1. The
facts in this matter, so far as relevant, are fully set out in the judgment
which will be delivered by Barron J.
2. The
case presented on behalf of the Respondents/Appellants (hereafter “the
developers”) both in the High Court and in this court was founded on a
distinction between what were described as “works developments” and
“use
3. There
was evidence before the learned trial judge (Morris J, as he then was) from
which he considered himself entitled to infer that, if the development which
the applicant/respondent (hereafter “the County Council”) sought to
interdict was commenced before the coming into operation of the Local
Government (Planning and Development) Act 1963, it had either been abandoned
or, if not abandoned, intensified to a degree which constituted in law a new
development.
4. There
is ample authority, both here and in England, for the proposition that a
development, which was initiated before the relevant planning code became
operative and for that reason did not require permission, may subsequently be
regarded as having been abandoned, resulting in the necessity for planning
permission if it is resumed : see
Hartley
v. Minister of Housing and Local Government & Anor.
[1970]
1 QB 413
and
the decision of this court in
Dublin
County Council v. Tallaght Block Company Limited
[1982]
ILRM 534.
There
is similarly authority for the proposition that such a development, although
not abandoned in that sense, may have been intensified to a degree which
necessitates permission: see
Patterson
v. Murphy
[1978] ILRM 85.
The
5. “the
appointed day” for the purposes of the 1963 Act was October 1st 1964. It
is not in dispute that sand and gravel had been extracted from the lands in
question prior to that date. That, the developers say, constituted a
“works development” to which the concepts of
“abandonment” and “intensification” did not apply. In
support of that submission, Mr. Paul Gallagher, SC. on behalf of the developers
lays understandable emphasis on the precise form of the definitions which the
draftsman of the 1963 Act employed.
6. ‘‘
use’, in relation to land, does not include the use of the land by the
carrying out of any works thereon.
7. The
reason for the latter provision can be made clear by an example. In ordinary
parlance, putting up a building on farmland hitherto used for growing crops
would be treated as changing the use of the land. Since, however, the
8. The
fallacy in the submission advanced on behalf of the developers is that it
assumes that the necessary consequence of these statutory provisions is that a
particular series of operations must in planning terms be either a
“material
change in use”
development
or
“a
carrying out of works”
development.
But that is not so. To confine oneself to the facts of the present case, when
people began to extract sand or gravel from this land before 1964 the land in
question was no longer being used for agriculture, but for a form of industrial
or quasi-industrial use: see the definition of “agriculture” in s.2
of the 1963 Act. However, since that process involved the
“excavation” of sand or gravel from the land, it also constituted
the carrying out of “works” within the meaning of s.2. Thus,
applying the terminology adopted by Mr. Gallagher, this was both a “use
development” and a “works development”.
9. Mr.
Gallagher relied on the decision in
In
re Viscount Securities Limited
(112 ILTR 17). In that case, it was held by the High Court (Finlay P as he then
was) that a developer who was carrying out an extensive residential development
on agricultural land in County Dublin was not deprived of his right to
compensation in respect of the refusal on the ground that the
10. However,
the learned President went on to point out that these two categories were
“not
necessarily always exclusive and sometimes inevitably overlapping...”
It
should also be remembered that the case was concerned with an entirely
different subject, i.e. the right of a developer refused permission on
admittedly compensatable grounds to be paid such compensation and the need
11. The
decision, accordingly, does not, in my view, lend any support to the argument
advanced on behalf of the developers in the present case. The activities on the
land before October 1st, 1964 constituted both the carrying out of works and a
material change in the use of the land. Since there was clear evidence on which
the learned trial judge was entitled to find that the use in question had long
been abandoned before the present operations began and that, in any event, the
present operations constituted a significant intensification of that use, it
follows that permission was required.
12. As
to the argument based on the lapse of five years before the present application
was brought, for the reasons elaborated by Barron J in his judgment, that
argument also cannot succeed.
14. The
appellants are the owners of substantial deposits of sand and gravel at
Broadleas, Ballymore Eustace, Co. Kildare. These deposits are contained in a
fifty acre field
(“the
lands”)
which
the appellants acquired in 1991. Following upon this acquisition, the
appellants commenced to open up workings which had previously existed on the
lands and to extract the sand and gravel which lay under the topsoil.
