1. This
is an appeal from a judgment and order of Mr. Justice Lynch in the High Court
of the 8th June 1994 in which, at the conclusion of the proceedings, having
heard submissions from counsel on the issue of costs, he awarded the costs of
the proceedings to the defendants against the plaintiffs. In the proceedings,
he had in an earlier reserved judgment dismissed each of the claims brought by
the plaintiffs in the proceedings and had held having set them out seriatim
that they were not entitled to any of the reliefs which they had claimed in the
proceedings. The appeal that is now before the court is confined to that order
as to costs. It has not been sought to disturb any of the other findings of the
learned High Court judge.
2. This
court has repeatedly said in relation to costs in High Court proceedings that
they are primarily a matter for the discretion of the High Court judge.
However, that is
3. The
Court has considered carefully the submissions advanced by Mr. MacMenamin on
behalf of the Plaintiffs and is satisfied that no circumstances exist in the
present case which would justify this court in interfering with the undoubted
discretion of the High Court judge to treat the costs in this case as following
the event and awarding them against the plaintiff. Mr. MacMenamin has referred
to a number of authorities well known to the court in which the general
principle has been departed from where plaintiffs have failed to establish
particular matters generally relating to the unconstitutionality of either
specific legislation or the unconstitutionality of actions of the executive and
the court has nonetheless awarded the costs. An examination of those cases will
demonstrate that in each of those cases a point of general public importance
which might never have come before the courts and which might never have been
decided was at issue. Now in the present case, or if one looks to the
circumstances of the present case, the Court would have no doubt, as indeed is
expressly conceded by Mr. Connolly on behalf of the defendants, that an issue
of public importance and an issue of the greatest public importance arose in
the earlier proceedings, the case now referred to
4. In
the defence which they filed in the proceedings and which indeed reflected the
earlier correspondence between the parties, the defendants made it abundantly
clear that they did not regard themselves as entitled to proceed with this
development. They said that it was denied that the Commissioners of Public
Works in Ireland intended building on or further developing the works and
development already carried out to date on the site in Mullaghamore. The
defendants pleaded that no decision had yet been taken by the Government as to
whether or not any further development of the said works would be carried out
at the said site by the first named defendants. The first named defendants
admitted that in the event that a decision is taken by the Government to
develop or continue to develop work already carried out at Mullaghamore the first
5. The
first named defendants admit that no application has been made to the Planning
Authority for retention of the works carried out for the said site. Now there
was a plain and unambiguous statement, as I say, reflecting earlier
correspondence that the defendants had no intention of carrying out any work
save in accordance with the law. In the light of that, the plaintiffs proceeded
with the present proceedings and the High Court judge in a comprehensive
judgment found that they were not entitled to any of the reliefs that they had
claimed. They took the risk of issuing those proceedings. They were entitled so
to do, of course, but they took the risks involved in issuing those proceedings
and this Court cannot discern any ground for interfering with the decision of
the learned High Court Judge to apply the usual rule in relation to costs. The
court will dismiss the appeal.
6. The
Court is satisfied the costs of this appeal must also follow the event and that
the respondents are entitled to the costs of this appeal.