
submitted that the plaintiffs should be compensated by reference to the present
day value of the house as it stands and the present value of the comparable
type of house which the plaintiffs would have bought as an alternative if the
contract had been properly performed by the defendants. The Court of Appeal in
Perry
v Sydney Phillips & Son
[1982] 3 All ER 705 rejected such a submission and at page 709 of the
judgment, when dealing with the points raised, Oliver LJ said:
16. Oliver
LJ also considered it to be significant that in
Perry
v Sydney Phillips
the plaintiff had been aware of the defects but had chosen not to cut his
losses by selling. In
Watts v
Morrow
,
Ralph Gibson LJ thought that it was arguable that inflationary increases might
be taken into account if the defects were not discovered for a substantial
period of time after the purchase. On the other hand, as the learned authors
of 16
th
Edition of McGregor on Damages point out, at paragraph 1286, the normal measure
of damages applies if there is a collapse in the market – see
Banque Bruxelles.
In this case I am satisfied that one of the primary reasons for the plaintiff
continuing to remain in the subject premises was their misconceived
apprehension that the house should be demolished and rebuilt. I note that the
prima facie rule as stated by the learned authors of Jackson & Powell on
Professional Negligence (4
th
Edition 1997) para 3-137 was recently confirmed as correct by the Court of
Appeal in
Patel
v Cooper & Jackson
[1999] 1 All ER 992 at 1000.
17. Accordingly,
it seems to me that the proper basis upon which to compensate the plaintiffs is
the diminution in value at the date of purchase, namely, £30,000.
18. In
addition, the plaintiffs claimed a total of £8,061.07 in respect of
solicitors fees and stamp duty, tiling, wardrobes, bathroom cabinets and lawn
laying, being sums which they claimed they would not have expended if they had
received proper advice from the defendants. While there are no doubt cases in
which plaintiffs may be properly compensated on the basis of the costs of
extricating themselves from the consequences of negligent advice, for example,
County
Personnel (Employment Agency) Limited v Pulver & Company
[1987]
1 WLR 916;
Hayes
v James and Charles Dodd
[1990] 2 All ER 815, as I have already noted above, since the date of the
original purchase, these plaintiffs have remained in occupation of the subject
premises and, on the basis of the evidence, I remain far from convinced that
they intend to leave. Accordingly, I do not allow these items by way of
damages. For the same reason, I do not allow the sum of £2,500 claimed in
respect of the alleged cost of transfer of furniture to be incurred on removal.
19. In
my view, the cost of investigative works carried out by Mr Wilson properly fall
to be measured as part of the costs of the hearing.
20. The
plaintiffs also claim compensation for the discomfort and inconvenience that
they had endured in not being able to enjoy the full amenities of the house.
In essence, the evidence in relation to this aspect of the case was restricted
to the plaintiffs’ inability to make full use of the three rooms effected
by damp. Mr McBlain described how the family had Christmas dinner on a
“plastic picnic table” for four years. Mrs McBlain said that
they tended to keep the central heating system on to cope with the damp. On
the balance of probabilities, I find that the plaintiff’s have
established that, as a consequence of the defendants fault, they suffered some
degree of discomfort and inconvenience caused by the damp but this has to be
seen in the context of the complete omission by the plaintiffs to take any
steps whatever to deal with the problem since the purchase of the premises. In
Patel
v Cooper
the Court of Appeal affirmed an award of £2,000 general damages to each of
the plaintiffs as a consequence of being compelled to live in alternative
accommodation for some seven years. In the circumstances, it seems to me that
an appropriate figure to award is £1,000 to each plaintiff. Consequently,
I propose to make a total award of £32,000 in respect of damages together
with interest thereon at the appropriate rate.