15. The
County Council objected to this activity and on the 30th April 1991 served a
warning notice on the appellants under the provisions of s. 26 of the Local
Government (Planning and Development) Amendment Act, 1976 on the appellants.
The appellants replied by letter dated the 1st May 1991 which contained inter
alia the following comments relating to their activity.
16. On
the 7th February 1992 the appellants applied for the planning permission which
they had indicated. This was refused by the County Council. This refusal was
accepted and all activity on the lands ceased. It started up again in April
1995. A second warning notice was served on the 6th June
1995.
When
this was not complied with, the County Council commenced present proceedings by
way of notice of motion pursuant to the provisions of s. 27 of the 1976 Act as
inserted by the 1992 Act. This notice of motion sought to restrain the use of
the lands for the purposes of a sand and gravel pit and other purposes
ancillary thereto.
17. The
application came before Morris J., as he then was, who granted the relief
sought. The respondents have appealed to this Court against the grant of such
relief.
18. Although
a number of matters were raised in the High Court and in the notice of appeal
to this Court, the main submission at the hearing of this appeal related to one
basic contention. It was submitted that the extraction of sand and gravel is a
“works
development”
rather
than a
“use
development”;
that
such works development had commenced before the appointed day and that it could
be completed at any time without any further permission granted pursuant to the
provisions of the Planning Acts.
19. To
understand this submission, it is necessary to follow through the essential
provisions of the Local Government (Planning and Development) Act, 1963. It
applies to both land and buildings. This is made clear
20. Permission
is required for the development of land as so defined. Development is defined
by s. 3 of the Act as meaning save where the context otherwise requires
“the
carrying out of any works on, in, or under land or the making of any material
change in the use of any structures or other land.”
It
is these two separate and distinct types of development
21. A
works development must necessarily involve a use of the land, which during the
time it is being carried on would almost certainly be materially different from
the usual use of the land both before the works commenced and after their
completion. As there would have been cases where such development would not
have required permission, any such exemption would have been negatived if at
the same time permission would have been required to carry out such works
because they would at the same time have constituted a material change of use.
22. This
problem was met by defining both works and use for the purposes of the Acts so
as to avoid this conclusion. The definitions are as follows:
“‘Use’,
in
relation to land, does not include the use of the land by the carrying out of
any works thereon”; and
“‘works’
includes
any act or
23. In
the instant case, extraction of sand and gravel is clearly
“works”
and
it is submitted that by reason of the definition of use it is not a use of the
land for the purposes of the Acts.
24. I
have little doubt but that the expression
“works”
was
intended to refer to activity which was carried out once and for all and was a
means to an end rather than an end in itself. It was intended to apply to a
temporary activity involving the erection of structures or change to or removal
of existing structures. That is not the case with extraction.
26. Nevertheless,
extractive industries have been treated in the authorities as being the
carrying on of works developments - see
Patterson
v. Murphy
[1978] ILRM 85
.
27. There
may well be a case for maintaining that mining is a use. Inclusion of the word
“thereon”
in
the definition of
“use”
rather
than a phrase including
“on,
in or under”
might
have suggested that mining was a use. However, as can be seen from the
authorities this distinction does not seem to have been made. Such a
construction has not been given to the relevant definitions and if any
different interpretation is to be sought, it is a matter for the Oireachtas.
28. In
the instant case, counsel for the appellants is seeking to establish that once
works commenced on land prior to the appointed day, similar works are
permissible at any time thereafter without any further
29. Therefore,
where it is alleged that a use commenced after the appointed day is a material
change requiring planning permission, it may be a defence to show that the same
use was being made of the land prior to the appointed day.
30. In
relation to works, the issue is approached differently. 5. 24(1) provides that
permission is required inter alia (a) in respect of any development of land,
being neither exempted development nor
development
commenced before the appointed day.
It
is these last words which it is submitted entitle anyone who has commenced a
works development before the appointed day to complete it at any time in the
future without any permission being required for such completion.
31. As
I have already indicated counsel has submitted that while the concepts of
abandonment and intensification would be applicable to a p re-appointed day
use, they do not apply to the case of pre-appointed day works. When the basis
of the present submission is analysed, it is clear that the principles
applicable to a works development commenced prior to the appointed day are not
identical to those applicable to a use development in existence on the
appointed day. But the principles to be
32. Since
this submission on the part of the appellants involves proof that a works
development commenced before the appointed day, it is necessary for them to show:
33. These
questions may be answered by the findings of the learned trial judge. These are
contained in the following passage from his judgment:
34. The
periods of abandonment to which he later referred were from 1971 to the death
of Mr. Driver in 1981 and thereafter until 1991 when the pit was acquired by
the appellants.
35. From
these passages it is reasonable to infer that an inspection of the lands at the
time of the sale in 1991 would not have disclosed the existence of any sand
pit. This view is reinforced by the following sentence from an earlier portion
of the judgment of the learned trial judge where he says:
36. As
of the date of the hearing in the High Court the area of the then existing sand
pit was approximately 7¼ acres.
37. The
activity so found by the learned trial judge to have been subsisting on the
appointed day would not have constituted an uncompleted development in the
sense contemplated by s. 24(1) of the Act. In order to constitute such an
uncompleted development involving an extractive industry, it would have been
necessary to have in existence an open pit or quarry of a reasonably defined
body of material to be excavated continuously until exhaustion.
38. An
example is to be found in
Waterford
County Council v. John A. Wood Limited
1999 1 ILRM 217
.
There, a quarry was in operation on the appointed day. Dealing with what works
development could be carried
39. In
that case the development the completion of which did not require a permission
was the extraction of a known deposit from a specified location. The position
in the present case is quite different. It may well have been known that there
was a deposit of sand and gravel under all the lands, but it is clear that
extraction was haphazard. Although the deposit was available for extraction,
there was no ordered activity. The legal result of this was that, if the 1963
Act had been in force, development would have taken place from time to time and
any particular development would have been completed when the particular need
which prompted any particular series of extraction was satisfied. This actual
user of the pit was fundamentally different from a pit kept open for financial
gain and always available, but with only sporadic demand. In such a case, it
would be a question of fact as to what was the development and whether it had
been completed.
40. In
my view, there is no evidence of any uncompleted development on the appointed
day. If there had been, it would have been necessary to consider what further
development would have been permitted without a permission pursuant to the
provisions of s. 24.
41. It
is submitted on behalf of the respondents that once there is an uncompleted
development on the appointed day, it can be completed at anytime thereafter. In
support of this submission, it is contended that the situation is the same as
when a permission is obtained for a development. In such case, there was
originally no time limit before which the development had to commence.
Likewise, there should be no limit of time within which the uncompleted
development must be completed.
42. There
is a fallacy in this submission. In the first case there was originally no
limit, now five years, within which a development for which a permission had
been obtained had to be commenced. It has never been
43. In
support of his submissions, counsel for the appellants contended that in the
case of a works development, there was no place for the concepts of abandonment
or intensification of use. This submission follows the submission that there is
not time within which the uncompleted development must be completed. So far as
intensification is concerned the submission goes contrary to the decision in
Patterson
v. Murphy
where
44. Costello
J., as he then was, having accepted that he had to consider the excavations as
works development continued at p. 105 as follows:
46. It
is fundamental to counsel’s submission that there is an intention to
carry out a specified project. Both concepts are relevant to a determination
whether the intention remains or has been altered. Abandonment is the objective
sign of a decision not to continue further with the development, whereas
intensification may be the objective sign of an intention to carry out a
different development. In the former case, if the intention revives, a
permission will be required, whereas in the latter it is required as soon as it
47. Although
I have referred inter alia to intention as controlling the nature of the
uncompleted development which may proceed to completion without permission,
intention per se is not a material factor. What is material is such intention
as can be inferred from the activity. So in
Waterford
County Council v. John A. Wood Limited,
it
was possible to infer that the development was the extraction of the existing
deposit on the applicant’s lands. A totally different situation would
exist when there are plans for example to build a dozen chalets on the grounds
of a hotel. At the appointed day, six had been built and the hotel owner
intended to build the other six sometime in the future if demand warranted it.
Such
48. Counsel
for the appellant also submitted that if the works carried out by the appellant
were a use, then it commenced more than five years before the County Council
brought the present application and accordingly s. 27(6)(b) disentitled the
County Council to an order under that section. I would reject this submission.
The period of five years provided by the section is intended to give the
planning authority that length of time within which to bring proceedings to
restrain an unauthorised use. Where, as here, the planning authority took steps
within the period and those steps brought about a cesser of the use then the
five year period ceased to run and could only recommence if the use began once
more. In any event this is a works development.